Protective drainage prefabrication installation construction process for roadbed engineering
By using stone-filled embankments, reverse filter isolation layers, soil-filled roadbeds, inclined retaining walls, drainage channels combined structures and strong ramming and compaction and impact rolling technology in roadbed construction, the poor drainage effect in traditional roadbed construction is solved. and the problem of uneven settlement have achieved rapid settlement and stability improvement in the roadbed, and are suitable for high-fill stone filling roadbeds.
Patent Information
- Application Number
- CN202411256297.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-11-01
AI Technical Summary
Traditional roadbed construction methods have problems such as poor drainage effect, low material utilization, uneven settlement, long construction period and frequent maintenance under high fill roadbeds and complex geological conditions, resulting in poor stability and short service life of the roadbed.
The prefabricated installation and construction technology of protective drainage is adopted, including a stone-filled embankment drainage structure layer composed of stone-filled embankment, reverse filter isolation layer, soil-filled roadbed, inclined retaining wall, and drainage channel. Through strong ramming and compaction and impact rolling technology , reduce uneven settlement of the roadbed, improve filling quality and drainage performance.
It achieves rapid settlement of the roadbed, shortens the construction period, saves materials and energy, improves the stability and service life of the roadbed, and reduces the later maintenance costs. It is suitable for high-fill stone filling roadbeds in mountainous areas.
Smart Images

Figure CN118880698A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of drainage construction, in particular to a protective drainage prefabrication installation construction process for roadbed engineering. Background Art
[0002] Modern transportation projects have increasingly higher requirements for roadbed stability and drainage performance. Traditional roadbed construction methods can no longer meet the needs of fast, efficient and stable construction. Especially under high fill roadbed and complex geological conditions, the shortcomings of traditional construction methods are particularly prominent.
[0003] When the high fill roadbed is constructed entirely of earthwork, surface water has a greater impact on the stability of the embankment, the construction period is relatively long, and the post-construction settlement is large;
[0004] Therefore, in general, traditional construction methods not only have poor drainage effects, low material utilization and uneven settlement, but also have a long construction period, resulting in poor drainage and serious water accumulation, which affects the stability and service life of the roadbed. They also require a large amount of sand, gravel and soil, and may need to be transported from a distance, increasing the project time. The roadbed constructed with traditional technology is prone to uneven settlement, resulting in poor roadbed stability, a long construction period, and the need for frequent maintenance and repair, which increases the cost of later maintenance.
[0005] In summary, it is necessary to propose a prefabricated installation construction process for protective drainage for roadbed projects to solve the above problems. Summary of the invention
[0006] The purpose of the present invention is to provide a prefabricated installation construction process for protective drainage for roadbed engineering to solve the problems raised in the above-mentioned background technology.
[0007] To achieve the above object, the present invention provides the following technical solutions:
[0008] The construction process for prefabrication and installation of protective drainage for roadbed engineering includes the following steps:
[0009] S1. Construction preparation;
[0010] S2. Test section;
[0011] S3. Settlement displacement pile burial;
[0012] S4. Layered filling of stone-filled roadbed;
[0013] S5.Concrete retaining wall construction;
[0014] S6. Construction of flood drainage channel, using retaining wall as side wall on one side of the flood drainage channel, the construction process is the same as step S5;
[0015] S7. Fill the top with stones and compact it;
[0016] S8. Construction of filter layer;
[0017] S9. Layered filling;
[0018] S10. Impact rolling every 3m;
[0019] S11. Strong compaction accelerates settlement. After the roadbed is filled, strong compaction construction is carried out again to accelerate the settlement of the roadbed, shortening the settlement period from 12 months to 6 months. Then the roadbed is repaired and the bending-settlement test is carried out.
[0020] Preferably, the specific implementation process of step S1 is:
[0021] S1.1. Re-survey the traverse and leveling points, and re-survey the original ground after approval by the supervisor;
[0022] S1.2. Lay out the specific locations of the roadbed edge, slope top, slope foot intercepting ditch, and slope protection road on site, and provide fixed protection for all stakes during construction;
[0023] S1.3. Remove the grass, topsoil and debris within the roadbed area manually and mechanically, and remove all tree roots;
[0024] S1.4. The compaction degree of the base shall not be less than 85%. After removing the sediment, the original ground pits, holes and caves shall be backfilled and compacted in layers with qualified fillers. Replacement treatment measures shall be adopted for poor soft soil bases;
[0025] S1.5. The stone materials for the rock-fill embankment shall be medium-hard and hard rocks that are not easily weathered, and the uniaxial saturated compressive strength shall not be less than 40MP;
[0026] S1.6. Use 20cm to 40cm graded stones for mixed filling.
[0027] Preferably, the specific implementation process of step S2 is:
[0028] S2.1. Before construction, a trial paving of the stone-filled embankment shall be carried out on the experimental road section to determine the layered filling thickness, compaction process, and quality control standards of the stone-filled embankment;
[0029] S2.2. Use heavy-duty vibratory rollers of more than 20 tons for layered rolling. The porosity is used as the control index for compaction quality. The construction compaction quality is controlled by the porosity and compaction settlement difference or construction parameters. The average value of compaction settlement difference shall not exceed 5mm, and the standard deviation shall not exceed 3mm.
[0030] S2.3. Organize the test parameter results of the test section and submit them to the supervising engineer for approval as the basis for subsequent stone-fill embankment construction control.
[0031] Preferably, the specific implementation process of step S3 is:
[0032] S3.1. According to the requirements of the specification, high embankments and steep embankments with a slope height of more than 20m are required to be monitored for construction. The monitoring content mainly includes settlement and displacement.
[0033] S3.2. Determine the number of monitoring sections according to the scope of the monitoring section, and set up 3 surface displacement piles and 3 settlement plates in each monitoring section;
[0034] S3.3. The first settlement plate is set at the top of the stone-filled embankment, horizontally located 1m outside the toe of the first-level platform. The second and third settlement plates are set 4m below the top of the road surface. Under normal circumstances, the two settlement plates are located 0.25m away from the edge of the earth shoulder on both sides of the roadbed; if the left side is on a steep slope, the layout of the settlement plates can be appropriately adjusted according to the actual terrain and construction conditions. A total of 3 displacement side piles are set for each section, 0.5m away from the toe of the right roadbed slope, and 1.0m and 6.0m away from the outer edge of the drainage channel.
[0035] Preferably, the specific implementation process of step S4 is:
[0036] S4.1. The thickness of the paving layer of the stone-filled embankment shall not exceed 50 cm. Stones of different sizes ranging from 20 cm to 40 cm shall be used for mixing and filling. The elevation shall be measured by a level meter and 50 cm high limit steel bars shall be set to cross and control the thickness of the stone-filled embankment layer.
[0037] S4.2. The edges of the stone-filled embankment shall be laid with a thickness of 2m and a minimum size of stone blocks not less than 300mm.
[0038] Preferably, the specific implementation process of step S5 is:
[0039] S5.1. The overall design method of concrete retaining wall and flood drainage channel is adopted. The construction process is construction preparation, surveying and setting out, foundation trench excavation, foundation bearing capacity testing, formwork reinforcement, installation of drainage holes, water filter layer, pouring of rubble concrete, removal of formwork and maintenance.
[0040] S5.2. The retaining wall foundation is excavated manually with an excavator. Before foundation construction, a base bearing capacity test is conducted. The formwork is made of glued wood or steel, and vibrated and compacted with an inserted 50-type vibrating rod. φ10cm PVC pipe drainage holes are set alternately every 2m up, down, left and right. A rammed clay anti-seepage layer is set below the lowest drainage hole and within 0.5m below the wall top. A 5% water flow slope is set. The area above the lowest drainage hole is backfilled with permeable materials. The thickness of each layer is 15cm, and the backfill is 30cm.
[0041] S5.3. When the wall concrete reaches more than 70% of the design strength, backfill the retaining wall. Set an expansion joint every 10m along the wall body and the wall height. The joint width is 2cm. Fill the retaining wall with asphalt hemp reinforcement along the three inner and outer sides of the top of the wall. The filling depth is 20cm.
[0042] Preferably, the specific implementation process of step S7 is:
[0043] S7.1. After the stone-filled embankment is completed, it shall be compacted to eliminate the differential deformation between the roadbeds and reduce the uneven settlement of the roadbed;
[0044] S7.2. The unit impact energy of dynamic compaction is proposed to be 3000KN·m / m2, the weight of the compaction hammer is 22t, the bottom surface is circular, the static pressure value of the hammer bottom is 48kPa, and it is determined through on-site compaction test;
[0045] S7.3. The number of tamping times of the tamping point is 6 times, which is determined according to the relationship curve between the number of tamping times and the tamping amount obtained by the on-site tamping test. The average tamping amount of the last two tampings shall not exceed 50 mm, and the total tamping amount shall not be less than 90% of the total tamping amount of the test tamping. The ground around the tamping shall not be too bulging, and there shall be no difficulty in lifting the hammer due to the tamping hammer being too deep. The number of tamping times is 2, and the last tamping time is low-energy tamping. The time interval between the two times is 1 to 2 weeks. The tamping points are arranged in a side triangle. The spacing between the tamping points in the first time is 5 to 7 m. The spacing between the tamping points in each subsequent time can be the same as that in the first time, or can be appropriately reduced.
[0046] S7.4. Based on the preliminarily determined dynamic compaction parameters, propose a dynamic compaction test plan and conduct on-site dynamic compaction tests;
[0047] S7.5. According to different soil conditions, after several weeks of trial compaction, the trial compaction site shall be tested and compared with the test data before compaction to detect the compaction effect and determine the various compaction parameters used in the project. It is prohibited to compact within 5m of the retaining wall and culvert.
[0048] Preferably, the specific implementation process of step S8 is:
[0049] S8.1. After the rock-fill embankment is compacted, a layer of non-woven geotextile and 30 cm thick graded crushed stone are laid on the top of the embankment as a filter isolation layer;
[0050] S8.2. The unit area mass of non-woven geotextile is 350-500g / m2, its elongation is <50%, the holding strength is ≥1600N, the tear strength is ≥800N, the puncture strength is ≥800N, and the CBR bursting strength is ≥3500N.
[0051] Preferably, the specific implementation process of step S9 is:
[0052] S9.1. Take samples of filler materials for testing to determine the optimum moisture content and maximum dry density and submit to the supervising engineer for approval;
[0053] S9.2. Before the formal construction, pave a 200m test section and record the type of compaction equipment, the best combination, the number of rolling passes and rolling speed, the process, the loose thickness and moisture content of the material, and the flatness of the roadbed;
[0054] S9.3. The filling and rolling method is adopted in longitudinal sections and horizontal layers. The loose thickness of each layer of filler shall not exceed 30cm. The thickness shall not be less than 10cm. The filler shall be transported to the construction site by car, spread by bulldozer and rolled by heavy vibratory roller to the specified compaction degree. The particle size of the filler shall be strictly controlled not to exceed 15cm, and the particle size within 30cm of the top of the roadbed shall not exceed 10cm;
[0055] S9.4. The particle size should be controlled outside the construction site. Crushing on the site is strictly prohibited. During the paving process, the coarse and fine particles should be evenly distributed. Large particles should not be concentrated on the slope side. Finer materials should be used for filling within 1m outside. To ensure the compaction of the roadbed edge, the roadbed filling construction width should be overfilled by 30cm on each side. Finally, the slope should be cut according to the slope rate to ensure the stability of the slope. The filling material to be paved on the same day should be rolled on the same day. In the rainy season, timely inspection and removal of water accumulation on the roadbed should be carried out. Temporary drainage facilities should be unobstructed and free of siltation. "Springs" found in the filling section should be completely removed. The bridgehead roadbed should be filled with gravel or crushed stone with good permeability and compacted in layers. The compaction degree requirement is that the heavy compaction degree solid volume ratio should be ≥96% (87%) from the bottom to the top of the roadbed.
[0056] S9.5. According to the requirements of the specification, construction monitoring of high embankments with a slope height of more than 20m shall be carried out, including settlement and displacement.
[0057] Preferably, the specific test process of step S10 is:
[0058] S10.1. Use an impact compactor equipped with a polygonal compaction wheel. During rolling, the potential energy difference between the large and small radii of the polygonal compaction wheel generates concentrated impact energy with the characteristics of seismic wave propagation. With the combined effect of rolling and kneading, the deep layer of the soil is compacted as the shock wave propagates. The effective compaction thickness reaches 1.5m, which has better compaction effect than the existing vibratory compaction machinery. The rolling speed of the impact compactor is twice that of the vibratory compactor.
[0059] S10.2. For the roadbed from the top of the high-filled stone embankment to the bottom of the roadbed, impact rolling shall be used for reinforcement and compaction every 3 m after the roadbed is completed to eliminate differential deformation between roadbeds and reduce uneven settlement of the roadbed;
[0060] S10.3. Use a triangular twin-wheel impact roller with an impact energy of more than 25 kJ, with a net weight of not less than 12 t, a compaction width of not less than 2 × 900 mm, a trailer speed of 10 km / h to 15 km / h, an impact frequency of 60 to 110 times / min, and a round trip to complete a compaction pass, with a compaction width of not less than 4 m;
[0061] S10.4. Before impact rolling, a test section shall be tested. The length of the test section shall not be less than 150m and the width shall not be less than 8m. The elevation shall be measured after 5, 10, 15, 20 and 25 times of impact rolling, and the settlement after every 5 times of impact rolling shall be calculated. If the average settlement is less than 30mm, the impact rolling shall be stopped; if the average settlement is still greater than 30mm, the impact rolling shall be continued. The maximum number of times for roadbed impact rolling is 30 times.
[0062] S10.5. Summarize the data of moisture content and compaction degree of the test section, determine the reasonable number of compaction passes, and use it to guide the construction of the entire roadbed. The length of the impact rolling working surface should be 200 to 500 meters. The impact rolling should be carried out evenly. The overlap length of two adjacent impact rolling sections should not be less than 15 meters. When the impact roller is working, the outer edge of the compaction wheel should maintain a safety distance of not less than 1 meter from the edge of the roadbed to prevent the impact energy from being large and easily damaging the edge of the filling layer. When encountering culverts and retaining walls, the corresponding safety distance must be maintained. Before the reinforcement and compaction of 2m, the roadbed at this elevation is first compacted to the designed compaction degree with a general roller, and then impact rolling is performed after a layer of filler of more than 30cm is loosely spread. When the surface of the filler is dry, water is sprinkled appropriately to prevent the surface from becoming dusty and affecting the energy transmission to the deep layer. When turning, the driver adjusts the turning route so that the impact energy cam point does not repeat the previous landing point to reduce the wave phenomenon. During the impact and compaction process, if the spring phenomenon occurs, the punching is immediately stopped, and the enhanced compaction is performed after digging and drying or other measures are taken;
[0063] S10.6. After impact compaction, the cross slope and flatness of the roadbed shall be restored to facilitate drainage of the roadbed.
[0064] Compared with the prior art, the invention has the following beneficial effects: the drainage structure layer of the stone-filled embankment composed of the stone-filled embankment, the anti-filtration isolation layer, the earth-filled roadbed, the inclined retaining wall, the flood discharge channel and the drainage ditch occupies less space, uses local materials, and adopts strong tamping and impact rolling, so the roadbed compaction effect is good and the economic benefit is remarkable; the stone-filled embankment adopts two-side masonry, the layered filling thickness is large, the construction progress is fast and the drainage performance is good; by performing strong tamping on the top surface of the stone-filled embankment and the top of the roadbed to enhance the pressure, the differential deformation between the roadbeds is eliminated, the uneven settlement of the roadbed is reduced, the quality of the roadbed filling is improved and the purpose of rapid settlement of the roadbed is achieved, which greatly saves the construction period; the overall design of the stone-filled embankment drainage layer, the inclined retaining wall and the flood discharge channel can be adapted to local conditions, use local materials, save materials, be energy-saving, low-carbon and environmentally friendly, the equipment invested in the construction method is simple, the operation is convenient and the process is mature, so the method is suitable for high-filled stone-filled roadbeds in highway engineering, especially for high-filled stone-filled roads in mountainous areas. BRIEF DESCRIPTION OF THE DRAWINGS
[0065] Figure 1 The present invention is a flowchart of the construction process of prefabrication and installation of protective drainage for roadbed engineering. DETAILED DESCRIPTION
[0066] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0067] See also Figure 1 The present invention proposes a prefabricated installation construction process for protective drainage for roadbed engineering, comprising the following steps:
[0068] S1. Construction preparation;
[0069] S2. Test section;
[0070] S3. Settlement displacement pile burial;
[0071] S4. Layered filling of stone-filled roadbed;
[0072] S5.Concrete retaining wall construction;
[0073] S6. Construction of flood drainage channel, using retaining wall as side wall on one side of the flood drainage channel, the construction process is the same as step S5;
[0074] S7. Fill the top with stones and compact it;
[0075] S8. Construction of filter layer;
[0076] S9. Layered filling;
[0077] S10. Impact rolling every 3m;
[0078] S11. Strong compaction accelerates settlement. After the roadbed is filled, strong compaction construction is carried out again to accelerate the settlement of the roadbed, shortening the settlement period from 12 months to 6 months. Then the roadbed is repaired and the bending-settlement test is carried out.
[0079] Example
[0080] See also Figure 1 Based on the above construction technology, in actual application, the process flow of prefabrication and installation of protective drainage for roadbed engineering includes the following steps:
[0081] (1) Construction preparation
[0082] Re-survey the traverse and leveling points, and re-survey the original ground after approval by the supervisor;
[0083] The specific locations of the roadbed edge, slope top, slope foot intercepting ditch, slope protection road, etc. are laid out on site, and all stakes in construction are fixed and protected;
[0084] Manual and mechanical methods are used to remove grass, topsoil and other debris within the roadbed, and all tree roots are dug out;
[0085] The compaction degree of the base shall not be less than 85%. After removing the sediment, the original ground pits, holes, and caves shall be backfilled and compacted in layers with qualified fillers. Poor soft soil bases shall be treated by replacement and other measures;
[0086] The stone materials for the rock-fill embankment shall be medium-hard and hard rocks that are not easily weathered, and the uniaxial saturated compressive strength shall not be less than 40MP;
[0087] In order to ensure the compactness of the embankment, 20cm to 40cm graded stones are used for mixing and filling;
[0088] (2) Test section
[0089] Before construction, a test section of the rock-filled embankment is first paved to determine the layered filling thickness, compaction process, and quality control standards of the rock-filled embankment;
[0090] Use heavy-duty vibratory rollers of more than 20 tons for layered rolling. The porosity is used as the control index of the compaction quality standard. The construction compaction quality is controlled by the porosity and compaction settlement difference or construction parameters. The average value of the compaction settlement difference is not more than 5mm, and the standard deviation is not more than 3mm.
[0091] Arrange the test parameter results of the test section and submit them to the supervision engineer for approval as the basis for subsequent stone-fill embankment construction control;
[0092] 3. Settlement displacement pile burial
[0093] According to the specification requirements, high embankments and steep embankments with a slope height of more than 20m are required to be monitored for construction. The monitoring content mainly includes settlement and displacement.
[0094] The number of monitoring sections is determined according to the scope of the monitoring section, and each monitoring section is equipped with 3 surface displacement piles and 3 settlement plates;
[0095] The first settlement plate is set at the top of the stone-filled embankment, 1m outside the slope foot of the first-level platform. The second and third settlement plates are set 4m below the top of the road surface. Generally, the two settlement plates are located 0.25m away from the edge of the earth shoulder on both sides of the roadbed. If the left side is on a steep slope, the layout of the settlement plates can be adjusted appropriately according to the actual terrain and construction conditions.
[0096] A total of three displacement side piles are set in one section, 0.5m away from the right side of the roadbed slope foot, 1.0m and 6.0m away from the outer edge of the flood discharge channel;
[0097] 4. Layered filling of stone-filled roadbed
[0098] The paving layer thickness of the stone-filled embankment is not more than 50cm. In order to ensure the compactness of the stone-filled embankment, 20cm ~ 40cm stones of different sizes are mixed and filled, and the elevation is measured by leveling instrument and 50cm limit steel bar heads are set to cross and control the thickness of the stone-filled embankment filling layer;
[0099] The quality control standards are shown in Table 1 and Table 2:
[0100] Table 1 Quality control standards for compaction of hard stone
[0101] Roadbed Depth below road surface (m) Paving layer thickness (mm) Maximum particle size (mm) Compacted dry density (kg / m3) Porosity (%) Upper Embankment 1.2~1.9 ≤400 Less than 2 / 3 of layer thickness Determined by experiment ≤23 Lower Embankment >1.9 ≤600 Less than 2 / 3 of layer thickness Determined by experiment ≤25
[0102] Table 2 Quality control standards for compaction of hard stone
[0103] Roadbed Depth below road surface (m) Paving layer thickness (mm) Maximum particle size (mm) Compacted dry density (kg / m3) Porosity (%) Upper Embankment 1.2~1.9 ≤400 Less than 2 / 3 of layer thickness Determined by experiment ≤22 Lower Embankment >1.9 ≤500 Less than 2 / 3 of layer thickness Determined by experiment ≤24
[0104] The edge of the stone-filled embankment is paved with a thickness of 2m and a minimum size of paved stones of no less than 300mm;
[0105] 5Retaining wall construction
[0106] In order to save land and ensure smooth drainage of high fill roadbed in the narrow valley section, the overall design method of concrete retaining wall and flood drainage channel is adopted. The construction process is as follows:
[0107] Construction preparation → measurement and layout → foundation trench excavation → foundation bearing capacity testing → formwork reinforcement → installation of drainage holes → water filter layer → pouring of rubble concrete → removal of formwork → maintenance;
[0108] The retaining wall foundation is excavated manually with an excavator. Before foundation construction, a base bearing capacity test is conducted.
[0109] The formwork is made of glued wood or steel, and is compacted by inserting a 50-type vibrating rod;
[0110] φ10cm PVC pipe drainage holes are set alternately up, down, left and right every 2m;
[0111] A rammed clay anti-seepage layer is set at the bottom of the lowest drainage hole and within 0.5m below the wall top, with a water flow slope of 5%;
[0112] The area above the lowest drainage hole is backfilled with permeable materials, with each layer of fill 15cm thick and 30cm backfilled;
[0113] When the wall concrete reaches more than 70% of the design strength, the retaining wall backfill is carried out. An expansion joint is set every 10m along the wall body and combined with the wall height. The joint width is 2cm. The retaining wall is filled with asphalt hemp tendons along the inner and outer sides of the top of the wall, and the filling depth is 20cm.
[0114] (6) Construction of flood drainage channels
[0115] The retaining wall is used as the side wall on one side of the flood discharge channel, and its construction technology refers to the construction of concrete retaining wall;
[0116] (7) Strong tamping of top filling with stones
[0117] After the stone-filled embankment is completed, it is subjected to strong compaction treatment to eliminate the differential deformation between the roadbeds and reduce the uneven settlement of the roadbed;
[0118] The unit tamping energy of the strong compaction is proposed to be 3000KN·m / m2, the weight of the tamping hammer is 22t, the bottom surface is circular, the static pressure value of the hammer bottom is 48kPa, and it is determined through on-site tamping test;
[0119] The number of tamping times at the tamping point is 6 times, which is determined according to the relationship curve between the number of tamping times and the tamping amount obtained from the on-site tamping test. The average tamping amount of the last two hits is not more than 50mm, and the total tamping amount is not less than 90% of the total tamping amount of the test tamping. The ground around the tamping does not bulge too much, and there is no difficulty in lifting the hammer due to the tamping hammer being too deep.
[0120] Tamping is done twice, and finally one tamping with low energy, with an interval of 1 to 2 weeks between the two times;
[0121] The tamping points are arranged in an equilateral triangle. The spacing between the tamping points in the first pass is 5 to 7 meters. The spacing between the tamping points in subsequent passes can be the same as the first pass or can be appropriately reduced.
[0122] Take good traffic organization and safety measures on site;
[0123] According to the initially determined dynamic compaction parameters, a dynamic compaction test plan is proposed and on-site dynamic compaction tests are carried out;
[0124] According to different soil conditions, after several weeks of test tamping, the test tamping site is tested and compared with the test data before tamping to detect the tamping effect and determine the various tamping parameters used in the project;
[0125] Strong tamping is prohibited within 5m of retaining walls and culverts;
[0126] (8) Filter layer construction
[0127] After the rock-fill embankment is compacted, a layer of non-woven geotextile and 30 cm thick graded crushed stone are laid on the top of the embankment as a filter isolation layer;
[0128] The unit area mass of non-woven geotextile is 350-500g / m2, its elongation is less than 50%, the holding strength is ≥1600N, the tear strength is ≥800N, the puncture strength is ≥800N, and the CBR bursting strength is ≥3500N;
[0129] For the requirements of relevant parameters such as equivalent pore size, permeability coefficient and gradient ratio of geosynthetics of geotextiles, please refer to the Test Code for Geosynthetics for Highway Engineering (JTGE50-2006) and the Test Code for Highway Geotechnical Engineering (JTGE40-2007);
[0130] (9) Layered filling
[0131] Take samples of fillers for testing, determine the optimum moisture content and maximum dry density, and submit to the supervisory engineer for approval;
[0132] Before the formal filling work begins, a 200m test section is paved to record the compaction equipment type, optimal combination, number of rolling passes and rolling speed, process, loose material thickness and moisture content, roadbed flatness, etc.;
[0133] The relevant test results of the test section shall be sorted out and submitted to the supervision engineer for approval and approval, which will serve as the basis for the control of the construction of this type of filler;
[0134] The method of longitudinal segmentation, horizontal layer filling and rolling is adopted;
[0135] The loose thickness of each layer of filler should not exceed 30cm, and the thickness should not be less than 10cm.
[0136] The filler is transported to the construction site by car, spread by bulldozer, and rolled by heavy-duty vibratory roller in layers to the specified compaction degree (operated according to the relevant data obtained from the test section);
[0137] Strictly control the particle size of the filler to no more than 15cm, and the particle size within 30cm of the top of the roadbed to no more than 10cm;
[0138] The particle size is controlled outside the construction site, and crushing on site is strictly prohibited;
[0139] Evenly distribute coarse and fine particles during paving;
[0140] It is forbidden to concentrate large particles on the slope side, and finer materials should be used for filling within 1m outside;
[0141] To ensure the compaction of the roadbed edge, the roadbed filling construction width is overfilled by 30cm on each side, and finally the slope is cut according to the slope rate to ensure the stability of the slope;
[0142] The filling material to be laid on the same day shall be rolled and completed on the same day;
[0143] During the rainy season, timely check and remove water on the roadbed, and ensure that temporary drainage facilities are unobstructed and free of siltation;
[0144] The "spring" found in the filled road section was completely removed;
[0145] The bridgehead roadbed is filled with permeable gravel or crushed stone, compacted in layers, and the compaction degree (solid volume ratio) from the bottom to the top of the roadbed is required to be ≥96% (87%);
[0146] According to the requirements of the specification, the construction monitoring of high embankments with a slope height of more than 20m is carried out, and the monitoring contents include settlement and displacement;
[0147] (10) Impact rolling every 3m
[0148] Impact compaction technology is a construction process that changes the high frequency and low amplitude of vibration compaction into high amplitude and low frequency.
[0149] The impact compactor equipped with polygonal compacting wheels is used. During rolling, the potential energy difference between the large and small radii of the polygonal compacting wheels is used to generate concentrated impact energy with the characteristics of seismic wave propagation. The combined effects of rolling and kneading are used to compact the deep soil layer as the shock wave propagates.
[0150] The effective compaction thickness can reach 1.5m, which has better compaction effect than the existing vibrating compaction machinery, and the rolling speed of the impact compactor is twice that of the vibrating compactor;
[0151] For the embankment from the top of the high-filled stone embankment to the bottom of the roadbed, impact rolling is used to enhance the pressure every 3m after the embankment is completed to eliminate the differential deformation between the embankments and reduce the uneven settlement of the embankment;
[0152] Use a triangular double-wheel impact roller with an impact energy of more than 25 kJ, with a double-wheel net weight of not less than 12t, a compaction width of not less than 2×900mm, a trailer speed of between 10km / h and 15km / h, an impact frequency of 60 to 110 times / min, and a round trip to complete a compaction, with a compaction width of not less than 4m;
[0153] Before the impact rolling is implemented, a test section shall be tested. The length of the test section shall not be less than 150m and the width shall not be less than 8m. The elevation shall be measured after 5, 10, 15, 20 and 25 times of impact rolling, and the settlement after every 5 times of rolling shall be calculated. If the average settlement is less than 30mm, the rolling can be stopped; if the average settlement is still greater than 30mm, the rolling shall continue.
[0154] According to the requirements of the "Technical Guidelines for Highway Impact Rolling Application", the maximum number of times for roadbed impact compaction is 30 times;
[0155] At the same time, the water content, compaction degree and other data of the test section are summarized to determine the reasonable number of compaction passes to guide the construction of the entire roadbed;
[0156] The length of the impact rolling working surface should be 200 to 500 meters. The impact rolling should be carried out evenly, and the overlap length of two adjacent impact rolling sections should not be less than 15 meters.
[0157] When the impact roller is working, the outer edge of the compacting wheel should maintain a safe distance of not less than 1m from the edge of the roadbed to prevent the impact energy from being large and easily damaging the edge of the filling layer;
[0158] When encountering culverts and retaining wall sections, the corresponding safety distance must be ensured. The horizontal safety distance for impact rolling is shown in Table 3;
[0159] Table 3 Horizontal safety distance of impact rolling
[0160] Structure Type Impact horizontal safety distance Structure Type Impact horizontal safety distance U-shaped abutment and culvert passage 5m from abutment wing wall or culvert passage Traverse points, level points, electric poles 10m Other types of abutments 10m Underground pipelines 5m Gravity retaining wall 2m from the inner side of the wall Interchange bridge 10m Buttress (cantilever) retaining wall 2.5m from the inner side of the buttress (supporting wall) building 30m
[0161] Before every 2m reinforcement compaction, the roadbed at the elevation is first compacted to the designed compaction degree using a general roller, and then a layer of filler with a thickness of more than 30cm is loosely spread before impact rolling;
[0162] When the filling surface is dry, sprinkle water appropriately to prevent the surface from becoming dusty and affecting the energy transfer to the deeper layers;
[0163] When turning, the driver adjusts the turning route so that the impact energy cam point does not repeat the previous landing point to reduce the wave phenomenon;
[0164] During the impact pressure replenishment process, if spring phenomenon occurs, stop the stamping immediately;
[0165] After taking measures such as digging, drying and other measures, the pressure can be increased;
[0166] After impact rolling is completed, the cross slope and flatness of the roadbed are restored, which is conducive to roadbed drainage;
[0167] (11) Strong compaction to accelerate settlement
[0168] After the roadbed is filled, strong compaction construction is carried out again to accelerate the settlement of the roadbed, shortening the settlement period from 12 months to 6 months, and then the roadbed is repaired and subjected to bending and settlement tests;
[0169] Materials and Equipment
[0170] Engineering Materials
[0171] The following table only lists the main materials required, which will be determined based on the actual or existing material specifications of the project;
[0172] The main engineering materials are shown in Table 4;
[0173] Table 4 Main engineering materials
[0174] Serial number Material Name Specification Serial number Material Name Specification 1 Stone 20~40cm 6 PVC pipe φ10cm 2 Non-woven geotextile 350~500g / m2 7 Cement, yellow sand P·042.5 / fineness 2.47 3 Graded crushed stone 8 Settling plate 4 Soil-rock mixture Particle size not exceeding 15cm 9 Displacement pile 5 template Glued wood formwork
[0175] Mechanical equipment
[0176] The main mechanical equipment is shown in Table 5;
[0177] Table 5 Main construction machinery and equipment
[0178] Serial number Device Name model quantity Serial number Device Name model quantity 1 Compaction equipment The tamping energy is 3000KN·m / m2 1 6 Deflection test vehicle 1 2 Vibratory roller 20t 2 7 Insert vibrator Type 50 4 3 Pickaxe Machine SY225C-9 1 8 Mixer truck 6m3 3 4 Impact roller Impact energy 25 kJ or more 1 9 Level DZ2 1 5 Total Station TCP402 1 10 ruler 3m 1
[0179] Quality Control
[0180] Quality Control Standards
[0181] 1) The construction method complies with the Technical Specifications for Highway Roadbed Construction (JTGF10-2006);
[0182] 2) The construction method shall comply with the Technical Specification for Strong Compaction Foundation Treatment (CECS279:2010);
[0183] 3) The construction method shall comply with the "Highway Engineering Quality Inspection and Assessment Standard" (JTGF80 / 1-2004);
[0184] 4) The construction method shall comply with the Technical Specifications for Highway Engineering Construction Safety (JTGF90-2015);
[0185] Quality Control Measures
[0186] Strictly control the quality of filler materials. The stone materials for stone embankment should be medium-hard and hard rocks that are not easily weathered, and the particle size should be controlled within 20cm to 40cm.
[0187] The filling material for the earth-fill roadbed is slag mixture with good water stability and low compressibility;
[0188] Control the drop distance;
[0189] Add waste tires as buffers at the corresponding boom of the tamping machine to prevent the tamping hammer from colliding with the boom due to accidental disturbance and causing huge damage; use a paint pen to make clear marks on the waste tires at the designated height to ensure the lifting height;
[0190] Arrange a dedicated person on site to direct the tamping process and instruct the operator to drop the hammer after it rises to the specified height;
[0191] Strictly control the thickness of the paving layer;
[0192] Use a level to measure the elevation and set a 50cm height limit steel bar head to cross and control the thickness of the stone-fill embankment filling layer;
[0193] After the stone-filled embankment is filled to the designed elevation and repaired, its construction quality shall comply with Table 6;
[0194] Table 6 Construction quality standards for rock-fill embankments
[0195] Item Inspection items Specified value or allowable deviation Inspection method and frequency 1 Compaction Comply with the construction technology determined by the test road Construction records Settlement difference ≤ settlement difference determined by test road Level instrument: Detect one section every 40m, and detect 5 to 9 points in each section 2 Vertical elevation (mm) +10,-30 Level instrument: measure 4 sections every 200m 3 Deflection Not greater than the design value one 4 Centerline deviation (mm) 100 Theodolite: 4 points every 200m, plus HY and YH points for curves 5 width Not less than the design value Meter ruler: Measure 4 points every 200m
[0196] Control the compaction quality of wall backs, trenches and corners;
[0197] During the high fill construction process, settlement plates and displacement piles are buried according to the specifications, and regular observations are conducted by designated personnel;
[0198] Safety measures
[0199] During the tamping process, people and vehicles are prohibited from passing through;
[0200] Place warning signs on site and appoint dedicated personnel for command;
[0201] Add waste tires to the boom at the drop distance of the tamping machine as a buffer to prevent the tamping hammer from colliding with the boom directly due to unexpected disturbance, causing huge damage or accidents;
[0202] Carry out settlement and displacement observation of high fill embankments, designate personnel to conduct observation and data analysis according to the specifications, and communicate with supervisors and designers in a timely manner if any abnormality is found, so as to take measures to guide construction;
[0203] Repair canals and build dams, provide mortar protection, and make reasonable layouts to eliminate potential accidents;
[0204] Build unobstructed drainage channels around buildings and production houses, and build roadbed slope protection and flood prevention facilities;
[0205] Prepare emergency plans for flood control, landslides, etc.;
[0206] Environmental measures
[0207] During the construction period, noise, vibration, wastewater, waste gas and solid waste shall be fully controlled, transportation machinery and equipment shall be strictly managed and controlled, and environmental protection work in the construction area shall be done effectively;
[0208] Take measures such as regular watering of major transport access roads and vehicle entrances and exits to reduce dust;
[0209] During construction, the vegetation along the route must be protected and indiscriminate felling is strictly prohibited; waste must be concentrated at designated locations and indiscriminate collection and disposal along the route is strictly prohibited; during construction, the relationship with local residents must be properly handled to create a friendly and peaceful external environment;
[0210] Benefit Analysis
[0211] This method uses strong tamping to enhance the pressure for rock-filled embankments in mountainous areas. It has fast construction speed, good roadbed compaction effect, and significant economic benefits.
[0212] The economic benefits comparison with conventional high fill roadbed construction is shown in Table 7;
[0213] Table 7 Rapid filling construction method for anti-subsidence composite drainage roadbed in mountainous areas (taking 1000m3 as an example)
[0214] Serial number Construction method name Duration Crushing cost (yuan) Relative construction period (days) Roadbed stability Construction cost (yuan) Economic benefit (yuan) 1 Strong tamping and pressure enhancement 0.5 days 2000 -0.5 good 3000 10000 2 Conventional roadbed filling 1 day 5000 0 generally 10000 0
[0215] Project Examples
[0216] The G530 Chaqiao to Niuji first-class highway construction project is located in Dongzhi County, Chizhou City. This section is the first contract section, starting at K0+000 of Taiyangwu Village on the east side of Chaqiao and ending at K16+300 of Longgang Village. The total length of the route is 16.30km. The terrain is low in the north and high in the south, with a height difference of nearly 50m, which is quite different.
[0217] Considering that the high-fill road section of this project is located in a narrow strip between two mountains, the existing surface drainage system will be greatly damaged after the roadbed is filled. In order to ensure smooth drainage of the road boundary after the roadbed is filled, the roadbed subgrade of the high-fill road section is filled with stone embankment as a surface drainage permeable layer;
[0218] Among them, in the section from K17+720 to K18+180, the fill height is between 7 and 30m, and the top surface of the stone-filled embankment is reinforced with strong tamping technology. The roadbed compaction effect is good and the construction period is greatly saved. The construction quality is unanimously recognized by the construction, supervision units and competent departments.
[0219] In summary, the construction process of the present invention adopts the bottom stone-filled embankment as the surface drainage permeable layer, and sets up an inclined retaining wall and a flood discharge channel combined structure, so as to achieve the purpose of less land occupation and economical use of local materials;
[0220] The stone material particle size is discontinuously graded (between 20 and 40 cm to facilitate drainage), and the filling is carried out in layers. The top surface of the stone filling is strongly compacted to increase the pressure to reduce uneven settlement of the roadbed.
[0221] A crushed stone cushion layer + geotextile filter layer is set on the top of the stone-filled embankment, and then the earth roadbed is filled on it. Impact rolling is performed every 3m to achieve the purpose of fast construction progress, compaction, good drainage performance, stable roadbed and economic savings of the high-fill roadbed;
[0222] For high-fill sections with complex geology and weak foundations, the roadbed consolidation period is long, and a settlement stabilization period of 9-12 months is required after the roadbed is completed;
[0223] Carry out strong tamping again on the top surface of the roadbed to accelerate the settlement of the roadbed, shorten the settlement period, shorten the consolidation period, and improve stability;
[0224] The embankment compaction is achieved by using a huge hammer (hammer weight 15-22kN) to freely fall from a height to apply huge impact energy and shock waves to the roadbed, causing great impact stress on the roadbed fill stone, resulting in instantaneous deformation or breakage, pore compression, gas in the filler escaping, particles rearrangement, reducing porosity, increasing density, and eliminating differential deformation between roadbeds.
[0225] The present invention comprises a stone-filled embankment drainage structure layer consisting of a stone-filled embankment, an anti-filtration isolation layer, a soil-filled roadbed, an inclined retaining wall, a flood discharge channel, and a drainage ditch. It occupies a small area, uses local materials, and adopts strong tamping and impact rolling, so the roadbed compaction effect is good and the economic benefit is remarkable. The stone-filled embankment adopts two-side masonry, and the layered filling thickness is large, the construction progress is fast, and the drainage performance is good. By performing strong tamping on the top surface of the stone-filled embankment and the top of the roadbed to enhance the pressure, the differential deformation between the roadbeds is eliminated, the uneven settlement of the roadbed is reduced, the filling quality of the roadbed is improved, and the purpose of rapid settlement of the roadbed is achieved, which greatly saves the construction period. The stone-filled embankment drainage layer and the inclined retaining wall and the flood discharge channel are designed as a whole, which can be adapted to local conditions, use local materials, save materials, and be energy-saving, low-carbon, and environmentally friendly. The equipment invested in the construction method is simple, the operation is convenient, and the process is mature.
[0226] Therefore, it is suitable for high-fill stone-filled roadbeds in highway engineering, especially for high-fill stone-filled roads in mountainous areas.
[0227] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A prefabricated installation construction process for protective drainage for roadbed engineering, characterized in that: The following steps are involved: S1. Construction preparation; S2. Test section; S3. Settlement displacement pile burial; S4. Layered filling of stone-filled roadbed; S5.Concrete retaining wall construction; S6. Construction of flood drainage channel, using retaining wall as side wall on one side of the flood drainage channel, the construction process is the same as step S5; S7. Fill the top with stones and compact it; S8. Construction of filter layer; S9. Layered filling; S10. Impact rolling every 3m; S11. Strong compaction accelerates settlement. After the roadbed is filled, strong compaction construction is carried out again to accelerate the settlement of the roadbed, shortening the settlement period from 12 months to 6 months. Then the roadbed is repaired and the bending-settlement test is carried out.
2. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 1 is characterized in that: The specific implementation process of step S1 is as follows: S1.
1. Re-survey the traverse and leveling points, and re-survey the original ground after approval by the supervisor; S1.
2. Lay out the specific locations of the roadbed edge, slope top, slope foot intercepting ditch, and slope protection road on site, and provide fixed protection for all stakes during construction; S1.
3. Remove the grass, topsoil and debris within the roadbed area manually and mechanically, and remove all tree roots; S1.
4. The compaction degree of the base shall not be less than 85%. After removing the sediment, the original ground pits, holes and caves shall be backfilled and compacted in layers with qualified fillers. Replacement treatment measures shall be adopted for poor soft soil bases; S1.
5. The stone materials for the rock-fill embankment shall be medium-hard and hard rocks that are not easily weathered, and the uniaxial saturated compressive strength shall not be less than 40MP; S1.
6. Use 20cm to 40cm graded stones for mixed filling.
3. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 2 is characterized in that: The specific implementation process of step S2 is: S2.
1. Before construction, a trial paving of the stone-filled embankment shall be carried out on the experimental road section to determine the layered filling thickness, compaction process, and quality control standards of the stone-filled embankment; S2.
2. Use heavy-duty vibratory rollers of more than 20 tons for layered rolling. The porosity is used as the control index for compaction quality. The construction compaction quality is controlled by the porosity and compaction settlement difference or construction parameters. The average value of compaction settlement difference shall not exceed 5mm, and the standard deviation shall not exceed 3mm. S2.
3. Organize the test parameter results of the test section and submit them to the supervising engineer for approval as the basis for subsequent stone-fill embankment construction control.
4. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 3 is characterized in that: The specific implementation process of step S3 is as follows: S3.
1. According to the requirements of the specification, high embankments and steep embankments with a slope height of more than 20m are required to be monitored for construction. The monitoring content mainly includes settlement and displacement. S3.
2. Determine the number of monitoring sections according to the scope of the monitoring section, and set up 3 surface displacement piles and 3 settlement plates in each monitoring section; S3.
3. The first settlement plate is set at the top of the stone-filled embankment, horizontally located 1m outside the toe of the first-level platform. The second and third settlement plates are set 4m below the top of the road surface. Under normal circumstances, the two settlement plates are located 0.25m away from the edge of the earth shoulder on both sides of the roadbed; if the left side is on a steep slope, the layout of the settlement plates can be appropriately adjusted according to the actual terrain and construction conditions. A total of 3 displacement side piles are set for each section, 0.5m away from the toe of the right roadbed slope, and 1.0m and 6.0m away from the outer edge of the drainage channel.
5. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 4 is characterized in that: The specific implementation process of step S4 is as follows: S4.
1. The thickness of the paving layer of the stone-filled embankment shall not exceed 50 cm. Stones of different sizes ranging from 20 cm to 40 cm shall be used for mixing and filling. The elevation shall be measured by a level meter and 50 cm high limit steel bars shall be set to cross and control the thickness of the stone-filled embankment layer. S4.
2. The edges of the stone-filled embankment shall be laid with a thickness of 2m and a minimum size of stone blocks not less than 300mm.
6. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 5 is characterized in that: The specific implementation process of step S5 is as follows: S5.
1. The overall design method of concrete retaining wall and flood drainage channel is adopted. The construction process is construction preparation, surveying and setting out, foundation trench excavation, foundation bearing capacity testing, formwork reinforcement, installation of drainage holes, water filter layer, pouring of rubble concrete, removal of formwork and maintenance. S5.
2. The retaining wall foundation is excavated manually with an excavator. Before foundation construction, a base bearing capacity test is conducted. The formwork is made of glued wood or steel, and vibrated and compacted with an inserted 50-type vibrating rod. φ10cm PVC pipe drainage holes are set alternately every 2m up, down, left and right. A rammed clay anti-seepage layer is set below the lowest drainage hole and within 0.5m below the wall top. A 5% water flow slope is set. The area above the lowest drainage hole is backfilled with permeable materials. The thickness of each layer is 15cm, and the backfill is 30cm. S5.
3. When the wall concrete reaches more than 70% of the design strength, backfill the retaining wall. Set an expansion joint every 10m along the wall body and the wall height. The joint width is 2cm. Fill the retaining wall with asphalt hemp reinforcement along the three inner and outer sides of the top of the wall. The filling depth is 20cm.
7. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 6 is characterized in that: The specific implementation process of step S7 is as follows: S7.
1. After the stone-filled embankment is completed, it shall be compacted to eliminate the differential deformation between the roadbeds and reduce the uneven settlement of the roadbed; S7.
2. The unit impact energy of dynamic compaction is proposed to be 3000KN·m / m2, the weight of the compaction hammer is 22t, the bottom surface is circular, the static pressure value of the hammer bottom is 48kPa, and it is determined through on-site compaction test; S7.
3. The number of tamping times of the tamping point is 6 times, which is determined according to the relationship curve between the number of tamping times and the tamping amount obtained by the on-site tamping test. The average tamping amount of the last two tampings shall not exceed 50 mm, and the total tamping amount shall not be less than 90% of the total tamping amount of the test tamping. The ground around the tamping shall not be too bulging, and there shall be no difficulty in lifting the hammer due to the tamping hammer being too deep. The number of tamping times is 2, and the last tamping time is low-energy tamping. The time interval between the two times is 1 to 2 weeks. The tamping points are arranged in a side triangle. The spacing between the tamping points in the first time is 5 to 7 m. The spacing between the tamping points in each subsequent time can be the same as that in the first time, or can be appropriately reduced. S7.
4. Based on the preliminarily determined dynamic compaction parameters, propose a dynamic compaction test plan and conduct on-site dynamic compaction tests; S7.
5. According to different soil conditions, after several weeks of trial compaction, the trial compaction site shall be tested and compared with the test data before compaction to detect the compaction effect and determine the various compaction parameters used in the project. It is prohibited to compact within 5m of the retaining wall and culvert.
8. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 7 is characterized in that , the specific implementation process of step S8 is: S8.
1. After the rock-fill embankment is compacted, a layer of non-woven geotextile and 30 cm thick graded crushed stone are laid on the top of the embankment as a filter isolation layer; S8.
2. The unit area mass of non-woven geotextile is 350-500g / m2, its elongation is <50%, the holding strength is ≥1600N, the tear strength is ≥800N, the puncture strength is ≥800N, and the CBR bursting strength is ≥3500N.
9. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 8 is characterized in that: The specific implementation process of step S9 is as follows: S9.
1. Take samples of filler materials for testing to determine the optimum moisture content and maximum dry density and submit to the supervising engineer for approval; S9.
2. Before the formal construction, pave a 200m test section and record the type of compaction equipment, the best combination, the number of rolling passes and rolling speed, the process, the loose thickness and moisture content of the material, and the flatness of the roadbed; S9.
3. The filling and rolling method is adopted in longitudinal sections and horizontal layers. The loose thickness of each layer of filler shall not exceed 30cm. The thickness shall not be less than 10cm. The filler shall be transported to the construction site by car, spread by bulldozer and rolled by heavy vibratory roller to the specified compaction degree. The particle size of the filler shall be strictly controlled not to exceed 15cm, and the particle size within 30cm of the top of the roadbed shall not exceed 10cm; S9.
4. The particle size should be controlled outside the construction site. Crushing on the site is strictly prohibited. During the paving process, the coarse and fine particles should be evenly distributed. Large particles should not be concentrated on the slope side. Finer materials should be used for filling within 1m outside. To ensure the compaction of the roadbed edge, the roadbed filling construction width should be overfilled by 30cm on each side. Finally, the slope should be cut according to the slope rate to ensure the stability of the slope. The filling material to be paved on the same day should be rolled on the same day. In the rainy season, timely inspection and removal of water accumulation on the roadbed should be carried out. Temporary drainage facilities should be unobstructed and free of siltation. "Springs" found in the filling section should be completely removed. The bridgehead roadbed should be filled with gravel or crushed stone with good permeability and compacted in layers. The compaction degree requirement is that heavy compaction degree (solid volume rate) should be adopted from the bottom to the top of the roadbed, and the compaction degree (solid volume rate) should be ≥96% (87%). S9.
5. According to the requirements of the specification, construction monitoring of high embankments with a slope height of more than 20m shall be carried out, including settlement and displacement.
10. The protective drainage prefabrication installation construction process for roadbed engineering according to claim 9, characterized in that: The specific test process of step S10 is as follows: S10.
1. Use an impact compactor equipped with a polygonal compaction wheel. During rolling, the potential energy difference between the large and small radii of the polygonal compaction wheel generates concentrated impact energy with the characteristics of seismic wave propagation. With the combined effect of rolling and kneading, the deep layer of the soil is compacted as the shock wave propagates. The effective compaction thickness reaches 1.5m, which has better compaction effect than the existing vibratory compaction machinery. The rolling speed of the impact compactor is twice that of the vibratory compactor. S10.
2. For the roadbed from the top of the high-filled stone embankment to the bottom of the roadbed, impact rolling shall be used for reinforcement and compaction every 3 m after the roadbed is completed to eliminate differential deformation between roadbeds and reduce uneven settlement of the roadbed; S10.
3. Use a triangular twin-wheel impact roller with an impact energy of more than 25 kJ, with a net weight of not less than 12 t, a compaction width of not less than 2 × 900 mm, a trailer speed of 10 km / h to 15 km / h, an impact frequency of 60 to 110 times / min, and a round trip to complete a compaction pass, with a compaction width of not less than 4 m; S10.
4. Before impact rolling, a test section shall be tested. The length of the test section shall not be less than 150m and the width shall not be less than 8m. The elevation shall be measured after 5, 10, 15, 20 and 25 times of impact rolling, and the settlement after every 5 times of impact rolling shall be calculated. If the average settlement is less than 30mm, the impact rolling shall be stopped; if the average settlement is still greater than 30mm, the impact rolling shall be continued. The maximum number of times for roadbed impact rolling is 30 times. S10.
5. Summarize the data of moisture content and compaction degree of the test section, determine the reasonable number of compaction passes, and use it to guide the construction of the entire roadbed. The length of the impact rolling working surface should be 200 to 500 meters. The impact rolling should be carried out evenly. The overlap length of two adjacent impact rolling sections should not be less than 15 meters. When the impact roller is working, the outer edge of the compaction wheel should maintain a safety distance of not less than 1 meter from the edge of the roadbed to prevent the impact energy from being large and easily damaging the edge of the filling layer. When encountering culverts and retaining walls, the corresponding safety distance must be maintained. Before the reinforcement and compaction of 2m, the roadbed at this elevation is first compacted to the designed compaction degree with a general roller, and then impact rolling is performed after a layer of filler of more than 30cm is loosely spread. When the surface of the filler is dry, water is sprinkled appropriately to prevent the surface from becoming dusty and affecting the energy transmission to the deep layer. When turning, the driver adjusts the turning route so that the impact energy cam point does not repeat the previous landing point to reduce the wave phenomenon. During the impact and compaction process, if the spring phenomenon occurs, the punching is immediately stopped, and the enhanced compaction is performed after digging and drying or other measures are taken; S10.
6. After impact compaction, the cross slope and flatness of the roadbed shall be restored to facilitate drainage of the roadbed.