A method, system and medium for generating a three-dimensional model design scheme for industrial park planning
By generating the basic three-dimensional model and performing sunshine analysis and adjusting the building spacing, the problem of failure to verify building spacing compliance in the three-dimensional model in the existing technology is solved, and the rationality and effectiveness of park planning are improved.
Patent Information
- Application Number
- CN202411277504.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2044-09-12
AI Technical Summary
When converting two-dimensional drawings into three-dimensional models, the existing three-dimensional modeling technology of park planning failed to effectively verify whether the spacing between buildings meets the building standards, resulting in occlusion problems. The design standards that cannot be considered in two-dimensional drawings failed to be in three-dimensional. Reasonable adjustments were obtained in the model.
By obtaining the floor plan and height of the building, a basic three-dimensional model is generated, and the sunshine analysis model is used to simulate the sunshine information of the building, analyzing whether there is occlusion between the buildings. If there is occlusion, the distance between the buildings will be adjusted to generate a final three-dimensional model.
It improves the effectiveness and rationality of the three-dimensional modeling technology of park planning, ensures that the sunshine between buildings meets the regulations, and solves the problem of occlusion of design standards in the three-dimensional model that are difficult to consider in the two-dimensional diagram.
Smart Images

Figure CN118779977B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of industrial park planning, and in particular to a method, system and medium for generating a three-dimensional model design scheme for industrial park planning. Background Art
[0002] Park planning 3D modeling technology refers to the use of computer software to create a 3D digital model of the park, which is used to display, analyze and optimize the layout and design of the park. This technology integrates geographic data, architectural design and environmental factors to provide planners with visualization tools, enabling them to more intuitively evaluate and adjust park plans.
[0003] The existing three-dimensional modeling technology for park planning usually converts the park planning from two-dimensional drawings directly into a three-dimensional model. However, when designing the intervals between buildings in the two-dimensional drawings, only roads and green areas are usually reserved, without considering whether other aspects meet the building standards. The three-dimensional model should be adjusted for aspects that are difficult to consider in the two-dimensional drawings to ensure that the buildings meet the specified standards. The existing three-dimensional modeling technology for park planning is only a technology for converting from two-dimensional to three-dimensional, without verifying and adjusting the buildings. For example, in a patent application with publication number CN116956402A, a "building information model forward design method, device, medium, and electronic device" is disclosed. This solution is to directly convert the buildings in the target park from two-dimensional to three-dimensional models, without considering whether the design standards that cannot be considered in two-dimensional graphics are compliant through the three-dimensional model, resulting in unreasonable problems in the spacing design between buildings. The existing three-dimensional modeling technology for park planning also has the problem of not verifying and adjusting the building standards that are difficult to consider in the two-dimensional level through the three-dimensional model, resulting in problems such as occlusion between buildings that do not meet the building regulations. Summary of the invention
[0004] The present invention aims to solve one of the technical problems in the prior art to at least a certain extent. By acquiring the floor plan and building heights of the building planning in the industrial park planning, a basic three-dimensional model of the industrial park is generated, and then the sunlight information of different buildings in the basic three-dimensional model is simulated through a sunlight analysis model. Then, based on the sunlight information, it is analyzed whether there is any obstruction between the buildings. If there is any obstruction between the buildings, the intervals between the buildings are adjusted, and a final three-dimensional model is obtained to solve the problem that the existing three-dimensional modeling technology for park planning still has the problem of not verifying and adjusting the building standards that are difficult to consider at the two-dimensional level through the three-dimensional model, resulting in obstruction between buildings and other problems that do not comply with architectural regulations.
[0005] To achieve the above objectives, in a first aspect, the present application provides a method for generating a three-dimensional model design scheme for industrial park planning, comprising the following steps:
[0006] Obtain the floor plan and building height of the buildings in the industrial park planning, and generate a basic three-dimensional model of the industrial park;
[0007] The sunshine information of different buildings in the basic three-dimensional model is simulated through the sunshine analysis model;
[0008] Analyze whether there is any shading between buildings based on sunlight information;
[0009] If there is any occlusion between buildings, the interval between the buildings is adjusted to obtain the final three-dimensional model.
[0010] Furthermore, obtaining the floor plan and building height of the buildings in the industrial park planning and generating a basic three-dimensional model of the industrial park includes the following sub-steps:
[0011] Obtain the floor plan of the building plan in the industrial park plan;
[0012] With the length as the X-axis and Y-axis respectively, a plane rectangular coordinate system is established, named the floor space frame selection coordinate system, and the plane map is drawn into the floor space frame selection coordinate system;
[0013] Name the figure corresponding to the building's footprint as the footprint figure;
[0014] For any area graph, obtain the maximum and minimum values of X in the area graph, mark them as maximum X and minimum X respectively, and obtain the maximum and minimum values of Y, mark them as maximum Y and minimum Y respectively;
[0015] Connect the coordinate point (minimum X, minimum Y) with (minimum X, maximum Y), connect the coordinate point (minimum X, minimum Y) with (maximum X, minimum Y), connect the coordinate point (maximum X, minimum Y) with (maximum X, maximum Y), connect the coordinate point (maximum X, maximum Y) with (minimum X, maximum Y), and connect the coordinate point (maximum X, maximum Y) with (minimum X, maximum Y). After connecting, a rectangle is obtained, which is the building's footprint rectangle. Analyze all the footprint graphics to obtain the footprint rectangles of all buildings;
[0016] Taking the rectangular area of each building in the plan view as the base and the corresponding building height as the height to construct a cuboid, the plan view is converted from a two-dimensional image to a three-dimensional image to obtain a basic three-dimensional model.
[0017] Furthermore, simulating the sunshine information of different buildings in the basic three-dimensional model through the sunshine analysis model includes the following sub-steps:
[0018] Establish a sunshine analysis model;
[0019] Get the latitude and longitude of the industrial park;
[0020] Enter the longitude and latitude and the basic three-dimensional model into the sunshine analysis model;
[0021] One day is randomly selected from each month of the previous year as the simulation date, and the simulation dates are sorted and numbered in ascending order of the month. n Represents, where n is a positive integer and n is the sequence number of M;
[0022] M n Run the sunlight analysis model as a simulation date and record the sunlight information of different buildings.
[0023] Further, in turn, M n Running the sunlight analysis model as a simulation date and recording sunlight information for different buildings includes the following sub-steps:
[0024] The buildings in the basic 3D model are numbered using the symbol B i Represents, where i is a positive integer and i is the serial number of B;
[0025] Starting with n=1, set M n Run the sunshine analysis model as the simulation date and obtain the B at 12:00 noon i The area on the south side of the sun is marked as S (n,i) , S (n,i) Indicates M n As the simulated date B i The area of the south side exposed to sunlight;
[0026] Increase n by 1 and repeat until n=max(n) and stop the analysis, where max(n) is the maximum value of n.
[0027] The S (n,i) That is the sunshine information.
[0028] Furthermore, analyzing whether there is any shading between buildings based on sunlight information includes the following sub-steps:
[0029] Obtaining construction standards of the building, wherein the construction standards include window height from the ground, left margin, right margin, and building length;
[0030] By formula C i =(BH-2×GCH)×(BL-LR) Calculate the sunny area of the building. i , the sunny area is marked as C i , where C i is the sunny area, BH is the building height, GCH is the height of the window from the ground, BL is the building length, L is the left distance, and R is the right distance;
[0031] Starting with i=1, search for S (n,i) The maximum value in is marked as E i, add i+1, and repeat the search for E i , until i=max(i), where max(i) is the maximum value of i;
[0032] E i With C i Compare, if E i Less than C i , then the output is insufficient sunshine signal, if E i Greater than or equal to C i , then the output is a normal sunshine signal.
[0033] Furthermore, if there is occlusion between buildings, the intervals between the buildings are adjusted, and obtaining the final 3D model includes the following sub-steps:
[0034] B for outputting insufficient sunlight signal i , analyzing how the spacing between buildings needs to be adjusted;
[0035] Based on the analysis results, the intervals between buildings are adjusted to obtain the final three-dimensional model.
[0036] Furthermore, for B outputting a sunshine shortage signal i , analyzing how the spacing between buildings needs to be adjusted includes the following sub-steps:
[0037] Get the solar declination, represented by the symbol δ, and get the geographical latitude of the industrial park, represented by the symbol φ;
[0038] The solar altitude angle is calculated by the formula sinθ=cos(φ-δ), where θ is the solar altitude angle, which can be simplified to θ=90-(δ-φ);
[0039] Get B i The highest point of the shaded part on the south side is marked as the highest occlusion point, and the distance between the highest occlusion point and the ground is obtained, which is marked as the highest occlusion height;
[0040] Calculate H / tanθ and mark the result as the interval adjustment value, where H is the highest occlusion height;
[0041] Calculate the B of all output sunshine shortage signals i The corresponding interval adjustment value is represented by the symbol T i express.
[0042] Furthermore, adjusting the intervals between buildings according to the analysis results includes the following sub-steps:
[0043] B for outputting insufficient sunlight signal i , which will be temporarily referred to as the building to be adjusted, and the building adjacent to the south of the building to be adjusted will be temporarily referred to as the blocking building;
[0044] Increase the distance between the building to be adjusted and the blocking building by T i , for all B outputting insufficient sunshine signals i All changes were made;
[0045] If the buildings after adjustment are beyond the scope of the industrial park, all buildings will be moved to the south as a whole until all buildings are within the industrial park;
[0046] The adjusted basic 3D model is marked as the final 3D model.
[0047] In a second aspect, the present application provides a system for generating a three-dimensional model design scheme for industrial park planning, including a basic model construction module, a sunshine information simulation module, an occlusion analysis module, and a final version model construction module; the basic model construction module, the sunshine information simulation module, and the occlusion analysis module are respectively connected to the data of the final version model construction module;
[0048] The basic model building module is used to obtain the floor plan and building height of the building planning in the industrial park planning, and generate a basic three-dimensional model of the industrial park;
[0049] The sunshine information simulation module is used to simulate the sunshine information of different buildings in the basic three-dimensional model through the sunshine analysis model;
[0050] The shading analysis module is used to analyze whether there is shading between buildings based on sunshine information;
[0051] The final model building module is used to adjust the interval between buildings if there is any obstruction between the buildings, and obtain the final three-dimensional model.
[0052] In a third aspect, the present application provides a storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the steps in the above method are performed.
[0053] Beneficial effects of the present invention: The present invention generates a basic three-dimensional model of the industrial park by acquiring the floor plan and building height of the building planning in the industrial park planning, and then simulates the sunshine information of different buildings in the basic three-dimensional model through the sunshine analysis model, and then analyzes whether there is any obstruction between the buildings based on the sunshine information. The advantage is that the industrial park planning is usually planned using two-dimensional graphics, and it is difficult for two-dimensional graphics to consider whether there is an obstruction relationship between buildings based on the heights and intervals of different buildings. In order to make the sunshine of the building meet the relevant regulations, the three-dimensional model can be used to analyze whether the sunshine of the building is sufficient, thereby improving the effectiveness and rationality of the three-dimensional modeling technology of the park planning;
[0054] The present invention provides a method for outputting a sunshine shortage signal. i, analyze how the intervals between buildings need to be adjusted, adjust the intervals between buildings according to the analysis results, and get the final 3D model. The advantage is that the sun’s altitude angle is highest at noon during the day, and the buildings can get the most sunlight at this time. If there is still occlusion at this time, it means that the intervals between buildings are unreasonable. By analyzing the distance that the buildings need to be moved through the occlusion area, the 3D modeling is adjusted to improve the rationality of the intervals between buildings in the park planning. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] Figure 1 is a functional block diagram of the system of the present invention;
[0056] Figure 2 is a schematic diagram of a plan view of the present invention;
[0057] Figure 3 A schematic diagram of a coordinate system for selecting an area frame of the present invention;
[0058] Figure 4 Schematic diagram of the maximum X, minimum X, maximum Y and minimum Y of the present invention;
[0059] Figure 5 A schematic diagram of a rectangular area of the present invention;
[0060] Figure 6 A schematic diagram of the rectangular area of all buildings of the present invention;
[0061] Figure 7 A schematic diagram of the definition of the left margin, the right margin and the building length of the present invention;
[0062] Figure 8 is a schematic diagram of the highest occlusion point of the present invention;
[0063] Fig. 9 is a schematic diagram of a sunshine analysis model of the present invention;
[0064] Fig.10 is a flow chart of the steps of the method of the present invention;
[0065] Fig.11 It is a schematic structural diagram of the electronic device of the present invention. DETAILED DESCRIPTION
[0066] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0067] Example 1, please refer to Figure 1 As shown, the present application provides a system for generating a three-dimensional model design scheme for industrial park planning, including a basic model construction module, a sunshine information simulation module, an occlusion analysis module and a final version model construction module; the basic model construction module, the sunshine information simulation module and the occlusion analysis module are respectively connected to the data of the final version model construction module;
[0068] The basic model building module is used to obtain the floor plan and building height of the building planning in the industrial park planning, and generate the basic three-dimensional model of the industrial park;
[0069] The basic model building module is configured with a basic model building strategy, which includes:
[0070] See also Figure 2 As shown, obtain the floor plan of the building planning in the industrial park planning;
[0071] See also Figure 3 As shown, take the length as the X-axis and the Y-axis respectively, establish a plane rectangular coordinate system, named as the floor space frame selection coordinate system, and draw the plane map into the floor space frame selection coordinate system;
[0072] Name the figure corresponding to the building's footprint as the footprint figure;
[0073] See also Figure 4 As shown, for any land occupation figure, obtain the maximum and minimum values of X in the land occupation figure, mark them as maximum X and minimum X respectively, and obtain the maximum and minimum values of Y, mark them as maximum Y and minimum Y respectively;
[0074] See also Figures 5 and 6 As shown, connect the coordinate point (minimum X, minimum Y) with (minimum X, maximum Y), connect the coordinate point (minimum X, minimum Y) with (maximum X, minimum Y), connect the coordinate point (maximum X, minimum Y) with (maximum X, maximum Y), and connect the coordinate point (maximum X, maximum Y) with (minimum X, maximum Y). After connecting, a rectangle is obtained, which is the floor area rectangle of the building. Analyze all the floor area graphics to obtain the floor area rectangles of all buildings.
[0075] Taking the rectangular area of each building in the plan as the base and the corresponding building height as the height to construct a cuboid, the plan is converted from a two-dimensional image to a three-dimensional image to obtain a basic three-dimensional model;
[0076] In practical applications, the plane diagram is obtained as Figure 2 As shown, Figure 2 The plan view shown is only a simplified diagram and is only used as an example in this embodiment. The coordinate system of the selected area is constructed as follows: Figure 3As shown, taking the building at the bottom of the plan as an example, the maximum X, minimum X, maximum Y and minimum Y are obtained as follows Figure 4 As shown, draw the area rectangle as Figure 5 As shown, Figure 5 The dotted lines in the figure are the lines connecting the coordinate points. Similarly, all other non-rectangular land figures are designed as rectangles, and several land rectangles are obtained as follows: Figure 6 As shown; the purpose of converting the footprint graphic into a footprint rectangle is to consider the shading relationship between different buildings for sunlight. The irregular shape of the building itself will also have a certain impact on its own sunlight, which will affect the subsequent judgment. Therefore, converting all of them into rectangles can avoid the misjudgment of the shading relationship between buildings caused by their own irregular shapes; using the footprint rectangle of each building in the plan view as the base and the corresponding building height as the height to construct a cuboid, convert the plan view from a two-dimensional image to a three-dimensional image, that is, convert the two-dimensional rectangle into a three-dimensional cuboid, and obtain a basic three-dimensional model.
[0077] The sunshine information simulation module is used to simulate the sunshine information of different buildings in the basic three-dimensional model through the sunshine analysis model; the sunshine information simulation module includes a sunshine simulation unit and an information recording unit;
[0078] The sunshine simulation unit is equipped with sunshine simulation strategies, which include:
[0079] Establish a sunshine analysis model;
[0080] Get the latitude and longitude of the industrial park;
[0081] Enter the longitude and latitude and the basic three-dimensional model into the sunshine analysis model;
[0082] One day is randomly selected from each month of the previous year as the simulation date, and the simulation dates are sorted and numbered in ascending order of the month. n Represents, where n is a positive integer and n is the sequence number of M;
[0083] In practical applications, the sunshine analysis model is implemented using the existing real-time simulation technology for building sunlight. The longitude and latitude of the industrial park are obtained as (117.35, 31.82). The longitude and latitude are used to input the sunshine analysis model to simulate the lighting effects corresponding to the solar altitude angle in different regions at a certain moment. If the current year is 2024, one day is randomly selected from each month from January to December in 2023 as the simulation date to obtain M1 to M2. 12They are January 12, 2023, February 15, 2023, March 22, 2023, April 8, 2023, May 12, 2023, June 28, 2023, July 5, 2023, August 2, 2023, September 16, 2023, October 4, 2023, November 24, 2023, and December 29, 2023. Multiple days in different months are used as simulation dates to prevent the failure to obtain real sunshine information due to weather reasons.
[0084] The information recording unit is configured with an information recording strategy, which includes:
[0085] The buildings in the basic 3D model are numbered using the symbol B i Represents, where i is a positive integer and i is the serial number of B;
[0086] Starting with n=1, set M n Run the sunshine analysis model as the simulation date and obtain the B at 12:00 noon i The area on the south side of the sun is marked as S (n,i) , S (n,i) Indicates M n As the simulated date B i The area of the south side exposed to sunlight;
[0087] Increase n by 1 and repeat until n=max(n) and stop the analysis, where max(n) is the maximum value of n.
[0088] S (n,i) That is sunshine information;
[0089] In practical applications, since the sun rises in the east, is directly above and slightly south at noon, and sets in the west, and the solar altitude angle at noon is the maximum in a day, the area of the south side of the building illuminated by sunlight at 12:00 noon is taken as the sunshine information of the building; for example, when running the sunshine analysis model with M1 as the simulation date, the area of the south side of building B1 illuminated by sunlight is 4782 m2, that is, S (1,1) is 122㎡; and so on, we can get several S (n,i) .
[0090] The shading analysis module is used to analyze whether there is shading between buildings based on sunlight information;
[0091] The occlusion analysis module is configured with occlusion analysis strategies, which include:
[0092] See also Figure 7 As shown, obtain the building construction standards of the building, which include the height of the window from the ground, the left distance, the right distance and the length of the building;
[0093] By formula C i =(BH-2×GCH)×(BL-LR) Calculate the sunny area of the building. i , the sunny area is marked as C i , where C i is the sunny area, BH is the building height, GCH is the height of the window from the ground, BL is the building length, L is the left distance, and R is the right distance;
[0094] Starting with i=1, search for S (n,i) The maximum value in is marked as E i , add i+1, and repeat the search for E i , until i=max(i), where max(i) is the maximum value of i;
[0095] E i With C i Compare, if E i Less than C i , then the output is insufficient sunshine signal, if E i Greater than or equal to C i , then the output is a normal sunshine signal;
[0096] In practical applications, the definitions of left margin, right margin and building length are as follows: Figure 7 As shown in the figure, the left margin, right margin and building length are all values taken on the south side of the building; for building B1, the window height from the ground is 1m, the left margin is 1m, the right margin is 1m, the building length is 122m, and the building height is 40m. By calculation, the sunny area C1 of B1 is (40-2×1)×(122-1-1)=4560㎡; for B1, i is always 1, and in S (1,1) To S (12,1) The maximum value E1 of the area of the south side of building B1 illuminated by sunlight is 4875 m2. By comparison, if E1 is greater than or equal to C1, a normal sunlight signal is output.
[0097] The final version model building module is used to adjust the interval between buildings if there is occlusion between the buildings, and obtain the final version of the three-dimensional model; the final version model building module includes an adjustment analysis unit and a model adjustment unit;
[0098] The adjustment analysis unit is used to output the insufficient sunshine signal B i , analyzing how the spacing between buildings needs to be adjusted;
[0099] The adjustment analysis unit is configured with an adjustment analysis strategy, which includes:
[0100] Get the solar declination, represented by the symbol δ, and get the geographical latitude of the industrial park, represented by the symbol φ;
[0101] The solar altitude angle is calculated by the formula sinθ=cos(φ-δ), where θ is the solar altitude angle, which can be simplified to θ=90-(δ-φ);
[0102] See also Figures 8 to 9 As shown, get B i The highest point of the shaded part on the south side is marked as the highest occlusion point, and the distance between the highest occlusion point and the ground is obtained, which is marked as the highest occlusion height;
[0103] Calculate H / tanθ and mark the result as the interval adjustment value, where H is the highest occlusion height;
[0104] Calculate the B of all output sunshine shortage signals i The corresponding interval adjustment value is represented by the symbol T i express;
[0105] In practical applications, in this embodiment, E1 outputs a normal sunshine signal, while E2 outputs an insufficient sunshine signal, which means that B2 is blocked, resulting in insufficient sunshine. The solar declination δ is obtained to be 8.61°, the geographical latitude of the industrial park is 31.82°, and the solar altitude angle θ is calculated to be 66.39°. The highest blocking point is as follows: Figure 8 As shown, Figures 2 to 8 These are simple diagrams for easy understanding. The actual sunshine analysis model can be referred to Fig. 9 , the highest shielding height is 12m, H / tanθ is calculated, and the interval adjustment value T2 is 5.25m. The calculation result is rounded to two decimal places. Since B1 outputs a normal sunshine signal, T1 does not exist. Similarly, the analysis of other buildings T i ;
[0106] The model adjustment unit is used to adjust the intervals between buildings according to the analysis results to obtain the final 3D model.
[0107] The model adjustment unit is configured with a model adjustment strategy, which includes:
[0108] B for outputting insufficient sunlight signal i , which will be temporarily referred to as the building to be adjusted, and the building adjacent to the south of the building to be adjusted will be temporarily referred to as the blocking building;
[0109] Increase the distance between the building to be adjusted and the blocking building by T i , for all B outputting insufficient sunshine signals i All changes were made;
[0110] If the buildings after adjustment are beyond the scope of the industrial park, all buildings will be moved to the south as a whole until all buildings are within the industrial park;
[0111] Mark the adjusted basic 3D model as the final 3D model;
[0112] In actual applications, if B2 outputs a signal of insufficient sunlight, B2 is temporarily called the building to be adjusted, and the adjacent building to the south of B2 is B1. Therefore, the distance between B1 and B2 is 13m, and the distance is increased by T2, that is, 13+5.25=18.25m, and the distance between B2 and B1 is changed to 18.25m. B1 does not move, B2 moves 5.25m to the north, and all buildings to the north of B2 need to move 5.25m to the north to ensure that the distance between B2 and other buildings remains unchanged. For example, B1, B2, B3 and B4 are a row of buildings from south to north. After B2 is moved, B3 and B4 They all need to be moved the same distance to ensure that the distance between B2 and B3 and the distance between B3 and B4 remain unchanged. If B3 also outputs a signal of insufficient sunlight, after B3 is moved, B4 needs to be moved again. If B4 exceeds the planning scope of the industrial park, B1, B2, B3 and B4 will be moved south as a whole until B1, B2, B3 and B4 are all within the planning scope of the industrial park. This method is to make the design of buildings in industrial parks with sufficient planning scope more reasonable. If there is no industrial park with sufficient planning scope, no matter how it is changed, it will not meet the requirements. At this time, it is only necessary to perform the two-dimensional to three-dimensional model construction.
[0113] Example 2, please refer to Fig.10 As shown, the present application provides a method for generating a three-dimensional model design scheme for industrial park planning, comprising the following steps:
[0114] Step S1, obtaining the floor plan and building height of the building planning in the industrial park planning, and generating a basic three-dimensional model of the industrial park; Step S1 includes the following sub-steps:
[0115] Step S101, obtaining a floor plan of a building plan in an industrial park plan;
[0116] Step S102, using the length as the X-axis and the Y-axis, respectively, to establish a plane rectangular coordinate system, named as the floor space frame selection coordinate system, and draw the plane map into the floor space frame selection coordinate system;
[0117] Step S103, naming the graphic corresponding to the floor area of the building as a floor area graphic;
[0118] Step S104, for any land occupation pattern, obtain the maximum value and minimum value of X in the land occupation pattern, mark them as maximum X and minimum X respectively, and obtain the maximum value and minimum value of Y, mark them as maximum Y and minimum Y respectively;
[0119] Step S105, connect the coordinate point (minimum X, minimum Y) with (minimum X, maximum Y), connect the coordinate point (minimum X, minimum Y) with (maximum X, minimum Y), connect the coordinate point (maximum X, minimum Y) with (maximum X, maximum Y), connect the coordinate point (maximum X, maximum Y) with (minimum X, maximum Y), and connect the coordinate point (maximum X, maximum Y) with (minimum X, maximum Y), and obtain a rectangle after connection, which is the floor area rectangle of the building. Analyze all floor area graphics to obtain the floor area rectangles of all buildings;
[0120] Step S106, using the rectangular area of each building in the plan view as the base and the corresponding building height as the height to construct a cuboid, converting the plan view from a two-dimensional image to a three-dimensional image, and obtaining a basic three-dimensional model;
[0121] Step S2, simulating the sunshine information of different buildings in the basic three-dimensional model through the sunshine analysis model; Step S2 includes the following sub-steps:
[0122] Step S201, establishing a sunshine analysis model;
[0123] Step S202, obtaining the longitude and latitude of the industrial park;
[0124] Step S203, entering the longitude and latitude and the basic three-dimensional model into the sunshine analysis model;
[0125] Step S204, randomly select one day from each month of the previous year as a simulation date, sort and number the simulation dates in ascending order of the month, and use the symbol M to identify the simulation date. n Represents, where n is a positive integer and n is the sequence number of M;
[0126] Step S205, sequentially n Run the sunshine analysis model as a simulation date and record the sunshine information of different buildings;
[0127] Step S205 includes the following sub-steps:
[0128] Step S2051: Number the buildings in the basic three-dimensional model, using symbol B i Represents, where i is a positive integer and i is the serial number of B;
[0129] Step S2052, starting with n=1, n Run the sunshine analysis model as the simulation date and obtain the B at 12:00 noon i The area on the south side of the sun is marked as S (n,i) , S (n,i) Indicates M n As the simulated date B i The area of the south side exposed to sunlight;
[0130] Step S2053, increase n by 1, repeat the process until n=max(n), and stop the analysis, where max(n) is the maximum value of n;
[0131] Step S2054, S (n,i) That is the sunshine information;
[0132] Step S3, analyzing whether there is any obstruction between buildings based on the sunshine information; Step S3 includes the following sub-steps:
[0133] Step S301, obtaining the construction standard of the building, the construction standard includes the window height from the ground, the left margin, the right margin and the building length;
[0134] Step S302, by formula C i =(BH-2×GCH)×(BL-LR) Calculate the sunny area of the building. i , the sunny area is marked as C i , where C i is the sunny area, BH is the building height, GCH is the height of the window from the ground, BL is the building length, L is the left distance, and R is the right distance;
[0135] Step S303, starting with i=1, search for S (n,i) The maximum value in is marked as E i , add i+1, and repeat the search for E i , until i=max(i), where max(i) is the maximum value of i;
[0136] Step S304: E i With C i Compare, if E i Less than C i , then the output is insufficient sunshine signal, if E i Greater than or equal to C i , then the output is a normal sunshine signal;
[0137] Step S4, if there is any occlusion between the buildings, the interval between the buildings is adjusted to obtain a final three-dimensional model; Step S4 includes the following sub-steps:
[0138] Step S401: for B outputting a sunshine shortage signal i , analyzing how the spacing between buildings needs to be adjusted;
[0139] Step S401 includes the following sub-steps:
[0140] Step S4011, obtaining the solar declination, represented by the symbol δ, and obtaining the geographical latitude of the industrial park, represented by the symbol φ;
[0141] Step S4012, using the solar altitude angle calculation formula sinθ=cos(φ-δ), where θ is the solar altitude angle, simplified to θ=90-(δ-φ);
[0142] Step S4013, obtain B i The highest point of the shaded part on the south side is marked as the highest occlusion point, and the distance between the highest occlusion point and the ground is obtained, which is marked as the highest occlusion height;
[0143] Step S4014, calculating H / tanθ, and marking the calculation result as the interval adjustment value, where H is the highest occlusion height;
[0144] Step S4015, calculate the B of all output sunshine shortage signals i The corresponding interval adjustment value is represented by the symbol T i express;
[0145] Step S402, adjusting the intervals between buildings according to the analysis results to obtain a final three-dimensional model;
[0146] Step S402 includes the following sub-steps:
[0147] Step S4021: for B outputting a sunshine shortage signal i , which will be temporarily referred to as the building to be adjusted, and the building adjacent to the south of the building to be adjusted will be temporarily referred to as the blocking building;
[0148] Step S4022: Increase the distance between the building to be adjusted and the blocking building by T i , for all B outputting insufficient sunshine signals i All changes were made;
[0149] Step S4023: If the adjusted buildings are beyond the scope of the industrial park, all buildings are moved to the south as a whole until all the buildings are within the industrial park;
[0150] Step S4024: Mark the adjusted basic 3D model as the final 3D model.
[0151] Example 3, please refer to Fig.11 As shown, Fig.11The structural schematic diagram of an electronic device is illustrated, and the electronic device may include: a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other through the communication bus. The memory stores computer-readable instructions, and the processor can call the instructions in the memory. When the computer-readable instructions are executed by the processor, the steps in a method for generating a three-dimensional model design scheme for industrial park planning are executed to achieve the following functions: obtaining the floor plan and building height of the building planning in the industrial park planning, and generating a basic three-dimensional model of the industrial park; simulating the sunshine information of different buildings in the basic three-dimensional model through the sunshine analysis model; analyzing whether there is occlusion between the buildings based on the sunshine information; if there is occlusion between the buildings, adjusting the interval between the buildings, and obtaining the final three-dimensional model.
[0152] In addition, the logic instructions in the above-mentioned memory can be implemented in the form of software functional units and can be stored in a computer-readable storage medium when sold or used as an independent product. Based on this understanding, the technical solution of the present application can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, server, or network device, etc.) to execute all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc. Various media that can store program codes.
[0153] Embodiment 4. The present application also provides a computer program product, which includes a computer program stored on a computer-readable storage medium, and the computer program includes program instructions. When the program instructions are executed by a computer, the computer can execute a method for generating a three-dimensional model design scheme for industrial park planning provided by the above methods, and the method includes: obtaining a floor plan and building height of building planning in the industrial park planning, and generating a basic three-dimensional model of the industrial park; simulating the sunlight information of different buildings in the basic three-dimensional model through a sunlight analysis model; analyzing whether there is any obstruction between the buildings based on the sunlight information; if there is any obstruction between the buildings, adjusting the interval between the buildings, and obtaining the final three-dimensional model.
[0154] Example 5. The present application also provides a computer-readable storage medium. The present application provides a storage medium on which a computer program is stored. When the computer program is executed by a processor, the steps in the above method for generating a three-dimensional model design scheme for industrial park planning are executed to achieve the following functions: obtain the floor plan and building height of the building planning in the industrial park planning, and generate a basic three-dimensional model of the industrial park; simulate the sunlight information of different buildings in the basic three-dimensional model through a sunlight analysis model; analyze whether there is any obstruction between the buildings based on the sunlight information; if there is any obstruction between the buildings, adjust the interval between the buildings, and obtain the final three-dimensional model.
[0155] Through the description of the above implementation methods, the embodiments of the present invention can be provided as methods, systems or computer program products. Based on such an understanding, the above technical solutions can be essentially or partly contributed to the prior art in the form of software products, which can be stored in a computer-readable storage medium, such as ROM / RAM, a magnetic disk, an optical disk, etc., and include several instructions for enabling a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each embodiment or some parts of the embodiments.
[0156] In the embodiments provided in the present application, it should be understood that the disclosed system or method can be implemented in other ways. The embodiments described above are merely schematic. For example, the division of modules or units is only a logical function division. There may be other division methods in actual implementation. For example, multiple modules or units can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some communication interfaces, and the indirect coupling or communication connection of systems, modules and units can be electrical, mechanical or other forms.
[0157] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A method for generating a three-dimensional model design scheme for industrial park planning, characterized in that: The steps include: Obtain the floor plan and building height of the buildings in the industrial park planning, and generate a basic three-dimensional model of the industrial park; The sunshine information of different buildings in the basic three-dimensional model is simulated through the sunshine analysis model; Analyze whether there is any shading between buildings based on sunlight information; If there is any occlusion between buildings, the interval between the buildings is adjusted and the final 3D model is obtained; Obtaining the floor plan and building height of the buildings in the industrial park planning and generating the basic 3D model of the industrial park includes the following sub-steps: Obtain the floor plan of the building plan in the industrial park plan; With the length as the X-axis and Y-axis respectively, a plane rectangular coordinate system is established, named the floor space frame selection coordinate system, and the plane map is drawn into the floor space frame selection coordinate system; Name the figure corresponding to the building's footprint as the footprint figure; For any area graph, obtain the maximum and minimum values of X in the area graph, mark them as maximum X and minimum X respectively, and obtain the maximum and minimum values of Y, mark them as maximum Y and minimum Y respectively; Connect the coordinate point (minimum X, minimum Y) with (minimum X, maximum Y), connect the coordinate point (minimum X, minimum Y) with (maximum X, minimum Y), connect the coordinate point (maximum X, minimum Y) with (maximum X, maximum Y), connect the coordinate point (maximum X, maximum Y) with (minimum X, maximum Y), and connect the coordinate point (maximum X, maximum Y) with (minimum X, maximum Y). After connecting, a rectangle is obtained, which is the building's footprint rectangle. Analyze all the footprint graphics to obtain the footprint rectangles of all buildings; Taking the rectangular area of each building in the plan as the base and the corresponding building height as the height to construct a cuboid, the plan is converted from a two-dimensional image to a three-dimensional image to obtain a basic three-dimensional model; The sunlight analysis model is used to simulate the sunlight information of different buildings in the basic 3D model, including the following sub-steps: Establish a sunshine analysis model; Get the latitude and longitude of the industrial park; Enter the longitude and latitude and the basic three-dimensional model into the sunshine analysis model; One day is randomly selected from each month of the previous year as the simulation date, and the simulation dates are sorted and numbered in ascending order of the month. n Represents, where n is a positive integer and n is the sequence number of M; M n Run the sunshine analysis model as a simulation date and record the sunshine information of different buildings; M n Running the sunlight analysis model as a simulation date and recording sunlight information for different buildings includes the following sub-steps: The buildings in the basic 3D model are numbered using the symbol B i Represents, where i is a positive integer and i is the serial number of B; Starting with n=1, set M n Run the sunshine analysis model as the simulation date and obtain the B at 12:00 noon i The area on the south side of the sun is marked as S (n,i) , S (n,i) Indicates M n As the simulated date B i The area of the south side exposed to sunlight; Increase n by 1 and repeat until n=max(n) and stop the analysis, where max(n) is the maximum value of n. The S (n,i) That is sunshine information; Analyzing whether there is shading between buildings based on sunlight information includes the following sub-steps: Acquire the construction standards of the building, wherein the construction standards include the height of the window from the ground, the left margin, the right margin, and the length of the building; By formula C i =(BH-2×GCH)×(BL-LR) Calculate the sunny area of the building. i , the sunny area is marked as C i , where C i is the sunny area, BH is the building height, GCH is the height of the window from the ground, BL is the building length, L is the left distance, and R is the right distance; Starting with i=1, search for S (n,i) The maximum value in is marked as E i , add i+1, and repeat the search for E i , until i=max(i), where max(i) is the maximum value of i; E i With C i Compare, if E i Less than C i , then the output is insufficient sunshine signal, if E i Greater than or equal to C i , then the output is a normal sunshine signal.
2. The method for generating a three-dimensional model design scheme for industrial park planning according to claim 1, characterized in that: If there is occlusion between buildings, the interval between the buildings is adjusted, and the final 3D model is obtained, including the following sub-steps: B for outputting insufficient sunlight signal i , analyzing how the spacing between buildings needs to be adjusted; Based on the analysis results, the intervals between buildings are adjusted to obtain the final three-dimensional model.
3. The method for generating a three-dimensional model design scheme for industrial park planning according to claim 2, characterized in that: B for outputting insufficient sunlight signal i , analyzing how the spacing between buildings needs to be adjusted includes the following sub-steps: Get the solar declination, represented by the symbol δ, and get the geographical latitude of the industrial park, represented by the symbol φ; The solar altitude angle is calculated by the formula sinθ=cos(φ-δ), where θ is the solar altitude angle, which can be simplified to θ=90-(δ-φ); Get B i The highest point of the shaded part on the south side is marked as the highest occlusion point, and the distance between the highest occlusion point and the ground is obtained, which is marked as the highest occlusion height; Calculate H / tanθ and mark the result as the interval adjustment value, where H is the highest occlusion height; Calculate B of all output sunshine shortage signals i The corresponding interval adjustment value is represented by the symbol T i express.
4. The method for generating a three-dimensional model design scheme for industrial park planning according to claim 3 is characterized in that: Adjusting the spacing between buildings based on the analysis results includes the following sub-steps: B for outputting insufficient sunlight signal i , which will be temporarily referred to as the building to be adjusted, and the building adjacent to the south of the building to be adjusted will be temporarily referred to as the blocking building; Increase the distance between the building to be adjusted and the blocking building by T i , for all B outputting insufficient sunshine signals i All changes were made; If the buildings after adjustment are beyond the scope of the industrial park, all buildings will be moved to the south as a whole until all buildings are within the industrial park; The adjusted basic 3D model is marked as the final 3D model.
5. A system for generating a three-dimensional model design scheme for industrial park planning, used to implement a method for generating a three-dimensional model design scheme for industrial park planning as described in any one of claims 1 to 4, characterized in that: It includes a basic model construction module, a sunshine information simulation module, a shading analysis module and a final version model construction module; the basic model construction module, the sunshine information simulation module and the shading analysis module are respectively connected with the data of the final version model construction module; The basic model building module is used to obtain the floor plan and building height of the building planning in the industrial park planning, and generate a basic three-dimensional model of the industrial park; The sunshine information simulation module is used to simulate the sunshine information of different buildings in the basic three-dimensional model through the sunshine analysis model; The shading analysis module is used to analyze whether there is shading between buildings based on sunshine information; The final model building module is used to adjust the interval between buildings if there is any obstruction between the buildings, and obtain the final three-dimensional model.
6. A storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 4 are executed.
Citation Information
Patent Citations
Building information model forward design method and device, medium and electronic equipment
CN116956402A
High-rise building group daylighting optimization processing method based on BIM (Building Information Modeling) technology
CN107341296A
Building planning method and device, electronic equipment and storage medium
CN111523189A