Method for solving blocking of spent fuel balls at slope pipe section during unloading of high-temperature gas cooled reactor

By setting up a bypass air pipe and return air pipe in the slope section of the high-temperature air-cooled reactor, the alternating operation of the Roots fan and the air valve generates airflow disturbance, which solves the problem of spent fuel ball blockage, ensuring the normal operation of the reactor and radiation protection.

CN118919110APending Publication Date: 2024-11-08HUANENG SHANDONG SHIDAOBAY NUCLEAR POWER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411015211.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

When unloading high-temperature gas-cooled reactors, the spent fuel ball is stuck in the slope pipe section, resulting in the inability to be discharged smoothly, affecting the operation of the reactor.

Method used

Set up the bypass air pipe and return air pipe upstream of the slope pipe section, and use a Roots fan to cooperate with the alternating opening and closing of the first and second return air valves to generate airflow disturbances to loosen the stuck spent fuel ball until the stuck is lifted . Options include parallel Roots fans, variable frequency fans and specific valve control strategies.

Benefits of technology

Effectively remove the blockage of spent fuel balls in the slope pipe section, avoid affecting the operation of the reactor, improve unloading efficiency, and reduce the radiation dose and the generation of radioactive solid waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118919110A_ABST
    Figure CN118919110A_ABST
Patent Text Reader

Abstract

The invention provides a method for solving blockage of spent fuel balls at a slope pipe section during unloading of a high-temperature gas cooled reactor, and belongs to the technical field of nuclear island equipment.The method includes the steps that a bypass gas pipe is arranged at the upstream of the slope pipe section, the bypass gas pipe is communicated to an inlet of a Roots blower, and a first gas return valve is arranged on the bypass gas pipe; an air return pipeline is arranged at the downstream of the slope pipe section, the air return pipeline is communicated to an inlet of the Roots blower, and a second air return valve is arranged on the air return pipeline; when the spent fuel ball is blocked in the slope pipe section, the Roots blower is started, and the first air return valve and the second air return valve are alternately closed and started, so that the spent fuel ball blocked in the slope pipe section is disturbed until blocking is relieved; according to the invention, the Roots blower is matched with the alternate opening and closing of the first air return valve and the second air return valve to disturb the spent fuel ball blocked in the slope pipe section, so that the blocking is loosened until the blocking is removed, and the problem of influencing the operation of a reactor is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of nuclear island equipment, and in particular to a method for solving the problem of spent fuel balls being stuck in a slope pipe section during unloading of a high-temperature gas-cooled reactor. Background Art

[0002] When the high-temperature gas-cooled reactor is unloaded, the unloaded spent fuel balls are first stored in the unloading temporary storage device of the fuel loading and unloading system. When the number of spent fuel balls in the unloading temporary storage device reaches 3,800, the spent fuel balls are unloaded for the second time.

[0003] The secondary unloading of spent fuel balls starts from the temporary unloading storage device. The spent fuel balls in the temporary unloading storage device are sent to the secondary unloading pipeline through the unloading direct drive mechanism arranged at the lower part. The spent fuel balls enter the bottom of the lifting pipe section through two ball-way electric isolation valves. A launcher is arranged at the bottom of the lifting pipe section. The launcher provides power to lift the spent fuel balls through the Roots blower of the spent fuel air delivery system. The spent fuel balls go through an ascending stage of about 47 meters in the pipeline. After reaching the top, the lifting gas is diverted by the gas diverter and returns to the inlet of the Roots blower. The spent fuel balls after the gas diversion will fall into the spent fuel tank after passing through the electric ball valve and the counter along the unloading descending pipe section under the action of their own gravity.

[0004] However, since there may be dust or incomplete spent fuel balls during the unloading process, there is a possibility that the spent fuel balls and debris or broken balls are stuck in the downcomer section, making it impossible to unload the spent fuel balls smoothly. If the spent fuel balls cannot be unloaded from the unloading temporary storage device, it will be impossible to carry out the core refueling without stopping, which will seriously affect the operation of the reactor. Summary of the invention

[0005] Therefore, the present invention provides a method for solving the problem of spent fuel balls being stuck in a slope pipe section during unloading of a high-temperature gas-cooled reactor, so as to solve the problem of spent fuel balls being stuck in a slope pipe section.

[0006] In order to solve the above technical problems, the present invention provides a method for solving the problem of spent fuel balls being stuck in a slope pipe section during unloading of a high-temperature gas-cooled reactor. A bypass air pipe is provided upstream of the slope pipe section, the bypass air pipe is connected to the inlet of a Roots blower, and a first return air valve is provided on the bypass air pipe;

[0007] An air return duct is provided downstream of the slope pipe section, the air return duct is connected to the inlet of the Roots blower, and a second air return valve is provided on the air return duct;

[0008] When the spent fuel ball is stuck in the slope pipe section, the Roots blower is turned on, and the first air return valve and the second air return valve are closed and opened alternately to disturb the spent fuel ball stuck in the slope pipe section until the blockage is released.

[0009] Optionally, the first air return valve is opened first, during which the second air return valve is closed; after a first period of time, the first air return valve is closed and the second air return valve is opened.

[0010] Optionally, the first time is greater than or equal to five minutes.

[0011] Optionally, there are at least two Roots blowers connected in parallel, and when the spent fuel ball is stuck in the slope pipe section, a plurality of the Roots blowers are started simultaneously.

[0012] Optionally, the outlet of the Roots blower is divided into two paths, a first path leading to the atmosphere, and a second path leading to a launcher, through which the spent fuel balls in the pipeline are pneumatically pushed; an exhaust valve is provided on the first path, and when the spent fuel balls are stuck in the slope pipe section, the exhaust valve is closed.

[0013] Optionally, the bottom of the temporary unloading storage device is connected to the lifting pipe of the launcher outlet through a secondary unloading pipe, and a unloading electric valve is provided on the secondary unloading pipe. When the spent fuel ball is stuck in the slope pipe section, the unloading electric valve is closed.

[0014] Optionally, the unloading electric valve has at least two valves arranged in sequence.

[0015] Optionally, a spent fuel tank is provided at the downstream end of the slope pipe section, and after the spent fuel balls are unblocked by the slope pipe section, the spent fuel balls fall into the interior of the spent fuel tank.

[0016] Optionally, a spent fuel tank inlet valve is provided on the slope pipe section.

[0017] Optionally, the Roots blower is a variable frequency blower, and when the spent fuel ball is stuck in the slope pipe section, the frequency of the Roots blower is increased to the maximum.

[0018] The technical solution of the present invention has the following advantages:

[0019] 1. The method provided by the present invention for solving the problem of spent fuel balls being stuck in a slope pipe section during unloading of a high-temperature gas-cooled reactor is to disturb the spent fuel balls stuck inside the slope pipe section by means of a Roots blower in cooperation with a first air return valve and a second air return valve, so as to loosen the blockage until it is released, thereby avoiding the problem of affecting the operation of the reactor.

[0020] 2. The method provided by the present invention for solving the problem of spent fuel balls being stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor is as follows: when the first air return valve is opened and the second air return valve is closed, a slight reverse air flow disturbance will be generated at the position of the spent fuel balls stuck in the slope pipe section, thereby loosening the blockage; after a period of time, the first air return valve is closed and the second air return valve is opened at the same time. At this time, the Roots blower lifts the airflow and only flows back through the second air return valve, thereby providing a maximum positive lifting gas disturbance to the stuck spent fuel balls, thereby generating a maximum positive momentum for the spent fuel balls. The momentum of the spent fuel balls may release the blockage. This is a cyclic operation cycle. If the blockage is not released, this cyclic operation cycle is repeated until the blockage is released.

[0021] 3. The present invention provides a method for solving the problem of spent fuel balls getting stuck in a slope pipe section during unloading of a high-temperature gas-cooled reactor. The method comprises at least two Roots blowers connected in parallel. When the spent fuel balls get stuck in the slope pipe section, multiple Roots blowers can be turned on simultaneously to increase the gas disturbance energy, thereby further improving the clearing effect.

[0022] 4. The present invention provides a method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor. The Roots blower is a variable frequency blower. When the spent fuel balls get stuck in the slope pipe section, the frequency of the Roots blower can be increased to the maximum to increase the gas disturbance energy, thereby further improving the clearing effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 It is a schematic diagram of a specific implementation of a high temperature gas-cooled reactor unloading system provided in an embodiment of the present invention.

[0025] Description of reference numerals:

[0026] 1. Temporary storage device for unloading; 2. Launcher; 3. Lifting pipeline; 4. Slope pipe section; 5. Spent fuel tank; 6. Roots blower; 7. Secondary unloading pipeline; 8. Bypass air pipe; 9. First return air valve; 10. Return air pipeline; 11. Second return air valve; 12. Exhaust valve; 13. Unloading electric valve; 14. Spent fuel tank inlet valve. DETAILED DESCRIPTION

[0027] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0029] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0030] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0031] like Figure 1As shown, a specific implementation of the high temperature gas-cooled reactor unloading system provided in this embodiment includes: a temporary unloading storage device 1, a launcher 2, a lifting pipe 3, a slope pipe section 4, a spent fuel tank 5 and a Roots blower 6. The bottom of the temporary unloading storage device 1 is connected to the lifting pipe 3 at the outlet of the launcher 2 through a secondary unloading pipe 7; the inlet of the launcher 2 is connected to the outlet of the Roots blower 6 through an air intake pipe; the top of the lifting pipe 3 is connected to the slope pipe section 4, and the downstream of the slope pipe section 4 is connected to the spent fuel tank 5. After the spent fuel ball is unblocked by the slope pipe section 4, the spent fuel ball falls into the interior of the spent fuel tank 5. A bypass air pipe 8 is provided upstream of the slope pipe section 4, the bypass air pipe 8 is connected to the inlet of the Roots blower 6, and a first return air valve 9 is provided on the bypass air pipe 8; a return air duct 10 is provided downstream of the slope pipe section 4, the return air duct 10 is connected to the inlet of the Roots blower 6, and a second return air valve 11 is provided on the return air duct 10. It should be noted that, in this embodiment, the spent fuel ball refers to the spent fuel ball of the high-temperature gas-cooled reactor, which is spherical, has a diameter of 60mm, and has high radioactivity. The lifting pipe section refers to the upward movement of the spent fuel ball in the pipe section due to the lifting effect of the Roots blower 6. The slope pipe section 4 refers to the downward movement of the spent fuel ball in the slope pipe section 4 under the action of gravity, and the slope of the pipe section is about 20°.

[0032] The solution to the problem of spent fuel balls getting stuck in the slope pipe section 4 during the unloading of the high-temperature gas-cooled reactor provided in this embodiment is: when the spent fuel balls get stuck in the slope pipe section 4, the Roots blower 6 is turned on, and the first air return valve 9 and the second air return valve 11 are alternately closed and opened to disturb the spent fuel balls stuck inside the slope pipe section 4 until the blockage is released. In the above method, the spent fuel balls stuck inside the slope pipe section 4 are disturbed by the Roots blower 6 in coordination with the alternate opening and closing of the first air return valve 9 and the second air return valve 11, so that the blockage is loosened until it is released, thereby avoiding the problem of affecting the operation of the reactor.

[0033] like Figure 1As shown, in the solution to the stuck spent fuel ball in the slope pipe section 4 during the unloading of the high temperature gas-cooled reactor provided in this embodiment, the first air return valve 9 is first opened, during which the second air return valve 11 is closed. After the first time, the first air return valve 9 is closed and the second air return valve 11 is opened. In this way, when the first air return valve 9 is opened and the second air return valve 11 is closed, a slight reverse air flow disturbance will be generated at the position of the spent fuel ball stuck in the slope pipe section 4, forming a loosening effect on the blockage; after a period of time, the first air return valve 9 is closed and the second air return valve 11 is opened at the same time. At this time, the Roots blower 6 lifts the air flow and only flows back through the second air return valve 11, which will provide a maximum positive lifting gas disturbance to the stuck spent fuel ball, so that the spent fuel ball generates a maximum positive momentum, and the momentum of the spent fuel ball may release the blockage. This is a cyclic operation cycle. If the blockage is not released, this cyclic operation cycle is repeated until the blockage is released. Of course, the above description is not restrictive, and in some alternative embodiments, the opening sequence of the first air return valve 9 and the second air return valve 11 may also be interchanged.

[0034] like Figure 1 As shown, in the solution to the problem of spent fuel balls being stuck in the slope pipe section 4 during the unloading of the high-temperature gas-cooled reactor provided in this embodiment, the first time is greater than or equal to five minutes, that is, the first return air valve 9 is opened for a time greater than or equal to five minutes. With such a configuration, sufficient reverse airflow disturbance can be generated at the position of the spent fuel balls stuck in the slope pipe section 4. Of course, the above description is not restrictive, and in some alternative embodiments, the first time can also be other times.

[0035] like Figure 1 As shown, in the solution to the problem of spent fuel balls being blocked in the slope pipe section 4 during the unloading of the high-temperature gas-cooled reactor provided in this embodiment, the Roots blowers 6 have at least two units connected in parallel. When the spent fuel balls are blocked in the slope pipe section 4, multiple Roots blowers 6 are turned on at the same time. With such a configuration, by turning on multiple Roots blowers 6 at the same time, the air supply during the blockage clearing can be increased, and the success rate of the blockage clearing can be increased. Of course, the above description is not restrictive. In some alternative embodiments, the number of the Roots blowers 6 can also be set to only one.

[0036] like Figure 1As shown, in the solution to the problem of spent fuel balls getting stuck in the slope pipe section 4 during the unloading of a high-temperature gas-cooled reactor provided in this embodiment, the outlet of the Roots blower 6 is divided into two paths, wherein the first path leads to the atmosphere, and the second path leads to the launcher 2, through which the spent fuel balls in the pipeline are pneumatically pushed; an exhaust valve 12 is provided on the first path, and when the spent fuel balls are stuck in the slope pipe section 4, the exhaust valve 12 is closed. With such a configuration, during normal operation, the exhaust valve 12 is opened by about 45° to meet the normal secondary unloading requirements, and when the exhaust valve 12 is closed, the air supply to the slope pipe section 4 can be increased, thereby improving the efficiency of clearing the blockage. Of course, the above description is not restrictive, and in some alternative embodiments, the outlet of the Roots blower 6 may not lead to the atmosphere.

[0037] like Figure 1 As shown, in the solution to the problem of spent fuel balls getting stuck in the slope pipe section 4 during the unloading of a high-temperature gas-cooled reactor provided in this embodiment, the bottom of the unloading temporary storage device 1 is connected to the lifting pipe 3 at the outlet of the launcher 2 through the secondary unloading pipe 7, and the secondary unloading pipe 7 is provided with a unloading electric valve 13. When the spent fuel balls are stuck in the slope pipe section 4, the unloading electric valve 13 is closed. This arrangement can prevent more spent fuel balls from entering the blocked position when a blockage occurs. Furthermore, the unloading electric valve 13 has at least two arranged in sequence. This arrangement can avoid the problem of being unable to close the secondary unloading channel in time due to damage to one unloading electric valve 13. Of course, the above description is not restrictive. In some alternative embodiments, more unloading electric valves 13 can be provided, or only one can be provided.

[0038] like Figure 1 As shown, in the solution to the problem of spent fuel balls being stuck in the slope pipe section 4 during the unloading of the high-temperature gas-cooled reactor provided in this embodiment, a spent fuel tank inlet valve 14 is provided on the slope pipe section 4. With such a configuration, the spent fuel tank inlet valve 14 can be opened or closed according to the capacity of the spent fuel tank 5, thereby facilitating the replacement of the spent fuel tank 5. Of course, the above description is not restrictive, and in some alternative embodiments, the spent fuel tank inlet valve 14 can be omitted.

[0039] like Figure 1 As shown, in the solution to the problem of spent fuel balls being stuck in the slope pipe section 4 during the unloading of the high-temperature gas-cooled reactor provided in this embodiment, the Roots blower 6 is a variable frequency blower. When the spent fuel ball is stuck in the slope pipe section 4, the frequency of the Roots blower 6 is increased to the maximum. With such a configuration, when the spent fuel ball is stuck in the slope pipe section 4, the gas disturbance energy can be increased by increasing the frequency of the Roots blower 6 to the maximum, thereby further improving the clearing effect. Of course, the above description is not restrictive. In some alternative embodiments, the Roots blower 6 can also adopt a fixed frequency.

[0040] Working principle:

[0041] When it is determined that the spent fuel balls are blocked in the slope pipe section 4, the ball unloading operation of the unloading temporary storage device 1 is stopped, and the unloading electric valve 13 is closed, and the spent fuel balls no longer enter the lifting pipe 3 to prevent excessive spent fuel balls from accumulating and blocking inside the pipe. The outlet exhaust valve 12 of the Roots blower 6 is closed, and more gas from the outlet of the Roots blower 6 enters the lifting pipe section. In order to continue to increase the air flow inside the pipe 3, the second Roots blower 6 is started, and the operation mode of the two Roots blowers 6 is maintained, and the frequency of the two Roots blowers 6 is increased to the maximum frequency of 50Hz.

[0042] After the maximum lifting flow of the Roots blower 6 in the system is established, the air flow disturbance operation of the slope pipe section 4 is started. First, the second return air valve 11 is closed. The Roots blower 6 lifts the airflow and only flows back through the first return air valve 9. At this time, a slight reverse air flow disturbance will be generated at the position of the stuck spent fuel ball, which will loosen the blockage. After the second return air valve 11 is closed for five minutes, the first return air valve 9 is closed and the second return air valve 11 is opened at the same time. At this time, the Roots blower 6 lifts the airflow and only flows back through the second return air valve 11, and at the same time, a maximum positive lifting gas disturbance is generated for the stuck spent fuel ball, which will cause the spent fuel ball to generate a maximum positive momentum. The momentum of the spent fuel ball may release the blockage. This is a cycle operation period. If the blockage is not released, continue to repeat this cycle operation period until the blockage is released.

[0043] This embodiment changes the system status settings to solve the jamming operation online. It has been verified in practice that this method is fast, effective and has obvious effects. It greatly reduces the radiation dose caused by the system dismantling and repairing method, and optimizes radiation protection. For example, close maintenance operations by personnel increase the radiation dose to personnel. At the same time, it avoids the radioactive waste generated by the dismantling and repair work, and greatly reduces the amount of radioactive solid waste generated.

[0044] Obviously, the above embodiments are merely examples for clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from these are still within the scope of protection of the present invention.

Claims

1. A method for solving the problem of spent fuel balls getting stuck in the slope pipe section during the unloading of a high-temperature gas-cooled reactor, characterized in that: A bypass air pipe (8) is provided upstream of the slope pipe section (4), the bypass air pipe (8) is connected to the inlet of the Roots blower (6), and a first air return valve (9) is provided on the bypass air pipe (8); A return air duct (10) is provided downstream of the slope pipe section (4), the return air duct (10) is connected to the inlet of the Roots blower (6), and a second return air valve (11) is provided on the return air duct (10); When the spent fuel balls are blocked in the slope pipe section (4), the Roots blower (6) is turned on, and the first air return valve (9) and the second air return valve (11) are alternately closed and opened to disturb the spent fuel balls blocked inside the slope pipe section (4) until the blockage is relieved.

2. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor according to claim 1, characterized in that: The first air return valve (9) is opened first, during which the second air return valve (11) is closed; after a first period of time, the first air return valve (9) is closed and the second air return valve (11) is opened.

3. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor according to claim 2, characterized in that: The first time is greater than or equal to five minutes.

4. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor according to claim 1, characterized in that: The Roots blowers (6) have at least two units connected in parallel, and when the spent fuel balls are blocked in the slope pipe section (4), a plurality of the Roots blowers (6) are started simultaneously.

5. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor according to claim 1, characterized in that: The outlet of the Roots blower (6) is divided into two paths, wherein the first path leads to the atmosphere and the second path leads to the launcher (2), and the spent fuel balls in the pipeline are pneumatically pushed through the launcher (2); an exhaust valve (12) is provided on the first path, and when the spent fuel balls are blocked in the slope pipe section (4), the exhaust valve (12) is closed.

6. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor according to claim 5, characterized in that: The bottom of the temporary unloading storage device (1) is connected to the lifting pipeline (3) at the outlet of the launcher (2) through a secondary unloading pipeline (7). The secondary unloading pipeline (7) is provided with an electric unloading valve (13). When the spent fuel ball is blocked in the slope pipe section (4), the electric unloading valve (13) is closed.

7. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor according to claim 6, characterized in that: The discharge electric valve (13) comprises at least two valves which are arranged in sequence.

8. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during the unloading of a high temperature gas-cooled reactor according to claim 1, characterized in that: A spent fuel tank (5) is provided at the downstream end of the slope pipe section (4), and after the spent fuel balls are freed from being blocked by the slope pipe section (4), the spent fuel balls fall into the interior of the spent fuel tank (5).

9. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high-temperature gas-cooled reactor according to claim 8, characterized in that: The slope pipe section (4) is provided with a spent fuel tank inlet valve (14).

10. The method for solving the problem of spent fuel balls getting stuck in the slope pipe section during unloading of a high temperature gas-cooled reactor according to any one of claims 1 to 9, characterized in that: The Roots blower (6) is a variable frequency blower. When the spent fuel ball is blocked in the slope pipe section (4), the frequency of the Roots blower (6) is increased to the maximum.