Method for moving dumping plough

Through modular disassembly and precise installation methods, the problem of relocation and assembly of drainage machines in complex terrain environments is solved, and safe and efficient equipment relocation and assembly is achieved, which is suitable for large-scale mine construction.

CN118877699APending Publication Date: 2024-11-01CHINA COAL BUILDING & INSTALLATION ENG GRP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411141564.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The overall relocation of traditional drainage machines is difficult, unsafe and difficult to ensure installation accuracy in complex terrain environments. Especially when the equipment is large in size and weight, a safer and more reliable disassembly and installation method is needed.

Method used

Modularly disassemble the drain machine into large parts, and lifting, disassembly and combined installation through the collaborative operation of cranes and forklifts, ensuring that each component maintains structural integrity and independence, using precise reference points and reference lines. Measurement and target fixation ensure accuracy and quality during assembly.

Benefits of technology

It realizes the safe and reliable relocation and high-precision assembly of the drainage machine, reduces project volume and investment, improves component utilization efficiency, has the advantages of energy saving and carbon reduction and strong operability, and is suitable for large-scale mine construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118877699A_ABST
    Figure CN118877699A_ABST
Patent Text Reader

Abstract

The invention discloses a dumping plough moving method, and belongs to the field of transportation devices. The dumping plough moving method comprises the following steps that preparation is conducted before the dumping plough is dismantled; a crane and a forklift mechanically enter the site and are in place according to site regulations; a steel wire rope of the crane is connected with parts of the dumping plough for hoisting and dismounting; loading and transporting the components; preparing an installation dumping airport; machinery enters the site, and a crane and a forklift are in place according to site requirements; disassembling the components, connecting the steel wire rope of the crane with the components of the dumping plough, and combining and mounting; and debugging the dumping plough. The whole dumping plough is modularly disassembled into large parts, the large parts keep the relative integrity and independence in structural function, modular installation is conducted after moving, and the precision and quality of equipment during reassembly are guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of transport devices, in particular to a method for relocating a soil dumper. Background Art

[0002] With the rapid development of my country's economy, energy demand continues to grow, and the development and utilization of mineral resources are becoming more and more extensive. In the process of mining, a large amount of solid waste, namely soil spoil, is generated. These soil spoils need to be properly treated and disposed of to ensure environmental safety and production efficiency. Traditional soil spoil methods include simple stacking and compaction, but these methods have many problems, such as occupying a large amount of land resources and affecting the surrounding environment.

[0003] As a key equipment in the continuous or semi-continuous mining process of open-pit mines, the soil dumper is at the last link of the equipment system and is used more and more widely. The soil dumper is mainly used in the soil dumping site of open-pit mines. When the stacking space is full, the soil dumper needs to be moved to expand the stacking space of the soil dumper to meet production needs. For soil dumping sites with flat terrain, the soil dumper can be directly moved to the required location as a whole. However, for soil dumping sites with complex terrain, due to the large size and weight of the soil dumper, such as Sandvik's PA200 soil dumper, the equipment is about 30 meters high and weighs 900 tons. It is difficult to relocate the soil dumper as a whole, and the relocation process is unsafe. The method of disassembly and installation is generally adopted. However, the restoration and installation of the soil dumper after the complete disassembly of the entire machine will bring about problems such as large engineering workload and difficulty in grasping installation accuracy. Summary of the invention

[0004] In order to solve the defects of the prior art, the present invention provides a method for relocating a soil dumper, which modularly disassembles the entire soil dumper into large components, and each large component maintains relative integrity and independence in structure and function, and is accurately installed at the destination after relocation.

[0005] The present invention provides the following technical solutions:

[0006] A method for relocating a soil dumper comprises the following steps:

[0007] S1. Preparation before dismantling the soil dumper;

[0008] S2. Cranes and forklifts enter the site and are positioned according to site regulations;

[0009] S3. The steel wire rope of the crane is connected to the parts of the earthmoving machine for lifting and disassembly;

[0010] S4, parts loading and transportation;

[0011] S5. Preparation of the site for installing the earthmover;

[0012] S6. Machinery enters the site, and cranes and forklifts are in place as required on site;

[0013] S7, unload the parts, connect the parts of the earthmoving machine with the steel wire rope of the crane, and assemble and install them;

[0014] S8. Debug the soil dumper;

[0015] In the above S1, the preparation before dismantling the soil dumper includes:

[0016] S11. Debug the soil dumper to check whether it can be used normally, check whether the existing equipment can operate normally, check the parts that affect the normal operation of the equipment, and make statistics for maintenance and parts procurement;

[0017] S12. Clean up the dismantling site; cut off power, wipe and drain oil before dismantling; protect electrical, oxidizable and rust-prone parts;

[0018] In the above S3, disassemble in the following order: electronic control equipment → hydraulic and lubrication pipelines → mast and pitch cylinder → unloading tail car → counterweight arm → receiving arm → unloading arm → tower → slewing platform → chassis;

[0019] The preparation for installing the spoil dump site in the above-mentioned S5 includes:

[0020] S51, site leveling and power box assembly;

[0021] S52. Determine the longitudinal and transverse centerline positions of the component foundation according to the design requirements, determine the reference points and reference lines for component installation according to the component layout drawing and the measurement control network, and measure the plane positions and elevations of all component installations based on the determined reference points and reference lines; set targets for the longitudinal and transverse centerlines and fix them firmly;

[0022] S53, construct the foundation of the earthmoving machine;

[0023] S54. Re-measure or calibrate the center line of the entire foundation according to the center target to determine the center line that meets the engineering quality requirements, and set up a permanent center mark plate, elevation reference point and auxiliary center reference line to control the plane position of component installation;

[0024] In the above-mentioned S7, the components are installed in the following order: chassis → slewing platform → unloading arm → tower → receiving arm → counterweight arm → mast and pitch cylinder → unloading tail car → hydraulic and lubrication pipelines → electronic control equipment.

[0025] Furthermore, in the above S2 and S6, a 70-ton crane, a 130-ton crane and a 200-ton crane are selected, and a forklift is selected as an auxiliary.

[0026] Further, in S7, the slewing platform includes a platform body, side wings and a rotary bearing, and the installation of the platform body and side wings of the slewing platform includes the following steps:

[0027] a1. Make temporary support for the assembly of the rotary platform. Use H250×250 steel to make four 1000mm long legs. Use a 25mm thick steel plate as the bottom plate, lay it on the compacted ground and level it. Place the four legs on the bottom plate and weld them firmly.

[0028] a2. Place the main body of the slewing platform on the upper part of the outriggers and adjust the levelness of the slewing platform;

[0029] a3. Assemble the side wing and the rotating platform, weld the side wing and the rotating platform firmly, and perform non-destructive testing on the weld after welding.

[0030] Furthermore, in the above S8, debugging the soil dumper is specifically as follows: ensuring that each functional unit of the system can start and stop safely and operate normally during no-load and heavy-load trial operation, and at the same time, completing no-load and heavy-load start and stop of the entire soil dumper according to the established procedures under the premise of ensuring safety.

[0031] The present invention has the following beneficial effects:

[0032] (1) The whole soil dumper is modularly disassembled into large components, and after long-distance transportation, modular installation is carried out to ensure the accuracy and quality of the equipment during reassembly;

[0033] (2) The technical solution of the present invention is reasonable, the construction technology is advanced, and the process arrangement is reasonable, which ensures the quality of the project, reduces equipment investment, and improves the utilization efficiency of components;

[0034] (3) Compared with the traditional technology, the present invention has the advantages of energy saving and carbon reduction, safety and reliability, strong operability, etc. With the increasing number of large-scale coal mines and other large mines in my country, the promotion and application prospects of this technology will be very broad. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 A flowchart of the steps of the earthmoving machine relocation method;

[0036] Figure 2 This is a schematic diagram of the tail car for lifting and unloading;

[0037] Figure 3 It is a schematic diagram of hoisting counterweight arm;

[0038] Figure 4 This is a schematic diagram of the lifting receiving arm.

[0039] Among them, 1. 70-ton crane; 2. 130-ton crane; 3. 200-ton crane; 4. unloading tail car; 5. counterweight arm; 6. receiving arm. DETAILED DESCRIPTION

[0040] In order to make the technical problems, technical solutions and advantages to be solved by the present invention more clear, the following will be described in conjunction with the accompanying drawings. Figures 1 to 4 The technical solutions of the present invention are clearly and completely described in the accompanying drawings and specific embodiments. Obviously, the described embodiments are only some embodiments of the present invention, rather than all embodiments. The components of the embodiments of the present invention generally described and shown in the drawings herein can be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without making creative efforts belong to the scope of protection of the present invention.

[0041] The embodiment of the present invention is described by taking the relocation of a PA200 soil spreader of Sandvik Company as an example. The relocation of other soil spreaders may also adopt the soil spreader relocation method of the embodiment of the present invention.

[0042] An embodiment of the present invention provides a method for relocating a soil dumper, comprising the following steps:

[0043] S1. Preparation before dismantling the soil dumper;

[0044] S2. Cranes and forklifts enter the site and are positioned according to site regulations;

[0045] S3. The steel wire rope of the crane is connected to the parts of the earthmoving machine for lifting and disassembly;

[0046] S4, parts loading and transportation;

[0047] S5. Preparation of the site for installing the earth dump;

[0048] S6. Machinery enters the site, and cranes and forklifts are in place as required on site;

[0049] S7, unload the parts, connect the parts of the earthmoving machine with the steel wire rope of the crane, and assemble and install them;

[0050] S8. Debug the soil dumper.

[0051] In the above S1, the preparation before dismantling the soil dumper includes:

[0052] S11. Debug the soil dumper to check whether it can be used normally, check whether the existing equipment can operate normally, check the parts that affect the normal operation of the equipment, and make statistics for maintenance and parts procurement;

[0053] S12. Clean up the disassembly site; cut off power, wipe and drain oil before disassembly; protect electrical, oxidizable and rust-prone parts.

[0054] In the above-mentioned S2 and S6, a 70-ton crane 1, a 130-ton crane 2 and a 200-ton crane 3 are selected, and a forklift is selected as an auxiliary.

[0055] The parts to be removed and installed are shown in the following table:

[0056] Serial number Part Name Monomer mass (tons) quantity 1 Electronic control equipment 1 2 Hydraulic and lubrication lines 1 3 Mast and Luffing Cylinders 1 4 Unloading tail car 52.6 1 5 Counterweight arm 45 1 6 Receiving arm 70 1 7 Discharge arm 55 1 8 Tower 45 1 9 Rotating platform 36 1 10 Chassis 1

[0057] In the above S4, disassembly is carried out in the following order: electronic control equipment → hydraulic and lubrication pipelines → mast and pitch cylinder → unloading tail car 4 → counterweight arm 5 → receiving arm 6 → unloading arm → tower → rotating platform → chassis.

[0058] Specifically, the relevant dimensions of the components should be measured before hoisting, and compared with the basic dimensions for confirmation. Understand the weight and center of gravity of the components, correctly select the wire rope and hoisting position to ensure the hoisting balance and horizontal stability of the components, and protect the parts that may be damaged in the hanging parts to prevent damage to the components. The entire earthmoving machine is modularly disassembled into large components, and each large component maintains relative integrity and independence in terms of structure and function to ensure the accuracy and quality of the equipment when it is reassembled.

[0059] Specifically, during the component disassembly process, the weight of each component is recorded based on the data provided by the crane. After the disassembly is completed, the component is packaged according to the type, weight and size for easy loading.

[0060] During the disassembly process, the direction of the parts' loosening, thickness end, and size must be clearly identified; the disassembled parts must be placed in order and in a regular manner to avoid clutter and accumulation; the disassembled parts should be connected together according to the original structure as much as possible. All parts must be marked (stamped with letters or markers, spray-painted) to avoid errors during assembly that affect their original matching properties.

[0061] Specifically, when disassembling precision or complex parts, draw assembly sketches or mark them during disassembly to avoid misassembly. After disassembling, parts should be thoroughly cleaned, oiled to prevent rust, and the processed surfaces should be protected to avoid loss and damage. Long and thin parts should be hung to prevent bending and deformation. Precision parts should be stored separately to avoid damage. Small parts should be packed in time to prevent loss.

[0062] Among them, the disassembly of electric control equipment: after marking the electrical, instrument and cable heads, the electrical parts that need to be disassembled are disassembled and stored in categories. Small electrical equipment is disassembled manually, and larger electrical equipment (such as motors, transformers, cable drums, etc.) is disassembled with the help of a crane. Before disassembling the electrical equipment, ensure that the high-voltage cables have been discharged, and arrange electricians to test the cabinets, cables, etc. Confirm that the power supply is cut off.

[0063] Among them, the disassembly of hydraulic and lubrication pipelines: after draining the engine oil and removing the oil pan. When disassembling the hydraulic and lubrication pipelines, the flanged parts are directly disassembled. When installing new pipelines, add 1mm asbestos sheets between the flanges, or use white silk to plug about 30mm into the old pipelines to prevent dirt from falling into the new pipelines and polluting the pipelines; the parts without flanges or live joints are cut by mechanical saws, and white silk is plugged into the pipes after sawing. After the pipe bevel is completed, the inside of the pipe is cleaned, and then the joints and pipelines are installed. The hoses at all moving points are disassembled according to the loading requirements.

[0064] Among them, the mast and pitch cylinder are disassembled: the ladder, operating platform and wire rope on the upper part of the mast are not disassembled, first disassemble the connecting pins between the hydraulic cylinder, tower and mast, disassemble the cylinder to the ground, use a crane to hang the lifting point at the head end of the mast steel structure support to cooperate with the disassembly of the pin connecting the mast and the unloading arm, and finally hoist the mast to the ground.

[0065] Among them, the disassembly of the unloading tail car 4: the unloading tail car 4 is divided into a walking mechanism, a frame steel structure, an operating platform, rollers and rollers and other components, and is disassembled in a top-down order. The disassembly order of the unloading tail car 4 is: platform, rollers, rollers, chute, distribution room → hydraulic, lubrication pipelines → frame steel structure → track.

[0066] Analysis of the unloading tail car 4: The unloading tail car 4 is hoisted in three parts, and the weights of the three parts are approximately 8.6 tons, 30 tons and 14 tons respectively.

[0067] Analysis of the 430-ton portion of the unloading tail car:

[0068] The weight of this part was checked. The lifting height of this part was 8.6 meters and the weight was Q = 30 tons.

[0069] Q 总 =(Q+q)×K 1 =(30+0.1)×1.2=36.12 tons;

[0070] K 1 ——The dynamic load coefficient is 1.2;

[0071] q——The weight of the sling is about 0.1 ton;

[0072] Due to the large size of the components, a 130-ton crane 2 is selected for lifting. The analysis is as follows: the 130-ton crane 2 has a boom of 25.42m and an operating radius of 10m. The rated lifting weight is 43 tons, which meets the lifting requirements. Similarly, other parts of the unloading trolley meet the lifting requirements. Figure 2 shown.

[0073] Among them, the disassembly of the counterweight arm 5: first hoist the hydraulic station, lubrication station, power distribution room and counterweight block of the counterweight arm 5 to the ground respectively, then remove the connecting axle pin between the tail of the counterweight arm 5 and the top of the tower, remove the tie rod, and finally disassemble the counterweight arm 5. The weight of the power distribution room and the counterweight block is less than 10 tons, and the use of a 70-ton crane 1 for installation during disassembly also meets the hoisting requirements.

[0074] Analysis of counterweight arm 5:

[0075] The weight of this part was checked. The lifting height of this part was 15 meters and the weight was Q = 45 tons.

[0076] Q 总 =(Q+q)×K 1 =(45+0.1)×1.2=54.12 tons;

[0077] K 1 ——The dynamic load coefficient is 1.2;

[0078] q——The weight of the sling is about 0.1 ton.

[0079] Due to the large size of the parts, a 130-ton crane 2 and a 70-ton crane 1 are selected for lifting. The analysis is as follows: the 130-ton crane 2 has a boom of 25.42m and an operating radius of 12m, while the 70-ton crane 1 has a boom of 18.77m and an operating radius of 10m. The rated lifting weights are 37.5 tons and 12 tons respectively, which meet the lifting requirements. Figure 3 shown.

[0080] Among them, the disassembly of the receiving arm 6 and the unloading arm: the structure and disassembly process of the receiving arm 6 and the unloading arm are basically the same. The main working parts of the receiving arm 6 and the unloading arm are belt conveyors. First, dismantle the belt conveyor, then lift the unloading arm as a whole, slowly dismantle and hoist it to the bracket on the ground, then disassemble it on the ground, and load it on the truck for transportation in time. During the process, keep the center of gravity of the equipment basically at the center of the equipment without deviation to prevent it from tipping over and decomposing on the ground. First, remove the belts of the receiving arm 6 and the unloading arm. The disassembly procedure is: test electricity → loosen and tighten → cut the tape → remove the belt → remove the belt roller → roller frame → intermediate frame → remove the tail roller, tail frame / head frame, and drive. Analysis of the unloading arm: The unloading arm is hoisted in two parts during installation, one of which weighs about 37 tons and the other weighs about 18 tons. The disassembly is also planned to be disassembled in two parts.

[0081] Analysis of the 37-ton section of the unloading arm:

[0082] The weight of this part was checked and it was known from the equipment list that the height of this part was 8.7 meters and the weight was Q = 37 tons.

[0083] Q 总 =(Q+q)×K1 =(37+0.1)×1.2=44.52 tons;

[0084] K 1 ——The dynamic load coefficient is 1.2;

[0085] q——The weight of the sling is about 0.1 ton.

[0086] Due to the large size of the parts, a 130-ton crane and a 70-ton crane 1 are selected for lifting. The analysis is as follows: the total arm length of the 130-ton crane 2 is 21.28m, and the operating radius is 14 meters. The total arm length of the 70-ton crane 1 is 18.77m, and the operating radius is 8m. The rated lifting weights are 29.3 tons and 21 tons respectively, which meet the lifting requirements. Similarly, the other 18-ton parts also meet the requirements, so these two cranes can meet the requirements for the lifting of the unloading arm.

[0087] The receiving arm 6 is disassembled and hoisted as a whole, and the receiving arm 6 is analyzed:

[0088] The weight of this part was checked. The lifting height of this part was 12.2 meters and the weight was Q = 70 tons.

[0089] Q 总 =(Q+q)×K 1 =(70+0.1)×1.2=84.12 tons;

[0090] K 1 ——The dynamic load coefficient is 1.2;

[0091] q——The weight of the sling is about 0.1 ton.

[0092] Due to the large size of the components, a 70-ton crane 1, a 130-ton crane 2 and a 200-ton crane 3 are selected for lifting. The analysis is as follows: the 200-ton crane 3 has a boom of 21.9m and an operating radius of 10m, and the 130-ton crane 2 has a boom of 25.42m and an operating radius of 12m. When the 70-ton crane 1 assists in lifting, the rated lifting weights are 59 tons and 37.5 tons respectively, which meet the lifting requirements. The lifting diagram is as follows Figure 4 shown.

[0093] Among them, the disassembly of the tower and the slewing platform: This part consists of 7 parts, and each part is disassembled in a top-down order. The tower consists of 4 parts, which are connected by welding. They are divided according to the original welds, cut a section, hoist a section, then dismantle the wing, and finally dismantle the slewing platform. The slewing platform is mainly equipped with a slewing bearing, and special attention must be paid to the removal of the slewing bearing. Lock the slewing platform with a wire rope sling and slowly dismantle and hoist the slewing platform to the designated position.

[0094] The tower is hoisted and dismantled as a whole, and the tower is analyzed:

[0095] The weight of this part was checked. The lifting height of this part was 24.7 meters and the weight was Q = 45 tons.

[0096] Q 总 =(Q+q)×K 1 =(45+0.1)×1.2=54.12 tons;

[0097] K 1 ——The dynamic load coefficient is 1.2;

[0098] q——The weight of the sling is about 0.1 ton.

[0099] Due to the large size of the parts, a 200-ton crane 3 and a 130-ton crane 2 are selected for lifting. The analysis is as follows: the 200-ton crane 3 has a boom of 30.5m and an operating radius of 10m, and the rated lifting weight is 59 tons. The 130-ton crane 2 assists in lifting to meet the lifting requirements.

[0100] The overall weight of the rotary platform is 36 tons. Analysis of the rotary platform:

[0101] Q 总 =(Q+q)×K 1 =(36+0.1)×1.2=43.32 tons;

[0102] K 1 ——The dynamic load coefficient is 1.2;

[0103] q——The weight of the sling is about 0.1 ton.

[0104] Due to the large size of the parts, a 130-ton crane 2 is selected for lifting. The analysis is as follows: The 130-ton crane 2 has a boom of 21.28m and an operating radius of 9m. The rated lifting weight is 50 tons, which meets the lifting requirements.

[0105] Among them, the chassis center seat, balance beam, track beams on both sides, tracks and drives are disassembled: the track beam, tracks and drives are disassembled as a whole, first remove the connecting axle pin between the balance beam and the chassis center seat, and hoist the balance beam to the ground, then use a jack to lift up the chassis center seat, remove the pin shaft between the track beam and the chassis center seat, and disassemble the track beams on both sides and hoist them to the ground.

[0106] Among them, the disassembly of the chassis: the main structure of the chassis includes the chassis center seat, balance beam, crawler beams on both sides, crawler tracks and drive. The crawler beam, crawler tracks and drive are disassembled as a whole. First, the connecting shaft pin between the balance beam and the chassis center seat is removed, and the balance beam is hoisted to the ground. Then, the chassis center seat is lifted up with a jack, the pin shaft between the crawler beam and the chassis center seat is removed, and the crawler beams on both sides are disassembled and hoisted to the ground.

[0107] The entire earthmoving machine is modularly disassembled into large components, and each large component maintains relative integrity and independence in structure and function, ensuring the accuracy and quality of the equipment when it is reassembled.

[0108] In the above-mentioned S5, the preparation of the site for installing the spoil dump includes:

[0109] S51, site leveling and power box assembly;

[0110] S52. Determine the longitudinal and transverse centerline positions of the component foundation according to the design requirements, determine the reference points and reference lines for component installation according to the component layout drawing and the measurement control network, and measure the plane positions and elevations of all component installations based on the determined reference points and reference lines; set targets for the longitudinal and transverse centerlines and fix them firmly;

[0111] S53, construct the foundation of the earthmoving machine;

[0112] S54. Re-measure or correct the center line of the entire foundation based on the center target to determine the center line that meets the engineering quality requirements, and set up a permanent center mark plate, elevation reference point and auxiliary center reference line to control the plane position of component installation.

[0113] In the specific S5, the longitudinal and transverse centerline positions of the component foundation are determined according to the design requirements. The foundation is qualified if the deviation is within 20mm. The allowable deviation of the embedded anchor bolt elevation is 20mm, the center distance deviation is 2mm, the center position deviation of the embedded anchor bolt hole is 10mm, the depth deviation is 20mm, and the verticality deviation of the hole wall is not more than 10mm per meter. Due to the high installation accuracy of the units and components in this project, the centerline, elevation, horizontality and verticality of the installed components to the operation line are particularly strict. In order to ensure the installation quality of the entire set of operation line components, before the foundation construction, the longitudinal and transverse centerline targets should be set at both ends of the foundation and fixed firmly to ensure that the deviation of the entire foundation to the operation line is minimized. After the foundation construction is completed, the centerline of the entire foundation should be re-measured or corrected according to the center target to determine the centerline that meets the engineering quality requirements, and set a permanent center mark plate, elevation reference point and auxiliary center reference line to control the plane position of the component installation.

[0114] In order to control the impact of component installation elevation and foundation settlement on component installation accuracy, before component installation, plane elevation reference points should be set based on the elevation control points handed over by the owner or the elevation control points set by civil construction, close to the components and convenient for observation. The number of permanent center mark plates and permanent reference points should not be too many, and the installation reference line of auxiliary components should be set according to the center line of the determined center mark plate. The preparation work for the installation site of the earthmover ensures the accuracy and quality of assembly.

[0115] During the S4 process, the foundation is made and constructed in advance at the destination. In this way, the disassembly, transportation, foundation making and construction of the earthmoving machine do not interfere with each other and can be completed at their own pace, making full use of time. After the parts of the earthmoving machine are transported to the destination, the parts can be directly installed, shortening the entire construction time.

[0116] In the above S7, the component groups are installed in the following order: chassis → rotating platform → unloading arm → tower → receiving arm 6 → counterweight arm 5 → mast and pitch cylinder → unloading tail car 4 → hydraulic and lubrication pipelines → electronic control equipment.

[0117] The earth spreader is generally installed from bottom to top, layer by layer. The plate feeder can be installed simultaneously with other components, but the center of gravity of the equipment must be kept basically in the center of the equipment without deviation. If necessary, support should be made to prevent tipping.

[0118] Among them, the installation of the chassis: the installation order of the main structure of the chassis is: chassis center seat → balance beam → crawler beams on both sides → crawler and drive. Use δ25mm thick steel plate and #25H steel to make 8 support seats with a height of 500mm to ensure that they have sufficient strength to support the door frame. First, hoist the chassis center seat into place. The overall weight of the chassis center seat is 39.6 tons.

[0119] Q 总 =(Q+q)×K 1 =(39.6+0.1)×1.2=47.64 tons;

[0120] K 1 ——The dynamic load coefficient is 1.2;

[0121] q——The weight of the sling is about 0.1 ton.

[0122] Due to the large size of the parts, two 70-ton cranes 1 are selected for lifting. The analysis is as follows: When the 70-ton crane 1 has a boom of 18.77m and an operating radius of 6m, the rated lifting weight of each crane is 28 tons, which meets the lifting requirements.

[0123] Place 4 50-ton hydraulic jacks under the center seat of the chassis. Adjust the horizontality and elevation of the center seat according to the drawing requirements. The elevation is 150mm higher than the actual height to facilitate the installation of the crawler beams on both sides. After the adjustment, place a wooden tread beside each jack to prevent the center seat from tipping over due to jack failure. The balance beam weighs about 11 tons and is 10 meters long. It is hoisted into place by a 70-ton crane 1 and temporarily supported by wooden treads and 2 32-ton hydraulic jacks. Then hoist the crawler beams on both sides into place. The crawler beam weighs 19 tons and is 11 meters long. It is hoisted into place by a 70-ton crane 1. Before installing the balance beam, first install its connecting pin on the gate seat. The pin and the gate seat frame are interference fit. First measure the deviation of the journal and the shaft hole, confirm that the deviation value meets the requirements of the installation manual, and then use the cold installation process for installation.

[0124] Among them, the installation of the slewing platform: The slewing platform includes the platform body (weighing 26 tons), 2 side wings (weighing 5 tons) and the rotating bearing. The installation process is: hoist the platform body to the top of the temporary support → adjust its level → rust removal of the connection parts assembled with the side wings → measurement and laying out → hoisting and assembling the side wings → welding the side wings → cleaning and rust removal of the rotating bearing flange → installing the rotating bearing on the center seat of the chassis → tightening the outer ring bolts → hoisting and positioning the slewing platform → tightening the inner ring bolts. The installation of the platform body and side wings of the slewing platform includes the following steps:

[0125] a1. Make temporary support for the assembly of the rotary platform. Use H250×250 steel to make four 1000mm long legs. Use a 25mm thick steel plate (size: 4m×4m) as the bottom plate, lay it on the compacted ground and level it. Place the four legs on the bottom plate and weld them firmly.

[0126] a2. Place the main body of the slewing platform on the upper part of the outriggers and adjust the levelness of the slewing platform;

[0127] a3. Assemble the two front side wings of the rotary platform with the rotary platform, weld the side wings and the rotary platform firmly, and perform non-destructive testing on the welds after welding to ensure that the welds meet the requirements of the second-level welds.

[0128] The legs and bottom plate are used as auxiliary components for the installation of the platform body and the side wings, which facilitates the installation of the side wings on the platform body and ensures that the side wings are accurately fixed in the platform body.

[0129] The rotary bearing is the main device of the slewing platform. The rotary bearing should be calibrated during installation. The elastic deformation of the rotary bearing should be used for calibration (tools such as screw jacks can be used). It should be measured at least 6 times to ensure that the ovality of the rotary bearing meets the requirements, and then it should be installed. The inner sleeve of the rotary bearing is connected to the lower structure through M30 10.9 grade bolts. In order to ensure that the rotary bearing and the lower structure are well fixed, the bolts are tightened with a hydraulic torque wrench. The tightening sequence is: lightly tighten any bolt → lightly tighten the bolt opposite the bolt diameter → lightly tighten the bolt at 90° to the above bolt, lightly tighten all the subsequent bolts in this order, and then tighten all the bolts to the specified tension in the same steps. The tightening force must meet the requirements. After the rotary bearing is installed, turn the rotary bearing to check whether there is any jamming phenomenon. After passing the inspection, hoist the platform body to the upper part of the rotary bearing. The slewing platform is hoisted as a whole, with a total weight of 36 tons. The crane used is the same as that used when disassembling the slewing platform.

[0130] Among them, the installation of the discharge arm: the main working part of the discharge arm is the belt conveyor, which is a belt corridor that can move and rotate with the earthmoving machine. Its installation process is: temporary support frame production → discharge arm assembly and welding → operating platform installation → roller and drum installation → discharge arm hoisting → accessories installation → drive device installation → belt spreading and vulcanized joints → sweeper installation → belt tensioning. The discharge arm is divided into four sections with a total length of 50m, each section weighs about 60 tons, connected in the middle by high-strength bolts, and connected at both ends by welding. It is assembled in two sections on the ground, and the accessories that can be installed are installed as much as possible. The weight of the two sections of the discharge arm is about 37 tons and 23 tons respectively. The first section of the discharge arm is hoisted by a crane and installed on the revolving platform, and the pre-made first support frame is placed on the lower part of the discharge arm to temporarily support the first section of the discharge arm, and then the second section of the discharge arm is hoisted and docked with the first section, and the second support frame is placed under the second section.

[0131] Among them, the installation of the tower: the tower consists of four parts, each part is connected by welding, and the horizontal assembly method is adopted, which reduces the risk factor of construction and greatly improves the construction efficiency. The tower welding material model should meet the requirements, the welding operation should be carried out strictly in accordance with the requirements of the welding operation instruction, and reasonable welding process measures should be taken. After the welding is completed, non-destructive testing is carried out, and the next process is carried out after the inspection is qualified. The crane used for the tower hoisting is the same as the crane used for the tower dismantling.

[0132] Among them, the installation of the receiving arm 6: the receiving arm 6 is divided into five sections, the tail section is connected by high-strength bolts, and the other four sections are connected by welding. It is 50m long and weighs about 70 tons. The installation process is similar to that of the unloading arm. It is assembled in sections on the ground, and its installable accessories are installed as much as possible.

[0133] The installation of the counterweight arm 5: The counterweight arm 5 is connected to the tower frame by two tie bars and two axle pins, each tie bar is in two sections, the two sections of tie bars are assembled on the ground, and the middle connection part is fixed with a channel steel clamping plate by a channel steel, so as to facilitate the overall hoisting. The crane used for hoisting the counterweight arm 5 is the same as the crane used for disassembling the counterweight arm 5.

[0134] The installation of mast and pitch cylinder: the mast upper ladder and operating platform, and wire rope are assembled on the ground. The length of pitch cylinder is calculated to be 12.8m according to the position of the unloading arm. The cylinder body is extended by temporary hydraulic station. The overall length of the cylinder is measured to be 12.8m. The hydraulic station is closed and the nozzles of the cylinder are sealed. Then the mast is hoisted into place by 70-ton crane 1 and adjusted to a reasonable angle. Another 70-ton crane 1 is used to hoist the cylinder between the top of the tower and the support arm and connect them. Then the four wire ropes at the bottom of the mast are connected to the unloading arm.

[0135] Among them, the installation of the tail car 4: the tail car 4 is divided into a traveling mechanism, a frame steel structure, an operating platform, rollers, rollers and other accessories. The installation adopts a bottom-up order. First, lay an 80m temporary track as the foundation of the tail car 4, and then install the traveling mechanism. There are 8 parts in total, including 4 8-wheelers and 4 4-wheelers. They are installed on the track respectively, and then the frame steel structure is installed on the upper part. Finally, the operating platform, rollers, rollers and chutes are completed. The hoisting of the tail car 4 is the same as the crane when the tail car 4 is disassembled.

[0136] Among them, the installation of hydraulic and lubrication pipelines: the overall pipeline wiring must comply with the relevant drawings. The detailed wiring must be measured and installed according to the actual position on the machine. The installation of various pipelines must be closely coordinated to prevent conflicts between pipes, cable conduits and other installed equipment. Hoses must be used at all moving points. For on-site pipeline wiring, a suitable location must be selected to safely install hangers and supports, and the appearance must be considered. Before cleaning and flushing the pipeline, the original parts in the system that are easily corroded or damaged by the cleaning agent must be disassembled or isolated to prevent the cleaning agent from entering the equipment and affecting its performance. Temporary pipelines must be installed as required to ensure that there is no leakage at the joints during the cleaning process.

[0137] The installation of electric control equipment: first install the cable tray in place according to the original installation position. The installation of electrical and instrumentation is to lay the power cable, control cable and instrument cable from the joint according to the markings and relevant drawings marked during disassembly, and restore the instrument installation to the original position.

[0138] In the above S8, debugging the earthmoving machine is specifically as follows: ensuring that each functional unit of the system can start and stop safely and operate normally during the no-load and heavy-load trial operation, and at the same time, completing the no-load and heavy-load start and stop of the entire component according to the established procedures under the premise of ensuring safety, and completing the relevant test content in this process.

[0139] The machine parts are as follows:

[0140] Serial number Device Name Model Specifications quantity 1 crane 70 tons 2 units 2 crane 130 tons 1 unit 3 crane 200 tons 1 unit 4 Hydraulic jack EXPRC-50 12 5 Hydraulic jack EXPRC-100 8 6 Steel measuring tape 5m 10 7 Ruler 50m 1 8 Manual torque wrench 0-3000N*m 2 9 Hydraulic torque wrench 0-3600N*m 2 10 sleeper several 11 Shaft puller several 12 Bevel cutting machine 1 unit 13 Electric cutting machine 1 unit 14 Bolt loosener several 15 Chain Reversal 2 tons, 5 tons, 10 tons 10 16 Snap ring 20 tons 4 17 Oxygen, acetylene several 18 Steel structure platform support self made 4 19 Suspenders 3 tons, 5 tons, 10 tons 10 each 20 Wire rope buckle 7-point rope, 16 meters 2 pay 21 Alloy ladder 9m 2 22 seat belt 8 pairs

[0141] The embodiment of the present invention provides a method for relocating a soil dismantling machine. According to the structural functions, transportation conditions, weight and other parameters of the components, the entire soil dismantling machine is modularly disassembled into large components. Each large component maintains relative integrity and independence in terms of structure and function. After relocation, modular installation is performed to ensure the accuracy and quality of the equipment when it is reassembled. The amount of engineering work is reduced, the construction efficiency is improved, and the construction safety is guaranteed. The components are heavy and large in size. In order to maintain the balance and precision of the installation, human-machine cooperation and multi-machine collaboration are required during the installation process, and multiple cranes and aerial platforms are used for synchronous and collaborative lifting, thereby ensuring the installation quality and safety of the soil dismantling machine.

[0142] The method for relocating a soil dumper provided by the embodiment of the present invention has the advantages of low environmental pollution and green production. It reduces the input of personnel, shortens the construction period, and all structures and components are protectively disassembled and reused. Compared with traditional technologies, the present invention has the advantages of energy saving and carbon reduction, safety and reliability, and strong operability. With the increasing construction of large coal mines and other large mines in my country, the promotion and application prospects of this technology will be very broad.

[0143] Finally, it should be noted that the above-described embodiments are only specific implementations of the present invention, which are used to illustrate the technical solutions of the present invention, rather than to limit them. The protection scope of the present invention is not limited thereto. Although the present invention is described in detail with reference to the above-described embodiments, ordinary technicians in the field should understand that any technician familiar with the technical field can still modify the technical solutions recorded in the above-described embodiments within the technical scope disclosed by the present invention, or can easily think of changes, or make equivalent replacements for some of the technical features therein; and these modifications, changes or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention. They should all be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.

Claims

1. A method for relocating a soil dumper, characterized in that: The following steps are involved: S1. Preparation before dismantling the soil dumper; S2. Cranes and forklifts enter the site and are positioned according to site regulations; S3. The steel wire rope of the crane is connected to the parts of the earthmoving machine for lifting and disassembly; S4, parts loading and transportation; S5. Preparation of the site for installing the earthmover; S6. Machinery enters the site, and cranes and forklifts are in place as required on site; S7, unload the parts, connect the parts of the earthmoving machine with the steel wire rope of the crane, and assemble and install them; S8. Debug the soil dumper; In the above S1, the preparation before dismantling the soil dumper includes: S11. Debug the soil dumper to check whether it can be used normally, check whether the existing equipment can operate normally, check the parts that affect the normal operation of the equipment, and make statistics for maintenance and parts procurement; S12. Clean up the dismantling site; cut off power, wipe and drain oil before dismantling; protect electrical, oxidizable and rust-prone parts; In the above S3, disassemble in the following order: electronic control equipment → hydraulic and lubrication pipelines → mast and pitch cylinder → unloading tail car (4) → counterweight arm (5) → receiving arm (6) → unloading arm → tower → rotating platform → chassis; The preparation for installing the spoil dump site in the above-mentioned S5 includes: S51, site leveling and power box assembly; S52. Determine the longitudinal and transverse centerline positions of the component foundation according to the design requirements, determine the reference points and reference lines for component installation according to the component layout drawing and the measurement control network, and measure the plane positions and elevations of all component installations based on the determined reference points and reference lines; set targets for the longitudinal and transverse centerlines and fix them firmly; S53, construct the foundation of the earthmoving machine; S54. Re-measure or calibrate the center line of the entire foundation according to the center target to determine the center line that meets the engineering quality requirements, and set up a permanent center mark plate, elevation reference point and auxiliary center reference line to control the plane position of component installation; In the above-mentioned S7, the components are installed in the following order: chassis → rotating platform → unloading arm → tower → receiving arm (6) → counterweight arm (5) → mast and pitch cylinder → unloading tail car (4) → hydraulic and lubrication pipelines → electronic control equipment.

2. The method for relocating a soil dumper according to claim 1, characterized in that: In the above-mentioned S2 and S6, a 70-ton crane (1), a 130-ton crane (2) and a 200-ton crane (3) are selected, and a forklift is selected as an auxiliary.

3. The method for relocating a soil dumper according to claim 1, characterized in that: In S7, the slewing platform includes a platform body, side wings and a rotary bearing, and the installation of the platform body and side wings of the slewing platform includes the following steps: a1. Make temporary support for the assembly of the rotary platform. Use H250×250 steel to make four 1000mm long legs. Use a 25mm thick steel plate as the bottom plate, lay it on the compacted ground and level it. Place the four legs on the bottom plate and weld them firmly. a2. Place the main body of the slewing platform on the upper part of the outriggers and adjust the levelness of the slewing platform; a3. Assemble the side wing and the rotating platform, weld the side wing and the rotating platform firmly, and perform non-destructive testing on the weld after welding.

4. The method for relocating a soil dumper according to claim 1, characterized in that: In the above S8, debugging the soil dumper is specifically as follows: ensuring that each functional unit of the system can start and stop safely and operate normally during no-load and heavy-load trial operation, and completing no-load and heavy-load start and stop of the entire soil dumper according to the established procedures under the premise of ensuring safety.