Novel protection system for ultra-small clear distance parallel shield tunnel construction
By using MJS isolation piles, double slurry reinforcement and synchronous top support equipment in ultra-small clear distance parallel tunnel construction, the sludge-effective grouting technology solves the problems of construction safety and quality control, and achieves efficient and economical construction Effects reduce the impact of human use and secondary disturbances.
Patent Information
- Application Number
- CN202411327751.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-24
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-09-24
AI Technical Summary
In the construction of ultra-small clear distance parallel tunnel shields, the existing technology has problems such as poor construction safety and quality control, unscientific project costs, and excessive manpower use, and secondary disturbances seriously affect the tunnel structure.
MJS isolation piles and double slurry reinforcement technology is adopted, combined with synchronous support equipment and sludge grouting, an isolation wall and reinforcement layer is formed, which reduces disturbance sources, enhances media strength, and ensures construction safety and quality.
It realizes safe and efficient construction under ultra-small clear distance conditions, reduces manpower use, improves construction efficiency and structural stiffness, and reduces formation deformation and engineering costs.
Smart Images

Figure CN118933815A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of shield construction, in particular to a new type of protection system for ultra-small clearance parallel shield tunnel construction. Background Art
[0002] With the rapid development of underground space development in my country, double-line parallel tunnels are highly favored in engineering projects. Due to limited space, the distance between the two tunnels is getting smaller and smaller, and parallel tunnels with a distance less than 0.5D are becoming more and more common. Due to the small distance between the two tunnels, the secondary disturbance problem is serious, which will not only cause the superposition of stratum losses and increase settlement, but the construction of the rear line will also have a drastic impact on the structure of the leading tunnel, aggravating the problems of misalignment, cracks, longitudinal uneven deformation, seepage water and other diseases of the leading tunnel, affecting its construction quality and service performance. However, the current construction process and reinforcement technology for shield construction of parallel tunnels with ultra-small clearance are not systematic, and the reinforcement scope and parameters do not take into account the engineering cost, which lacks scientificity; in addition, the supporting trolley in the existing technology is large in size and requires a lot of manpower to move, hoist and fix, which is time-consuming and labor-intensive.
[0003] In view of this, there is an urgent need to invent a new type of protection system for ultra-small clearance parallel tunnel shield construction, which can not only ensure the safety and quality of construction and ensure an economical and reasonable construction progress, but also be scientific and intelligent and reduce the use of manpower. Summary of the invention
[0004] The purpose of the present invention is to overcome the defects of the prior art and provide a new protection system for the shield construction of parallel tunnels with ultra-small clearance. The invention aims to organize the construction safely and efficiently and ensure the construction progress by innovating the shield construction method, equipment and concept of parallel tunnels with ultra-small clearance under the premise of ensuring the safety and quality of the construction.
[0005] To achieve the above object, the present invention provides the following technical solution: a new type of protection system for ultra-small clearance parallel shield tunnel construction, comprising the following construction steps: Step 1: First, construct one side of the parallel tunnels with a small clearance. The shield machine penetrates from the starting shaft on one side to the receiving shaft to complete the construction of the first tunnel; Step 2: MJS isolation piles are constructed between the two tunnels. The cross section of the MJS isolation piles is a semicircular column with a diameter of 2400mm. The MJS isolation piles are arranged along the axis of the tunnel. The distance between the pile centers of adjacent MJS isolation piles is 1.5m-2m to ensure that the two adjacent piles are fitted together to form an isolation wall. The length of the MJS isolation piles extends from 3m above the tunnel to 3m below the tunnel and is a solid pile body. The MJS isolation piles contain P.042.5 grade ordinary Portland cement, the cement content is not less than 40% by mass, and the water-cement ratio is 1.0; Step 3: After the construction of MJS isolation piles is completed, the grouting trolley enters the pilot tunnel, and sleeve valve pipe deep hole grouting reinforcement is carried out on the pilot tunnel through the grouting holes and hoisting holes. The grouting range is 2m in radial direction, and the slurry adopts cement-water glass double liquid slurry, and the volume ratio of cement slurry to water glass is 1:1; water glass is diluted with water, and the dilution ratio of water glass to water is 1:3 by volume; the water-cement ratio of cement slurry is 1:1, and the grouting pressure is 0.5Mpa-1Mpa, forming a radial grouting reinforcement layer in the pilot tunnel; Step 4: After the deep hole grouting reinforcement treatment of the first tunnel is completed, the construction trolley withdraws from the first tunnel, and the tunnel synchronous support equipment enters the site and is located at the position where the support is required in the first tunnel; Step 5: The shield machine and its supporting equipment of the rear tunnel are ready for site entry. After the construction conditions are met, the rear tunnel construction excavation is carried out. At the same time, the synchronous support equipment for the leading tunnel moves forward synchronously with the shield machine of the rear line to ensure that the leading tunnel is supported at the six ring positions of the cutter head of the rear line; Step 6: With the construction of the rear tunnel, the shield position of the rear line is grouting with mud effect to form a mud effect grouting filling layer to fill the stratum over-excavated by the cutter head as soon as possible; Step 7: When the assembly of the rear tunnel segments is completed and there is space for working, the grouting trolley enters the rear tunnel to perform deep hole grouting in the rear tunnel to form a radial grouting reinforcement layer in the rear tunnel.
[0006] As a further solution of the present invention: the synchronous supporting equipment includes more than two independent supporting units, each of which is connected by a universal electric telescopic rod; the synchronous supporting equipment includes an upper bracket and a lower bracket, and an electric roller is installed on the outer peripheral wall of the upper bracket and the lower bracket; the synchronous supporting equipment is provided with a reinforcement mechanism, and the reinforcement mechanism is installed between the upper bracket and the lower bracket; the upper bracket and the lower bracket are connected by a connecting mechanism, and the reinforcement mechanism includes a reinforcement rod and a reinforcement frame, and the reinforcement rod and the reinforcement frame are located in the inner cavity of the synchronous supporting equipment, and the inner wall of the synchronous supporting equipment is provided with a slot, and the inner wall of the slot is provided with a positioning slot, and the reinforcement rod is slidably connected to the inner wall of the reinforcement frame, and the interior of the reinforcement rod is slidably connected to a positioning block extending to the outer wall of the reinforcement rod, and the interior of the reinforcement rod is rotatably connected to a first threaded rod extending to the inside of the positioning block, and one end of the first threaded rod is fixedly connected to a first bevel gear, The interior of the reinforcement rod is located on the outer wall of the first bevel gear and is rotatably connected to a second bevel gear. One end of the second bevel gear is fixedly connected to a connecting shaft, and one end of the connecting shaft is fixedly connected to a rotating block.
[0007] As a further solution of the present invention: the reinforcement mechanism also includes a docking groove, the docking groove is opened at one end of the reinforcement rod, the rotating block is located in the docking groove, the outer wall of the reinforcement frame is opened with an installation groove, the inner wall of the installation groove is slidably connected with the installation frame, the interior of the reinforcement frame is slidably connected with a docking block extending to the inner cavity of the installation groove, the bottom end of the docking block is fixedly connected to a limiting block, and a spring is connected between the limiting block and the reinforcement frame.
[0008] As a further solution of the present invention: the connecting mechanism includes a connecting groove, which is opened at the top of the lower bracket, and the inner wall of the connecting groove is opened with a fixing groove, the bottom end of the upper bracket is fixedly connected with a connecting block, the interior of the connecting block is symmetrically and slidably connected with a fixed block extending to the outer wall of the connecting block, one end of the fixed block is rotatably connected with a connecting rod, one end of the connecting rod is rotatably connected with a displacement block, the displacement block is slidably connected to the interior of the connecting block, the interior of the connecting block is rotatably connected with a second threaded rod extending to the interior of the displacement block, and one end of the second threaded rod is fixedly connected to a rotating column.
[0009] As a further solution of the present invention: the outer wall of the reinforcing rod is in contact with the inner wall of the slot, and the outer wall of the positioning block is in contact with the inner wall of the positioning groove.
[0010] As a further solution of the present invention: the first bevel gear is meshed with the second bevel gear, and a first threaded hole is formed on the outer wall of the positioning block, and the first threaded hole matches the first threaded rod.
[0011] As a further solution of the present invention: the inner wall of the installation groove is in contact with the outer wall of the installation frame, the outer wall of the docking block is in contact with the inner wall of the docking groove, the docking block is located at one end of the inner cavity of the installation groove and is provided with an inclined surface, and the docking block is in a Y-shape; slots are provided at the four top corners of the reinforcement frame, and the docking block extends into the slots.
[0012] As a further solution of the present invention: a first through hole is formed on the outer wall of the installation frame, a second through hole is formed in the inner cavity of the installation groove, bolts are slidably connected to the inner walls of the first through hole and the second through hole, and nuts are connected to the outer walls of the bolts.
[0013] As a further solution of the present invention: the inner wall of the connecting groove fits with the outer wall of the connecting block, and the inner wall of the fixing groove fits with the outer wall of the fixing block.
[0014] As a further solution of the present invention: both ends of the connecting rod are connected to the fixed block and the displacement block through a rotating shaft, and a second threaded hole is opened on the outer wall of the displacement block, and the second threaded hole matches the second threaded rod.
[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. The innovative method of "MJS interlocking isolation wall + double-line tunnel grouting + synchronous top support of the first tunnel + mud-resistance grouting outside the subsequent line shield" in the present invention forms a complete protection system, and can be expanded to adapt to ultra-small clearance shield multi-angle crossing projects. It takes all-round considerations such as reducing the disturbance source, strengthening the strength of the transmission medium, cutting off the deformation transmission path, increasing the disturbance object ring and longitudinal stiffness, and forms a complete new protection system for parallel tunnel shield construction, which can also be expanded to adapt to ultra-small clearance shield multi-angle crossing projects.
[0016] 2. The shield construction is the disturbance source, the soil is the transmission medium, and the preceding tunnel is the disturbance object. The principle of this new protection system is to reduce the disturbance source of the shield construction, strengthen the strength of the transmission medium, cut off the deformation transmission path, and increase the circumferential and longitudinal stiffness of the disturbance object.
[0017] The MJS isolation piles in step 2 have a reinforcement range from 3m above the tunnel to 3m below the tunnel. This range has been demonstrated to ensure isolation of disturbance loads while saving engineering costs.
[0018] The deep hole grouting reinforcement depth in step three and step seven is 2 meters. This reinforcement range has been proven to ensure the strength of the transmission medium and save engineering costs.
[0019] The synchronous top supporting equipment in steps four and five has the functions of servo precision control, automatic walking, large-angle climbing, small curve turning, etc., which can effectively enhance the ring and longitudinal stiffness of the leading tunnel and prevent the additional load of the rear line from affecting the structure of the leading tunnel.
[0020] The mud-reducing grouting technology outside the shield in the back line in step six can synchronously fill the over-excavation loss of the stratum caused by the cutterhead and posture around the shield, and make up for the delay in synchronous grouting. In addition, the disturbance to the stratum caused by parallel shield construction will be superimposed. The mud-reducing grouting technology can timely control the deformation of the stratum around the shield and reduce the second disturbance of the stratum caused by the excavation of the back line.
[0021] 3. In step 5, synchronous support equipment is used to ensure that the leading tunnel has support at the six ring positions in front of the cutterhead (including the cutterhead ring) of the trailing line. The six ring range is a strong impact area. The present invention can strengthen the structural rigidity of this range. The synchronous support equipment that can move automatically is used to restrain the deformation of the leading tunnel structure under the additional load in advance, ensuring the safety of the leading tunnel structure during construction.
[0022] In addition, the synchronous top supporting equipment described in the present invention is composed of multiple independent supporting units connected by universal electric telescopic rods. The top supporting length can be controlled by controlling the number of connected independent supporting units as needed; due to the setting of the universal electric telescopic rod, flexible connection can be achieved between the independent supporting units, so that they can adapt to different tunnel structures such as turning and climbing, and have stronger adaptability; the independent supporting units adopt a split structure, which is not only convenient for lifting and transportation, but also can be assembled quickly and in real time in the tunnel, which can further save labor and scheduling time, making the synchronous top supporting equipment more flexible and convenient to use.
[0023] In summary, the construction method of the present invention is ingeniously designed, has high construction efficiency, strong operability, good safety, and is environmentally friendly, with broad market prospects. The reinforcement scope, parameters, and methods of the present invention are scientific, systematic, and intelligent, avoiding the use of a large amount of manpower, and can ensure construction safety, quality, and progress. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is a flow chart of the application of the new protection system for shield construction of ultra-small clearance parallel tunnels of the present invention; Figure 2 It is a longitudinal section schematic diagram of a novel protection system for shield construction of ultra-small clearance parallel tunnels of the present invention; Figure 3 It is a schematic diagram of the cross-sectional structure of the novel protection system for shield construction of ultra-small clearance parallel tunnels of the present invention; Figure 4 It is a structural schematic diagram of the synchronous top supporting equipment of the present invention; Figure 5 It is a schematic structural diagram of an independent support unit body of the present invention; Figure 6 It is a structural schematic diagram of the slot of the present invention; Figure 7 It is a schematic diagram of the internal structure of the reinforcement rod of the present invention; Figure 8 It is a schematic diagram of installing the installation frame of the present invention; Fig. 9 It is a schematic diagram of the installation of the docking block of the present invention; Fig.10 It is a schematic diagram of the connection between the upper bracket and the lower bracket of the present invention; Fig.11 It is a schematic diagram of the internal structure of the connection block of the present invention.
[0025] In the figure: 1. advance tunnel; 2. MJS isolation pile; 3. radial grouting reinforcement layer in the advance tunnel; 4. synchronous top support equipment; 401. independent support unit; 402. upper bracket; 403. lower bracket; 404. universal electric telescopic rod; 5. rear tunnel; 6. mud-effect grouting filling layer; 7. radial grouting reinforcement layer in the rear tunnel; 8. reinforcement mechanism; 801. reinforcement rod; 802. reinforcement frame; 803. slot; 804. positioning groove; 805. positioning block; 806. first threaded rod; 807. first bevel gear; 808, second bevel gear; 809, connecting shaft; 810, rotating block; 811, docking groove; 812, mounting groove; 813, mounting frame; 814, docking block; 815, limiting block; 816, spring; 817, slot; 9, connecting mechanism; 901, connecting groove; 902, fixing groove; 903, connecting block; 904, fixing block; 905, connecting rod; 906, displacement block; 907, second threaded rod; 908, rotating column; 10, first through hole; 11, second through hole; 12, bolt; 13, nut. DETAILED DESCRIPTION
[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0027] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance. In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", and "set" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be the internal connection of two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances. The following is an explanation of an embodiment of the present invention based on the overall structure of the present invention.
[0028] See also Figures 1 to 11In an embodiment of the present invention, a new type of protection system for ultra-small clearance parallel shield tunnel construction includes the following construction steps: Step 1: First, construct one side of the parallel tunnels with a small clearance. The shield machine penetrates from the starting shaft on one side to the receiving shaft to complete the construction of the first tunnel 1; Step 2: construct MJS isolation piles 2 between the two tunnels. The cross section of the MJS isolation piles 2 is a semicircular column with a diameter of 2400mm. The MJS isolation piles 2 are arranged along the axis of the tunnel. The distance between the pile centers of adjacent MJS isolation piles 2 is 1.5m-2m, ensuring that the two adjacent piles are fitted together to form an isolation wall. The length direction of the MJS isolation piles 2 extends from 3m above the tunnel to 3m below the tunnel and is a solid pile body. The MJS isolation piles 2 contain P.042.5 grade ordinary Portland cement, the cement content is not less than 40% by mass, and the water-cement ratio is 1.0; Step 3: After the construction of MJS isolation pile 2 is completed, the grouting trolley enters the pilot tunnel 1, and sleeve valve pipe deep hole grouting reinforcement is performed on the pilot tunnel 1 through the grouting holes and the hoisting holes. The grouting range is 2m in radial direction. The grouting liquid adopts cement-water glass double liquid slurry. The volume ratio of cement slurry to water glass is 1:1; the water glass is diluted with water, and the dilution ratio of water glass to water is 1:3 by volume; the water-cement ratio of cement slurry is 1:1, and the grouting pressure is 0.5Mpa-1Mpa, forming a radial grouting reinforcement layer in the pilot tunnel (3); Step 4: After the deep hole grouting reinforcement treatment of the first tunnel 1 is completed, the construction trolley withdraws from the first tunnel 1, and the tunnel synchronous support equipment 4 enters the site and is located at the position where the support is required in the first tunnel 1; Step 5: The shield machine and its supporting equipment of the rear tunnel 5 are ready for site entry. After the construction conditions are met, the rear tunnel 5 is excavated. At the same time, the synchronous support equipment 4 supporting the top of the leading tunnel 1 moves forward synchronously with the shield machine of the rear line to ensure that the leading tunnel 1 is supported at the six ring positions away from the cutter head of the rear line; Step 6: With the construction of the rear tunnel 5, the shield position of the rear line is grouting with a grouting effect to form a grouting filling layer 6 to fill the stratum over-excavated by the cutter head as soon as possible; Step 7: When the assembly of the segments of the rear tunnel 5 is completed and there is space for operation, the grouting trolley enters the rear tunnel 5 to perform deep hole grouting on the rear tunnel 5 to form a radial grouting reinforcement layer 7 in the rear tunnel.
[0029] Please refer to Figures 4 to 11The synchronous supporting equipment 4 includes more than two independent supporting units 401, and each independent supporting unit is connected by a universal electric telescopic rod 404; the synchronous supporting equipment 4 includes an upper bracket 402 and a lower bracket 403, and electric rollers are installed on the outer peripheral walls of the upper bracket 402 and the lower bracket 403; a reinforcement mechanism 8 is arranged in the synchronous supporting equipment 4, and the reinforcement mechanism 8 is installed between the upper bracket 402 and the lower bracket 403; the upper bracket 402 and the lower bracket 403 are connected by a connecting mechanism 9.
[0030] The reinforcement mechanism 8 includes a reinforcement rod 801 and a reinforcement frame 802. The reinforcement rod 801 and the reinforcement frame 802 are located in the inner cavity of the synchronous support equipment 4. The inner wall of the synchronous support equipment 4 is provided with a slot 803. The inner wall of the slot 803 is provided with a positioning groove 804. The reinforcement rod 801 is slidably connected to the inner wall of the reinforcement frame 802. The interior of the reinforcement rod 801 is slidably connected to a positioning block 805 extending to the outer wall of the reinforcement rod 801. The interior of the reinforcement rod 801 is rotatably connected to a first threaded rod 806 extending to the interior of the positioning block 805. One end of the first threaded rod 806 is fixedly connected to a first bevel gear 807. The interior of the reinforcement rod 801 is located on the outer wall of the first bevel gear 807 and is rotatably connected to the second bevel gear 808. One end of the second bevel gear 808 is fixedly connected to a connecting shaft 809, and one end of the connecting shaft 809 is fixedly connected to a rotating block 810. The reinforcement mechanism 8 also includes a docking groove 811, which is provided at one end of the reinforcement rod 801. The rotating block 810 is located in the docking groove 811. An installation groove 812 is provided on the outer wall of the reinforcement frame 802. An installation frame 813 is slidably connected to the inner wall of the installation groove 812. The interior of the reinforcement frame 802 is slidably connected to a docking block 814 extending to the inner cavity of the installation groove 812. The bottom end of the docking block 814 is fixedly connected to a limiting block 815, and a spring 816 is connected between the limiting block 815 and the reinforcement frame 802.
[0031] In this embodiment, when assembling the single independent support unit 401 of the synchronous support equipment 4, the reinforcement mechanism is assembled first. The reinforcement mechanism is assembled as follows: insert the reinforcement rod 801 into the slot 803, and after completion, rotate the rotating block 810, the rotating block 810 rotates to drive the connecting shaft 809 to rotate, the connecting shaft 809 rotates to drive the second bevel gear 808 to rotate, the second bevel gear 808 rotates to drive the first bevel gear 807 to rotate, the first bevel gear 807 rotates to drive the first threaded rod 806 to rotate, the first threaded rod 806 rotates to drive the positioning block 805 to move, the positioning block 805 moves and inserts into the positioning groove 804, and the reinforcement rod 801 is fixed in the slot 803.
[0032] Thereafter, the reinforcement frame 802 is placed into the inner cavity of the synchronous support equipment 4 (i.e., between the assembled upper bracket 402 and the lower bracket 403), and contacts one end of the reinforcement rod 801. Thereafter, the installation frame 813 is installed into the installation groove 812. The installation frame 813 is displaced to contact the docking block 814, pushing the docking block 814 and the limit block 815 to be displaced, thereby squeezing the spring 816. The docking block 814 is displaced out of the reinforcement frame 802 and inserted into the docking groove 811, thereby fixing the reinforcement rod 801 and the reinforcement frame 802, thereby facilitating the assembly of the reinforcement mechanism in the synchronous support equipment 4.
[0033] Please refer to Figure 10 to Figure 11 The connecting mechanism 9 includes a connecting groove 901, which is opened at the top of the lower bracket 403. A fixing groove 902 is opened on the inner wall of the connecting groove 901. A connecting block 903 is fixedly connected to the bottom end of the upper bracket 402. A fixing block 904 extending to the outer wall of the connecting block 903 is symmetrically slidably connected inside the connecting block 903. One end of the fixing block 904 is rotatably connected to a connecting rod 905. One end of the connecting rod 905 is rotatably connected to a displacement block 906. The displacement block 906 is slidably connected to the inside of the connecting block 903. The inside of the connecting block 903 is rotatably connected to a second threaded rod 907 extending to the inside of the displacement block 906. One end of the second threaded rod 907 is fixedly connected to a rotating column 908.
[0034] In this embodiment: when connecting the upper bracket 402 and the lower bracket 403, the connecting block 903 is inserted into the connecting groove 901, and after completion, the rotating column 908 is rotated, and the rotating column 908 rotates to drive the second threaded rod 907 to rotate, and the second threaded rod 907 rotates to drive the displacement block 906 to move, and the displacement block 906 moves through the connecting rod 905 to drive the fixed block 904 to move, and the fixed block 904 moves and inserts into the fixed groove 902, so that the upper bracket 402 and the lower bracket 403 are fixedly connected, which is convenient for the installation operation of the synchronous support equipment 4; It is worth noting that electric rollers are installed on the outer peripheral wall of the synchronous support equipment 4, that is, on the outer peripheral wall of the upper bracket 402 and the lower bracket 403. Electric rollers are installed for moving the synchronous support equipment 4. The electric rollers are pressure-resistant electric rollers that can be remotely started and stopped and speed-regulated.
[0035] Please refer to Figures 5 to 7 The outer wall of the reinforcing rod 801 fits with the inner wall of the slot 803 , the outer wall of the positioning block 805 fits with the inner wall of the positioning groove 804 , the first bevel gear 807 meshes with the second bevel gear 808 , and the outer wall of the positioning block 805 is provided with a first threaded hole, which matches the first threaded rod 806 .
[0036] In this embodiment: the reinforcement rod 801 is inserted into the slot 803. After completion, the rotating block 810 is rotated. The rotating block 810 rotates to drive the connecting shaft 809 to rotate. The connecting shaft 809 rotates to drive the second bevel gear 808 to rotate. The second bevel gear 808 rotates to drive the first bevel gear 807 to rotate. The first bevel gear 807 rotates to drive the first threaded rod 806 to rotate. The first threaded rod 806 rotates to drive the positioning block 805 to move. The positioning block 805 is moved and inserted into the positioning groove 804 to fix the reinforcement rod 801 in the slot 803.
[0037] Please refer to Figures 7 to 9 The inner wall of the mounting groove 812 is in contact with the outer wall of the mounting frame 813, the outer wall of the docking block 814 is in contact with the inner wall of the docking groove 811, and the docking block 814 is located at one end of the inner cavity of the mounting groove 812 and is provided with an inclined surface. The shape of the docking block 814 is Y-shaped; slots 817 are provided at the four top corners of the reinforcement frame 802, and the docking block 814 extends into the slots 817.
[0038] In this embodiment: the installation frame 813 is installed into the installation groove 812, the installation frame 813 is displaced to contact the docking block 814, pushing the docking block 814 and the limit block 815 to be displaced, causing compression on the spring 816, and the docking block 814 passes through the slot 817 and moves out of the reinforcement frame 802 and then is inserted into the docking groove 811 to fix the reinforcement rod 801 and the reinforcement frame 802.
[0039] Please refer to Figure 8 A first through hole 10 is formed on the outer wall of the mounting frame 813, a second through hole 11 is formed in the inner cavity of the mounting groove 812, bolts 12 are slidably connected to the inner walls of the first through hole 10 and the second through hole 11, and a nut 13 is connected to the outer wall of the bolt 12.
[0040] In this embodiment: after the installation frame 813 is moved into the installation groove 812, the bolt 12 is passed through the first through hole 10 and the second through hole 11, and the nut 13 is connected to the outer wall of the bolt 12, and the bolt 12 and the nut 13 fix the installation frame 813 in the installation groove 812.
[0041] Please refer to Figure 10 to Figure 11 The inner wall of the connecting groove 901 fits with the outer wall of the connecting block 903 , and the inner wall of the fixing groove 902 fits with the outer wall of the fixing block 904 .
[0042] In this embodiment: the connection block 903 is inserted into the connection groove 901 , and after completion, the rotation column 908 is rotated, and the fixing block 904 is displaced and inserted into the fixing groove 902 , so as to fix the upper bracket 402 and the lower bracket 403 together.
[0043] Please refer to Figure 10 to Figure 11The two ends of the connecting rod 905 are connected to the fixed block 904 and the displacement block 906 through a rotating shaft. The outer wall of the displacement block 906 is provided with a second threaded hole, and the second threaded hole matches the second threaded rod 907.
[0044] In this embodiment, the rotating column 908 is rotated, and the rotation of the rotating column 908 drives the second threaded rod 907 to rotate, and the rotation of the second threaded rod 907 drives the displacement block 906 to displace, and the displacement of the displacement block 906 drives the fixed block 904 to displace through the connecting rod 905.
[0045] What is described above is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A new type of protection system for ultra-small clearance parallel shield tunnel construction, characterized in that: The construction steps include: Step 1: First, construct one side of the parallel tunnels with a small clearance. The shield machine penetrates from the starting shaft on one side to the receiving shaft to complete the construction of the first tunnel (1); Step 2: constructing MJS isolation piles (2) between the two tunnels. The cross section of the MJS isolation piles (2) is a semicircular column with a diameter of 2400 mm. The MJS isolation piles (2) are arranged along the tunnel axis. The distance between the pile centers of adjacent MJS isolation piles (2) is 1.5 m to 2 m, so as to ensure that two adjacent piles are arranged close to each other to form an isolation wall. The length direction of the MJS isolation piles (2) extends from 3 m above the tunnel to 3 m below the tunnel and is a solid pile body. The MJS isolation piles (2) contain P.042.5 grade ordinary silicate cement, the cement content of which is not less than 40% by mass, and the water-cement ratio is 1.
0. Step 3: After the construction of the MJS isolation pile (2) is completed, the grouting trolley enters the pilot tunnel (1) and performs sleeve valve pipe deep hole grouting reinforcement on the pilot tunnel (1) through the grouting holes and the hoisting holes. The grouting range is 2m in radial direction. The grouting liquid adopts cement-water glass double liquid slurry. The volume ratio of cement slurry to water glass is 1:
1. The water glass is diluted with water. The dilution ratio of water glass to water is 1:3 by volume. The water-cement ratio of cement slurry is 1:
1. The grouting pressure is 0.5Mpa-1Mpa, forming a radial grouting reinforcement layer (3) in the pilot tunnel. Step 4: After the deep hole grouting reinforcement treatment of the first tunnel (1) is completed, the construction trolley withdraws from the first tunnel (1), and the tunnel synchronous support equipment (4) enters the site and is located at the position of the first tunnel (1) that needs support; Step 5: The shield machine and its supporting equipment of the rear tunnel (5) are ready for on-site construction. After the construction conditions are met, the rear tunnel (5) is excavated. At the same time, the synchronous support equipment (4) supporting the top of the leading tunnel (1) moves forward synchronously with the shield machine of the rear line to ensure that the leading tunnel (1) is supported at the six ring positions away from the cutter head of the rear line. Step 6: With the construction of the rear tunnel (5), the shield position of the rear line is grouting with a grouting effect to form a grouting effect filling layer (6), and the stratum over-excavated by the cutter head is filled in as soon as possible; Step 7: When the assembly of the segments of the rear tunnel (5) is completed and there is space for operation, the grouting trolley enters the rear tunnel (5) and performs deep hole grouting on the rear tunnel (5) to form a radial grouting reinforcement layer (7) in the rear tunnel.
2. According to claim 1, a new type of protection system for parallel shield tunnel construction with ultra-small clearance is characterized in that: The synchronous top supporting equipment (4) comprises more than two independent supporting units (401), each of which is connected via a universal electric telescopic rod (404); the synchronous top supporting equipment (4) comprises an upper bracket (402) and a lower bracket (403), and electric rollers are installed on the outer peripheral walls of the upper bracket (402) and the lower bracket (403); a reinforcement mechanism (8) is provided in the synchronous top supporting equipment (4), and the reinforcement mechanism (8) is installed between the upper bracket (402) and the lower bracket (403); the upper bracket (402) and the lower bracket (403) are connected via a connecting mechanism (9); The reinforcement mechanism (8) comprises a reinforcement rod (801) and a reinforcement frame (802); the reinforcement rod (801) and the reinforcement frame (802) are located in the inner cavity of the synchronous top supporting device (4); a slot (803) is provided on the inner wall of the synchronous top supporting device (4); a positioning groove (804) is provided on the inner wall of the slot (803); the reinforcement rod (801) is slidably connected to the inner wall of the reinforcement frame (802); a positioning block (805) extending to the outer wall of the reinforcement rod (801) is slidably connected inside the reinforcement rod (801); a first threaded rod (806) extending to the inside of the positioning block (805) is rotatably connected inside the reinforcement rod (801); one end of the first threaded rod (806) is fixedly connected to a first bevel gear (807); The interior of the reinforcement rod (801) is rotatably connected to the outer wall of the first bevel gear (807), one end of the second bevel gear (808) is fixedly connected to a connecting shaft (809), and one end of the connecting shaft (809) is fixedly connected to a rotating block (810).
3. A new type of protection system for ultra-small clearance parallel shield tunnel construction according to claim 2, characterized in that: The reinforcement mechanism (8) further comprises a docking groove (811), wherein the docking groove (811) is provided at one end of the reinforcement rod (801), the rotating block (810) is located in the docking groove (811), an outer wall of the reinforcement frame (802) is provided with a mounting groove (812), an inner wall of the mounting groove (812) is slidably connected to a mounting frame (813), an interior of the reinforcement frame (802) is slidably connected to a docking block (814) extending into an inner cavity of the mounting groove (812), a bottom end of the docking block (814) is fixedly connected to a limit block (815), and a spring (816) is connected between the limit block (815) and the reinforcement frame (802).
4. A new type of protection system for ultra-small clearance parallel shield tunnel construction according to claim 3, characterized in that: The connecting mechanism (9) comprises a connecting groove (901), wherein the connecting groove (901) is provided at the top end of the lower bracket (403), and a fixing groove (902) is provided on the inner wall of the connecting groove (901); the bottom end of the upper bracket (402) is fixedly connected to a connecting block (903); the interior of the connecting block (903) is symmetrically slidably connected to a fixing block (904) extending to the outer wall of the connecting block (903); one end of the fixing block (904) is rotatably connected to a connecting rod (905); one end of the connecting rod (905) is rotatably connected to a displacement block (906); the displacement block (906) is slidably connected to the interior of the connecting block (903); the interior of the connecting block (903) is rotatably connected to a second threaded rod (907) extending to the interior of the displacement block (906); one end of the second threaded rod (907) is fixedly connected to a rotating column (908).
5. The new type of protection system for parallel shield tunnel construction with ultra-small clearance according to claim 3 is characterized in that: The outer wall of the reinforcing rod (801) fits with the inner wall of the slot (803), and the outer wall of the positioning block (805) fits with the inner wall of the positioning groove (804).
6. The new type of protection system for parallel shield tunnel construction with ultra-small clearance according to claim 3 is characterized in that: The first bevel gear (807) is meshed with the second bevel gear (808), and a first threaded hole is formed on the outer wall of the positioning block (805), and the first threaded hole matches the first threaded rod (806).
7. The new type of protection system for parallel shield tunnel construction with ultra-small clearance according to claim 3 is characterized in that: The inner wall of the installation groove (812) is in contact with the outer wall of the installation frame (813); the outer wall of the docking block (814) is in contact with the inner wall of the docking groove (811); an inclined surface is provided at one end of the docking block (814) located in the inner cavity of the installation groove (812); the docking block (814) is in a Y-shape; slots (817) are provided at the four top corners of the reinforcement frame (802), and the docking block (814) extends into the slots (817).
8. The new type of protection system for parallel shield tunnel construction with ultra-small clearance according to claim 3 is characterized in that: The outer wall of the installation frame (813) is provided with a first through hole (10), the inner cavity of the installation groove (812) is provided with a second through hole (11), the inner walls of the first through hole (10) and the second through hole (11) are slidably connected with bolts (12), and the outer wall of the bolt (12) is connected with a nut (13).
9. The novel protection system for parallel shield tunnel construction with ultra-small clearance according to claim 4 is characterized in that: The inner wall of the connecting groove (901) fits with the outer wall of the connecting block (903), and the inner wall of the fixing groove (902) fits with the outer wall of the fixing block (904).
10. The new type of protection system for parallel shield tunnel construction with ultra-small clearance according to claim 4, characterized in that: The two ends of the connecting rod (905) are connected to the fixed block (904) and the displacement block (906) via a rotating shaft. The outer wall of the displacement block (906) is provided with a second threaded hole, and the second threaded hole matches the second threaded rod (907).
Citation Information
Patent Citations
Construction method of overlapped shield tunnel
CN103277110A
Soft soil stratum small clear distance shield end reinforcing system and design method thereof
CN113790058A
Shield construction method for small-radius curve small-clear-distance overlapped tunnel in water-rich complex stratum
CN114412482A
In-tunnel reinforcing structure for enabling shield to pass through advanced tunnel at near interval
CN209799987U
Middle partition wall system for small-clear-distance shield tunnel
CN220748352U