Fabricated temporary steel trestle for tunnel construction
By designing support frames and operating boxes in tunnel construction trests, rapid fixation and construction of adjacent trests are achieved, which solves the problem of difficulty in rapid splicing and building in the existing technology, and improves construction efficiency and flexibility .
Patent Information
- Application Number
- CN202410997780.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-11-08
AI Technical Summary
It is difficult to quickly splice and fix steel trests of different lengths for existing tunnel construction, which cannot meet construction needs.
A prefabricated temporary steel trest bridge including the first steel plate and the second steel plate is designed. By installing a support frame, an operating box, a slot, a card block, a worm gear, an elliptical wheel and a double-section connecting rod at the bottom of the steel plate, the shaking is used. The rotation of the driving worm and worm gear is linked to the movement of the double-section connecting rod and the connecting block, so as to achieve the fixing of the limit block and the clamp block, and quickly fix the two adjacent trests.
The rapid splicing of adjacent trestles and the construction of steel trestles of different lengths are realized, which simplifies the construction process and improves construction efficiency and flexibility.
Smart Images

Figure CN118910995A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel trestles, in particular to an assembled temporary steel trestle for tunnel construction. Background Art
[0002] Tunnels are engineering structures buried in the ground, and are a form of human use of underground space. Tunnels can be divided into traffic tunnels, hydraulic tunnels, municipal tunnels, and mining tunnels. During tunnel construction, poor geological conditions and abundant groundwater are often encountered, and such adverse conditions are a high-probability event. Trestle bridges are often used to transport equipment and materials. In civil engineering, trestles are temporary bridge facilities built for transporting materials, equipment, and personnel. They are divided into wooden trestles and steel trestles according to the materials used.
[0003] The patent with application number CN201921496897.6 discloses a trestle steel structure for tunnel construction, including a steel panel, a steel bottom bar, a support bar and a cross bar, wherein the steel panel is arranged on the upper part of the steel bottom bar, the cross bar is arranged at the bottom of the steel panel and its two ends are welded to the steel bottom bar, the support bar is arranged between the steel panel and the cross bar, and the two ends of the support bar are respectively connected to the steel panel and the cross bar through plug-ins, the bottom of the steel panel is fixedly connected with an insert cylinder, the outer side of the upper part of the steel bottom bar is threadedly connected with an insert block, and the steel bottom bar and the insert cylinder are plugged through the insert block; the plug-in between the insert cylinder and the insert block makes the installation between the steel panel and the steel bottom bar simple and firm, and easy to reuse, and the plug-in is arranged, because the vertical or inclined baffles arranged on the plug-in meet the connection of support bars with different inclination angles, so as to support the entire trestle steel structure, and the structure is easy to construct, uses less steel, and has obvious economic advantages.
[0004] However, in the above patent, it is not convenient to quickly splice and fix two adjacent steel trestles, and it is not convenient to build and use steel trestles of different lengths according to construction requirements.
[0005] Based on this, this plan proposes an assembled temporary steel trestle for tunnel construction. Summary of the invention
[0006] The object of the present invention is to provide a temporary assembled steel trestle for tunnel construction to solve the problems raised in the above-mentioned background technology.
[0007] To achieve the above object, the present invention provides the following technical solution: a temporary assembled steel trestle for tunnel construction, comprising a first steel plate and a second steel plate,
[0008] The bottom of the first steel plate and the second steel plate are both fixedly installed with a support frame, the bottom of the first steel plate is fixedly installed with an operation box, and two slots are provided on one side of the steel plate close to the second steel plate, and through holes are provided at the junction of the two slots and the operation box, and vertical rods are movably installed in the two through holes, and the top ends of the two vertical rods are fixedly installed with limit blocks, and the bottom ends of the two vertical rods are fixedly installed with square blocks;
[0009] Two plastic blocks are fixedly installed in the operation box, and a round rod is rotatably installed in the operation box, a worm wheel and an elliptical wheel are fixedly sleeved on the round rod, movable holes are opened on the two plastic blocks, cross bars are movably installed in the two movable holes, two ends of the two cross bars close to each other are rotatably installed with double-section connecting rods between the elliptical wheels, and connecting blocks are fixedly installed on the ends of the two cross bars away from each other, and extrusion shafts are rotatably installed on the two connecting blocks, and inclined holes are opened on the two square blocks, and the two extrusion shafts are movably installed in the corresponding inclined holes respectively;
[0010] A worm meshing with the worm wheel is rotatably mounted at the bottom of the operating box;
[0011] Two clamping blocks adapted to the clamping slots are fixedly mounted on one side of the second steel plate close to the first steel plate;
[0012] The bottoms of the two clamping blocks are both provided with limiting grooves matched with the limiting blocks.
[0013] Preferably, both support frames are made of stainless steel.
[0014] Preferably, counterweights are fixedly mounted on both sides of the bottom of the two support frames.
[0015] By adopting the above technical solution, the stability of both sides can be increased by the counterweight blocks, thereby preventing the trestle from tipping over.
[0016] Preferably, a crank is fixedly sleeved on the bottom end of the worm.
[0017] By adopting the technical solution, the worm can be easily rotated by the crank.
[0018] Preferably, first springs are sleeved on the two vertical rods, one end of the two first springs is fixed on the corresponding vertical rod, and the other end is fixed on the inner wall of the corresponding through hole.
[0019] By adopting the above technical solution, the vertical rod can be easily reset by the first spring.
[0020] Preferably, the two cross bars are sleeved with second springs, one end of the two second springs is fixed to the corresponding cross bar, and the other end is fixed to the inner wall of the corresponding movable hole.
[0021] By adopting the above technical solution, the second spring facilitates the resetting of the cross bar.
[0022] An assembled temporary steel trestle for tunnel construction includes the following steps:
[0023] Step S1: The device can be carried to the tunnel construction site. When two adjacent trestles need to be spliced, the two card blocks on the second steel plate can be firstly inserted into the corresponding card slots respectively;
[0024] Step S2: Then, the cranking handle drives the worm to rotate, the worm drives the worm wheel to rotate, the worm wheel drives the round rod and the elliptical wheel to rotate, the elliptical wheel drives the two double-section connecting rods to rotate, the two double-section connecting rods drive the movement of the two cross bars, and thus the movement of the two connecting blocks;
[0025] Step S3: During the movement of the extrusion shafts on the two connecting blocks, the corresponding inclined holes are respectively squeezed, thereby driving the two square blocks to move upward, thereby driving the two limit blocks to move upward;
[0026] Step S4: The two limit blocks are respectively inserted into the bottom of the corresponding card blocks, so that the two card blocks can be fixed in the corresponding card slots, the first steel plate and the second steel plate can be quickly fixed, and the two adjacent trestles can be quickly fixed, which is convenient for building and using steel trestles of different lengths according to construction requirements.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] The adjacent trestles can be spliced together, and then the worm can be driven to rotate by turning the crank handle, which can drive the two limit blocks to move upward, so that the two limit blocks are respectively stuck in the bottom of the corresponding blocks, and the two blocks can be fixed in the corresponding slots, so that the first steel plate and the second steel plate can be quickly fixed, and the two adjacent trestles can be quickly fixed, so that steel trestles of different lengths can be built and used according to construction requirements. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a schematic diagram of the structure of the present invention;
[0030] Figure 2 A three-dimensional diagram of the internal structure of the operating box of the present invention;
[0031] Figure 3 This is a schematic diagram of the structure of part A of the present invention;
[0032] Figure 4 This is a schematic diagram of the structure of part B of the present invention;
[0033] Figure 5 It is a schematic diagram of the top structure of the present invention.
[0034] In the figure: 1. first steel plate; 2. slot; 3. block; 4. second steel plate; 5. operating box; 6. counterweight; 7. support frame; 8. first spring; 9. vertical rod; 10. square block; 11. inclined hole; 12. worm; 13. connecting block; 14. cross bar; 15. second spring; 16. extrusion shaft; 17. limit block; 18. crank; 19. worm gear; 20. elliptical wheel; 21. double-section connecting rod; 22. round rod. DETAILED DESCRIPTION
[0035] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] See also Figure 1-5The present invention provides a technical solution: an assembled temporary steel trestle for tunnel construction, comprising a first steel plate 1 and a second steel plate 4, a support frame 7 is fixedly installed at the bottom of the first steel plate 1 and the second steel plate 4, an operation box 5 is fixedly installed at the bottom of the first steel plate 1, and two card slots 2 are provided on one side of the steel plate 1 close to the second steel plate 4, through holes are provided at the junction of the two card slots 2 and the operation box 5, vertical rods 9 are movably installed in the two through holes, and limited blocks 17 are fixedly installed at the top ends of the two vertical rods 9, and square blocks 10 are fixedly installed at the bottom ends of the two vertical rods 9, and the two vertical rods 9 are fixedly installed. A first spring 8 is sleeved on each of the two first springs 8, one end of the two first springs 8 is fixed on the corresponding vertical rod 9, and the other end is fixed on the inner wall of the corresponding through hole. Two plastic blocks are fixedly installed in the operation box 5, and a round rod 22 is rotatably installed in the operation box 5. A worm gear 19 and an elliptical wheel 20 are fixedly sleeved on the round rod 22. A movable hole is opened on the two plastic blocks, and a cross bar 14 is movably installed in the two movable holes. A double-section connecting rod 21 is rotatably installed between the elliptical wheel 20 at one end of the two cross bars 14 that are close to each other, and a connecting block 13 is fixedly installed at one end of the two cross bars 14 that are away from each other. The connecting block 13 is rotatably mounted with an extrusion shaft 16, and the two square blocks 10 are provided with an inclined hole 11. The two extrusion shafts 16 are movably mounted in the corresponding inclined holes 11. The two cross bars 14 are sleeved with a second spring 15, and one end of the two second springs 15 is fixed to the corresponding cross bar 14, and the other end is fixed to the inner wall of the corresponding movable hole. The bottom of the operating box 5 is rotatably mounted with a worm 12 meshing with a worm wheel 19, and the bottom end of the worm 12 is fixedly sleeved with a crank 18. Through the above-mentioned structural setting, the two blocks 3 on the second steel plate 4 are respectively inserted into the corresponding The crank handle 18 is then turned to drive the worm 12 to rotate, the worm 12 drives the worm wheel 19 to rotate, the worm wheel 19 drives the round rod 22 and the elliptical wheel 20 to rotate, the elliptical wheel 20 drives the two double-section connecting rods 21 to rotate, the two double-section connecting rods 21 drive the movement of the two cross bars 14, and then drive the movement of the two connecting blocks 13. During the movement, the extrusion shafts 16 on the two connecting blocks 13 squeeze the corresponding inclined holes 11 respectively, which can drive the two square blocks 10 to move upward, and can drive the two limit blocks 17 to move upward.
[0037] Combination Figure 1-3 As shown, two blocks 3 adapted to the slots 2 are fixedly installed on one side of the second steel plate 4 close to the first steel plate 1, and the bottoms of the two blocks 3 are provided with limit slots adapted to the limit blocks 17. Through the above-mentioned structural setting, the two limit blocks 17 are respectively inserted into the bottoms of the corresponding blocks 3, so that the two blocks 3 can be fixed in the corresponding slots 2, and the first steel plate 1 and the second steel plate 4 can be quickly fixed, and the two adjacent trestles can be quickly fixed, which is convenient for building and using steel trestles of different lengths according to construction requirements.
[0038] Combination Figure 1-2 As shown, the two support frames 7 are both made of stainless steel, and counterweights 6 are fixedly installed on both sides of the bottom of the two support frames 7. Through the above-mentioned structural setting, the counterweights 6 can increase the stability of both sides and prevent the trestle from tipping over.
[0039] An assembled temporary steel trestle for tunnel construction, characterized in that it includes the following operating steps:
[0040] Step S1: The device can be carried to the tunnel construction site. When two adjacent trestles need to be spliced, the two card blocks 3 on the second steel plate 4 can be firstly inserted into the corresponding card slots 2 respectively;
[0041] Step S2: Then, the crank 18 is turned to drive the worm 12 to rotate, the worm 12 drives the worm wheel 19 to rotate, the worm wheel 19 drives the round rod 22 and the elliptical wheel 20 to rotate, the elliptical wheel 20 drives the two double-section connecting rods 21 to rotate, the two double-section connecting rods 21 drive the movement of the two cross bars 14, and thus drive the movement of the two connecting blocks 13;
[0042] Step S3: During the movement, the extrusion shafts 16 on the two connecting blocks 13 respectively squeeze the corresponding inclined holes 11, thereby driving the two square blocks 10 to move upward, thereby driving the two limit blocks 17 to move upward;
[0043] Step S4: The two limit blocks 17 are respectively inserted into the bottom of the corresponding card blocks 3, so that the two card blocks 3 can be fixed in the corresponding card slots 2, and the first steel plate 1 and the second steel plate 4 can be quickly fixed, and the two adjacent trestles can be quickly fixed, which is convenient for building and using steel trestles of different lengths according to construction requirements.
[0044] The present invention can carry the device to the tunnel construction site. When two adjacent trestles need to be spliced, the two card blocks 3 on the second steel plate 4 can be respectively inserted into the corresponding card slots 2, and then the crank 18 is turned to drive the rotation of the worm 12, the worm 12 drives the rotation of the worm wheel 19, the worm wheel 19 drives the rotation of the round rod 22 and the elliptical wheel 20, the elliptical wheel 20 drives the rotation of the two double-section connecting rods 21, the two double-section connecting rods 21 drive the movement of the two cross bars 14, and then drive the movement of the two connecting blocks 13. During the movement, the extrusion shafts 16 on the two connecting blocks 13 respectively squeeze the corresponding inclined holes 11, which can drive the two square blocks 10 to move upward, and drive the two limit blocks 17 to move upward, so that the two limit blocks 17 are respectively stuck in the bottom of the corresponding card blocks 3, and the two card blocks 3 can be fixed in the corresponding card slots 2, and the first steel plate 1 and the second steel plate 4 can be quickly fixed, and the two adjacent trestles can be quickly fixed, which is convenient for building and using steel trestles of different lengths according to construction requirements. The present invention has a simple structure and is easy to use. The described assembled temporary steel trestles for tunnel construction are convenient for quickly splicing and fixing two adjacent steel trestles, and are not convenient for building and using steel trestles of different lengths according to construction requirements, and are convenient for tunnel construction.
[0045] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in the field. Although the embodiments of the present invention have been shown and described, it is understood by ordinary technicians in the field that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principle and spirit of the present invention. The scope of the present invention is defined by the attached claims and their equivalents.
Claims
1. A temporary assembled steel trestle for tunnel construction, comprising a first steel plate (1) and a second steel plate (4), Features: The bottoms of the first steel plate (1) and the second steel plate (4) are both fixedly mounted with a support frame (7), the bottom of the first steel plate (1) is fixedly mounted with an operating box (5), and two slots (2) are provided on one side of the steel plate (1) close to the second steel plate (4), both slots (2) are provided with through holes at the junction with the operating box (5), vertical rods (9) are movably mounted in the two through holes, the tops of the two vertical rods (9) are both fixedly mounted with limit blocks (17), and the bottoms of the two vertical rods (9) are both fixedly mounted with square blocks (10); Two plastic blocks are fixedly installed in the operating box (5), and a round rod (22) is rotatably installed in the operating box (5), and a worm wheel (19) and an elliptical wheel (20) are fixedly sleeved on the round rod (22); The two plastic blocks are each provided with a movable hole, and a cross bar (14) is movably installed in each of the two movable holes. A double-section connecting rod (21) is rotatably installed between the ends of the two cross bars (14) that are close to each other and the elliptical wheel (20), and a connecting block (13) is fixedly installed on the ends of the two cross bars (14) that are away from each other. The two connecting blocks (13) are both rotatably mounted with extrusion shafts (16), the two square blocks (10) are both provided with inclined holes (11), and the two extrusion shafts (16) are movably mounted in the corresponding inclined holes (11); A worm (12) meshing with a worm wheel (19) is rotatably mounted at the bottom of the operating box (5); Two clamping blocks (3) adapted to the clamping slots (2) are fixedly mounted on a side of the second steel plate (4) close to the first steel plate (1); The bottoms of the two clamping blocks (3) are each provided with a limiting groove matched with the limiting block (17).
2. The assembled temporary steel trestle for tunnel construction according to claim 1, Features: The two support frames (7) are both made of stainless steel.
3. The assembled temporary steel trestle for tunnel construction according to claim 1, Features: Counterweight blocks (6) are fixedly mounted on both sides of the bottom of the two support frames (7).
4. The assembled temporary steel trestle for tunnel construction according to claim 1, Features: The bottom end of the worm (12) is fixedly sleeved with a crank (18).
5. The assembled temporary steel trestle for tunnel construction according to claim 1, Features: The two vertical rods (9) are sleeved with first springs (8), one end of the two first springs (8) is fixed on the corresponding vertical rod (9), and the other end is fixed on the inner wall of the corresponding through hole.
6. The assembled temporary steel trestle for tunnel construction according to claim 1, Features: The two cross bars (14) are sleeved with second springs (15), one end of the two second springs (15) is fixed on the corresponding cross bar (14), and the other end is fixed on the inner wall of the corresponding movable hole.
7. The assembled temporary steel trestle for tunnel construction according to claim 1, Features: The steps are as follows: Step S1: The device can be carried to the tunnel construction site. When two adjacent trestles need to be spliced, the two card blocks (3) on the second steel plate (4) can first be inserted into the corresponding card slots (2) respectively; Step S2: Then, the crank (18) is rotated to drive the worm (12), the worm (12) drives the worm wheel (19), the worm wheel (19) drives the round rod (22) and the elliptical wheel (20), the elliptical wheel (20) drives the two double-section connecting rods (21) to rotate, the two double-section connecting rods (21) drive the movement of the two cross bars (14), and thus drive the movement of the two connecting blocks (13); Step S3: During the movement, the extrusion shafts (16) on the two connecting blocks (13) respectively squeeze the corresponding inclined holes (11), thereby driving the two square blocks (10) to move upward, thereby driving the two limit blocks (17) to move upward; Step S4: The two limit blocks (17) are respectively inserted into the bottom of the corresponding clamping blocks (3), so that the two clamping blocks (3) can be fixed in the corresponding clamping grooves (2), and the first steel plate (1) and the second steel plate (4) can be quickly fixed, and the two adjacent trestles can be quickly fixed, so that steel trestles of different lengths can be built and used according to construction requirements.
Citation Information
Patent Citations
Trestle steel structure for tunnel construction
CN211312158U
Cited By
Steel grid building structure of fabricated overhead bridge
CN120350602A