Charging station management method and device and storage medium
By using monitoring components and image recognition technology, the input power and status of charging piles are verified, solving the problem of inconsistent charging pile operating data and realizing effective management and safety monitoring of charging stations.
Patent Information
- Application Number
- CN202411202289.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-12
AI Technical Summary
The discrepancy between the charging pile's operational data and the actual situation leads to errors in cost accounting and anomaly detection, making it difficult to effectively manage the charging piles in the charging station.
By monitoring components to collect the input power and recorded power supply of the charging pile, matching and verifying them, and combining historical risk analysis and regional image monitoring, the system can determine the abnormal status of the charging pile and output prompt information.
It improves the accuracy of monitoring charging pile operation data, ensures safe and effective management, reduces errors in anomaly detection, and enhances the accuracy and safety of management.
Smart Images

Figure CN118928116A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of smart park technology, and in particular to charging station management methods, equipment and storage media. Background Art
[0002] Vehicle management is an important part of park management. Traditional vehicle management includes traffic management, parking management, etc. As the number of electric vehicles continues to increase, the management of electric vehicle charging has gradually become the key to vehicle management.
[0003] In the related art, a charging station is set up in the park, and the charging station usually includes several charging piles to provide charging services for electric vehicles. At the same time, the charging piles can be connected to the charging pile management platform through the network, so that the work of the charging piles can be monitored and managed through the charging pile management platform.
[0004] However, due to factors such as charging pile failures and illegal operations, the working parameters uploaded to the management platform may not match the actual working conditions of the charging piles, which will lead to errors in cost accounting, abnormality judgment, etc., which makes it inconvenient to effectively manage the charging piles in the charging station. Summary of the invention
[0005] In order to facilitate the effective management of charging piles in a charging station, the present application provides a charging station management method, device and storage medium.
[0006] In a first aspect, the present application provides a charging station management method, which adopts the following technical solution: A charging station management method, wherein the charging station includes more than two charging piles, and the method includes: For a target charging pile in a power supply state, obtaining a recorded power supply power of the target charging pile recorded in a charging pile management platform, where the recorded power supply power is determined by the charging pile management platform based on working data uploaded by the target charging pile; Determine the input power of the target charging pile based on monitoring data collected by a monitoring component provided on the transmission line of the target charging pile; Determining whether the recorded supply power matches the input power; When the recorded power supply power does not match the input power, monitoring the state of the target charging pile; When the target charging pile completes power supply, the recorded power supply of the target charging pile is obtained from the charging pile management platform, and a reference power supply of the target charging pile is determined based on the monitoring data, wherein the recorded power supply is determined by the charging pile management platform based on the working data uploaded by the target charging pile; determining whether the recorded power supply amount matches the reference power supply amount; When the reference power supply amount does not match the recorded power supply amount, it is determined that the power supply of the target charging pile is abnormal.
[0007] By adopting the above-mentioned technical scheme, the accuracy of the working data can be verified based on the monitoring data collected by the detection component, and whether the charging pile is abnormal can be determined based on the verification result, thereby realizing the monitoring of the accuracy of the working data of the charging pile, which can help to realize the effective management of the charging piles in the charging station based on the effective working data.
[0008] Optionally, when the recorded power supply power does not match the input power, monitoring the working state of the target charging pile includes: In the case that the recorded power supply power does not match the input power, determining whether a difference between the recorded power supply power and the input power is greater than a preset power difference threshold; When the difference between the recorded power supply power and the input power is not greater than the power difference threshold, the working state of the target charging pile is monitored.
[0009] In the above technical solution, when the difference between the recorded supply power and the input power is not greater than the power difference threshold, it means that the risk status of the target charging pile is controllable and there is no major safety risk. At this time, the target charging pile can be further monitored to further determine whether the target charging pile is abnormal.
[0010] Optionally, after determining whether the difference between the recorded power supply power and the input power is greater than a preset power difference threshold, the method further includes: When the difference between the recorded power supply power and the input power is greater than a working difference threshold, it is directly determined that the power supply of the target charging pile is abnormal.
[0011] By adopting the above technical solution, it can help to directly determine the power supply abnormality of the target charging pile when it is determined that there is a greater safety risk in the target charging pile based on the difference between the recorded power supply power and the input power, thereby helping to promptly remind the staff to deal with the abnormality of the charging pile, and further help to safely manage the charging piles in the charging station.
[0012] Optionally, when the recorded power supply power does not match the input power, determining whether a difference between the recorded power supply power and the input power is greater than a preset power difference threshold includes: In the case that the recorded power supply power does not match the input power, determining whether the recorded power supply power and the input power are both greater than a preset warning power threshold; In the case that either the recorded power supply power or the input power is not greater than the warning power threshold, determining whether the difference between the recorded power supply power and the input power is greater than a preset power difference threshold; When the recorded power supply power and the input power are both greater than the warning power threshold, the target charging pile is directly switched to a shutdown state.
[0013] By adopting the above technical solution, it can help to directly stop the operation of the target charging pile when it is determined that there is a greater safety risk in the target charging pile based on the recorded power supply power and input power, thereby helping to minimize the safety risk of the charging pile, and further helping to buy time for staff to carry out maintenance.
[0014] Optionally, after determining whether the reference power supply amount matches the recorded power supply amount, the method further includes: When it is determined that the reference power supply matches the recorded power supply, recording the number of risks corresponding to the target charging pile; Determine whether the risk number corresponding to the target charging pile reaches the risk number threshold; When the number of risks corresponding to the target charging pile reaches the risk number threshold, it is determined that the power supply of the target charging pile is abnormal.
[0015] By adopting the above technical solution, the target charging pile can be analyzed for abnormalities based on its historical risk conditions, which can help improve the accuracy of the abnormal analysis results and further help manage the charging piles in the charging station.
[0016] Optionally, the method further includes: For each of the charging piles, obtaining a regional image of a monitoring area corresponding to the charging pile; Determine whether there is a charging gun at the plugging position of the charging pile based on the regional image; In the case where there is no charging gun at the plugging position of the charging pile, determining whether there is a target vehicle in the monitoring area based on the area image; In the case where there is a vehicle in the monitoring area, determining whether there is a charging gun at the charging position of the target vehicle based on the area image; In the case where there is a charging gun at the charging position of the target vehicle, it is determined that the charging pile is in a power supply state.
[0017] By adopting the above technical solution, the status of the charging pile can be directly determined in combination with the regional image of the monitoring area, which can help improve the accuracy of charging pile status judgment and further help to effectively manage the charging pile.
[0018] Optionally, after determining whether there is a target vehicle in the monitoring area based on the regional image, the method further includes: In the case where the target vehicle does not exist in the monitoring area, determining whether the charging pile is in a power supply state based on the monitoring data; In the case where it is determined based on the monitoring data that the charging pile is in a power supply state, determining that the charging pile has a leakage risk, and outputting leakage alarm prompt information corresponding to the charging pile; When it is determined based on the monitoring data that the charging pile is not in a power supply state, a charging gun position abnormality prompt message is output.
[0019] By adopting the above technical solution, when there is no target vehicle in the monitoring area, the monitoring data is further combined to determine whether the charging pile is in a power supply state, and corresponding prompt information is output based on whether the charging pile is in a power supply state. In this way, the risk situation of the charging pile can be accurately reminded to the staff, which can facilitate the effective management of the charging piles in the charging station.
[0020] Optionally, after determining whether there is a charging gun at the charging position of the target vehicle based on the regional image, the method further includes: When it is determined based on the regional image that there is no charging gun at the charging position of the target vehicle, obtaining the status of the charging pile recorded in the charging pile management platform; When the management platform records that the charging pile is in a power supply state, a charging gun detachment prompt message is output.
[0021] By adopting the above technical solution, when there is no charging gun at the charging position of the target vehicle, corresponding prompt information can be further output in combination with the status of the charging pile recorded in the charging pile management platform. In this way, the staff can be accurately reminded of the risk situation of the charging pile, which can facilitate the effective management of the charging piles in the charging station.
[0022] In a second aspect, the present application provides an electronic device, which adopts the following technical solution: An electronic device, comprising: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute any one of the charging station management methods provided in the first aspect.
[0023] In a third aspect, the present application provides an electronic device, which adopts the following technical solution: A computer-readable storage medium stores a computer program, which, when executed in a computer, causes the computer to execute any one of the charging station management methods provided in the first aspect.
[0024] In summary, the present application includes at least one of the following beneficial technical effects: 1. The accuracy of the working data can be verified based on the monitoring data collected by the detection component, and whether the charging pile is abnormal can be determined based on the verification result, so as to realize the monitoring of the accuracy of the working data of the charging pile, and further help to realize the effective management of the charging piles in the charging station based on the effective working data.
[0025] 2. When the recorded power supply power does not match the input power, the recorded power supply amount and the reference power supply amount can be further determined, and when the reference power supply amount does not match the recorded power supply amount, the power supply abnormality of the target charging pile can be determined. This can help avoid the influence of short-term power differences on the abnormal judgment results, and thus help improve the accuracy of the abnormal judgment results. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a flowchart of a first charging station management method provided in an embodiment of the present application; Figure 2 is a flow chart of a second charging station management method provided in an embodiment of the present application; Figure 3 is a flowchart of a third charging station management method provided in an embodiment of the present application; Figure 4 is a flowchart of a fourth charging station management method provided in an embodiment of the present application; Figure 5 is a flowchart of a fifth charging station management method provided in an embodiment of the present application; Figure 6 is a flowchart of a sixth charging station management method provided in an embodiment of the present application; Figure 7 is a flowchart of a seventh charging station management method provided in an embodiment of the present application; Figure 8 It is a structural schematic diagram of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical solutions and advantages of this application more clear, the following Figure 1-8 It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0028] The present application embodiment discloses a charging station management method. Figure 1 , the charging station management method includes the following steps: Step 101: for a target charging pile in a power supply state, obtain the recorded power supply power of the target charging pile recorded in a charging pile management platform.
[0029] Among them, the recorded power supply power is determined by the charging pile management platform based on the working data uploaded by the target charging pile.
[0030] Optionally, the charging pile includes a power supply state, a standby state, and a shutdown state. Specifically, the power supply state means that the charging pile is being used, that is, it is outputting electric energy; the standby state means that the charging pile is in an available state; and the shutdown state means that the charging pile is in an unavailable state. In one example, the state of the charging pile is controlled by the charging pile management platform. For example, after the user scans the code to pay, the charging pile management platform controls the charging pile to enter the power supply state; after the user finishes charging or the user's balance is insufficient, the charging pile management platform controls the charging pile to end the power supply state and enter the standby state. In actual implementation, the state of the charging pile can also be adjusted by directly operating the charging pile.
[0031] In this embodiment, the charging pile has a built-in data monitoring system for collecting the working data of the charging pile, such as output current, output voltage and other data. The charging pile will transmit the working data to the charging pile management platform for the charging pile management platform to monitor and manage the charging pile.
[0032] Correspondingly, the recorded power supply power may be the power supply power directly uploaded by the target charging pile to the charging pile management platform, or may be the power supply power calculated by the charging pile management platform based on the output current and the output current uploaded by the target charging pile.
[0033] Generally speaking, since working data can directly reflect the working conditions of charging piles, they are used in the process of charging cost calculation and charging pile status monitoring. Therefore, the accuracy of working data is crucial to the management of charging piles.
[0034] Step 102: Determine the input power of the target charging pile based on monitoring data collected by a monitoring component provided on the transmission line of the target charging pile.
[0035] Among them, the transmission line of the target charging pile refers to: the cable that transmits power to the target charging pile. Specifically, the charging pile is only an electric energy conversion device, and its working principle is to convert the input electric energy and then output it to the vehicle. In other words, the charging pile itself does not generate electric energy. The transmission line is used to connect the charging pile to the power supply, which can be alternating current, such as: mains power or converted mains power, or it can also be direct current, such as: electric energy stored in an energy storage device.
[0036] In actual implementation, the operating cost of the charging station can be reduced by supplying power through the energy storage device. In one example, the charging station is provided with a parking shed, and a photovoltaic panel is provided on the top of the parking shed. The photovoltaic panel is connected to the energy storage power supply to charge the energy storage power supply. In another example, the energy storage device is connected to the mains, and the energy storage device is charged by the mains during the off-peak period.
[0037] Optionally, the monitoring component includes a current monitoring component and a voltage monitoring component, which are respectively used to collect the current and voltage of the transmission line, so that the power supply power can be calculated and recorded.
[0038] In actual implementation, the monitoring component can be installed in a hidden location of the transmission line, such as in the distribution cabinet corresponding to the charging station, and transmit the signal wirelessly. This can help avoid damage to the monitoring component and thus help improve the reliability of the monitoring data.
[0039] Step 103: determine whether the recorded power supply power matches the input power.
[0040] Generally speaking, since there will be losses in the process of power conversion by the charging pile, the actual output power will be less than the input power. Therefore, the correspondence between the recorded power supply power and the input power can be determined in advance, so as to determine whether the recorded power supply power matches the input power based on the correspondence.
[0041] In one example, determining whether the actual output power matches the input power includes: determining whether the actual output power is greater than the product of the input power and the minimum electric energy conversion rate; when the actual output power is greater than the product of the input power and the minimum electric energy conversion rate, determining that the actual output power matches the input power; when the actual output power is less than or equal to the product of the input power and the minimum electric energy conversion rate, determining that the actual output power does not match the input power.
[0042] Among them, the minimum power conversion rate is a value between 0 and 1. In actual implementation, the minimum power conversion rate can be obtained through testing. Furthermore, since the minimum power conversion rate may be affected by the input power, the value range of the input power can be divided into several continuous power intervals, and the corresponding minimum power conversion rate can be set separately for each interval, which can help improve the accuracy of the determined results.
[0043] In another example, determining whether the actual output power matches the input power includes: determining whether the actual output power is greater than the product of the input power and the maximum electric energy conversion rate; when the actual output power is greater than the product of the input power and the maximum electric energy conversion rate, determining that the actual output power does not match the input power; when the actual output power is less than or equal to the product of the input power and the maximum electric energy conversion rate, determining that the actual output power matches the input power.
[0044] The maximum power conversion rate is a value between 0 and 1, and the maximum power conversion rate is greater than the minimum power conversion rate. The method for determining the maximum power conversion rate is similar to the method for determining the minimum power conversion rate, and this embodiment will not be repeated here.
[0045] In practice, it is found that when the actual electric energy conversion rate is too high, the data acquisition system of the charging pile itself may fail, or the working data may be tampered with. These situations will affect the management of the charging pile and may also cause financial and tax risks. Therefore, it is also necessary to judge the situation where the electric energy conversion rate is too high.
[0046] In some embodiments, the power loss of the charging pile can be estimated, and the minimum power conversion rate and / or the maximum power conversion rate can be adjusted in combination with the estimated power loss, so as to further improve the accuracy of the determined results. In one example, the actual temperature of the charging pile is recorded in the charging pile management platform. At this time, the power conversion rate can be adjusted in combination with the difference between the actual temperature and the reference temperature corresponding to the input power. Specifically, taking the adjustment of the minimum power conversion rate as an example, when the actual temperature is less than the reference temperature, the minimum power conversion rate is increased; when the actual temperature is greater than the reference temperature, the minimum power conversion rate is reduced. Furthermore, the amplitude of the power conversion rate adjustment can be determined within a preset amplitude range in combination with the gap between the actual temperature and the reference temperature. The larger the gap, the larger the adjustment amplitude.
[0047] Step 104 , when the recorded power supply power does not match the input power, the working state of the target charging pile is monitored.
[0048] Optionally, when the recorded supply power matches the input power, there is no need to monitor the working status of the target charging pile.
[0049] In this embodiment, monitoring the state of the target charging pile includes: determining whether the target charging pile has completed the current power supply. Specifically, when the target working pile switches from the power supply state to the standby state or the shutdown state, it is determined that the target charging pile has completed the current power supply.
[0050] Step 105, when the target charging pile completes power supply this time, obtain the recorded power supply of the target charging pile this time from the charging pile management platform, and determine the reference power supply of the target charging pile this time based on the monitoring data.
[0051] Among them, the recorded power supply amount is determined by the charging pile management platform based on the data uploaded by the target charging pile.
[0052] In actual implementation, the recorded power supply amount can be determined based on the recorded power supply power of the target charging pile during the charging process, and the reference power supply amount can be determined based on the real-time input power of the target charging pile during the charging process.
[0053] Step 106, determining whether the recorded power supply matches the reference power supply; Generally speaking, since there will be losses in the process of power conversion of the charging pile, the recorded power supply will be less than the reference power supply. Therefore, the correspondence between the recorded power supply and the reference power supply can be determined in advance to determine whether the recorded power supply power matches the input power based on the correspondence.
[0054] In one example, determining whether the recorded power supply matches the reference power supply includes: determining the power supply difference between the recorded power supply and the reference power supply; determining whether the ratio of the power supply difference to the current power supply duration is greater than a minimum ratio threshold; if so, determining that the recorded power supply matches the reference power supply; if not, determining that the recorded power supply does not match the reference power supply.
[0055] In actual implementation, the minimum ratio threshold can be obtained through testing. For example, the minimum ratio threshold is the ratio threshold calculated when the power conversion rate of the charging pile is the highest. The method for determining the minimum ratio threshold refers to the method for determining the minimum power conversion rate mentioned above, which will not be repeated here.
[0056] In the above example, since it is taken into account that the difference in power supply will produce a cumulative effect as the charging time increases, the charging time factor is taken into account in the process of recording the power supply to match the reference power supply. This can help reduce the impact of the charging time on the determination result, which in turn can help improve the accuracy of the determination result.
[0057] Furthermore, when it is determined that the ratio of the power supply difference to the power supply duration is greater than a preset minimum ratio threshold, it is further determined whether the ratio of the power supply difference to the power supply duration is greater than a preset maximum ratio threshold; if not, it is determined that the recorded power supply matches the reference power supply; if so, it is determined that the recorded power supply does not match the reference power supply.
[0058] Step 107 : When the reference power supply amount does not match the recorded power supply amount, it is determined that the power supply of the target charging pile is abnormal.
[0059] Optionally, after determining that the target charging pile has power supply anomaly, the method further includes: generating abnormal prompt information corresponding to the target power supply pile and outputting it to the administrator. For example, the abnormal prompt information corresponding to the target charging pile is sent to the administrator through an application installed on the administrator terminal. Another example is: outputting the abnormal prompt information corresponding to the target charging pile on the abnormal warning interface of the charging pile management system.
[0060] In actual implementation, the content of the abnormal prompt information can be set according to actual needs. Specifically, the abnormal prompt information may include at least one of the information related to the target charging pile, such as the number of the target charging pile, the location information of the target charging pile, the abnormal type of the target charging pile (for example: the conversion rate is too high or the conversion rate is too low), etc.
[0061] Optionally, after determining that the target charging pile has power supply anomaly, the method further includes: performing corresponding processing based on the anomaly type corresponding to the target charging pile. Specifically, the method includes but is not limited to the following situations: When the abnormal type of the target charging pile is too low power conversion rate, the target charging pile is controlled to stop supplying power or reduce the input power of the target charging pile. When the power conversion rate is too low, the target charging pile may have a greater safety risk, such as leakage, excessive heat generation, etc. At this time, the system can automatically control the target charging pile to stop supplying power or reduce the input power, which can help reduce the safety risk of the target charging pile and buy time for maintenance staff.
[0062] When the abnormality type of the target charging pile is that the electric energy conversion rate is too high, in the process of settling the current charging fee, the reference power supply and the preset conversion rate are used to determine the predicted power supply, and the electricity fee for this charging is calculated based on the predicted power supply. At this time, since the preset conversion rate will be lower than the maximum conversion rate, this can help improve the rationality of fee settlement, thereby helping to ensure user experience. In actual implementation, when the abnormality type of the target charging pile is that the conversion rate is too high, coupons can also be issued to the corresponding users for the settlement of this fee, which can help to ensure user experience.
[0063] The implementation principle of a charging station management method in an embodiment of the present application is as follows: for a target charging pile in a power supply state, obtaining a recorded power supply power of the target charging pile recorded in a charging pile management platform, where the recorded power supply power is determined by the charging pile management platform based on the working data uploaded by the target charging pile; determining the input power of the target charging pile based on the monitoring data collected by a monitoring component arranged on the transmission line of the target charging pile; determining whether the recorded power supply power matches the input power; in the case where the recorded power supply power does not match the input power, monitoring the state of the target charging pile; in the case where the power supply of the target charging pile is completed this time, obtaining the recorded power supply amount of the target charging pile this time from the charging pile management platform, and determining the reference power supply amount of the target charging pile this time based on the monitoring data, where the recorded power supply amount is determined by the charging pile management platform based on the working data uploaded by the target charging pile; determining whether the recorded power supply amount matches the reference power supply amount; in the case where the reference power supply amount does not match the recorded power supply amount, determining that the power supply of the target charging pile is abnormal. In the above technical scheme, the corresponding parameters can be determined and matched based on the working data uploaded by the charging pile and the monitoring data collected by the monitoring component set on the transmission line of the charging pile, and whether the state of the charging pile is abnormal can be determined based on the matching relationship between the parameters. In this way, the accuracy of the working data can be verified based on the monitoring data collected by the monitoring component, and whether the charging pile is abnormal can be determined based on the verification result, thereby realizing the monitoring of the accuracy of the working data of the charging pile, which can help to realize the effective management of the charging piles in the charging station based on the effective working data.
[0064] At the same time, since the recorded power supply power and the input power do not match, the recorded power supply and the reference power supply are further determined, and the power supply abnormality of the target charging pile is determined when the reference power supply does not match the recorded power supply. This can help avoid the impact of short-term power differences on the abnormal judgment results, and thus help improve the accuracy of the abnormal judgment results.
[0065] In some embodiments, reference Figure 2 Step 104, when the recorded power supply power does not match the input power, monitor the working state of the target charging pile, including the following steps: Step 201: When the recorded power supply power does not match the input power, determine whether the difference between the recorded power supply power and the input power is greater than a preset power difference threshold.
[0066] Specifically, the power difference threshold can be set based on actual experience or can also be obtained through actual testing. In one example, the power difference threshold is determined based on the maximum difference between the input power and the power supply power when the charging pile is working normally, and the power difference threshold is not less than the maximum power difference obtained by the test. In one example, the maximum power difference obtained by the test is determined as the power difference threshold.
[0067] Step 202: When the difference between the recorded supply power and the input power is not greater than the power difference threshold, the working state of the target charging pile is monitored.
[0068] Specifically, when the difference is not greater than the power difference threshold, it means that the risk status of the target charging pile is controllable and there is no major safety risk. At this time, the target charging pile can be further monitored to further determine whether the target charging pile is abnormal.
[0069] Step 203: When the difference between the recorded power supply power and the input power is greater than the working difference threshold, it is directly determined that the power supply of the target charging pile is abnormal.
[0070] Specifically, when the difference is greater than the power recharge threshold, it means that the charging pile may have a greater safety risk. At this time, directly determining that there is an abnormality in the charging pile can help prompt management personnel to inspect and handle the target charging pile in a timely manner.
[0071] In other embodiments, when the difference between the recorded power supply power and the transmission power is greater than the working difference threshold, the target charging pile can be directly adjusted to the shutdown state, or the temperature of the target charging pile can be further determined; when the temperature of the target charging pile is greater than the preset maximum temperature threshold, the target charging pile is adjusted to the shutdown state; when the temperature of the target charging pile is less than or equal to the preset maximum temperature threshold, it is determined that the power supply of the target power supply pile is abnormal. In this way, the high-risk situation of excessive temperature can be handled, which can help improve the safety of the charging pile.
[0072] In the above implementation, when the recorded power supply power does not match the input power, it can be determined whether to continue monitoring the working status of the target charging pile by further combining the relationship between the difference between the power supply power and the input power and the power difference threshold, and when it is monitored that the difference is greater than the power difference threshold, it is directly determined that the power supply of the target charging pile is abnormal. In this way, when there is a greater safety risk in the target charging pile, it can be directly determined that the power supply of the target charging pile is abnormal, which can help to promptly remind the staff to deal with the abnormality of the charging pile, and further help to safely manage the charging piles in the charging station.
[0073] For further reference, Figure 3 In the above step 201, when the recorded power supply power does not match the input power, determining whether the difference between the recorded power supply power and the input power is greater than a preset power difference threshold value includes the following steps: Step 301: When the recorded power supply power does not match the input power, determine whether the recorded power supply power and the input power are both greater than a preset warning power threshold.
[0074] Specifically, the warning power threshold can be set based on actual experience or obtained through actual testing. In one example, the warning power threshold is determined based on the maximum value of the power supply power when the charging pile is working normally, and the warning power threshold is not greater than the maximum value of the power supply power obtained by the test. In one example, the maximum value of the power supply power obtained by the test is determined as the warning power threshold.
[0075] Step 302: When either the recorded power supply power or the input power is not greater than the warning power threshold, determine whether the difference between the recorded power supply power and the input power is greater than a preset power difference threshold.
[0076] Specifically, when either the recorded power supply power or the input power is not greater than the warning power threshold, it means that the risk status of the target charging pile is controllable and there is no major safety risk. At this time, the recorded power and input power corresponding to the target charging pile can be judged to determine whether the target charging pile is abnormal.
[0077] Step 303: When the recorded power supply power and input power are both greater than the warning power threshold, the target charging pile is directly switched to a shutdown state.
[0078] Specifically, when both the recorded power and the input power are greater than the warning power threshold, there is a greater risk in the target charging pile. At this time, directly switching the target charging pile to the shutdown state can minimize the safety risk of the charging pile, thereby buying time for staff to carry out maintenance.
[0079] In other examples, when both the recorded power supply power and the input power are greater than the warning power threshold, the input power of the target charging pile can be reduced without switching the target charging pile to a shutdown state, thereby reducing safety risks while ensuring the user experience. Furthermore, when the input power of the target charging pile is reduced, it is possible to continue to determine whether the difference between the recorded power supply power and the input power is greater than a preset power difference threshold to determine the abnormality of the target charging pile.
[0080] In one example, when the recorded power supply power and input power are both greater than the warning power threshold, it also includes: output power abnormality prompt information to prompt the management personnel to deal with the power abnormality of the target charging pile.
[0081] In the above embodiment, before determining the working state of the target charging pile based on the relationship between the difference between the recorded power supply power and the input power and the power difference threshold, the relationship between the recorded power supply power and the input power and the warning power threshold can be determined, and when the recorded power supply power and the input power are both greater than the preset power difference threshold, the target charging pile can be directly switched to the shutdown state. This can help to directly stop the operation of the target charging pile when it is determined that there is a greater safety risk in the target charging pile based on the size of the recorded power supply power and the input power, thereby helping to minimize the safety risk of the charging pile, and further helping to buy time for the staff's maintenance.
[0082] In some embodiments, reference Figure 4 , step 106, after determining whether the recorded power supply amount matches the reference power supply amount, further comprising: Step 401, when it is determined that the reference power supply matches the recorded power supply, the number of risks corresponding to the target charging pile is recorded.
[0083] Among them, within a preset time range (for example: one week), the number of risks corresponding to different charging piles is cumulatively calculated.
[0084] Step 402, determining whether the number of risks corresponding to the target charging pile reaches a risk number threshold.
[0085] Specifically, the risk times threshold can be preset. Furthermore, the preset risk times threshold can be adjusted according to the actual situation. In one example, the risk factor adjustment method is determined based on the distribution of the risk times corresponding to each charging pile in the charging station where the target charging pile is located; the preset risk times threshold is adjusted based on the risk factor adjustment method to obtain the risk times threshold actually used.
[0086] In one example, the average value of the risk times corresponding to each charging pile in the charging station where the target charging pile is located is determined as the average risk time; when the average risk time is greater than the preset reference risk time, the risk time threshold adjustment method is determined to increase the risk time threshold; when the average risk time is less than the preset reference risk time, the risk time threshold adjustment method is determined to reduce the risk time threshold.
[0087] Step 403: When the number of risks corresponding to the target charging pile reaches a risk number threshold, it is determined that the power supply of the target charging pile is abnormal.
[0088] When the number of risks corresponding to the target charging pile does not reach the risk number threshold, the target charging pile may be marked as a risk, or may not be processed.
[0089] In the above embodiment, when it is determined that the reference power supply matches the recorded power supply, the number of risk times corresponding to the target charging pile can be recorded, and when the number of risk times corresponding to the target charging pile reaches a risk number threshold, the power supply abnormality of the target charging pile can be determined. In this way, the target charging pile can be analyzed for abnormalities based on the historical risk situation of the target charging pile, which can help improve the accuracy of the abnormal analysis results, and further help manage the charging piles in the charging station.
[0090] In some embodiments, reference Figure 5 , the charging station management method further includes the following steps: Step 501: for each charging pile, a regional image of the monitoring area corresponding to the charging pile is obtained.
[0091] The monitoring area includes the area where the charging pile is located and the area where the charging position corresponding to the charging pile is located. In one example, several cameras are set up in the charging station to collect real-time images of the charging station, and the images collected by different cameras are spliced based on the installation positions and image acquisition directions of different cameras to obtain the monitoring video corresponding to the charging station. In this way, the area image corresponding to the charging pile can be intercepted from the monitoring video based on the monitoring area corresponding to the charging pile.
[0092] Step 502: Determine whether there is a charging gun at the plugging position of the charging pile based on the area image.
[0093] Among them, the plug-in position refers to the position on the charging pile for placing the charging gun.
[0094] Optionally, determining whether there is a charging gun at the plugging position of the charging pile based on the area image includes: intercepting first image information corresponding to the plugging position from the area image; and analyzing the first image information to determine whether there is a charging gun at the plugging position.
[0095] In one example, image information is analyzed to determine whether there is a charging gun at the plug-in position, including: calculating the similarity between the image information and the template image; when the similarity is greater than or equal to a preset similarity threshold, determining that there is a charging gun at the plug-in position; when the similarity is less than the similarity threshold, determining that there is no charging gun at the plug-in position.
[0096] The template image is collected when there is a charging gun at the plug-in position of the charging pile.
[0097] In actual implementation, a pre-trained image recognition model can also be used to determine whether there is a charging gun at the plug-in position of the charging pile.
[0098] Step 503: When there is no charging gun at the plugging position of the charging pile, determine whether there is a target vehicle in the monitoring area based on the area image.
[0099] When there is a charging gun at the plugging position of the charging pile, it is determined that the charging pile is not in a power supply state.
[0100] Optionally, determining whether there is a target vehicle in the monitoring area based on the regional image includes: inputting the image information into a pre-trained vehicle recognition model to obtain a recognition result.
[0101] The recognition result is used to indicate whether there is a vehicle in the image information.
[0102] The vehicle model is obtained by training the initial network model using training data, wherein the training data includes at least one set of sample data, each set of sample data includes a sample image and a label indicating whether the sample image includes a vehicle. Furthermore, the sample image is obtained by collecting monitoring areas corresponding to different charging piles.
[0103] Step 504 : if there is a vehicle in the monitoring area, determine whether there is a charging gun at the charging position of the target vehicle based on the area image.
[0104] The charging position refers to the position on the target vehicle for inserting the charging gun.
[0105] Optionally, determining whether there is a charging gun at the charging position of the target vehicle based on the area image includes: intercepting second image information corresponding to the charging position from the area image; and analyzing the second image information to determine whether there is a charging gun at the charging position.
[0106] Specifically, the method of analyzing the second image information is the same as the method of analyzing the first image information, and this embodiment will not be repeated here.
[0107] In one example, capturing second image information corresponding to the charging position from the area image includes: determining a vehicle image corresponding to the target vehicle from the area image; and determining an image corresponding to the charging position in the vehicle image as the second image information.
[0108] In actual implementation, the target vehicle may correspond to multiple charging positions. In this case, as long as there is a charging gun at any charging position of the target vehicle, it can be determined that there is a charging gun at the charging position of the target vehicle.
[0109] Step 505: When there is a charging gun at the charging position of the target vehicle, determine that the charging pile is in a power supply state.
[0110] In the above embodiment, since the position status of the charging gun and whether there is a target vehicle in the area can be determined based on the regional image of the monitoring area corresponding to the charging pile, and when there is a target vehicle in the monitoring area and a charging gun at the charging position of the target vehicle, it is determined that the charging pile is in a power supply state, the state of the charging pile can be directly determined in combination with the regional image of the monitoring area, which can help improve the accuracy of the judgment of the charging pile state, and further help to effectively manage the charging pile.
[0111] For further reference, Figure 6 In the above step 503, after determining whether there is a target vehicle in the monitoring area based on the regional image, the following steps are also included: Step 601: When there is no target vehicle in the monitoring area, determine whether the charging pile is in a power supply state based on the monitoring data.
[0112] Specifically, when there is no charging gun at the plug-in position and no vehicle in the monitoring area, it means that the charging gun is not properly protected, which may cause safety risks. Therefore, further judgment and processing are performed in this embodiment.
[0113] Optionally, determining whether the charging pile is in a power supply state based on the monitoring data includes: determining the input power of the target charging pile based on the monitoring data; determining whether the input power is greater than a preset minimum input power; if so, determining that the charging pile is in a power supply state; if not; determining that the charging pile is not in a power supply state.
[0114] In actual implementation, it is also possible to determine whether the charging pile is in a power supply state based on the current, voltage and other data in the monitoring data.
[0115] Step 602, when it is determined based on the monitoring data that the charging pile is in a power supply state, it is determined that there is a leakage risk in the charging pile, and leakage alarm prompt information corresponding to the charging pile is output.
[0116] Specifically, when the monitoring data indicates that the charging pile is in a power supply state but the charging gun is not placed in a standardized manner, there is a greater risk of leakage. At this time, outputting the leakage alarm prompt information corresponding to the charging pile can help prompt the management personnel to take corresponding measures in time, thereby avoiding fire caused by leakage.
[0117] Furthermore, when it is determined based on monitoring data that the charging pile is in a power supply state, the method includes: switching the charging pile to a shutdown state or limiting the input power of the charging pile. This can help reduce the safety risk of the charging pile and buy time for maintenance staff.
[0118] Step 603: When it is determined based on the monitoring data that the charging pile is not in a power supply state, output a prompt message indicating that the charging gun position is abnormal.
[0119] Specifically, when the monitoring data indicates that the charging pile is not in a power supply state, it means that the safety risk of the charging gun not being properly prevented is low. At this time, only the abnormal position prompt information of the charging gun is output to guide the management personnel to return the charging gun to its position.
[0120] In the above implementation, when there is no target vehicle in the monitoring area, the monitoring data is further combined to determine whether the charging pile is in a power supply state, and corresponding prompt information is output in combination with whether the charging pile is in a power supply state. This can accurately remind the staff of the risk situation of the charging pile, thereby facilitating the effective management of the charging piles in the charging station.
[0121] For further reference, Figure 7 , step 504, after determining whether there is a charging gun at the charging position of the target vehicle based on the regional image, the following steps are also included: Step 701, when it is determined based on the area image that there is no charging gun at the charging position of the target vehicle, the status of the charging pile recorded in the charging pile management platform is obtained.
[0122] The status of the charging pile recorded by the charging pile management platform is determined based on the charging order data. Specifically, if there is an uncompleted order corresponding to the charging pile, the charging pile management platform records that the charging pile is in a power supply state; if there is no uncompleted order corresponding to the charging pile, the charging pile management platform records that the charging pile is in a non-power supply state.
[0123] Step 702: When the charging pile is in a power supply state, the management platform records that the charging gun has fallen off and outputs a prompt message.
[0124] Specifically, if the management platform records that the charging pile is in power supply status, it means that the charging pile is in use. However, if the charging gun is not in the charging position of the target vehicle at this time, it means that the charging gun may fall off during the charging process, so corresponding prompts are required.
[0125] In actual implementation, the charging gun detachment prompt information can be sent to the management personnel, or it can be sent to the users of the uncompleted orders corresponding to the charging pile, for example: pushed to the user terminal through in-application messages or text messages, which can help to handle abnormalities in the charging process in a timely manner.
[0126] Optionally, when it is recorded in the management platform that the charging pile is not in a power supply state, a prompt message indicating that the charging gun position is abnormal can be output to prompt the management personnel to return the charging gun to its position.
[0127] In actual implementation, when it is determined based on the area image that there is no charging gun at the charging position of the target vehicle, the technical solution of outputting prompt information based on monitoring data in the above steps 601 to 603 can also be executed, which can help to further realize the refined management of charging piles.
[0128] In the above embodiment, when there is no charging gun at the charging position of the target vehicle, it is further necessary to output corresponding prompt information in combination with the status of the charging pile recorded in the charging pile management platform, so that the staff can be accurately reminded of the risk situation of the charging pile, thereby facilitating the effective management of the charging piles in the charging station.
[0129] The present application also provides an electronic device. Figure 8 As shown, Figure 8 The electronic device 800 shown includes: a processor 801 and a memory 803. The processor 801 and the memory 803 are connected, such as through a bus 802. Optionally, the electronic device 800 may also include a transceiver 804. It should be noted that in actual applications, the transceiver 804 is not limited to one, and the structure of the electronic device 800 does not constitute a limitation on the embodiments of the present application.
[0130] The processor 801 may be a CPU (Central Processing Unit), a general-purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), or other programmable logic devices, transistor logic devices, hardware components, or any combination thereof. It may implement or execute various exemplary logic blocks, modules, and circuits described in conjunction with the disclosure of this application. The processor 801 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, and the like.
[0131] The bus 802 may include a path to transmit information between the above components. The bus 802 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus. The bus 802 may be divided into an address bus, a data bus, etc. For ease of representation, Figure 8 Only one thick line is used in the diagram, but this does not mean that there is only one bus or only one type of bus.
[0132] The memory 803 can be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited to these.
[0133] The memory 803 is used to store the application code for executing the solution of the present application, and the execution is controlled by the processor 801. The processor 801 is used to execute the application code stored in the memory 803 to implement the content shown in the above method embodiment.
[0134] The electronic devices include, but are not limited to, mobile terminals such as mobile phones, laptop computers, PDAs (personal digital assistants), PADs (tablet computers), etc., and fixed terminals such as digital TVs, desktop computers, etc. It can also be a server terminal, etc. Figure 8 The electronic device shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.
[0135] The embodiment of the present application also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed in a computer, the computer is caused to execute the charging station management method provided in the above embodiment.
[0136] It should be understood that although the steps in the flowchart of the accompanying drawings are shown in sequence according to the instructions of the arrows, these steps are not necessarily performed in the order indicated by the arrows. Unless otherwise clearly stated in this document, the execution of these steps is not strictly limited in order and can be performed in other orders.
[0137] The above are only some implementation methods of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.
Claims
1. A charging station management method, wherein the charging station includes more than two charging piles, characterized in that: The method comprises: For a target charging pile in a power supply state, obtaining a recorded power supply power of the target charging pile recorded in a charging pile management platform, where the recorded power supply power is determined by the charging pile management platform based on working data uploaded by the target charging pile; Determine the input power of the target charging pile based on monitoring data collected by a monitoring component provided on the transmission line of the target charging pile; Determining whether the recorded supply power matches the input power; When the recorded power supply power does not match the input power, monitoring the state of the target charging pile; When the target charging pile completes power supply, the recorded power supply of the target charging pile is obtained from the charging pile management platform, and a reference power supply of the target charging pile is determined based on the monitoring data, wherein the recorded power supply is determined by the charging pile management platform based on the working data uploaded by the target charging pile; determining whether the recorded power supply amount matches the reference power supply amount; When the reference power supply amount does not match the recorded power supply amount, it is determined that the power supply of the target charging pile is abnormal.
2. The method according to claim 1, characterized in that When the recorded power supply power does not match the input power, monitoring the working state of the target charging pile includes: In the case that the recorded power supply power does not match the input power, determining whether a difference between the recorded power supply power and the input power is greater than a preset power difference threshold; When the difference between the recorded power supply power and the input power is not greater than the power difference threshold, the working state of the target charging pile is monitored.
3. The method according to claim 2, characterized in that After determining whether the difference between the recorded power supply power and the input power is greater than a preset power difference threshold, the method further includes: When the difference between the recorded power supply power and the input power is greater than a working difference threshold, it is directly determined that the power supply of the target charging pile is abnormal.
4. The method according to claim 2, characterized in that: In the case where the recorded power supply power does not match the input power, determining whether a difference between the recorded power supply power and the input power is greater than a preset power difference threshold includes: In the case that the recorded power supply power does not match the input power, determining whether the recorded power supply power and the input power are both greater than a preset warning power threshold; In the case that either the recorded power supply power or the input power is not greater than the warning power threshold, determining whether the difference between the recorded power supply power and the input power is greater than a preset power difference threshold; When the recorded power supply power and the input power are both greater than the warning power threshold, the target charging pile is directly switched to a shutdown state.
5. The method according to claim 1, characterized in that After determining whether the reference power supply amount matches the recorded power supply amount, the method further includes: When it is determined that the reference power supply matches the recorded power supply, recording the number of risks corresponding to the target charging pile; Determine whether the risk number corresponding to the target charging pile reaches the risk number threshold; When the number of risks corresponding to the target charging pile reaches the risk number threshold, it is determined that the power supply of the target charging pile is abnormal.
6. The method according to claim 1, characterized in that The method further comprises: For each of the charging piles, obtaining a regional image of a monitoring area corresponding to the charging pile; Determine whether there is a charging gun at the plugging position of the charging pile based on the regional image; In the case where there is no charging gun at the plugging position of the charging pile, determining whether there is a target vehicle in the monitoring area based on the area image; In the case where there is a vehicle in the monitoring area, determining whether there is a charging gun at the charging position of the target vehicle based on the area image; In the case where there is a charging gun at the charging position of the target vehicle, it is determined that the charging pile is in a power supply state.
7. The method according to claim 6, characterized in that After determining whether there is a target vehicle in the monitoring area based on the regional image, the method further includes: In the case where the target vehicle does not exist in the monitoring area, determining whether the charging pile is in a power supply state based on the monitoring data; In the case where it is determined based on the monitoring data that the charging pile is in a power supply state, determining that the charging pile has a leakage risk, and outputting leakage alarm prompt information corresponding to the charging pile; When it is determined based on the monitoring data that the charging pile is not in a power supply state, a charging gun position abnormality prompt message is output.
8. The method according to claim 6, characterized in that After determining whether there is a charging gun at the charging position of the target vehicle based on the regional image, the method further includes: When it is determined based on the regional image that there is no charging gun at the charging position of the target vehicle, obtaining the status of the charging pile recorded in the charging pile management platform; When the management platform records that the charging pile is in a power supply state, a charging gun detachment prompt message is output.
9. An electronic device, characterized in that: The electronic device comprises: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute the charging station management method according to any one of claims 1 to 8.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed in a computer, the computer is caused to execute the charging station management method according to any one of claims 1 to 8.
Citation Information
Cited By
Charging gun intelligent electric leakage detection method, storage medium and execution equipment
CN119199642A
Monitoring method and system for electricity stealing behavior of smart station
CN120986251A