Laterally-arranged undercarriage down lock force transmission assembly

By designing the side-mounted landing gear lower lock force transmission component, using the original structural reinforcement of the fuselage to form a closed frame structure, the problem of load transmission of large seaplanes is solved, and the structure is lightweight and efficient load transmission is achieved.

CN118907397APending Publication Date: 2024-11-08AVIC GENERAL HUANAN AIRCRAFT IND CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411090295.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

Due to the height of the fuselage and the need for wave-resistant design, the landing gear needs to be arranged on the side of the fuselage. The landing gear has a long cantilever and a large load, the design of the lower lock force transmission component is difficult, and the structural weight is heavy.

Method used

Design a side-mounted landing gear lower lock force transmission assembly, including lower lock beams, cross beams, joints, connection components and bolt groups. By symmetrically arranged and closed the enclosure structure, the original structural reinforcement of the fuselage is used to form the front and reverse fulcrum points. It bears the ground load of the landing gear and transmits the load to the fuselage.

Benefits of technology

The landing gear is fixed and load transmission, and the structural design problem of increasing the load in the cantilever state of the landing gear pillar is solved. The structure layout is simple, the force transmission route is clear, and the structural efficiency is high, which achieves a certain degree of structural weight reduction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118907397A_ABST
    Figure CN118907397A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of aircraft fuselage structure design, and particularly relates to a side undercarriage down lock force transmission assembly which is arranged in a left-right symmetrical structure mode, is used for connecting an undercarriage and a fuselage and comprises a down lock beam, a cross beam, a right front connector, a left front connector, a right rear connector, a left rear connector and a connecting assembly. The number of the lower lock beams is two, the lower lock beams are arranged on the axis of a long truss of the fuselage and the outer surfaces of skins on the left side and the right side of the fuselage respectively, and two single-lug connector lug holes are further formed in each lower lock beam and used for being connected with an undercarriage on the same side as the lower lock beams; the two cross beams are arranged at common frames in front of and behind the undercarriage along the course of the aircraft; the cross beam, the connector and the connecting assembly are located in the machine body. The left end and the right end of the cross beam are connected with the connectors through the connecting assemblies and then connected with the lower lock beam. The lower lock beams on the left and right sides and the front and rear cross beams form a closed enclosure frame structure; the invention effectively solves the problems that the landing gear strut is in a large cantilever state due to the special appearance of the upper single-wing seaplane, the load of the landing gear is increased, and the structural design is difficult. Reinforcing structures are arranged in the front and rear frame planes to form positive and negative fulcrums to bear undercarriage ground loads, the structural efficiency is high, the force transmission route is clear, meanwhile, the assembly structure adopts a conventional structural design, the assembly manufacturability is good, and structural weight reduction can be achieved to a certain extent.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of aircraft fuselage structure design, and in particular relates to a side-mounted landing gear lower lock force transmission component. Background Art

[0002] Generally speaking, the landing gear of land-based high-wing aircraft is usually arranged under the wing or on the side of the fuselage. For some high-wing aircraft, especially large seaplanes, considering the wave-resistant design requirements of seaplanes, the aircraft fuselage is relatively high, and the wings are also relatively high. The underwing arrangement cannot meet the landing gear layout requirements, and the landing gear can only be arranged on the fuselage. Considering that seaplanes need to ensure the smoothness of the V-shaped bottom shape, it is impossible to design a bulge-type fairing at the bottom of the fuselage for the landing gear to be stored like conventional aircraft. One solution is to arrange the landing gear on the side of the boat-shaped fuselage and retract the landing gear backwards. Specifically: when the landing gear is retracted backwards, it is placed in the fairing on the side of the fuselage; when the landing gear is lowered, the lower locking point arranged on the fuselage locks the landing gear, and the ground load of the landing gear is borne through the force transmission component. However, due to the shape characteristics of the hull, the lower locking point on the fuselage cannot be arranged too low, which will result in a relatively long landing gear cantilever and a large load transmitted from the landing gear to the force transmission component on the fuselage, making the design of the lower lock force transmission component difficult and the structure heavy. Summary of the invention

[0003] In order to solve the above problems, the present invention provides a side-mounted landing gear lower lock force transmission assembly, which is used to fix the landing gear to the fuselage after the landing gear is lowered, and transmit the load of the aircraft during landing and ground taxiing to the fuselage. The lower lock force transmission assembly is a bilaterally symmetrical structure, including a lower lock beam, a cross beam, a joint, a connection assembly and a bolt group;

[0004] There are two lower locking beams, which are arranged at the axis of the fuselage long truss and the outer surface of the left and right skin of the fuselage respectively; each lower locking beam is also provided with two single-ear joints for connecting the landing gear on the same side of the lower locking beam; the crossbeams include two, which are arranged at the common frames in front and behind the landing gear along the heading of the aircraft; there are four groups of joints, which are arranged on the left and right sides of the common frames in front and behind the landing gear respectively, and fit with the inner surface of the fuselage skin; it also includes multiple groups of bolt groups (a total of 16 groups of bolt groups), which are respectively arranged on the left and right joints on the front and rear common frames; the crossbeams, joints, and connecting components are all located inside the fuselage.

[0005] The left and right ends of the cross beam are connected to the joints through connecting components to form an integral load-bearing structure inside the fuselage, and then connected to the lower locking beam on the outer surface of the fuselage skin through a bolt group to form a closed frame structure.

[0006] Furthermore, in the closed frame structure, in the center plane where the cross beam is located, the intersection points of the common frame and the fuselage shape are respectively O1 and O2, the center point of the landing gear strut is O′, and the centers of the two single-ear joint ear holes of the lower locking beam are respectively located on the lines O′O1 and O′O2.

[0007] Furthermore, the left and right ends of the two cross beams are connected to the joint in the same manner, and the cross beams and the joints have the same cross section at the connection; specifically: the webs of the cross beams and the joints are connected via web connectors I and II, the flanges of the cross beams and the joints are connected via flange connectors, web connectors I and web connectors II, and the web ribs of the cross beams and the joints are connected via two connecting plates on both sides; a gap is left between the web connector I and the cross beam flanges.

[0008] Furthermore, the connection assembly includes a flange connector, a web connector I, a web connector II, and a connection plate.

[0009] Furthermore, four bolt groups are connected between each group of joints and the lower lock beam, and are arranged on the upper and lower sides of the single-ear joint of the lower lock beam.

[0010] Furthermore, the single ear joint of the lower locking beam is arranged near the frame station where the cross beam is located.

[0011] Furthermore, two bushings are respectively inlaid in the two single-ear joint ear holes of the lower lock beam, and the bushing material is 15-5PH.

[0012] Furthermore, the lower locking beam is an I-shaped beam structure.

[0013] Furthermore, the lower lock beam is made of titanium alloy forging material.

[0014] Furthermore, the flange connecting the lower locking beam and the fuselage surface is locally thickened at the single ear joint.

[0015] Furthermore, a plurality of reinforcing ribs are arranged near the single ear joint of the lower locking beam.

[0016] Furthermore, the crossbeam is an I-shaped section machine-added beam structure.

[0017] Furthermore, vertical ribs are provided at the center of the lower surface of the web of the cross beam along the length direction of the beam.

[0018] Furthermore, the crossbeam is made of 7050-T7451 aluminum alloy material.

[0019] Furthermore, the joint part is T-shaped as a whole, a plurality of vertical ribs are provided along the length direction of the beam, and the upper and lower sides are multi-cavity structures.

[0020] Furthermore, the joints are all made of titanium alloy forging material.

[0021] Furthermore, the edge strip connector and the connecting piece are flat plate parts; the web connector I is a U-shaped machined part and is provided with vertical ribs; and the web connector II is an L-shaped machined part.

[0022] Technical effect: The side-mounted landing gear lower lock force transmission component provided by the present invention is the internal structure of the fuselage that fixes the landing gear after the landing gear is lowered. It can transmit the ground load transmitted by the landing gear during the landing and ground taxiing of the aircraft, and solves the problem of structural design difficulties caused by the special shape of the upper-wing seaplane, which causes the landing gear strut to be in a large cantilever state and the landing gear load to increase. The component structure cleverly uses the original long stringers, frames and other inherent structures of the fuselage to design and arrange reinforcements, without destroying the integrity of the original fuselage structure, and the structural layout is simple; by setting the reinforcement structure in the front and rear frame planes to form positive and negative fulcrums to bear the ground load of the landing gear, the structural efficiency is high and the force transmission route is clear. At the same time, the component structure adopts a conventional structural design, and the assembly process is good, which can achieve structural weight reduction to a certain extent. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a schematic diagram of the installation structure of the side-mounted landing gear and the lower lock force transmission assembly;

[0024] Figure 2 It is an axial schematic diagram of the connection relationship between the lower lock force transmission component and the surrounding structure;

[0025] Figure 3 It is the axial side view of the lower lock force transmission component;

[0026] Figure 4 for Figure 3 AA section view;

[0027] Figure 5 It is an exploded view of the connection components at the connection between the beam and the joint;

[0028] Figure 6 It is the connection relationship diagram between the lower locking beam and the joint;

[0029] Figure 7 This is the axial schematic diagram of the lower lock beam structure;

[0030] Figure 8 It is a schematic diagram of the beam axial side structure;

[0031] Fig. 9 Schematic diagram of the typical structure of the joint;

[0032] Fig.10 It is a load transfer relationship diagram after the landing gear is connected with the lower lock force transmission component;

[0033] Description of reference numerals:

[0034] 1-lower lock force transmission assembly, 2-landing gear, 3-fuselage, 11-lower lock beam, 12-cross beam, 13-joint, 14-connection assembly, 15-bolt group, 11a-bushing, 12a-cross beam edge strip, 12b-cross beam web, 12c-cross beam vertical rib, 14a-edge strip connector, 14b-web connector I, 14c-web connector II, 14d-connection plate, 31-ordinary frame, 32-strengthening plate, 33-column;

[0035] O′-center of landing gear strut, O1, O2-intersection points of common frame plane in beam plane and outer surface of fuselage, F, F1, F2, F3, F4, F5, F6-tension or compression force, M-bending moment. DETAILED DESCRIPTION

[0036] In order to better understand the function and purpose of the present invention, and not to be regarded as a limiting solution, a detailed description of the embodiments of the present invention is further given below based on the accompanying drawings.

[0037] In the accompanying drawings, symbols with the same identification represent the same or similar elements, or elements with the same or similar functions. The following description of the embodiments through the accompanying drawings is exemplary and is intended to be used to explain the patent of the present invention, and should not be understood as a limitation of the patent of the present invention. Based on the embodiments of the patent of the present invention, other embodiments obtained by engineers and technicians in this field without further creative work are all within the scope of protection of the patent of the present invention. The following is a detailed description in conjunction with the accompanying drawings.

[0038] like Figure 1 , which shows a schematic diagram of a side-mounted landing gear 2 being installed on a fuselage 3 via a lower lock force transmission assembly 1; Figure 2 The main structure of the lower lock force transmission component 1 and its installation relationship with the surrounding common frame are further provided; Figure 3 Shows Figure 2 Structural composition diagram of the middle and lower lock force transmission component 1; Figure 4 A cross-sectional view showing the connection between the joint assembly 14 and the beam 12 is shown; Figure 5 Further demonstrated Figure 4 An exploded view of the joint assembly 14 at the connection between the crossbeam 12 and the joint 13 is shown; Figure 6 The structural details and composition of the lower locking beam 11 are shown in detail; Figure 7 , Figure 8 The structural bearing diagram of the beam 12 and the joint 13 is given; Fig. 9 The relationship between the positions of the two single-ear joint ear holes on the lower locking beam 11 and the load transmission is given.

[0039] Specifically, Figure 1 As shown, the lower lock force transmission assembly 1 is installed through the left and right sides of the fuselage to connect the landing gear 2 and the fuselage 3.

[0040] like Figure 2 As shown, the lower lock force transmission assembly 1 is a bilaterally symmetrical structure, which is respectively installed on the common frames 31 at the front and rear of the landing gear. At the same time, in order to increase the load-bearing stability of the lower lock force transmission assembly 1, each common frame 31 is connected to the lower lock force transmission assembly 1 through a supporting structure including a reinforcing plate 32 and a column 33; the reinforcing plate 32 and the column 33 are arranged bilaterally symmetrically.

[0041] More detailed, such as Figure 3 As shown, the lower lock force transmission assembly 1 comprises a lower lock beam 11, two cross beams 12, a joint 13, a connection assembly 14 and a bolt group 15. There are two lower lock beams, which are symmetrically arranged at the long girders axis on the left and right sides of the fuselage and installed on the outer surface of the fuselage skin. Each lower lock beam is also provided with two single-ear joints for connecting the landing gear on the same side as the lower lock beam; there are two cross beams, which are arranged at the common frame 31 in front and behind the landing gear along the heading of the aircraft; there are 4 groups of joints, which are arranged on the left and right sides of the common frame 31 in front and behind the landing gear, respectively, and fit with the inner surface of the fuselage skin.

[0042] like Figure 4 , Figure 5 , Figure 6As shown, the connection assembly 14 includes a flange connector 14a, a web connector I 14b, a web connector II 14c, and a connecting piece 14c, wherein: the flange connector 14a and the connecting piece 14c are flat pieces; the web connector I 14b is a U-shaped machined piece, and is provided with vertical ribs at the connection between the cross beam 12 and the joint 13; the web connector II 14c is an L-shaped machined piece. The left and right ends of the front and rear cross beams 12 inside the fuselage are respectively connected to the joint 13 through the connection assembly 14 to form an integral bearing structure, and then connected to the lower locking beam 11 outside the fuselage through four bolt groups 15 to form a closed frame structure. The cross beam 12 and the joint 13 have the same cross section at the connection, which is more conducive to connecting the two by the connecting component 14. The upper web of the cross beam 12 and the joint 13 are connected by the web connector Ⅰ14b, and the lower web is connected by two front and rear connectors Ⅱ14c; the edge strips of the cross beam 12 and the joint 13 are connected by the outer edge strip connector 14a and the web connector Ⅰ14b and the web connector Ⅱ14c, and the web ribs of the cross beam and the joint are connected by two connecting plates (14d) on both sides. Among them, a gap δ=0.5~1 (mm) is left between the web connector Ⅰ14b and the edge strip of the crossbeam 12; the design of this gap is on the one hand to obtain better assembly processability, and on the other hand, when the aircraft landing gear is lowered, the lower locking point arranged on the fuselage locks the landing gear and bears the ground load of the landing gear through the force transmission component. During the load transfer process, under the action of the lateral support force and the aircraft's own gravity, adaptive adjustment can be achieved between the two sections of the lower locking beams and the two sections of the crossbeams. While ensuring the load, the aircraft is finally in a horizontal and stable state.

[0043] like Figure 7 As shown, the lower locking beam 11 is made of TC18 titanium alloy forging material and is an "I"-shaped profile machined beam structure; two boss bushings are pressed at both ends of the two single-ear joint ear holes. The flange connecting the lower locking beam 11 to the surface of the fuselage 3 is locally thickened at the web of the single-ear joint.

[0044] like Figure 8 As shown, the cross beam 12 is an "I"-section machine-added beam made of 7050-T7451 material, with a plurality of vertical ribs arranged along the length direction. At the same time, a transverse vertical rib 12c is provided along the length direction on the plane of the common frame 31 on the lower surface of the web, which is used to connect the supporting structure including the reinforcing plate 32 and the column 33.

[0045] like Fig. 9 As shown, the joint 13 is made of titanium alloy forgings, the overall part is T-shaped, a plurality of vertical ribs are arranged along the length direction of the beam, and the upper and lower sides are multi-slot cavity structures, which is conducive to load transmission after the bolt group 15 is installed.

[0046] In order to facilitate the understanding of the load transfer path of the force transmission component, such as Fig.10As shown, in the center plane where the cross beam 12 is located, the intersection points of the common frame 31 and the outer shape of the fuselage 3 are respectively O1 and O2, the center point of the landing gear 2 buffer support is O′, and the centers of the two single-ear joint ear holes of the lower locking beam 11 are respectively located on the lines O′O1 and O′O2. The purpose of this design is to ensure that after the landing gear 2 is lowered and connected to the fuselage 3, the landing gear ground load generated when the aircraft lands or taxis on the ground can be more directly transmitted to the cross beam through the ear holes without generating additional bending moment. It can be understood that, assuming that the landing gear 2 is subjected to force F or bending moment M, it can be decomposed into F1 and F2, and then the load is transmitted to the single-ear joint of the lower locking beam 11 through the locking arm of the landing gear 2. At the joint, it is further decomposed into transverse loads F3 and F4 and longitudinal loads F5 and F6. The transverse loads F3 and F4 are then transmitted to the cross beam 12 through the four bolt groups 15, and the longitudinal loads F5 and F6 are borne by the lower locking beam 11, and finally diffused to the fuselage skin. Among them, F1 is along the O′O1 direction, and F2 is along the O′O2 direction, and the bolt group 15 bears the combined tensile and shear loads. By setting a reinforcement structure on the common frame 31 within a certain distance in front and behind the landing gear 2 to form positive and negative fulcrums, the landing gear load is cleverly converted to the reinforcement structure, and the load transfer of the landing gears on both sides is just in opposite directions, which can offset each other in the structure; at the same time, the structural design increases the support reaction arm, which is more conducive to improving the load-bearing efficiency, while ensuring that the force line transfer is more direct, avoiding the generation of additional additional bending moment, and to a certain extent, it is conducive to improving the structural fatigue performance.

[0047] For the lower lock force transmission assembly 1 disclosed in the above embodiment, it can be understood by those skilled in the art that the lower lock beam 11 uses TC18 titanium alloy forgings, which is a better choice based on the fact that the parts are exposed to the fuselage and are in a harsh corrosive environment, and taking into account factors such as structural weight reduction and load-bearing. At the same time, considering that the lower lock beam 11 will simultaneously bear tension, compression, shear and bending moment, an "I"-shaped cross-section beam structure is adopted.

[0048] For the lower lock force transmission assembly 1 disclosed in the above embodiment, it can be understood by those skilled in the art that the connection between the cross beam 12 and the common frame 31 through the reinforcing plate 32 and the reinforcing profile 33 is to further support the cross beam 12 on the premise that the cross beam 12 itself ensures stability, but it is not the only measure to ensure the compressive stability of the cross beam 12.

[0049] For the lower lock force transmission assembly 1 disclosed in the above embodiment, those skilled in the art can understand that the load borne by each single ear joint of the lower lock beam 11 is transmitted through the four bolt groups 18 .

[0050] In some optional embodiments, the lower locking beam 11 may be made of high-strength steel materials such as 4130.

[0051] In some optional embodiments, the joint 13 may also be a combination of two joints in front of the frame and in the back of the frame connected by fasteners.

[0052] The above specific implementation methods or cases are only used to explain the technical solutions of the present invention, and are not intended to limit the present invention. Any parts not described in detail are regarded as conventional technical means in the art. A person of ordinary skill in the art should understand that based on the design concept of the present application, the technical solutions described in the aforementioned implementation methods should be adaptively modified, or some or all of the technical features therein should be replaced by equivalents. These modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A side-mounted landing gear lower lock force transmission assembly, characterized in that: The lower lock force transmission assembly is a bilaterally symmetrical structure, comprising a lower lock beam, a cross beam, a joint, a connecting assembly and a bolt group; There are two lower locking beams, which are arranged at the axis of the fuselage long truss and the outer surface of the left and right skin of the fuselage; each lower locking beam is also provided with two single-ear joints for connecting the landing gear on the same side as the lower locking beam; the cross beams include two, which are arranged at the common frames in front and behind the landing gear along the heading of the aircraft; there are four groups of joints, which are arranged on the left and right sides of the common frames in front and behind the landing gear, respectively, and fit with the inner surface of the fuselage skin; it also includes multiple groups of bolt groups, which are arranged on the left and right joints of the front and rear common frames respectively; the cross beams, joints, and connecting components are all located inside the fuselage; The left and right ends of the cross beam are connected to the joints through connecting components to form an integral load-bearing structure inside the fuselage, and then connected to the lower locking beam on the outer surface of the fuselage skin through a bolt group to form a closed frame structure.

2. A side-mounted landing gear lower lock force transmission assembly as claimed in claim 1, characterized in that: In the closed frame structure, in the center plane where the crossbeam is located, the intersection points of the common frame and the fuselage shape are O1 and O2 respectively, the center point of the landing gear strut is O′, and the centers of the two single-ear joint ear holes of the lower locking beam are respectively located on the lines O′O1 and O′O2.

3. A side-mounted landing gear lower lock force transmission assembly as claimed in claim 1 or 2, characterized in that: The left and right ends of the two beams are connected to the joints in the same manner, and the cross-sections of the beams and the joints at the connection are the same; specifically: the webs of the beams and the joints are connected via web connectors I and II, the flanges of the beams and the joints are connected via flange connectors, web connectors I and web connectors II, and the web ribs of the beams and the joints are connected via two connecting plates on both sides; a gap is left between the web connector I and the beam flanges.

4. A side-mounted landing gear lower lock force transmission assembly as claimed in claim 1, characterized in that: The edge strip connector and the connecting piece are flat plate parts; the web connector I is a U-shaped machined part and is provided with vertical ribs; the web connector II is an L-shaped machined part.

5. The side-mounted landing gear lower lock force transmission assembly according to claim 1, characterized in that: The single ear joint of the lower locking beam is arranged near the frame station where the cross beam is located.

6. A side-mounted landing gear lower lock force transmission assembly as claimed in claim 5, characterized in that: Two bushings are respectively inlaid in the two single-ear joint ear holes of the lower lock beam, and the bushing material is selected from 15-5PH.

7. A side-mounted landing gear lower lock force transmission assembly as claimed in claim 6, characterized in that: The lower locking beam is an I-shaped beam structure.

8. The side-mounted landing gear lower lock force transmission assembly according to claim 1, characterized in that: The cross beam is a "I"-shaped section machine-added beam structure.

9. A side-mounted landing gear lower lock force transmission assembly as claimed in claim 8, characterized in that: A vertical rib is arranged at the center of the lower surface of the web of the cross beam along the length direction of the beam.

10. The side-mounted landing gear lower lock force transmission assembly according to claim 1, characterized in that: The joint is T-shaped as a whole, with a plurality of vertical ribs arranged along the length direction of the cross beam, and a multi-slot cavity structure on the upper and lower sides.

Citation Information

Patent Citations

  • Mounting beam for auxiliary power unit of aircraft

    CN102849218A

  • Main landing gear opening structure of high-wing general aircraft

    CN106184694A

  • Truss-type main undercarriage butt-joint frame

    CN107521670A

  • Support structure for aircraft landing gear

    CN115107994A