Concrete mixing station intelligent scheduling system and working method thereof

Through the inter-station collaborative dispatching and intra-station intelligent scheduling subsystem of the concrete mixing station intelligent dispatching system, the problems of insufficient concrete supply and chaotic data management in the existing technology are solved, and the efficient operation of concrete is realized and the needs of the construction site are met, improving improve production and operational efficiency.

CN118798577AInactive Publication Date: 2024-10-18SHANDONG BOSURE AUTOMATION TECH CO LTD

Patent Information

Application Number
CN202411259097.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing technologies have limitations in optimizing concrete transportation and cannot effectively meet the demand for concrete supply volume and speed at the construction site. This results in chaotic data management and opaque supply chains, making it difficult to cope with dynamically changing construction needs.

Method used

An intelligent dispatching system for concrete mixing stations is designed, including an inter-station collaborative dispatching subsystem and an intra-station intelligent scheduling subsystem. By generating a concrete supply allocation plan and a transportation vehicle allocation plan, the rational allocation of resources between multiple mixing stations is achieved. and unified management.

Benefits of technology

It realizes the efficient operation of concrete, meets the needs of the construction site, improves production efficiency and operational efficiency, reduces operating costs, and makes the supply chain transparent, making it easier for managers to understand the construction progress in real time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118798577A_ABST
    Figure CN118798577A_ABST
Patent Text Reader

Abstract

The invention provides a concrete mixing station intelligent scheduling system and a working method thereof, and relates to the technical field of building construction and resource scheduling. The system comprises an interaction platform, an inter-station cooperative scheduling subsystem and an in-station intelligent production scheduling subsystem, wherein the inter-station cooperative scheduling subsystem comprises an inter-station task scheduling module and an inter-station vehicle scheduling module; the inter-station cooperative scheduling subsystem is used for realizing concrete supply based on a plurality of mixing stations, the in-station intelligent production scheduling subsystem is used for realizing production management in each mixing station, and the inter-station task scheduling module is used for generating a concrete supply allocation scheme based on a plurality of mixing stations. And the inter-station vehicle dispatching module is used for generating a transport vehicle dispatching scheme. According to the invention, reasonable allocation of concrete resources among a plurality of mixing stations is realized, so that the problem that the existing technical means has relatively large limitation in the aspect of realizing high-efficiency operation of concrete is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction and resource scheduling, and in particular to an intelligent scheduling system for a concrete mixing station and a working method thereof. Background Art

[0002] Concrete is a basic material widely used in construction. With the continuous improvement of the requirements for engineering efficiency in the industry, the efficient operation of concrete has become more and more important. Based on this, some auxiliary systems or methods have gradually emerged in the prior art, and most of these systems or methods are optimized for the link of concrete transportation. For example, the Chinese patent with publication number CN115439042A provides a monitoring and management system for concrete transportation and on-site construction. The system provides the most suitable and most compliant concrete transportation route for construction transportation requirements by reasonably matching the concrete transportation process with the on-site construction information, and by weighted graph calculation. However, this approach, which only focuses on the transportation link, has great limitations in effect in practical applications. Specifically: At present, most construction sites, especially large-scale projects, cannot meet the needs of continuous pouring due to the limited production capacity of a single mixing station, which may even cause construction interruption. Therefore, the construction party usually sets up multiple mixing stations on site or calls concrete across regions. In this case, whether concrete can be operated efficiently is not only related to the transportation link, but also directly affected by the concrete mixing plan; and the existing method of only optimizing the transportation link cannot act on the mixing plan, and there will be a situation where the mixing stations are relatively fragmented. Due to the large amount of production data, it will lead to a large workload of data collection and maintenance, and chaotic data management, which is not conducive to the generation and maintenance of mixing plans. In addition, in the absence of a unified scheduling system, each link in the concrete supply chain is not transparent, so it is difficult for managers at all levels to grasp the progress of construction in real time, and it is difficult to cope with dynamically changing construction needs.

[0003] Therefore, the present invention provides a concrete mixing station intelligent scheduling system and a working method thereof. Summary of the invention

[0004] The purpose of the present invention is to provide an intelligent scheduling system for a concrete mixing station and a working method thereof, so as to solve the problem mentioned in the above background technology that the existing technical means have great limitations in achieving efficient operation of concrete.

[0005] The present invention is achieved by adopting the following technical solutions: A concrete mixing station intelligent scheduling system comprises an interactive platform, an inter-station collaborative scheduling subsystem and an intra-station intelligent production scheduling subsystem, wherein the inter-station collaborative scheduling subsystem comprises an inter-station task scheduling module and an inter-station vehicle scheduling module; the inter-station collaborative scheduling subsystem is used to realize concrete supply based on multiple mixing stations, and the intra-station intelligent production scheduling subsystem is used to realize production management in each mixing station, wherein the inter-station task scheduling module is used to generate a concrete supply deployment plan based on multiple mixing stations, and the inter-station vehicle scheduling module is used to generate a transport vehicle deployment plan.

[0006] The intelligent scheduling system for concrete mixing stations provided by the present invention can realize efficient operation of concrete. Specifically: an inter-station collaborative scheduling subsystem is set up, in which an inter-station task scheduling module is set up to generate a concrete supply and deployment plan, and an inter-station vehicle scheduling module is set up to generate a transport vehicle deployment plan, thereby realizing a concrete supply effect based on multiple mixing stations, and then being able to meet the construction site's requirements for concrete supply volume and supply speed; and, an in-station intelligent production scheduling subsystem is set up to perform production management, which can verify in advance whether the mixing stations arranged in the concrete supply and deployment plan can achieve the corresponding supply tasks, thereby helping to ensure the smooth completion of the supply tasks.

[0007] Furthermore, it also includes a vehicle transportation monitoring subsystem, which is used to monitor the transportation process of concrete by the transportation vehicle.

[0008] Furthermore, the inter-station task scheduling module includes a data communication service unit, a data collection service unit, a task allocation service unit and an intelligent station selection service unit; the data communication service unit includes a data upload interface and a data download interface, the data collection service unit includes a data collection interface, and the task allocation service unit includes an allocation application interface, an allocation distribution interface and a collaborative ticketing interface.

[0009] Furthermore, the inter-station vehicle dispatching module includes an equipment communication service unit, a dispatching vehicle service unit and an automatic dispatching vehicle service unit; the equipment communication service unit includes a status check interface, a message sending interface, a message receiving interface and a message parsing interface, and the dispatching vehicle service unit includes a production dispatching interface, a cancellation dispatching interface, a change dispatching interface, a production upload interface and a production real-time data interface.

[0010] Furthermore, the in-site intelligent production scheduling subsystem includes a capacity assessment service unit, an automatic production scheduling service unit and an allocation management service unit; the capacity assessment service unit includes an indicator evaluation interface, and the allocation management service unit includes an allocation request interface, an allocation release interface, an allocation claim interface and an allocation assignment service interface.

[0011] A working method of an intelligent scheduling system for a concrete mixing station, using the above-mentioned intelligent scheduling system for a concrete mixing station, comprises the following steps: Step 1: Task release: Each construction site publishes its own concrete engineering tasks to the interactive platform; Step 2: Generate a deployment plan: Based on the concrete engineering tasks received by the interactive platform, the inter-station task scheduling module generates a concrete supply and deployment plan based on the comprehensive information of each mixing station, and the inter-station vehicle scheduling module generates a transportation vehicle deployment plan based on transportation-related factors; Step 3: Conduct an assessment: Each mixing station receives the concrete supply and deployment plan and conducts capacity assessment through the intelligent production scheduling subsystem within the station; Step 4: Coordinate processing: If the result of the capacity assessment is that the requirements of the concrete supply and allocation plan cannot be met, it will be fed back to the inter-station task scheduling module for adjustment; if the result of the capacity assessment is that the requirements of the concrete supply and allocation plan can be met, specific production tasks will be arranged according to the situation within the station; if the result of the capacity assessment is that there is idle capacity, you can choose to initiate a production task request to the inter-station task scheduling module or undertake the assigned production tasks.

[0012] Furthermore, in step three, each mixing station will also evaluate whether the vehicles in the station meet the usage requirements. If the evaluation result is not satisfied, it will be fed back to the inter-station vehicle scheduling module.

[0013] set up yes The maximum production capacity of the mixing plants is combined. yes The production task volume of each mixing station has been scheduled. Yes Pre-allocate concrete volume collection for each mixing station; With constraint 1: Each mixing station can complete its own production tasks, that is, , ; Constraint 2: Each mixing station coordinates to complete the supply of concrete engineering tasks, that is, complete ; Based on constraints 1 and 2, the concrete supply and deployment scheme with the least impact on each mixing station is solved, that is, .

[0014] Furthermore, when the inter-station vehicle scheduling module generates a transport vehicle deployment plan, the following vehicle scheduling algorithm is used: set up yes The collection of concrete volumes required for a concrete engineering task, yes The vehicle transport capacity set of vehicles; express The road condition coefficient set of the construction site, express The distance set between the task location and the departure location, It indicates the transportation time; Represents the starting time point set of concrete required at different construction sites, Represents the set of time points at which concrete mixing is completed at different construction sites; Constraint 1: Give priority to fully loaded vehicles for transportation, ensuring that the transportation capacity of the remaining dispatchable vehicles is greater than the required concrete volume of the remaining concrete engineering tasks, that is, let the transportation capacity of the remaining dispatchable vehicles be , ; Assume that the required concrete volume of the remaining concrete engineering task is , ; then there is ; Based on constraint 1, the difference between the material usage time and the delivery time of each construction site is minimized, that is, .

[0015] Furthermore, when the in-station intelligent production scheduling subsystem performs capacity evaluation, it first uses the intelligent production scheduling algorithm to generate a capacity analysis report, and then evaluates the completion of the concrete supply and deployment plan based on the capacity analysis report. The intelligent production scheduling algorithm is as follows: set up is a collection of pending task orders of a mixing station. is a collection of raw material stocks; It is the daily production capacity of all production lines in a mixing plant; calculate The value of The capacity analysis report is generated based on the two values.

[0016] The beneficial effects achieved by the present invention are: Provided is an intelligent scheduling system for a concrete mixing station and a working method thereof, wherein the system includes an inter-station collaborative scheduling subsystem and an intra-station intelligent production scheduling subsystem, and working steps based on the two subsystems are set, thereby realizing the reasonable allocation of concrete resources between multiple mixing stations and forming a unified management of the entire intelligent process. Compared with the prior art, the present invention can meet the concrete demand of the construction site to the maximum extent by reasonably allocating multiple mixing stations, and realizes the rapid transportation of concrete through comprehensive scheduling of vehicles, thereby forming an efficient operation of concrete, which can effectively improve production efficiency and reduce operating costs; at the same time, based on unified management, each link in the concrete supply chain is relatively transparent, so managers at all levels can grasp the construction progress in real time, which helps to improve operational efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a flowchart of the working method of the intelligent scheduling system of the concrete mixing station described in the embodiment of the present invention. DETAILED DESCRIPTION

[0018] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0019] Example 1 In a first aspect, the present embodiment provides an intelligent scheduling system for a concrete mixing station, including an interactive platform, an inter-station collaborative scheduling subsystem, an intra-station intelligent production scheduling subsystem, and a vehicle transportation monitoring subsystem. The specific contents of each subsystem are as follows: 1. Inter-station collaborative dispatching subsystem The inter-station collaborative scheduling subsystem is used to realize the concrete supply based on multiple mixing stations. It includes an inter-station task scheduling module and an inter-station vehicle scheduling module. Specifically: 1) Inter-station task scheduling module The inter-station task scheduling module is used to generate a concrete supply and deployment plan based on multiple mixing stations. It includes a data communication service unit, a data collection service unit, a task allocation service unit and an intelligent station selection service unit; the data communication service unit includes a data upload interface and a data delivery interface, the data collection service unit includes a data collection interface, and the task allocation service unit includes an allocation application interface, an allocation distribution interface and a collaborative ticketing interface.

[0020] Based on the above structural settings and in accordance with the operating concept of the microservice architecture, the inter-station task scheduling module can implement the following microservices: a) Data communication service: Provide data communication services between each mixing station and the interactive platform through the data upload interface and data download interface in the data communication service unit.

[0021] b) Data collection service: Through the data collection interface in the data collection service unit, information such as the production plan and resource usage of each mixing station is collected to provide support for subsequent intelligent station selection services.

[0022] c) Task allocation service: Through the allocation application interface, allocation distribution interface and collaborative ticketing interface in the task allocation service unit, the data transmission of relevant information between the mixing station and the interactive platform is realized.

[0023] d) Intelligent station selection service: Receive allocation applications through the allocation application interface, obtain information such as the production plan and resource usage of each mixing station through the data collection interface, select the appropriate mixing station, and then send the concrete supply and deployment plan to the mixing station that needs to coordinate supply through the allocation distribution interface.

[0024] When the inter-station task scheduling module is working, it is carried out in the following aspects: a) Collect the production plan, capacity and other factors of each mixing station in real time, and automatically select a mixing station to supply alone or multiple mixing stations to supply together, i.e., concrete supply and allocation plan, based on the parameters such as the type of concrete to be allocated, the amount of concrete, the transportation distance, and the transportation time, and issue it.

[0025] b) Relevant managers can monitor the implementation progress of the concrete supply and allocation plan in real time.

[0026] c) Unified processing of ticketing requests from each mixing station in the concrete supply and allocation plan to ensure the continuity of ticket numbers, cumulative vehicle trips, cumulative volume, etc.

[0027] d) When the production task allocated to a mixing station in the concrete supply and allocation plan exceeds its own production capacity, the production task can be re-published to the inter-station task scheduling module.

[0028] In summary, this inter-station task scheduling module can achieve the following target effects: a) Solve the problem of insufficient supply: Currently, most construction sites have a high demand for concrete. Some large-scale projects also require continuous concrete pouring. The concrete supply of a single mixing station is usually unable to meet the above demand. Through the inter-station task scheduling module, the concrete resources of mixing stations in other areas can be flexibly allocated to construction sites with tight demand, so as to meet the construction site's demand for large quantities of continuous supply of concrete.

[0029] b) Achieve efficient operation: By rationally allocating the resources of mixing plants in different regions, resources can be utilized more fully and reasonably, which in turn helps to improve operational efficiency and reduce operating costs.

[0030] 2) Inter-station vehicle dispatching module The inter-station vehicle dispatching module is used to generate transport vehicle allocation plans, which include equipment communication service units, dispatching vehicle dispatching service units and automatic vehicle dispatching service units; the equipment communication service unit includes a status check interface, a message sending interface, a message receiving interface and a message parsing interface, and the dispatching vehicle dispatching service unit includes a production vehicle dispatching interface, a cancellation vehicle dispatching interface, a change vehicle dispatching interface, a production upload interface and a production real-time data interface.

[0031] Based on the above structural settings and in accordance with the operating concept of the microservice architecture, the inter-station vehicle dispatching module can implement the following microservices: a) Equipment communication service: Through the status check interface, message sending interface, message receiving interface and message parsing interface in the equipment communication service unit, it provides underlying communication service support for dispatching vehicles.

[0032] b) Dispatching and dispatching service: Through the production dispatching interface, cancellation dispatching interface, change dispatching interface, production upload interface and production real-time data interface in the dispatching and dispatching service unit, various dispatching methods and automatic collection of production data are realized.

[0033] c) Automatic vehicle dispatch service: Call the dispatch vehicle dispatch service to realize the automatic vehicle dispatch function.

[0034] When the inter-station vehicle dispatching module is working, it is carried out in the following aspects: a) Realize multiple dispatching modes such as dispatching empty vehicles, dispatching vehicles with added materials, dispatching vehicles with adjusted materials, dispatching vehicles with changed materials, and canceling dispatching vehicles; and realize automatic collection of production data, and do not allow manual modification to ensure the authenticity and reliability of the data.

[0035] b) Support the automatic queuing and unqueuing of vehicles in various ways (such as GPS, RFID, IC); support various methods of handling leftover materials, such as direct forwarding of leftover materials outside the station, direct forwarding of leftover materials returned to the yard, forwarding of leftover materials returned to the yard with additional materials, and discarding of leftover materials returned to the yard.

[0036] c) Send various warning reminder information to relevant management personnel in a timely manner. Warning information includes production overtime, out-of-tolerance, on-site vehicle pressure, and return to the factory overtime, etc. Reminder information includes on-site material requests and material urging, etc.

[0037] In summary, this inter-station vehicle scheduling module can perform intelligent scheduling of vehicles based on conditions such as task lists, transportation volume, transportation distance and production capacity, generate the optimal scheduling plan, and perfectly combine the specific transportation process with the dynamic information of the transportation operation to provide users with a variety of services.

[0038] 2. Intelligent production scheduling subsystem within the station The in-station intelligent scheduling subsystem is used to realize production management in each mixing station, which includes a capacity assessment service unit, an automatic scheduling service unit and an allocation management service unit; the capacity assessment service unit includes an indicator evaluation interface, and the allocation management service unit includes an allocation request interface, an allocation release interface, an allocation claim interface and an allocation assignment service interface.

[0039] Based on the above structural settings and in accordance with the operating concept of the microservice architecture, the in-station intelligent production scheduling subsystem can implement the following microservices: a) Capacity assessment service: Through the indicator assessment interface in the capacity assessment service unit, various indicators related to the mixing plant capacity are evaluated to provide support for automatic production scheduling services.

[0040] b) Automatic production scheduling service: automatically create production tasks and call the capacity assessment service to generate a capacity analysis report.

[0041] c) Transfer management service: Provide service support for the transfer management of production tasks through the transfer request interface, transfer release interface, transfer claim interface and transfer assignment service interface in the transfer management service unit.

[0042] The intelligent production scheduling subsystem in this station is working in the following aspects: a) Production scheduling management: Automatically create the production tasks for the next day based on the approved sales orders; and generate the capacity assessment report for the mixing station for the next day based on the mixing station's capacity and the number of production tasks.

[0043] b) Early warning reminder: If the production task of the next day exceeds the assessed production capacity of the mixing plant, an early warning message will be automatically sent to relevant management personnel.

[0044] c) Release of transfer tasks: ① During the production process of the mixing station, if there is a shortage of production capacity due to temporary increase in production volume, the mixing station can feedback the production task to the interactive platform; relevant management personnel can publish all or part of the production task on the interactive platform, and can set the mixing station recommended to undertake the production task when publishing the production task; ② Relevant management personnel can view the production tasks released by each mixing station and review them. After the review is passed, each mixing station can see the production tasks released by other mixing stations on the interactive platform.

[0045] d) Task allocation and claim: Each mixing station can view the approved production tasks to be allocated. If the mixing station evaluates its capacity and finds that the current number of production tasks in the station is insufficient to match the capacity of the station, it can apply to undertake the allocated production tasks. After the relevant management personnel review and approve the application, the production task will be issued to the mixing station.

[0046] e) Assignment of transfer tasks: ① The intelligent production scheduling subsystem in the station can automatically recommend production tasks to be assigned to the mixing station with insufficient production capacity based on the production capacity of each mixing station, the number of released tasks, the location of the construction site and other factors; after review by relevant management personnel, the production tasks can be directly issued to the mixing station; ② Relevant management personnel can grasp the production capacity of each mixing station and the issued tasks in real time, and can directly designate a mixing station to undertake the assigned production tasks. The designated mixing station will automatically receive the production tasks.

[0047] In summary, the intelligent production scheduling subsystem in this site can achieve the following target effects: a) It can quickly and accurately schedule production according to the requirements of various tasks to ensure the smooth implementation of the production plan; and it can flexibly adjust and optimize the production schedule according to changing factors such as construction requirements; thereby improving production efficiency and resource utilization and reducing production costs.

[0048] b) It can provide accurate production data and decision-making support to managers at all levels, so as to better control the production process and adjust the production strategy; and it can achieve traceability of the production process to ensure the control and safety management of concrete quality.

[0049] 3. Vehicle transportation monitoring subsystem The vehicle transport monitoring subsystem is used to monitor the transport process of concrete by transport vehicles, and includes a data acquisition service unit and a data analysis service unit; the data acquisition service unit includes a sensor module and a positioning module, and the data analysis service unit includes a server.

[0050] Based on the above structural settings, the vehicle transportation monitoring subsystem can provide the following services: a) Data collection service: Through the sensor module and positioning module in the data collection service unit, the vehicle terminal collects the vehicle's location, fuel level and other data in real time, and transmits the data to the server using the wireless communication module.

[0051] b) Data analysis service: Through the server in the data analysis service unit, the data uploaded by the vehicle terminal is managed, the data is saved, analyzed, and alarmed, and various monitoring functions are provided to display the status, driving trajectory, timeout records and other information of each vehicle in real time.

[0052] When the vehicle transport monitoring subsystem is working, it is carried out in the following aspects: a) Mark the vehicle on the map and monitor the vehicle coordinates and status in real time.

[0053] b) Check the transportation status of the vehicle according to the task and replay the vehicle's driving trajectory in different time periods.

[0054] c) Alarm for abnormal vehicle conditions such as speeding, timeout, abnormal shutdown, abnormal unloading, etc.

[0055] In summary, this vehicle transportation monitoring subsystem can achieve the following target effects: a) During the transportation of concrete, vehicles may encounter problems such as breakdowns and traffic accidents, which may result in the concrete not being delivered to the construction site or not being delivered in time, thus causing negative consequences on the construction; however, through the vehicle transportation monitoring subsystem, the vehicle's speed, fuel volume, driving trajectory, driving area and other information can be monitored and managed in real time, and the alarm function can be used to promptly remind relevant management personnel so that they can quickly respond to unexpected situations.

[0056] b) Relevant management personnel can check the position relationship between vehicles and construction sites at any time, which makes it easier to schedule vehicles to return to the site in advance, thus helping to improve production efficiency.

[0057] The second aspect of this embodiment provides a working method of the intelligent scheduling system of a concrete mixing station. The above-mentioned intelligent scheduling system of a concrete mixing station is applied. Please refer to Figure 1 , including the following steps: Step 1: Task release: Each construction site publishes its own concrete engineering tasks to the interactive platform, which include information such as the model and volume of concrete.

[0058] Step 2: Generate a deployment plan: Based on the concrete engineering tasks received by the interactive platform, the inter-station task scheduling module generates a concrete supply allocation plan based on the comprehensive information of each mixing station, and the inter-station vehicle scheduling module generates a transportation vehicle allocation plan based on transportation-related factors. Among them, the comprehensive information of each mixing station includes the existing production plan, remaining capacity, distance from the construction site, road conditions, etc., and transportation-related factors include the concrete demand model, volume, time requirements, distance, road conditions, etc. of each construction site.

[0059] In this step: The goal of inter-station task scheduling is to meet the concrete demand of each construction site. The supply of concrete needs to be coordinated with the construction progress of the construction site. When the inter-station task scheduling module generates a concrete supply allocation plan, it uses the following task scheduling algorithm: set up yes The maximum production capacity of the mixing plants is combined. yes The production task volume of each mixing station has been scheduled. Yes Pre-allocate concrete volume collection for each mixing station; With constraint 1: Each mixing station can complete its own production tasks, that is, , ; Constraint 2: Each mixing station coordinates to complete the supply of concrete engineering tasks, that is, complete ; Based on constraints 1 and 2, the concrete supply and deployment scheme with the least impact on each mixing station is solved, that is, .

[0060] When multiple construction sites initiate concrete demands at different times and there are vehicles of various specifications (different rated load volumes), the vehicle dispatching principle is to use fully loaded vehicles for transportation as much as possible. When there are multiple volume demands, fully loaded vehicles should be used as much as possible. This can ensure high transportation efficiency and low transportation costs. When the inter-station vehicle dispatching module generates a transportation vehicle dispatching plan, it uses the following vehicle dispatching algorithm: set up yes The collection of concrete volumes required for a concrete engineering task, yes The vehicle transport capacity set of vehicles; express The road condition coefficient set of the construction site, express The distance set between the task location and the departure location, It indicates the transportation time; Represents the starting time point set of concrete required at different construction sites, Represents the set of time points at which concrete mixing is completed at different construction sites; Constraint 1: Give priority to fully loaded vehicles for transportation, ensuring that the transportation capacity of the remaining dispatchable vehicles is greater than the required concrete volume of the remaining concrete engineering tasks, that is, let the transportation capacity of the remaining dispatchable vehicles be , ; Assume that the required concrete volume of the remaining concrete engineering task is , ; then there is ; Based on constraint 1, the difference between the material usage time and the delivery time of each construction site is minimized, that is, .

[0061] Step 3: Conduct an assessment: Each mixing station receives the concrete supply and allocation plan and conducts capacity assessment through the station intelligent scheduling subsystem. In this step, the goal of the station intelligent scheduling is to improve the capacity utilization rate of the mixing station; when conducting capacity assessment, first use the intelligent scheduling algorithm to generate a capacity analysis report based on sales plans, raw material reserves, equipment capacity and other information, and then evaluate the completion of the concrete supply and allocation plan based on the capacity analysis report. The intelligent scheduling algorithm is as follows: set up is a collection of pending task orders of a mixing station. is a collection of raw material stocks; It is the daily production capacity of all production lines in a mixing plant; calculate The value of The capacity analysis report is generated based on the two values.

[0062] Step 4: Coordinate processing: If the result of the capacity assessment is that the requirements of the concrete supply and allocation plan cannot be met, it will be fed back to the inter-station task scheduling module for adjustment; if the result of the capacity assessment is that the requirements of the concrete supply and allocation plan can be met, specific production tasks will be arranged according to the situation within the station; if the result of the capacity assessment is that there is idle capacity, you can choose to initiate a production task request to the inter-station task scheduling module or undertake the assigned production tasks.

[0063] In addition, in step three, each mixing station will also evaluate whether the vehicles in the station meet the usage requirements; based on this, in step four, if the evaluation result is not met, it will be fed back to the inter-station vehicle scheduling module, so that the inter-station vehicle scheduling module will dispatch additional vehicles from nearby stations.

[0064] In summary, the intelligent scheduling system and working method provided by this embodiment have the following advantages: a) Supply guarantee: Through coordinated scheduling among stations, rational allocation of concrete resources can be achieved, which can solve the problem of insufficient supply and ensure the continuity of construction.

[0065] b) Operation optimization: It can optimize the utilization of mixing station resources, reduce operating costs and improve production efficiency.

[0066] c) Reduced transportation costs: Rationally allocate mixing station resources to reduce transportation distance and transportation costs.

[0067] d) Real-time monitoring: Real-time monitoring of the concrete delivery process, timely handling of abnormal situations, and ensuring that the concrete is delivered to the construction site on time and safely.

[0068] e) Intelligent management: Through data communication, data collection and intelligent station selection services, the whole process of concrete production, transportation and delivery can be managed intelligently to improve overall operational efficiency.

[0069] It should be noted that the parts not described in detail or expanded in the above scheme are all existing technologies, which do not belong to the improvements made by the present invention on the existing technologies, nor do they belong to the protection scope of the technical scheme of the present invention. Therefore, they will not be described in detail in this article.

[0070] Of course, the above contents are only preferred embodiments of the present invention and cannot be considered to limit the scope of the embodiments of the present invention. The present invention is not limited to the above examples, and equal changes and improvements made by ordinary technicians in the technical field within the essential scope of the present invention should all fall within the scope of the patent coverage of the present invention.

Claims

1. An intelligent dispatching system for a concrete mixing station, characterized in that: It includes an interactive platform, an inter-station collaborative scheduling subsystem and an intra-station intelligent production scheduling subsystem, wherein the inter-station collaborative scheduling subsystem includes an inter-station task scheduling module and an inter-station vehicle scheduling module; The inter-station collaborative scheduling subsystem is used to realize the concrete supply based on multiple mixing stations, the in-station intelligent production scheduling subsystem is used to realize the production management in each mixing station, wherein the inter-station task scheduling module is used to generate a concrete supply deployment plan based on multiple mixing stations, and the inter-station vehicle scheduling module is used to generate a transport vehicle deployment plan.

2. The intelligent dispatching system for a concrete mixing station according to claim 1 is characterized in that: It also includes a vehicle transportation monitoring subsystem, which is used to monitor the transportation process of concrete by the transportation vehicle.

3. The intelligent dispatching system for a concrete mixing station according to claim 1 is characterized in that: The inter-station task scheduling module includes a data communication service unit, a data collection service unit, a task allocation service unit and an intelligent station selection service unit; the data communication service unit includes a data upload interface and a data download interface, the data collection service unit includes a data collection interface, and the task allocation service unit includes an allocation application interface, an allocation distribution interface and a collaborative ticketing interface.

4. The intelligent dispatching system for a concrete mixing station according to claim 1 is characterized in that: The inter-station vehicle dispatching module includes an equipment communication service unit, a dispatching vehicle service unit and an automatic dispatching vehicle service unit; the equipment communication service unit includes a status check interface, a message sending interface, a message receiving interface and a message parsing interface, and the dispatching vehicle service unit includes a production dispatching interface, a cancellation dispatching interface, a change dispatching interface, a production upload interface and a production real-time data interface.

5. The intelligent dispatching system for a concrete mixing station according to claim 1 is characterized in that: The in-station intelligent production scheduling subsystem includes a capacity assessment service unit, an automatic production scheduling service unit and an allocation management service unit; the capacity assessment service unit includes an indicator assessment interface, and the allocation management service unit includes an allocation request interface, an allocation release interface, an allocation claim interface and an allocation assignment service interface.

6. A working method of an intelligent scheduling system for a concrete mixing station, using the intelligent scheduling system for a concrete mixing station according to any one of claims 1 to 5, characterized in that: The steps include: Step 1: Task release: Each construction site publishes its own concrete engineering tasks to the interactive platform; Step 2: Generate a deployment plan: Based on the concrete engineering tasks received by the interactive platform, the inter-station task scheduling module generates a concrete supply and deployment plan based on the comprehensive information of each mixing station, and the inter-station vehicle scheduling module generates a transportation vehicle deployment plan based on transportation-related factors; Step 3: Conduct an assessment: Each mixing station receives the concrete supply and deployment plan and conducts capacity assessment through the intelligent production scheduling subsystem within the station; Step 4: Coordinate processing: If the result of the capacity assessment is that the requirements of the concrete supply and allocation plan cannot be met, it will be fed back to the inter-station task scheduling module for adjustment; if the result of the capacity assessment is that the requirements of the concrete supply and allocation plan can be met, specific production tasks will be arranged according to the situation within the station; if the result of the capacity assessment is that there is idle capacity, you can choose to initiate a production task request to the inter-station task scheduling module or undertake the assigned production tasks.

7. The working method of the intelligent dispatching system of a concrete mixing station according to claim 6 is characterized by: In the step three, each mixing station will also evaluate whether the vehicles in the station meet the usage requirements. If the evaluation result is not satisfied, it will be fed back to the inter-station vehicle scheduling module.

8. The working method of the intelligent scheduling system of a concrete mixing station according to claim 6 is characterized in that: When the inter-station task scheduling module generates a concrete supply allocation plan, the following task scheduling algorithm is used: set up yes The maximum production capacity of the mixing plants is combined. yes The production task volume of each mixing station has been scheduled. Yes Pre-allocate concrete volume collection for each mixing station; Constraint 1: Each mixing station can complete its own production tasks, that is, , ; Constraint 2: Each mixing station coordinates to complete the supply of concrete engineering tasks, that is, complete ; Based on constraints 1 and 2, the concrete supply and deployment scheme with the least impact on each mixing station is solved, that is, .

9. The working method of the intelligent scheduling system of a concrete mixing station according to claim 6, characterized in that: When the inter-station vehicle scheduling module generates a transport vehicle deployment plan, it uses the following vehicle scheduling algorithm: set up yes The collection of concrete volumes required for a concrete engineering task, yes The vehicle transport capacity set of vehicles; express The road condition coefficient set of the construction site, express The distance set between the task location and the departure location, It indicates the transportation time; Represents the starting time point set of concrete required at different construction sites, Represents the set of time points at which concrete mixing is completed at different construction sites; Constraint 1: Prioritize fully loaded vehicles for transportation, ensuring that the transportation capacity of the remaining dispatchable vehicles is greater than the required concrete volume of the remaining concrete engineering tasks, that is, let the transportation capacity of the remaining dispatchable vehicles be , ; Assume that the required concrete volume of the remaining concrete engineering task is , ; then there is ; On the basis of constraint 1, the difference between the material usage time and the delivery time of each construction site is minimized, that is, .

10. The working method of the intelligent dispatching system of a concrete mixing station according to claim 6 is characterized by: When the intelligent production scheduling subsystem in the station performs capacity evaluation, it first uses the intelligent production scheduling algorithm to generate a capacity analysis report, and then evaluates the completion of the concrete supply and allocation plan based on the capacity analysis report. The intelligent production scheduling algorithm is as follows: set up is a collection of pending task orders of a mixing station. is a collection of raw material stocks; It is the daily production capacity of all production lines in a mixing plant; calculate The value of The capacity analysis report is generated based on the two values.

Citation Information

Patent Citations

  • Concrete order intelligent analyzing and production scheduling system and method

    CN108876168A

  • Concrete mixing plant informatization management system and method thereof

    CN112183974A

  • Centralized control system and method of concrete mixing plant

    CN112223547A

  • Intelligent transportation scheduling method and system, medium and electronic equipment

    CN112598273A

  • Method and system for concrete transport vehicle dispatching optimization calculation theoretical model

    CN112668248A

Cited By

  • Concrete production, transportation and pouring vertical management system

    CN119740837A