A hydrate loop experimental system and test method for a gas-dominated flow system
By designing a gas-phase-dominant flow system hydrate loop experimental system, the problem of difficult to simulate the generation and inhibitor testing of hydrate under gas-phase-dominant flow in the prior art is solved, and the three-phase circulating flow of gas-liquid solid is realized, and water under gas-liquid and solid is simulated in gas field production conditions is simulated. The production and blocking process of the compound provide an effective inhibitor testing method.
Patent Information
- Application Number
- CN202411310220.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-19
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-09-19
AI Technical Summary
The prior art is difficult to simulate and study the generation, growth, deposition and inhibitor effects of hydrates under the gas-phase-dominated flow system. It lacks a gas-phase loop that can achieve the gas-liquid and solid three-phase non-separation circulation flow, and it is difficult to test the gas-phase-dominated flow system to drain. Equipment and methods of compound inhibitors.
A gas-phase-dominant flow system hydrate loop experimental system is designed, including main pipeline, visual pipe section, recording system, high-pressure fan, flowmeter, temperature sensor, pressure sensor, cold storage temperature control system and gas supply system, through high pressure The fan drives the circulation flow of gas, liquid and solid three-phase fluids, simulates the flow scenarios during the production and transportation process of gas fields, and realizes real-time observation and data recording of the experimental process.
The research on hydrate generation, growth, and deposition under the gas-phase-dominant flow system and the testing of inhibitor effects can be realized. It can simulate the hydrate generation and blockage process under the actual production conditions of the gas field, and provides testing conditions for the long-term inhibitor effect. Observe the three-phase flow state of gas, liquid and solid in the pipeline under different conditions and the growth morphology of hydrates.
Smart Images

Figure CN118837505B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to hydrate formation simulation and hydrate inhibitor testing, and in particular to a hydrate loop experimental system and a testing method for a gas-phase-dominated flow system. Background Art
[0002] The development of conventional oil and gas and natural gas hydrates in the ocean and cold regions is often accompanied by high pressure and low temperature environments. Hydrates are easily generated under such conditions. Newly generated hydrates will adhere to and deposit on pipelines, causing pipeline blockages, affecting production efficiency, and in severe cases, damaging equipment and causing accidents, which has brought great troubles to oil and gas production. Adding hydrate inhibitors is a widely used hydrate prevention and control method. Therefore, it is very important to study the process of hydrate formation and blockage, test the effect of hydrate inhibitors, and propose corresponding hydrate blockage prevention and control plans to ensure the safe and efficient operation of oil and gas fields.
[0003] At present, the conventional equipment used in the laboratory to carry out hydrate formation and inhibitor effect testing and research is mainly a high-pressure reactor. The use of this equipment can easily and quickly obtain experimental data. The reactor uses mechanical stirring or magnetic stirring to simulate the flow, thereby enhancing the mass transfer and disturbance between the gas and liquid phases. However, this method is different from the flow of gas-liquid phase fluids in actual oil and gas field pipelines, and it is difficult to study the impact of different flow states on hydrate growth.
[0004] The experimental loops currently used for hydrate-related research are mainly liquid phase loops that simulate mixed oil and gas transportation. Experiments can be carried out under oil-dominated or water-dominated systems. However, during gas field exploitation and transportation, the flow system is gas-dominated. There are differences in the flow morphology, gas-liquid contact mode, mass transfer rate, etc. between the gas-dominated and liquid-dominated systems, resulting in differences in the hydrate nucleation, growth, aggregation, deposition, and blockage processes in the two systems. However, at this stage, there are relatively few loops in the gas-dominated system, and there is a lack of gas phase loops that can realize non-separation circulating flow of gas-liquid-solid multiphases, as well as a lack of equipment and methods for testing hydrate inhibitors in gas-dominated flow systems.
[0005] It should be noted that the information disclosed in the above background technology section is only used for understanding the background of the present application, and therefore may include information that does not constitute prior art known to ordinary technicians in the field. Summary of the invention
[0006] The invention provides a gas-phase-dominated flow system hydrate loop experimental system and a testing method.
[0007] The present invention adopts the following technical solution:
[0008] In the first aspect, a hydrate loop experimental system in a gas-phase-dominated flow system is provided, which includes: a main pipeline for circulating fluid therein; a visual pipe section connected to the main pipeline; a recording system corresponding to the visual pipe section for real-time observation and recording of the flow morphology of the fluid and the formation, deposition and growth morphology of hydrates during the experiment; a high-pressure fan installed below the main pipeline to ensure that the fluid circulates in the main pipeline, wherein the high-pressure fan includes a casing, fan blades, a transmission shaft, an internal magnet, a motor and an external magnet, and a controller, the casing is connected to the main pipeline, the fan blades, the transmission shaft and the internal magnet are sealed in the casing, one end of the transmission shaft is connected to the fan blades, and the other end is connected to the internal magnet, the motor and the external magnet are located outside the casing and coupled to the internal magnet, and the controller is connected to the main pipeline. The motor is connected to the external magnet, and the controller is used to operate the motor and the external magnet, driving the internal magnet to rotate, thereby driving the transmission shaft to rotate and the fan blades to rotate, driving the fluid in the main pipeline to circulate; a flow meter, a temperature sensor and a pressure sensor are all installed on the main pipeline, and are used to measure the fluid flow, temperature and pressure in the main pipeline during the experiment; a differential pressure gauge is installed on the main pipeline and located on both sides of the inlet and outlet of the high-pressure fan, and is used to measure the change in pressure difference during the experiment; a cold storage temperature control system is used to control the temperature of the fluid in the main pipeline during the experiment; a gas supply system and a liquid injection system are both connected to the main pipeline, and are used to provide gas and liquid to the main pipeline respectively; a data acquisition system is used to record and save temperature, pressure, flow, pressure difference and video images.
[0009] In a second aspect, a method for testing a hydrate loop experiment in a gas-dominated flow system according to the system of the first aspect is provided, comprising the following steps: (1) liquid injection: injecting an experimental solution into the main pipeline through the liquid injection system; (2) gas injection: injecting an experimental gas into the evacuated main pipeline through the gas supply system until the pressure in the main pipeline increases to a target pressure value; (3) stabilizing the initial temperature and flow rate: turning on the high-pressure fan, setting the fan speed and running it so that the gas-liquid phase fluid circulates in the main pipeline, and cooling it through the cold storage temperature control system to stabilize the fluid temperature, pressure and flow rate in the main pipeline; (4) generating hydrates: cooling the main pipeline through the cold storage temperature control system to stabilize the fluid temperature, pressure and flow rate; Generate hydrates, lower the temperature of the fluid in the main pipeline to the hydrate generation temperature and then keep the temperature constant. Under the action of the nucleation driving force, hydrates begin to nucleate and grow in the main pipeline, and the data acquisition system continuously records the temperature, pressure, flow, pressure difference parameters and video images; (5) Hydrate decomposition: increase the temperature through the cold storage temperature control system to decompose the hydrates and discharge the gas and liquid in the main pipeline; (6) Cleaning and purging: inject pure water into the main pipeline through the liquid injection system to clean the main pipeline. After cleaning, continuously inject nitrogen into the main pipeline through the gas supply system to purge and discharge the residual water in the main pipeline. After the purge is completed, the next experiment can be carried out.
[0010] The present invention has the following beneficial effects: the present invention designs and establishes a set of gas phase loops for research related to hydrate technology under gas phase dominant flow systems, involving research on the generation, deposition, and blockage of hydrates under simulated actual production and transportation conditions of gas fields, and research on inhibitor effect testing. Specifically, a specific high-pressure fan is used to rotate and drive the gas-liquid-solid three-phase fluid to continuously circulate in the main pipeline, which can not only simulate the flow scene in the gas phase dominant system pipeline during gas field production and transportation, but also simulate long-distance pipeline flow through circulating flow, creating conditions for testing the long-term inhibition effect of inhibitors. Therefore, through the system of the present invention, it can be achieved: ① Under the conditions of simulating the actual production and transportation process of gas fields, study the generation, growth, and deposition of hydrates under the gas phase dominant flow system; ② Under the conditions of simulating the actual production and transportation process of gas fields, test the effects of various inhibitors in inhibiting hydrate nucleation and growth; ③ Study the generation, growth, and deposition of hydrates under different reagent solutions, gas-liquid ratios, flow rates, etc.; ④ Observe the gas-liquid-solid three-phase flow state and hydrate growth morphology in the pipeline under different conditions. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 Schematic diagram of the structure of a hydrate loop experimental system in a gas-dominated flow system according to an embodiment of the present invention.
[0012] Figure 2 Schematic diagram of the structure of a high-pressure blower according to an embodiment of the present invention.
[0013] Figure 3 It is a schematic diagram of the induction time of different drugs measured in the examples of the present invention.
[0014] Figure 4 It is a schematic diagram of the gas consumption rate of different agents measured in an embodiment of the present invention. DETAILED DESCRIPTION
[0015] The following is a detailed description of the embodiments of the present invention. It should be emphasized that the following description is only exemplary and is not intended to limit the scope and application of the present invention. In the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other.
[0016] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it can be directly on the other element or indirectly on the other element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element. In addition, connection can be used for fixing as well as for coupling or communication.
[0017] It should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0018] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the embodiments of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0019] In view of the problem that it is difficult to realize the research on hydrate formation and growth in a gas-dominated atmospheric-liquid ratio pipeline flow system in the prior art, and the problem that it is difficult to realize the circulation flow of gas, liquid and solid three phases in a gas-dominated system in a pipeline, a specific embodiment of the present invention provides a hydrate loop experimental system for a gas-dominated flow system, which includes: a main pipeline for circulating fluid therein; a visual pipe section connected to the main pipeline; a video recording system corresponding to the visual pipe section for real-time observation and recording of the flow morphology of the fluid and the formation, deposition and growth morphology of hydrates during the experiment; a high-pressure fan installed below the main pipeline to ensure that the fluid circulates in the main pipeline, wherein the high-pressure fan includes a casing, blades, a transmission shaft, an internal magnet, a motor and an external magnet, and a controller, the casing is connected to the main pipeline, the blades, the transmission shaft and the internal magnet are sealed in the casing, one end of the transmission shaft is connected to the blades, and the other end is connected to the The inner magnet is connected, the motor and the outer magnet are located outside the shell and coupled with the inner magnet, the controller is connected with the motor and the outer magnet, and the motor and the outer magnet are operated by the controller to drive the inner magnet to rotate, thereby driving the transmission shaft to rotate and the fan blades to rotate, driving the fluid in the main pipeline to circulate; the flow meter, temperature sensor and pressure sensor are all installed on the main pipeline, and are used to measure the fluid flow, temperature and pressure in the main pipeline during the experiment; the differential pressure gauge is installed on the main pipeline and located on both sides of the inlet and outlet of the high-pressure fan, and is used to measure the change of pressure difference during the experiment; the cold storage temperature control system is used to control the temperature of the fluid in the main pipeline during the experiment; the gas supply system and the liquid injection system are both connected to the main pipeline, and are used to provide gas and liquid to the main pipeline respectively; the data acquisition system is used to record and save temperature, pressure, flow, pressure difference and video images.
[0020] In a preferred embodiment, the main pipe includes an upper horizontal pipe section, a lower horizontal pipe section, a left vertical pipe section and a right vertical pipe section, and the four pipe sections are connected to form a "U"-shaped main pipe. The main pipe arranged in this way is simple to construct and is more convenient for fluid to circulate in the main pipe.
[0021] In a preferred embodiment, the middle areas of the upper horizontal pipe section and the lower horizontal pipe section are connected with the visual pipe section, and each of the visual pipe sections is provided with a corresponding recording system. The visual pipe section is installed in the middle areas of the upper horizontal pipe section and the lower horizontal pipe section, so as to avoid the influence area of the fluid flow caused by other equipment such as flow meter and pipe section connection joints as much as possible, so that the gas and liquid fluid can develop normally for a distance before entering the observation, reducing the influence of other equipment on the flow observation, and ensuring that the normal flow observation can be carried out through the visual pipe section.
[0022] In a preferred embodiment, the high-pressure blower can operate in an environment containing high-pressure gas, and its maximum tolerable pressure is 4 MPa.
[0023] In a preferred embodiment, the high-pressure fan is installed at the lower right of the main pipeline, at the connection between the lower horizontal pipe section and the right vertical pipe section, and the fluid flows in from the inlet on the left side of the high-pressure fan through the lower horizontal pipe section, and flows out from the outlet on the upper part of the high-pressure fan to the right vertical pipe section driven by the internal blades of the high-pressure fan. The high-pressure fan has a heavy weight, and is installed at the lower right position of the main pipeline, so the high-pressure fan can be directly fixed on the ground, which is relatively stable; at the same time, the gas-liquid mixed fluid flows in from the left side of the high-pressure fan, and flows out from the upper part of the high-pressure fan driven by the internal blades of the high-pressure fan. Since the energy of the fluid just flowing out of the high-pressure fan is the largest, it is easier to climb up through the vertical pipe section and flow out. Therefore, the arrangement position of the high-pressure fan ensures that the fluid can flow through the rising vertical pipe section well, ensuring that it can circulate.
[0024] In a preferred embodiment, the differential pressure gauge is installed between the upper horizontal pipe section and the lower horizontal pipe section; the flow meter, the temperature sensor and the pressure sensor are all installed in the upper horizontal pipe section. The two interfaces of the differential pressure gauge are respectively installed on both sides of the high-pressure blower, so that the flow distance of the fluid in the main pipe is longer, the measured pressure difference value is large, and the difference in pressure difference values under different experimental conditions and the change of pressure difference can be more significantly reflected.
[0025] In a preferred embodiment, the cold storage temperature control system includes an insulated warehouse, a refrigeration system, a control system and a gas alarm system. The main line is placed in the insulated warehouse, the control system and the refrigeration system are connected to control the temperature in the insulated warehouse, and the gas alarm system is connected to the insulated warehouse to monitor the leakage of experimental gas.
[0026] In a preferred embodiment, the gas supply system includes a high-pressure gas cylinder, a booster pump and a solenoid valve. The high-pressure gas cylinder is connected to the left vertical pipe section through the booster pump and the solenoid valve, and is used to inject the boosted high-pressure gas into the main line until the pressure in the main line reaches the target pressure.
[0027] In a preferred embodiment, the liquid injection system includes a variable frequency high-pressure liquid injection pump, a high-pressure solution tank, a first valve and a second valve; wherein the variable frequency high-pressure liquid injection pump is connected to the left vertical pipe section through the first valve, and is used to inject the experimental solution into the main pipe during the experiment and to inject pure water for cleaning into the main pipe after the experiment is completed; the high-pressure solution tank is used to inject the initial solution into the main pipe during the experimental preparation stage, or to replenish pure water and inhibitor solution into the main pipe during the experiment, the upper part of the high-pressure solution tank is connected to the right vertical pipe section to maintain the pressure balance between the high-pressure solution tank and the main pipe, and the lower part of the high-pressure solution tank is connected to the right vertical pipe section through the second valve.
[0028] In a preferred embodiment, it also includes a collecting tank, a vacuum pump, a third valve and a fourth valve. The vacuum pump is connected to the main line through the third valve to extract the air in the main line, and the collecting tank is connected to the main line through the fourth valve to collect waste gas and waste liquid.
[0029] The specific embodiment of the present invention also provides a gas-phase-dominated flow system hydrate loop experimental test method according to the above-mentioned gas-phase-dominated flow system hydrate loop experimental system, which comprises the following steps:
[0030] (1) Liquid injection: injecting the experimental solution into the main pipe through the liquid injection system;
[0031] (2) Gas injection: injecting the experimental gas into the evacuated main pipeline through the gas supply system until the pressure in the main pipeline increases to the target pressure value;
[0032] (3) Stabilizing the initial temperature and flow rate: Turn on the high-pressure fan, set the fan speed and run it, so that the gas-liquid phase fluid circulates in the main pipeline, cools through the cold storage temperature control system, and stabilizes the fluid temperature, pressure and flow rate in the main pipeline;
[0033] (4) Hydrate generation: the cold storage temperature control system is used to reduce the temperature to generate hydrates, the fluid temperature in the main pipeline is reduced to the hydrate generation temperature and then the temperature is kept constant. Under the action of the nucleation driving force, hydrates begin to nucleate and grow in the main pipeline, and the data acquisition system continuously records the temperature, pressure, flow rate, pressure difference parameters and video images;
[0034] (5) Hydrate decomposition: decomposing hydrates by increasing the temperature through the cold storage temperature control system, and discharging the gas and liquid in the main pipeline;
[0035] (6) Cleaning and purging: Pure water is injected into the main line through the liquid injection system to clean the main line. After cleaning, nitrogen is continuously injected into the main line through the gas supply system to purge the main line to discharge the residual water in the main line. After the purging is completed, the next experiment can be carried out.
[0036] In a preferred embodiment, the testing method further comprises step (7):
[0037] (7) Inhibitor effect test: Based on the pressure and temperature data recorded by the data acquisition system, the time point when the pressure begins to drop rapidly due to hydrate formation is determined as the hydrate nucleation time point, and the period from the beginning of entering the hydrate phase equilibrium zone to the nucleation time point is determined as the induction time; the gas consumption is calculated according to the gas state equation PV=ZnRT, and then divided by the hydrate growth time to obtain the gas consumption rate caused by hydrate growth; the inhibitory effect of the hydrate inhibitor is obtained by comparing the induction time and gas consumption rate test results.
[0038] Hereinafter, the present invention is described in more detail.
[0039] See also Figure 1 , the gas phase dominated flow system hydrate loop experimental system includes:
[0040] The main pipe 1 is used for the fluid to circulate therein, and includes an upper horizontal pipe section 101, a lower horizontal pipe section 102, a left vertical pipe section 103 and a right vertical pipe section 104. The four pipe sections are connected to form a "U"-shaped main pipe 1, and the fluid circulates counterclockwise in the main pipe 1. In this example, the main pipe 1 is made of 316L stainless steel with a maximum pressure resistance of 4 MPa. The total volume in the main pipe is 24.9 L, which can realize the flow of the gas-phase-dominated system with an atmospheric-liquid ratio.
[0041] Two visible pipe sections 201 and 202 are installed in the middle area of the upper horizontal pipe section 101 and the lower horizontal pipe section 102. The visible pipe sections 201 and 202 are made of fully visible and transparent organic glass.
[0042] The video recording systems 301 and 302 are respectively matched with the visual tube sections 201 and 202 to observe and record the flow pattern of the fluid and the formation, deposition and growth morphology of hydrates in real time during the experiment.
[0043] High pressure blower 4 can operate in an environment containing high pressure gas, and its maximum pressure is 4MPa. Figure 2, which includes a housing 401, a fan blade 402, a transmission shaft 403, an inner magnet 404, a motor and an outer magnet 405, and a controller 406. The housing 401 is connected to the main pipeline 1, the fan blade 402, the transmission shaft 403, and the inner magnet 404 are all wrapped and sealed by the housing 401 inside the main pipeline 1, the fan blade 402 is located on the path of fluid circulation, one end of the transmission shaft 403 is connected to the fan blade 402, and the other end is connected to the inner magnet 404, the motor and the outer magnet 405 are installed outside the housing 401, coupled with the inner magnet 404, and the controller 406 is connected to the motor and the outer magnet 405. The controller 406 sets the speed to make the motor and the outer magnet 405 installed outside the housing 401 run, drive the inner magnet 404 to rotate, thereby drive the transmission shaft 403 to rotate and make the fan blade 402 rotate, and then drive the fluid inside the main pipeline 1 to circulate. The high-pressure fan 4 is installed at the lower right of the main pipeline 1, at the connection between the lower horizontal pipe section 102 and the right vertical pipe section 104. The fluid flows in from the inlet on the left side of the high-pressure fan 4 through the lower horizontal pipe section 102, and flows out from the upper outlet of the high-pressure fan 4 to the right vertical pipe section 104 driven by the internal fan blades of the high-pressure fan 4. The fan blades inside the high-pressure fan rotate, driving the gas, solution and hydrate particles in the main pipeline to flow along the main pipeline, realizing the circulation of gas, liquid and solid phases. The controller 406 of the high-pressure fan 4 can control the flow rate of the fluid in the main pipeline 1 by setting the rotation speed.
[0044] The flowmeter 5 is a venturi flowmeter, which is installed on the upper horizontal pipe section 101 of the main pipe, and can measure the fluid flow in the main pipe 1. The differential pressure meter 6 is installed between the upper horizontal pipe section 101 and the lower horizontal pipe section 102, and can measure the change of the pressure difference during the experiment. The temperature sensor 7 and the pressure sensor 8 are both installed on the upper horizontal pipe section 101, and are used to measure the temperature and pressure in the main pipe during the experiment.
[0045] The cold storage temperature control system includes an insulated warehouse 9, a refrigeration system 10, a control system 11 and a gas alarm system 12, and also includes an emergency exhaust system and a fresh air system. The main pipeline 1 is placed in a walk-in insulated warehouse 9 as a whole. The temperature of the insulated warehouse is adjusted by setting the control system 11. When the refrigeration system 10 is running, the temperature of the insulated warehouse can be quickly lowered or raised, thereby controlling the temperature of the fluid in the main pipeline 1 during the experiment. The gas alarm system 12 installed in the walk-in insulated warehouse 9 can monitor the leakage of the experimental gas. For example, the gas alarm system 12 can include a combustible gas leak alarm and an oxygen concentration alarm. When the combustible gas leak alarm and the oxygen concentration alarm detect that the combustible gas concentration is too high or the oxygen concentration is too low, an audible and visual alarm is issued, and the emergency exhaust system and the fresh air system are linked to open to suck out the original air in the insulated warehouse 9 and inject fresh air.
[0046] The gas supply system includes a high-pressure gas cylinder 13, a booster pump 14 and a solenoid valve 15. The high-pressure gas cylinder 13 is the experimental gas source and provides gas. The booster pump 14 pressurizes the source gas to a specified pressure, and then opens the solenoid valve 15 to inject the pressurized high-pressure gas into the main line 1 until the pressure in the main line 1 reaches the target pressure. Combined with the pressure sensor 8, the pressure value in the main line is controlled by controlling the opening and closing of the solenoid valve 15.
[0047] The liquid injection system includes a variable frequency high-pressure liquid injection pump 16, a high-pressure solution tank 17, a first valve 23 (a needle valve in this example) and a second valve 18, wherein the variable frequency high-pressure liquid injection pump 16 is connected to the left vertical pipe section 103 through the first valve 23, and is used to inject the experimental solution into the main pipe 1 during the experiment, and to inject the cleaning pure water into the main pipe 1 after the experiment is completed; the high-pressure solution tank 17 is used to inject the initial solution into the main pipe 1 in the experimental preparation stage, or to supplement the main pipe 1 with pure water and inhibitor solution (such as KHI solution) during the experiment. The upper part of the high-pressure solution tank 17 is connected to the right vertical pipe section 104 of the main pipe through the air pipe to keep the pressure of the two balanced. The experimental liquid in the high-pressure solution tank 17 automatically flows downward into the main pipe 1 under the action of gravity. In particular, a high-precision controlled second valve 18 is installed at the connection between the lower part of the high-pressure solution tank 17 and the right vertical pipe section 104 of the main pipe, and the inflow speed of the solution can be accurately controlled by controlling the opening and closing degree of the second valve 18.
[0048] The data acquisition system 19 is used to record and save temperature, pressure, flow, pressure difference and video images.
[0049] The collecting tank 20 is connected to the main pipeline 1 through a fourth valve 24 (a needle valve in this example) for collecting waste gas and waste liquid. In this example, the collecting tank 20 is connected to the lower horizontal pipe section 102 of the main pipeline 1 through the fourth valve 24, and the connection point is located in front of the inlet of the high-pressure fan 4.
[0050] The vacuum pump 21 is connected to the main pipe 1 through a third valve 22 (a needle valve in this example) to extract the air in the main pipe 1. In this example, the vacuum pump 21 is connected to the connection between the upper horizontal pipe section 101 and the left vertical pipe section 103 of the main pipe 1 through the third valve 22.
[0051] Through the above Figure 1 The gas phase dominant flow system hydrate loop experimental system shown, the specific process of the gas phase dominant flow system hydrate loop experimental test method and the inhibitor test method are as follows:
[0052] (1) Injection: Use pure water and PVP (polyvinyl pyrrolidone, purchased from Boai New Open Source Pharmaceutical Co., Ltd.), Inhibex 501 (Inhibex 501 is a trade name, purchased from Ashland), Luvicap EG (Luvicap EG is a trade name purchased from BASF), HY-501 (HY-501 is homemade in the laboratory and is prepared by the following steps: weigh 4 g of monomer vinyl caprolactam and 0.5 g of vinyl acetate, weigh 0.027 g of initiator azobisisobutyronitrile (AIBN), weigh 0.025 g of chain transfer agent 3-mercaptopropionic acid, mix with 18 ml of diethylene glycol butyl ether, and add to a 100 ml three-necked flask. The system is degassed and sealed under nitrogen protection. Turn on condensation water and magnetic stirring, the stirring rate is 300 rpm, and the oil bath is reacted at 80°C for 6 hours, and the oil bath and stirring are turned off. The final product is obtained when the reaction solution is cooled to room temperature, and it is named HY-501.) Four hydrate inhibitors are respectively prepared with 600 g of experimental solution with a mass concentration of 1%, and placed in a high-pressure solution tank 17, and the high-precision controlled second valve 18 is opened to allow the experimental solution to flow into the main pipeline 1 under the action of gravity, and then the second valve 18 is closed;
[0053] (2) Gas injection: Open the third valve 22, run the vacuum pump 21 to extract the air in the main pipeline 1, and after the vacuum is exhausted, close the third valve 22, then open the high-pressure gas cylinder 13, start the booster pump 14, pressurize the gas flowing out of the high-pressure gas cylinder 13, open the solenoid valve 15, and inject the experimental gas into the main pipeline 1. After the pressure in the main pipeline 1 increases to the target pressure value, close the solenoid valve 15;
[0054] (3) Stabilize the initial temperature and flow rate: Turn on the high-pressure fan 4, set the fan speed and run it, let the gas-liquid phase fluid circulate in the main line 1, set the initial temperature of the insulation warehouse 9 to 20 °C through the control system 11, and start cooling the refrigeration system 10. When the fluid temperature, pressure and flow rate in the main line 1 are all stable, the initial stabilization stage ends;
[0055] (4) Hydrate formation: The temperature of the heat preservation chamber 9 is set by the control system 11, and the temperature is lowered to generate hydrates. The fluid temperature in the main pipe 1 is lowered to 1.9°C and then kept constant. At this time, the pressure is about 2.316 MPa. Under the action of the nucleation driving force, hydrates begin to nucleate and grow in the main pipe 1. The data acquisition system 19 continuously records the temperature, pressure, flow rate, pressure difference parameters and video images. Starting from the initial temperature of 20°C, the total duration of the experiment is 25.5 hours;
[0056] (5) Hydrate decomposition: After the hydrate formation experiment is completed, the cold storage temperature is set by the control system 11, and the temperature is increased to decompose the hydrate. After the hydrate is completely decomposed, the high-pressure blower 4 is turned off, and the fourth valve 24 is opened to discharge the gas and liquid in the main pipeline 1 to the collection tank 20;
[0057] (6) Cleaning and purging: Open the first valve 23, use the variable frequency high pressure injection pump 16, continuously inject pure water into the main line 1, clean the main line 1, and continuously discharge the waste liquid into the collection tank 20. After continuously injecting pure water to clean the main line 1, turn off the variable frequency high pressure injection pump 16, close the first valve 23, and then open the solenoid valve 15, and continuously inject nitrogen into the main line 1 for purging to discharge the residual water inside. After the purging is completed, the next experiment can be started;
[0058] (7) Data processing and analysis: During the experiment, when hydrates are generated, gas will be consumed, resulting in a decrease in pressure. Therefore, the time point of hydrate nucleation can be determined based on the time point when the pressure begins to drop rapidly. The period from the beginning of entering the hydrate phase equilibrium zone to the nucleation time point is determined as the induction time. According to the temperature and pressure data recorded during the experiment, the gas consumption can be calculated according to the gas state equation PV=ZnRT, and then divided by the hydrate growth time to obtain the gas consumption rate caused by hydrate growth. In order to reduce the impact of experimental randomness, the above steps are repeated to obtain multiple induction times and gas consumption rates of an inhibitor under the same conditions. The average induction time and average gas consumption rate can be obtained by averaging them. By changing the type of inhibitor and conducting multiple experiments, the average induction time and average gas consumption rate of different inhibitors can be obtained.
[0059] (8) Evaluation of inhibitor effect: By comparing the induction time (e.g. Figure 3 ), and the gas consumption rate (as Figure 4 As shown), the inhibitory effect of the hydrate inhibitor can be evaluated. The longer the induction time, the smaller the gas consumption rate, indicating that the effect of the hydrate inhibitor is better. In this example, the induction time and gas consumption rate of pure water and four inhibitors at 10°C supercooling were tested using the system of the present invention. The results showed that HY-501 had the best inhibitory effect and PVP had the worst inhibitory effect. In addition, by analyzing the recorded video images, it can be observed that after adding the inhibitor, the flow state of the gas-liquid phase fluid in the main pipeline 1 and the morphology of hydrate formation and deposition in the main pipeline 1 are affected.
[0060] In other embodiments, the diameter, length and other dimensions of the main pipeline may be changed, the horizontal, vertical, tilt angle and other layouts of different pipe sections of the main pipeline may be changed, and the main pipeline may be completely changed to a fully visible transparent pipe section.
[0061] In other embodiments, the injection method of the reagent solution and gas can be changed; condensate oil is added to the liquid phase to change the gas phase to dominate the oil-water-gas three-phase flow; the gas-liquid ratio, rotation speed, temperature, and pressure can be changed; the type and concentration of the reagent can be changed.
[0062] The system of the present invention can also be used for research related to hydrate promoters in gas-phase-dominated systems, including research on hydrate-based gas storage, hydrate-based gas separation, hydrate-based carbon dioxide capture, etc.
[0063] The above content is a further detailed description of the present invention in combination with specific / preferred embodiments, and it cannot be determined that the specific implementation of the present invention is limited to these descriptions. For ordinary technicians in the technical field to which the present invention belongs, without departing from the concept of the present invention, it can also make several substitutions or modifications to these described embodiments, and these substitutions or modifications should be regarded as belonging to the protection scope of the present invention. In the description of this specification, the description of the reference terms "an embodiment", "some embodiments", "preferred embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in combination with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily target the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner. In the absence of mutual contradiction, those skilled in the art can combine and combine the different embodiments or examples described in this specification and the features of different embodiments or examples. Although the embodiments of the present invention and their advantages have been described in detail, it should be understood that various changes, substitutions and modifications can be made herein without departing from the scope of protection of the patent application.
Claims
1. A hydrate loop experimental system with gas-dominated flow system, It is characterized in that include: A main pipe, for fluid to circulate therein, the main pipe comprising an upper horizontal pipe section, a lower horizontal pipe section, a left vertical pipe section and a right vertical pipe section, the four pipe sections being connected to form a "U"-shaped main pipe; A visible pipe section connected to the main pipe; A video recording system, corresponding to the visual tube section, is used to observe and record in real time the flow pattern of the fluid and the formation, deposition and growth morphology of hydrates during the experiment; A high-pressure fan is installed below the main pipeline and is used to ensure that the fluid circulates in the main pipeline, wherein the high-pressure fan includes a shell, a fan blade, a transmission shaft, an inner magnet, a motor and an outer magnet, and a controller, the shell is connected to the main pipeline, the fan blade, the transmission shaft and the inner magnet are sealed in the shell, one end of the transmission shaft is connected to the fan blade, and the other end is connected to the inner magnet, the motor and the outer magnet are located outside the shell and coupled to the inner magnet, the controller is connected to the motor and the outer magnet, the motor and the outer magnet are operated by the controller, the inner magnet is driven to rotate, thereby driving the transmission shaft to rotate and the fan blade to rotate, driving the fluid in the main pipeline to circulate; A flow meter, a temperature sensor and a pressure sensor are all installed on the main pipe and are used to measure the fluid flow, temperature and pressure in the main pipe during the experiment; A differential pressure gauge is installed on the main pipe and located on both sides of the inlet and outlet of the high-pressure blower to measure the change of the differential pressure during the experiment; A cold storage temperature control system, used to control the temperature of the fluid in the main pipeline during the experiment; A gas supply system and a liquid injection system are both connected to the main pipeline, and are used to provide gas and liquid into the main pipeline respectively; the liquid injection system includes a variable frequency high-pressure liquid injection pump, a high-pressure solution tank, a first valve and a second valve; wherein the variable frequency high-pressure liquid injection pump is connected to the left vertical pipe section through the first valve, and is used to inject the experimental solution into the main pipeline during the experiment and to inject pure water for cleaning into the main pipeline after the experiment is completed; the high-pressure solution tank is used to inject the initial solution into the main pipeline during the experimental preparation stage, or to supplement the pure water and inhibitor solution into the main pipeline during the experiment, the upper part of the high-pressure solution tank is connected to the right vertical pipe section to keep the pressure of the high-pressure solution tank and the main pipeline balanced, and the lower part of the high-pressure solution tank is connected to the right vertical pipe section through the second valve; The data acquisition system is used to record and save temperature, pressure, flow, pressure difference and video images.
2. The gas-phase dominant flow system hydrate loop experimental system according to claim 1, It is characterized in that The visible pipe sections are connected to the middle areas of the upper horizontal pipe section and the lower horizontal pipe section, and each visible pipe section is provided with a corresponding recording system; the differential pressure gauge is installed between the upper horizontal pipe section and the lower horizontal pipe section; the flow meter, the temperature sensor and the pressure sensor are all installed in the upper horizontal pipe section.
3. The gas-phase dominant flow system hydrate loop experimental system according to claim 1, It is characterized in that The high-pressure fan is installed at the lower right side of the main pipeline, located at the connection between the lower horizontal pipe section and the right vertical pipe section. The fluid flows into the inlet on the left side of the high-pressure fan through the lower horizontal pipe section, and driven by the fan blades inside the high-pressure fan, flows out from the upper outlet of the high-pressure fan to the right vertical pipe section.
4. The gas-phase dominant flow system hydrate loop experimental system according to claim 1, It is characterized in that The cold storage temperature control system includes an insulated warehouse, a refrigeration system, a control system and a gas alarm system. The main pipeline is placed in the insulated warehouse. The control system and the refrigeration system are connected to control the temperature in the insulated warehouse. The gas alarm system is connected to the insulated warehouse to monitor the leakage of experimental gas.
5. The gas-phase dominant flow system hydrate loop experimental system according to claim 1, It is characterized in that The gas supply system includes a high-pressure gas cylinder, a booster pump and a solenoid valve. The high-pressure gas cylinder is connected to the left vertical pipe section through the booster pump and the solenoid valve, and is used to inject the boosted high-pressure gas into the main pipeline until the pressure in the main pipeline reaches the target pressure.
6. The gas-phase dominant flow system hydrate loop experimental system according to claim 1, It is characterized in that It also includes a collecting tank, a vacuum pump, a third valve and a fourth valve. The vacuum pump is connected to the main pipeline through the third valve to extract the air in the main pipeline, and the collecting tank is connected to the main pipeline through the fourth valve to collect waste gas and waste liquid.
7. A method for testing a hydrate loop experiment in a gas-phase-dominated flow system according to any one of claims 1 to 6, It is characterized in that The steps include: (1) Liquid injection: injecting the experimental solution into the main pipe through the liquid injection system; (2) Gas injection: injecting the experimental gas into the evacuated main pipeline through the gas supply system until the pressure in the main pipeline increases to the target pressure value; (3) Stabilizing the initial temperature and flow rate: Turn on the high-pressure fan, set the fan speed and run it, so that the gas-liquid phase fluid circulates in the main pipeline, cools through the cold storage temperature control system, and stabilizes the fluid temperature, pressure and flow rate in the main pipeline; (4) Hydrate generation: the cold storage temperature control system is used to reduce the temperature to generate hydrates, the fluid temperature in the main pipeline is reduced to the hydrate generation temperature and then the temperature is kept constant. Under the action of the nucleation driving force, hydrates begin to nucleate and grow in the main pipeline, and the data acquisition system continuously records the temperature, pressure, flow rate, pressure difference parameters and video images; (5) Hydrate decomposition: decomposing hydrates by increasing the temperature through the cold storage temperature control system, and discharging the gas and liquid in the main pipeline; (6) Cleaning and purging: Pure water is injected into the main line through the liquid injection system to clean the main line. After cleaning, nitrogen is continuously injected into the main line through the gas supply system to purge the main line to discharge the residual water in the main line. After the purging is completed, the next experiment can be carried out.
8. The hydrate loop experimental test method of the gas-dominated flow system according to claim 7, It is characterized in that Also includes: (7) Inhibitor effect test: Based on the pressure and temperature data recorded by the data acquisition system, the time point when the pressure begins to drop rapidly due to hydrate formation is determined as the hydrate nucleation time point, and the period from the beginning of entering the hydrate phase equilibrium zone to the nucleation time point is determined as the induction time; the gas consumption is calculated according to the gas state equation PV=ZnRT, and then divided by the hydrate growth time to obtain the gas consumption rate caused by hydrate growth; the inhibitory effect of the hydrate inhibitor is obtained by comparing the induction time and gas consumption rate test results.