Photovoltaic ground pile and use method

By incorporating cavities and anchor fin structures within the photovoltaic ground piles, the issues of stability and installation complexity in harsh environments are resolved, achieving both stability and simplified installation while reducing costs.

CN118880925APending Publication Date: 2024-11-01CHANGYUAN MAIDE (DONGGUAN) TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411049636.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

Existing photovoltaic ground piles are difficult to maintain stability and firmness in harsh environments, and the installation process is complicated, affecting the construction period and cost.

Method used

A photovoltaic ground stake was designed with an internal cavity, positioning seat, guide seat, and vertically retractable anchor wings. Under external force, the anchor wings extend into the soil to form a claw-shaped structure, increasing the gripping area and enhancing resistance to tilting and pull-out.

Benefits of technology

It improves the stability and tilt resistance of the ground piles, simplifies the installation process, adapts to harsh environments, and reduces material and labor costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880925A_ABST
    Figure CN118880925A_ABST
Patent Text Reader

Abstract

According to the photovoltaic ground pile and the using method, the structure is simple, the ground pile is balanced and firm, the ground gripping area is increased, it is ensured that the ground pile is vertically fixed, the reverse retaining force is increased, and the photovoltaic ground pile can cope with the severe environment. The device comprises a pile body, a cavity is formed in the pile body, the cavity is provided with a positioning seat, a guide seat and an anchor wing capable of stretching up and down, the positioning seat is arranged at the top of the guide seat, a positioning hole matched with the anchor wing is formed in the top of the positioning seat, the bottom of the anchor wing is inserted into the positioning hole, and the anchor wing is arranged on the guide seat. An inlet and outlet hole matched with the anchor wing is formed in the edge side of the pile body, the inlet and outlet hole is close to the inclined waist portion of the guide seat, and when external force presses the anchor wing downwards, the anchor wing penetrates out of the inlet and outlet hole along the inclined waist portion of the guide seat, and the anchor wing extends towards soil around the pile body. The invention is applied to the technical fields of photovoltaics, greenhouses and road fences.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention is applied to the technical field of photovoltaic, greenhouse and road fence ground piles, and particularly relates to a photovoltaic ground pile and a method of using the same. Background Art

[0002] Solar energy resources are abundant and widely distributed. As a clean energy, it is the most promising renewable energy. With the increasing prominence of global energy shortages and environmental pollution, its exploitation and utilization are receiving attention from countries around the world. Using solar photovoltaic power generation technology to create clean renewable energy for mankind is a major trend in the future and has become an emerging energy industry that is widely concerned and focused on by countries around the world. In order to collect a large amount of solar energy, it is necessary to set up photovoltaic brackets on a vast land. In some places with hard geological structures or underground rock formations, it is difficult to ensure the same height of the piles after the existing solar photovoltaic brackets are driven, which brings inconvenience to the subsequent installation of front and rear columns and the final fixation of the solar photovoltaic brackets. For some brackets installed on slopes, the existing brackets cannot properly adjust their installation angles and cannot ensure that the installation height of the photovoltaic components remains consistent relative to the ground. In order to pursue stability, the joints of the components are often welded, which is labor-intensive and time-consuming, and the disassembly is also troublesome. The construction period of the power station is long. At the same time, due to unreasonable structure and errors during assembly, it often leads to the situation that the installation on site cannot occur.

[0003] There are two types of ground piles in the prior art: the first type is to dig a pit in the ground, fill it with concrete, and pre-set bolts on the concrete pile. After the concrete solidifies, the ground pile is installed on the concrete, and the position and height of the ground pile must be adjusted at the same time; the second type is a spiral ground pile. Although the pile body is screwed into the soil, the peripheral fins do not extend far beyond the main body, and the pull-out force and anti-tilt force are not obvious. In the process of screwing the ground pile into the soil, the soil around the ground pile is easily loosened, thereby reducing the pull-out force and anti-tilt force. However, the production of concrete pile mounting bases is labor-intensive and time-consuming, and is particularly susceptible to the influence of terrain, environment and temperature. For installation environments with harsh terrain, the transportation of materials is more troublesome, such as mountainous areas or deserts, where it is not convenient to transport concrete. If spiral piles are used for installation, the requirements for the installation position are high. Once the adjustment fails to meet the design requirements, it needs to be repositioned, which affects the construction schedule and greatly increases the material cost and labor cost. At the same time, it is easy to loosen the soil around the pile body, the wing does not extend far from the body, the soil gripping area is not large, the tilting force and the pulling force are not obvious, and there are requirements for the soil quality, and soft soil cannot be used. For example, the Chinese patent with the publication number CN208533524U discloses a new type of photovoltaic power station pile, which improves the firmness and stability of the photovoltaic panel by adjusting the number and angle of the upward support arms, and enhances the stability and firmness of the pile by adjusting the number and angle of the downward support arms. However, its installation method is spiral, and during the spiral process, it is easy to loosen the soil around the pile, thereby reducing the pulling force and tilting force. In addition, the support arm is prone to rust or loosening after years of wind and rain corrosion, making it difficult to withstand strong winds and rainstorms, and its stability is greatly reduced. Therefore, it is necessary to provide a photovoltaic ground pile with a simple structure, a stable and balanced ground pile, a larger gripping area, vertical fixation of the ground pile, increased reverse stop force, and the ability to cope with harsh environments, and a method of use. Summary of the invention

[0004] The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a photovoltaic ground pile and a method of use which has a simple structure, a balanced and firm ground pile, an increased gripping area, ensures that the ground pile is vertically fixed, increases the reverse stop force, and can cope with harsh environments.

[0005] The technical solution adopted by the present invention is: the present invention includes a pile body, a cavity is opened inside the pile body, and the cavity is provided with a positioning seat, a guide seat, and anchor wings that can be telescoped up and down, the positioning seat is arranged at the top of the guide seat, and a positioning hole matched with the anchor wing is opened on the top of the positioning seat, and the bottom of the anchor wing is inserted into the positioning hole, and an entry and exit hole matched with the anchor wing is opened on the edge side of the pile body, and the entry and exit hole is close to the oblique waist of the guide seat. When external force presses the anchor wing downward, the anchor wing passes through the entry and exit hole along the oblique waist of the guide seat, and the anchor wing extends toward the soil around the pile body.

[0006] It can be seen from the above scheme that the anchor wing expands and contracts up and down inside the pile body, and the anchor wing extends toward the surrounding soil of the pile body according to the law of external force. The anchor wing cooperates with the top pressure of the soil to form a claw-shaped structure, thereby increasing the grip area, enhancing the anti-tilting force of the pile body and increasing the pulling force of the pile body, ensuring its stability and firmness. The pile is not easy to tilt, has good compatibility, and is suitable for terrain with harsh environments. At the same time, the soil around the pile is not loosened, which is beneficial to improving the anti-pulling force and tilting force of the pile.

[0007] A preferred solution is that the anchor wing includes two groups of support bars, both groups of support bars are U-shaped structures, both groups of support bars are inverted and cross-crossed horizontally and vertically, and the support bars are steel structures.

[0008] A preferred solution is that wedge blocks are provided at the upper and lower ends of the outer wall of the anchor wing, and the wedge blocks are of a slope structure with a higher top and a lower bottom. Initially, the wedge block at the lower end is positioned and matched with the edge of the positioning hole; when the anchor wing extends outward and stops, the wedge block at the upper end is positioned and matched with the edge of the positioning hole.

[0009] A preferred solution is that a cone head is provided at the bottom of the pile body, the cone head is in a cone shape, and the cone head is a structure that is wide at the top and narrow at the bottom.

[0010] A preferred solution is that the oblique waist portion of the guide seat is a curved surface structure, and the longitudinal section of the guide seat is trapezoidal in shape. Initially, the bottom end of the anchor wing is tightly attached to the oblique waist portion of the guide seat.

[0011] A preferred solution is that the upper portion of the positioning seat is a square structure, the lower portion of the positioning seat is a cylindrical structure, the cylindrical structure is positioned and matched with the cavity, and the positioning hole is a square hole.

[0012] A preferred solution is that the number of groups of the positioning holes and the number of groups of the entry and exit holes are both four, the four groups of the positioning holes are symmetrically arranged on the top of the square structure, and the four groups of the entry and exit holes are symmetrically arranged on the edge side of the pile body.

[0013] A preferred solution is that an opening is provided at the top of the pile body, and a reinforcement block is provided at the edge of the opening.

[0014] A preferred embodiment is that the method comprises the following steps: Step A: bend the tail of the anchor wing outward and tilt it up, cross-connect the two groups of support bars and insert them into the positioning seat through the positioning hole, the wedge-shaped block at the lower end is clamped at the edge of the positioning hole to prevent the anchor wing from tilting in a natural state, and install the positioning seat, the guide seat and the anchor wing into the cavity and realize the clamping position; Step B: using a pile driver to plant the pile body. During the planting phase, the cone head guides the pile body. Under the guidance of the cone head, the pile body is more easily inserted into the soil without damaging the original solid state of the soil around the pile. When the pile body reaches a specified depth, the downward pressure on the pile body is stopped, and the existing position and state of the pile body are maintained. Step C: external force is applied to press down the anchor wing, and the anchor wing moves downward under the force, and the anchor wing passes through the inlet and outlet hole along the oblique waist of the guide seat, and the anchor wing extends toward the soil around the pile body and is inserted into the soil, and the anchor wing cooperates with the top pressure of the soil to form a claw-shaped structure; Step D: When the anchor wing extends outward to a certain length, the wedge-shaped block at the upper end is stuck on the edge of the positioning hole, thereby preventing the anchor wing from retracting after extending. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a three-dimensional structural diagram of the present invention; Figure 2 It is a three-dimensional structural exploded diagram of the present invention; Figure 3 It is a cross-sectional view of the present invention when the anchor fins extend toward the soil around the body; Figure 4 This is a three-dimensional structural exploded view of the present invention when the anchor fins extend toward the soil around the body; Figure 5 is a three-dimensional structural diagram of the guide seat; Figure 6 is a three-dimensional structural diagram of the positioning seat; Figure 7 It is a three-dimensional structural diagram of the anchor wing. DETAILED DESCRIPTION

[0016] like Figures 1 to 7 As shown, in this embodiment, the present invention includes a pile body 1, the interior of the pile body 1 is provided with a cavity, the cavity is provided with a positioning seat 3, a guide seat 4, and an anchor wing 5 that can be telescoped up and down, the positioning seat 3 is arranged at the top of the guide seat 4, the top of the positioning seat 3 is provided with a positioning hole 6 that is compatible with the anchor wing 5, the bottom of the anchor wing 5 is inserted into the positioning hole 6, the edge side of the pile body 1 is provided with an inlet and outlet hole 7 that is compatible with the anchor wing 5, the inlet and outlet hole 7 is close to the oblique waist of the guide seat 4, when external force applies downward pressure to the anchor wing 5, the anchor wing 5 passes through the inlet and outlet hole 7 along the oblique waist of the guide seat 4, and the anchor wing 5 extends toward the soil around the pile body 1.

[0017] The pile body 1 is planted with a pile driver. During the planting stage, the anchor wing 2 is hidden in the cavity, and the positioning seat 3 positions the anchor wing 5 to prevent the anchor wing 5 from shifting. When the pile body 1 reaches the specified depth, the downward pressure on the pile body 1 is stopped, and the anchor wing 2 is pressed downward. The anchor wing 5 moves downward under the force. Since the guide seat 4 is a slope structure that is narrow at the top and wide at the bottom, and the oblique waist of the guide seat 4 is a smooth surface, the anchor wing 5 is guided by the guide seat 4. The anchor wings 2 pass through the entry and exit holes 7 along the waist of the guide seat 4, extend regularly toward the soil around the pile body 1, and are inserted into the soil. The anchor wings 5 ​​cooperate with the top pressure of the soil to form a claw-shaped structure, thereby increasing the gripping area, enhancing the anti-tilting force of the pile body 1 and increasing the pulling force of the pile body 1. The extension of the anchor wings 5 ​​can not only ensure the balance of the pile, but also increase the reverse stopping force, to ensure that the pile is not easy to tilt when the object above is subjected to external force, thereby ensuring its practicality and stability.

[0018] like Figures 1 to 7 As shown, in this embodiment, the anchor wing 5 includes two groups of support bars, both of which are U-shaped structures, both of which are inverted and cross-crossed horizontally and vertically, and the support bars are steel structures. The two groups of support bars are cross-arranged, and the tops of the two groups of support bars are connected by bolts. The overall structure is conducive to improving the stability of the anchor wing 5, while ensuring that the two groups of support bars extend outward synchronously, and the anchor wing 5 deforms regularly toward the outside of the pile body 1 and extends toward the periphery.

[0019] like Figures 1 to 7 As shown, in this embodiment, the upper and lower ends of the outer wall of the anchor wing 5 are both provided with wedge blocks 8, and the wedge blocks 8 are of a slope structure with a high top and a low bottom. Initially, the wedge blocks 8 at the lower end are positioned and matched with the edge of the positioning hole 6; when the anchor wing 5 extends outward and stops, the wedge blocks 8 at the upper end are positioned and matched with the edge of the positioning hole 6. The wedge blocks 8 are convex structures, and the wedge blocks 8 at the lower end are used to prevent the anchor wing 5 from tilting itself in a natural state, so as to achieve a positioning effect; when the anchor wing 5 extends outward to a certain length, the wedge blocks 8 at the upper end are stuck at the edge of the through hole 7 to prevent the anchor wing 5 from retreating after extending out.

[0020] like Figures 1 to 7 As shown, in this embodiment, a cone head 9 is provided at the bottom of the pile body 1, and the cone head 9 is in a cone shape, and the cone head 9 is a structure that is wide at the top and narrow at the bottom. The pile driver implements the pile planting on the pile body 1. During the pile planting stage, the cone head 9 guides the pile body 1. Under the guidance of the cone head 9, the pile body 1 is easier to insert into the soil without destroying the original solid state of the soil around the pile.

[0021] like Figures 1 to 7As shown, in this embodiment, the oblique waist of the guide seat 4 is a curved surface structure, and the longitudinal section of the guide seat 4 is trapezoidal. Initially, the bottom end of the anchor wing 5 is closely attached to the oblique waist of the guide seat 4. The oblique waist of the guide seat 4 guides the extension of the anchor wing 5.

[0022] like Figures 1 to 7 As shown, in this embodiment, the upper portion of the positioning seat 3 is a square structure, and the lower portion of the positioning seat 3 is a cylindrical structure. The cylindrical structure is positioned and matched with the cavity, and the positioning hole 6 is a square hole.

[0023] like Figures 1 to 7 As shown, in this embodiment, the number of groups of the positioning holes 6 and the number of groups of the inlet and outlet holes 7 are both four groups, and the four groups of the positioning holes 6 are symmetrically arranged at the top of the square structure, and the four groups of the inlet and outlet holes 7 are symmetrically arranged at the edge side of the pile body 1. The inlet and outlet holes 7 are located below the oblique waist of the guide seat 4, and the anchor wings 5 ​​extend from the four groups of symmetrically arranged inlet and outlet holes 7, regularly extend toward the soil around the pile body 1, and insert into the soil. The anchor wings 5 ​​cooperate with the top pressure of the soil to form a claw-shaped structure, increase the grip area, and ensure its three-dimensional stability.

[0024] like Figures 1 to 7 As shown, in this embodiment, the top of the pile body 1 is provided with an opening 10, and a reinforcement block 11 is provided at the edge of the opening 10. The pile driver implements the pile driving on the pile body 1 through the reinforcement block 11, so as to avoid the pile driver from hard collision with the pile body 1, thereby causing the pile body 1 to break.

[0025] In this embodiment, the number and length of the anchor fins 5 are configured according to the geological conditions.

[0026] In this embodiment, the method of use includes the following steps: Step A: bend the tail of the anchor wing 5 outward to prevent the anchor wing 5 from directly passing through the guide seat 4 under the pressure of external force, cross-connect the two groups of support bars and insert them into the positioning seat 3 through the positioning hole 6, and the wedge block 8 at the lower end is clamped on the edge of the positioning hole 6 to prevent the anchor wing 5 from tilting in a natural state, and install the positioning seat 3, the guide seat 4, and the anchor wing 5 into the cavity and realize the clamping position; Step B: using a pile driver to plant the pile body 1. During the planting stage, the cone head 9 guides the pile body 1. Under the guidance of the cone head 9, the pile body 1 is more easily inserted into the soil without damaging the original solid state of the soil around the pile. When the pile body 1 reaches the specified depth, stop the downward pressure on the pile body 1 and keep the current position and state of the pile body 1. Step C: external force is applied to press down the anchor wing 5, and the anchor wing 5 moves downward under the force, and the anchor wing 5 passes through the inlet and outlet hole 7 along the oblique waist of the guide seat 4, and the anchor wing 5 extends toward the soil around the pile body 1 and is inserted into the soil, and the anchor wing 5 cooperates with the top pressure of the soil to form a claw-shaped structure; Step D: When the anchor wing 5 extends outward to a certain length, the wedge block 8 at the upper end is stuck on the edge of the positioning hole 6, thereby preventing the anchor wing 5 from retreating after being extended.

[0027] Although the embodiments of the present invention are described with practical solutions, they do not constitute limitations on the meaning of the present invention. For those skilled in the art, it is obvious to modify the implementation scheme and combine it with other solutions based on this description.

Claims

1. A photovoltaic ground pile, comprising a pile body (1), characterized in that: The pile body (1) has a cavity formed inside, and the cavity is provided with a positioning seat (3), a guide seat (4), and an anchor wing (5) that can be telescoped upward and downward. The positioning seat (3) is arranged at the top of the guide seat (4). A positioning hole (6) that matches the anchor wing (5) is formed at the top of the positioning seat (3). The bottom of the anchor wing (5) is inserted into the positioning hole (6). An inlet and outlet hole (7) that matches the anchor wing (5) is formed at the edge of the pile body (1). The inlet and outlet hole (7) is close to the oblique waist of the guide seat (4). When an external force presses the anchor wing (5) downward, the anchor wing (5) passes through the inlet and outlet hole (7) along the oblique waist of the guide seat (4), and the anchor wing (5) extends toward the soil surrounding the pile body (1).

2. A photovoltaic ground pile according to claim 1, characterized in that: The anchor wing (5) comprises two groups of support bars, both groups of support bars are U-shaped structures, both groups of support bars are inverted and cross-shaped horizontally and vertically, and the support bars are steel structures.

3. A photovoltaic ground pile according to claim 2, characterized in that: The upper and lower ends of the outer wall of the anchor wing (5) are both provided with wedge blocks (8), and the wedge blocks (8) are of a sloped structure with a higher top and a lower bottom. Initially, the wedge block (8) at the lower end is positioned and matched with the edge of the positioning hole (6); when the anchor wing (5) extends outward and stops, the wedge block (8) at the upper end is positioned and matched with the edge of the positioning hole (6).

4. A photovoltaic ground pile according to claim 3, characterized in that: A cone head (9) is provided at the bottom of the pile body (1); the cone head (9) is in a cone shape and has a structure that is wide at the top and narrow at the bottom.

5. The photovoltaic ground pile according to claim 1, characterized in that: The oblique waist portion of the guide seat (4) is a curved surface structure, and the longitudinal section of the guide seat (4) is trapezoidal in shape. Initially, the bottom end of the anchor wing (5) is tightly attached to the oblique waist portion of the guide seat (4).

6. The photovoltaic ground pile according to claim 1, characterized in that: The upper portion of the positioning seat (3) is a square structure, and the lower portion of the positioning seat (3) is a cylindrical structure, the cylindrical structure is positioned and matched with the cavity, and the positioning hole (6) is a square hole.

7. The photovoltaic ground pile according to claim 6, characterized in that: The number of groups of the positioning holes (6) and the number of groups of the inlet and outlet holes (7) are both four. The four groups of positioning holes (6) are symmetrically arranged on the top of the square structure, and the four groups of inlet and outlet holes (7) are symmetrically arranged on the edge side of the pile body (1).

8. The photovoltaic ground pile according to claim 1, characterized in that: An opening (10) is provided at the top of the pile body (1), and a reinforcement block (11) is provided at the edge of the opening (10).

9. A method for using a photovoltaic ground pile as claimed in claim 4, characterized in that: The method of use includes the following steps: Step A: The tail of the anchor wing (5) is bent outward and tilted, the two groups of support bars are cross-connected and inserted into the positioning seat (3) through the positioning hole (6), the wedge block (8) at the lower end is clamped on the edge of the positioning hole (6) to prevent the anchor wing (5) from tilting in a natural state, and the positioning seat (3), the guide seat (4) and the anchor wing (5) are installed into the cavity and locked in place; Step B: using a pile driver to plant the pile body (1). During the planting phase, the cone head (9) guides the pile body (1). Under the guidance of the cone head (9), the pile body (1) is more easily inserted into the soil without damaging the original solid state of the soil around the pile. When the pile body (1) reaches a specified depth, the downward pressure on the pile body (1) is stopped, and the current position and state of the pile body (1) is maintained. Step C: external force is applied to press the anchor wing (5) downward, and the anchor wing (5) moves downward under the force, and the anchor wing (5) passes through the inlet and outlet hole (7) along the oblique waist of the guide seat (4), and the anchor wing (5) extends toward the soil around the pile body (1) and is inserted into the soil, and the anchor wing (5) cooperates with the top pressure of the soil to form a claw-shaped structure; Step D: When the anchor wing (5) extends outward to a certain length, the wedge-shaped block (8) at the upper end is stuck on the edge of the positioning hole (6), thereby preventing the anchor wing (5) from retracting after extending.