Electric energy metering device, charging controller, charging pile and electric leakage protection method thereof
By integrating metering, insulation and adhesion detection circuits in the charging pile, sharing the high-voltage sampling wire harness, and dynamically adjusting the leakage threshold, the problem of too many high-voltage sampling wire harnesses and fixed leakage protection thresholds in the charging pile is solved, achieving safer and more accurate electric energy. Metering and leakage protection.
Patent Information
- Application Number
- CN202410772075.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-14
- Publication Date
- 2024-10-18
AI Technical Summary
In terms of electric energy measurement and leakage protection, existing charging piles have problems such as many high-voltage sampling wire harnesses, complex wiring, and messy wiring. Moreover, the leakage protection threshold is fixed and it is difficult to take into account both false tripping and electric shock protection.
An electric energy metering device is designed, which integrates the metering circuit, insulation detection circuit and adhesion detection circuit, shares the high-voltage sampling wire harness, and introduces a leakage protection device and a current sensor into the charging pile to dynamically adjust the leakage threshold to adapt to the working conditions of the charging pile. .
It reduces the number of high-voltage sampling wire harnesses, simplifies wiring and wiring, improves the safety and accuracy of charging piles, and can respond to leakage and electric shock protection in a timely manner.
Smart Images

Figure CN118790086A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of charging piles, and in particular to an electric energy metering device, a charging controller, a charging pile and a leakage protection method thereof. Background Art
[0002] A charging pile is a device that replenishes electricity for electric vehicles. Its function is similar to that of a gas pump in a gas station. It can be fixed on the ground or on a wall and installed in public buildings, residential parking lots or charging stations. It can charge various models of electric vehicles according to different voltage levels.
[0003] In order to measure the electric energy charged in the electric vehicle for the convenience of billing, in addition to the main circuit, the charging pile generally needs to be equipped with a DC energy meter and a charging controller; the DC energy meter measures the electric energy charged in the electric vehicle by high-voltage sampling of the charging voltage and current on the DC side of the main circuit, and transmits it to the charging controller; the charging controller is mainly used to control the operation of the main circuit and to perform billing based on the received metering information. In addition, it is usually equipped with circuits for insulation detection and switch adhesion detection on the DC side of the main circuit. Both of them realize corresponding detection functions through high-voltage sampling of the DC side of the main circuit, so that the charging controller can provide timely protection when any detection result indicates an abnormality, so as to improve the safety of the charging pile. Summary of the invention
[0004] In view of the above problems, the present application provides an electric energy metering device, a charging controller, a charging pile and a leakage protection method thereof, so as to reduce the high-voltage sampling harness, avoid the problem of complex wiring and scattered and messy internal wiring of the charging pile. The specific scheme is as follows:
[0005] The first aspect of the present application provides an electric energy metering device, comprising: a metering circuit, an insulation detection circuit and an adhesion detection circuit; wherein:
[0006] The metering circuit is used to sample the output side voltage and current of the charging pile where the electric energy metering device is located, and to perform electric energy metering according to the sampled information;
[0007] The adhesion detection circuit is used to perform adhesion detection on the output side switch, wherein the output side switch is arranged between the output side of the power conversion unit in the main circuit of the charging pile and the output side of the charging pile;
[0008] The insulation detection circuit is used to perform insulation detection on the output side of the charging pile;
[0009] The first side sampling pin of the adhesion detection circuit is connected to the sampling pin of the metering circuit for sampling the same position; and / or the second side sampling pin of the adhesion detection circuit is connected to the sampling pin of the insulation detection circuit for sampling the same position;
[0010] Any two connected sampling pins are connected to the outside through the same interface on the electric energy metering device.
[0011] In a possible implementation, the negative electrode sampling pin of the metering circuit is used to connect the negative electrode of the output side of the power conversion unit;
[0012] The low potential current sampling pin of the metering circuit is used to connect the current output end of the shunt; the shunt is arranged in the positive transmission branch between the output side of the power conversion unit and the output side switch;
[0013] The high potential current sampling pin of the metering circuit is used to connect the current input terminal of the shunt;
[0014] The first side negative electrode sampling pin of the adhesion detection circuit is connected to the negative electrode sampling pin of the metering circuit;
[0015] The first-side positive sampling pin of the adhesion detection circuit is connected to the low-potential current sampling pin of the metering circuit.
[0016] In a possible implementation, the positive electrode sampling pin of the insulation detection circuit is used to connect the positive electrode of the output side of the charging pile;
[0017] The negative electrode sampling pin of the insulation detection circuit is used to connect the negative electrode of the output side of the charging pile;
[0018] The second side positive sampling pin of the adhesion detection circuit is connected to the positive sampling pin of the insulation detection circuit;
[0019] The second side negative electrode sampling pin of the adhesion detection circuit is connected to the negative electrode sampling pin of the insulation detection circuit.
[0020] In a possible implementation, the electric energy metering device also includes: a processing module, which is used to process each piece of information separately after obtaining the metering information of the metering circuit, the detection information of the insulation detection circuit and the detection information of the adhesion detection circuit, and report the processing result to the charging controller of the charging pile.
[0021] In a possible implementation, the electric energy metering device further includes: a display screen, used to display the processing result.
[0022] In a first aspect, the present application provides a charging controller, comprising: a processor, and at least one electric energy metering device as described in the first aspect or any one of the implementation forms of the first aspect; wherein:
[0023] The processor is connected to the electric energy metering device and the electric vehicle connected to the charging pile respectively; wherein the processor is used to: control the on-off state of the input side switch and the output side switch in the charging pile, and control the operation of the main circuit in the charging pile.
[0024] In a possible implementation, a leakage protection device is provided between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile; wherein,
[0025] The leakage threshold of the leakage protection device corresponds to the current working condition of the charging pile;
[0026] The charging controller also includes: a communication circuit, which is used to communicate with the leakage protection device and connect with the processor.
[0027] In a possible implementation, a current sensor is provided between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile;
[0028] The charging controller further includes: a leakage detection circuit connected to the current sensor and the processor respectively;
[0029] The leakage threshold of the leakage detection circuit corresponds to the current operating condition of the charging pile.
[0030] The third aspect of the present application provides a charging pile, comprising: a main circuit, a charging controller, and at least one electric energy metering device; wherein:
[0031] The main circuit includes at least one power conversion unit, the input side of the power conversion unit is connected to the input side of the charging pile through an input side switch, and the output side of the power conversion unit is connected to the corresponding output side of the charging pile through a shunt and an output side switch in sequence;
[0032] The input side of the charging pile is used to connect to the power grid, and the output side of the charging pile is used to connect to the electric vehicle;
[0033] The electric energy metering device is used to measure the electric energy for the corresponding power conversion unit;
[0034] The input side switch, the output side switch and the power conversion unit are respectively controlled by the charging controller; the charging controller is connected to the electric energy metering device and the electric vehicle connected to the charging pile;
[0035] Among them, the electric energy metering device is the electric energy metering device as described in the first aspect or any one of the implementation forms of the first aspect; or, the charging controller is the charging controller as described in the second aspect or any one of the implementation forms of the second aspect; or, the power conversion unit is equipped with an insulation detection circuit and a adhesion detection circuit, and the first side sampling pin of the adhesion detection circuit is correspondingly connected to the sampling pin of the electric energy metering device of the same power conversion unit for sampling the same position, and / or, the second side sampling pin of the adhesion detection circuit is correspondingly connected to the sampling pin of the insulation detection circuit of the same power conversion unit for sampling the same position.
[0036] In a possible implementation, the charging pile further includes: a leakage protection device;
[0037] The leakage protection device is arranged between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile, and is connected to the charging controller;
[0038] The leakage threshold of the leakage protection device corresponds to the current working condition of the charging pile.
[0039] In a possible implementation, the leakage protection device includes: a current sensor, a leakage detection circuit and a leakage communication module; wherein,
[0040] The current sensor is arranged between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile, and its output end is connected to the input end of the leakage detection circuit;
[0041] The output end of the leakage detection circuit is connected to one side of the leakage communication module;
[0042] The other side of the leakage communication module is used to connect with the charging controller.
[0043] In a possible implementation, the charging pile further includes: a current sensor;
[0044] The current sensor is arranged between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile;
[0045] The input end of the current sensor is connected to the leakage detection circuit in the charging controller;
[0046] The leakage threshold of the leakage detection circuit corresponds to the current operating condition of the charging pile.
[0047] In a possible implementation, when the number of the power conversion units is greater than 1:
[0048] Each of the power conversion units is connected to the input side of the charging pile through the corresponding input side switch;
[0049] Alternatively, at least two of the power conversion units share the same input-side switch.
[0050] In a possible implementation, the power conversion unit includes: a power module, or a plurality of power modules connected in parallel.
[0051] In a possible implementation, when the power grid is an AC power grid, the power module is an AC / DC conversion circuit, or the power module includes an AC / DC conversion circuit and a DC / DC conversion circuit connected in series;
[0052] Alternatively, when the power grid is a direct current power grid, the power module is a DC / DC conversion circuit.
[0053] A fourth aspect of the present application provides a leakage protection method for a charging pile, which is applied to the charging pile described in the third aspect or any one of the implementation forms of the third aspect, and the leakage protection method includes:
[0054] Get the leakage value of the charging pile;
[0055] If the leakage value exceeds the leakage threshold, the input side switch of the charging pile is controlled to be disconnected.
[0056] In a possible implementation, the leakage threshold is: the sum of the leakage increment and the working leakage current of the charging pile under the current working condition;
[0057] The working leakage current is determined according to the historical leakage data of the charging pile, and the leakage increment is determined according to the leakage current detection type of the power grid to which the charging pile is connected and the leakage current planned to be monitored.
[0058] By means of the above technical scheme, the electric energy metering device provided by the present application includes a metering circuit, an insulation detection circuit and an adhesion detection circuit; wherein, the first side sampling pin of the adhesion detection circuit is connected to the sampling pin of the metering circuit for sampling the same position; and / or, the second side sampling pin of the adhesion detection circuit is connected to the sampling pin of the insulation detection circuit for sampling the same position; and, any two connected sampling pins are connected to the outside through the same interface on the electric energy metering device, so that the connected sampling pins can share the same sampling wire harness, thereby reducing the number of sampling wire harnesses and avoiding the problems of complicated wiring and scattered and messy internal wiring of the charging pile. BRIEF DESCRIPTION OF THE DRAWINGS
[0059] The above and other features, advantages and aspects of the embodiments of the present disclosure will become more apparent with reference to the following detailed description in conjunction with the accompanying drawings. Throughout the accompanying drawings, the same or similar reference numerals represent the same or similar elements. It should be understood that the drawings are schematic and the originals and elements are not necessarily drawn to scale.
[0060] Figure 1 A schematic diagram of the structure of the charging pile provided for this application;
[0061] Figure 2 A schematic diagram of the structure of the charging pile provided in this application;
[0062] Figure 3 Another structural schematic diagram of the charging pile provided for this application;
[0063] Figure 4 Another structural schematic diagram of the charging pile provided for this application;
[0064] Figure 5 Another structural schematic diagram of the charging pile provided for this application;
[0065] Figure 6 Another structural schematic diagram of the charging pile provided for this application;
[0066] Figure 7 Another structural schematic diagram of the charging pile provided for this application;
[0067] Figure 8 Another structural schematic diagram of the charging pile provided for this application;
[0068] Fig. 9 Another structural schematic diagram of the charging pile provided for this application;
[0069] Fig.10 Another structural schematic diagram of the charging pile provided for this application;
[0070] Fig.11 Another structural schematic diagram of the charging pile provided for this application;
[0071] Fig.12 Another structural schematic diagram of the charging pile provided for this application;
[0072] Fig.13 Another structural schematic diagram of the charging pile provided for this application;
[0073] Fig.14 Another structural schematic diagram of the charging pile provided for this application;
[0074] Fig.15Another structural schematic diagram of the charging pile provided for this application;
[0075] Fig.16 Another structural schematic diagram of the charging pile provided for this application;
[0076] Fig.17 A flow chart of a leakage protection method for a charging pile provided in this application. DETAILED DESCRIPTION
[0077] The following describes the embodiments of the present application in conjunction with the drawings in the embodiments of the present application. The terms used in the implementation method section of the present application are only used to explain the specific embodiments of the present application, and are not intended to limit the present application.
[0078] The embodiments of the present application are described below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention. It is known to ordinary technicians in this field that with the development of technology and the emergence of new scenarios, the technical solutions provided in the embodiments of the present application are also applicable to similar technical problems.
[0079] The terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and need not be used to describe a specific order or sequential order. It should be understood that the terms used in this way can be interchangeable under appropriate circumstances, which is only to describe the distinction mode adopted by the objects of the same attributes when describing in the embodiments of the present application. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, so that the process, method, system, product or equipment comprising a series of units need not be limited to those units, but may include other units that are not clearly listed or inherent to these processes, methods, products or equipment.
[0080] Figure 1 The structure of the charging pile is shown in Figure 1 In the main circuit of the charging pile, the structure for charging an electric vehicle includes: an input side switch 01, a power conversion unit 02, a shunt 03 and an output side switch 04 connected in sequence; the power conversion unit 02 is also equipped with a DC energy meter, an adhesion detection circuit and an insulation detection circuit, all of which need to perform high-voltage sampling on the output side of the power conversion unit 02, that is, all of the three have leads connected to the output side circuit, resulting in more high-voltage sampling harnesses required, such as Figure 1The wiring harnesses 1# to 9# shown in the figure, among which, wiring harnesses 1#, 2# and 9# are wiring harnesses for the DC energy meter to sample the output side of the power conversion unit 02, wiring harnesses 3#, 4#, 5# and 6# are wiring harnesses for the adhesion detection circuits respectively set on both sides of the output side switch 04 for sampling, and wiring harnesses 7# and 8# are wiring harnesses for the insulation detection circuit to sample the output side of the charging pile; in this case, not only is the wiring complicated, but also the wiring inside the charging pile is scattered and messy.
[0081] Based on this, the embodiment of the present application provides an electric energy metering device to reduce the high-voltage sampling harness and avoid the problem of complex wiring and scattered and messy wiring inside the charging pile. The specific solution is as follows:
[0082] See also Figure 2 The electric energy metering device 20 comprises: a metering circuit 201, an insulation detection circuit 203 and an adhesion detection circuit 202; wherein:
[0083] The function of the metering circuit 201 is equivalent to Figure 1 The DC electric energy meter shown in the figure is used to sample the output side voltage and current of the charging pile where the electric energy metering device 20 is located, and to measure the electric energy according to the sampling information so that the charging controller 30 in the charging pile can record the charging cost.
[0084] The sticking detection circuit 202 is used to perform sticking detection on the output side switch 104, that is, to detect whether the output side switch 104 is stuck. The output side switch 104 is located between the output side of the power conversion unit 102 in the main circuit of the charging pile and the output side of the charging pile.
[0085] The insulation detection circuit 203 is used to perform insulation detection on the output side of the charging pile. In actual applications, the insulation detection circuit 203 can take a wire from each branch connecting the positive and negative poles DC+ and DC- on the output side of the charging pile, and can monitor whether the resistance of the positive and negative poles DC+ and DC- to the PE line (that is, the insulation impedance to the ground) is within a safe range.
[0086] In addition, the metering circuit 201, the insulation detection circuit 203 and the adhesion detection circuit 202 are not only integrated in the electric energy metering device 20, but also: the first side sampling pin of the adhesion detection circuit 202 is correspondingly connected to the sampling pin of the metering circuit 201 for sampling the same position; and / or, the second side sampling pin of the adhesion detection circuit 202 is correspondingly connected to the sampling pin of the insulation detection circuit 203 for sampling the same position. That is, at least one side of the adhesion detection circuit 202 is correspondingly connected to the sampling pin of another circuit.
[0087] It should be noted that since the influence of cable impedance on high-voltage sampling results can be ignored, sampling points with the same or substantially the same potential can be regarded as the same positions mentioned above. For example, different sampling points on the same cable or on different cables connected in parallel whose potential difference is less than a certain threshold can be regarded as the same positions.
[0088] Furthermore, any two connected sampling pins are externally connected through the same interface on the electric energy metering device 20; thus, the connected sampling pins can share the same high-voltage sampling wire harness.
[0089] like Figure 2 As shown in , the two sides of the adhesion detection circuit 202 are respectively connected to the sampling pins of another circuit. In this case, the adhesion detection circuit 202 and the metering circuit 201 can share the wiring harnesses 1# and 2#, and the adhesion detection circuit 202 and the insulation detection circuit 203 can share the wiring harnesses 7# and 8#; compared with Figure 1 The situation shown, Figure 2 The solution shown can save four high-voltage sampling wire harnesses, that is, Figure 1 The number of high-voltage sampling harnesses is reduced by nearly 50% by using harnesses 3#, 4#, 5#, and 6# shown in FIG. 2 . In practical applications, only one side of the adhesion detection circuit 202 can be set to be connected to the corresponding sampling pin of another circuit. For example, the adhesion detection circuit 202 only shares harnesses 1# and 2# with the metering circuit 201, and the adhesion detection circuit 202 is still connected to the metering circuit 201 through Figure 1 The wiring harnesses 5# and 6# shown in FIG. 1 are subjected to high voltage sampling, and the insulation detection circuit 203 is still Figure 1 The wiring harnesses 7# and 8# shown in the figure are used for high voltage sampling. In this case, Figure 1 Alternatively, the adhesion detection circuit 202 only shares the wiring harnesses 7# and 8# with the insulation detection circuit 203, and the adhesion detection circuit 202 still passes Figure 1 The wiring harnesses 3# and 4# shown in FIG. 1 are used for high voltage sampling, and the metering circuit 201 is still connected through Figure 1 The wiring harnesses 1#, 2# and 9# shown in the figure are used for high voltage sampling. In this case, Figure 1 Wire harnesses 5# and 6# are shown in FIG.
[0090] The electric energy metering device 20 provided in this embodiment, through the above principle, allows the connected sampling pins to share the same sampling wire harness, thereby reducing the number of sampling wire harnesses and avoiding the problems of complex wiring and scattered and messy wiring inside the charging pile.
[0091] In addition, the electric energy metering device 20 combines the functions of electric energy metering with insulation detection and adhesion detection. While reducing the high-voltage sampling wiring harness, compared with the existing technology in which the high-voltage sampling of each circuit needs to be isolated separately, this embodiment can also centrally process high-voltage sampling and share isolation circuits, thereby reducing the isolation cost of high-voltage sampling.
[0092] Based on the previous embodiment, this embodiment specifically describes the connection relationship of each sampling pin in the electric energy metering device 20:
[0093] First, in the charging pile, Figure 2 As shown, the structure for charging an electric vehicle includes: an input side switch 101, a power conversion unit 102, a shunt 103 and an output side switch 104 connected in sequence; the shunt 103 can be specifically arranged in the positive transmission branch between the output side of the power conversion unit 102 and the output side switch 104, and the function of the shunt 103 is to convert the large current signal on the output side line of the charging pile into a small voltage signal, so as to facilitate the signal processing by the charging controller 30. In addition, the negative sampling pin of the metering circuit 201 is connected to the negative pole of the output side of the power conversion unit 102 through the wiring harness 1#; the positive sampling pin of the metering circuit 201 includes a low potential current sampling pin and a high potential current sampling pin, wherein the low potential current sampling pin is connected to the current output end of the shunt 103 through the wiring harness 2#, and the high potential current sampling pin is connected to the current input end of the shunt 103 through the wiring harness 9#; the positive sampling pin of the insulation detection circuit 203 is connected to the positive pole of the output side of the charging pile through the wiring harness 8#; the negative sampling pin of the insulation detection circuit 203 is connected to the negative pole of the output side of the charging pile through the wiring harness 7#.
[0094] Based on this structure:
[0095] If the first side sampling pin of the adhesion detection circuit 202 is connected to the sampling pin of the metering circuit 201 for sampling the same position, then specifically: the first side negative electrode sampling pin of the adhesion detection circuit 202 is connected to the negative electrode sampling pin of the metering circuit 201, and both are used to connect the output side negative electrode of the power conversion unit 102, specifically through Figure 2 and the first side positive sampling pin of the adhesion detection circuit 202 is connected to the low potential current sampling pin of the metering circuit 201, both of which are used to connect the current output end of the shunt 103, specifically through Figure 2 The connection is made using the wiring harness #2 shown in FIG.
[0096] If the second side sampling pin of the adhesion detection circuit 202 is connected to the sampling pin of the insulation detection circuit 203 for sampling the same position, then specifically: the second side positive sampling pin of the adhesion detection circuit 202 is connected to the positive sampling pin of the insulation detection circuit 203, and both are used to connect the positive electrode of the output side of the charging pile, specifically through Figure 2 The wiring harness 8# shown in the figure is connected; the second side negative electrode sampling pin of the adhesion detection circuit 202 is connected to the negative electrode sampling pin of the insulation detection circuit 203, both of which are used to connect the output side negative electrode of the charging pile, specifically through Figure 2 The connection is made using the wiring harness 7# shown in FIG.
[0097] by Figure 2 Taking the situation shown as an example for explanation, the two sides of the adhesion detection circuit 202 are respectively connected to the corresponding sampling pins of another circuit and share the sampling harness. For the electric energy metering device 20, the voltage sampling on the output side of the charging pile can be realized through harnesses 1# and 2#; the voltage on both sides of the shunt 103 is taken through harnesses 9# and 2#, and then the current signal is obtained to realize current detection; the negative pole voltage on both sides of the output side switch 104 is sampled through harnesses 1# and 7#, so that the adhesion detection circuit 202 can monitor the contact state of the output side switch 104 on the negative branch to determine whether the contact is adhered; the positive pole voltage on both sides of the output side switch 104 is sampled through harnesses 2# and 8#, so that the adhesion detection circuit 202 can monitor the contact state of the output side switch 104 on the positive branch to determine whether the contact is adhered; in addition, through harnesses 7# and 8#, the needs of the insulation detection circuit 203 can be met to realize the insulation detection function.
[0098] In addition, the metering circuit 201, the insulation detection circuit 203 and the adhesion detection circuit 202 can be connected to the charging controller 30 through corresponding signal lines to report corresponding information to the charging controller 30. Figure 3In practical applications, the electric energy metering device 20 may also include: a processing module 204, so as to obtain the metering information of the metering circuit 201, the detection information of the insulation detection circuit 203 and the detection information of the adhesion detection circuit 202, and process each information respectively, and obtain the processing results including electric energy data, relay electric shock status and insulation detection results, and then report these processing results to the charging controller 30. At this time, the electric energy metering device 20 can realize a unified connection with the charging controller 30 through the processing module 204, and specifically, the electric energy data, relay electric shock status and insulation detection results can be reported to the charging controller 30 in the form of messages. In actual applications, the electric energy data specifically refers to the electric energy that has been charged into the electric vehicle currently being charged, and the charging controller 30 can charge according to the electric energy data; the relay electric contact state includes the on-off state of the two contacts in the output side switch 104 on the positive and negative branches on the output side of the charging pile. When any contact should be disconnected, if the charging controller 30 learns through the relay electric contact state that the corresponding contact is not disconnected, it can be determined that the contact is stuck; the insulation detection result specifically refers to the insulation impedance to the ground on the output side of the charging pile. The charging controller 30 can compare and judge the insulation impedance to the ground with a preset impedance threshold. If it is found that the insulation impedance to the ground is less than the preset impedance threshold, it can be determined that an insulation fault occurs on the output side of the charging pile, and it is necessary to control the input side switch 101 and the output side switch 104 to be disconnected.
[0099] Furthermore, the electric energy metering device 20 may also include a display screen for displaying the above processing results, so that the processing results of the metering circuit 201, the insulation detection circuit 203 and the adhesion detection circuit 202 can be displayed together.
[0100] The electric energy metering device 20 provided in this embodiment combines the functions of electric energy metering with insulation detection and adhesion detection, reduces high-voltage sampling harnesses, shares the isolation circuit for high-voltage sampling, and can also share the display, thereby reducing overall costs.
[0101] It should be noted that Figure 1In the existing scheme shown in , in order to realize leakage protection for the charging pile, its input side switch 01 needs to use a circuit breaker with leakage protection function, and such circuit breakers have set a fixed leakage current protection threshold; if a circuit breaker with a smaller leakage current protection threshold, such as 30mA, is used in the charging pile, it is easy to cause false tripping caused by leakage of the power conversion unit 02; in order to prevent false tripping, it is necessary to use a circuit breaker with a larger rated leakage current number, such as a circuit breaker with a leakage current protection threshold of 100mA, which greatly reduces the safety of leakage protection, fails to detect leakage accidents in time and disconnect the equipment from the power grid, and fails to play a good role in electric shock protection. Therefore, the existing scheme cannot take into account both false tripping and electric shock protection for high-power charging piles with power changes.
[0102] Therefore, in this embodiment, in the charging pile, Figure 4 or Figure 5 As shown in , a circuit breaker with leakage protection function is no longer used, but an ordinary circuit breaker is used to implement the input side switch 101, and a current sensor 111 and a leakage detection circuit are added; there are two specific implementation forms:
[0103] (1) Add a leakage protection device 100; the leakage protection device 100 can be arranged between the input side switch 101 and the input side of the charging pile (such as Figure 4 and Figure 5 As shown in ), or, it can also be set between the output side switch 104 and the output side of the charging pile, depending on its specific application environment, all of which are within the protection scope of this application.
[0104] See also Figure 4 (In Figure 3 The leakage protection device 100 can include a current sensor 111, a leakage detection circuit and a leakage communication module. The current sensor 111 can be a mutual inductor, and the leakage detection circuit can be a leakage signal processing chip. Moreover, the leakage protection device 100 can detect AC leakage and DC leakage. Specifically, when the input side of the charging pile is connected to the AC power grid, if Figure 4 As shown in the figure, if the current sensor 111 is set on the input side of the charging pile, AC leakage can be detected, and leakage of the input side switch 101 and its back-end circuit can be monitored by the leakage protection device 100; if the current sensor 111 is set on the output side of the charging pile, DC leakage can be detected; the current sensor 111 can also be set on the input side of the charging pile, and a special sensor can be used to detect and identify AC and DC leakage together; all three leakage detection methods are optional, depending on their specific application environment, and are all within the protection scope of this application.
[0105] In the leakage protection device 100 , the current sensor 111 detects the current at the corresponding position and outputs the detection information to the leakage detection circuit, which determines the leakage current and transmits the leakage data to the charging controller 30 when the leakage current is greater than the leakage threshold.
[0106] In one example, the leakage detection circuit can set the required leakage current protection threshold according to the actual situation. For example, the working leakage current corresponding to the charging pile under the current working condition can be determined based on the historical leakage data of the charging pile, and the leakage threshold under the current working condition can be set accordingly as the threshold for leakage protection; in actual applications, the leakage threshold can be set to be one leakage increment more than the working leakage current under the same working condition, thereby providing a certain margin to avoid false tripping.
[0107] During the normal operation of the charging pile, the charging controller 30 maintains communication with the leakage protection device 100 to ensure normal communication; if leakage occurs, the leakage protection device 100 sends the leakage data to the charging controller 30, and the charging controller 30 controls the input side switch 101 to disconnect and cut off the circuit.
[0108] (2) In practical applications, the leakage detection circuit can also be set in the charging controller 30, such as Figure 5 (In Figure 3 Accordingly, the current sensor 111 is arranged between the input side switch 101 and the input side of the charging pile (such as Figure 5 ), or is arranged between the output side switch 104 and the output side of the charging pile, for detecting the current at the corresponding position; the leakage detection circuit in the charging controller 30 is connected to the current sensor 111 and the processor 301 in the charging controller 30, respectively, and can receive the detection information output by the current sensor 111, determine the leakage current size according to it, and directly transmit the leakage data to the processor 301 when the leakage current is greater than the leakage threshold. The setting principle of the leakage threshold is the same as the above content, and will not be repeated here.
[0109] This embodiment not only reduces the high-voltage sampling harness and isolation costs, but also eliminates the circuit breaker with leakage protection function in the existing solution, so that the input side switch 101 can directly use a circuit breaker without leakage protection function, and realize the leakage detection function by adding a leakage protection device or by adding a current sensor 111 and a leakage detection circuit; moreover, its leakage threshold corresponds to the current working condition of the charging pile, that is, it can change according to the current working condition of the charging pile, and can also adapt to the power change of a high-power charging pile with power change, so that the leakage current monitoring is more refined, and it can respond in time when an electric shock accident occurs, thereby taking into account both false tripping and electric shock protection.
[0110] Another embodiment of the present application further provides a charging controller 30, see Figure 6 or Figure 7 , which specifically includes: a processor 301, and at least one electric energy metering device 20 as described in any of the above embodiments; wherein the processor 301 is used to: control the on-off state of the input side switch 101 and the output side switch 104 in the charging pile, and control the operation of the main circuit in the charging pile, and respectively connect with the electric energy metering device 20 and the electric vehicle connected to the charging pile. The processor 301 can specifically adopt MCU (Microcontroller Unit, microcontroller), but is not limited to this. Devices in the prior art that can realize the above functions are also within the protection scope of this application.
[0111] The structure and working principle of the electric energy metering device 20 can be referred to the above embodiment, and will not be described here one by one. In this embodiment, the electric energy metering device 20 is integrated into the charging controller 30, which can also reduce the high-voltage sampling harness, so that the metering circuit 201, the insulation detection circuit 203 and the adhesion detection circuit 202 described in the above embodiment can share the isolation circuit of high-voltage sampling, and the processing results of the three can also be displayed in a shared manner.
[0112] See also Figure 6 , when the charging pile includes the leakage protection device 100 described in the above embodiment, the charging controller 30 also includes: a communication circuit 302, which is used to connect with the leakage protection device 100 and the processor 301. That is, in the leakage protection device 100, the current sensor 111 detects the current at the corresponding position and outputs the detection information to the leakage detection circuit, which determines the leakage current and transmits the leakage data to the processor 301 through the leakage communication module and the communication circuit 302 in sequence when the leakage current is greater than the leakage threshold.
[0113] During the normal operation of the charging pile, the processor 301 maintains communication with the leakage protection device 100 to ensure normal communication; if leakage occurs, the leakage protection device 100 sends the leakage data to the processor 301, and the processor 301 controls the input side switch 101 to disconnect and cut off the circuit.
[0114] In actual applications, when the charging controller 30 communicates with other devices, such as between the communication circuit 302 and the leakage protection device 100, and between the processor 301 and the processing module 204 in the electric vehicle and the electric energy metering device 20, they can be connected through corresponding communication lines, or they can communicate with each other through wireless communication, depending on the specific application environment, which is within the protection scope of this application; the communication connections in each figure are shown as dotted line connections.
[0115] As described in the above embodiment, in practical applications, the above leakage detection circuit can also be set in the charging controller 30, such as Figure 7 As shown in ; the setting position of the current sensor 111 and the setting principle of the leakage threshold can all be referred to the above embodiment and will not be repeated here.
[0116] The charging controller 30 provided in this embodiment can further cancel the circuit breaker with leakage protection function in the existing solution on the basis of reducing the high-voltage sampling harness and isolation costs, so that the input side switch 101 can directly use a circuit breaker without leakage protection function, and realize the leakage detection function by adding a leakage protection device or adding a current sensor 111 and a leakage detection circuit; moreover, its leakage threshold corresponds to the current working condition of the charging pile, that is, it can change according to the current working condition of the charging pile, and can also adapt to the power change of a high-power charging pile with power change, so that the leakage current monitoring is more refined, and it can respond in time when an electric shock accident occurs, thereby taking into account both false tripping and electric shock protection.
[0117] Another embodiment of the present application further provides a charging pile, such as Figure 8 As shown in, it includes: a main circuit, a charging controller 30, and at least one electric energy metering device 20; wherein:
[0118] like Figures 2 to 5 As shown in, the main circuit includes at least one ( Figures 2 to 5 The power conversion unit 102 is shown in the figure with one as an example. The input side of the power conversion unit 102 is connected to the input side of the charging pile through the input side switch 101. The output side of the power conversion unit 102 is connected to the corresponding output side of the charging pile through the shunt 103 and the output side switch 104 in turn. The shunt 103 can be specifically arranged in the positive transmission branch between the output side of the power conversion unit 102 and the output side switch 104.
[0119] The input side of the charging pile is used to connect to the power grid, and the output side of the charging pile is used to connect to the electric vehicle.
[0120] In practical applications, the input side of the charging pile can be connected to an AC grid or a DC grid, which is not limited here. In addition, the main circuit can include multiple branches to connect multiple electric vehicles through the output sides of the charging pile, and each branch can be provided with: an input side switch 101, a power conversion unit 102, a shunt 103 and an output side switch 104 connected in sequence.
[0121] It should be noted that the description of the input and output sides of the charging pile and its power conversion units 102 in this application is explained by taking the operating mode of charging the electric vehicle after taking electricity from the power grid as an example; in actual applications, the charging pile can also operate in other modes, such as in V2V (Vehicle to Vehicle) or V2G (Vehicle to Grid) application scenarios, electric energy can also flow from the input side of the charging pile or any power conversion unit 102 to the input side; the naming of the above input and output sides is only to distinguish different sides of the same device, and does not limit the flow direction of electric energy.
[0122] In addition, the electric energy metering device 20 is used to measure the electric energy for the corresponding power conversion unit 102; in any branch, the input side switch 101, the output side switch 104 and the power conversion unit 102 are respectively controlled by the charging controller 30; and the charging controller 30 is connected to the electric energy metering device 20 and the electric vehicle connected to the charging pile. For the above basic structure and working principle of the charging pile, please refer to the prior art, and no further description will be given here.
[0123] The present embodiment is different from the prior art in any of the following situations:
[0124] (1) The electric energy metering device 20 is an electric energy metering device 20 as described in any of the above embodiments (such as Figures 2 to 5 ).
[0125] (2) The charging controller 30 is a charging controller 30 as described in any of the above embodiments (such as Figure 6 or Figure 7 That is, the electric energy metering device 20 can also be integrated into the charging controller 30. Figure 8 The following only shows the two independent settings as an example, but the actual application is not limited to this.
[0126] (3) See Fig. 9 Although the electric energy metering device 20 is a DC electric energy meter in the prior art, the charging controller 30 is also the same as that in the prior art, and the power conversion unit 102 in any branch is equipped with an insulation detection circuit 203 and a adhesion detection circuit 202, in any branch, the first side sampling pin of the adhesion detection circuit 202 is connected to the sampling pin of the electric energy metering device 20 for sampling the same position, and / or the second side sampling pin of the adhesion detection circuit 202 is connected to the sampling pin of the insulation detection circuit 203 for sampling the same position. Fig. 9 In the figure, the example in which both sides of the adhesion detection circuit 202 are connected to corresponding sampling pins of other circuits is used for demonstration.
[0127] In this embodiment, the scheme for high-voltage sampling can adopt any of the above-mentioned situations; that is, regardless of whether the insulation detection circuit 203 and the adhesion detection circuit 202 of each branch are integrated in the electric energy metering device 20 of the branch, as long as they are connected through the sampling pins of different circuits to share the high-voltage sampling harness and save the high-voltage sampling harness, they are all within the protection scope of this application. The principle of saving high-voltage sampling harnesses by connecting the sampling pins of different circuits can be referred to the above embodiments, which will not be repeated here. It should be noted that for the third case, the insulation detection circuit 203 and the adhesion detection circuit 202 can also be set in other positions, for example, both or any one of them can also be independent of the charging controller 30; it depends on the specific application environment, and it is all within the protection scope of this application.
[0128] In practical applications, the input side switch 101 may be a circuit breaker, and the output side switch 104 may be a contactor, a relay, etc.; the power conversion unit 102 may be configured to include only one power module (such as Figures 2 to 9 Alternatively, it may include a plurality of power modules connected in parallel ( Fig.10 or Fig.11 Take two power modules in parallel as an example for demonstration); moreover, the specific structure of the power module can be selected according to the type of power grid connected to the input side of the charging pile. For example, when the power grid is an AC power grid, the power module is an AC / DC conversion circuit (such as Figures 2 to 10 Alternatively, the power module includes an AC / DC conversion circuit and a DC / DC conversion circuit connected in series (as shown in Fig.12 ); when the power grid is a DC power grid, the power module is a DC / DC conversion circuit (as shown in Fig.11 ).
[0129] In addition, when there are multiple branches connected to electric vehicles in the charging pile, that is, when the number of power conversion units 102 is greater than 1, each power conversion unit 102 can share the same input side switch 101 to connect to the input side of the charging pile (such as Fig.13 or Fig.14 ), or respectively use the corresponding input side switches 101 to connect the input side of the charging pile (as shown in Fig.15 As shown in FIG. 1 , any two power conversion units 102 can also share the same input side switch 101 (as shown in FIG. Fig.16 In practical applications, Fig.16 The structure shown can be applied to DC grid V2V charging scenarios; Fig.14 The structure shown can be applied to AC power grid V2V charging scenarios.
[0130] It is worth noting that when there are multiple branches connected to electric vehicles in the charging pile, the structures of the power conversion units 102 in each branch do not need to be the same. Figures 13 to 16 Specifically, in different power conversion units 102, the number of power modules connected in parallel may be different (eg Fig.13 , Fig.15 and Fig.16 ), the topology adopted by the power module may also be different, and even one power conversion unit 102 may adopt part of the circuit in another power conversion unit 102 (such as Fig.14 It depends on the specific application environment and is within the protection scope of this application.
[0131] Furthermore, when there are multiple branches connected to electric vehicles in the charging pile, the electric energy metering device 20 corresponding to each branch can be integrated into the charging controller 30, or a part of it can be integrated into the charging controller 30 and the other part can be independent of the charging controller 30 (such as Fig.13 , Fig.15 and Fig.16 ), and can also be independent of the charging controller 30 (as shown in Fig.14 ), not limited here.
[0132] On the basis of the above embodiments, in order to realize leakage detection and protection, the charging pile provided in this embodiment may further include: a leakage protection device 100 (such as Figure 4 , Figure 6 , Fig. 9 , Fig.10 , Fig.11 , Fig.13 , Fig.15 and Fig.16 The leakage protection device 100 can be arranged between the input side switch 101 and the input side of the charging pile (as shown in the various figures), or can also be arranged between the output side switch 104 and the output side of the charging pile (not shown in the figures), both of which are within the protection scope of the present application; and the leakage protection device 100 is connected to the charging controller 30.
[0133] As described in the above embodiments, the leakage protection device 100 may specifically include: a current sensor 111, a leakage detection circuit and a leakage communication module; wherein the current sensor 111 is arranged between the input side switch 101 and the input side of the charging pile, or between the output side switch 104 and the output side of the charging pile, and its output end is connected to the input end of the leakage detection circuit; the output end of the leakage detection circuit is connected to one side of the leakage communication module; the other side of the leakage communication module is used to connect to the charging controller 30.
[0134] Alternatively, the charging pile may also include: a current sensor 111 (such as Figure 5 , Figure 7 , Fig.12 and Fig.14 The current sensor 111 may be disposed between the input side switch 101 and the input side of the charging pile (as shown in the various figures), or may be disposed between the output side switch 104 and the output side of the charging pile (not shown), both being within the protection scope of the present application; the input end of the current sensor 111 is connected to the leakage detection circuit in the charging controller 30.
[0135] Similarly, as described in the above embodiments, the leakage threshold of the leakage protection device 100, or the leakage threshold of the leakage detection circuit, corresponds to the current operating condition of the charging pile; for example, both leakage thresholds can be set to: the sum of the leakage increment and the working leakage current of the charging pile under the current operating condition; and the working leakage current is determined based on the historical leakage data of the charging pile.
[0136] The leakage detection and protection principles in the two cases can be found in the above embodiments and will not be described in detail here.
[0137] The charging pile provided in this embodiment can reduce the high-voltage sampling harness and can also cancel the circuit breaker with leakage protection function in the existing solution, so that the input side switch 101 can directly use a circuit breaker without leakage protection function, and realize the leakage detection function by adding a leakage protection device or adding a current sensor 111 and a leakage detection circuit; moreover, its leakage threshold can be changed according to the current working condition of the charging pile, and for a high-power charging pile with power changes, it can also adapt to its power changes, so that the leakage current monitoring is more refined, and it can respond in time when an electric shock accident occurs, thereby taking into account both false tripping and electric shock protection.
[0138] Another embodiment of the present application further provides a leakage protection method for a charging pile, which is applied to the charging pile described in any of the above embodiments. The leakage protection method is as follows: Fig.17 As shown in, including:
[0139] S101. Obtain the leakage value of the charging pile.
[0140] Specifically, the leakage detection circuit described in the above embodiment determines the leakage current size according to the detection information output by the current sensor 111 as the leakage value.
[0141] If the leakage detection circuit detects that the leakage value exceeds the leakage threshold, the charging controller may be notified through communication so that it can execute S102.
[0142] S102, controlling the input side switch of the charging pile to be disconnected.
[0143] As described in the above embodiment, a current sensor 111 and a leakage detection circuit are provided in the charging pile. Regardless of whether the two are integrated in a leakage protection device or the leakage detection circuit is provided in a charging controller, as long as the leakage detection circuit detects that the leakage value exceeds the leakage threshold, it can be determined that leakage occurs, and then the processor of the charging controller is notified so that the processor can control the input side switch to disconnect.
[0144] In actual applications, after the processor learns that a leakage has occurred, the output side switch can be controlled to be disconnected as well; moreover, specifically, only the input side switch and the output side switch of the branch involved in the location where the leakage current occurs can be controlled to be disconnected, or the input side switch and the output side switch of each branch in the charging pile can be controlled to be disconnected; it depends on the specific application environment and is within the protection scope of this application.
[0145] The leakage threshold can be set to: the sum of the leakage increment and the working leakage current of the charging pile under the current working conditions; wherein the working leakage current is determined based on the historical leakage data of the charging pile, and the leakage increment is determined based on the leakage current detection type under the power grid to which the charging pile is connected and the leakage current planned to be monitored.
[0146] In practical applications, the generation process of the leakage threshold can be specifically described as follows:
[0147] Set the leakage current increment according to the leakage current detection type of the power grid to which the charging pile is connected and the leakage current to be monitored.
[0148] It is understandable that the power grid to which the charging pile is connected can be an AC power grid or a DC power grid; when connected to different power grids, the leakage current detection position is different, and the leakage increment △I will also be different. After the leakage current detection position is set for the charging pile, it can be determined whether to detect AC leakage, DC leakage, or both AC and DC leakage to set the leakage increment △I.
[0149] The role of the leakage increment △I, that is, to provide a certain margin to avoid false tripping as described in the above embodiment, can be within 15 to 30 mA, for example, 15 mA. In practical applications, the leakage increment △I can also be modified according to the input leakage current to be monitored, wherein the leakage current to be monitored can be determined according to the actual situation of the charging pile, such as the different powers, and is not limited here, and can be determined according to the specific application environment.
[0150] According to the historical leakage data of the charging pile, determine the working leakage current corresponding to the current working condition.
[0151] It is understandable that the charging pile can have multiple operating conditions, such as: power-on, stable operation, end of operation, standby, etc.; moreover, when operating stably, the charging pile can also be divided into multiple different power segments. For example, different powers can be achieved by controlling the number of parallel power modules.
[0152] Therefore, the historical leakage data may include leakage data under the various working conditions mentioned above; in practical applications, for each working condition, the average value of all leakage data under the working condition since the first operation of the charging pile can be calculated respectively, and used as the leakage data of the corresponding working condition; various working conditions and their corresponding leakage data are made into a leakage characteristic table, so that when determining the working leakage current Iw corresponding to the current working condition, the table can be looked up according to the current working condition to determine the corresponding leakage data as the working leakage current Iw.
[0153] In practical applications, the leakage characteristic table can be stored in the charging pile in advance, and the leakage characteristic table can be updated in real time or according to a certain period to ensure that the obtained working leakage current Iw is closer to the actual situation of the charging pile.
[0154] That is, under different working conditions, such as power-on conditions and stable operating conditions with output powers of 60kW, 90kW, 120kW, 240kW, etc., the working leakage current Iw is different.
[0155] The sum of the working leakage current and the leakage increment is taken as the leakage threshold.
[0156] That is, the leakage threshold I △ The calculation formula is: △ =Iw+△I.
[0157] It can be understood that since the working leakage current Iw varies according to the current working condition of the charging pile, the leakage threshold I △ It changes according to the current working condition of the charging pile. In practical applications, the working status and / or working time of the charging pile can be monitored in real time to determine its working condition, and then the corresponding leakage threshold I can be determined in real time. △ ; Then the leakage detection circuit determines that the current leakage value exceeds the corresponding leakage threshold I △ In the event of a fault, the situation will be reported to the charging controller, causing the charging controller to issue an instruction to cut off the corresponding circuit.
[0158] The leakage threshold I △ A leakage increment △I is added to the working leakage current Iw, and then under the current working state, only when the leakage value exceeds the working leakage current Iw by a leakage increment △I, it is determined to be a leakage and the circuit needs to be cut off.
[0159] For example, when the charging pile is powered on, the leakage current is large. Although it exceeds the working leakage current Iw under the current working condition, the leakage detection circuit can increase an appropriate leakage increment △I according to the characteristic of large leakage current under the power-on condition to obtain the corresponding leakage threshold I △ , in order to filter out the larger leakage current when the charging pile is started without reporting the leakage fault, eliminate self-interference, prevent malfunction, and only pay attention to whether the leakage current further exceeds the leakage increment △I above the working leakage current Iw. Under stable operating conditions, the leakage threshold I can also be adjusted in real time according to the power of the charging pile. △ .
[0160] In this embodiment, under different working conditions, by changing different leakage thresholds I △ , real-time adjustment of the leakage protection strategy can ensure accurate protection under various working conditions, which can not only reduce false tripping, but also disconnect the equipment from the power grid more promptly to prevent electric shock.
[0161] The same and similar parts between the various embodiments in this specification can refer to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the system or system embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can refer to the partial description of the method embodiment. The system and system embodiments described above are only schematic, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules can be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative work.
[0162] Professionals may further appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in the above description according to function. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians may use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.
[0163] With respect to the above description of the disclosed embodiments, the features described in the various embodiments in this specification may be replaced or combined with each other to enable professionals in the field to implement or use the present invention. Various modifications to these embodiments will be apparent to professionals in the field, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. An electric energy metering device, characterized in that: include: Metering circuit, insulation detection circuit and adhesion detection circuit; wherein, The metering circuit is used to sample the output side voltage and current of the charging pile where the electric energy metering device is located, and to perform electric energy metering according to the sampled information; The adhesion detection circuit is used to perform adhesion detection on the output side switch, wherein the output side switch is arranged between the output side of the power conversion unit in the main circuit of the charging pile and the output side of the charging pile; The insulation detection circuit is used to perform insulation detection on the output side of the charging pile; The first side sampling pin of the adhesion detection circuit is connected to the sampling pin of the metering circuit for sampling the same position; and / or the second side sampling pin of the adhesion detection circuit is connected to the sampling pin of the insulation detection circuit for sampling the same position; Any two connected sampling pins are connected to the outside through the same interface on the electric energy metering device.
2. The electric energy metering device according to claim 1, characterized in that: The negative electrode sampling pin of the metering circuit is used to connect the negative electrode of the output side of the power conversion unit; The low potential current sampling pin of the metering circuit is used to connect the current output end of the shunt; the shunt is arranged in the positive transmission branch between the output side of the power conversion unit and the output side switch; The high potential current sampling pin of the metering circuit is used to connect the current input terminal of the shunt; The first side negative electrode sampling pin of the adhesion detection circuit is connected to the negative electrode sampling pin of the metering circuit; The first-side positive sampling pin of the adhesion detection circuit is connected to the low-potential current sampling pin of the metering circuit.
3. The electric energy metering device according to claim 1, characterized in that: The positive sampling pin of the insulation detection circuit is used to connect the positive electrode of the output side of the charging pile; The negative electrode sampling pin of the insulation detection circuit is used to connect the negative electrode of the output side of the charging pile; The second side positive sampling pin of the adhesion detection circuit is connected to the positive sampling pin of the insulation detection circuit; The second side negative electrode sampling pin of the adhesion detection circuit is connected to the negative electrode sampling pin of the insulation detection circuit.
4. The electric energy metering device according to any one of claims 1 to 3, characterized in that: Also includes: The processing module is used to process the metering information of the metering circuit, the detection information of the insulation detection circuit and the detection information of the adhesion detection circuit respectively, and report the processing results to the charging controller of the charging pile.
5. The electric energy metering device according to claim 4, characterized in that: Also includes: A display screen is used to display the processing results.
6. A charging controller, characterized in that: include: A processor, and at least one electric energy metering device according to any one of claims 1 to 5; wherein, The processor is connected to the electric energy metering device and the electric vehicle connected to the charging pile respectively; wherein the processor is used to: control the on-off state of the input side switch and the output side switch in the charging pile, and control the operation of the main circuit in the charging pile.
7. The charging controller according to claim 6, characterized in that: A leakage protection device is provided between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile; wherein the leakage threshold of the leakage protection device corresponds to the current working condition of the charging pile; The charging controller also includes: a communication circuit, which is used to communicate with the leakage protection device and connect with the processor.
8. The charging controller according to claim 6, characterized in that: A current sensor is provided between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile; The charging controller further includes: a leakage detection circuit connected to the current sensor and the processor respectively; The leakage threshold of the leakage detection circuit corresponds to the current operating condition of the charging pile.
9. A charging pile, characterized in that: include: A main circuit, a charging controller, and at least one electric energy metering device; wherein, The main circuit includes at least one power conversion unit, the input side of the power conversion unit is connected to the input side of the charging pile through an input side switch, and the output side of the power conversion unit is connected to the corresponding output side of the charging pile through a shunt and an output side switch in sequence; The input side of the charging pile is used to connect to the power grid, and the output side of the charging pile is used to connect to the electric vehicle; The electric energy metering device is used to measure the electric energy for the corresponding power conversion unit; The input side switch, the output side switch and the power conversion unit are respectively controlled by the charging controller; the charging controller is connected to the electric energy metering device and the electric vehicle connected to the charging pile; Wherein, the electric energy metering device is the electric energy metering device as described in any one of claims 1 to 5; or, the charging controller is the charging controller as described in any one of claims 6 to 8; or, the power conversion unit is equipped with an insulation detection circuit and a adhesion detection circuit, and the first side sampling pin of the adhesion detection circuit is correspondingly connected to the sampling pin of the electric energy metering device of the same power conversion unit for sampling the same position, and / or, the second side sampling pin of the adhesion detection circuit is correspondingly connected to the sampling pin of the insulation detection circuit of the same power conversion unit for sampling the same position.
10. The charging pile according to claim 9, characterized in that: Also includes: Leakage protection device; The leakage protection device is arranged between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile, and is connected to the charging controller; The leakage threshold of the leakage protection device corresponds to the current working condition of the charging pile.
11. The charging pile according to claim 10, characterized in that: The leakage protection device comprises: a current sensor, a leakage detection circuit and a leakage communication module; wherein, The current sensor is arranged between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile, and its output end is connected to the input end of the leakage detection circuit; The output end of the leakage detection circuit is connected to one side of the leakage communication module; The other side of the leakage communication module is used to connect with the charging controller.
12. The charging pile according to claim 9, characterized in that: Also includes: Current sensor; The current sensor is arranged between the input side switch and the input side of the charging pile, or between the output side switch and the output side of the charging pile; The input end of the current sensor is connected to the leakage detection circuit in the charging controller; The leakage threshold of the leakage detection circuit corresponds to the current operating condition of the charging pile.
13. The charging pile according to any one of claims 9 to 12, characterized in that: When the number of the power conversion units is greater than 1: Each of the power conversion units is connected to the input side of the charging pile through the corresponding input side switch; Alternatively, at least two of the power conversion units share the same input-side switch.
14. The charging pile according to any one of claims 9 to 12, characterized in that: The power conversion unit includes: a power module, or a plurality of power modules connected in parallel.
15. The charging pile according to claim 14, characterized in that: In the case where the power grid is an AC power grid, the power module is an AC / DC conversion circuit, or the power module includes an AC / DC conversion circuit and a DC / DC conversion circuit connected in series; Alternatively, when the power grid is a direct current power grid, the power module is a DC / DC conversion circuit.
16. A leakage protection method for a charging pile, characterized in that: Applied to the charging pile according to any one of claims 9 to 15, the leakage protection method comprises: Get the leakage value of the charging pile; If the leakage value exceeds the leakage threshold, the input side switch of the charging pile is controlled to be disconnected.
17. The leakage protection method for a charging pile according to claim 16, characterized in that: The leakage threshold is: the sum of the leakage increment and the working leakage current of the charging pile under the current working condition; The working leakage current is determined according to the historical leakage data of the charging pile, and the leakage increment is determined according to the leakage current detection type of the power grid to which the charging pile is connected and the leakage current planned to be monitored.
Citation Information
Cited By
Automatic detection method for insulation leakage of electric energy metering box
CN122506432A