Real-time control method and device for voltage response of high-proportion new energy power system
By establishing a voltage response reduction model and real-time data judgment, the minimum cost startup and load cutting amount is determined, and the problem of insufficient timeliness of voltage response when high proportion of new energy is connected is solved, and the voltage safety and stability control of the power system is achieved.
Patent Information
- Application Number
- CN202411273810.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-09-12
AI Technical Summary
When the existing power system is connected to a high proportion of new energy, the timeliness and accuracy of the voltage response is insufficient, which makes it difficult to ensure the stability of the power grid voltage. Especially when the interaction characteristics of DC and new energy are complex, it is difficult to formulate effective voltages. Stable defense control measures.
A real-time control method for voltage response of high-proportion new energy power system is proposed. By establishing a voltage response reduction model of AC and DC power system, the minimum cost starting plan and load cutting amount are determined to achieve voltage safety and stable control. The method includes the aggregation model of dynamic components, DC equivalent, parallel constant impedance load of induction motors and new energy considerations, and uses real-time operation data to determine the stability of the system and implement emergency load measures.
Real-time stable control of the voltage of the high-proportion new energy AC and DC power system, rapid calculation of voltage stability, adapt to different system operating modes and fault scenarios, prevent and control voltage safety risks, and improve the voltage safety and stability of the power grid.
Smart Images

Figure CN118801399B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of power system safety and stability analysis and control, and more specifically, to a method and device for real-time control of voltage response of a high-proportion new energy power system. Background Art
[0002] The large-scale access of ultra-high voltage direct current has replaced conventional power sources, leading to the "hollowing out" of load centers, and the problem of voltage safety and stability has become increasingly prominent.
[0003] With the rapid development of distributed renewable energy, the scale of access to distributed renewable energy generation on the load side continues to increase. The fragility and weak support of renewable energy have further reduced the voltage support capacity of the receiving power grid load center, and the risk of grid voltage collapse will be further aggravated. The grid's new energy consumption and safe operation will face huge challenges.
[0004] Power electronic equipment such as DC, new energy, and loads exhibit multi-time scale voltage interaction characteristics. The causes and development processes of system voltage instability are complex and the mechanisms are unclear. It is difficult to formulate voltage stability defense control measures, and the level of new energy absorption and multi-DC power receiving is severely limited.
[0005] Therefore, in view of the current status and development trend of AC / DC hybrid power grids with a high proportion of distributed renewable energy, it is urgent to study the voltage safety and stability analysis methods and control technologies of large-scale AC / DC hybrid power grids with a high proportion of distributed renewable energy access, so as to provide technical guarantee for the receiving power grid under the development of new power systems. Summary of the invention
[0006] In view of this, the present application proposes a real-time control method, device and terminal for voltage response of a high-proportion renewable energy power system, aiming to solve the problems of insufficient timeliness and accuracy of existing power system transient stability assessment methods.
[0007] In a first aspect, the present application provides a method for real-time voltage response control of a high-proportion new energy power system, comprising:
[0008] Establish a voltage response reduced-order model for AC / DC receiving-end power systems containing a high proportion of renewable energy;
[0009] Using the established voltage response reduction model, a minimum cost startup plan is determined to enable the AC / DC receiving-end power system to access a high proportion of new energy and DC on the basis of voltage safety and stability;
[0010] When the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, a load shedding plan is determined and executed to enable the AC / DC receiving-end power system to access a high proportion of new energy and DC.
[0011] Furthermore, the establishment of a voltage response reduced-order model of an AC / DC receiving-end power system containing a high proportion of new energy sources includes:
[0012] In the AC / DC receiving-end power system containing a high proportion of new energy, the dynamic elements include generator nodes, active load nodes, DC nodes and other nodes;
[0013] Establish a generator aggregation model for all generator nodes;
[0014] For DC node equivalence, determine the DC equivalent impedance;
[0015] For active load nodes, induction motors are used in parallel with constant impedance loads and new energy sources;
[0016] The generator nodes, active load nodes, and DC nodes are retained and aggregated, and other nodes are eliminated. After simplifying the network, a voltage response reduced-order model of the AC / DC receiving-end power system with a high proportion of renewable energy is obtained.
[0017] Furthermore, the method of determining the minimum cost startup scheme by utilizing the established voltage response reduced-order model includes:
[0018] Obtain the number M of local conventional units in the AC / DC receiving-end power system containing a high proportion of new energy and the corresponding 2 M A boot combination;
[0019] For the startup combination y, determining a voltage response reduced-order model corresponding to the AC / DC receiving-end power system containing a high proportion of new energy;
[0020] Determine an equivalent electromagnetic torque curve of the induction motor by using a voltage response reduction model corresponding to the startup combination y, wherein the equivalent electromagnetic torque curve takes the rotor slip of the induction motor as an independent variable;
[0021] For the starting combination y, according to the obtained critical stable slip and equivalent mechanical torque of the induction motor rotor, using the determined load-side voltage stability criterion considering DC and new energy, it is determined whether the AC / DC receiving-end power system containing a high proportion of new energy will remain stable or lose stability when the starting combination y is started;
[0022] Among all the startup combinations determined to be stable, the startup combination with the smallest capacity is selected as the minimum cost startup plan for the AC / DC receiving-end power system containing a high proportion of new energy. The minimum cost startup plan enables the AC / DC receiving-end power system to access a high proportion of new energy and DC on the basis of safe and stable voltage.
[0023] Furthermore, it also includes:
[0024] The load-side voltage stability criterion considering DC and new energy sources is determined by using the motor equivalent electromagnetic torque curve, the critical stable slip of the induction motor rotor and the equivalent mechanical torque of the induction motor.
[0025] Furthermore, when the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, a load shedding scheme is determined, including:
[0026] Estimate the predicted power decline slope at the measurement point;
[0027] The load shedding amount corresponding to the measuring point is determined by using the determined electromagnetic power change coefficient of the induction motor after load shedding, the ratio coefficient of the electromagnetic power of the induction motor to the power of the measuring point, the new energy active power and the obtained steady-state total load of the measuring point before the fault.
[0028] Furthermore, when the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, before determining the load shedding scheme, the method further includes:
[0029] For each power supply area, the local voltage instability judgment is performed using the established local voltage instability judgment criteria to determine if local voltage instability occurs in any power supply area;
[0030] Perform DC instability detection to determine if any DC instability has occurred;
[0031] When local voltage instability occurs in any power supply area and any DC loop instability occurs, it is determined that global voltage instability occurs.
[0032] Furthermore, for each power supply area, using the established local voltage instability criterion, performing local voltage instability determination to determine whether local voltage instability occurs in any power supply area includes:
[0033] Determine whether the reactive power delivered to the grid via the AC substation meets the reactive power criterion; and
[0034] Determine whether the active power connected to the grid via the AC substation meets the active power criterion; and
[0035] Determine whether the voltage on the high voltage side of the AC substation meets the voltage criterion.
[0036] Furthermore, it also includes:
[0037] Determine that the value of the electromagnetic power variation coefficient of the induction motor after load shedding is 1;
[0038] Determine the value of the ratio coefficient between the electromagnetic power of the induction motor and the power at the measuring point to be 1;
[0039] The slope of the transformer off-grid power change is estimated by collecting the time series data of the transformer off-grid power.
[0040] Furthermore, when determining the load shedding amount corresponding to the measuring point,
[0041] When the receiving end area does not contain new energy and synchronous machine, the value of the new energy active power is determined to be zero;
[0042] When the receiving end area contains renewable energy and synchronous generators, and the power of renewable energy and synchronous generators can be measured, the value of the renewable energy active power can be directly measured;
[0043] When the receiving area contains renewable energy and synchronous machines, but the power of the renewable energy and synchronous generators cannot be measured, the operating power of the renewable energy at the time of load shedding action 0- is taken as the active power of the renewable energy.
[0044] In a second aspect, the present application provides a device for real-time voltage response control of a high-proportion new energy power system, comprising:
[0045] A reduced-order model building unit is used to establish a voltage response reduced-order model of an AC / DC receiving-end power system containing a high proportion of new energy;
[0046] A minimum startup determination unit, used to determine a minimum cost startup scheme by using the established voltage response reduction model, so that the AC / DC receiving-end power system can access a high proportion of new energy and DC on the basis of voltage safety and stability;
[0047] The load shedding determination unit is used to determine a load shedding plan when judging that the AC / DC receiving-end power system is unstable by using the established voltage instability criterion, and execute the load shedding plan so that the AC / DC receiving-end power system can access a high proportion of new energy and DC.
[0048] In a third aspect, the present application provides a terminal, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the method described in the first aspect.
[0049] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present application. Also, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:
[0051] Figure 1 A schematic diagram of a voltage response reduced-order model of an AC / DC receiving-end power system in an embodiment of the present application;
[0052] Figure 2 is an equivalent circuit of the induction motor load in the embodiment of the present application;
[0053] Figure 3 It is the △-aggregated impedance model of the AC / DC receiving-end power system in the embodiment of the present application;
[0054] Figure 4 A circuit diagram of a Y-aggregated impedance model and Thevenin equivalent of an AC / DC receiving-end power system in an embodiment of the present application;
[0055] Figure 5 It is an induction motor load equivalent model considering DC and new energy in the embodiment of the present application;
[0056] Figure 6 Schematic diagram of equivalent electromagnetic torque curve and mechanical torque in the embodiment of the present application;
[0057] Figure 7 Schematic diagram of the measurement points and power grid structure in the embodiment of the present application (the power supply area below is a partial enlarged display of the power grid above);
[0058] Figure 8 for Figure 7 A partial schematic diagram of the power grid structure;
[0059] Fig. 9 Schematic diagram of voltage instability boundary of induction motor under different load levels in the embodiment of the present application;
[0060] Fig.10 It is a schematic diagram of the voltage instability boundary or power-slip curve of the induction motor under different induction motor proportions and system strengths in the embodiment of the present application;
[0061] Fig.11 This is a schematic diagram of the voltage instability boundary of an induction motor under another different load level in an embodiment of the present application;
[0062] Fig.12 A schematic diagram of the power relationship on the load side dominated by the induction motor in the embodiment of the present application;
[0063] Fig.13 A comparison diagram of the electromagnetic power, port power and load side power curves of the induction motor in the embodiment of the present application;
[0064] Fig.14 The power transformation ratio coefficient curve under different system impedances in the embodiment of the present application;
[0065] Fig.15 The power ratio coefficient curve under different proportions of induction motors in the embodiment of the present application;
[0066] Fig.16 This is a simplified system diagram of an actual power grid in an embodiment of the present application;
[0067] Fig.17 The active, reactive and voltage curves of Shandong power grid under a stable working condition in the embodiment of the present application;
[0068] Fig.18 This is a DC power curve of Shandong power grid under an unstable condition in the embodiment of this application;
[0069] Fig.19 The active, reactive and voltage curves of the Yimeng main transformer under the power instability condition when it is disconnected from the grid in the embodiment of the present application;
[0070] Fig. 20 This is the power curve of the Taishan main transformer off-grid in the embodiment of this application;
[0071] Fig.21 This is the power curve of the Yimeng main transformer offline in the embodiment of this application;
[0072] Fig. 22 This is the active, reactive and voltage curve of Shandong power grid under another stable working condition in the embodiment of this application;
[0073] Fig.23 This is the active, reactive and voltage curves of Shandong power grid under another unstable condition in the embodiment of the present application;
[0074] Fig.24 This is the power curve of the main transformer offline in the Taishan power supply area in the embodiment of this application;
[0075] Fig.25 This is the voltage curve of the Taishan area after load shedding in the embodiment of the present application;
[0076] Fig.26 This is the active, reactive and voltage curves of Shandong power grid under another stable working condition in the embodiment of this application;
[0077] Fig. 27 This is the active, reactive and voltage curves of Shandong power grid under another unstable condition in the embodiment of this application;
[0078] Fig.28 This is the power curve of the Linyi main transformer off-grid in the embodiment of this application;
[0079] Fig.29 The voltage curve of the Yimeng area after load shedding in the embodiment of the present application;
[0080] Fig.30 A schematic diagram of a flow chart of a method for real-time voltage response control of a high-proportion new energy power system according to an embodiment of the present application;
[0081] Fig.31This is a schematic diagram of the composition of a voltage response real-time control device for a high-proportion new energy power system according to an embodiment of the present application;
[0082] Fig.32 A schematic diagram of the composition of a terminal to which the method according to an embodiment of the present application is applied. DETAILED DESCRIPTION
[0083] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present disclosure and to be able to fully convey the scope of the present disclosure to those skilled in the art. It should be noted that, without conflict, the embodiments in this application and the features in the embodiments can be combined with each other.
[0084] At present, power system simulation is still the main means to understand the characteristics of large-scale power grids and analyze system stability. Among them, time domain simulation analysis is the most widely used, with strong applicability to complex models, and can obtain the operation trajectory of the state quantity of the whole system, and can analyze a variety of stability problems. In actual projects, preventive control and emergency control measures for voltage stability are generally obtained through offline calculations of time domain simulation. The above research determines the voltage stability control strategy based on the traditional offline decision-making method. When implementing the control, it only needs to search the matching strategy table, and the action is fast and timely.
[0085] The time domain simulation method requires long-term numerical integration calculation of the mathematical model of the power system. The calculation speed of large-scale power grids is slow, which limits its real-time application. In addition, the time domain simulation method relies on the accuracy of the model and has poor adaptability to system operation mode and faults.
[0086] The present application provides a technical solution for real-time control of voltage response of a power system with a high proportion of renewable energy, establishes a reduced-order model of voltage response of an AC / DC receiving-end power system containing a high proportion of renewable energy, determines startup preventive control measures by the stability of the reduced-order model with different startup combinations, and can quickly calculate voltage stability; judges local or global voltage stability by measuring real-time operating data such as active and reactive power of hub substations, calculates load shedding amount and executes emergency load shedding measures after determining instability, thereby achieving real-time stable voltage control of an AC / DC receiving-end (receiving external DC) power system containing a high proportion of renewable energy (such as wind power or wind power).
[0087] The real-time control method for voltage response of a high-proportion renewable energy power system provided in this application does not rely on model parameters and can adapt to different system operation modes and fault scenarios. By quickly calculating the stability of the reduced-order model, it is possible to determine voltage safety and stability prevention and control measures; based on the measured real-time operation data, the system stability is judged, and then the emergency control measures for voltage safety and stability are determined when the system is unstable. The voltage safety risk can be prevented and controlled throughout the process, and the voltage safety of the AC / DC receiving-end power system containing a high proportion of renewable energy can be achieved.
[0088] like Fig.30 As shown, the voltage response real-time control method of a high-proportion new energy power system according to an embodiment of the present application includes the following steps S100, S200 and S300.
[0089] S100: Establish a voltage response reduced-order model for AC / DC receiving-end power systems with a high proportion of renewable energy;
[0090] S200: using the established voltage response reduction model, determining a minimum cost startup plan, so that the AC / DC receiving-end power system can access a high proportion of new energy and DC on the basis of voltage safety and stability;
[0091] S300: When it is determined by using the established voltage instability criterion that the AC / DC receiving-end power system is unstable, a load shedding plan is determined, and the load shedding plan is executed so that the AC / DC receiving-end power system is connected to a high proportion of new energy and DC.
[0092] In some embodiments, the step of establishing a voltage response reduced-order model of an AC / DC receiving-end power system containing a high proportion of renewable energy includes:
[0093] In the AC / DC receiving-end power system containing a high proportion of new energy, the dynamic elements include generator nodes, active load nodes, DC nodes and other nodes;
[0094] Establish a generator aggregation model for all generator nodes;
[0095] For DC node equivalence, determine the DC equivalent impedance;
[0096] For active load nodes, induction motors are used in parallel with constant impedance loads and new energy sources;
[0097] The generator nodes, active load nodes, and DC nodes are retained and aggregated, and other nodes are eliminated. After simplifying the network, a voltage response reduced-order model of the AC / DC receiving-end power system with a high proportion of renewable energy is obtained.
[0098] In some embodiments, the step of determining a minimum cost startup solution by using the established voltage response reduced-order model includes:
[0099] Obtain the number M of local conventional units in the AC / DC receiving-end power system containing a high proportion of new energy and the corresponding 2 M A boot combination;
[0100] For the startup combination y, determining a voltage response reduced-order model corresponding to the AC / DC receiving-end power system containing a high proportion of new energy;
[0101] Determine an equivalent electromagnetic torque curve of the induction motor by using a voltage response reduction model corresponding to the startup combination y, wherein the equivalent electromagnetic torque curve takes the rotor slip of the induction motor as an independent variable;
[0102] For the starting combination y, according to the obtained critical stable slip and equivalent mechanical torque of the induction motor rotor, using the determined load-side voltage stability criterion considering DC and new energy, it is determined whether the AC / DC receiving-end power system containing a high proportion of new energy will remain stable or lose stability when the starting combination y is started;
[0103] Among all the startup combinations determined to be stable, the startup combination with the smallest capacity is selected as the minimum cost startup plan for the AC / DC receiving-end power system containing a high proportion of new energy. The minimum cost startup plan enables the AC / DC receiving-end power system to access a high proportion of new energy and DC on the basis of safe and stable voltage.
[0104] In some embodiments, it also includes:
[0105] The load-side voltage stability criterion considering DC and new energy sources is determined by using the motor equivalent electromagnetic torque curve, the critical stable slip of the induction motor rotor and the equivalent mechanical torque of the induction motor.
[0106] In some embodiments, when the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, determining a load shedding scheme includes:
[0107] Estimate the predicted power decline slope at the measurement point;
[0108] The load shedding amount corresponding to the measuring point is determined by using the determined electromagnetic power change coefficient of the induction motor after load shedding, the ratio coefficient of the electromagnetic power of the induction motor to the power of the measuring point, the new energy active power and the obtained steady-state total load of the measuring point before the fault.
[0109] In some embodiments, when the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, before determining the load shedding scheme, the method further includes:
[0110] For each power supply area, the local voltage instability judgment is performed using the established local voltage instability judgment criteria to determine if local voltage instability occurs in any power supply area;
[0111] Perform DC instability detection to determine if any DC instability has occurred;
[0112] When local voltage instability occurs in any power supply area and any DC loop instability occurs, it is determined that global voltage instability occurs.
[0113] In some embodiments, for each power supply area, using the established local voltage instability criterion to perform local voltage instability judgment to determine whether local voltage instability occurs in any power supply area includes:
[0114] Determine whether the reactive power delivered to the grid via the AC substation meets the reactive power criterion; and
[0115] Determine whether the active power connected to the grid via the AC substation meets the active power criterion; and
[0116] Determine whether the voltage on the high voltage side of the AC substation meets the voltage criterion.
[0117] In some embodiments, it also includes:
[0118] Determine that the value of the electromagnetic power variation coefficient of the induction motor after load shedding is 1;
[0119] Determine the value of the ratio coefficient between the electromagnetic power of the induction motor and the power at the measuring point to be 1;
[0120] The slope of the transformer off-grid power change is estimated by collecting the time series data of the transformer off-grid power.
[0121] In some embodiments, when determining the load shedding amount corresponding to the measuring point,
[0122] When the receiving end area does not contain new energy and synchronous machine, the value of the new energy active power is determined to be zero;
[0123] When the receiving end area contains renewable energy and synchronous generators, and the power of renewable energy and synchronous generators can be measured, the value of the renewable energy active power can be directly measured;
[0124] When the receiving area contains renewable energy and synchronous machines, but the power of the renewable energy and synchronous generators cannot be measured, the operating power of the renewable energy at the time of load shedding action 0- is taken as the active power of the renewable energy.
[0125] Specifically, in step S100, a voltage response reduced-order model of an AC / DC receiving-end power system containing a high proportion of new energy is established, including:
[0126] For AC / DC receiving power systems, Figure 1 As shown in the figure, the main dynamic elements in the system include generator G, active load (including induction motor M, static load Z ZIP, new energy R), direct current DC and other nodes (not shown in the figure); retain the three types of nodes, namely generator nodes, active load nodes and DC nodes, and aggregate them, and eliminate other nodes, so as to simplify the network while retaining the system dynamics, and obtain the system voltage response reduced-order model, that is, the system aggregation model, such as Figure 3 , Figure 4 or Figure 5 shown.
[0127] In this way, the subsequent step S200 can determine the equivalent electromagnetic torque of the induction motor based on the electromagnetic torque characteristics of the induction motor, and further determine whether the startup combination will cause system instability.
[0128] Specifically, Figure 1 The upper left part indicates the dynamic element, the generator G. E G is the equivalent internal potential of the generator, X G is the equivalent reactance of the generator, U G is the equivalent terminal voltage of the generator, Z S is the equivalent impedance of the generator branch. Figure 1 The upper right part indicates the dynamic element, DC. U DC is the equivalent voltage of the DC grid connection point, Z D is the equivalent impedance of the DC branch; X C Supplement capacitor for DC branch. Figure 1 The lower middle part indicates the active load, a dynamic element. U M is the equivalent voltage at the load end, Z M is the equivalent impedance of the load branch, the static load Z ZIP is a constant impedance load model. Naturally, other types of static loads can be equivalent to current or power respectively. M is used to indicate induction motors. X MC It is a capacitor used to compensate the power factor of the induction motor in the actual system to ensure steady-state operation. R is used to indicate renewable energy.
[0129] Specifically, when aggregating the DC nodes, generator nodes, load nodes and the entire network in the AC / DC receiving-end power system, the following steps A1 to A4 are included.
[0130] A1) Equivalent DC node
[0131] Inverter side DC voltage V di With DC currentI d With the following relationship:
[0132] (1)
[0133] (2)
[0134] In formula (1) and (2), V di is the DC voltage on the inverter side, S is the number of bridges in series, N is the transformer ratio, E d is the effective value of the AC bus line voltage of the converter station, β To trigger the lead angle, X d is the commutation reactance, I d is the DC current, γ is the arc extinction angle.
[0135] The inverter side converter station power equation includes the following equations (3) and (4):
[0136] (3)
[0137] (4)
[0138] In formula (3) and (4), P d is the DC active power delivered, Q d is the absorbed reactive power, is the DC equivalent conductance, B is the DC equivalent susceptance.
[0139] According to equations (1) to (4), we can determine Figure 4 The DC equivalent impedance Z shown on the right DC , DC grid-connected point equivalent voltage U DC And DC branch supplementary capacitor X C , no more details.
[0140] A2) Equivalence of generator nodes
[0141] When the generator nodes are aggregated, the equivalent internal potential of the generator E G and generator equivalent reactance X G They have the following formulas (5) and (6) respectively:
[0142] (5)
[0143] (6)
[0144] In formula (5) and (6), E di For generator i The equivalent potential of S Gi For generator i Rated capacity, For generator i The subtransient reactance, Ge is the total number of generators recorded in the generator set, i is a natural number less than or equal to the total number of generators.
[0145] A3) Equivalence of load nodes
[0146] like Figure 1 As shown, the active load includes the parallel induction motor load M, the static load Z ZIP and new energy R.
[0147] use Figure 2 The equivalent circuit of the induction motor load after aggregation or the induction motor aggregation model shown is as follows, wherein: U M for Figure 1 The equivalent voltage at the middle load end, the induction motor adopts the first-order model, R s is the resistance of the stator winding, X s is the leakage reactance of the stator winding, R r is the equivalent resistance of the rotor winding, X r is the leakage reactance of the rotor winding, X m is the magnetizing reactance, s is the rotor slip of the induction motor.
[0148] The values of the above parameters of the induction motor load are determined based on the capacity of each induction motor j. The capacity of the induction motor aggregation model is the sum of the rated capacities of all induction motor loads, which will not be described in detail.
[0149] Specifically, the new energy equivalent impedance is determined as Z RE , ,in U RE is the terminal voltage, S RE is the apparent power of the new energy.
[0150] Specifically, determine the static load Z ZIP For the constant impedance load model, the static load equivalent impedance holds
[0151] Z zip = R R + j X R ,in, R R is the static load resistance, X R is the static load reactance.
[0152] A4) Network aggregation
[0153] When the AC / DC receiving-end power system is network aggregated, the nodes of the AC / DC receiving-end power system are numbered in the order of generator nodes, load nodes, DC nodes and other nodes in the power grid, and the network equation is as shown in formula (7):
[0154] (7)
[0155] In formula (7), , and are the self-admittance matrix, voltage column vector and current column vector of the generator node respectively; , and are the self-admittance matrix, voltage column vector and current column vector of the load node respectively; , and are the self-admittance matrix, voltage column vector and current column vector of the DC node respectively; , and are the self-admittance matrix, voltage column vector and current column vector of other nodes respectively, and other nodes are the nodes to be eliminated; , , , , and They are the mutual admittances between four types of nodes: generator nodes, load nodes, DC nodes and other nodes.
[0156] make
[0157] , (8)
[0158] Then formula (7) can be expressed as formula (9):
[0159] (9)
[0160] Performing Gaussian elimination on other nodes in equation (9) yields:
[0161] (10)
[0162] In formula (10), .
[0163] make
[0164] , (11)
[0165] In formula (11), , , , and , are the voltage and current of the generator node, load node and DC node in the aggregation model respectively; that is, , is the voltage and current of the generator node in the aggregate model, , is the voltage and current of the load nodes in the aggregate model, , are the voltage and current of the DC nodes in the aggregate model.
[0166] Remember the transformation matrix , ; where m, n0, and k0 are the dimensions of the column vector respectively.
[0167] Further deduction, we can get:
[0168]
[0169] Thus, the equivalent admittance matrix after aggregation is for:
[0170] (12)
[0171] In formula (12), H* is the generalized inverse of H.
[0172] In this way, it can be determined Figure 3 Impedance between generator node, load node and DC node , , They are , , , that is, the impedance between the generator node and the DC node for , the impedance between the generator node and the load node for , the impedance between the DC node and the load node for .
[0173] right Figure 3 The impedance model after polymerization shown in the figure is transformed into equation (13), where after Y transformation, the impedance model after polymerization is as follows: Figure 4 Left or Figure 1 As shown, Z S is the equivalent impedance of the generator branch, Z M is the load branch equivalent impedance, Z D is the DC branch impedance:
[0174] (13)
[0175] Similarly, we can get:
[0176] (14)
[0177] In this way, the equivalent impedance of the generator branch can be determined Z S , load branch equivalent impedance Z M And DC branch impedance Z D .
[0178] Thus, the Figure 1 , Figure 3 or Figure 5 The reduced-order model of voltage response of the AC / DC receiving-end power system containing a high proportion of renewable energy is shown.
[0179] Referring to the following description, the subsequent step S300 can utilize the established AC / DC receiving-end power system voltage response reduced-order model to perform voltage safety and stability preventive control on the system access to a high proportion of new energy and DC scenarios.
[0180] Specifically, in step S200, the established voltage response reduced-order model is used to determine the minimum cost startup plan so that the AC / DC receiving-end power system can access a high proportion of new energy and DC on the basis of voltage safety and stability, thereby achieving voltage safety and stability preventive control of the high proportion of new energy and DC access system.
[0181] Specifically, the established voltage response reduced-order model is used to determine the minimum cost startup scheme of the AC / DC receiving-end power system, including the following steps B1 to B4.
[0182] B1) In an AC / DC receiving power system containing a high proportion of renewable energy, there are M local conventional generators (such as thermal power units or hydropower units), and the local conventional start-up has 2 M A boot combination;
[0183] For the startup combination y, determine the voltage response reduced-order model corresponding to the AC / DC receiving-end power system containing a high proportion of renewable energy, where y is less than or equal to 2 M A natural number.
[0184] Specifically, in different startup combinations y, the number of generators is different, and correspondingly, the values of the parameters of the voltage response reduced-order model of the AC / DC receiving-end power system containing a high proportion of renewable energy are different.
[0185] For the startup combination y, considering DC and renewable energy, the corresponding voltage response reduced-order model (such as Figure 4 As shown on the left), calculate the Thevenin equivalent potential from the load port of the induction motor into the system E TH-DC-RE and Thevenin equivalent impedance Z TH-DC-RE ,like Figure 4 Shown on the right:
[0186] (15)
[0187] (16)
[0188] In equations (15) and (16), the symbol “ / / ” indicates that two adjacent impedances are connected in parallel. Referring to the above description, the equivalent impedance of the generator branch can be determined using equations (13) and (14): Z S , load branch equivalent impedance Z M And DC branch impedance Z D ; Refer to the above description, Z RE is the new energy equivalent impedance.
[0189] Combination Figure 2 and Figure 4 On the right, we get Figure 5 The equivalent model of the induction motor is shown in Figure 1. Figure 5 Determine the equivalent electromagnetic torque T of the induction motor e As shown in formula (17):
[0190] (17)
[0191] In formula (17), R s is the resistance of the stator winding, X s is the leakage reactance of the stator winding, R r is the equivalent resistance of the rotor winding, X r is the leakage reactance of the rotor winding, X m is the magnetizing reactance, s is the rotor slip of the induction motor.
[0192] Thus, for the starting combination y, considering DC and renewable energy, the equivalent electromagnetic torque of the motor taking into account renewable energy and DC can be determined using equation (17). Specifically, the slip torque curve formed by the equivalent electromagnetic torque of the motor and the rotor slip of the induction motor, that is, the equivalent electromagnetic torque curve of the motor is as follows: Figure 6 As shown, the horizontal axis is the rotor slip s ; The vertical axis is the equivalent electromagnetic torque T e .
[0193] In this way, for any starting combination y, the slip torque curve of the motor equivalent electromagnetic torque and the induction motor rotor slip, that is, the motor equivalent electromagnetic torque curve, can be generated according to formula (17).
[0194] B2) The motor equivalent mechanical torque T m (a fixed constant) is plotted in the slip torque curve, then the equivalent electromagnetic torque T e and equivalent mechanical torque T m They intersect at the left intersection point and the right intersection point respectively. The left intersection point indicates the steady-state operation point; the right intersection point indicates the unstable operation point.
[0195] Furthermore, the load-side voltage stability criterion considering DC and new energy sources can be determined as follows: If the critical stability slip S of the induction motor rotor max The corresponding equivalent electromagnetic torque is not less than its equivalent mechanical torque, and the system remains stable during the startup process; if the critical stable slip S of the induction motor rotor max If the corresponding equivalent electromagnetic torque is smaller than its equivalent mechanical torque, the system will become unstable during the startup process.
[0196] Referring to the above description, the parameters of the induction motor load are determined based on the capacity of each induction motor j. Naturally, the equivalent mechanical torque of the induction motors corresponding to the system operation mode under the startup combination y is obtained by weighting the capacities of all induction motors, which will not be described in detail.
[0197] B3) For any startup combination y, according to the obtained critical stable slip S of the induction motor rotor max and equivalent mechanical torque, and using the load-side voltage stability criterion considering DC and new energy, determine whether the corresponding AC / DC receiving-end power system containing a high proportion of new energy is stable; wherein the load-side voltage stability criterion considering DC and new energy is as follows:
[0198] ;
[0199] Specifically, if the equivalent electromagnetic torque of the motor corresponding to the startup combination y taking into account the new energy and DC (corresponding to the system operation mode under the startup combination y) is at the critical stable slip S of the rotor max If the value at is not less than its equivalent mechanical torque, the startup combination y satisfies the load side voltage stability criterion, and the startup combination y can be determined to be a stable startup combination;
[0200] If the equivalent electromagnetic torque of the motor corresponding to the startup combination y, taking into account the new energy and DC (corresponding to the system operation mode under the startup combination y), is within the critical stable slip S of the rotor max If the value at is less than its equivalent mechanical torque, the starting combination y does not meet the load side voltage stability criterion, and it can be determined that the starting combination y is an unstable starting combination.
[0201] Specifically, according to the actual grid characteristics, the critical stable slip of the induction motor rotor S max Any value within the range of 0.06 to 0.07 can be taken, and no further details will be given.
[0202] Furthermore, if the motor equivalent electromagnetic torque curve corresponding to the starting combination y does not meet the load side voltage stability criterion, the starting combination y is determined to be an unstable starting combination; and the next starting combination (y+1) is judged to meet the load side voltage stability criterion until all 2 M The start-up combinations are respectively judged to satisfy or not satisfy the load side voltage stability criterion.
[0203] B4) Among all the startup combinations determined to be stable, the startup combination with the smallest capacity is selected as the minimum cost startup scheme of the AC / DC receiving-end power system containing a high proportion of new energy. Specifically, the capacity here is the installed capacity of all generators included in the startup combination y, and its unit is MVA.
[0204] In this way, when the minimum cost startup scheme is adopted for startup, the AC / DC receiving-end power system containing a high proportion of renewable energy can achieve voltage stability. In this way, voltage safety and stability preventive control is achieved for the system access to a high proportion of renewable energy and DC scenarios.
[0205] Specifically, in step S300, when the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, a load shedding scheme is determined and executed, so that the AC / DC receiving-end power system is connected to a high proportion of new energy and DC. In this way, voltage safety and stability emergency control of a high proportion of new energy and DC access system is achieved.
[0206] Specifically, when the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, a load shedding plan is determined, including the following steps C1 to C5.
[0207] C1) Voltage instability determination
[0208] Based on the characteristics of the system voltage response reduced-order model, the AC / DC receiving power system (such as Figure 7 The real-time operation data obtained from the medium and high voltage side or the DC receiving end (such as 1000kV DC) is used to determine the system voltage instability criterion.
[0209] Figure 7 New energy stations within the central power supply area are indicated by the letter R surrounded by a circle; the voltage levels within the power grid include: 1000kV, 500kV, 220kV and 110kV, and Pdc1 and Pdc2 represent the active power of the two DC receiving ends.
[0210] like Figure 7 As shown, the real-time operation data that can be obtained include: the high-voltage side voltage U or V of each AC substation, the active power from each AC substation to the grid P and reactive power Q, DC power during fault (e.g. 1000kV DC) P dc And DC power before fault P dc0 (such as 1000kV DC).
[0211] The sampling time is assumed to be k , the sampling interval is selected as 10ms, then the determination of the system voltage instability criterion includes the following steps D1 to D3 。
[0212] D1) Local voltage instability determination:
[0213] The power supply area covered by each AC substation is taken as the local area, and whether the local area voltage or local voltage is unstable during the low-breakthrough period of renewable energy is considered.
[0214] ① Determine whether the reactive power Q connected to the grid via the AC substation meets the following reactive power criteria:
[0215]
[0216] in, is the total reactive power of all new energy nodes in the power supply area during the period of new energy low penetration at two adjacent sampling times k and (k+1) The change value of RE is the set of new energy nodes, Q REi is the new energy node i RE The reactive power of the network, i RE Greater than or equal to 1 and less than N RE , N RE is the number of new energy nodes in the power supply area; reactive power change value K q Under typical parameters, it can be conservatively taken as 0;
[0217] If it is determined that the reactive power of the off-grid power meets the reactive power criterion, it is determined that the reactive power of the off-grid power of the AC substation is sufficient after the fault occurs, the local voltage is stable, and the logic value is recorded as 1;
[0218] If it is determined that the reactive power of the off-grid power does not meet the reactive power criterion, it is determined that the reactive power of the off-grid power of the AC substation is insufficient after the fault occurs, the local voltage is unstable, and the logical value is recorded as 0.
[0219] ② Determine whether the active power P connected to the grid via the AC substation meets the following active power criteria:
[0220]
[0221] in, It is the total active power of all new energy nodes in the power supply area during the period of new energy low penetration at two adjacent sampling times. k and (k+1) The change value of RE is a collection of new energy nodes. P REi New energy node i RE Active power of the grid, i RE Greater than or equal to 1 and less than N RE , N RE is the number of new energy nodes in the power supply area; the active power change value K P Under typical parameters, it can be conservatively taken as 0;
[0222] If it is determined that the active power of the AC substation meets the active power criterion, it is determined that the active power of the AC substation is sufficient, the local voltage is stable, and the logic value is recorded as 1;
[0223] If it is determined that the active power of the off-grid power does not meet the active power criterion, it is determined that the off-grid active power of the AC substation is insufficient, the local voltage is unstable, and the logical value is recorded as 0.
[0224] ③ Determine whether the voltage V on the high-voltage side of the AC substation meets the following voltage criteria:
[0225] .
[0226] Among them, the DC voltage V is k and (k+1) The change value threshold e Use a small value close to zero, such as 0.001.
[0227] The sign on the right side of the inequality here is positive, which means that the voltage on the high-voltage side of the power supply area covered by the AC substation gradually decreases between two adjacent sampling moments during the period of low penetration of new energy. If it is greater than the preset DC voltage change value threshold e .
[0228] If the voltage on the high-voltage side of the AC substation meets the voltage criterion, the local voltage is determined to be stable and the logic value is recorded as 1; if the voltage on the high-voltage side of the AC substation does not meet the voltage criterion, the local voltage is unstable and the logic value is recorded as 0.
[0229] ④If the above conditions ①② and ③ all meet the criteria (each logical value is taken as 1), the local instability timer starts timing (such as starting timing from zero), so the timing output is cumulative timing and is a non-zero value; otherwise, if any of the three conditions ①② and ③ does not meet the criteria (each logical value is taken as 0), the timing output of the local instability timer is kept at 0, that is, zero value.
[0230] ⑤ Considering the recovery speed of DC during the fault, the local instability criterion triggering needs to be added with the preset duration t d .
[0231] That is, if the local instability timer outputs tt > t d , then the local instability criterion is triggered, the local voltage instability conclusion is generated and output or displayed to warn of local voltage instability; otherwise, if the local instability timer outputs tt < t d , the local instability criterion is not triggered, the local voltage instability conclusion is not generated and is not output or displayed.
[0232] Specifically, the preset duration t d The value can be determined according to the actual grid characteristics. For example, in the following Shandong grid calculation example, the preset duration t d It can be taken as 0.7s.
[0233] Repeat steps ① to ⑤ above to use the local instability timer tt 1. Conduct local voltage instability judgment for each power supply area, generate local voltage instability conclusions and output or display them.
[0234] D2) For all DC in the area, uniformly perform DC instability judgment:
[0235] ① Determine whether the DC power meets the DC power criterion:
[0236]
[0237] in, P dck For DC at the sampling time k Active power at ;
[0238] Among them, the drop ratio threshold k dc It can take a value of 0.5, or be adjusted between 0.1 and 1.0; P dc0 is the DC power before the fault.
[0239] The above inequality means that the ratio of the active power received during the DC fault to the DC power received before the fault is less than the drop ratio threshold. If the inequality holds, it is judged that the DC power drops too much (such as dropping to the preset low-crossing threshold, that is, the ratio of the DC power before the fault to the drop ratio threshold). k dc The product of ), the logical value is recorded as 1; if the inequality does not hold, it is determined that the DC power has not dropped to the preset low-crossing threshold, and the logical value is recorded as 0.
[0240] ② If the logic value of the output of condition ① is 1, the DC instability timer starts timing, and the output of the DC instability timer is a non-zero value; otherwise, the output of the DC instability timer is always 0, that is, zero value.
[0241] Repeat the above steps ① to ② to use the DC instability timer tt 2. Perform DC instability judgment uniformly for all DC in the area, generate DC instability conclusions and output or display them. Or add a preset duration t d , please refer to the above D1) ⑤, no further details will be given.
[0242] D3) Global voltage instability determination
[0243] Any local instability timer tt 1 and DC instability timer tt 2 outputs are greater than the preset duration t d, the global instability criterion is triggered, the global voltage instability conclusion is generated and output or displayed as “global voltage instability” to warn of global voltage instability; otherwise, the global instability criterion is not triggered, and the global voltage instability conclusion is not generated and output.
[0244] In this way, if DC instability and any local instability occur at the same time, the global voltage instability is determined, and it is necessary to further determine the load shedding plan and execute the load shedding plan so that the AC / DC receiving-end power system can achieve a high proportion of new energy and DC access, thereby achieving safe and stable voltage emergency control.
[0245] C2) Calculate the load shedding
[0246] like Figure 8 As shown, the power supply area includes not only AC substations and conventional generator sets, but also new energy and induction motor loads. R in the figure is used to indicate new energy stations, and G is used to indicate conventional generator sets. Three different icons are used to indicate the three voltage levels in the power supply area: 500kV, 220kV and 110kV. Usually the load is connected to the lowest voltage level, which is lower than the voltage on the high-voltage side of the AC substation, such as 110kV. Measuring devices are installed on the high-voltage side of the hub substation (one or more of multiple AC substations) in the power supply area to form a measuring point; real-time operating data of the measuring point is monitored, such as active power P and reactive power Q, DC power P dc , DC power before fault P dc0 , AC substation high voltage side voltage V or U. If the measurement point is set at the 500kV bus, the bus is connected to new energy, induction motor load and static load.
[0247] When the global or local instability criterion is triggered, the load shedding amount is calculated using formula (18) based on the real-time operation data of the measurement point obtained by real-time measurement:
[0248] (18)
[0249] Among them, m% is the percentage of load shedding to the total steady-state load or total load power before the fault at the measuring point;
[0250] t c- It is the 0-time of load shedding action;
[0251] K e is the electromagnetic power variation coefficient of the induction motor after load shedding, which can usually be taken as 1;
[0252] is the ratio coefficient between the electromagnetic power of the induction motor and the power at the measuring point, which can usually be taken as 1;
[0253] Ktc- for t c- The percentage of active power of the induction motor to the total load power at any moment, K s is the percentage of the electromagnetic power of the induction motor to the active power at the induction motor port, K 0 is the percentage of the active power of the steady-state induction motor to the total load power before the fault;
[0254] P Used to indicate the active power at the measurement point, P(0) is the power at the measurement point before the fault; P ( t c- )= P ( t 1)- t dy D P , in P ( t 1) To determine the voltage instability moment t 1. Active power at the measuring point, D P Predict the decreasing slope of the power at the measurement point, t dy To control the delay (usually 100ms);
[0255] P RE Used to indicate the active power of new energy sources. P RE (0) is the active power of new energy before the fault, P RE (t c - ) The active power of new energy at the time of load shedding action 0;
[0256] P G Used to indicate the active power of the generator. P G (0) is the active power of the generator before the fault, P G (t c - ) It is the active power of the generator at the moment of load shedding action 0.
[0257] The above formula (18) is applicable to the voltage instability scenario on the load side dominated by induction motors, and can reflect the impact of new energy access on voltage instability.
[0258] Above, in the control delay t dy After that, directly enter the load shedding action 0- t c- It is generally believed that during the control delay process, the calculation and device response have been completed, and the load shedding action 0- t c- Perform load shedding operation.
[0259] In this way, when the local instability criterion is triggered, the load shedding amount is calculated based on the real-time operating data of the measuring point obtained by real-time measurement; when the local instability criterion is triggered in multiple local areas, the respective load shedding amounts are calculated based on the real-time operating data of the measuring points obtained by real-time measurement, which will not be repeated.
[0260] The following is a detailed description of the process of determining the values of the key parameters in equation (18).
[0261] C3) Determine the electromagnetic power variation coefficient of the induction motor after load shedding K e The value is 1
[0262] According to the critical stable slip of the induction motor under different load levels, the critical slip-mechanical torque stability boundary can be determined, and then the voltage instability boundary of the induction motor can be determined.
[0263] Referring to the above description, the equivalent electromagnetic torque T of the induction motor e As shown in formula (17):
[0264] (17)
[0265] Considering the electromagnetic torque T e Or mechanical torque T m Not as good as electromagnetic power P e Or mechanical power P m For the convenience of measurement, power is used to replace torque. Combined with formula (17), the power can be used to describe the load side voltage stability criterion as follows:
[0266]
[0267] .
[0268] Accordingly, power is used to replace torque, combined with Figure 6 The equivalent electromagnetic torque curve of the motor shown in Figure 2 can be obtained. Fig. 9 The voltage instability boundary of the induction motor under different load levels is shown in Figure 1, where point A is the load level. P m The critical stable operating point when S cr-A; Point B is the load level P m The critical stable operating point at ' corresponds to the critical slip S cr-B Specifically, point A is the critical stable operation point before load shedding, and point B is the critical stable operation point after load shedding. Accordingly, the load level before load shedding is P m Greater than the load level after load shedding P m '; Critical slip before load shedding S cr-A Less than the critical slip after load shedding S cr-B Before and after load shedding, if the slip is less than the critical slip corresponding to the corresponding load level, the system is stable.
[0269] Fig.10 The voltage instability boundary of induction motors under different proportions of induction motors (50% or 60%) and system strength (X=0.2pu or 0.3pu, benchmark capacity 1000MVA) is shown, corresponding to load levels of 600MW to 2000MW.
[0270] according to Fig.10 It can be seen that under the critical stable slip, the slip after load shedding is within the critical slip. Fig.11 , that is, the load is cut to the critical stable slip P e 'or P e The subsequent operating point is within the stability boundary, that is, s ( P m '= P e '), s ( P m = P e ) are all within the critical slip.
[0271] Fig. 9 It is also a schematic diagram of the power stability boundary. The power stability boundary is the intersection of electromagnetic power and mechanical power, that is, the curve of the critical operating point corresponding to the slip. The ordinate is power, and the abscissa is the slip corresponding to the critical operating point. Fig.10 The electromagnetic power-slip curves under different boundary conditions are shown, without corresponding ordinate or abscissa markings. Fig.11 By showing the operating point under instability, the power requirement under stable system condition can be obtained as shown in equations (19) and (20):
[0272] (19)
[0273] (20)
[0274] According to equations (19) and (20), two load shedding control quantities can be obtained:
[0275] (twenty one)
[0276] (twenty two)
[0277] In formula (22), P e =K e P e , K e is the electromagnetic power variation coefficient of the induction motor after load shedding, P e is the electromagnetic power of the induction motor.
[0278] That is, the load shedding amount Δ corresponding to the induction motor P m = P m - P e or Δ P m = P m - P e ' can ensure the stability of the system, and then conclude K e =1, that is, there is no need to consider the change of electromagnetic power curve. In this way, the electromagnetic power change coefficient of the induction motor after load shedding is K e Usually it can be 1.
[0279] C4) Determine the ratio coefficient between the electromagnetic power of the induction motor and the power at the measuring point The value is 1
[0280] Refer to the above description, is the ratio coefficient of the electromagnetic power of the induction motor to the power at the measuring point, where K tc- for t c- At the moment (0-time of load shedding action), the percentage of active power of the induction motor to the total load power, K s It is the ratio of the electromagnetic power of the induction motor to the active power of the port or the percentage of the electromagnetic power of the induction motor to the active power of the induction motor port. K0 is the percentage of the steady-state induction motor active power to the total load power before the fault.
[0281] like Fig.12 As shown, the power relationship of the induction motor satisfies the following equations (23), (24) and (25), where: P M is the port power, P L is the load power:
[0282] (twenty three)
[0283] (twenty four)
[0284] (25)
[0285] Fig.13 The electromagnetic power of the induction motor is given by P e , Port Power P M And load power P L From the curve comparison chart, it can be seen that as the slip (slip is the difference between the stator rotating magnetic field speed and the rotor speed) increases, the proportional relationship between the three powers will change.
[0286] Fig.14 The power ratio coefficient under different system impedance or system strength is provided. Specifically, the system strength under the load power of 1000MW and the proportion of induction motors of 80% is given. X From 0.05pu to 0.3pu, the power ratio coefficient The curve changes with the slip. It can be seen that when the slip is within 0.15, Slightly or slightly greater than 1 or around 1.
[0287] Fig.10 and Fig.14 In the system impedance or system strength X for Figure 4 or Figure 5 The Thevenin equivalent potential E from the load port of the induction motor into the system TH-DC-RE The imaginary part is different X The electromagnetic power curve of the induction motor is as follows: Fig.14 shown.
[0288] Fig.15 The power ratio coefficient is given when the load initial power is 1000MW and the system strength X is 0.2pu, and the proportion of induction motors changes from 20% to 80%. The curve changes with the slip. When the slip is within 0.15, the power ratio coefficient Basically greater than 1.
[0289] Considering that the actual power grid is in a load-side voltage instability dominated by induction motors, the slip is usually within 0.15, so The value of is 1, which is conducive to ensuring the conservatism of the load shedding control amount.
[0290] C5) Determine the active power of new energy P RE The value of is used to determine the load shedding amount corresponding to the new energy
[0291] The following analyzes the active power of new energy under four working conditions in turn. P RE The value of .
[0292] Condition 1: The receiving area does not contain new energy and synchronous machines
[0293] When there is no new energy source and synchronous machine (that is, the generator mentioned above), equation (26) holds:
[0294] (26)
[0295] That is, the active power of new energy P RE The value is zero, the active power of the synchronous generator P G The value is zero, and the active power of the measurement point can be directly obtained, such as the power before the fault P(0) and the power at the load shedding action 0-time P( t c -), and calculate the load shedding amount according to equation (26) and equation (18).
[0296] Working condition 2: The receiving area contains renewable energy and synchronous generators, and the power of renewable energy and synchronous generators can be measured
[0297] When the measurement point contains renewable energy and synchronous machines with measurable power, the real-time operating data of the measurement point can be directly measured, including: , , , , and , which can then be calculated based on the real-time operation data The load shedding amount is then calculated according to formula (18).
[0298] Condition 3: The receiving area contains renewable energy and synchronous generators, but the power of renewable energy and synchronous generators cannot be measured
[0299] From formula (18) and the values determined in the above steps C4) and C5), we can get formula (27):
[0300] (27)
[0301] Then the equation can be transformed to get equation (28):
[0302] (28)
[0303] Considering The essence is the total load power at the stable operating point, then the load shedding action 0-time t c- Moment and Determine the operating power of each of the new energy source and the generator at the stable operating point, and then get:
[0304] (29)
[0305] Working condition 4: When considering the voltage instability caused by external power supply of the regional network rather than the voltage instability on the load side dominated by the induction motor, the most conservative load shedding plan can be adopted, that is, cutting the off-grid power to 0.
[0306] C6) Estimate the power prediction decline slope D at the measurement point P Or the slope of transformer off-grid power change
[0307] Refer to the above description, P ( t c -)= P ( t 1)- t dy D P ,in P ( t 1) To determine the active power at the measuring point at the moment t1 of transient voltage instability, D P Predict the decreasing slope of the power at the measurement point, t dy To control the delay (usually 100ms).
[0308] The following estimates the slope of the transformer off-grid power change by collecting the time series data of the transformer off-grid power. D P .
[0309] Record the nth sampling time t n The corresponding substation or transformer offline active power is P tn ,set upP tn With sampling time t n The following linear relationship exists:
[0310] (30)
[0311] Considering the active power of the substation or transformer from sampling time n to sampling time n+m, there exists a matrix relationship (31), where ε is the measurement error, b is a constant:
[0312] (31)
[0313] According to the least squares estimation, we can get formula (32):
[0314] (32)
[0315] In this way, the power prediction down slope D can be obtained P and constant b, complete the power prediction decline slope D at the measurement point P Estimates.
[0316] In some embodiments, using Fig.16 The AC / DC receiving-end power system with a load of 4800MW and a DC load of 1000MW shown in the figure uses the method of the aforementioned step S200 to verify the accuracy of the aforementioned voltage prevention and control measures. Specifically, the AC / DC receiving-end power system has different numbers of generator sets (such as 3, 3 and 7) connected at 3 nodes, and the generated minimum startup plan is shown in Table 1. As listed in Table 1, the minimum cost startup plan determined by the aforementioned voltage response reduction model, that is, the theoretical minimum startup, is basically consistent with the minimum startup plan determined by the time domain simulation calculation. It should be understood that, Fig.16 In the figure, the new energy is evenly connected under each Uxx node (such as U1, U2, U3, U4, U13, U14 and U23, etc.). Because the new energy is too dispersed, it is not convenient to display it on the figure, so it is not shown in the figure.
[0317] Table 1 Minimum startup plan
[0318]
[0319] In some embodiments, based on the Shandong power grid (load 4800MW and DC 1000MW), three cases are taken as examples, and the accuracy of the voltage emergency control measures is verified respectively using the method of the aforementioned step S300.
[0320] Case 1: If Figures 17 to 21 As shown, at 1.0s, the UHV multi-circuit line fault (such as Fig.17 and Fig.18 Then, the active power of the Yimeng and Taishan transformers (dark blue curve) decreased (as shown in Fig.17 As shown in Figure 2), reactive power (red curve) increases (as Fig.17 As shown in the figure, the voltage (green curve) does not recover (as shown in the figure). Fig.17 As shown), DC power is not restored (as Fig.18 The power of the two DC receiving terminals of Guanggu and Yinan under the unstable working condition shown in the figure); when the active power decreases, the reactive power increases and the voltage does not recover and the conditions last for 0.7s, the local voltage instability criterion is triggered; the load shedding amount is calculated according to the above formula (18), and the load of the whole network is cut off by 12000MW; the load shedding amount of Taishan main transformer is 1400MW (such as Fig. 20 As shown,) and the load shedding capacity of Yimeng main transformer is 1400MW (as shown Fig. 20 After that, the system returns to stability (as shown in Fig.19 As shown in ), where the action command is issued at the time (such as Fig. 20 and Fig.21 The red dot on the left) and the load shedding action time (as shown in Fig. 20 and Fig.21 The delay between the two (shown by the red dot on the right) is 100ms. Fig.17 The power and voltage curves are put together, with the left vertical axis representing active and reactive power, and the right vertical axis representing voltage. Fig. 22 and Fig.23 and Fig.26 and Fig. 27 Similar, no further elaboration.
[0321] Case 2: If Figure 22 to Figure 25 As shown in Figure 1, at 1.0s, a short circuit fault occurred in the Taishan area, and the Taishan-Daizong and Daizong-Yuncheng lines were cut off successively, causing the voltage in the Taian area to become unstable (as shown in Figure 1). Fig.25 At 1.3s, the active power of the Lutaishan station is ( Fig.23 The green curve in the middle) decreases, reactive power increases, and the voltage does not recover. The instability criterion is triggered at 2s. Considering a 100ms action delay (such as Fig.24 As shown in the figure, the delay between the time when the action command is issued and the time when the load is cut is 100ms). The active power of Taishan Station off the grid is predicted at 2.1s. According to the above formula (18), the load cut control amount is 1.25 million kilowatts (1250MW). After the main transformer of Lutaishan Station cuts the load (such as Fig.24 As shown, the system voltage returns to stability (as shown Fig.25 as shown).
[0322] Case 3: If Figure 26 to Figure 29As shown in the figure, at 1.0s, the Yimeng-Rizhao N-1 fault occurred and the protection refused to operate. The delayed fault removal caused the voltage instability in the Linyi area. At 1.3s, the active power of the Yimeng station decreased, the reactive power increased, and the voltage did not recover. At 2s, the instability criterion was triggered. Considering the 100ms action delay of the device (such as Fig.28 As shown in the figure, the delay between the time when the action command is issued and the time when the load is cut is 100ms). The active power of the Linyi main transformer off-grid at 2.1s is predicted, and the load cut control amount is 1.51 million kilowatts (that is, 1510MW). After the load is cut, the system returns to stability (as shown in the figure). Fig.29 as shown).
[0323] like Fig.31 As shown, the voltage response real-time control device of a high-proportion new energy power system of the embodiment of the present application includes:
[0324] A reduced-order model building unit 10 is used to establish a voltage response reduced-order model of an AC / DC receiving-end power system containing a high proportion of new energy;
[0325] The minimum startup determination unit 20 is used to determine the minimum cost startup scheme by using the established voltage response reduction model, so that the AC / DC receiving-end power system can access a high proportion of new energy and DC on the basis of voltage safety and stability;
[0326] The load shedding determination unit 30 is used to determine a load shedding plan when judging that the AC / DC receiving-end power system is unstable by using the established voltage instability criterion, and execute the load shedding plan so that the AC / DC receiving-end power system can access a high proportion of new energy and DC.
[0327] The device of the embodiment of the present application and the method of the embodiment of the present application are based on the same inventive concept, can be implemented as a reference, and have the same beneficial effects as the method adopted, operated or implemented.
[0328] The present application also provides a terminal to execute the method. Fig.32 It shows a schematic diagram of a terminal provided by some embodiments of the present application. Fig.32 As shown, the terminal 8 includes: a processor 800, a memory 801, a bus 802 and a communication interface 803, and the processor 800, the communication interface 803 and the memory 801 are connected via the bus 802; the memory 801 stores a computer program that can be run on the processor 800, and the processor 800 executes the method provided by any embodiment described in the present application when running the computer program.
[0329] The memory 801 may include a high-speed random access memory (RAM), and may also include a non-volatile memory, such as at least one disk storage. The communication connection between the device network element and at least one other network element is realized through at least one communication interface 803 (which may be wired or wireless), and the Internet, wide area network, local area network, metropolitan area network, etc. may be used.
[0330] The bus 802 may be an ISA bus, a PCI bus, or an EISA bus, etc. The bus may be divided into an address bus, a data bus, a control bus, etc. The memory 801 is used to store programs, and the processor 800 executes the program after receiving an execution instruction. The method disclosed in any implementation of the embodiment of the present application may be applied to the processor 800, or implemented by the processor 800.
[0331] The processor 800 may be an integrated circuit chip with signal processing capabilities. In the implementation process, each step of the method can be completed by the hardware integrated logic circuit or software instructions in the processor 800. The processor 800 may be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it may also be a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a readily available programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. The methods, steps and logic block diagrams disclosed in the embodiments of the present application can be implemented or executed. The general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc. The steps of the method disclosed in the embodiments of the present application can be directly embodied as a hardware decoding processor to be executed, or the hardware and software modules in the decoding processor are combined and executed. The software module may be located in a mature storage medium in the field such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory or an electrically erasable programmable memory, a register, etc. The storage medium is located in the memory 801, and the processor 800 reads the information in the memory 801 and completes the steps of the method in combination with its hardware.
[0332] The terminal provided in the embodiment of the present application and the method in the embodiment of the present application are based on the same inventive concept and have the same beneficial effects as the method adopted, operated or implemented by them.
[0333] An embodiment of the present application also provides a computer-readable storage medium corresponding to the method provided by the embodiment, and the computer-readable storage medium is a CD, on which a computer program (i.e., a program product) is stored. When the computer program is run by a processor, it will execute the method provided by any of the embodiments.
[0334] It should be noted that examples of the computer-readable storage medium may also include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other optical or magnetic storage media, which are not listed here one by one.
[0335] The computer-readable storage medium provided by the embodiments of the present application is based on the same inventive concept as the method of the embodiments of the present application, and has the same beneficial effects as the method adopted, run or implemented by the application program stored therein.
[0336] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these adjustments and modifications of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these changes and modifications.
Claims
1. A real-time control method for voltage response of a high-proportion renewable energy power system. It is characterized in that include: Establish a voltage response reduced-order model for AC / DC receiving-end power systems containing a high proportion of renewable energy; The establishment of a voltage response reduced-order model of an AC / DC receiving-end power system containing a high proportion of new energy sources comprises: In the AC / DC receiving-end power system containing a high proportion of new energy, the dynamic elements include generator nodes, active load nodes, DC nodes and other nodes; Establish a generator aggregation model for all generator nodes; For DC node equivalence, determine the DC equivalent impedance; For active load nodes, induction motors are used in parallel with constant impedance loads and new energy sources; The generator nodes, active load nodes, and DC nodes are retained and aggregated, and other nodes are eliminated. After simplifying the network, the voltage response reduced-order model of the AC / DC receiving-end power system with a high proportion of new energy is obtained. Using the established voltage response reduction model, a minimum cost startup plan is determined to enable the AC / DC receiving-end power system to access a high proportion of new energy and DC on the basis of voltage safety and stability; When the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, a load shedding plan is determined, and the load shedding plan is executed so that the AC / DC receiving-end power system is connected to a high proportion of new energy and DC; When the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, a load shedding scheme is determined, including: Estimate the predicted power decline slope at the measurement point; The load shedding amount corresponding to the measuring point is determined by using the determined electromagnetic power change coefficient of the induction motor after load shedding, the electromagnetic power of the induction motor and the power ratio coefficient of the measuring point, the new energy active power and the obtained total steady-state load of the measuring point before the fault; The method of determining a minimum cost startup scheme by using the established voltage response reduced-order model comprises: Obtain the number M of local conventional units in the AC / DC receiving-end power system containing a high proportion of new energy and the corresponding 2M startup combinations; For the startup combination y, determining a voltage response reduced-order model corresponding to the AC / DC receiving-end power system containing a high proportion of new energy; Determine an equivalent electromagnetic torque curve of the induction motor by using a voltage response reduction model corresponding to the startup combination y, wherein the equivalent electromagnetic torque curve takes the rotor slip of the induction motor as an independent variable; For the starting combination y, according to the obtained critical stable slip and equivalent mechanical torque of the induction motor rotor, using the determined load-side voltage stability criterion considering DC and new energy, it is determined whether the AC / DC receiving-end power system containing a high proportion of new energy will remain stable or lose stability when the starting combination y is started; Among them, the load-side voltage stability criterion considering DC and new energy is determined by using the motor equivalent electromagnetic torque curve, the critical stable slip of the induction motor rotor and the equivalent mechanical torque of the induction motor; Among all the startup combinations determined to be stable, the startup combination with the smallest capacity is selected as the minimum cost startup plan for the AC / DC receiving-end power system containing a high proportion of new energy. The minimum cost startup plan enables the AC / DC receiving-end power system to access a high proportion of new energy and DC on the basis of safe and stable voltage.
2. The method according to claim 1, It is characterized in that When the AC / DC receiving-end power system is judged to be unstable by using the established voltage instability criterion, before determining the load shedding scheme, the method further includes: For each power supply area, the local voltage instability judgment is performed using the established local voltage instability judgment criteria to determine if local voltage instability occurs in any power supply area; Perform DC instability detection to determine if any DC instability has occurred; When local voltage instability occurs in any power supply area and any DC loop instability occurs, it is determined that global voltage instability occurs.
3. The method according to claim 2, It is characterized in that The method of performing local voltage instability determination for each power supply area by using the established local voltage instability determination criteria to determine whether local voltage instability occurs in any power supply area includes: Determine whether the reactive power delivered to the grid via the AC substation meets the reactive power criterion; and Determine whether the active power connected to the grid via the AC substation meets the active power criterion; and Determine whether the voltage on the high voltage side of the AC substation meets the voltage criterion.
4. The method according to claim 1, It is characterized in that Also includes: Determine that the value of the electromagnetic power variation coefficient of the induction motor after load shedding is 1; Determine the value of the ratio coefficient between the electromagnetic power of the induction motor and the power at the measuring point to be 1; The slope of the transformer off-grid power change is estimated by collecting the time series data of the transformer off-grid power.
5. The method according to claim 1, It is characterized in that When determining the load shedding amount corresponding to the measuring point, When the receiving end area does not contain new energy and synchronous machine, the value of the new energy active power is determined to be zero; When the receiving end area contains renewable energy and synchronous generators, and the power of renewable energy and synchronous generators can be measured, the value of the renewable energy active power can be directly measured; When the receiving area contains renewable energy and synchronous machines, but the power of the renewable energy and synchronous generators cannot be measured, the operating power of the renewable energy at the time of load shedding action 0- is taken as the active power of the renewable energy.
6. A real-time voltage response control device for a high-proportion new energy power system. It is characterized in that The method for implementing the real-time control method of voltage response of a high-proportion new energy power system as claimed in claim 1 comprises: A reduced-order model building unit is used to establish a voltage response reduced-order model of an AC / DC receiving-end power system containing a high proportion of new energy; A minimum startup determination unit, used to determine a minimum cost startup scheme by using the established voltage response reduction model, so that the AC / DC receiving-end power system can access a high proportion of new energy and DC on the basis of voltage safety and stability; The load shedding determination unit is used to determine a load shedding plan when judging that the AC / DC receiving-end power system is unstable by using the established voltage instability criterion, and execute the load shedding plan so that the AC / DC receiving-end power system can access a high proportion of new energy and DC.
7. A terminal, include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the method according to any one of claims 1 to 5.