Multi-objective collaborative optimization method and system for shield construction management

By constructing a multi-objective collaborative optimization model and solving the E-NSWOA algorithm, the problem of collaborative optimization of safety, cost, quality and construction period in the shield tunnel construction management of the subway section was solved, a scientific and reasonable selection of construction plans was achieved, and the efficiency of construction management was improved. Scientific and effective.

CN118798499APending Publication Date: 2024-10-18EAST CHINA JIAOTONG UNIVERSITY

Patent Information

Application Number
CN202411287754.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-14
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

It is difficult to achieve multi-objective collaborative optimization of safety, cost, quality and construction period in the shield construction management of subway section projects, and there are high risks and management problems.

Method used

Construct the construction period, cost, quality and safety sub-models to form a multi-objective collaborative optimization model, and use the E-NSWOA algorithm to solve the problem and provide a scientific and reasonable construction plan.

Benefits of technology

Through multi-objective collaborative optimization, scientific and reasonable plan selection for shield construction of subway section projects was achieved, which improved the scientificity and effectiveness of construction management and reduced risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118798499A_ABST
    Figure CN118798499A_ABST
Patent Text Reader

Abstract

The invention discloses a multi-objective collaborative optimization method and system for shield construction management. The scheme comprises the following steps: constructing a subway interval project shield construction management quality-safety-progress-cost multi-objective collaborative optimization element system; building a metro interval project shield construction period, cost, quality and safety target calculation formula, setting constraint conditions, and forming a multi-target collaborative optimization model of metro interval project shield construction management; and the E-NSWOA algorithm is used to solve the multi-target collaborative optimization model of subway section project shield construction management. And more scientific and reasonable scheme selection is provided for shield construction management of subway section projects through multi-objective collaborative optimization.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of shield construction of subway section projects, and in particular relates to a multi-objective collaborative optimization method and system for shield construction management. Background Art

[0002] As a high-speed, large-capacity electric traction railway, the subway can make full use of the underground, relieve the pressure brought by traffic, reduce urban noise and environmental pollution; at the same time, it can also promote the rapid growth of related industries, enrich the city's economic development, increase employment opportunities, and strengthen the connection between regions. However, subways are generally built in busy streets and places where buildings are densely distributed in the city. The underground pipeline network is complex and may have a great impact on the surrounding underground facilities. Therefore, in order to meet the requirements of urban subway construction, shield construction as a modern, efficient and safe underground engineering construction method is widely used in the construction of major subway sections.

[0003] Subway shield construction can be applied to various geological conditions and ensure construction quality, but due to its high equipment cost and the many complex risk factors in the construction process of subway section projects, it is difficult for managers to achieve scientific and comprehensive balanced optimization. On the basis of meeting safety requirements, taking into account multiple goals such as cost, quality and construction period, and achieving multi-objective coordinated optimization of subway section project shield construction management has become a hot and difficult issue that the current management field is committed to solving. Summary of the invention

[0004] The present invention provides a multi-objective collaborative optimization method and system for shield construction management, which are used to solve the technical problem that multi-objective collaborative optimization cannot be performed on shield construction management of subway section projects.

[0005] In a first aspect, the present invention provides a multi-objective collaborative optimization method for shield construction management, comprising: Construct the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model; Under preset constraints, a multi-objective collaborative optimization model for shield construction management is constructed according to the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model. The expression of the multi-objective collaborative optimization model is: , In the formula, The total construction period of the shield construction of the subway section project is is the total cost of shield construction for the subway section project, To improve the quality of shield construction in subway section projects. The safety level of shield construction in subway section projects. For process The actual duration of For process The direct costs corresponding to the normal duration of For key lines, For process The direct cost coefficient, For process The normal duration of is the indirect cost coefficient, is a natural constant, For process The quality level corresponding to the shortest duration of For process The minimum duration of For process The safety impact margin coefficient, For process Cost of normal duration, For process The safety level during normal duration, For process Cost of minimum duration, is the number of processes, , They are all integral operation symbols. For rewards received one day earlier or later, Plan the total completion period for shield construction of subway section projects; The multi-objective collaborative optimization model is solved according to the preset E-NSWOA algorithm to obtain the multi-objective collaborative optimization result.

[0006] In a second aspect, the present invention provides a multi-objective collaborative optimization system for shield construction management, comprising: A first construction module is configured to construct a construction period sub-model, a total construction cost target sub-model, a quality sub-model, and a safety sub-model; The second construction module is configured to construct a multi-objective collaborative optimization model for shield construction management according to the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model under preset constraints. The expression of the multi-objective collaborative optimization model is: , In the formula, The total construction period of the shield construction of the subway section project is is the total cost of shield construction for the subway section project, To improve the quality of shield construction in subway section projects. The safety level of shield construction in subway section projects. For process The actual duration of For process The direct costs corresponding to the normal duration of For key lines, For process The direct cost coefficient, For process The normal duration of is the indirect cost coefficient, is a natural constant, For process The quality level corresponding to the shortest duration of For process The minimum duration of For process The safety impact margin coefficient, For process Cost of normal duration, For process The safety level during normal duration, For process Cost of minimum duration, is the number of processes, , They are all integral operation symbols. For rewards received one day earlier or later, Plan the total completion period for shield construction of subway section projects; The solution module is configured to solve the multi-objective collaborative optimization model according to a preset E-NSWOA algorithm to obtain a multi-objective collaborative optimization result.

[0007] According to a third aspect, an electronic device is provided, comprising: at least one processor, and a memory communicatively connected to the at least one processor, wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor can perform the steps of the multi-objective collaborative optimization method for shield construction management of any embodiment of the present invention.

[0008] In a fourth aspect, the present invention further provides a computer-readable storage medium having a computer program stored thereon, wherein when the program instructions are executed by a processor, the processor executes the steps of the multi-objective collaborative optimization method for shield construction management of any embodiment of the present invention.

[0009] The multi-objective collaborative optimization method and system for shield construction management of this application constructs a multi-objective collaborative optimization element system of quality-safety-progress-cost for shield construction management of subway section projects; establishes calculation formulas for the construction period, cost, quality, and safety targets of shield construction of subway section projects, sets constraints and forms a multi-objective collaborative optimization model for shield construction management of subway section projects; and uses the E-NSWOA algorithm to solve the multi-objective collaborative optimization model for shield construction management of subway section projects. Through multi-objective collaborative optimization, a more scientific and reasonable solution selection is provided for shield construction management of subway section projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0011] Figure 1 A flowchart of a multi-objective collaborative optimization method for shield construction management provided by an embodiment of the present invention; Figure 2 A structural block diagram of a multi-objective collaborative optimization system for shield construction management provided by an embodiment of the present invention; Figure 3 It is a schematic diagram of the structure of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0012] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0013] See also Figure 1 , which shows a flow chart of a multi-objective collaborative optimization method for shield construction management of the present application.

[0014] like Figure 1 As shown in Figure 2, the multi-objective collaborative optimization method for shield construction management specifically includes the following steps: Step S101, constructing a construction period sub-model, a total construction cost target sub-model, a quality sub-model and a safety sub-model.

[0015] In this step, the factors that affect the construction period of the shield tunneling project of the subway section project are divided into three categories: construction factors, construction conditions and organizational management. The construction factors are further subdivided into shield machine type, tunnel diameter, maximum thrust, cutter head speed, and main drive power. The construction conditions are further subdivided into hydrological conditions, geological conditions, and environmental protection requirements. The organizational management is further subdivided into operation mode, supply of personnel, materials, and machines, and management level. The factors that affect the shield construction cost of subway section projects are divided into two parts: direct costs and indirect costs, which are mainly composed of labor costs, material costs, machinery costs, other direct costs and indirect costs; The factors that affect the quality of shield construction in subway section projects are divided into construction preparation, segment production and acceptance, tunneling construction, segment assembly, back-wall grouting and construction in special areas; The factors that affect the safety of shield construction in subway section projects are divided into four parts: safety organization management, safety technology management, environmental safety management, and safety monitoring and early warning management. Among them, safety organization management evaluates the construction safety organization management work of the main construction units participating in the entire process of shield construction in subway section projects, focusing on the evaluation of the status and level of the construction safety management responsibilities of the participating units, and is further subdivided into three parts: safety management organization and personnel, production safety system, and construction site safety management. Safety technology management evaluates the safety management work of machinery, materials, and various construction methods in the construction process, and is further subdivided into shield selection and configuration, shield working shaft, and shield starting. It is divided into five parts: arrival, shield tunneling, and communication channel construction; environmental safety management is aimed at the disturbance of the surrounding environment caused by the shield construction of the subway section project and the new sources of danger caused by unexplored special circumstances, and is further subdivided into three parts: engineering and hydrogeology, surrounding buildings (structures), and underground pipelines; safety monitoring and early warning management can timely discover risks, control risks, and eliminate engineering hazards, thereby improving the real-time early warning and vigilance capabilities of safety risks, as well as the prediction and prevention capabilities of catastrophic accidents. It plays a very important role in the safety control of the shield construction process of the subway section project, and is further subdivided into three parts: safety risk management, safety monitoring management, and safety early warning management.

[0016] The construction period of the subway section project shield tunnel is a dynamic development control of each process in the construction process. It is organized according to the construction period target plan, and the actual construction situation is compared and analyzed with the plan to correct the deviation and prevent construction delays. The construction period sub-model is constructed based on the duration of key work on the critical route. , In the formula, The total construction period of the shield construction of the subway section project is For key lines, For process The normal duration of For process The minimum duration of For process The actual duration of

[0017] The total project cost includes direct cost, indirect cost and reward and punishment funds. The direct cost is the sum of the direct costs of each process. The direct cost sub-model is established as follows: , , In the formula, is the direct cost coefficient of process i, The direct cost of shield construction for the subway section project. is the direct cost corresponding to the normal duration of process i, is the direct cost corresponding to the shortest duration of process i; Indirect costs are fixed costs for construction companies to operate, which have no direct relationship with product production. They are mainly the salaries of management personnel and house depreciation, etc. They increase with the extension of the construction period. On the contrary, if the construction period is shortened, the on-site construction management fees and rental fees will also decrease. The two increase and decrease in a positive correlation. The indirect costs of shield construction of subway section projects are evenly allocated to each day, and the indirect cost sub-model is established as follows: , In the formula, The indirect cost of shield construction for subway section projects. is the indirect cost coefficient; In actual projects, the project will enter the profit period ahead of schedule due to the shortened construction period, and the profit will increase as the construction period is shortened; while the delay in construction period will also lead to reduced profit on the basis of increased costs; in order to better motivate and urge each construction unit to complete the project as soon as possible, the enterprise will set up a certain reward and punishment mechanism, and the reward and punishment fund sub-model is: , In the formula, The amount of rewards and penalties received for the early completion or delayed construction of the subway section project shield construction, For rewards received one day earlier or later, Plan the total completion period for shield construction of subway section projects; Therefore, the total cost target sub-model of shield construction for subway section projects is: , In the formula, The total cost of shield construction for the subway section project; There is a nonlinear relationship between quality and duration. When the construction period is tight, compressing the construction period will affect the quality level of the process. When the construction period is compressed by a small amount, the quality level decreases slowly, and when the construction period is compressed by a large amount, the quality level decreases quickly. When the process duration is the normal duration, the process quality is the largest, and when the process duration is the shortest duration, the process quality coefficient is the smallest. The quality sub-model is established as: , In the formula, is the number of processes, , They are all integral operation symbols. is a natural constant, For process The quality level corresponding to the shortest duration of For process The normal duration of For process the minimum duration of Within a reasonable construction period, as the cost increases, the safety level is gradually improved, and the safety sub-model is established as follows: , , , In the formula, The safety level of shield construction in subway section projects. For process The minimum duration of safety level, For process The safety level during normal duration, For process The safety impact margin coefficient, For process Cost of minimum duration, For process Cost of normal duration, Cost for normal duration.

[0018] Step S102: constructing a multi-objective collaborative optimization model for shield construction management according to the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model under preset constraints.

[0019] In this step, by analyzing the relationship between the four objectives and the connection between the various processes, combined with the actual situation of shield construction of subway section projects, the following constraints are made for the multi-objective collaborative optimization model of shield construction of subway section projects: Assuming the initial construction time of the subway section project ; During the construction of the subway section, the total construction period should meet the required construction period ,Right now ; The duration of each process meets ; The direct cost of each process meets ; The quality of general projects in shield tunneling section construction is qualified when it reaches 95% or above; according to this requirement, the project quality should meet ; According to the existing specifications, in the construction management of subway section projects, each process has a minimum safety standard that must be met. The total value of the metric is 1, and the overall score should be ; The expression of the multi-objective collaborative optimization model is: , In the formula, The total construction period of the shield construction of the subway section project is is the total cost of shield construction for the subway section project, To improve the quality of shield construction in subway section projects. The safety level of shield construction in subway section projects. For process The actual duration of For process The direct costs corresponding to the normal duration of For key lines, For process The direct cost coefficient, For process The normal duration of is the indirect cost coefficient, is a natural constant, For process The quality level corresponding to the shortest duration of For process The minimum duration of For process The safety impact margin coefficient, For process Cost of normal duration, For process The safety level during normal duration, For process Cost of minimum duration, is the number of processes, , They are all integral operation symbols. For rewards received one day earlier or later, Plan the total completion period for shield construction of subway section projects; The constraint expression is: , In the formula, is the direct cost corresponding to the shortest duration of process i, The total construction period should meet the required construction period.

[0020] Step S103, solving the multi-objective collaborative optimization model according to a preset E-NSWOA algorithm to obtain a multi-objective collaborative optimization result.

[0021] In this step, parameters are initialized, including setting the population size, dimension, and maximum number of iterations; Population initialization: use 2D-CSCM method to randomly generate the initialization population; Fast non-dominated sorting and crowding sorting, sorting the initial population matrix by non-dominated rank and crowding distance, and returning a final population matrix; Calculate the fitness value of each individual in the population and record the optimal individual and position; Using improved search strategy, randomly generated value, and based on If the value is less than the preset threshold, select the corresponding search strategy to update the individual whale position; Adjust differential mutation and parasitic search to improve the search mechanism, and increase the number of iterations by 1; Repeat the iteration until the maximum number of iterations is reached and the loop ends.

[0022] Specifically, the population is initialized by randomly generating the initialization population using the 2D-CSCM method; the large differences and uneven distribution problems caused by randomly selecting a set of feasible solutions as the initial population within the value range are improved by adding shift parameters and control parameters, thereby improving the stability, convergence speed and solution quality of the algorithm. At the same time, the disadvantage of the existing chaotic interval discontinuity is overcome, making the system chaotic within a larger parameter range. The mathematical expression is: , In the formula, is the horizontal coordinate of the v+1th observation value, , To control the parameters, is the horizontal coordinate of the vth observation value, is the ordinate of the vth observation, is the shift parameter in the horizontal direction, is the ordinate of the v+1th observation, is the displacement parameter in the vertical direction.

[0023] In addition, the search strategy randomly generates P values, and selects the corresponding search strategy to update the individual position of the whale according to whether the P value is less than 0.5; with the continuous in-depth search and update in the later stage, the individual whale is prone to stay in the local optimal position. A search strategy that changes with the increase in the number of iterations is proposed, and the chaos adjustment coefficient is added to make the local search more refined to prevent falling into the local extreme value. The p value is randomly generated, and the p value is judged to be less than 0.5. The search strategy reference formula is: , In the formula, is the chaos regulation coefficient, is the number of iterations, is the current iteration number, is the coefficient vector, For prey and whales The distance between To determine the constant parameters of the logarithmic spiral shape, is a random number in the range [-1, 1], is the maximum number of iterations, is a random number between 0 and 1, for the location of the whale, For whales The position of the w+1th iteration, For whales No. The position of the iteration.

[0024] Furthermore, the adjustment coefficient is added to the differential mutation to produce a large jump when searching for new individuals, effectively expanding the search space and creating favorable conditions for finding the global optimal solution. In addition, the robustness of the algorithm is increased, making it less dependent on the initial solution, and the algorithm is more capable of dealing with situations where the initial solution is improperly selected or has large deviations. The calculation formula is: , In the formula, For mutation carriers, is the best individual in the population, , , are three different individuals randomly selected from the population, Indicates the first Individuals, Represents the individual Dimensional variables; Among them, the adjustment coefficient expression of differential variation is: , In the formula, is a random number in the range of [-1, 1]; The adjusted differential mutation enhances the local search capability of the algorithm, but it mainly generates new individuals based on the current optimal solution, which still has limitations. The parasitic vector with mutation adjustment factor is introduced to enhance the local search capability of the algorithm by randomly selecting some dimensions for mutation, which helps to jump out of the local optimal solution. The parasitic process of mutation factor adjustment is: , , In the formula, For mutation carriers, For organisms, is the mutation site, is the mutation adjustment factor, , are the upper and lower bounds respectively, is a random function, is the length of the mutation site; The formula for the mutation adjustment factor is: , In the formula, is a random number between 0 and 1. is the mutation perturbation value, which makes the solution range wider and more diverse.

[0025] In summary, the method of this application constructs a multi-objective collaborative optimization factor system of quality-safety-progress-cost for shield construction management of subway section projects; establishes calculation formulas for the construction period, cost, quality, and safety targets of shield construction of subway section projects, sets constraints and forms a multi-objective collaborative optimization model for shield construction management of subway section projects; and uses the E-NSWOA algorithm to solve the multi-objective collaborative optimization model for shield construction management of subway section projects. Through multi-objective collaborative optimization, a more scientific and reasonable solution selection is provided for shield construction management of subway section projects.

[0026] See also Figure 2 , which shows a structural block diagram of a multi-objective collaborative optimization system for shield construction management of the present application.

[0027] like Figure 2 As shown, the multi-objective collaborative optimization system 200 includes a first construction module 210 , a second construction module 220 and a solution module 230 .

[0028] The first construction module 210 is configured to construct a construction period sub-model, a total construction cost target sub-model, a quality sub-model, and a safety sub-model; The second construction module 220 is configured to construct a multi-objective collaborative optimization model for shield construction management according to the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model under preset constraints. The expression of the multi-objective collaborative optimization model is: , In the formula, The total construction period of the shield construction of the subway section project is is the total cost of shield construction for the subway section project, To improve the quality of shield construction in subway section projects. The safety level of shield construction in subway section projects. For process The actual duration of For process The direct costs corresponding to the normal duration of For key lines, For process The direct cost coefficient, For process The normal duration of is the indirect cost coefficient, is a natural constant, For process The quality level corresponding to the shortest duration of For process The minimum duration of For process The safety impact margin coefficient, For process Cost of normal duration, For process The safety level during normal duration, For process Cost of minimum duration, is the number of processes, , They are all integral operation symbols. For rewards received one day earlier or later, Plan the total completion period for shield construction of subway section projects; The solving module 230 is configured to solve the multi-objective collaborative optimization model according to a preset E-NSWOA algorithm to obtain a multi-objective collaborative optimization result.

[0029] It should be understood that Figure 2 Modules and references documented in Figure 1 Therefore, the operations and features described above for the method and the corresponding technical effects are also applicable to Figure 2 The modules in it will not be described in detail here.

[0030] In other embodiments, the embodiments of the present invention further provide a computer-readable storage medium having a computer program stored thereon, wherein when the program instructions are executed by a processor, the processor is caused to execute the multi-objective collaborative optimization method for shield construction management in any of the above method embodiments; As an implementation mode, the computer-readable storage medium of the present invention stores computer-executable instructions, and the computer-executable instructions are configured as follows: Construct the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model; Under preset constraints, a multi-objective collaborative optimization model for shield construction management is constructed according to the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model; The multi-objective collaborative optimization model is solved according to the preset E-NSWOA algorithm to obtain the multi-objective collaborative optimization result.

[0031] The computer-readable storage medium may include a program storage area and a data storage area, wherein the program storage area may store an operating system and application programs required for at least one function; the data storage area may store data created according to the use of the multi-objective collaborative optimization system for shield construction management, etc. In addition, the computer-readable storage medium may include a high-speed random access memory, and may also include a memory, such as at least one disk storage device, a flash memory device, or other non-volatile solid-state storage device. In some embodiments, the computer-readable storage medium may optionally include a memory remotely disposed relative to the processor, and these remote memories may be connected to the multi-objective collaborative optimization system for shield construction management via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.

[0032] Figure 3 is a schematic diagram of the structure of an electronic device provided by an embodiment of the present invention, such as Figure 3 As shown, the device includes: a processor 310 and a memory 320. The electronic device may also include: an input device 330 and an output device 340. The processor 310, the memory 320, the input device 330 and the output device 340 may be connected via a bus or other means. Figure 3The example of connection via bus is taken. The memory 320 is the above-mentioned computer-readable storage medium. The processor 310 executes various functional applications and data processing of the server by running the non-volatile software programs, instructions and modules stored in the memory 320, that is, the multi-objective collaborative optimization method of shield construction management in the above-mentioned method embodiment is realized. The input device 330 can receive input digital or character information, and generate key signal input related to user settings and function control of the multi-objective collaborative optimization system of shield construction management. The output device 340 may include display devices such as display screens.

[0033] The electronic device can execute the method provided by the embodiment of the present invention, and has the functional modules and beneficial effects corresponding to the execution method. For technical details not described in detail in this embodiment, please refer to the method provided by the embodiment of the present invention.

[0034] As an implementation mode, the electronic device is applied to a multi-objective collaborative optimization system for shield construction management, and is used for a client, and includes: at least one processor; and a memory connected to the at least one processor in communication; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor can: Construct the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model; Under preset constraints, a multi-objective collaborative optimization model for shield construction management is constructed according to the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model; The multi-objective collaborative optimization model is solved according to the preset E-NSWOA algorithm to obtain the multi-objective collaborative optimization result.

[0035] Through the description of the above implementation methods, those skilled in the art can clearly understand that each implementation method can be implemented by means of software plus a necessary general hardware platform, and of course, can also be implemented by hardware. Based on this understanding, the above technical solution is essentially or the part that contributes to the prior art can be embodied in the form of a software product, and the computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, a disk, an optical disk, etc., including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods of each embodiment or some parts of the embodiment.

[0036] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A multi-objective collaborative optimization method for shield construction management, characterized in that: include: Construct the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model; Under preset constraints, a multi-objective collaborative optimization model for shield construction management is constructed according to the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model. The expression of the multi-objective collaborative optimization model is: , In the formula, The total construction period of the shield construction of the subway section project is is the total cost of shield construction for the subway section project, To improve the quality of shield construction in subway section projects. The safety level of shield construction in subway section projects. For process The actual duration of For process The direct costs corresponding to the normal duration of For key lines, For process The direct cost coefficient, For process The normal duration of is the indirect cost coefficient, is a natural constant, For process The quality level corresponding to the shortest duration of For process The minimum duration of For process The safety impact margin coefficient, For process Cost of normal duration, For process The safety level during normal duration, For process Cost of minimum duration, is the number of processes, , They are all integral operation symbols. For rewards received one day earlier or later, Plan the total completion period for shield construction of subway section projects; The multi-objective collaborative optimization model is solved according to the preset E-NSWOA algorithm to obtain the multi-objective collaborative optimization result.

2. A multi-objective collaborative optimization method for shield construction management according to claim 1, characterized in that: The constraint condition is expressed as: , In the formula, is the direct cost corresponding to the shortest duration of process i, The total construction period should meet the required construction period.

3. The multi-objective collaborative optimization method for shield construction management according to claim 1 is characterized in that: The multi-objective collaborative optimization model is solved according to the preset E-NSWOA algorithm to obtain the multi-objective collaborative optimization result, which includes: Parameter initialization, including setting population size, dimension and maximum number of iterations; Population initialization: use 2D-CSCM method to randomly generate the initialization population; Fast non-dominated sorting and crowding sorting, sorting the initial population matrix by non-dominated rank and crowding distance, and returning a final population matrix; Calculate the fitness value of each individual in the population and record the optimal individual and position; An improved search strategy is used to randomly generate P values, and the corresponding search strategy is selected to update the individual whale positions based on whether the P value is less than the preset threshold. Adjust differential mutation and parasitic search to improve the search mechanism, and increase the number of iterations by 1; Repeat the iteration until the maximum number of iterations is reached and the loop ends.

4. A multi-objective collaborative optimization method for shield construction management according to claim 3, characterized in that: in, The expression for randomly generating the initialization population using the 2D-CSCM method is: , In the formula, is the horizontal coordinate of the v+1th observation value, , To control the parameters, is the horizontal coordinate of the vth observation value, is the ordinate of the vth observation, is the shift parameter in the horizontal direction, is the ordinate of the v+1th observation, is the displacement parameter in the vertical direction.

5. The multi-objective collaborative optimization method for shield construction management according to claim 3 is characterized in that: in, The expression of the improved search strategy is: , In the formula, is the chaos regulation coefficient, is the number of iterations, is the current iteration number, is the coefficient vector, For prey and whales The distance between To determine the constant parameters of the logarithmic spiral shape, is a random number in the range [-1, 1], is the maximum number of iterations, is a random number between 0 and 1, for the whale's location, For whales The position of the w+1th iteration, For whales No. The position of the iteration.

6. A multi-objective collaborative optimization method for shield construction management according to claim 3, characterized in that: The adjustment of differential mutation and parasitic search to improve the search mechanism includes: Adding the adjustment coefficient to the differential variation, the calculation formula is: , In the formula, For mutation carriers, is the best individual in the population, , , are three different individuals randomly selected from the population, Indicates the first Individuals, Represents the individual Dimensional variables; Among them, the adjustment coefficient expression of differential variation is: , In the formula, is a random number in the range of [-1, 1]; A parasitic vector containing a mutation bit adjustment factor is introduced, and some dimensions are randomly selected for mutation. The parasitic process of mutation bit factor adjustment is expressed as: , , In the formula, For mutation carriers, For organisms, is the mutation site, is the mutation adjustment factor, , are the upper and lower bounds respectively, is a random function, is the length of the mutation site; The expression of the mutation adjustment factor is: , In the formula, is a random number between 0 and 1. is the disturbance value of the mutation position.

7. A multi-objective collaborative optimization system for shield construction management, characterized in that: include: A first construction module is configured to construct a construction period sub-model, a total construction cost target sub-model, a quality sub-model, and a safety sub-model; The second construction module is configured to construct a multi-objective collaborative optimization model for shield construction management according to the construction period sub-model, the total construction cost target sub-model, the quality sub-model and the safety sub-model under preset constraints. The expression of the multi-objective collaborative optimization model is: , In the formula, The total construction period of the shield construction of the subway section project is is the total cost of shield construction for the subway section project, To improve the quality of shield construction in subway section projects. The safety level of shield construction in subway section projects. For process The actual duration of For process The direct costs corresponding to the normal duration of For key lines, For process The direct cost coefficient, For process The normal duration of is the indirect cost coefficient, is a natural constant, For process The quality level corresponding to the shortest duration of For process The minimum duration of For process The safety impact margin coefficient, For process Cost of normal duration, For process The safety level during normal duration, For process Cost of minimum duration, is the number of processes, , They are all integral operation symbols. For rewards received one day earlier or later, Plan the total completion period for shield construction of subway section projects; The solution module is configured to solve the multi-objective collaborative optimization model according to a preset E-NSWOA algorithm to obtain a multi-objective collaborative optimization result.

8. An electronic device, characterized in that: include: At least one processor, and a memory communicatively connected to the at least one processor, wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor to enable the at least one processor to perform the method described in any one of claims 1 to 6.

9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the method according to any one of claims 1 to 6 is implemented.

Citation Information

Patent Citations

  • RF-PSO-based slurry balance type shield tunneling parameter optimization method

    CN113935546A

  • Hybrid energy storage system optimization configuration solving method based on multi-strategy improved whale optimization algorithm

    CN116632869A

  • Shield construction parameter multi-objective optimization method based on machine learning and improved genetic algorithm

    CN116702271A

  • Railway construction management multi-objective balance optimization method and system

    CN118134438A

  • System and method for location-based construction scheduling

    WO2024022566A1

Cited By

  • Soft foundation in-situ solidification construction optimization method and system based on Beidou 3D positioning

    CN122022374A

  • Earth pressure risk early warning decision-making method for subway shield construction

    CN122335016A

  • A soil pressure risk early warning decision method for subway shield construction

    CN122335016B