Method for stabilizing high and steep slope of bauxite goaf and application of method

By building a drainage system, excavating slope reduction zones, compacting soil and spreading plant seeds, the complexity and high cost of stabilizing slopes in high steep slopes in bauxite goafs are solved, and the ecological environment and slopes are quickly restored Stability, vegetation coverage rate reaches 95%.

CN118911161APending Publication Date: 2024-11-08GUANGXI PANGU ECOLOGICAL ENVIRONMENT ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410973051.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The prior art method for high steep slope stabilization methods for bauxite goaf is complex, costly and long recovery time, so it is impossible to quickly restore the ecological environment.

Method used

Build a drainage system, excavate the slope reduction zone, compact the soil and lay non-woven bags, mix the feces organic fertilizer and topsoil, spread plant seeds with wide adaptability, and form stable root and soil composites to improve slope stability.

Benefits of technology

The rapid stability of the high steep slopes in the bauxite goaf and the recovery of the ecological environment have been achieved. The vegetation coverage rate has reached 95% within two years, avoiding soil erosion and geological disasters, and the method is simple and cost-effective.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911161A_ABST
    Figure CN118911161A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of ecological restoration, in particular to a method for stabilizing a high and steep slope of a bauxite goaf and application of the method. The method comprises the following steps: (1) constructing a perfect drainage system: constructing a barrier and a drainage ditch at a position 1.5-2.5 m above the bauxite goaf; (2) reducing steep slope and stabilizing slope: excavating slope reducing belts every 1-3 meters from the top of the high steep slope of the bauxite goaf to the bottom of the slope; (3) the slope is pressed and stabilized, specifically, soil of the slope of the downhill zone is pressed tightly, and the slope of the downhill zone is stabilized; (4) slope stabilization of vegetation: mixing manure organic fertilizer with surface soil to obtain a modifier, applying the modifier into the downhill zone, and sowing plant seeds. According to the method for treating the high and steep side slope of the bauxite goaf, the ecological environment with the vegetation coverage rate being 95% or above can be obtained within two years, and a basis is provided for stabilizing the high and steep side slope of the bauxite goaf.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of ecological restoration, and in particular to a method for stabilizing high and steep slopes in a bauxite goaf area and an application thereof. Background Art

[0002] Pingguo Bauxite Mine is the bauxite raw material production base of Aluminum Corporation of China Guangxi Branch. The region is rich in mineral resources. According to the current mining scale of Pingguo Bauxite Mine, the annual mining covers an area of ​​3,500 mu, and the entire mine will eventually occupy nearly 100,000 mu of mining land. After bauxite mining, high and steep slopes appear, with a height of more than 20 meters and a slope of more than 60°. The appearance of high and steep slopes is likely to form strong surface runoff on the slope, affecting the stability of the slope and the stability of the ecological environment. The methods currently used to stabilize high and steep slopes include anti-slide piles, anchoring, concrete shear structures, retaining, frame beams, etc. These methods are complex and costly to operate, and some cannot even grow crops. The ecological balance is restored only by seeds in the topsoil, and the recovery time is very long.

[0003] Based on this, a method for stabilizing the steep slopes in bauxite goaf areas that is easy to operate, low in cost, effective, green, and can quickly restore the ecological environment is urgently needed. Summary of the invention

[0004] The purpose of the present invention is to provide a method for stabilizing the high and steep slopes in the goaf of bauxite mines and its application.

[0005] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions:

[0006] The present invention provides a method for stabilizing a high and steep slope in a bauxite goaf area, comprising the following steps:

[0007] (1) Build a complete drainage system: build dams and drainage ditches 1.5 to 2.5 meters above the bauxite goaf;

[0008] (2) Steepness reduction and slope stabilization: From the top of the steep slope to the bottom of the bauxite goaf, a slope reduction belt is excavated every 1 to 3 meters;

[0009] (3) Slope compression and stabilization: Compact the soil on the slope of the slope-drop zone to stabilize the slope of the slope-drop zone;

[0010] (4) Vegetation stabilization: Mixing manure organic fertilizer with topsoil to obtain an improver, applying the improver to the slope reduction belt, and sowing plant seeds;

[0011] The plant seeds include tree seeds, shrub seeds, herbaceous plant seeds and vine plant seeds;

[0012] The weight ratio of the tree seeds: shrub seeds: herbaceous plant seeds: vine plant seeds is 3-5:3-5:5-7:1-3.

[0013] Preferably, the width of the slope reduction zone is 0.4 to 0.5 m.

[0014] Preferably, the method of compacting the soil on the slope of the slope reduction belt is: compacting the loose soil on the slope of the slope reduction belt by using a hook machine;

[0015] The method for stabilizing the slope of the slope reduction belt is as follows: a non-woven bag filled with heavy objects is laid on the slope of the slope reduction belt compacted by a hook machine;

[0016] The heavy objects include one or more of stones, rubble and waste soil;

[0017] The number of layers laid is 1 to 3;

[0018] The paving width is 0.30 to 0.40 m.

[0019] Preferably, the mass ratio of the feces organic fertilizer to the topsoil is 1:20-30;

[0020] The excrement organic fertilizer comprises the following components in parts by mass:

[0021] 50-60 parts of pig manure, 20-30 parts of chicken manure, 10-20 parts of peat, 20-30 parts of Chinese medicine residue, 3-8 parts of water retaining agent, 1-2 parts of EM bacterial agent, and 8-16 parts of compound fertilizer;

[0022] The Chinese medicine residue is a blood-tonifying and beauty-enhancing Chinese medicine residue;

[0023] The compound fertilizer is a nitrogen, phosphorus and potassium compound fertilizer;

[0024] The effective content of nitrogen in the compound fertilizer is ≥18%, the effective content of phosphorus is ≥18%, and the effective content of potassium is ≥18%;

[0025] The content of total nutrients in the compound fertilizer is ≥54%.

[0026] Preferably, the method for preparing the feces organic fertilizer is as follows:

[0027] Pig manure, chicken manure, peat, Chinese medicine residue and EM microbial agent are mixed to obtain a mixture, the water content of the mixture is adjusted to 60-65%, and the mixture is piled and fermented for 8-12 days to obtain a fermented material; the fermented material is mixed with a water retaining agent and a compound fertilizer, and granulated to obtain feces organic fertilizer.

[0028] Preferably, the temperature of the central pile during the pile fermentation is 40-65°C.

[0029] Preferably, the amount of the modifier applied to the slope reduction zone is 1500-2000 kg / mu.

[0030] Preferably, the tree seeds include one or more of pine seeds, Dalbergia cochinchinensis seeds, camphor seeds and Dalbergia odorifera seeds;

[0031] The shrub seeds include one or more of Amorpha fruticosa seeds, pigeon pea seeds, beech seeds, pigeon pea seeds, red willow seeds, willow of the sedge seeds, red back mountain hemp stems and vitex seeds;

[0032] The herbaceous plant seeds include one or more of forage grass seeds, large-leaf grass seeds, reed seeds, ramie seeds, benguet seeds, bidens pilosa seeds, foxtail grass, vetch seeds and dandelion seeds;

[0033] The vine plant seeds include one or more of kudzu vine seeds, oleifera vine seeds, euonymus fortunei seeds, calanthera chinensis seeds and saffron vine seeds.

[0034] Preferably, the amount of plant seeds sown is 10-20 kg / mu.

[0035] The present invention also provides application of the method in stabilizing the high and steep slopes in the bauxite goaf area or in repairing the ecological environment of the high and steep slopes in the bauxite goaf area.

[0036] The present invention provides a method for stabilizing the high and steep slopes in the bauxite goaf area and its application. The method of the present invention comprises the following steps: (1) constructing a complete drainage system: constructing a dam at 1.5 to 2.5 meters above the bauxite goaf area and constructing a drainage ditch; the purpose of constructing the dam is to intercept the surface runoff water on the upper slope of the goaf area and divert it to an area where geological disasters are not prone to occur, so as to prevent it from entering the steep slope surface, causing serious soil erosion on the steep slope surface, and even geological disasters such as landslides and collapses. The drainage ditch diverts the accumulated water on the steep slope surface away from the slope surface, preventing the accumulated water from invading the soil body, thereby affecting the stability of the slope surface. That is, the setting of the dam and the drainage ditch is to reduce the soil erosion caused by surface runoff and improve the stability of the slope. (2) Steepness reduction and slope stabilization: from the top to the bottom of the high and steep slope in the bauxite goaf area, a slope reduction belt is excavated every 1 to 3 meters; the setting of the slope reduction belt is to reduce the slope gradient and improve the stability of the slope surface. (3) Slope compression and stabilization: Compact the soil on the slope of the slope reduction belt to stabilize the slope of the slope reduction belt; Compact the slope surface, and use the stones, gravel and waste soil cleared during the slope reduction process to press the slope of the slope reduction belt to increase the stability of the slope surface. (4) Vegetation stabilization: Mix the manure organic fertilizer with the topsoil to obtain an improver, apply the improver to the slope reduction belt, and sow plant seeds; the present invention mixes the manure organic fertilizer with the topsoil, the topsoil is conducive to plant growth, and the manure organic fertilizer provides nutrition for plant growth. The plant seeds are taken from the plant seeds around the bauxite goaf area, which have wide adaptability and can quickly adapt to the surrounding environment. After germination for about half a month, the roots of the plants with developed root systems penetrate deep into the soil, and in about a month, they connect with the soil on the steep slope to form a stable root-soil complex, which significantly improves the soil stability and significantly enhances the slope stability. One year after sowing, the vegetation coverage rate of the steep slope reaches more than 80%, and there is no obvious soil erosion during this period, and no disasters such as landslides and collapses occur. Two years after sowing, the vegetation coverage rate of the high and steep slopes reaches more than 95%. In addition, the method of the invention is simple, easy to operate and low in cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is a high and steep slope in the bauxite mining area of ​​Matou Town;

[0038] Figure 2 This is a process diagram of steepening and stabilizing the slope;

[0039] Figure 3 This is the landscape picture after the slope is compressed and stabilized;

[0040] Figure 4 The landscape of the steep slope in the bauxite mining area of ​​Matou Town after one year of treatment;

[0041] Figure 5 This is the landscape of the steep slope in the bauxite goaf area of ​​Matou Town two years after treatment. DETAILED DESCRIPTION

[0042] The present invention provides a method for stabilizing a high and steep slope in a bauxite goaf area, comprising the following steps:

[0043] (1) Build a complete drainage system: build dams and drainage ditches 1.5 to 2.5 meters above the bauxite goaf;

[0044] (2) Steepness reduction and slope stabilization: From the top of the steep slope to the bottom of the bauxite goaf, a slope reduction belt is excavated every 1 to 3 meters;

[0045] (3) Slope compression and stabilization: Compact the soil on the slope of the slope-drop zone to stabilize the slope of the slope-drop zone;

[0046] (4) Vegetation stabilization: Mixing manure organic fertilizer with topsoil to obtain an improver, applying the improver to the slope reduction belt, and sowing plant seeds;

[0047] The plant seeds include tree seeds, shrub seeds, herbaceous plant seeds and vine plant seeds;

[0048] The weight ratio of the tree seeds: shrub seeds: herbaceous plant seeds: vine plant seeds is 3-5:3-5:5-7:1-3.

[0049] In the present invention, the location of the dam and drainage ditch is preferably 2 meters above the bauxite goaf. The purpose of the dam is to intercept the surface runoff water on the upper slope of the goaf and divert it to an area where geological disasters are not likely to occur, so as to prevent it from entering the steep slope surface, causing serious soil erosion on the steep slope surface, and even geological disasters such as landslides and collapses. The drainage ditch diverts the accumulated water on the steep slope surface away from the slope surface, preventing the accumulated water from invading the soil and affecting the stability of the slope surface.

[0050] In the present invention, the location of the slope reduction belt is preferably from the top to the bottom of the slope, and a slope reduction belt is excavated every 2 meters; the purpose of excavating the slope reduction belt is to reduce the slope of the steep slope and improve the stability of the slope.

[0051] In the present invention, the width of the slope reduction zone is 0.4-0.5 m, preferably 0.45 m.

[0052] In the present invention, the method of compacting the soil of the slope of the slope reduction belt is: using a hook machine to compact the loose soil of the slope of the slope reduction belt; the method of stabilizing the slope of the slope reduction belt is: laying a non-woven bag filled with heavy objects on the slope of the slope reduction belt compacted by the hook machine; the heavy objects include one or more of stones, gravel and waste soil; the number of layers of the laying is 1 to 3 layers, preferably 2 layers; the width of the laying is 0.30 to 0.40m, preferably 0.35m. The purpose of laying the non-woven bag filled with heavy objects is to stabilize the slope.

[0053] In the present invention, the mass ratio of the manure organic fertilizer to the topsoil is 1:20-30, preferably 1:25; the manure organic fertilizer includes the following components by mass: 50-60 parts of pig manure, preferably 55 parts; 20-30 parts of chicken manure, preferably 25 parts; 10-20 parts of peat, preferably 15 parts; 20-30 parts of Chinese medicinal residues, preferably 25 parts; 3-8 parts of water retaining agent, preferably 5 parts; 1-2 parts of EM bacterial agent, preferably 1.5 parts; 8-16 parts of compound fertilizer , preferably 12 parts; the Chinese medicine residue is a blood-enriching and beauty-enhancing Chinese medicine residue; the Chinese medicine residue is purchased from Nanning Yihua Trading Co., Ltd.; the compound fertilizer is a nitrogen-phosphorus-potassium compound fertilizer; the effective content of nitrogen in the compound fertilizer is ≥18%, preferably 18%; the effective content of phosphorus is ≥18%, preferably 18%; the effective content of potassium is ≥18%, preferably 18%; the content of total nutrients in the compound fertilizer is ≥54%, preferably 54%; in the present invention, the compound fertilizer is purchased from Gansu Sudi Fertilizer Co., Ltd. In the present invention, the water-retaining agent is purchased from Langfang Lanjin Environmental Protection Technology Co., Ltd.; in the present invention, the EM bacterial agent is purchased from Jinan Zimo Chemical Co., Ltd., and the effective viable bacteria count of the EM bacterial agent is 1×10 11 cfu / g.

[0054] In the present invention, the preparation method of the feces organic fertilizer is as follows:

[0055] Pig manure, chicken manure, peat, Chinese medicine residue and EM microbial agent are mixed to obtain a mixture, the water content of the mixture is adjusted to 60-65%, and the mixture is piled and fermented for 8-12 days to obtain a fermented material; the fermented material is mixed with a water retaining agent and a compound fertilizer, and granulated to obtain feces organic fertilizer.

[0056] In the present invention, the stacking fermentation time is preferably 10 days; and the temperature of the central pile during the stacking fermentation is 40-65°C.

[0057] In the present invention, the amount of the improver applied to the slope reduction zone is 1500-2000 kg / mu, preferably 1800 kg / mu.

[0058] In the present invention, the tree seeds include one or more of pine seeds, Dalbergia cochinchinensis seeds, camphor seeds and Dalbergia odorifera seeds;

[0059] The shrub seeds include one or more of Amorpha fruticosa seeds, pigeon pea seeds, beech seeds, pigeon pea seeds, red willow seeds, willow of the sedge seeds, red back mountain hemp stems and vitex seeds;

[0060] The herbaceous plant seeds include one or more of forage grass seeds, large-leaf grass seeds, reed seeds, ramie seeds, benguet seeds, bidens pilosa seeds, foxtail grass, vetch seeds and dandelion seeds;

[0061] The vine plant seeds include one or more of kudzu vine seeds, oleifera vine seeds, euonymus fortunei seeds, calanthera chinensis seeds and saffron vine seeds.

[0062] In the present invention, the amount of plant seeds sown is 10-20 kg / mu, preferably 15 kg / mu.

[0063] The present invention also provides application of the method in stabilizing the high and steep slopes in the bauxite goaf area or in repairing the ecological environment of the high and steep slopes in the bauxite goaf area.

[0064] The technical solutions provided by the present invention are described in detail below in conjunction with the embodiments, but they should not be construed as limiting the protection scope of the present invention.

[0065] In the embodiment of the present invention, the Chinese medicine residue is a blood-tonifying and beauty-enhancing Chinese medicine residue; the Chinese medicine residue was purchased from Nanning Yihua Trading Co., Ltd. The compound fertilizer is a nitrogen-phosphorus-potassium compound fertilizer; the compound was purchased from Gansu Sudi Fertilizer Co., Ltd., and the effective content of nitrogen, phosphorus and potassium in the compound is 18%, 18% and 18% respectively. The water-retaining agent was purchased from Langfang Lanjin Environmental Protection Technology Co., Ltd. The EM bacterial agent was purchased from Jinan Zimo Chemical Co., Ltd., and the effective viable bacteria count of the EM bacterial agent was 1×10 11 cfu / g.

[0066] Example 1

[0067] This embodiment is an experiment conducted in a bauxite mine goaf in Taiping Town, Pingguo City, Baise City, Guangxi Zhuang Autonomous Region. The height of the soil slope in the area is 25 meters and the slope angle is 75°. Figure 1 shown.

[0068] Take 500kg of pig manure, 300kg of chicken manure, 150kg of peat, 300kg of Chinese medicine residue for nourishing blood and beauty, and 20kg of EM microbial agent and mix them evenly to obtain a mixture. Adjust the water content of the mixture to 65% to obtain the material to be fermented. Pile the material to be fermented and ferment it. Control the temperature of the central pile to be 40-65℃. When the temperature exceeds 65℃, turn the pile. When the temperature is lower than 40℃, cover the pile and control the humidity of the environment to be 65%. Pile and ferment for 10 days. The fermentation pile emits a wine aroma. The fermentation is completed and the fermented material is obtained. Mix the fermented material with 50kg of water retaining agent and 160kg of compound fertilizer, granulate it, and obtain feces organic fertilizer for standby use.

[0069] Take seeds of plants around the bauxite goaf in Taiping Town, including 1kg of pine seeds, 1kg of camphor seeds, 1kg of Dalbergia odorifera, 2kg of pigeon pea seeds, 2kg of beech seeds, 1kg of dahlia seeds, 1kg of reed seeds, 1kg of forage grass seeds, 1kg of giant grass seeds, 1kg of Bidens pilosa, 1kg of dog bud root seeds, and 1kg of kudzu seeds, mix them evenly for later use.

[0070] A dam and drainage ditch was built 2 meters above the top of the slope in the bauxite goaf area in Taiping Town, Pingguo City. The specifications of the dam and drainage ditch were determined based on the rainfall in the area in recent years, and the sides and bottom of the dam and drainage ditch were hardened.

[0071] From the top to the bottom of the slope, a slope reduction strip with a width of 0.5m is excavated every 2m using a hook machine. Figure 2 Use a hook machine to compact the loose soil on the slope of the slope reduction belt, put the stones, gravel and waste soil when excavating the slope reduction belt into a degradable non-woven bag, and lay it on the slope of the slope reduction belt. Lay 2 layers with a laying width of 0.3m to complete the slope compaction and stabilization. Figure 3 shown.

[0072] The above-mentioned manure organic fertilizer was mixed with the topsoil discarded during the excavation of bauxite at a mass ratio of 1:30 to obtain an improver, which was applied to the slope reduction belt at an application rate of 1500kg / mu. After the soil was improved, the above-mentioned mixed seeds were sown at an amount of 15kg / mu. Management was carried out according to conventional methods.

[0073] 15 days after germination, it was observed that the roots of some plants had penetrated through the improver and entered deeper into the soil. 30 days after germination, it was observed that the roots of plants on the steep slopes penetrated deeper into the soil, forming a stable root-soil complex.

[0074] 30 days after germination, the soil of the sowing site was randomly sampled to test the content of total nitrogen, alkaline nitrogen, total phosphorus, available phosphorus, total potassium, available potassium, organic carbon, and the pH value of the soil, and compared with the nutrient composition and content of the soil before slope stabilization. The results are shown in Table 1.

[0075] Table 1 Effect of the method of Example 1 on nutrients in high and steep slope soil

[0076]

[0077] Different lowercase letters in the same column indicate significant differences among treatments (P < 0.05), and the same letters indicate no significant differences among treatments (P > 0.05).

[0078] Table 1 shows that after the high and steep slopes in the bauxite goaf area were treated by the method of the present invention, the nutrient content of the slope soil was significantly improved.

[0079] The landscape after one year of treating the high and steep slopes with the method of the present invention is as follows: Figure 4 As shown, the landscape after 2 years is as follows Figure 5 shown.

[0080] Figures 4-5It is shown that after one year of using the method of this embodiment to treat the high and steep slopes in the bauxite goaf area of ​​Taiping Town, the vegetation coverage rate reached 80%, and no soil erosion occurred during the period, let alone landslides, collapses and other geological disasters. After two years of using the method of this embodiment to treat the high and steep slopes in the bauxite goaf area of ​​Taiping Town, the vegetation coverage rate reached 95%, and a stable ecological management model of trees, shrubs, grasses and vines was obtained, and the stability of the high and steep slopes was more stable.

[0081] The ecological management cost of treating the high and steep slopes in the bauxite goaf of Taiping Town according to the method of this embodiment is significantly lower than other methods.

[0082] Example 2

[0083] This embodiment is an experiment conducted in a bauxite goaf area in Xin'an Town, Pingguo City, Baise City, Guangxi Zhuang Autonomous Region. The height of the soil slope in the area is 22 meters and the slope angle is 70°.

[0084] Take 600kg of pig manure, 200kg of chicken manure, 100kg of peat, 200kg of Chinese medicine residue for nourishing blood and beauty, and 10kg of EM microbial agent and mix them evenly to obtain a mixture. Adjust the water content of the mixture to 60% to obtain the material to be fermented. Pile the material to be fermented and ferment it. Control the temperature of the central pile to be 40-65℃. When the temperature exceeds 65℃, turn the pile. When the temperature is lower than 40℃, cover the pile and control the humidity of the environment to be 60%. Pile and ferment for 12 days. The fermentation pile emits a wine aroma. The fermentation is completed and the fermented material is obtained. Mix the fermented material with 80kg of water retaining agent and 80kg of compound fertilizer, granulate, and obtain feces organic fertilizer for standby use.

[0085] Take seeds of plants around the bauxite goaf in Xin'an Town, including 1kg pine seeds, 2kg Dalbergia odorifera seeds, 2kg camphor seeds, 1kg Amorpha fruticosa seeds, 1kg pigeon pea seeds, 1kg beech seeds, 1kg scutellaria baicalensis seeds, 1kg eryngii stalk seeds, 1kg redback mountain hemp stalk seeds, 1kg reed seeds, 1kg forage grass seeds, 1kg foxtail grass seeds, 1kg dandelion seeds, 1kg macrophylla seeds, 1kg dogtooth grass seeds, 1kg Bidens pilosa seeds, 1kg kudzu seeds, 1kg Euonymus fortunei seeds, and 1kg Sargentodactyla grandiflora seeds, mix them evenly for later use.

[0086] A water retaining and drainage ditch was built 1.8 meters above the top of the slope in the bauxite goaf area in Xin'an Town, Pingguo City. According to the rainfall in the area in recent years, the specifications of the water retaining and drainage ditch were determined, and the sides and bottom of the retaining and drainage ditch were hardened.

[0087] From the top to the bottom of the slope, a 0.5m wide slope reduction belt is excavated every 3 meters using a crane. The loose soil on the slope of the slope reduction belt is compacted using a crane, and the stones, gravel and waste soil from the excavation of the slope reduction belt are put into biodegradable non-woven bags and laid on the slope of the slope reduction belt in 3 layers with a laying width of 0.30m to complete the slope compaction and stabilization.

[0088] The above-mentioned manure organic fertilizer was mixed with the topsoil discarded during the excavation of bauxite at a mass ratio of 1:20 to obtain an improver, which was applied to the slope reduction belt at an application rate of 2000 kg / mu. After the soil was improved, the above-mentioned mixed seeds were sown at an amount of 20 kg / mu. Management was carried out according to conventional methods.

[0089] 30 days after germination, the soil of the sowing site was randomly sampled to test the content of total nitrogen, alkaline nitrogen, total phosphorus, available phosphorus, total potassium, available potassium, organic carbon, and the pH value of the soil, and compared with the nutrient composition and content of the soil before slope stabilization. The results are shown in Table 2.

[0090] Table 2 Effect of the method in Example 2 on nutrients in high and steep slope soil

[0091]

[0092] As shown in Table 2, after the bauxite goaf area in Xin'an Town, Pingguo City is treated with the method of Example 2, the soil in the area can be effectively improved to make it suitable for planting.

[0093] After one year of treatment of the bauxite goaf area in Xin'an Town using the method of Example 2, the vegetation coverage rate reached more than 85%, and after two years of treatment, the vegetation coverage rate reached more than 95%.

[0094] As can be seen from the above embodiments, the present invention provides a method for stabilizing the steep slopes in the bauxite goaf and its application. The method of the present invention comprises the following steps: (1) constructing a complete drainage system: constructing a drainage ditch 1.5 to 2.5 meters above the bauxite goaf; (2) reducing the steepness and stabilizing the slope: excavating a slope reduction belt every 1 to 3 meters from the top to the bottom of the steep slope in the bauxite goaf; (3) compressing the slope and stabilizing the slope: compacting the soil on the slope of the slope reduction belt to stabilize the slope of the slope reduction belt; (4) stabilizing the slope with vegetation: mixing manure organic fertilizer with topsoil to obtain an improver, applying the improver to the slope reduction belt, and sowing plant seeds. According to the method of the present invention, by treating the steep slopes in the bauxite goaf, an ecological environment including symbiosis of trees, shrubs, herbs and vines can be obtained in a short time, so that the vegetation coverage rate reaches more than 95% within 2 years, and no disasters such as soil erosion will occur. A new method is provided for stabilizing the steep slopes in the bauxite goaf.

[0095] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A method for stabilizing steep slopes in bauxite goaf areas, characterized in that: The steps include: (1) Build a complete drainage system: build dams and drainage ditches 1.5 to 2.5 meters above the bauxite goaf; (2) Steepness reduction and slope stabilization: From the top of the steep slope to the bottom of the bauxite goaf, a slope reduction belt is excavated every 1 to 3 meters; (3) Slope compression and stabilization: Compact the soil on the slope of the slope-drop zone to stabilize the slope of the slope-drop zone; (4) Vegetation stabilization: Mixing manure organic fertilizer with topsoil to obtain an improver, applying the improver to the slope reduction belt, and sowing plant seeds; The plant seeds include tree seeds, shrub seeds, herbaceous plant seeds and vine plant seeds; The weight ratio of the tree seeds: shrub seeds: herbaceous plant seeds: vine plant seeds is 3-5:3-5:5-7:1-3.

2. The method according to claim 1, characterized in that The width of the slope reduction zone is 0.4 to 0.5 m.

3. The method according to claim 2, characterized in that The method of compacting the soil on the slope of the slope reduction belt is: compacting the loose soil on the slope of the slope reduction belt by using a hook machine; The method for stabilizing the slope of the slope reduction belt is as follows: a non-woven bag filled with heavy objects is laid on the slope of the slope reduction belt compacted by a hook machine; The heavy objects include one or more of stones, rubble and waste soil; The number of layers laid is 1 to 3; The paving width is 0.30 to 0.40 m.

4. The method according to claim 3, characterized in that The mass ratio of the manure organic fertilizer to the topsoil is 1:20-30; The excrement organic fertilizer comprises the following components in parts by mass: 50-60 parts of pig manure, 20-30 parts of chicken manure, 10-20 parts of peat, 20-30 parts of Chinese medicine residue, 3-8 parts of water retaining agent, 1-2 parts of EM bacterial agent, and 8-16 parts of compound fertilizer; The Chinese medicine residue is a blood-tonifying and beauty-enhancing Chinese medicine residue; The compound fertilizer is a nitrogen, phosphorus and potassium compound fertilizer; The effective content of nitrogen in the compound fertilizer is ≥18%, the effective content of phosphorus is ≥18%, and the effective content of potassium is ≥18%; The content of total nutrients in the compound fertilizer is ≥54%.

5. The method according to claim 4, characterized in that The preparation method of the excrement organic fertilizer is as follows: Pig manure, chicken manure, peat, Chinese medicine residue and EM microbial agent are mixed to obtain a mixture, the water content of the mixture is adjusted to 60-65%, and the mixture is piled and fermented for 8-12 days to obtain a fermented material; the fermented material is mixed with a water retaining agent and a compound fertilizer, and granulated to obtain feces organic fertilizer.

6. The method according to claim 5, characterized in that During the stacking fermentation, the temperature of the central pile is 40-65°C.

7. The method according to claim 1 or 6, characterized in that: The amount of the modifier applied to the slope reduction zone is 1500 to 2000 kg / mu.

8. The method according to claim 7, characterized in that The tree seeds include one or more of pine seeds, Dalbergia cochinchinensis seeds, camphor seeds and Dalbergia odorifera seeds; The shrub seeds include one or more of Amorpha fruticosa seeds, pigeon pea seeds, beech seeds, pigeon pea seeds, red willow seeds, willow of the sedge seeds, red back mountain hemp stems and vitex seeds; The herbaceous plant seeds include one or more of forage grass seeds, large-leaf grass seeds, reed seeds, ramie seeds, benguet seeds, bidens pilosa seeds, foxtail grass, vetch seeds and dandelion seeds; The vine plant seeds include one or more of kudzu vine seeds, oleifera vine seeds, euonymus fortunei seeds, calanthera chinensis seeds and saffron vine seeds.

9. The method according to claim 8, characterized in that The amount of plant seeds sown is 10-20 kg / mu.

10. Use of the method according to any one of claims 1 to 9 in stabilizing the high and steep slopes in bauxite goaf areas or in restoring the ecological environment of the high and steep slopes in bauxite goaf areas.