Building electromechanical prefabricated machine room pipeline segmenting method

By obtaining and splitting pipeline information, building polygonal contours and generating segmented cutting points, the problems of inconsistent logic and high cost of pipeline segmented segmented segmented segmented segmented segmented segmented and sectioned segmented and prefabricated assembly efficiency is achieved. promote.

CN118940480AActive Publication Date: 2024-11-12HUBEI CONSTR ENG TECH CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410953344.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-11-12
Estimated Expiration
2044-07-16

AI Technical Summary

Technical Problem

The existing construction electromechanical prefabricated prefabricated pipeline segmentation and sectioning methods have different connection methods and manual segmentation logic, the conflict between pipeline nodes during automatic segmentation affects the length of a single pipe segment, and the failure to consider multiple prefabricated processing forms, resulting in higher costs. .

Method used

By obtaining pipeline information, the pipeline route is extracted and split into pipelines in the xy direction, xz direction, and yz direction, the polygon range outline is constructed, non-90-degree inflection points are identified to generate contour segmented split points, and decompose them into rectangles according to the inflection points, considering pipe fittings Length and welding length generate segmented cutting points, adaptively adjust rectangular boxes to avoid conflicts, and complete pipeline segmentation.

Benefits of technology

The batch-based pipeline segmentation and sectioning is realized, which improves efficiency, and takes into account transportation conditions during the segmentation process, meets the requirements of the construction site and prefabricated processing site, and improves the prefabricated assembly efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118940480A_ABST
    Figure CN118940480A_ABST
Patent Text Reader

Abstract

The invention discloses a rapid segmentation method for building electromechanical prefabricated machine room pipelines, which comprises the following steps of: extracting pipeline information to form a data structure of vertexes and edges, simulating each edge into a rectangular range frame outline according to a pipeline transportation width, and analyzing a difference value between the length of each edge and the transportation width when the range frame outline is formed; decomposing the elbow into a plurality of rectangular frames and parallelogram range frames, cutting the plurality of rectangular frames formed in the previous step to obtain a plurality of standardized segmented rectangular frame results, and cutting the rectangular frames when cutting the rectangular frames; and generating a pipeline cutting vertex according to a rectangular frame cutting result obtained in the previous step, and obtaining a pipeline segmentation model. The method has the beneficial effects that the sectioning step of the pipeline of the building electromechanical prefabricated machine room can be simplified, the sectioned pipeline meeting the requirement is automatically generated, a user can quickly obtain the sectioned pipeline of the prefabricated machine room by setting related parameters such as the transportation length, the transportation width and the minimum welding length, and the deepening design efficiency of the prefabricated machine room is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of in-depth design of building electromechanical pipelines, in particular to a method for segmenting and dividing pipelines in a building electromechanical prefabricated machine room. Background Art

[0002] The construction industry is a pillar industry of the national economy. Construction industrialization is an inevitable trend for the construction industry to move towards high-quality development. With the vigorous development of the construction industrialization industry, the industrialized installation and construction of building mechanical and electrical equipment faces new challenges.

[0003] The characteristics of electromechanical engineering and the concept of industrialized production and processing of components have led to the development of prefabricated electromechanical pipeline production lines. The processing equipment and processes used in previous construction sites have been integrated, optimized, and combined to form complete sets of standard processing and production equipment that meet different installation needs, and intelligent production capabilities have been formed through industrial control programs and factory digital management platforms.

[0004] For example, a Chinese patent discloses an information processing device for layout detection of assembled electromechanical pipelines (publication number: CN110737684B), which includes a position sensor and a first acquisition unit to obtain the routing information of the electromechanical pipelines; a second acquisition unit to obtain the routing layout diagram of the electromechanical pipelines; a third acquisition unit to obtain the attribute information of the electromechanical pipelines; and a fourth acquisition unit to obtain the routing standard information of the electromechanical pipelines. Based on the thinking of the industrialization of electromechanical installation, the Revit electromechanical model completed by the in-depth design is combined with the civil engineering conditions for comprehensive analysis. Through the function settings of automatic segmentation, automatic numbering, automatic export of engineering quantities, and automatic processing drawings and assembly drawings, the transformation from the design model to the factory prefabrication format and the seamless connection from factory prefabrication to on-site assembly are completed. Ultimately, it ensures that the design results can be prefabricated in the factory, easy to transport in the middle, and easy to install on site, providing strong support for improving efficiency and benefits in the electromechanical field.

[0005] At present, mechanical and electrical components of buildings need to be segmented and divided into sections manually according to professional drawings before being produced in the list processing equipment. The existing segmentation methods are: one is that the user manually arranges the segmentation points, and the other is to use software to generate segmentation sections from the pipeline segments in the mechanical and electrical drawings, and split all the straight pipe sections on the drawing. Although the second method has a certain degree of automation, it still has the following problems:

[0006] (1) Different connection methods have the same segmentation method, which is inconsistent with the logic of manual segmentation method;

[0007] (2) During automatic segmentation, when a segment conflicts with a pipeline node, only the length of a single pipeline segment is affected;

[0008] (3) Various prefabrication processing forms were not considered during segmentation, and the types of segment accessories were too many and complex, resulting in high costs.

[0009] Therefore, it is necessary to propose a method for segmenting and dividing the pipelines of the building mechanical and electrical prefabricated room to solve the above problems. Summary of the invention

[0010] In view of the above-mentioned deficiencies in the prior art, the object of the present invention is to provide a method for segmenting and dividing pipelines in a prefabricated mechanical and electrical room of a building to solve the above-mentioned problems.

[0011] A method for segmenting and dividing pipelines in a building electromechanical prefabricated room, the method steps are as follows:

[0012] S1. Obtain pipeline information, extract pipeline routes from the pipeline information, and further split them into pipelines in the xy direction, xz direction, and yz direction. The riser is classified as the xz direction pipeline.

[0013] S2, analyzing the pipelines in the xy direction, xz direction, and yz direction obtained in step S1, taking the pipeline centerline as the rectangular outline centerline and the pipeline transportation width D1 as the rectangular outline width, and constructing a polygonal range outline;

[0014] S3, identifying the non-90-degree contour inflection point of the polygon range contour obtained in step S2, generating contour segmentation splitting points along the pipeline at the position of the inflection point that is the sum of the pipe length L3 and the minimum welding length L2 of the pipe section, and splitting the polygon formed thereby;

[0015] S4, identifying the polygon inflection points of the polygonal outline obtained in step S3 after splitting, and decomposing it into N rectangles according to the inflection points;

[0016] S5. The N rectangles obtained in step S5 are divided into sections and cut at the elbows, tees, crosses, etc. according to the distance between the center point of the pipe fitting and the sum of the pipe fitting length L3 and the minimum welding length L2 of the pipe section.

[0017] S6. Use the standard segmented rectangular frame formed by the pipeline transportation length L1 and the width D1 to segment the M rectangles obtained in step S4. When segmenting, adaptive adjustment should be made at the segmented cutting points generated in step S5. That is, when the segmented position of the standard segmented rectangular frame conflicts with the elbow, tee, cross, etc., the segmented rectangular frame should be reduced to form a rectangular segmented frame at the segmented cutting point, and the length is shortened from L1 to L1-x, where x is the distance between the conflicting point and the segmented cutting point.

[0018] S7. The rectangular segmentation frame position formed in step S6 is matched with each pipeline segment, and a pipeline segment segmentation point is generated at a corresponding position in the pipeline segment to complete the pipeline segmentation.

[0019] Step S1 extracts the pipeline route from the pipeline information, which refers to obtaining the pipeline center line from the building mechanical and electrical pipeline plan drawing or BIM model, wherein the pipeline center line obtained from the plan drawing is a plane line, and the pipeline center line obtained from the BIM model is a three-dimensional line.

[0020] The further splitting of step S1 refers to the pipeline center line obtained from the BIM model as a three-dimensional line, which needs to be split into plane lines to form pipelines in the xy direction, xz defense line, and yz direction. The vertical lines are classified as xz direction lines. When splitting, attention should be paid to the connection nodes, and it should be ensured that the distance L4 between the splitting point and the connecting pipe is greater than or equal to the minimum welding length L2 of the pipe section.

[0021] The rectangular outline in step S2 is constructed into a polygonal outline by taking the pipeline centerline as the rectangle centerline and the pipeline transportation width D1 as the rectangle width.

[0022] The contour segmentation splitting point in step S3 is at the inflection point where the pipeline centerline is not 90 degrees. Along the pipeline centerline, two inflection segmentation splitting points are generated at the sum of the pipe length L3 at the inflection point and the minimum welding length L2 of the pipe section; the polygon formed by this is a splicing figure of a parallelogram and a rectangle;

[0023] After the polygon outline in step S3 is split for the first time, the remaining Z figures should be polygons formed by splicing rectangles;

[0024] In step S4, each obtained polygonal contour is identified, the inflection point of each contour is identified, and the rectangles in other short-side directions are split based on the long side direction of the largest rectangular bounding box of the polygonal contour, and the rectangles whose shortest sides are less than the pipeline transportation width D1 / 2 are removed; when splitting rectangles in other short-side directions, segmentation cutting points should be generated at the splitting points, and the segmentation points are the intersection points of the split rectangles and the center line of the pipeline. If they do not intersect, the rectangles should be ignored;

[0025] In step S5, segment cutting marking points are generated along the length of the pipeline at a position where the distance from the center point of the pipe to the sum of the pipe length L3 and the minimum welding length L2 of the pipe segment is greater than or equal to the length of the pipe.

[0026] In step S6, when the segmentation position of the standard segmented rectangular frame conflicts with the elbow, tee, cross, etc., the size of the current standard rectangular frame should be modified, and its conflicting position should be reduced to the nearest segment cutting mark point, and the starting point of the next segment of the standard rectangular frame segment is updated to the segment cutting mark point.

[0027] The intersection of the segmentation frame and each pipeline segment in step S7 and the rectangle splitting point in step S4 are the pipeline segment splitting points.

[0028] Compared with the prior art, the present invention has the following beneficial effects:

[0029] (1) The present invention can batch-wise segment and section the pipelines of mechanical and electrical prefabricated machine rooms, thereby increasing efficiency;

[0030] (2) The present invention considers the limiting factors of transportation conditions while dividing the sections, meets the sectioning requirements of the construction site and the prefabrication processing site, and improves the prefabrication and assembly efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a flow chart of the method for segmenting and dividing pipelines in a building electromechanical prefabricated room of the present invention;

[0032] Figure 2 A flowchart of obtaining a polygon range outline of the present invention;

[0033] Figure 3 A flowchart of the present invention for splitting after obtaining polygon outlines;

[0034] Figure 4 It is a flowchart of using a standard rectangular frame to segment the split result of the present invention;

[0035] Figure 5 It is a schematic diagram of determining the pipeline splitting point of the present invention. DETAILED DESCRIPTION

[0036] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments may be combined with each other.

[0037] The embodiments of the present invention are described in detail below with reference to the accompanying drawings, but the present invention can be implemented in many different ways as defined and covered by the claims.

[0038] like Figure 1 Combined with Figures 2 to 5 As shown, a method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room is provided, and the method steps are as follows:

[0039] S1. Obtain pipeline information, extract pipeline routes from the pipeline information, and further split them into pipelines in the xy direction, xz direction, and yz direction. The riser is classified as the xz direction pipeline.

[0040] S2, analyzing the pipelines in the xy direction, xz direction, and yz direction obtained in step S1, taking the pipeline centerline as the rectangular outline centerline and the pipeline transportation width D1 as the rectangular outline width, and constructing a polygonal range outline;

[0041] S3, identifying the non-90-degree contour inflection point of the polygon range contour obtained in step S2, generating contour segmentation splitting points along the pipeline at the position of the inflection point that is the sum of the pipe length L3 and the minimum welding length L2 of the pipe section, and splitting the polygon formed thereby;

[0042] S4, identifying the polygon inflection points of the polygonal outline obtained in step S3 after splitting, and decomposing it into N rectangles according to the inflection points;

[0043] S5. The N rectangles obtained in step S5 are divided into sections and cut at the elbows, tees, crosses, etc. according to the distance between the center point of the pipe fitting and the sum of the pipe fitting length L3 and the minimum welding length L2 of the pipe section.

[0044] S6. Use the standard segmented rectangular frame formed by the pipeline transportation length L1 and the width D1 to segment the M rectangles obtained in step S4. When segmenting, adaptive adjustment should be made at the segmented cutting points generated in step S5. That is, when the segmented position of the standard segmented rectangular frame conflicts with the elbow, tee, cross, etc., the segmented rectangular frame should be reduced to form a rectangular segmented frame at the segmented cutting point, and the length is shortened from L1 to L1-x, where x is the distance between the conflicting point and the segmented cutting point.

[0045] S7. The rectangular segmentation frame position formed in step S6 is matched with each pipeline segment, and a pipeline segment segmentation point is generated at a corresponding position in the pipeline segment to complete the pipeline segmentation.

[0046] Step S1 extracts the pipeline route from the pipeline information, which refers to obtaining the pipeline center line from the building mechanical and electrical pipeline plan drawing or BIM model, wherein the pipeline center line obtained from the plan drawing is a plane line, and the pipeline center line obtained from the BIM model is a three-dimensional line.

[0047] The further splitting of step S1 refers to the pipeline center line obtained from the BIM model as a three-dimensional line, which needs to be split into plane lines to form pipelines in the xy direction, xz defense line, and yz direction. The vertical lines are classified as xz direction lines. When splitting, attention should be paid to the connection nodes, and it should be ensured that the distance L4 between the splitting point and the connecting pipe is greater than or equal to the minimum welding length L2 of the pipe section.

[0048] The rectangular outline in step S2 is constructed into a polygonal outline by taking the pipeline centerline as the rectangle centerline and the pipeline transportation width D1 as the rectangle width.

[0049] The contour segmentation splitting point in step S3 is at the inflection point where the pipeline centerline is not 90 degrees. Along the pipeline centerline, two inflection segmentation splitting points are generated at the sum of the pipe length L3 at the inflection point and the minimum welding length L2 of the pipe section; the polygon formed by this is a splicing figure of a parallelogram and a rectangle;

[0050] After the polygon outline in step S3 is split for the first time, the remaining figure should be a polygon formed by splicing rectangles;

[0051] In step S4, each obtained polygonal contour is identified, the inflection point of each contour is identified, and the rectangles in other short-side directions are split based on the long side direction of the largest rectangular bounding box of the polygonal contour, and the rectangles whose shortest sides are less than the pipeline transportation width D1 / 2 are removed; when splitting rectangles in other short-side directions, segmentation cutting points should be generated at the splitting points, and the segmentation points are the intersection points of the split rectangles and the center line of the pipeline. If they do not intersect, the rectangles should be ignored;

[0052] In step S5, segment cutting marking points are generated along the length of the pipeline at a position where the distance from the center point of the pipe to the sum of the pipe length L3 and the minimum welding length L2 of the pipe segment is greater than or equal to the length of the pipe.

[0053] In step S6, when the segmentation position of the standard segmented rectangular frame conflicts with the elbow, tee, cross, etc., the size of the current standard rectangular frame should be modified, and its conflicting position should be reduced to the nearest segment cutting mark point, and the starting point of the next segment of the standard rectangular frame segment is updated to the segment cutting mark point.

[0054] The intersection of the segmentation frame and each pipeline segment in step S7 and the rectangle splitting point in step S4 are the pipeline segment splitting points.

[0055] Compared with the prior art, the present invention has the following beneficial effects:

[0056] (1) The present invention can batch-wise segment and section the pipelines of mechanical and electrical prefabricated machine rooms, thereby increasing efficiency;

[0057] (2) The present invention considers the limiting factors of transportation conditions while dividing the sections, meets the sectioning requirements of the construction site and the prefabrication processing site, and improves the prefabrication and assembly efficiency.

[0058] Extracting the pipeline route from the pipeline information in step S1 refers to obtaining the pipeline center line from the building mechanical and electrical pipeline plane drawing or the BIM model, wherein the pipeline center line obtained from the plane drawing is a plane line, and the pipeline center line obtained from the BIM model is a three-dimensional line;

[0059] Step S1 is further split, which means that the pipeline center line obtained from the BIM model is a three-dimensional line, which needs to be split into plane lines to form pipelines in the xy direction, xz defense line, and yz direction, and the vertical line is classified as the xz direction line.

[0060] Step S1 is further split. When splitting, attention should be paid to the connection nodes. It should be ensured that the distance L4 between the split point and the connecting pipe is greater than or equal to the minimum welding length L2 of the pipe section.

[0061] The rectangular outline of step S2 is constructed into a polygonal outline by taking the pipeline centerline as the rectangle centerline and the pipeline transportation width D1 as the rectangle width;

[0062] The contour segmentation splitting point in step S3 is at the inflection point where the center line of the pipeline is not 90 degrees. Along the center line of the pipeline, two inflection segmentation splitting points are generated at the position where the distance from the inflection point pipe length L3 and the minimum welding length L2 of the pipe section are added;

[0063] Step S3 converts the formed polygon into a spliced ​​figure of a parallelogram and a rectangle;

[0064] After the polygon outline in step S3 is split for the first time, the remaining Z figures should be polygons formed by splicing rectangles;

[0065] In step S4, each obtained polygonal contour is identified, the inflection point of each contour is identified, and the rectangles in other short-side directions are split based on the long side direction of the largest rectangular bounding box of the polygonal contour, and the rectangles whose shortest sides are smaller than the pipeline transportation width D1 / 2 are removed;

[0066] In step S4, when splitting rectangles in other short-side directions, segmentation cutting points should be generated at the splitting locations. The segmentation points are the intersections of the split rectangle and the pipeline centerline. If they do not intersect, the rectangle should be ignored.

[0067] In step S5, segment cutting marking points are generated along the length of the pipeline at a position where the distance from the center point of the pipe fitting is the sum of the pipe fitting length L3 and the minimum welding length L2 of the pipe segment.

[0068] In step S6, when the segmentation position of the standard segmented rectangular frame conflicts with the elbow, tee, cross, etc., the size of the current standard rectangular frame should be modified, and its conflicting position should be reduced to the nearest segment cutting mark point, and the starting point of the next segment of the standard rectangular frame segment is updated to the segment cutting mark point.

[0069] In step S7, the intersection of the segmentation frame and each pipeline segment and the rectangle splitting point in step S4 are the pipeline segment splitting points.

[0070] This embodiment provides a storage medium having a computer program stored thereon. When the computer program is executed by a processor, the method for segmenting and dividing pipelines in a prefabricated mechanical and electrical machine room of a building considering transportation condition restrictions in the implementation manner is implemented.

[0071] The above description is only a preferred embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A method for segmenting pipelines in a building mechanical and electrical prefabricated room, characterized in that: The method steps are: S1. Obtain pipeline information, extract pipeline routes from the pipeline information, and further split them into pipelines in the xy direction, xz direction, and yz direction. The riser is classified as the xz direction pipeline; S2, analyzing the pipelines in the xy direction, xz direction, and yz direction obtained in step S1, taking the pipeline centerline as the rectangular outline centerline and the pipeline transportation width D1 as the rectangular outline width, and constructing a polygonal range outline; S3, identifying the non-90-degree contour inflection point of the polygon range contour obtained in step S2, generating contour segmentation splitting points along the pipeline at the position of the inflection point that is the sum of the pipe length L3 and the minimum welding length L2 of the pipe section, and splitting the polygon formed thereby; S4, identifying the polygon inflection points of the polygonal outline obtained in step S3 after splitting, and decomposing it into N rectangles according to the inflection points; S5, generating segmented cutting points at the elbow for the N rectangles obtained in step S5 according to the distance between the center point of the pipe fitting and the sum of the pipe fitting length L3 and the minimum welding length L2 of the pipe segment; S6. Use the standard segmented rectangular frame formed by the pipeline transportation length L1 and the width D1 to segment the M rectangles obtained in step S4. When segmenting, adaptive adjustment should be made at the segmented cutting point generated in step S5. That is, when the segmented position of the standard segmented rectangular frame conflicts with the elbow, the segmented rectangular frame should be reduced to form a rectangular segmented frame at the segmented cutting point, and the length is shortened from L1 to L1-x, where x is the distance between the conflicting point and the segmented cutting point. S7. The rectangular segmentation frame position formed in step S6 is matched with each pipeline segment, and a pipeline segment segmentation point is generated at a corresponding position in the pipeline segment to complete the pipeline segmentation.

2. A method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room as claimed in claim 1, characterized in that: Step S1 extracts the pipeline route from the pipeline information, which refers to obtaining the pipeline center line from the building mechanical and electrical pipeline plan drawing or BIM model, wherein the pipeline center line obtained from the plan drawing is a plane line, and the pipeline center line obtained from the BIM model is a three-dimensional line.

3. A method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room as claimed in claim 1, characterized in that: The further splitting of step S1 refers to the pipeline center line obtained from the BIM model as a three-dimensional line, which needs to be split into plane lines to form pipelines in the xy direction, xz defense line, and yz direction. The vertical lines are classified as xz direction lines. When splitting, attention should be paid to the connection nodes, and it should be ensured that the distance L4 between the splitting point and the connecting pipe is greater than or equal to the minimum welding length L2 of the pipe section.

4. A method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room as claimed in claim 1, characterized in that: The rectangular outline in step S2 is constructed into a polygonal outline by taking the pipeline centerline as the rectangle centerline and the pipeline transportation width D1 as the rectangle width.

5. A method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room as claimed in claim 1, characterized in that: The contour segmentation splitting point in step S3 is at the inflection point where the pipeline centerline is not 90 degrees. Along the pipeline centerline, two inflection point segmentation splitting points are generated at the position where the distance from the inflection point pipe length L3 and the minimum welding length L2 of the pipe section are equal; the polygon formed is a spliced ​​figure of a parallelogram and a rectangle.

6. A method for segmenting and dividing pipelines in a building electromechanical prefabricated room as claimed in claim 1, characterized in that: After the polygon outline in step S3 is split for the first time, the remaining figure should be a polygon formed by stitching rectangles.

7. A method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room as claimed in claim 1, characterized in that: In step S4, each obtained polygonal contour is identified, the turning point of each contour is identified, and the rectangles in other short-side directions are split based on the long side direction of the largest rectangular bounding box of the polygonal contour, and the rectangles whose shortest sides are less than the pipeline transportation width D1 / 2 are removed; when splitting rectangles in other short-side directions, segmentation cutting points should be generated at the splitting point, and the segmentation point is the intersection of the split rectangle and the center line of the pipeline. If they do not intersect, the rectangle should be ignored.

8. A method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room as claimed in claim 1, characterized in that: In step S5, segment cutting marking points are generated along the length of the pipeline at a position where the distance from the center point of the pipe to the sum of the pipe length L3 and the minimum welding length L2 of the pipe segment is greater than or equal to the distance from the center point of the pipe to the sum of the pipe length L3 and the minimum welding length L2 of the pipe segment.

9. A method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room as claimed in claim 1, characterized in that: In step S6, when the segment position of the standard segmented rectangular frame conflicts with the elbow, the size of the current standard rectangular frame should be modified, and its conflicting position should be reduced to the nearest segment cutting mark point, and the starting point of the next segment of the standard rectangular frame segment is updated to the segment cutting mark point.

10. A method for segmenting and dividing pipelines in a building mechanical and electrical prefabricated room as claimed in claim 1, characterized in that: The intersection of the segmentation frame and each pipeline segment in step S7 and the rectangle splitting point in step S4 are the pipeline segment splitting points.

Citation Information