Supporting structure for controlling tunnel surrounding rock deformation and supporting method thereof
By setting up a support structure with deformation compressive unit and articulated connection method at the deformation of the tunnel surrounding rock, the problem of poor stress release in the existing technology is solved, and the initial support stability and permanentness of the tunnel surrounding rock is improved. stability.
Patent Information
- Application Number
- CN202411101557.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-11-12
AI Technical Summary
When controlling the deformation of the surrounding rock in the tunnel, the existing support structure cannot effectively absorb and release the stress of the surrounding rock, resulting in excessive pressure on the surrounding rock and insufficient initial support stability, making it difficult to meet the requirements of permanent stability.
Using a support structure including the initial support of the hole body and the arch, the deformation and compression-resistant unit is installed on the hole body and the arch groove surface, and components such as transformers, stress adapter rods and pressure-bearing medium rods are absorbed and released. Stresses generated by surrounding rock deformation and hinged connections are embedded in the concrete layer to improve stress relief efficiency.
Effectively absorb and release the stress generated by surrounding rock deformation, avoid stress concentration, improve the stability and permanence of initial support, ensure the stable support force of the vault, side waist and bottom of the arch, and improve the stability of the overall support.
Smart Images

Figure CN118933872A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel engineering, and more specifically, to a supporting structure and a supporting method for controlling deformation of tunnel surrounding rocks. Background Art
[0002] The existing support structure is mainly a "strong support and hard top" method. This method is a passive pressure support, which restricts the deformation development of the surrounding rock. The deformation energy (stress) of the rock mass cannot be effectively released, which will induce excessive surrounding rock pressure. In the document "Research on Mechanical Behavior and Support Countermeasures for Large Deformation Construction of Tunnels with Weak and Broken Surrounding Rocks", it is recorded that the initial support adopts double-layer support: the first layer is steel support for arch wall erection and sprayed concrete; the second layer uses grid steel frame, and the system anchor rod uses small grouting pipes, and then grouting reinforcement. This support method can control the deformation of the surrounding rock to a certain extent, but large deformation and cracking occur in the arch wall, and serious deformation and distortion of the steel arch frame in the arch waist. This double-layer support method still belongs to the "strong support and hard top" support method, which is still not very suitable for tunnels with large extrusion deformation of surrounding rocks.
[0003] In view of the above situation, it is advisable to study a support structure that can absorb and resolve the stress generated by surrounding rock deformation to avoid it inducing excessive surrounding rock pressure. At the same time, it should have stable supporting capacity after the stress is released to improve the permanent stability of the support. Summary of the invention
[0004] An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.
[0005] In order to achieve these purposes and other advantages according to the present invention, a support structure for controlling deformation of surrounding rock of a tunnel is provided, comprising:
[0006] Advanced support, which is support before tunnel excavation;
[0007] The initial support of the tunnel body is the support after the tunnel body is excavated, and the initial support of the tunnel body includes an initial concrete layer of the tunnel body sprayed along the rock surface of the tunnel body, multiple anchor rod layers driven along the initial concrete layer of the tunnel body, a steel mesh hung and fixed on the initial concrete layer of the tunnel body, multiple steel arch frames erected near the steel mesh, multiple deformation and compression units arranged between two adjacent steel arch frames, and a tunnel body sprayed concrete layer formed by spraying and covering the steel arch frames, the steel mesh and the deformation and compression units; wherein the multiple deformation and compression units are respectively a tunnel top deformation and compression unit located at the arc top of the steel arch frame and a tunnel waist deformation and compression unit located at the side waist of the steel arch frame;
[0008] The initial support of the inverted arch is the support after the excavation of the inverted arch section, and the initial support of the inverted arch comprises an initial concrete layer of the inverted arch formed by spraying along the inverted arch groove surface, a plurality of inverted arch steel frames arranged on the initial concrete layer of the inverted arch, the deformation and compression resistance units arranged on two adjacent inverted arch steel frames, and an inverted arch sprayed concrete layer formed by spraying and covering the inverted arch steel frames and the deformation and compression resistance units; wherein the deformation and compression resistance units located on the inverted arch steel frames are deformation and compression resistance units of the inverted arch;
[0009] Wherein, each deformation compression unit includes:
[0010] A pair of supports, a pair of supports are arranged at intervals along the curvature direction of the tunnel section, and both ends of each support are fixed to two adjacent steel arch frames or two adjacent inverted arch steel frames;
[0011] A pair of transformers, the pair of transformers are respectively fixed on a pair of supports, the transformers include a base fixed to the supports, a cylinder body fixed to the base, and a shifting rod sealed and slidably arranged on the cylinder body; wherein a plurality of independent micro-accommodating chambers are provided in the base, one end of the micro-accommodating chamber is connected to the cylinder body, and a pressure valve is provided at the connection point; the shifting rod is provided in a gap between one end of the cylinder body and the end face of the cylinder body, and the gap is filled with hydraulic oil; the other end of the shifting rod is provided with a limiting portion and abuts against the end face of the cylinder body away from the hydraulic oil;
[0012] A pair of stress adapting rods, the pair of stress adapting rods are respectively hinged to one end of a pair of displacement rods located outside the cylinder body, and the stress adapting rods are arc-shaped;
[0013] A pressure-bearing middle rod, both ends of which are respectively hinged to the other ends of a pair of stress-adapting rods, and the pressure-bearing middle rod is arc-shaped;
[0014] The secondary lining of the inverted arch is arranged on the inverted arch sprayed concrete layer;
[0015] The secondary lining of the tunnel body is arranged on the sprayed concrete layer of the tunnel body.
[0016] Preferably, the spacing between a pair of supports of the cave roof deformation compression-resistant unit is set within an arc range of 45° on both sides above the center line of the tunnel section, and the center of the corresponding pressure-bearing middle rod deviates from the arc range of 15° on both sides of the center line of the tunnel section;
[0017] The spacing between a pair of supports of the tunnel waist deformation compression resistance unit is set to be within an arc range of 15° downward and 30° upward from the horizontal line of the center of the tunnel section;
[0018] The spacing between a pair of supports of the invert deformation compression-resistant unit is set to be within an arc range of 60° on both sides below the center of the tunnel section.
[0019] Preferably, the fixed positions of a pair of supports of two adjacent deformation compression-resistant units along the longitudinal direction of the tunnel, the hinged positions of the pressure transformer and the stress adaptation rod, and the hinged positions of the stress adaptation rod and the pressure-bearing middle rod are all staggered.
[0020] Preferably, the valve opening pressures of the pressure valves corresponding to the multiple micro-containing chambers increase sequentially, and the volume of each micro-containing chamber is set as follows: when the pressure valve reaches a preset valve opening pressure, the hydraulic oil enters and fills the micro-containing chamber under the pressure of the shift rod, and the distance that the shift rod moves toward the cylinder body is 0.1 to 0.2 mm.
[0021] A support method for controlling deformation of tunnel surrounding rock is provided, comprising the following steps:
[0022] S1. After the tunnel portal pipe shed is erected, advance support is applied;
[0023] S2. Excavate a tunnel of a certain length, spray concrete along the rock surface of the tunnel body to form an initial concrete layer of the tunnel body, then hang a steel mesh, splice the steel arch frame according to the designed shape, and when the initial concrete layer of the tunnel body reaches the designed strength, install the steel arch frame to the initial concrete layer of the tunnel body at a certain interval, and then install and fix the top deformation compression unit and the waist deformation compression unit according to the designed position. The two adjacent steel arch frames are connected and fixed by multiple steel bars, and sprayed with concrete to form a secondary sprayed concrete layer of the tunnel body. When the secondary sprayed concrete layer of the tunnel body reaches the designed strength, the initial support of the tunnel body is completed;
[0024] S3, excavating an inverted arch of a certain length, spraying concrete along the inverted arch groove surface to form an initial concrete layer of the inverted arch, when the initial concrete layer of the inverted arch reaches the design strength, splicing, installing, and fixing the inverted arch steel frame to the initial concrete layer of the inverted arch according to the design shape, installing and fixing the inverted arch deformation compression unit according to the design position, connecting and fixing two adjacent inverted arch steel frames through multiple steel bars, spraying concrete to cover, forming an inverted arch sprayed concrete layer, and when the inverted arch sprayed concrete layer reaches the design strength, the initial support of the inverted arch is completed;
[0025] S4, construct the secondary lining of the inverted arch;
[0026] S5. Construct secondary lining of the tunnel body;
[0027] S6. Repeat steps S1 to S6 to complete the support of the surrounding rock of the entire tunnel.
[0028] The present invention has at least the following beneficial effects:
[0029] First, on the existing support structure, the size, compressive deformation amount and installation position of the deformation compression unit are set according to the calculated settlement amount. After the installation of the deformation compression unit (cavern top deformation compression unit, cave waist deformation compression unit and inverted arch deformation compression unit) is completed, the stress caused by the deformation and settlement of the surrounding rock can be effectively absorbed and resolved, avoiding stress concentration and inducing excessive surrounding rock pressure, and the stress caused by the deformation and uplift of the inverted arch bottom plate can be effectively absorbed and resolved, avoiding stress concentration and inducing excessive deformation and uplift pressure of the inverted arch bottom plate; at the same time, after the stress of the surrounding rock deformation stress and the deformation and uplift of the inverted arch bottom plate is resolved, the arch top, side waist and inverted arch bottom have a more stable supporting force effect, thereby improving the initial support stability.
[0030] Second, the displacement rod, stress adaptation rod and pressure-bearing middle rod in the deformation and compression unit are connected by hinged connection. Since the entire deformation and compression unit is embedded in the concrete layer, the rotational displacement that can occur in the hinged connection is very small. The small rotational displacement is caused by the surrounding rock stress. Therefore, the small rotational displacement can adapt to the direction of the surrounding rock stress. Combined with the stress adaptation rod and the displacement rod, the direction change can be transmitted to the displacement rod, thereby improving the stress resolution efficiency of the transformer.
[0031] Third, usually when the surrounding rock settlement rate or the surrounding displacement rate is less than 0.1-0.2 mm / d, it means that the surrounding rock is relatively stable. Therefore, the single displacement distance of the displacement rod cannot be greater than 0.2 mm to avoid excessive disturbance to the original stability of the surrounding rock.
[0032] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 A cross-sectional view of the support structure along the tunnel section according to one of the technical solutions of the present invention;
[0034] Figure 2 A schematic diagram of the side structure of the deformation and compression-resistant unit according to one of the technical solutions of the present invention;
[0035] Figure 3 A detailed diagram of the transformer according to one of the technical solutions of the present invention;
[0036] Figure 4 This is a layout diagram of multiple deformation and compression-resistant units located at the dome position according to one of the technical solutions of the present invention.
[0037] Explanation of the reference numerals in the accompanying drawings in the specification: advance support 1, initial concrete layer of tunnel body 2, steel arch frame 3, re-sprayed concrete layer of tunnel body 4, initial concrete layer of invert arch 5, steel frame of invert arch 6, re-sprayed concrete layer of invert arch 7, secondary lining of tunnel body 8, secondary lining of invert arch 9, deformation compression resistant unit 100, support 11, base 12, cylinder body 13, displacement rod 14, micro-accommodating chamber 15, pressure valve 16, hydraulic oil 17, limit part 18, stress adaptation rod 19, pressure-bearing middle rod 10. DETAILED DESCRIPTION
[0038] The present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
[0039] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the orientation or positional relationship indicated by the terms is based on the orientation or positional relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0040] like Figures 1 to 4 As shown, the present invention provides a support structure for controlling deformation of tunnel surrounding rock, comprising:
[0041] Advance support 1 is the support before tunnel excavation; the existing conventional advance support method can be adopted. Specifically, the advance support 1 can adopt advance small pipe grouting support, with an external insertion angle of 10 to 30 degrees, and the overlapping length of longitudinally adjacent advance small pipes is greater than 15cm; the specific diameter of the advance small pipe can be 4.2cm, the wall thickness is 4mm, and the length is 4.5m. Made of hot-rolled seamless steel pipe;
[0042] The initial support of the tunnel body is the support after the tunnel body is excavated, and the initial support of the tunnel body includes an initial concrete layer 2 of the tunnel body sprayed along the rock surface of the tunnel body, multiple anchor rod layers driven along the initial concrete layer 2 of the tunnel body, a steel mesh hung and fixed on the initial concrete layer 2 of the tunnel body, multiple steel arch frames 3 erected near the steel mesh, multiple deformation and compression units 100 arranged between two adjacent steel arch frames 3, and a tunnel body sprayed concrete layer 4 formed by spraying and covering the steel arch frames 3, the steel mesh and the deformation and compression units 100; wherein the multiple deformation and compression units 100 are respectively It is a cave roof deformation compression unit located at the arc-shaped top of the steel arch frame 3, and a cave waist deformation compression unit located at the side waist of the steel arch frame 3; after tunnel excavation, the surrounding rock will produce deformation and settlement, and the settlement amount can be calculated based on the surrounding rock level and monitoring measurement data analysis. Therefore, the size, compressive deformation amount and installation position of the deformation compression unit 100 are set according to the calculated settlement amount. After the installation of the deformation compression unit 100 is completed, it can effectively absorb and resolve the stress caused by the deformation and settlement of the surrounding rock, avoid stress concentration, induce excessive surrounding rock pressure, and improve the initial support stability.
[0043] The initial support of the inverted arch is the support after the excavation of the inverted arch section, and the initial support of the inverted arch comprises an initial concrete layer 5 of the inverted arch formed by spraying along the inverted arch groove surface, a plurality of inverted arch steel frames 6 arranged on the initial concrete layer 5 of the inverted arch, the deformation and compression resistance units 100 arranged on two adjacent inverted arch steel frames 6, and an inverted arch sprayed concrete layer 7 formed by spraying and covering the inverted arch steel frames 6 and the deformation and compression resistance units 100; wherein the deformation and compression resistance units 100 located on the inverted arch steel frames 6 are the deformation and compression resistance units of the inverted arch. Compression unit; after the tunnel invert is excavated, the bottom plate will be under pressure and cause deformation stress of the bottom bulge. Therefore, support should be provided in time to avoid inducing displacement or deformation of the initial support of the upper tunnel body; by setting the size, compressive deformation amount and installation position of the deformation compression unit 100, after the installation of the deformation compression unit 100 is completed, the stress caused by the deformation and bulge of the invert bottom plate can be effectively absorbed and resolved, avoiding stress concentration, inducing excessive deformation and bulge pressure of the invert bottom plate, and improving the stability of the initial support.
[0044] Wherein, the deformation and compression resistance unit 100 comprises:
[0045] A pair of supports 11 are arranged at intervals along the curvature direction of the tunnel section, and both ends of each support 11 are fixed to two adjacent steel arch frames 3 or two adjacent inverted arch steel frames 6; the support 11 is used to support and fix the transformer, and the support 11 is connected to the steel arch frame 3 and can be connected to the steel arch frame 3 as a whole to effectively utilize the supporting force of the steel arch frame 3.
[0046] A pair of transformers, the pair of transformers are respectively fixed on a pair of supports 11, the transformers include a base 12 fixed to the support 11, a cylinder 13 fixed to the base 12, and a shift rod 14 sealed and slidably arranged on the cylinder 13; wherein the base 12 is provided with a plurality of independent micro-accommodating cavities 15, one end of the micro-accommodating cavities 15 is connected to the cylinder 13, and a pressure valve 16 is provided at the connection point, the shift rod 14 is located in the cylinder 13, and the gap between the end of the shift rod 14 and the end surface of the cylinder 13 is arranged, and is filled with hydraulic oil 17, the shift rod
[0047] 14 is located in the other end of the cylinder 13 and is provided with a limit part 18, and is in contact with the end face of the cylinder 13 away from the hydraulic oil 17; the transformer is used to bear and absorb and resolve the surrounding rock stress; the specific principle is: when the pressure on the displacement rod 14 (towards the end of the hydraulic oil 17 in the cylinder 13, when the cylinder 13 faces different directions, the main direction of absorbing stress is different) reaches a certain value, the pressure valve 16 opens, and a part of the hydraulic oil 17 in the cylinder 13 is pressed into and filled in the micro-accommodation cavity 15, and the displacement rod 14 moves a certain distance, that is, a certain displacement is generated, thereby absorbing and resolving the surrounding rock deformation stress. The pressure at which the pressure valve 16 opens is determined according to the surrounding rock characteristics. A plurality of micro-accommodation cavities 15 and different pressure valves 16 are provided to cope with different degrees of surrounding rock deformation stress.
[0048] A pair of stress adapting rods 19, the pair of stress adapting rods 19 are respectively connected to a pair of displacement rods 14 and are located in the cylinder body 13
[0049] One end outside is hinged, and the stress adaptation rod 19 is arc-shaped; although it is a hinged connection, since the entire deformation compression unit 100 is embedded in the concrete layer, the rotational displacement that can occur is very small, but even a small rotational displacement can adapt to the direction of the surrounding rock stress, and the stress adaptation rod 19 is connected to the displacement rod 14, so the change of direction can be transmitted to the displacement rod 14, thereby improving the stress resolution efficiency of the transformer.
[0050] The two ends of the pressure-bearing middle rod 10 are respectively hinged to the other ends of a pair of stress adapting rods 19, and the pressure-bearing middle rod 10 is arc-shaped; since the direction of the surrounding rock deformation stress is random, but the overall stress is transmitted downward to the arch and from the side waist to the inside,
[0051] As well as transmitting from the bottom upward, the pressure-bearing middle rod 10 is provided to guide the transmission of the above stress to decompose the stress, and at the same time, it has a more stable supporting force effect on the arch crown, side waist and bottom of the invert arch after the deformation stress of the surrounding rock is resolved.
[0052] Since the direction of the surrounding rock deformation stress is random, but is generally transmitted downward to the arch, inward from the side waist, and upward from the bottom, a deformation compression unit 100 is set at the corresponding position.
[0053] The inverted arch secondary lining 9 is arranged on the inverted arch sprayed concrete layer 7;
[0054] The tunnel secondary lining 8 is arranged on the tunnel secondary sprayed concrete layer 4. The invert secondary lining 9 and the tunnel secondary lining 8 are formed by conventional lining methods.
[0055] In the above technical scheme, the size, compressive deformation amount and installation position of the deformation and compression resistant unit 100 are set on the existing support structure according to the calculated settlement amount. After the installation of the deformation and compression resistant unit 100 is completed, the stress caused by the deformation and settlement of the surrounding rock can be effectively absorbed and resolved, avoiding stress concentration and inducing excessive surrounding rock pressure, and the stress caused by the deformation and uplift of the arch bottom plate can be effectively absorbed and resolved, avoiding stress concentration and inducing excessive deformation and uplift pressure of the arch bottom plate; at the same time, after the deformation stress of the surrounding rock and the deformation and uplift of the arch bottom plate are resolved, the arch crown, side waist and arch bottom have a more stable supporting force effect, thereby improving the initial support stability.
[0056] In another technical solution, the spacing between a pair of supports 11 of the cave roof deformation compression unit is set to be within an arc range of 45° on both sides above the center line of the tunnel section, and the center of the corresponding pressure-bearing middle rod 10 deviates from the arc range of 15° on both sides of the center line of the tunnel section;
[0057] The spacing between the pair of supports 11 of the tunnel waist deformation compression unit is set to be within an arc range of 15° downward and 30° upward from the horizontal line of the center of the tunnel section;
[0058] The spacing between a pair of supports 11 of the invert deformation compression-resistant unit is set to be within an arc range of 60° on both sides below the center of the tunnel section.
[0059] In the above technical scheme, since the direction of the deformation stress of the surrounding rock is regular in the general direction, only some branch stresses are randomly generated, that is, the overall stress is transmitted downward to the arch, from the side waist to the inside, and from the bottom to the top. Therefore, controlling the installation position of the cave roof deformation compression unit, the cave waist deformation compression unit and the inverted arch deformation compression unit can effectively absorb the surrounding rock deformation stress.
[0060] In another technical solution, the fixed positions of a pair of supports 11 of two adjacent deformation compression units 100 along the longitudinal direction of the tunnel, the hinge positions of the transformer and the stress adaption rod 19, and the hinge positions of the stress adaption rod 19 and the pressure-bearing middle rod 10 are all staggered. After the surrounding rock deformation is completed, the staggered setting is conducive to improving the rigidity of the overall support, and also has a better ability to absorb and resolve some randomly generated branch stresses.
[0061] In another technical solution, the valve opening pressure of the pressure valve 16 corresponding to the plurality of micro-accommodating chambers 15 increases in sequence, and the volume of each micro-accommodating chamber 15 is set as follows: when the pressure valve 16 reaches the preset valve opening pressure, the hydraulic oil 17 enters and fills the micro-accommodating chamber 15 under the pressure of the shift rod 14, and the distance that the shift rod 14 extends toward the cylinder body 13 is 0.1-0.2mm. Usually, when the surrounding rock settlement rate or the surrounding displacement rate is less than 0.1-0.2mm / d, it means that the surrounding rock is relatively stable, so the one-time displacement distance of the shift rod 14 cannot be greater than 0.2mm to avoid giving way too much and disturbing the original stability of the surrounding rock.
[0062] The present invention provides a supporting method of a supporting structure for controlling deformation of tunnel surrounding rock, comprising the following steps:
[0063] S1. After the tunnel portal pipe shed is erected, advance support is applied;
[0064] S2, excavate a tunnel of a certain length, spray concrete along the rock surface of the tunnel body to form an initial concrete layer 2 of the tunnel body, then hang a steel mesh, splice the steel arch frame 3 according to the designed shape, and when the initial concrete layer 2 of the tunnel body reaches the designed strength, install the steel arch frame 3 to the initial concrete layer 2 of the tunnel body at a certain interval, and then install and fix the top deformation compression unit and the waist deformation compression unit according to the designed position, connect and fix two adjacent steel arch frames 3 through multiple steel bars, spray concrete to cover, and form a tunnel body sprayed concrete layer 4, and when the tunnel body sprayed concrete layer 4 reaches the designed strength, the initial support of the tunnel body is completed;
[0065] S3, excavate an inverted arch of a certain length, spray concrete along the inverted arch groove surface to form an inverted arch initial concrete layer 5, when the inverted arch initial concrete layer 5 reaches the design strength, splice, install, and fix the inverted arch steel frame 6 to the inverted arch initial concrete layer 5 according to the design shape, install and fix the inverted arch deformation compression unit according to the design position, connect and fix two adjacent inverted arch steel frames 6 by a plurality of steel bars, spray concrete to cover, form an inverted arch sprayed concrete layer 7, and when the inverted arch sprayed concrete layer 7 reaches the design strength, complete the inverted arch initial support;
[0066] S4, construct the secondary lining of the inverted arch 9;
[0067] S5, construct the secondary lining of the tunnel body 8;
[0068] S6. Repeat steps S1 to S6 to complete the support of the surrounding rock of the entire tunnel.
[0069] In the above technical scheme, the side slope is excavated by open excavation method, and the excavation is carried out step by step from top to bottom, and the steps for entering the cave are reserved. After the side slope is excavated, anchor spraying and hanging nets are used for protection in time; then the large pipe shed support is carried out in advance of the tunnel entrance, and the sleeve arch construction method can be adopted, that is, the tunnel entrance position is constructed and laid out, and then the core soil is reserved on the upper step, and the sleeve arch construction is carried out. The length of the sleeve arch (in the length direction of the tunnel body) should not be less than 2m. According to the angle and position of the design drawing, the guide pipe is welded and fixed to the sleeve arch, wherein the external insertion angle is 1 to 3°; then the sleeve arch formwork and concrete pouring construction are carried out, and when the concrete curing reaches the design strength, the large pipe shed support in advance of the tunnel entrance is completed;
[0070] To construct advance support 1, first adjust and determine the grouting radius, grouting pressure and single-tube grouting amount by test, and then use the guide tube on the drilling rig to drill a hole. The borehole diameter is 20-30mm larger than the steel pipe (conduit). The length of the steel pipe depends on the thickness of the soft and broken surrounding rock, usually 20-30m. After the drilling is completed, use a high-pressure fan to clean up the residual slag in the hole to avoid pipe jamming during jacking; jack the steel pipe into the borehole. Specifically, the steel pipe can be a hot-rolled seamless steel pipe with a diameter of 108mm, a wall thickness of 6mm, and a section length of 4m or 6m. The pipe mouth section is 2.5m without a hole, the longitudinal spacing of the steel pipe is 15-20cm, the circumferential spacing is 9-12cm, and the grouting holes are arranged in a plum blossom shape. The diameter of the grouting hole is 10mm. The two sections of the steel pipe can be spliced by threaded connection, and the splicing length is not less than 1 5cm, when splicing, control the number of joints in the same section to be less than 50% of the number of steel pipe rows; then push the spliced steel pipes into the designed position in the borehole in turn, use high-pressure air to clear the residual slag in the pipe, and then place a steel cage into the steel pipe, and then use a grouting plug to seal the gap between the steel pipe and the hole wall, and pre-embed the exhaust hole, and then use a steel plate (with a round hole in the middle) to cover the steel pipe mouth, and weld the grouting conduit, and then use a grouting pump to press the slurry (concrete) into the hole, and close the grouting with pressure for more than 10 minutes. The grouting pressure is set to 0.5-1.0MPa to ensure that the slurry can quickly penetrate into the surrounding rock gaps. When slurry is discharged from the exhaust hole, the grouting pressure is changed to 2.0MPa, and grouting is continued until the designed grouting volume is reached. When the slurry strength reaches 70%, the next process can be executed, and the advanced support 1 is completed.
[0071] For the initial support of the tunnel body, after the excavation of the upper steps of the tunnel is completed, the rock surface is sealed with the initial spraying of concrete in time, and the thickness of the concrete layer is 4 to 6 cm. Then, anchor rods are installed in time, and concrete is sprayed again to the designed thickness. Then, a steel mesh is hung, and the gap between the steel mesh and the sprayed surface is 2 to 3 cm. A steel support (steel arch frame 3) is erected, and a hole position for drilling an advanced small conduit is opened in the middle of the web of the steel arch frame 3 according to the preset position. The hole diameter is 3 to 5 mm larger than the diameter of the advanced small conduit. A locking foot anchor rod is driven at the bottom of the steel support. According to the analysis of the reserved settlement amount based on the surrounding rock level and the monitoring measurement data, the installation position is set on the steel support in advance, and then The cave roof deformation compression unit and the cave waist deformation compression unit are installed and fixed accordingly, and the longitudinal connecting ribs are welded to connect and fix the two adjacent longitudinal steel supports; drill holes outward from the drilling hole position at an external insertion angle of 10 to 30°, clean up the residual slag, and drive in an advance small conduit. The specific diameter of the advance small conduit is 4.2cm, the wall thickness is 4mm, and the length is 4.5m. It is made of hot-rolled seamless steel pipe; grouting is injected into the advance small conduit, the initial grouting pressure is 0.5 to 1.0MPa, and the final pressure is appropriately increased and maintained for a certain time (about 15min). After the slurry strength reaches a certain strength, concrete is sprayed again to completely cover the steel support.
[0072] The initial support of the inverted arch is performed. After the excavation of the lower step of the tunnel (i.e., the inverted arch section) is completed, water, ballast and other debris are removed, a 5-10 cm thick concrete cushion is laid, and an inverted arch steel frame 6 is installed. The installation position is pre-set on the inverted arch steel frame 6, and then the inverted arch deformation compression unit is correspondingly installed and fixed. The inverted arch steel frame 6 is connected and fixed by connecting bars, and then concrete is sprayed to the designed thickness. When the designed hardness is reached, the initial support construction of the inverted arch is completed. The secondary lining 9 of the inverted arch is performed. After the initial support of the inverted arch is completed, the second lining steel bars of the inverted arch are tied in time. The construction joints and deformation joints of the inverted arch and the bottom of the paving are waterproofed with waterproof tape according to the design requirements, and the formwork is erected to pour the inverted arch concrete and the bottom of the paving concrete.
[0073] Construct the secondary lining of the tunnel body 8. When the vault sinking rate is less than 0.15mm / d and the displacement rate of the surrounding rock is less than 0.2mm / d, the secondary lining construction can be carried out; waterproof panels are laid on the surface of the tunnel body, and arched steel bars are tied and rolled. A trolley is used for construction, and the end formwork is installed. Then, concrete is poured. After the preset strength is reached, the formwork is removed for maintenance. Specifically, a trolley with functions such as automatic material distribution, vault pouring, and automatic alarm can be used.
[0074] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. A support structure for controlling deformation of tunnel surrounding rock, characterized in that: include: Advanced support, which is support before tunnel excavation; The initial support of the tunnel body is the support after the tunnel body is excavated, and the initial support of the tunnel body includes an initial concrete layer of the tunnel body sprayed along the rock surface of the tunnel body, multiple anchor rod layers driven along the initial concrete layer of the tunnel body, a steel mesh hung and fixed on the initial concrete layer of the tunnel body, multiple steel arch frames erected near the steel mesh, multiple deformation and compression units arranged between two adjacent steel arch frames, and a tunnel body sprayed concrete layer formed by spraying and covering the steel arch frames, the steel mesh and the deformation and compression units; wherein the multiple deformation and compression units are respectively a tunnel top deformation and compression unit located at the arc top of the steel arch frame and a tunnel waist deformation and compression unit located at the side waist of the steel arch frame; The initial support of the inverted arch is the support after the excavation of the inverted arch section, and the initial support of the inverted arch comprises an initial concrete layer of the inverted arch formed by spraying along the inverted arch groove surface, a plurality of inverted arch steel frames arranged on the initial concrete layer of the inverted arch, the deformation and compression resistance units arranged on two adjacent inverted arch steel frames, and an inverted arch sprayed concrete layer formed by spraying and covering the inverted arch steel frames and the deformation and compression resistance units; wherein the deformation and compression resistance units located on the inverted arch steel frames are deformation and compression resistance units of the inverted arch; Wherein, each deformation compression unit includes: A pair of supports, a pair of supports are arranged at intervals along the curvature direction of the tunnel section, and both ends of each support are fixed to two adjacent steel arch frames or two adjacent inverted arch steel frames; A pair of transformers, the pair of transformers are respectively fixed on a pair of supports, the transformers include a base fixed to the supports, a cylinder body fixed to the base, and a shifting rod sealed and slidably arranged on the cylinder body; wherein a plurality of independent micro-accommodating chambers are provided in the base, one end of the micro-accommodating chamber is connected to the cylinder body, and a pressure valve is provided at the connection point; the shifting rod is provided in a gap between one end of the cylinder body and the end face of the cylinder body, and the gap is filled with hydraulic oil; the other end of the shifting rod is provided with a limiting portion and abuts against the end face of the cylinder body away from the hydraulic oil; A pair of stress adaptation rods, the pair of stress adaptation rods are respectively hinged to one end of a pair of displacement rods located outside the cylinder body, and the stress adaptation rods are arc-shaped; A pressure-bearing middle rod, both ends of which are respectively hinged to the other ends of a pair of stress-adapting rods, and the pressure-bearing middle rod is arc-shaped; an inverted arch secondary lining, which is arranged on the inverted arch sprayed concrete layer; The secondary lining of the tunnel body is arranged on the sprayed concrete layer of the tunnel body.
2. The support structure for controlling deformation of tunnel surrounding rock according to claim 1, characterized in that: The spacing between a pair of supports of the cave roof deformation compression unit is set to be within an arc range of 45° on both sides above the center line of the tunnel section, and the center of the corresponding pressure-bearing middle rod deviates from the arc range of 15° on both sides of the center line of the tunnel section; The spacing between a pair of supports of the tunnel waist deformation compression resistance unit is set to be within an arc range of 15° downward and 30° upward from the horizontal line of the center of the tunnel section; The spacing between a pair of supports of the invert deformation compression-resistant unit is set to be within an arc range of 60° on both sides below the center of the tunnel section.
3. The support structure for controlling deformation of tunnel surrounding rock according to claim 2, characterized in that: The fixed positions of a pair of supports of two adjacent deformation compression units along the longitudinal direction of the tunnel, the hinged positions of the pressure transformer and the stress adaptation rod, and the hinged positions of the stress adaptation rod and the pressure-bearing middle rod are all staggered.
4. The support structure for controlling deformation of tunnel surrounding rock according to claim 1, characterized in that: The valve opening pressures of the pressure valves corresponding to the multiple micro-containing chambers increase successively, and the volume of each micro-containing chamber is set as follows: when the pressure valve reaches a preset valve opening pressure, the hydraulic oil enters and fills the micro-containing chamber under the pressure of the shift rod, and the distance that the shift rod moves toward the cylinder body is 0.1 to 0.2 mm.
5. A supporting method for controlling deformation of tunnel surrounding rock according to any one of claims 1 to 4, characterized in that: The following steps are involved: S1. After the tunnel portal pipe shed is erected, advance support is applied; S2. Excavate a tunnel of a certain length, spray concrete along the rock surface of the tunnel body to form an initial concrete layer of the tunnel body, then hang a steel mesh, splice the steel arch frame according to the designed shape, and when the initial concrete layer of the tunnel body reaches the designed strength, install the steel arch frame to the initial concrete layer of the tunnel body at a certain interval, and then install and fix the top deformation compression unit and the waist deformation compression unit according to the designed position. The two adjacent steel arch frames are connected and fixed by multiple steel bars, and sprayed with concrete to form a secondary sprayed concrete layer of the tunnel body. When the secondary sprayed concrete layer of the tunnel body reaches the designed strength, the initial support of the tunnel body is completed; S3, excavating an inverted arch of a certain length, spraying concrete along the inverted arch groove surface to form an initial concrete layer of the inverted arch, when the initial concrete layer of the inverted arch reaches the design strength, splicing, installing, and fixing the inverted arch steel frame to the initial concrete layer of the inverted arch according to the design shape, installing and fixing the inverted arch deformation compression unit according to the design position, connecting and fixing two adjacent inverted arch steel frames through multiple steel bars, spraying concrete to cover, forming an inverted arch sprayed concrete layer, and when the inverted arch sprayed concrete layer reaches the design strength, the initial support of the inverted arch is completed; S4, construct the secondary lining of the inverted arch; S5. Construct secondary lining of the tunnel body; S6. Repeat steps S1 to S6 to complete the support of the surrounding rock of the entire tunnel.