The invention discloses a cast-in place
pile post-grouting construction method for pouring construction. The method comprises the steps that cast-in place
pile pore-forming construction is carried out; first-time hole clearing is carried out; reinforcement cage and grouting
pipe mounting is carried out; second-time hole clearing is carried out;
pile body concrete placing is carried out; pile concrete curing is carried out; grouting
soil mass reinforcement is carried out; grouting is stopped; next cast-in place pile grouting working is carried out; and checking and accepting are carried out. After pile forming, the intensity of pile body concrete reaches a certain degree, a high-pressure generating device is used, high-pressure
cement grout flow with concentrated energy is formed,
grout is combined with pile body surrounding
soil mass through the effects of permeating, separation, filling, compaction and the like, pile body
sediment and pile side mud cakes are solidified, pile side friction resistance and pile end bearing force are enlarged, the shortcomings that due to hole bottom
sediment and pile side mud cakes of a common cast-in place pile, bearing force is low, and
vertical load decreasing is high are overcome, and important economic and
social significance is achieved in single pile bearing force improving, pile foundation
sedimentation lowering, pile
foundation engineering quality guaranteeing and the like.