RTDS distributed distribution network test centralized control system based on 5G
Through the 5G-based RTDS distributed distribution network test centralized control system, the problem of recording file integrity caused by inaccurate start time and network delay in distributed distribution network test is solved, and efficient distribution network testing is achieved, ensuring that Accuracy and efficiency of test results.
Patent Information
- Application Number
- CN202410802029.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-20
- Publication Date
- 2024-11-01
AI Technical Summary
In the distributed distribution network test, there are problems such as inaccurate start time of wave recording and network delay, which leads to insecure integrity of wave recording files, which limits the large-scale application and testing efficiency of distribution network automation systems.
A centralized control system for RTDS distributed distribution network testing based on 5G is designed to monitor the recording status and feedback packets of the RTDS workstation through the centralized control device, and real-time data synchronization is achieved using the 5G network to ensure the accuracy and completeness of the recording file. and automatically adjust the test action model through centralized control software to improve testing efficiency.
The accuracy of the test start time is achieved, the problem of premature or late recording is avoided, the integrity and accuracy of the recording file is ensured, the efficiency of distribution network testing is improved, and there is no need to rely on laboratory personnel to monitor it in real time.
Smart Images

Figure CN118884902A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of distribution network testing, and in particular to a 5G-based RTDS distributed distribution network testing centralized control system. Background Art
[0002] With the development of the electrification industry and the advancement of science and technology, modern society has entered an era of comprehensive electrical automation led by information technology, which requires high reliability of power supply. As an important equipment for the automation of distribution network (hereinafter referred to as "distribution network"), the stability and reliability of the functions and performance of distribution automation terminals directly affect the safety of electricity use and property safety of industry and residents. In order to ensure the safe and reliable operation of the distribution network system and improve the efficiency of automation debugging, a joint debugging and testing solution for the increasingly complex distribution automation terminals is needed.
[0003] The 5G-based RTDS distributed distribution network test automation technology effectively supports power supply reliability. Since the distribution automation terminals are dispersed in different locations and the configuration is relatively complex, it brings challenges to the functional joint debugging and testing of the distribution network system, limiting the large-scale application of the distribution network automation system.
[0004] Real-time digital simulation technology (RTDS) realizes digital modeling fault simulation. When the RTDS client loads the test action model file and performs fault replay, the power amplifier module of RTDS outputs the voltage, current, and switch quantity of the simulation model to the simulation interface device. The interface device converts the received physical quantity into a network message through the 5G network and transmits it synchronously to the distribution network tester at the distribution network site. The tester outputs analog quantity and switch quantity to the distribution automation terminal according to the received network message. Through the recording program (DTEST), the entire test is recorded, and the protection switch position feedback signal of the distribution automation terminal will be recorded in the recording file. By analyzing the position change signal of the recording file and combining it with the change of the analog quantity, it can be determined whether the fault simulation has achieved the expected result, thereby realizing the acceptance of the distribution automation terminal.
[0005] At present, distributed distribution network testing requires technical personnel to be stationed in the RTDS laboratory. When testing the distribution network on site, the laboratory needs professional technicians to be responsible for RTDS-related equipment status monitoring, model file playback start and stop, recording start and stop, test result analysis and other tasks, and at the same time, they need to frequently communicate with the site about the current test status. The test scenario has the following three problems.
[0006] 1. If the waveform recording starts too early during the test, the displacement information generated by the model file initialization content may be recorded, which is irrelevant to the test target. If the waveform recording starts too late, the displacement signal normally fed back by the distribution automation terminal will be missed. How to eliminate these irrelevant interferences to the test is crucial to the success of the test.
[0007] 2. Because it involves the calibration of electrical protection switches, the test requires high network real-time performance. If the network delay is greater than 100ms during the test, the recording program will stop running. If the test continues, the integrity of the recording file cannot be guaranteed. Summary of the invention
[0008] The purpose of the present invention is to provide a 5G-based RTDS distributed distribution network test centralized control system to improve the efficiency of distribution network testing.
[0009] In order to solve the above technical problems, the present invention provides a technical solution: a 5G-based RTDS distributed distribution network test centralized control system, comprising:
[0010] The centralized control device is used to send preset test action model files and prototype model files to the RTDS workstation according to the selected fault type, monitor the recording status and feedback message returned by the RTDS workstation, and judge whether the test results are consistent with the expected test results according to the recording files returned by the RTDS workstation;
[0011] RTDS workstation, used to send analog quantity and switch quantity to the simulation interface device according to the prototype model file and the test action model file, record the distribution automation terminal and send the generated recording file to the centralized control device, return the recording status to the centralized control device, return the feedback message to the centralized control device according to the execution status of the test action model file, and stop the test and recording when the network delay is greater than the preset delay;
[0012] The simulation interface device is used to convert the analog quantity and switch quantity sent by the RTDS workstation into network messages and send them to the distribution network tester through 5G;
[0013] Distribution network tester, used to convert network messages into analog and switch quantities and send them to the distribution automation terminal, obtain network delay according to network messages and send them to the RTDS workstation;
[0014] Distribution automation terminal, used to perform test actions based on analog and switch quantities.
[0015] According to the above scheme, the RTDS workstation includes:
[0016] The RPC server is connected to the centralized control device and the RTDS client respectively, and is used to receive the test action model file and the prototype model file sent by the centralized control device and transmit them to the RTDS client, and receive the feedback message from the RTDS client and transmit it to the centralized control software;
[0017] The RTDS client is used to output analog quantity and switch quantity to the simulation interface device according to the test action model file and prototype model file transmitted by the RPC server, and return feedback message to the RPC server;
[0018] The recording module is connected to the centralized control device and the IEC104 server respectively, and is used to record the distribution automation terminal and send the generated recording file to the centralized control device, send the recording status to the IEC104 server, and stop recording when receiving the stop recording signal from the distribution network tester;
[0019] IEC104 server is connected to the centralized control software and is used to return the recording status to the centralized control software.
[0020] According to the above scheme, the RPC server is connected to the centralized control device via RPC, the RPC server is connected to the RTDS client via TCP, and the IEC104 server is connected to the wave recording module via RPC.
[0021] According to the above scheme, the IEC104 server receives the control message from the centralized control software, and sends a start recording signal and a stop recording signal to the recording module according to the control message; when the recording module receives the start recording signal or the stop recording signal from the IEC104 server, it starts or stops recording.
[0022] According to the above scheme, the method of obtaining the prototype model file is as follows:
[0023] Input the drawn electrical connection diagram file into the RTDS client to obtain the prototype diagram model file.
[0024] According to the above scheme, the method of obtaining the test action model file is as follows:
[0025] Using the prototype model file, save the recorded simulated fault action script as a test action model file.
[0026] According to the above scheme, the recording state includes the recording start and stop state.
[0027] The present invention also provides a 5G-based RTDS distributed distribution network test method implemented by using the 5G-based RTDS distributed distribution network test centralized control system described above, comprising:
[0028] Send the preset test action model file and prototype model file to the RTDS workstation according to the selected fault type;
[0029] Monitor the recording status and feedback messages returned by the RTDS workstation;
[0030] Determine whether the test results are consistent with the expected test results based on the recorded wave files returned by the RTDS workstation.
[0031] According to the above scheme, when the test results are judged to be inconsistent with the expected test results, execute:
[0032] Modify the parameters of the test motion model;
[0033] Test again and determine whether the test result is consistent with the expected test result. If not, return to the previous step; if consistent, end.
[0034] According to the above scheme, the method for correcting the parameters of the test action model includes: correcting the protection constants of the test action model using an oscillation algorithm, or inverting the switch displacement of the test action model.
[0035] The beneficial effects of the present invention are as follows: the test personnel can use the portable centralized control device at the distribution network site to send information to the RTDS workstation according to the selected fault type. The RTDS workstation starts the test according to the information sent by the centralized control device and then automatically starts recording, ensuring the accuracy of the recording timing after the test starts, avoiding the omission of normal displacement signals due to late recording, and avoiding the recording of displacement signals irrelevant to the test target due to early recording, thereby ensuring the accuracy of the recording. The simulation interface device communicates with the distribution network tester through the 5G network, utilizing the low latency characteristics of 5G to avoid interruptions in recording due to excessive network delays, and ensuring the integrity and accuracy of the recording file.
[0036] Furthermore, the model file editing function that originally relied on the RTDS client to be implemented was transferred to the on-site centralized control software, so that verification could be carried out in a timely manner. At the same time, the optimization rate of the simulation model file was improved by combining the software algorithm, thereby improving the test efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 This is a schematic diagram of the hardware structure connection of the 5G-based RTDS distributed distribution network test centralized control system according to the first embodiment of the present invention;
[0038] Figure 2 This is an overall framework diagram of a 5G-based RTDS distributed distribution network test centralized control system according to the first embodiment of the present invention;
[0039] Figure 3 It is a data flow diagram of the 5G-based RTDS distributed distribution network test centralized control system of the first embodiment of the present invention;
[0040] Figure 4 This is an operation flow chart of the 5G-based RTDS distributed distribution network test centralized control system according to the second embodiment of the present invention;
[0041] Figure 5 It is a flow chart of a method for correcting a test action model file according to a third embodiment of the present invention. DETAILED DESCRIPTION
[0042] In order to make the purpose, technical solution and advantages of the embodiments of the present disclosure clearer, the technical solution of the embodiments of the present disclosure will be clearly and completely described below in conjunction with the drawings of the embodiments of the present disclosure. Obviously, the described embodiments are part of the embodiments of the present disclosure, not all of the embodiments. Based on the described embodiments of the present disclosure, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present disclosure.
[0043] Embodiment 1:
[0044] The existing distributed distribution network test has the problems of requiring cooperation between the RTDS laboratory and the distribution network site, low integrity of test recording data, and inability to monitor the test status in real time. To solve these technical problems, this embodiment provides a 5G-based RTDS distributed distribution network test centralized control system, see Figure 1 to Figure 3 The system comprises:
[0045] The centralized control device (equipped with centralized control software) is used to send preset test action model files and prototype model files to the RTDS workstation according to the selected fault type (on the RTDS client, the prototype model file is obtained according to the drawn electrical device connection diagram file. Using the prototype model file, the recorded simulated fault action script can be saved as a test action model file), monitor the recording state and feedback message returned by the RTDS workstation, and judge whether the test result is consistent with the expected test result (i.e., the correct displacement sequence of the fault line) according to the recording file returned by the RTDS workstation (the recording file records the protection switch displacement information and analog quantity data);
[0046] RTDS workstation, used to send analog quantity and switch quantity to the simulation interface device according to the prototype model file and the test action model file, record the distribution automation terminal and send the generated recording file to the centralized control device, return the recording status to the centralized control device, return the feedback message to the centralized control device according to the execution status of the test action model file, and stop the test and recording when the network delay is greater than the preset delay;
[0047] The simulation interface device is used to convert the analog quantity and switch quantity sent by the RTDS workstation into network messages and send them to the distribution network tester through 5G;
[0048] Distribution network tester, used to convert network messages into analog and switch quantities and send them to the distribution automation terminal, obtain network delay according to network messages and send them to the RTDS workstation;
[0049] Distribution automation terminal, used to perform test actions based on analog and switch quantities.
[0050] In a preferred embodiment of the present invention, the RTDS workstation comprises:
[0051] The RPC (remote interface call) server is connected to the centralized control device RPC and the RTDS client TCP, and is used to receive the test action model file and prototype model file sent by the centralized control device and pass them to the RTDS client, and receive the feedback message from the RTDS client and pass it to the centralized control software;
[0052] RTDS client (with action model file execution function, supports command line to start prototype model file and perform fault replay; using this, create RPC interface, the centralized control software at the power distribution site transmits and starts the corresponding prototype model file; during the test, according to the selected fault type, the centralized control software reads the test action model file pre-recorded in the laboratory, and transmits it to the RTDS client at the laboratory end through the RPC interface for fault replay), which is used to output analog quantity and switch quantity to the simulation interface device according to the test action model file and prototype model file transmitted by the RPC server (the RTDS client is provided with a power amplifier module, and the power amplifier module outputs analog quantity and switch quantity to the simulation interface device), and returns feedback message to the RPC server;
[0053] The recording module (with a recording program) is connected to the centralized control device for transmission, and is connected to the IEC104 server RPC (the recording module is provided with a corresponding recording program status report RPC interface), which is used to start recording for the distribution automation terminal in a timely manner and send the generated recording file to the centralized control device, send the recording status to the IEC104 server, and stop recording when receiving the stop recording signal from the distribution network tester; since the recording program is stopped midway due to network influence, the saved recording file will be incomplete, so the recording program status report RPC interface is triggered when the recording program is started and stopped;
[0054] The IEC104 server is connected to the centralized control software for returning the recording status to the centralized control software (through the telesignal message); the centralized control software monitors the status of the recording program by parsing the result data bits of the telesignal message containing the agreed point number.
[0055] The system provided in this embodiment uses a simulation interface device to build a closed-loop network connection environment and test environment consisting of a distribution network tester, a distribution automation terminal and an RTDS power simulator. Based on the low latency characteristics of 5G, the state quantity calculated in real time is synchronously transmitted to the site, and a one-click system joint debugging test is realized on site. The system realizes multi-terminal millisecond-level closed-loop testing, providing a fast, accurate and flexible solution for system-level functional debugging, acceptance and fault analysis at the engineering site. The software part of the system is composed of RTDS client, centralized control software, database, message parsing and monitoring software, etc. The core of the software part is the centralized control software, which is deployed on the site for the test-specific tablet computer and has the functions of RTDS model file execution, wave recording file parsing, and data import and export. The core data of the whole test process is centrally displayed, automatically archived and uniformly managed. This embodiment also adopts data archiving based on database technology to realize the full management of test projects, equipment, personnel, model files, etc., with planning, control and results, and all historical test data can be traced.
[0056] Embodiment 2:
[0057] Based on the 5G-based RTDS distributed distribution network test centralized control system described in Example 1, this embodiment also provides a 5G-based RTDS distributed distribution network test method, including:
[0058] Send the preset test action model file and prototype model file to the RTDS workstation according to the selected fault type;
[0059] Monitor the recording status and feedback messages returned by the RTDS workstation;
[0060] Determine whether the test results are consistent with the expected test results based on the recorded wave files returned by the RTDS workstation.
[0061] When executing the above method, the system operation process refers to Figure 4 .
[0062] After the centralized control software sends the test action model file to the RTDS client, it receives the feedback message from the RTDS client in real time. By checking the abnormal information in the feedback message, it can report the abnormality and ensure the integrity of the data. Combined with the running status monitoring of the recording program, the test process is double-monitored, thereby ensuring the integrity and validity of the experimental data.
[0063] According to the background technology, the timing of recording start has a great impact on the test results. In order to solve the technical problem of when to start the recording program for recording, the centralized control software combines the specific action model file type and can accurately control the sequence of sending the action model file, starting the RTDS power amplifier module, and starting the recording program through dual monitoring of the recording process and the test process, ensuring the test's anti-interference ability and improving the test efficiency.
[0064] Embodiment three:
[0065] When the experimental action model file is always inconsistent with the actual expected result, the action model file parameters must be adjusted, and the model parameters need to be adjusted with the help of the laboratory RTDS client. In the prior art, the adjusted model file needs to be frequently verified back and forth with the experimental site, which reduces the efficiency of the experiment.
[0066] To solve the above technical problems, this embodiment proposes a method for modifying a test action model file based on the first embodiment. Figure 5 ,include:
[0067] By using an oscillation algorithm to correct the protection setting of the test action model, or by reversing the switch position of the test action model, the parameters of the test action model are corrected;
[0068] Test again and determine whether the test result is consistent with the expected test result. If not, return to the previous step; if consistent, end.
[0069] In a preferred embodiment of the present invention, after the test action model file is modified (experiments are conducted based on the obtained test action model file to obtain expected test results), the modified test action model file is stored in the test model library.
[0070] Specifically, the discretization formula of the oscillation algorithm that can be used for computer program processing is as follows:
[0071]
[0072] In the above formula, C ′ , C are the protection constants before and after correction respectively, α is the vibration amplitude, n is the number of vibrations, d is the flow rate multiplier of different fixed value protection types, which is an empirical value.
[0073] The switch position inversion is specifically as follows: Get the previous state of a specific switch S. If the previous state of the switch S is 1, then replace it with 0 in the memory in this test. If the previous state is 0, replace it with 1 in this test.
[0074] The method for correcting the test action model file proposed in this embodiment transfers the model file editing function that originally needed to rely on the RTDS client to the on-site centralized control software, thereby enabling timely verification. At the same time, combined with the software algorithm, the optimization rate of the simulation model file is improved, thereby improving the test efficiency.
[0075] In summary, the 5G-based RTDS distributed distribution network test centralized control system provided by the present invention realizes the centralized display, automatic archiving and unified management of the core data of the entire test process. Without the need for laboratory personnel on duty, on-site technicians can automatically test with one click, thereby freeing up manpower and improving joint debugging efficiency. The method for correcting the test action model file provided by the present invention sinks the function of editing the fault model file, which originally required the laboratory RTDS client, to the on-site centralized control software, and combines the feedback algorithm to realize the automatic correction of the model file.
[0076] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. RTDS distributed distribution network test centralized control system based on 5G, It is characterized in that include: The centralized control device is used to send preset test action model files and prototype model files to the RTDS workstation according to the selected fault type, monitor the recording status and feedback message returned by the RTDS workstation, and judge whether the test results are consistent with the expected test results according to the recording files returned by the RTDS workstation; RTDS workstation, used to send analog quantity and switch quantity to the simulation interface device according to the prototype model file and the test action model file, record the distribution automation terminal and send the generated recording file to the centralized control device, return the recording status to the centralized control device, return the feedback message to the centralized control device according to the execution status of the test action model file, and stop the test and recording when the network delay is greater than the preset delay; The simulation interface device is used to convert the analog quantity and switch quantity sent by the RTDS workstation into network messages and send them to the distribution network tester through 5G; Distribution network tester, used to convert network messages into analog and switch quantities and send them to the distribution automation terminal, obtain network delay according to network messages and send them to the RTDS workstation; Distribution automation terminal, used to perform test actions based on analog and switch quantities.
2. According to the 5G-based RTDS distributed distribution network test centralized control system according to claim 1, It is characterized in that The RTDS workstation includes: The RPC server is connected to the centralized control device and the RTDS client respectively, and is used to receive the test action model file and the prototype model file sent by the centralized control device and transmit them to the RTDS client, and receive the feedback message from the RTDS client and transmit it to the centralized control software; The RTDS client is used to output analog quantity and switch quantity to the simulation interface device according to the test action model file and prototype model file transmitted by the RPC server, and return feedback message to the RPC server; The recording module is connected to the centralized control device and the IEC104 server respectively, and is used to record the distribution automation terminal and send the generated recording file to the centralized control device, send the recording status to the IEC104 server, and stop recording when receiving the stop recording signal from the distribution network tester; IEC104 server is connected to the centralized control software and is used to return the recording status to the centralized control software.
3. According to the 5G-based RTDS distributed distribution network test centralized control system according to claim 2, It is characterized in that The RPC server is connected to the centralized control device by RPC, the RPC server is connected to the RTDS client by TCP, and the IEC104 server is connected to the recording module by RPC.
4. According to the 5G-based RTDS distributed distribution network test centralized control system according to claim 2 or 3, It is characterized in that The IEC104 server receives the control message from the centralized control software, and sends a start recording signal and a stop recording signal to the recording module according to the control message; when the recording module receives the start recording signal or the stop recording signal from the IEC104 server, it starts or stops recording.
5. According to the 5G-based RTDS distributed distribution network test centralized control system according to claim 2, It is characterized in that The method to obtain the prototype model file is: Input the drawn electrical device connection diagram file into the RTDS client to obtain the prototype diagram model file.
6. According to the 5G-based RTDS distributed distribution network test centralized control system according to claim 1, It is characterized in that The method to obtain the experimental action model file is as follows: Using the prototype model file, save the recorded simulated fault action script as a test action model file.
7. According to the 5G-based RTDS distributed distribution network test centralized control system according to claim 1, It is characterized in that The recording status includes the recording start and stop status.
8. A 5G-based RTDS distributed distribution network test method implemented by using the 5G-based RTDS distributed distribution network test centralized control system described in any one of claims 1-7, include: Send the preset test action model file and prototype model file to the RTDS workstation according to the selected fault type; Monitor the recording status and feedback messages returned by the RTDS workstation; Determine whether the test results are consistent with the expected test results based on the recorded wave files returned by the RTDS workstation.
9. According to the 5G-based RTDS distributed network testing method of claim 8, It is characterized in that When the test result is judged to be inconsistent with the expected test result, execute: Modify the parameters of the test motion model; Test again and determine whether the test result is consistent with the expected test result. If not, return to the previous step; if consistent, end.
10. The 5G-based RTDS distributed network testing method according to claim 9, It is characterized in that The method for correcting the parameters of the test action model includes: correcting the protection setting of the test action model using an oscillation algorithm, or inverting the switch displacement of the test action model.