Self-drilling anchor rod structure, new energy photovoltaic support and construction method of new energy photovoltaic support

Through self-drilling anchor structure and new energy photovoltaic support construction methods, the complex, slow and high cost of photovoltaic support foundation construction is solved, and a more stable, fast and economical photovoltaic support infrastructure is achieved, suitable for complex terrain sites. .

CN118932997APending Publication Date: 2024-11-12中能建数字科技集团有限公司 +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411145893.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The construction process of existing photovoltaic support pile foundations is complex, slow, and cost-effective, and has low applicability in complex terrain sites. Conventional pile foundations require additional procedures to be installed with anchor bolts and photovoltaic support bases.

Method used

Adopt self-drilling anchor structure and new energy photovoltaic bracket construction method, drilling and grouting are used to improve stability by using hollow anchor rods and steel pipe pile diameter protective sleeves, and simplify it through flange and fasteners. Connect to realize a lightweight, modular and prefabricated photovoltaic bracket infrastructure.

Benefits of technology

It improves the stability and construction speed of photovoltaic support foundations, reduces costs, enhances the construction flexibility and applicability in complex terrain, and reduces the workload and labor consumption of on-site steel bar binding.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932997A_ABST
    Figure CN118932997A_ABST
Patent Text Reader

Abstract

The invention discloses a self-drilling type anchor rod structure, a new energy photovoltaic support and a construction method of the new energy photovoltaic support, according to the anchor rod structure, through cooperation of a drilling machine, one of drilling, grouting or dry operation hole forming is carried out at the same time, after drilling is completed, pile body pouring is carried out through concentrated cement paste, and the anchor rod structure serves as pile body reinforcing bars; the anchor rod comprises a hollow anchor rod body, a drill bit, a centering device and a steel pipe pile diameter protection sleeve. The support is provided with the self-drilling type anchor rod structure and further comprises a foundation platform, a photovoltaic support middle column and a flange plate installed on the photovoltaic support middle column. The method is applied to the new energy photovoltaic support. According to the self-drilling anchor rod structure, the photovoltaic support foundation structure form is more systematic and stable, rapid in construction and better in technical economy, and light weight, modularization and prefabrication in the photovoltaic support foundation construction process are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of new energy technology, and in particular to a self-drilling anchor rod structure, a new energy photovoltaic bracket and a construction method thereof. Background Art

[0002] Photovoltaic brackets are an important part of solar power generation systems, supporting and fixing each photovoltaic module. In order to ensure the safety and stability of the photovoltaic system, it is very important to choose the right foundation.

[0003] Common forms of photovoltaic support pile foundations include: concrete cast-in-place pile foundation, microporous cast-in-place pile foundation, prefabricated pile foundation, etc. However, cast-in-place concrete generally has problems such as complex construction procedures and slow construction speed, requiring more human resources and high construction costs; although prefabricated piles reduce the difficulty of on-site construction to a certain extent, they require more large-scale machinery to enter the site, are less flexible, and are not very suitable for sites with more complex terrain. In addition, after the foundation is poured, conventional pile foundations need to be separately set up with anchor bolts to connect to the base of the photovoltaic support, adding additional procedures. Summary of the invention

[0004] The main purpose of the present invention is to provide a self-drilling anchor structure, a new energy photovoltaic bracket and a construction method thereof, a photovoltaic bracket foundation structure form with more systematic stability, quick construction, and better technical and economic performance, and to realize the lightweight, modularization and prefabrication of the photovoltaic bracket foundation construction process.

[0005] To achieve the above object, one of the technical solutions adopted by the present invention is: a self-drilling anchor rod structure, which is drilled, grouted or dry-drilled by a drilling rig, and after the drilling is completed, the pile body is grouted with concentrated cement slurry. The anchor rod structure is used as a pile body reinforcement, and the anchor rod comprises:

[0006] Hollow anchor 1;

[0007] A drill bit 2, used for drilling, which is located at one end of the hollow anchor rod 1;

[0008] A centering device 3, used for keeping the hollow anchor rod 1 centered when the drill bit 2 is drilling, and installed on the hollow anchor rod 1;

[0009] The steel pipe pile diameter protection sleeve 4 is used to improve the stability of the hollow anchor rod 1 after pouring, and is installed on the hollow anchor rod 1.

[0010] Furthermore, the anchor structure also includes:

[0011] The connecting sleeve 5 is used for connecting two or more hollow anchor rods 1 and is installed at the connection between every two hollow anchor rods 1 .

[0012] Furthermore, the anchor rod structure also includes: a fastener 6. When the anchor rod structure is drilled, the fastener 6 is used to fix the anchor rod structure on a preset foundation platform.

[0013] Another technical solution adopted by the present invention is: a new energy photovoltaic bracket, the bracket has at least one self-drilling anchor structure as described above, and the bracket also includes: a foundation base 7, a photovoltaic bracket center column 8 and a flange 9 installed on the photovoltaic bracket center column 8;

[0014] After the drilling of the self-drilling anchor structure is completed, the pile body is poured with thick cement slurry. The anchor structure serves as the reinforcement of the pile body, and the center column 8 of the photovoltaic bracket is installed on the foundation pedestal 7 through the cooperation of the flange 9 and the fastener 6 on the center column 8 of the photovoltaic bracket.

[0015] Furthermore, the connection between the flange 9 and the fastener 6 is provided with either an exposed anchor head protection cover 10 or a concrete sealing structure.

[0016] Another technical solution adopted by the present invention is: a new energy photovoltaic bracket construction method, which is applied to the above-mentioned new energy photovoltaic bracket, and the method comprises:

[0017] S1. Before construction, the work site should be cleared and loose soil removed before self-drilling micro-piles are constructed;

[0018] S2. During the construction process, the assembled self-drilling anchor structure is used for grouting while drilling. First, 1:1 thin cement slurry is used for grouting, and the wall protection effect of cement slurry is used to prevent hole collapse;

[0019] S3. After the drilling reaches the pile end position at the designed elevation, use concentrated cement slurry with a water-cement ratio of 0.5:1 to grout the pile;

[0020] S4, before the cement slurry is initially set, the steel pipe pile diameter protection sleeve 4 is installed at a position where the hollow anchor rod 1 enters the stable bedrock by no less than 30 cm, the steel pipe pile diameter protection sleeve 4 is passed through the hollow anchor rod 1 and pressed into the unsolidified cement slurry, and the length of the steel pipe pile diameter protection sleeve 4 that can be extended into the cap is controlled to be no less than 10-15 cm, and a prefabricated mold is used to fix the pile top position, and secondary grouting is performed at the hole mouth;

[0021] S5. After the pile top reaches a certain strength and passes the test, cast the foundation cap 7 in situ or install the prefabricated foundation cap 7 in the factory. The prefabricated foundation cap 7 needs to reserve holes corresponding to the holes of the hollow anchor rod 1.

[0022] S6. Then install the factory-prefabricated flange 9, and pass the hollow anchor rod 1 through the corresponding hole reserved on the flange 9;

[0023] S7, after the hollow anchor rod 1 is inserted into the hole, the hollow anchor rod 1 is locked on the flange 9 using the fastener 6;

[0024] S8. Install the exposed anchor head protection cover 10 at the position where the anchor head and the fastener 6 are exposed on the flange 9, and perform grouting to seal it.

[0025] Compared with the prior art, the present invention has the following beneficial effects:

[0026] (1) The self-drilling hollow anchor rod is both a drill rod and a pile reinforcement, which reduces the workload of on-site steel bar binding. At the same time, it is more convenient and reliable to connect with the upper foundation, greatly improving the stability and integrity of the photovoltaic support foundation, and effectively avoiding the slippage and lifting of the support foundation;

[0027] (2) Through auxiliary structural measures such as pile diameter protection sleeves, a tension-compression composite micropile is formed, which improves the micropile's ability to resist compression, horizontal shear force, and pull-out;

[0028] (3) Components such as the pedestal and flange can be prefabricated in the factory in advance, without the need to pour concrete on site, which is conducive to promoting the development of prefabrication and assembly of foundation engineering. The connection process between the flange and the photovoltaic bracket base is simple, which can speed up the on-site construction progress;

[0029] (4) Compared with conventional photovoltaic support micropiles, self-drilling micropiles have a fast hole-making speed, integrating drilling, hole-making, grouting, pile-making and anchoring, realizing integrated pile-making, fast construction speed, and reducing labor consumption, which can reduce overall costs;

[0030] (5) The equipment required for the construction of self-drilling micropiles is small, the machinery is relatively flexible, the construction angle can range from 0 to 90 degrees, the construction is convenient, and it can be constructed in places where large machinery and equipment cannot enter (such as hillsides, etc.). BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a structural schematic diagram of the self-drilling anchor structure of the present invention;

[0032] Figure 2 It is a cross-sectional view of the new energy photovoltaic support of the present invention;

[0033] Figure 3 This is a cross-sectional view of a new energy photovoltaic support installed on a steep slope according to the present invention;

[0034] Figure 4 is a cross-sectional view of the self-drilling anchor structure of the present invention;

[0035] Figure 5 It is a front view of a single anchor rod supported round tube steel column foot-flange connection node of the present invention;

[0036] Figure 6It is a top view of a single anchor rod supported round tube steel column foot-flange connection node of the present invention;

[0037] Figure 7 It is a front view of a single anchor rod supported I-beam column foot-flange connection node of the present invention;

[0038] Figure 8 It is a top view of a single anchor rod supported I-beam column foot-flange connection node of the present invention.

[0039] In the figure: 1. Hollow anchor rod; 2. Drill bit; 3. Centerer; 4. Steel pipe pile diameter protection sleeve; 5. Connecting sleeve; 6. Fastener; 7. Foundation pedestal; 8. Photovoltaic bracket center column; 9. Flange; 10. Exposed anchor head protection cover. DETAILED DESCRIPTION

[0040] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings.

[0041] Example 1

[0042] like Figure 1 As shown, a self-drilling anchor structure is provided. The anchor structure is formed by drilling, grouting or dry operation with the cooperation of a drilling rig. After the drilling is completed, the pile body is grouted with concentrated cement slurry. The anchor structure is used as a pile body reinforcement. The anchor includes:

[0043] Hollow anchor 1;

[0044] A drill bit 2, used for drilling, which is located at one end of the hollow anchor rod 1;

[0045] A centering device 3, used for keeping the hollow anchor rod 1 centered when the drill bit 2 is drilling, and installed on the hollow anchor rod 1;

[0046] The steel pipe pile diameter protection sleeve 4 is used to improve the stability of the hollow anchor rod 1 after pouring, and is installed on the hollow anchor rod 1.

[0047] Furthermore, the anchor structure also includes:

[0048] The connecting sleeve 5 is used for connecting two or more hollow anchor rods 1 and is installed at the connection between every two hollow anchor rods 1 .

[0049] Furthermore, the anchor rod structure also includes: a fastener 6. When the anchor rod structure is drilled, the fastener 6 is used to fix the anchor rod structure on a preset foundation platform.

[0050] Specifically, the fastener 6 includes but is not limited to fasteners such as nuts in the prior art.

[0051] Example 2

[0052] like Figure 2 and 4 As shown, a new energy photovoltaic bracket has at least one self-drilling anchor rod structure described in Example 1, and the bracket also includes: a foundation base 7, a photovoltaic bracket center column 8, and a flange 9 installed on the photovoltaic bracket center column 8;

[0053] After the drilling of the self-drilling anchor structure is completed, the pile body is poured with thick cement slurry. The anchor structure serves as the reinforcement of the pile body, and the center column 8 of the photovoltaic bracket is installed on the foundation pedestal 7 through the cooperation of the flange 9 and the fastener 6 on the center column 8 of the photovoltaic bracket.

[0054] Furthermore, the connection between the flange 9 and the fastener 6 is provided with either an exposed anchor head protection cover 10 or a concrete sealing structure.

[0055] Example 3

[0056] A new energy photovoltaic support construction method, which is applied to the new energy photovoltaic support described in Example 2, and comprises:

[0057] S1. Before construction, the work site should be cleared and loose soil removed before self-drilling micro-piles are constructed;

[0058] S2. During the construction process, the assembled self-drilling anchor structure is used for grouting while drilling. First, a 1:1 thin cement slurry is used for grouting, and the wall protection effect of the cement slurry is used to prevent the hole from collapsing.

[0059] S3. After the drilling reaches the pile end position at the designed elevation, use concentrated cement slurry with a water-cement ratio of 0.5:1 to grout the pile;

[0060] S4, before the cement slurry is initially set, the steel pipe pile diameter protection sleeve 4 is installed at a position where the hollow anchor rod 1 enters the stable bedrock by no less than 30 cm, the steel pipe pile diameter protection sleeve 4 is passed through the hollow anchor rod 1 and pressed into the unsolidified cement slurry, and the length of the steel pipe pile diameter protection sleeve 4 that can be extended into the cap is controlled to be no less than 10-15 cm, and a prefabricated mold is used to fix the pile top position, and secondary grouting is performed at the hole mouth;

[0061] S5. After the pile top reaches a certain strength and passes the test, cast the foundation cap 7 in situ or install the prefabricated foundation cap 7 in the factory. The prefabricated foundation cap 7 needs to reserve holes corresponding to the holes of the hollow anchor rod 1.

[0062] S6. Then install the factory-prefabricated flange 9, and pass the hollow anchor rod 1 through the corresponding hole reserved on the flange 9;

[0063] S7, after the hollow anchor rod 1 is inserted into the hole, the hollow anchor rod 1 is locked on the flange 9 using the fastener 6;

[0064] S8. Install the exposed anchor head protection cover 10 at the position where the anchor head and the fastener 6 are exposed on the flange 9, and perform grouting to seal it.

[0065] Specifically, according to different bearing capacity requirements, different numbers of self-drilling anchor rods can be used to form piles, such as a single anchor rod, two anchor rods or four anchor rods. The assembly method is the same as the construction plan. Several anchor rods are connected by flanges, and the flanges are connected to the upper photovoltaic support column foot by welding. Special attention should be paid to the fact that when a single anchor rod is used to form a pile, the cross-sectional centroid of the anchor rod below the flange coincides with the cross-sectional centroid of the upper support column foot. Figure 5-6 As shown in the figure, if the column foot of the photovoltaic bracket is a round tube steel, the round tube steel column foot covers the anchor head extending out of the flange, and is welded to the flange, and poured with concrete to seal it; Figure 7-8 As shown, if the column foot of the photovoltaic support is an I-beam, a hole is opened at the bottom of the I-beam web. The size of the hole allows the exposed anchor head to pass through to avoid conflict with the exposed anchor head, and the hole is poured with concrete to seal it.

[0066] If there is a soil slope above (behind) the photovoltaic support installation area, it is recommended to clear the surface to make the slope less than 1:1. The slope of the photovoltaic support installation area should not be greater than 1:1. Figure 3 As shown in the figure, for sites with large slopes, two vertical self-drilling micropiles and two inclined self-drilling micropiles at an angle of 15°-45° to the vertical are used under the foot of a single column to form a tensile and compressive structural system.

[0067] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the present invention and are not intended to limit the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. Self-drilling anchor structure, characterized in that: The anchor rod structure is formed by drilling, grouting or dry operation through the cooperation of the drilling rig. After the drilling is completed, the pile body is grouted with concentrated cement slurry. The anchor rod structure is used as the reinforcement of the pile body. The anchor rod includes: Hollow anchor (1); A drill bit (2) for drilling, which is located at one end of the hollow anchor rod (1); A centering device (3), used for keeping the hollow anchor rod (1) centered when the drill bit (2) is drilling, and installed on the hollow anchor rod (1); The steel pipe pile diameter protection sleeve (4) is used to improve the stability of the hollow anchor rod (1) after pouring, and is installed on the hollow anchor rod (1).

2. The self-drilling anchor structure according to claim 1, characterized in that: The anchor structure also includes: A connecting sleeve (5) is used for connecting two or more hollow anchor rods (1) and is installed at the connection between every two hollow anchor rods (1).

3. The self-drilling anchor structure according to claim 1, characterized in that: The anchor rod structure also includes a fastener (6). When the anchor rod structure is drilled, the fastener (6) is used to fix the anchor rod structure on a preset foundation platform.

4. New energy photovoltaic bracket, characterized by: The support has at least one self-drilling anchor structure according to any one of claims 1 to 3, and the support further comprises: a foundation support (7), a photovoltaic support center column (8), and a flange (9) installed on the photovoltaic support center column (8); After the drilling of the self-drilling anchor rod structure is completed, the pile body is poured with thick cement slurry. The anchor rod structure is used as the reinforcement of the pile body, and the center column (8) of the photovoltaic support is installed on the foundation pedestal (7) through the cooperation of the flange (9) and the fastener (6) on the center column (8) of the photovoltaic support.

5. The new energy photovoltaic bracket according to claim 4, characterized in that: The connection between the flange (9) and the fastener (6) is provided with either an exposed anchor head protection cover (10) or a concrete sealing structure.

6. A new energy photovoltaic support construction method, characterized in that: The method is applied to the new energy photovoltaic bracket according to claim 5, and the method comprises: S1. Before construction, the work site should be cleared and loose soil removed before self-drilling micro-piles are constructed; S2. During the construction process, the assembled self-drilling anchor structure is used for grouting while drilling. First, a 1:1 thin cement slurry is used for grouting, and the wall protection effect of the cement slurry is used to prevent the hole from collapsing. S3. After the drilling reaches the pile end position at the designed elevation, use concentrated cement slurry with a water-cement ratio of 0.5:1 to grout the pile; S4. Before the cement slurry is initially set, the steel pipe pile diameter protection sleeve (4) is installed at a position where the hollow anchor rod (1) enters the stable bedrock by no less than 30 cm. The steel pipe pile diameter protection sleeve (4) is passed through the hollow anchor rod (1) and pressed into the unsolidified cement slurry. The length of the steel pipe pile diameter protection sleeve (4) that can be extended into the cap is controlled to be no less than 10-15 cm. At the same time, a prefabricated mold is used to fix the pile top position, and secondary grouting is performed at the hole mouth; S5. After the pile top reaches a certain strength and passes the test, cast-in-place foundation cap (7) or install factory-prefabricated foundation cap (7). The prefabricated foundation cap (7) needs to reserve holes corresponding to the holes for the hollow anchor rods (1); S6. Then install the factory-prefabricated flange (9), and pass the hollow anchor rod (1) through the corresponding hole reserved on the flange (9); S7, after the hollow anchor rod (1) is inserted into the hole, the hollow anchor rod (1) is locked on the flange (9) using the fastener (6); S8. Install an exposed anchor head protection cover (10) at the position where the anchor head and the fastener (6) are exposed on the flange (9), and perform grouting to seal it.