PE pipe overhead construction method

By using a combination device of base, universal wheel, positioning platform, support roller and pneumatic fixture in PE pipe overhead construction, the problem of difficult alignment in PE pipe overhead construction is solved, and the stability of PE pipe in PE pipe under overhead state is achieved Alignment and docking improve construction efficiency.

CN118912266APending Publication Date: 2024-11-08FUJIAN HENGJIE PLASTIC IND NEW MATERIAL CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411274201.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The support and coaxial alignment of PE pipes before thermal welding during overhead construction is difficult, resulting in increased construction difficulty. It is urgent to improve the construction methods to achieve stable alignment support.

Method used

Using a PE pipe overhead construction device including a base, universal wheel, positioning platform, support roller, pneumatic fixture and rotatable positioning pallet structure, the initial positioning, axial adjustment and docking of the PE pipe is realized through the driving mechanism to ensure the PE pipe. Stable alignment and docking in overhead state.

Benefits of technology

Through the preliminary positioning of the supporting roller and pneumatic fixture and the lateral limiting of the rotatable pallet, stable axial alignment and docking of the PE pipe is achieved, simplifying the construction process and improving construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118912266A_ABST
    Figure CN118912266A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of PE pipe construction, in particular to a PE pipe overhead construction method. Firstly, the positioning platform is lowered, preliminary positioning of the PE pipe is facilitated under the action of the supporting rollers and the pneumatic clamp, by means of the rotatable positioning riding wheel structure, when the pneumatic clamp clamps and drags the PE pipe to move in the Y direction, the positioning riding wheel body plays a lateral limiting role, and after the PE pipe moves in place, the positioning riding wheel body is driven to rotate, so that the PE pipe is positioned in the Y direction. The supporting wheels serving as the PE pipes support the PE pipes, so that the PE pipes can only rotate axially, displacement of the positioning platform is achieved through the first driving mechanism and the universal wheels, and butt joint construction of the ends of the PE pipes in the overhead state is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of PE pipe construction, and in particular to a PE pipe overhead construction method. Background Art

[0002] PE pipes are often used as water supply pipes or drainage pipes. In order to increase the service life of PE pipes, most PE pipes are buried underground. For some special scenarios, PE pipes need to be laid overhead. Compared with underground laying, overhead laying is more difficult to construct, especially for the support and coaxial alignment of PE pipes before hot-melt welding. Therefore, it is urgent to improve the overhead construction method of PE pipes so that the PE pipes can be stably supported before overhead hot-melt welding. Summary of the invention

[0003] The technical problem to be solved by the present invention is: it is urgent to improve the PE pipe overhead construction method so that the PE pipe can be stably supported in position before overhead hot welding.

[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is:

[0005] PE pipe overhead construction method, based on PE pipe overhead construction device;

[0006] The PE pipe overhead construction device comprises:

[0007] Base;

[0008] Universal wheels, the universal wheels are connected to the lower part of the base;

[0009] A positioning platform, wherein the positioning platform is liftably disposed above the base through a first driving mechanism;

[0010] A supporting roller, wherein the supporting roller is arranged at the upper part of the Y-direction reverse end of the positioning platform;

[0011] A pneumatic clamp, the pneumatic clamp is located in the Y direction of the supporting roller, and the pneumatic clamp is movably connected to the positioning platform along the Y direction;

[0012] A second driving mechanism, the second driving mechanism is connected between the positioning platform and the pneumatic clamp, and is used to drive the pneumatic clamp to move;

[0013] Positioning support mechanism, wherein the four positioning support mechanisms are symmetrically arranged in pairs on the X-direction side or the X-direction reverse side of the positioning platform; the positioning support mechanism comprises:

[0014] A movable bracket, wherein the movable bracket is movably connected to the positioning platform along the X direction;

[0015] A third driving mechanism, the third driving mechanism is used to drive the movable bracket to move;

[0016] A first rotating shaft, wherein the circumferential direction of the first rotating shaft is the X direction, and the first rotating shaft is rotatably connected to the movable bracket;

[0017] A positioning roller seat, wherein the positioning roller seat is provided with a first rotating shaft;

[0018] A positioning roller body, wherein the positioning roller body is rotatably connected to the positioning roller seat, and the axial direction of the positioning roller body is perpendicular to the X direction;

[0019] a fourth driving mechanism, the fourth driving mechanism being connected between the movable bracket and the first rotating shaft and being used for driving the first rotating shaft to rotate;

[0020] The overhead construction method comprises the following steps:

[0021] The second driving mechanism is controlled to drive the pneumatic clamp to move to a position close to the reverse end of the X direction. According to the specifications of the PE pipe, the third driving mechanism is controlled to drive each movable bracket to move synchronously, so that each positioning roller body is adjusted to a position capable of supporting the PE pipe; the fourth driving mechanism is controlled to drive the first rotating shaft and the positioning roller seat to rotate, so that the circumferential direction of the positioning roller body is the vertical direction;

[0022] Control the first driving mechanism to drive the positioning platform to move downward, support the lower part of the Y-direction end of the PE tube to be connected on the support roller, push the PE tube in the Y direction until it reaches the clamping position of the pneumatic clamp, and control the pneumatic clamp to clamp the lower edge of the Y-direction end of the PE tube;

[0023] The second driving mechanism is controlled to drive the pneumatic clamp to move in the Y direction, and the PE pipe is driven to move in the Y direction, so that during the movement, under the guidance of each positioning roller body, the axial direction of the PE pipe is automatically adjusted so that the axial direction faces the Y direction;

[0024] When each positioning roller body contacts the surface of the PE pipe, the fourth driving mechanism is controlled to drive the first rotating shaft to rotate, so that the positioning roller body rotates until the axial direction is in the Y direction; the positioning of the PE pipe is completed. After positioning, the pneumatic clamp is controlled to release the clamping, and the PE pipe can only rotate along the axial direction at this time;

[0025] The base is moved to the position where the PE pipe needs to be docked by using the universal wheels, and the first driving mechanism is controlled to drive the positioning platform to move upward, so that the PE pipe is moved to the position where the positioning docking is required.

[0026] The beneficial effects of the present invention are as follows: in the PE pipe overhead construction method involved in the present invention, during construction, the positioning platform is first lowered, and the supporting rollers and the pneumatic clamp are utilized to facilitate the preliminary positioning of the PE pipe, and a rotatable positioning roller structure is utilized so that when the pneumatic clamp clamps and drags the PE pipe to move in the Y direction, the positioning roller body plays a role of lateral limiting, and when the PE pipe is moved into place, the positioning roller body is driven to rotate, and the supporting roller of the PE pipe supports the PE pipe, so that the PE pipe can only rotate axially, and the displacement of the positioning platform is realized by the first driving mechanism and the universal wheel, so as to facilitate the docking construction of the ends of the PE pipe in an overhead state. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram from a first perspective of a PE pipe overhead construction device according to a specific embodiment of the present invention;

[0028] Figure 2 It is a schematic diagram from a second perspective of a PE pipe overhead construction device according to a specific embodiment of the present invention;

[0029] Description of labels:

[0030] 1. Base;

[0031] 2. Universal wheel;

[0032] 3. Positioning platform; 31. Telescopic cylinder; 32. Long slot hole;

[0033] 4. Support roller;

[0034] 5. Pneumatic clamp;

[0035] 61. First screw guide rail assembly; 62. First slider;

[0036] 7. Positioning support mechanism; 71. Moving bracket; 72. Second screw guide rail assembly; 73. First rotating shaft; 74. Positioning roller seat; 75. Positioning roller body; 761. Motor; 762. First pulley; 763. Second pulley; 764. Transmission belt. DETAILED DESCRIPTION

[0037] In order to explain the technical content, achieved objectives and effects of the present invention in detail, the following is an explanation in combination with the implementation modes and the accompanying drawings.

[0038] Please refer to Figure 1 as well as Figure 2 , the specific implementation mode of the present invention relates to a PE pipe overhead construction method, based on a PE pipe overhead construction device;

[0039] The PE pipe overhead construction device comprises:

[0040] Base 1;

[0041] Universal wheels 2, the universal wheels 2 are connected to the lower part of the base 1;

[0042] A positioning platform 3, wherein the positioning platform 3 is liftably disposed above the base 1 through a first driving mechanism;

[0043] A supporting roller 4, wherein the supporting roller 4 is arranged at the upper part of the Y-direction reverse end of the positioning platform 3;

[0044] A pneumatic clamp 5, the pneumatic clamp 5 is located in the Y direction of the supporting roller 4, and the pneumatic clamp 5 is movably connected to the positioning platform 3 along the Y direction;

[0045] A second driving mechanism, which is connected between the positioning platform 3 and the pneumatic clamp 5 and is used to drive the pneumatic clamp 5 to move;

[0046] Positioning support mechanism 7, the four positioning support mechanisms 7 are symmetrically arranged in pairs on the X-direction side or the X-direction reverse side of the positioning platform 3; the positioning support mechanism 7 includes:

[0047] A movable bracket 71, wherein the movable bracket 71 is movably connected to the positioning platform 3 along the X direction;

[0048] A third driving mechanism, the third driving mechanism is used to drive the movable bracket 71 to move;

[0049] A first rotating shaft 73, wherein the circumferential direction of the first rotating shaft 73 is the X direction, and the first rotating shaft 73 is rotatably connected to the movable bracket 71;

[0050] A positioning roller seat 74, wherein the positioning roller seat 74 is connected to the first rotating shaft 73;

[0051] A positioning roller body 75, wherein the positioning roller body 75 is rotatably connected to the positioning roller seat 74, and the axial direction of the positioning roller body 75 is perpendicular to the X direction;

[0052] a fourth driving mechanism, the fourth driving mechanism being connected between the movable bracket 71 and the first rotating shaft 73 and being used for driving the first rotating shaft 73 to rotate;

[0053] The overhead construction method comprises the following steps:

[0054] The second driving mechanism is controlled to drive the pneumatic clamp 5 to move to a position close to the reverse end in the X direction. According to the specifications of the PE pipe, the third driving mechanism is controlled to drive each movable bracket 71 to move synchronously, so that each positioning roller body 75 is adjusted to a position capable of supporting the PE pipe; the fourth driving mechanism is controlled to drive the first rotating shaft 73 and the positioning roller seat 74 to rotate, so that the circumferential direction of the positioning roller body 75 is the vertical direction;

[0055] Control the first driving mechanism to drive the positioning platform 3 to move downward, support the lower part of the Y-direction end of the PE pipe to be connected on the support roller 4, push the PE pipe in the Y direction until it reaches the clamping position of the pneumatic clamp 5, and control the pneumatic clamp 5 to clamp the lower edge of the Y-direction end of the PE pipe;

[0056] The second driving mechanism is controlled to drive the pneumatic clamp 5 to move in the Y direction, and the PE pipe is driven to move in the Y direction, so that during the movement, under the guidance of each positioning wheel body 75, the axial direction of the PE pipe is automatically adjusted to face the Y direction;

[0057] When each positioning roller body 75 contacts the surface of the PE pipe, the fourth driving mechanism is controlled to drive the first rotating shaft 73 to rotate, so that the positioning roller body 75 rotates until the axial direction is in the Y direction; the positioning of the PE pipe is completed. After positioning, the pneumatic clamp 5 is controlled to release the clamping, and the PE pipe can only rotate along the axial direction at this time;

[0058] The base 1 is moved to the position where the PE pipe needs to be docked by using the universal wheel 2, and the first driving mechanism is controlled to drive the positioning platform 3 to move upward, so that the PE pipe is moved to the position for positioning and docking.

[0059] In the above embodiment, during construction, the positioning platform 3 is first lowered, and the supporting rollers 4 and the pneumatic clamp 5 are utilized to facilitate the preliminary positioning of the PE pipe. The rotatable positioning roller structure is utilized so that when the pneumatic clamp 5 clamps and drags the PE pipe to move in the Y direction, the positioning roller body 75 plays a role of lateral limiting. When the PE pipe is moved into place, the positioning roller body 75 is driven to rotate, and the PE pipe is supported by the roller as a PE pipe, so that the PE pipe can only rotate axially. The displacement of the positioning platform 3 is realized by the first driving mechanism and the universal wheel 2, so as to facilitate the docking construction of the ends of the PE pipe in an overhead state.

[0060] As a preferred embodiment, the first driving mechanism includes a plurality of synchronously moving telescopic cylinders 31 , the cylinder bodies of the telescopic cylinders 31 are connected to the base 1 , and the piston rods are connected to the positioning platform 3 .

[0061] As a preferred embodiment, the telescopic cylinder 31 is a pneumatic cylinder, a hydraulic cylinder or an electric cylinder.

[0062] As a preferred embodiment, the second driving mechanism includes a first screw guide rail assembly 61 arranged along the Y direction, and the pneumatic clamp 5 is slidably connected to the first screw guide rail assembly 61 via a first slider 62 .

[0063] As a preferred embodiment, the first screw guide rail assembly 61 is arranged at the lower part of the positioning platform 3, the positioning platform 3 is provided with a long slot hole 32 arranged along the Y direction, and the pneumatic clamp 5 is connected to the first slider 62 through the long slot hole 32 via a connecting piece.

[0064] As a preferred embodiment, the third driving mechanism is a second screw guide rail assembly 72 arranged along the X direction, and the movable bracket 71 is slidably connected to the second screw guide rail assembly 72 .

[0065] As a preferred embodiment, the fourth driving mechanism includes:

[0066] A motor 761, wherein the motor 761 is connected to the movable bracket 71;

[0067] A first pulley 762, wherein the first pulley 762 is drivingly connected to an output shaft of the motor 761;

[0068] A second belt pulley 763, wherein the second belt pulley 763 is coaxially sleeved on the first rotating shaft 73;

[0069] A transmission belt 764 is connected between the first pulley 762 and the second pulley 763 .

[0070] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent transformations made using the contents of the present invention's specification and drawings, or directly or indirectly applied in related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. PE pipe overhead construction method, characterized in that: Based on PE pipe overhead construction device; The PE pipe overhead construction device comprises: Base; Universal wheels connected to the lower part of the base; A positioning platform, wherein the positioning platform is liftably disposed above the base through a first driving mechanism; A supporting roller, wherein the supporting roller is arranged at the upper part of the Y-direction reverse end of the positioning platform; A pneumatic clamp, the pneumatic clamp is located in the Y direction of the supporting roller, and the pneumatic clamp is movably connected to the positioning platform along the Y direction; A second driving mechanism, the second driving mechanism is connected between the positioning platform and the pneumatic clamp, and is used to drive the pneumatic clamp to move; Positioning support mechanism, wherein the four positioning support mechanisms are symmetrically arranged in pairs on the X-direction side or the X-direction reverse side of the positioning platform; the positioning support mechanism comprises: A movable bracket, wherein the movable bracket is movably connected to the positioning platform along the X direction; A third driving mechanism, the third driving mechanism is used to drive the movable bracket to move; A first rotating shaft, wherein the circumferential direction of the first rotating shaft is the X direction, and the first rotating shaft is rotatably connected to the movable bracket; A positioning roller seat, wherein the positioning roller seat is provided with a first rotating shaft; A positioning roller body, wherein the positioning roller body is rotatably connected to the positioning roller seat, and the axial direction of the positioning roller body is perpendicular to the X direction; a fourth driving mechanism, the fourth driving mechanism being connected between the movable bracket and the first rotating shaft and being used for driving the first rotating shaft to rotate; The overhead construction method comprises the following steps: The second driving mechanism is controlled to drive the pneumatic clamp to move to a position close to the reverse end of the X direction. According to the specifications of the PE pipe, the third driving mechanism is controlled to drive each movable bracket to move synchronously, so that each positioning roller body is adjusted to a position capable of supporting the PE pipe; the fourth driving mechanism is controlled to drive the first rotating shaft and the positioning roller seat to rotate, so that the circumferential direction of the positioning roller body is the vertical direction; Control the first driving mechanism to drive the positioning platform to move downward, support the lower part of the Y-direction end of the PE tube to be connected on the support roller, push the PE tube in the Y direction until it reaches the clamping position of the pneumatic clamp, and control the pneumatic clamp to clamp the lower edge of the Y-direction end of the PE tube; The second driving mechanism is controlled to drive the pneumatic clamp to move in the Y direction, and the PE pipe is driven to move in the Y direction, so that during the movement, under the guidance of each positioning roller body, the axial direction of the PE pipe is automatically adjusted so that the axial direction faces the Y direction; When each positioning roller body contacts the surface of the PE pipe, the fourth driving mechanism is controlled to drive the first rotating shaft to rotate, so that the positioning roller body rotates until the axial direction is in the Y direction; the positioning of the PE pipe is completed. After positioning, the pneumatic clamp is controlled to release the clamping, and the PE pipe can only rotate along the axial direction at this time; The base is moved to the position where the PE pipe needs to be docked by using the universal wheels, and the first driving mechanism is controlled to drive the positioning platform to move upward, so that the PE pipe is moved to the position where the positioning docking is required.

2. The PE pipe overhead construction method according to claim 1, characterized in that: The first driving mechanism comprises a plurality of synchronously moving telescopic cylinders, wherein the cylinder bodies of the telescopic cylinders are connected to the base, and the piston rods are connected to the positioning platform.

3. The PE pipe overhead construction method according to claim 2, characterized in that: The telescopic cylinder is a pneumatic cylinder, a hydraulic cylinder or an electric cylinder.

4. The PE pipe overhead construction method according to claim 1, characterized in that: The second driving mechanism comprises a first screw guide rail assembly arranged along the Y direction, and the pneumatic clamp is slidably connected to the first screw guide rail assembly via a first sliding block.

5. The PE pipe overhead construction method according to claim 4, characterized in that: The first screw guide rail assembly is arranged at the lower part of the positioning platform. The positioning platform is provided with a long slot hole arranged along the Y direction. The pneumatic clamp is connected to the first sliding block through the long slot hole via a connecting piece.

6. The PE pipe overhead construction method according to claim 1, characterized in that: The third driving mechanism is a second screw guide rail assembly arranged along the X direction, and the movable bracket is slidably connected to the second screw guide rail assembly.

7. The PE pipe overhead construction method according to claim 1, characterized in that: The fourth driving mechanism comprises: A motor connected to the mobile support; A first pulley, the first pulley is drivingly connected to an output shaft of the motor; A second pulley, the second pulley is coaxially sleeved on the first rotating shaft; A transmission belt is connected between the first pulley and the second pulley.