Construction method of prefabricated assembly type cover plate combined slab culvert
By adopting fixed-type pouring integrated formwork, heavy object compaction truss system and other technologies in the construction of cover culverts, the problems of long construction cycles and difficult to control concrete quality in traditional construction methods are solved, and more efficient and safer Prefabricated prefabricated cover plate culvert construction.
Patent Information
- Application Number
- CN202410990209.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-11-12
AI Technical Summary
The traditional cover culvert construction methods have problems such as long construction cycle, difficult to control concrete quality, and great environmental impact. The existing prefabricated prefabricated methods have shortcomings in formwork design, transportation stability and pouring process.
Using fixed-shaped anti-spill casting integrated formwork, heavy-object compact truss system, transportation stabilization bracket, pouring scraping integrated mobile truss base plate casting device, internal support formwork system and hanging casting device, through splicing steel molds, heavy Material compaction, transportation and stabilization bracket, pouring scraping flat bottom plate, inner support formwork and hanging pouring technology to improve construction efficiency and quality.
The precast casting efficiency and uniformity of cover plates are improved, transportation safety and casting quality are enhanced, mold removal process is simplified, and construction speed and safety are improved.
Smart Images

Figure CN118932895A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge and culvert construction, and in particular relates to a construction method of a prefabricated assembled cover plate combined cover plate culvert. Background Art
[0002] In the traditional construction of slab culverts, the on-site pouring method is usually adopted, which has many limitations. First, on-site pouring depends on weather conditions, the construction period is long, and it is easily affected by environmental factors, resulting in low construction efficiency. Secondly, the quality of concrete poured on site is difficult to control, and cracks and leakage are prone to occur, which affects the durability and safety of the structure. In addition, on-site construction has a great interference with the surrounding environment, which is not conducive to environmental protection and the cleanliness of the construction site. In order to solve these problems, the prefabricated and assembled construction method came into being. It prefabricated components in the factory and then transported them to the site for assembly, which greatly improved the construction efficiency and quality and reduced the impact on the environment. However, the existing prefabricated and assembled slab culvert construction method still has deficiencies in template design, transportation stability, pouring process, etc., and needs to be further optimized to achieve a more efficient, safer and more environmentally friendly construction process. The present invention is proposed in this context, aiming to solve the deficiencies in the prior art through innovative construction methods and promote the development of prefabricated and assembled slab culvert construction technology. Summary of the invention
[0003] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a construction method for a prefabricated assembled cover plate combined cover plate culvert.
[0004] The construction method of the prefabricated assembled cover plate combined cover plate culvert comprises the following steps:
[0005] S1, L-shaped steel mold, irregular steel mold and rectangular steel mold are spliced to form a standardized anti-overflow casting integrated template, and the anti-overflow casting trolley slides on the upper part of the L-shaped steel mold to cast the prefabricated assembled cover plate combined cover plate culvert;
[0006] S2. Heavy object truss system compaction and curing: During the curing period, the steel formwork is compressed by compacting the truss system with heavy objects;
[0007] S3. Stack the prefabricated assembled cover plates, and arrange transportation and stabilization brackets between the cover plates of two adjacent layers of prefabricated assembled cover plates combined cover plate culvert; transport the cover plates to the designated installation location;
[0008] S4, casting the truss bottom plate by using a casting and leveling integrated movable truss bottom plate casting device, and performing leveling at the same time;
[0009] S5. Use the inner support formwork system to erect the side wall formwork, and then use the hanging casting device to cast the side wall;
[0010] S6. After hoisting the prefabricated assembled cover plate combined cover plate culvert, use the hanging casting device to carry out the cast-in-place layer construction.
[0011] Preferably, the standardized overflow prevention casting integrated formwork includes a steel mold and an overflow prevention casting trolley; the steel mold includes an L-shaped steel mold, an irregular steel mold and a rectangular steel mold; the L-shaped steel mold, the irregular steel mold and the rectangular steel mold are fixed and spliced by bolts to form a steel mold body; two channel steel slide rails are fixed at both ends of the upper part of the L-shaped steel mold by bolts; the overflow prevention casting trolley is mounted on the channel steel slide rails, and the overflow prevention casting trolley slides back and forth along the channel steel slide rails.
[0012] Preferably, the anti-overflow pouring trolley includes a cavity steel body, a first pulley, a Y-shaped hopper, an equipment box and a first scraper; the first pulley is fixed to the lower end of the cavity steel body, and the first pulley is mounted on a channel steel slide rail; the Y-shaped hopper is installed on the upper part of the cavity steel body; the equipment box is fixed to the front end of the cavity body, and the equipment box includes a telescopic rod, a fixed block, a battery, a first motor and a spiral stirring rod; the telescopic rod is installed on the fixed block; the tip of the telescopic rod is provided with a first clamping device, and the first clamping device is telescopically displaced forward and backward through the telescopic rod during pouring; a transverse slide is provided on the fixed block, and the telescopic rod is transversely displaced in the transverse slide; the fixed block is installed on the battery, and the battery supplies energy for the entire anti-overflow pouring trolley device; the first motor is installed under the battery, and the first motor is connected to the spiral stirring rod, and the spiral stirring rod rotates in the cavity steel body. When working, the first motor drives the spiral stirring rod to rotate and stir the falling concrete to make it uniform; the first scraper is installed at the rear end of the cavity body to facilitate the scraping of concrete at the top of the steel formwork.
[0013] Preferably, after the L-shaped steel formwork is set up, a first steel diagonal brace and a vibrating motor are installed between two sides of the L-shaped steel formwork.
[0014] Preferably, a weight compaction truss system is supported on a cover plate that has been cast but not yet demolded, and the weight compaction truss system includes a basic truss structure, a steel beam and a weight; the bottom end of the basic truss structure is supported above the bottom edge of the L-shaped steel formwork, and the steel beam is formed by splicing channel steels and supported on the top of the basic truss structure; by pressing the steel beam with a heavy object, it is ensured that the steel formwork does not expand during maintenance.
[0015] Preferably, the cover plate transportation stabilizing bracket comprises a steel plate and a steel diagonal brace; the prefabricated assembled cover plate transportation method adopts stacking transportation; the transportation stabilizing bracket is arranged between the cover plates of two adjacent layers of prefabricated assembled cover plate combined cover plate culvert.
[0016] Preferably, the casting and scraping integrated movable truss bottom plate casting device comprises a steel truss, a second pulley, a steel slider, a sliding channel steel bar and a second scraper; the steel trusses are arranged in parallel on both sides of the bottom plate, and a longitudinal slide rail is arranged on the upper end of the steel truss; second pulleys are installed at the bottom of both ends of the sliding channel steel bar, and the second pulleys are embedded in the longitudinal slide rail of the steel truss, and the sliding channel steel bar moves back and forth along the longitudinal slide rail as a whole; a transverse slide rail is added to the upper surface of the sliding channel steel bar; a second casting head is provided on one side of the steel slider, and the bottom of the steel slider is mounted on the sliding channel steel bar through wheels; the second scraper is fixed on one side of the sliding channel steel bar, and scrapes the concrete when the sliding channel steel bar slides along the longitudinal track.
[0017] Preferably, the internal support formwork system includes a side wall steel formwork, a segmented through-screw rod and a second steel diagonal brace; after the side wall steel formwork is erected, the second steel diagonal brace is installed on the inner side of the side wall steel formworks on both sides; then, the segmented through-screw rod is used to penetrate the side wall steel formworks on both sides and tension them inward, thereby fixing the internal support formwork system.
[0018] Preferably, the hanging casting device comprises a hanging rope, a third casting head, a second clamp, a lifting ear, a barrel, a spiral stirring rod and a second motor; during construction, the hanging device is lifted by a crane pulling the hanging rope through the lifting ear; a hole is provided at the bottom of the barrel body, the second clamp is fixed to the side of the barrel body, and concrete is pumped out from the third casting head; the pumped concrete falls into the barrel body, and a spiral stirring rod is provided in the barrel body to stir the concrete, which is evenly spread into the side wall steel mold from the hole at the bottom of the barrel body.
[0019] Preferably, when removing the formwork after the side wall curing is completed, the nodes of the segmented through screws are first disconnected, and then the bolts on both sides of the side form are loosened and the through screws are pulled out for demolding.
[0020] The beneficial effects of the present invention are:
[0021] 1) The present invention greatly improves the efficiency and uniformity of prefabricated cover plate casting through standardized anti-overflow casting integrated formwork technology, achieving an anti-overflow effect. Concrete is delivered to the casting nozzle by an external pouring machine delivery pump, and then evenly sprayed into the Y-shaped funnel by the repeated displacement of the telescopic rod; and the continuously rotating spiral stirring rod makes the concrete in the Y-shaped hopper fall evenly and quickly into the feed mold groove, and the trolley repeatedly moves at the same time, making the material drop more uniform and the concrete filling efficiency higher; a vibrating motor is added to the outside of the L-shaped steel mold to ensure that the concrete falling into the groove mold is evenly spread and settled; the scraper at the rear of the trolley also makes it possible to use the repeated displacement of the trolley to scrape the top concrete after the casting is completed; in addition, the setting of the battery makes the overall device not rely on an external power supply, which is convenient and lightweight.
[0022] 2) The present invention greatly improves the efficiency of bottom plate casting by setting a casting and scraping integrated movable truss bottom plate casting device. The concrete is delivered to the casting nozzle by an external pouring machine delivery pump, and then the steel slide holding the casting nozzle slides horizontally and repeatedly to evenly spray the concrete on the bottom plate position; at the same time, the sliding channel steel bar slowly moves along the track, so that the overall spraying trajectory is S-shaped and the spraying is even; the scraper moves slowly along the track with the sliding channel steel bar to scrape the sprayed concrete.
[0023] 3) The present invention improves the safety and stability of transportation by providing a transport stabilizing bracket.
[0024] 4) The present invention ensures the supporting strength of the model and saves the supporting trusses by adopting the side wall casting technology of the internal support formwork system; at the same time, the demolding steps are simple and convenient, and the demolding speed is fast, which further improves the casting quality and construction speed of the side wall.
[0025] 5) The suspended pouring device used in the present invention is internally provided with a spiral stirring rod, so that the material falling is more uniform and the concrete filling efficiency is higher. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a three-dimensional view of the front and side of the standardized anti-overflow pouring integrated formwork of the present invention;
[0027] Figure 2 This is a three-dimensional view of the rear side of the standardized anti-overflow pouring integrated formwork of the present invention;
[0028] Figure 3 This is a cross-sectional view of the standardized anti-overflow pouring integrated formwork trolley of the present invention;
[0029] Figure 4 It is a schematic diagram of the weight compaction truss system of the present invention;
[0030] Figure 5 Schematic diagram of the cover plate transport stabilizing bracket of the present invention;
[0031] Figure 6 This is a front view of the casting and leveling integrated movable truss bottom plate casting device of the present invention;
[0032] Figure 7 It is a top view of the casting and leveling integrated movable truss bottom plate casting device of the present invention;
[0033] Figure 8 It is a schematic diagram of the internal support formwork system of the present invention;
[0034] Fig. 9 It is a cross-sectional view of the hanging type casting device of the present invention;
[0035] In the figure: 1, Y-shaped hopper; 2, cavity body; 3, first pulley; 4, channel steel slide rail; 5, telescopic rod; 6, first pouring head; 7, fixed block; 8, battery; 9, first motor; 10, first steel diagonal support; 11, vibrating motor; 12, rectangular steel mold; 13, first clamp; 14, L-shaped steel mold; 15, irregular steel mold; 16, first scraper; 17, steel truss; 18, sliding channel steel bar; 19 , the second pulley; 20, the steel slider; 21, the second scraper; 22, the second pouring head; 23, the steel truss system; 24, the steel beam; 25, the heavy object; 26, the transport and stabilization bracket; 27, the segmented through-screw; 28, the node; 29, the second steel diagonal brace; 30, the second clamp; 31, the second motor; 32, the third pouring head; 33, the spiral stirring rod; 34, the barrel; 35, the lifting ear; 36, the lifting rope. DETAILED DESCRIPTION
[0036] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for ordinary persons in the art, without departing from the principle of the present invention, the present invention can also be modified in some ways, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
[0037] Embodiment 1
[0038] As an embodiment, a prefabricated assembled cover plate combined cover plate culvert construction device includes a standardized anti-overflow casting integrated formwork, a heavy object compaction truss system, a transport and stable support 26, a casting and leveling integrated mobile truss bottom plate casting device, an internal support formwork system and a hanging casting device.
[0039] like Figures 1 to 3 As shown, the standardized anti-overflow pouring integrated formwork is composed of a steel formwork and an anti-overflow pouring trolley; the steel formwork is composed of a plurality of L-shaped steel forms 14, a plurality of irregular steel forms 15, and a plurality of rectangular steel membranes 12; the three types of steel forms are sequentially spliced and fixed with bolts to form a steel formwork body; two L-shaped channel steels 4 are fixed with bolts at both ends of the upper part of the L-shaped steel formwork 14; a slide rail is arranged on the channel steel; the anti-overflow pouring trolley is mounted on the slide rail and can slide back and forth along the slide rail.
[0040] The anti-overflow pouring trolley is composed of a cavity steel body 2, a first pulley 3, a Y-shaped hopper 1, an equipment box, and a first scraper 16; the first pulley 3 is fixed to the lower end of the cavity steel body 2 and mounted on a channel steel slide rail 4; the Y-shaped hopper 1 is installed on the upper part of the cavity steel body 2; the equipment box is fixed to the front section of the cavity body 2, and is composed of a telescopic rod 5, a fixed block 7, a battery 8, a first motor 9, and a spiral stirring rod 33; the telescopic rod 5 is installed on the fixed block 7; the tip of the telescopic rod 5 is provided with a first clamp 13, which can be used during pouring The concrete is made uniform by telescopic displacement forward and backward; the fixed block 7 is provided with a transverse slideway, which can drive the telescopic rod 5 to move horizontally, further improving the uniformity of concrete pouring; the fixed block 7 is installed on the battery 8, and the battery 8 provides energy for the entire trolley device; the first motor 9 is installed under the battery 8 and connected to the spiral stirring rod 33, which drives the spiral stirring rod 33 to rotate and stir the falling concrete during operation to make it uniform; the first scraper 16 is installed at the rear end of the cavity body 2 to facilitate the scraping of concrete. After the L-shaped steel mold 14 is set up, the first steel diagonal braces 10 need to be installed on both sides to prevent the mold from falling off due to the expansion of the concrete during the pouring process. After the L-shaped steel mold 14 is set up, the vibrating motors 11 need to be installed on both sides to fully vibrate the concrete during the pouring process so that it can be evenly filled in the mold, thereby achieving the purpose of preventing overflow.
[0041] like Figure 4 As shown, the weight compaction truss system is supported on the cover plate which has been cast but not demolded, and is composed of a basic truss structure 23, a steel beam 24, and a weight 25; the steel beam 24 is spliced by channel steel; and the weight compaction ensures that the formwork does not expand during the curing period.
[0042] like Figure 5 As shown, the cover plate transport stabilizing bracket 26 is composed of a steel plate and a steel diagonal brace; the cover plate transportation method adopts stacking transportation; the transport stabilizing bracket cloth 26 is arranged on the lower cover plate to ensure that it is not crushed during transportation.
[0043] Embodiment 2
[0044] As another embodiment, this embodiment 2 proposes a more specific prefabricated assembled cover plate combined cover plate culvert construction device on the basis of embodiment 1.
[0045] like Figure 6 to Figure 7As shown, the casting and scraping integrated movable truss bottom plate casting device consists of a steel truss 17, a second pulley 19, a steel slider 20, a sliding channel steel bar 18, and a second scraper 21; the steel truss 17 is arranged in parallel on both sides of the bottom plate, and a slide rail is arranged on the upper end; second pulleys 19 are installed at the bottom of both ends of the sliding channel steel bar 18, embedded on the steel truss slide rail, and can move back and forth along the slide rail as a whole; a slide rail is added to the upper surface of the sliding channel steel bar 18; a second casting head 22 is provided on one side of the steel slider 20, and a pulley is provided at the bottom to be mounted on the sliding channel steel bar 18; the second scraper 21 is fixed to one side of the sliding channel steel bar 18, and scrapes the concrete when the sliding channel steel bar slides along the track.
[0046] like Figure 8 As shown, the inner support formwork system is composed of a side wall steel formwork, a segmented through-screw 27, and a second steel diagonal brace 29; after the side wall formwork is erected, the second steel diagonal brace 29 is installed on the inner side of the two side walls; then, the segmented through-screw 27 is used to penetrate the two side wall formworks and tension them inwards, thereby fixing the formwork inwards, thereby achieving the purpose of saving formwork and efficient construction. When removing the formwork after the side wall maintenance is completed, first disconnect the segmented through-screw node, then loosen the bolts on both sides of the side formwork, and pull out the through-screw for demoulding.
[0047] like Fig. 9 As shown, the hanging type pouring device is composed of a hanging rope 36, a second clamp 30, a lifting lug 35, a barrel body 34, a spiral stirring rod 33, and a second motor 31. During construction, the hanging type device is lifted by a crane pulling the hanging rope 36 through the lifting lug 35. The second clamp 30 is fixed to the side of the barrel body, and concrete is pumped in from below and pumped out from the third pouring head 32. The pumped concrete falls into the barrel, and the spiral stirring rod 33 is driven by the second motor 31 to stir the concrete, and the concrete is evenly spread in the mold from the cavity at the bottom of the barrel. The device is used to pour the side wall and the cast-in-place layer after the cover plate is hoisted.
[0048] It should be noted that the parts in this embodiment that are the same or similar to those in the first embodiment can be referenced to each other and will not be described in detail in this application.
[0049] Embodiment 3
[0050] As another embodiment, this embodiment 3 proposes, based on the embodiments 1 and 2, a construction method of a prefabricated assembled cover plate combined cover plate culvert using such a device, comprising the following steps:
[0051] S1. Use standardized anti-overflow casting integrated formwork to prefabricate π-shaped UHPC cover plates;
[0052] First, the standardized anti-overflow pouring integrated formwork is assembled. After the L-shaped steel formwork 14 is set up, the first steel diagonal brace 10 and the vibrating motor 11 are installed between the two sides of the L-shaped steel formwork 14 .
[0053] Cement is pumped in from the pouring pipe and sprayed out from the first pouring head 6; the telescopic rod 5 is moved forward and backward to make the concrete uniform; the horizontal slide provided on the fixed block 7 is used to drive the telescopic rod 5 to move horizontally to further improve the uniformity of concrete pouring; the battery 8 supplies energy to start the first motor 9, driving the spiral stirring rod 33 to rotate, stirring the falling concrete, so that it falls into the steel mold groove more evenly, and at the same time the trolley also moves back and forth repeatedly to ensure that the concrete falls into the steel mold groove evenly; the L-shaped steel plate 14 side wall vibrating motor 11 vibrates to make the concrete falling into the steel mold evenly filled, thereby achieving the purpose of overflow prevention; after the steel mold is filled, the overflow prevention pouring trolley moves forward and backward. The first scraper 16 is used to scrape the concrete flat.
[0054] S2. After pouring is completed, a heavy truss system is set up on the steel formwork for compaction and maintenance; the heavy compaction truss system is supported on the cover plate that has been poured but not yet demolded, and is composed of a basic truss structure 23, a steel beam 24, and a heavy object 25; the steel beam 24 is spliced by channel steel; heavy object compaction ensures that the formwork does not expand during maintenance.
[0055] After curing is completed, the mold is removed.
[0056] S2. The cover plates are transported in a stacked manner, and a transport stabilizing bracket 26 is arranged on the lower cover plate to ensure that the cover plate is not crushed during transportation.
[0057] Embodiment 4
[0058] As another embodiment, this fourth embodiment proposes, on the basis of the third embodiment, a more specific construction method of a prefabricated assembled cover plate combined cover plate culvert, further comprising bottom plate casting, side wall casting, hanging plate installation and cast-in-place layer casting:
[0059] S3. Use the pouring and leveling integrated mobile truss bottom plate pouring device to pour the bottom plate; concrete is pumped out from the pouring head, and the steel slider 20 moves left and right along the slide rail by holding the second pouring head 22; at the same time, the sliding channel steel bar 18 moves forward slowly along the top slide rail of the truss, and the concrete spreads in an S shape in the bottom plate pouring area, and then spreads evenly under the action of gravity; the scraper fixed on one side of the sliding channel steel bar 18 scrapes the concrete when the sliding channel steel bar 18 slides along the track. The integrated process greatly saves construction time and improves construction efficiency.
[0060] S4. After the bottom plate is poured, the side wall formwork of the internal support formwork system is erected; after the side wall formwork is erected, the second steel diagonal brace 29 is installed on the inner side of the two side walls; then, the segmented through-screws 27 are used to penetrate the two side wall formworks and tension them inwards, thereby fixing the formwork inwards, so as to achieve the purpose of saving formwork and efficient construction.
[0061] S5. Use a hanging casting device to cast the side wall; the lifting rope 36 passes through the lifting lug 35, and the device is lifted by a crane; the concrete is pumped out from the third casting head 32 and falls into the barrel body 34; the second motor 31 is started to drive the spiral stirring rod 33 to rotate, so that the falling concrete falls evenly into the side wall formwork groove; after the casting is completed, it is cured; when the side wall is removed after the curing is completed, the node 28 of the segmented through screw 27 is first disconnected, and then the bolts on both sides of the side form are loosened, and the segmented through screw 27 is pulled out for demolding.
[0062] S6. Lifting of cover plates. Before lifting, the UHPC cover plates are carefully inspected. During the lifting operation, professional rigging is used to ensure the balance and stability of the cover plates during the lifting process. At the same time, rubber pads and other materials are used to protect the contact points between the cover plates and the wire ropes to reduce the risk of damage. In terms of lifting command, experienced commanders are responsible for unified dispatch to ensure that all operators strictly follow the lifting plan and complete each step accurately.
[0063] S7, use the hanging pouring device to construct the cast-in-place layer; accurately measure and mark the position of the combined cover plate to ensure the accuracy of the pouring height; before pouring, thoroughly clean the surface of the cover plate to remove dust and debris to provide a good bonding interface; the lifting rope 36 passes through the lifting lug 35, and the device is lifted by a crane; the concrete is pumped out from the third pouring head 32 and falls into the barrel 34; the second motor 31 is started to drive the spiral stirring rod 33 to rotate so that the falling concrete falls evenly into the pouring area; during the pouring process, the layered pouring method is adopted, and the thickness of each layer is controlled within a reasonable range to ensure that the concrete is fully vibrated and dense; use a vibrator to carefully vibrate each layer of concrete to eliminate bubbles and prevent the occurrence of cavities and honeycombs; when the concrete is poured to a near height, be particularly careful to control the pouring speed and height to avoid overflow or unevenness. After pouring, the concrete surface is leveled; during the curing period, the temperature and humidity of the concrete are regularly checked and adjusted when necessary to ensure the quality of the concrete; finally, the back of the platform is backfilled, and the construction is completed.
[0064] It should be noted that the parts in this embodiment that are the same or similar to those in Embodiment 3 can be referenced to each other and will not be described in detail in this application.
[0065] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
Claims
1. A construction method for a prefabricated assembled cover plate combined cover plate culvert, characterized in that: The following steps are involved: S1, L-shaped steel mold, irregular steel mold and rectangular steel mold are spliced to form a standardized anti-overflow casting integrated template, and the anti-overflow casting trolley slides on the upper part of the L-shaped steel mold to cast the prefabricated assembled cover plate combined cover plate culvert; S2. Heavy object truss system compaction and curing: During the curing period, the steel formwork is compressed by compacting the truss system with heavy objects; S3, stacking the prefabricated assembled cover plates, and arranging a transport stabilizing bracket between the cover plates of two adjacent layers of prefabricated assembled cover plate combined cover plate culvert; Transport the cover to the designated installation location; S4, casting the truss bottom plate by using a casting and leveling integrated movable truss bottom plate casting device, and performing leveling at the same time; S5. Use the inner support formwork system to erect the side wall formwork, and then use the hanging casting device to cast the side wall; S6. After hoisting the prefabricated assembled cover plate combined cover plate culvert, use the hanging casting device to carry out the cast-in-place layer construction.
2. The construction method of a prefabricated assembled cover plate combined cover plate culvert according to claim 1 is characterized in that: The standardized anti-overflow pouring integrated formwork includes a steel mold and an anti-overflow pouring trolley; the steel mold includes an L-shaped steel mold, an irregular steel mold and a rectangular steel mold; the L-shaped steel mold, the irregular steel mold and the rectangular steel mold are fixed and spliced by bolts to form a steel mold body; two channel steel slide rails are fixed at both ends of the upper part of the L-shaped steel mold by bolts; the anti-overflow pouring trolley is mounted on the channel steel slide rails, and the anti-overflow pouring trolley slides back and forth along the channel steel slide rails.
3. The construction method of the prefabricated assembled cover plate combined cover plate culvert according to claim 2 is characterized in that: The anti-overflow pouring trolley includes a cavity steel body, a first pulley, a Y-shaped hopper, an equipment box and a first scraper; the first pulley is fixed to the lower end of the cavity steel body, and the first pulley is mounted on the channel steel slide rail; the Y-shaped hopper is installed on the upper part of the cavity steel body; the equipment box is fixed to the front end of the cavity body, and the equipment box includes a telescopic rod, a fixed block, a battery, a first motor and a spiral stirring rod; the telescopic rod is installed on the fixed block; the tip of the telescopic rod is provided with a first clamping device, and the first clamping device is telescopically displaced forward and backward through the telescopic rod during pouring; a transverse slide is provided on the fixed block, and the telescopic rod is transversely displaced in the transverse slide; the fixed block is installed on the battery, and the battery supplies energy for the entire anti-overflow pouring trolley device; the first motor is installed under the battery, and the first motor is connected to the spiral stirring rod, and the spiral stirring rod rotates in the cavity steel body. When working, the first motor drives the spiral stirring rod to rotate and stir the falling concrete to make it uniform; the first scraper is installed at the rear end of the cavity body to facilitate the concrete scraping at the top of the steel formwork.
4. The construction method of the prefabricated assembled cover plate combined cover plate culvert according to claim 1 is characterized in that: After the L-shaped steel formwork is set up, a first steel diagonal brace and a vibrating motor are installed between two sides of the L-shaped steel formwork.
5. The construction method of the prefabricated assembled cover plate combined cover plate culvert according to claim 1 is characterized in that: The heavy object compaction truss system is supported on the cover plate which has been cast but not yet demolded. The heavy object compaction truss system includes a basic truss structure, a steel beam and a heavy object. The bottom end of the basic truss structure is supported above the bottom edge of the L-shaped steel formwork. The steel beam is spliced by channel steel and supported on the top of the basic truss structure. By pressing the heavy object on the steel beam, it is ensured that the steel formwork does not expand during the maintenance period.
6. The construction method of the prefabricated assembled cover plate combined cover plate culvert according to claim 1 is characterized in that: The cover plate transportation stabilizing bracket includes a steel plate and a steel diagonal brace; the prefabricated assembled cover plate transportation method adopts stacking transportation; the transportation stabilizing bracket is arranged between the cover plates of two adjacent layers of prefabricated assembled cover plate combined cover plate culvert.
7. The construction method of the prefabricated assembled cover plate combined cover plate culvert according to claim 1 is characterized in that: The casting and scraping integrated movable truss bottom plate casting device comprises a steel truss, a second pulley, a steel slider, a sliding channel steel bar and a second scraper; the steel trusses are arranged in parallel on both sides of the bottom plate, and a longitudinal slide rail is arranged on the upper end of the steel truss; second pulleys are installed at the bottom of both ends of the sliding channel steel bar, and the second pulleys are embedded in the longitudinal slide rail of the steel truss, and the sliding channel steel bar moves back and forth along the longitudinal slide rail as a whole; a transverse slide rail is added to the upper surface of the sliding channel steel bar; a second casting head is provided on one side of the steel slider, and the bottom of the steel slider is mounted on the sliding channel steel bar through wheels; the second scraper is fixed on one side of the sliding channel steel bar, and scrapes the concrete when the sliding channel steel bar slides along the longitudinal track.
8. The construction method of the prefabricated assembled cover plate combined cover plate culvert according to claim 1 is characterized in that: The internal support formwork system includes a side wall steel formwork, a segmented through-screw rod and a second steel diagonal brace. After the side wall steel formwork is erected, the second steel diagonal brace is installed on the inner side of the side wall steel formworks on both sides. Subsequently, the segmented through-screw rod is used to penetrate the side wall steel formworks on both sides and tension them inwards, thereby fixing the internal support formwork system.
9. The construction method of the prefabricated assembled cover plate combined cover plate culvert according to claim 1 is characterized in that: The hanging casting device comprises a hanging rope, a third casting head, a second clamp, a lifting ear, a barrel, a spiral stirring rod and a second motor; during construction, the hanging device is lifted by a crane pulling the hanging rope through the lifting ear; a hole is provided at the bottom of the barrel, the second clamp is fixed to the side of the barrel, and concrete is pumped out from the third casting head; the pumped concrete falls into the barrel, and a spiral stirring rod is provided in the barrel to stir the concrete, which is evenly spread in the side wall steel mold from the hole at the bottom of the barrel.
10. The construction method of the prefabricated assembled cover plate combined cover plate culvert according to claim 8, characterized in that: When removing the formwork after the side wall maintenance is completed, first disconnect the nodes of the segmental through screws, then loosen the bolts on both sides of the side formwork, and pull out the through screws to demold.