Modular partition wall assembly type construction method and connecting device

By using modular construction methods and connection devices, the problems of construction quality and schedule caused by on-site cutting of traditional light steel keel have been solved, achieving efficient and uniform keel installation and material saving.

CN118933233APending Publication Date: 2024-11-12BEIJING HONG KONG YUAN CONSTR DECORATION ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411271872.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-11
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In traditional light steel keel construction, inconsistent dimensions are caused by manual on-site cutting, which affects construction quality and schedule.

Method used

A modular construction method is adopted, which involves pre-setting and variable keel shapes and using dovetail screws for fixing and connecting them, combined with a connecting device, to achieve rapid assembly and fixation of the keel.

Benefits of technology

Reduce on-site secondary processing, reduce material waste, improve installation efficiency, ensure process consistency, and improve installation quality and construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933233A_ABST
    Figure CN118933233A_ABST
Patent Text Reader

Abstract

The modular partition wall assembly type construction method comprises the steps that quantitative keels are determined according to a construction drawing, and the quantitative keels are profiles with the same structural size; the quantitative keels are prefabricated according to a construction drawing, quantitative forming keels are obtained, and each quantitative forming keel is quantitatively marked; the quantitatively-formed keels are spliced on a construction site, the size of the variable keels is determined after splicing is completed, and the variable keels are profiles with variable structural sizes; variable forming keels are manufactured according to the variable keel size, and variable labeling is conducted on each variable forming keel; and the variable-cost sectional materials are spliced, overall manufacturing and installation of the keel partition wall are completed, material losses can be reduced, and the installation efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building construction technology, and in particular to a modular partition wall assembly construction method and a connection device. Background Art

[0002] Lightweight partition walls have the advantages of light weight, good sound insulation, and easy installation. At present, lightweight partition walls have been widely used in construction projects. The main types of lightweight partition walls are frame partition walls and plate partition walls. Frame partition walls are mostly light steel keel frames plus decorative panels. The decorative panels include gypsum boards, Et boards, plywood, PC boards, etc.; plate partition walls mainly include ALC lightweight partition boards, GRC lightweight partition boards, cement ceramsite boards, gypsum hollow boards, etc. Light steel keel gypsum board partition walls are more widely used in practice.

[0003] Traditional light steel keels are generally cut and assembled on site one by one, which is inefficient. In addition, since all cutting is done manually, the cutting sizes are uneven, which seriously affects the construction quality and slows down the construction period. Summary of the invention

[0004] The embodiments of the present specification provide a modular partition wall assembly construction method and a connection device, which are used to solve the problem in the prior art that all the cutting is done manually on site, the cutting sizes are uneven, and the construction quality is seriously affected and the construction period is slowed down.

[0005] The technical solutions provided by the embodiments of this specification are: In a first aspect, an embodiment of the present application provides a modular partition wall assembly construction method, comprising: Determine the quantitative keel according to the construction drawings, and the quantitative keel refers to the profiles with the same structural dimensions; Prefabricate the quantitative keels according to the construction drawings to obtain quantitative formed keels, and quantitatively mark each quantitative formed keel; Assembling the quantitatively formed keels at the construction site, and determining the size of the variable keels after the assembly is completed. The variable keels refer to profiles with variable structural dimensions; Produce variable formed keels according to the variable keel sizes, and label each variable formed keel with variables; Assemble the variable cost profiles to complete the overall production and installation of the keel partition wall.

[0006] Furthermore, the quantitatively formed keels are assembled according to the corresponding quantitative markings.

[0007] Furthermore, the quantitatively formed keels are assembled according to the corresponding variable annotations.

[0008] Furthermore, the keels are connected and fixed by dovetail screws.

[0009] Furthermore, the through keel and the vertical keel are fixedly connected by dovetail screws.

[0010] Furthermore, pipeline ports are reserved when the keel is prefabricated.

[0011] Furthermore, the vertical pipeline is completed when the keel is assembled, and the horizontal section of the pipeline is constructed after the keel is installed and fixed.

[0012] Furthermore, after the keel partition wall is assembled, rock wool filling and covering panels are carried out.

[0013] Furthermore, the rock wool and panels are customized according to the size of the keel partition wall.

[0014] In a second aspect, an embodiment of the present application provides a connection device for a modular partition wall assembly construction method, comprising a vertical keel and a horizontal keel of a hollow structure, wherein a mounting groove is provided on one side of the vertical keel, and an insertion port is provided on the top of the mounting groove, and the insertion port is communicated with the mounting groove; A through hole is provided on the transverse keel; the transverse keel is connected to the vertical keel by bolts; the bolt includes a head and a screw rod, the head can enter the vertical keel through an insertion port, the screw rod can move into the installation groove, the diameter of the head is larger than the width of the installation groove, and the screw rod is provided with a matching nut.

[0015] At least one of the above technical solutions adopted in the embodiments of the present application can achieve the following beneficial effects: Reduce secondary processing on site, reduce material loss, and improve installation efficiency. Centralized batch production reduces the frequent movement of personnel and tools, improves installation efficiency, and unified production ensures process consistency and improves installation quality. Pre-installation of electromechanical points, vertical pipelines can be pre-produced together with the keel in a centralized processing plant, and after the partition wall is fixed and installed, the horizontal pipeline is connected to the reserved port, reducing damage to the keel partition wall and inaccurate positioning during electromechanical installation.

[0016] Through the connecting device, the keel can be quickly connected, which greatly improves the construction efficiency. At the same time, it can increase the fault tolerance during installation and further reduce material waste. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings: Figure 1 A schematic diagram of the method flow provided in the embodiments of this specification.

[0018] Figure 2 Schematic diagram of quantitative keel and variable keel provided in the embodiments of this specification.

[0019] Figure 3 This is a schematic diagram of the quantitative keel assembly structure provided in the embodiments of this specification.

[0020] Figure 4 This is a schematic diagram of the assembled structure provided in the embodiment of this specification.

[0021] Figure 5 This is a schematic diagram of the structure of the connection device provided in the embodiment of this specification. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the present application clearer, the technical solution of the present application will be clearly and completely described below in combination with the specific embodiments of the present application and the corresponding drawings. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present application.

[0023] The technical solutions provided by various embodiments of the present application are described in detail below in conjunction with the accompanying drawings.

[0024] This specification provides a modular partition wall assembly construction method. Figure 1 As shown, including: S1. Determine the quantitative keel according to the construction drawings, wherein the quantitative keel refers to the profile with the same structural dimensions; In a possible implementation, the quantitative keel includes but is not limited to the keel of the vertical partition wall surface, see Figure 2 shown.

[0025] S2, prefabricate the quantitative keels according to the construction drawings to obtain quantitative formed keels, and quantitatively mark each quantitative formed keel; In one possible implementation, Figure 3 As shown, the first horizontal quantitative mark in the first row is 1-1, and the next row is 1-2, and so on; the vertical keels matching 1-1 are marked 1-1a, 1-1b, 1-1c, and so on, for the convenience of later installation. Later installation assembles the quantitative formed keels according to the corresponding quantitative marks. For another example, if the on-site structure elevation is 4.1 meters, a 4.1-meter vertical keel can be customized, and the length of the top and bottom keels can be customized according to the divided quantitative lengths.

[0026] S3, assembling the quantitatively formed keels at the construction site, and determining the size of the variable keels after the assembly is completed, wherein the variable keel refers to a profile with a variable structural size; In a possible implementation, when installing a quantitatively formed keel, if the material manufacturer is close to the construction site, the keel frame can be processed and assembled in the factory. If the material manufacturer is far away from the construction site, the customized keel will be transported to the construction site. Figure 1 Shown include but are not limited to corners and door openings.

[0027] S4, making variable formed keels according to the variable keel sizes, and marking variables for each variable formed keel; In a possible implementation, the quantitatively formed keels are assembled according to the corresponding variable markings. It should be noted that the same door opening size is processed uniformly, and the door opening reinforcement is required. One type is the vertical keel double keel embraced, which can be assembled together, and the other type is reinforced with square steel, which needs to be assembled on site.

[0028] S5. Assemble the variable cost profiles to complete the overall production and installation of the keel partition wall.

[0029] For detailed processing, the connection between the keels is fixed with dovetail screws, and the through keels must be reliably connected to the vertical keels to the edges.

[0030] Further explanation, pipeline installation. The side partition walls can be accurately positioned, switches and sockets are positioned, and the vertical pipelines from the partition walls to the top or to the ground are completed when assembling the keel. After the partition walls are installed and fixed on site, the horizontal sections of the pipelines are connected. Rock wool filling and cover panels. Rock wool is filled and covered according to conventional processes. Rock wool can be customized to specifications such as keel spacing. For example, if the vertical keel spacing on site is 400*1000mm, the rock wool can be customized to 450*1000mm. Figure 4 shown.

[0031] This specification provides a connection device for modular partition wall assembly construction method. Figure 5 As shown, it includes a vertical keel 1 and a horizontal keel 3 of a hollow structure. A mounting groove 11 is opened on one side of the vertical keel 1, and an insertion port 12 is arranged on the top of the mounting groove. The insertion port 12 is connected to the mounting groove 11; the mounting groove is vertically arranged.

[0032] A through hole 31 is opened on the transverse keel 3; the transverse keel 3 is connected to the vertical keel 1 through a bolt 2; the bolt 2 includes a head 21 and a screw rod 22, the head 21 can enter the vertical keel through an insertion port, the screw rod can be moved into the installation groove, the head diameter is larger than the installation groove width, and a matching nut 4 is provided on the screw rod.

[0033] When in use, insert the bolt head into the vertical keel from the insertion port, move the screw along the installation slot, adjust the position of the bolt when installing the horizontal keel and the vertical keel, pass the screw through the through hole, and then tighten it with the nut. The keel can be quickly connected, greatly improving construction efficiency, while also increasing the tolerance rate during installation and further reducing material waste.

[0034] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0035] The above is only an embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included in the scope of the claims of the present application.

Claims

1. A modular partition wall assembly construction method, characterized in that: include: Determine the quantitative keel according to the construction drawings, and the quantitative keel refers to the profiles with the same structural dimensions; Prefabricate the quantitative keels according to the construction drawings to obtain quantitative formed keels, and quantitatively mark each quantitative formed keel; Assembling the quantitatively formed keels at the construction site, and determining the size of the variable keels after the assembly is completed. The variable keels refer to profiles with variable structural dimensions; Produce variable formed keels according to the variable keel sizes, and label each variable formed keel with variables; Assemble the variable cost profiles to complete the overall production and installation of the keel partition wall.

2. A modular partition wall assembly construction method according to claim 1, characterized in that: Assemble the quantitatively formed keels according to the corresponding quantitative markings.

3. A modular partition wall assembly construction method according to claim 1, characterized in that: Assemble the quantitatively formed keels according to the corresponding variable markings.

4. A modular partition wall assembly construction method according to claim 1, characterized in that: The connection between the keels is fixed with dovetail screws.

5. A modular partition wall assembly construction method according to claim 4, characterized in that: The through keel and the vertical keel are fixedly connected by dovetail screws.

6. A modular partition wall assembly construction method according to claim 1, characterized in that: Pipeline ports are reserved when the keel is prefabricated.

7. A modular partition wall assembly construction method according to claim 1, characterized in that: The vertical pipeline is completed when the keel is assembled, and the horizontal section of the pipeline is constructed after the keel is installed and fixed.

8. A modular partition wall assembly construction method according to claim 1, characterized in that: After the keel partition wall is assembled, rock wool filling and panel covering are carried out. The rock wool and panel are customized according to the size of the keel partition wall.

9. A connection device for modular partition wall assembly construction method, comprising vertical keels and horizontal keels of hollow structure, characterized in that: A mounting groove is provided on one side of the vertical keel, and an insertion port is provided on the top of the mounting groove, and the insertion port is communicated with the mounting groove; A through hole is provided on the transverse keel; the transverse keel is connected to the vertical keel by bolts; the bolt includes a head and a screw rod, the head can enter the vertical keel through an insertion port, the screw rod can move into the installation groove, the diameter of the head is larger than the width of the installation groove, and the screw rod is provided with a matching nut.