Soft soil foundation efficient treatment method combining gas lift with surcharge preloading
By passing compressed gas into the bottom of the drainage plate, the hydrostatic pressure is zeroed and the cracking cracks are formed, the problem of long treatment time and poor effect of deep soft soil foundations in the prior art is solved, and the soil seepage consolidation is significantly improved Efficiency and deep consolidation pressure simplify the construction process.
Patent Information
- Application Number
- CN202411061835.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-15
AI Technical Summary
The prior art has a long processing time, poor effect, and large settlement after processing when dealing with deep soft soil foundations. The maximum vacuum negative pressure of the vacuum pre-pressure method is limited. The loading pre-pressure method requires applying pressure step by step to avoid slip instability. This results in insufficient driving force for seepage consolidation and limited effect.
By using the combined gas lifting loading prepression method, compressed gas and liquid flow are introduced into the bottom of the drainage plate to form a two-phase flow of gas and liquid, clearing the hydrostatic pressure of the drainage plate core, significantly increasing the seepage pressure difference between the plate and soil, and Cracking cracks form in the soil body, improving the soil permeability coefficient and consolidation efficiency.
The soil consolidation rate is significantly accelerated, the seepage consolidation efficiency of soil in loading pre-pressure is improved, especially in deep soil, the consolidation pressure is significantly increased, the construction process is simplified and post-process settlement is reduced.
Smart Images

Figure CN118958264A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of geotechnical engineering, and in particular relates to an efficient soft soil foundation treatment method of gas lift combined with pile loading preloading. Background Art
[0002] As a relatively developed economic region, the southeastern coastal areas of my country have been carrying out a large number of project construction in recent years. These areas are widely distributed with deep soft foundations (high-water content silty soft soil or dredger fill), and the thickness of some engineering soft soil layers (layers to be treated) can reach more than 20m. Foundation treatment must be carried out before engineering construction. Conventional methods for treating deep soft foundations are vacuum preloading, surcharge preloading, or vacuum combined surcharge preloading. Regardless of the method, it is necessary to build an additional drainage channel in the soil - the drainage board, and then apply negative pressure to the drainage board (vacuum preloading method) or apply upper surcharge positive pressure to the soil (surcharge preloading method), so as to promote the foundation pore water to seep to the drainage board and gather and finally discharge it to the surface, so as to achieve the effect of consolidating the foundation seepage and improving the strength.
[0003] However, existing methods often face problems such as long treatment time, poor treatment effect, and large post-construction settlement when dealing with deep soft soil foundations. The reason is that for the vacuum preloading method, the maximum vacuum negative pressure that can be provided is about 90kPa. Considering that the vertical attenuation of the vacuum pressure in the drainage board is 5-10kPa / m, the maximum effective treatment depth is about 10m. For the surcharge preloading method, considering the low initial strength of the deep soft soil, the surcharge pressure needs to be applied step by step, otherwise the foundation may experience overall sliding instability under the surcharge pressure.
[0004] Driven by the additional stress caused by the pile load, the pore water in the soft soil foundation will seep and gather toward the drainage board, and eventually flow upward to the surface along the core of the drainage board (the collection and flow process of water in the core of the drainage board is similar to the collection and water level rise process in the water collection well). However, as mentioned earlier, the initial pile load pressure is small, the driving force for the seepage consolidation of the soft soil is insufficient, and the foundation treatment effect is limited. Even if the pile load pressure is fully loaded in the later stage, the additional stress will naturally decay with the depth of the foundation (according to Busineske's answer), resulting in insufficient consolidation pressure of the soil deep in the drainage board, resulting in poor consolidation effect. Summary of the invention
[0005] In order to solve the above-mentioned technical problems existing in the prior art, and inspired by the increase in oil well gas lift production, the present invention provides an efficient soft soil foundation treatment method of gas lift combined with heap preloading, which empties the water stored in the drainage board in the heap preloading method by means of gas lift, clears the hydrostatic pressure of the drainage board core in a short time, and significantly increases the seepage pressure difference between the board and the soil; at the same time, splitting cracks can be formed in the soil around the board, shortening the radial drainage distance of the soil and increasing the permeability coefficient of the soil, thereby improving the seepage consolidation efficiency of the soil in heap preloading. In addition, in order to ensure that the positive pressure gas at the bottom of the plate has sufficient pressure or flow rate, the present invention also designs the routing of the gas lift pipeline, reduces the compression deformation of the gas lift pipeline under the slag heap, and ensures that the compressed gas passes smoothly in the gas lift pipeline during gas lift.
[0006] In order to improve the foundation treatment effect of conventional preloading, especially the seepage consolidation degree of the deep soil of the drainage board, the technical solution adopted by the present invention is:
[0007] An efficient treatment method for soft soil foundation by gas lift combined with preloading, which is suitable for preloading and drainage treatment of soft soil foundation, is characterized in that the treatment method comprises the following steps:
[0008] S1: Modify the drainage board;
[0009] Install a joint at the bottom of the drain board to connect the vent pipe;
[0010] S2: The ventilation pipe is connected to the joint at the bottom and is driven into the soft soil foundation together with the drainage board through a board driving machine;
[0011] S3: After all the drainage boards are driven into the soft soil foundation, lay the sand cushion layer;
[0012] S4: Lay the air lift pipeline on the sand cushion layer and connect it to the air compressor, and extend it from the air compressor to each drain board;
[0013] S5: Connect the gas lift pipeline to the vent pipe and lay two layers of non-woven fabric on the gas lift pipeline;
[0014] S6: The machinery enters the site and starts loading step by step, while air lifting is performed by intermittently turning on the air compressor.
[0015] Furthermore, in step S6, the specific process of gas lift is as follows:
[0016] The compressed gas generated by the air compressor is passed into the bottom of the drain board along the air lift pipeline, and the water stored in the core of the drain board is carried to the top in the form of air-water two-phase flow, thereby emptying the water stored in the core of the drain board, clearing the static water pressure of the core of the drain board, and increasing the seepage pressure difference between the board and the soil, thereby significantly increasing the consolidation pressure of the soil.
[0017] Furthermore, in step S6, during the preloading process, air lift ventilation can be intermittently adopted according to the load classification during loading, soil consolidation rate, pore water pressure of soil around the drain board, and water level rising speed in the drain board. The air lift operation interval is 6h / time to 24h / time.
[0018] The present invention uses gas lift to drain the water from the core of the drainage board to increase the consolidation pressure. The so-called "gas lift" is a process technology that uses the buoyancy principle of gas to lift liquid or solid particles. It injects gas into the pipeline to mix the gas with the liquid or particles to form a gas-liquid two-phase flow, thereby achieving the purpose of lifting the material upward.
[0019] The present invention introduces air lift pressurized gas of a certain pressure and flow rate from the bottom of the drain board. The gas flows upward along the core of the drain board, and during its flow, the water in the core of the drain board is carried upward until it is taken out of the drain board. The water in the core of the drain board is emptied by air lift, the hydrostatic pressure of the core of the drain board is cleared, and the seepage pressure difference between the board and the soil is increased, thereby significantly improving the consolidation pressure of the soil. During the introduction of the air lift pressurized gas, since the filter membrane on the surface of the drain board is permeable, while the water in the air lift board moves upward, a large amount of positive pressure gas will escape from the filter membrane in the drain board, and split cracks will be formed in the soil around the board, shortening the radial drainage distance of the soil and increasing the permeability coefficient of the soil, thereby accelerating the seepage speed of water in the soil, thereby effectively improving the efficiency of the consolidation of the preloaded soil.
[0020] Compared with the prior art, the beneficial effects of the present invention are as follows:
[0021] 1. The gas lift pressurization method of the present invention is very simple and can be operated on the ground; and the main devices and instruments are located on the upper part of the soil, which is easy to install and maintain, and can be widely promoted in engineering practice.
[0022] 2. After the preloading of the present invention is added with the air lift method, the soil consolidation rate can be accelerated at each load stage; and in the actual construction process, the traditional drainage board is easy to modify, the construction process is relatively simple, and the placement and positioning of the compressed gas pipeline are taken into consideration.
[0023] 3. The present invention empties the water stored in the drainage board in the preloading method by means of air lift, clears the hydrostatic pressure of the drainage board core in a short time, and significantly increases the seepage pressure difference between the board and the soil; at the same time, splitting cracks can be formed in the soil around the board, shortening the radial drainage distance of the soil and increasing the permeability coefficient of the soil, thereby improving the seepage consolidation efficiency of the soil in the preloading method.
[0024] 4. The present invention introduces positive pressure gas of a certain pressure and flow rate into the bottom of the drainage board through the gas lift pipeline, and the positive pressure gas drives the water in the core of the drainage board to be discharged to the surface in the form of gas-water two-phase flow. Once the water in the core of the board is emptied, the ventilation is stopped. At this time, the water head in the core of the board is zero, but the water head in the foundation around the drainage board is still the deadweight water head, which significantly increases the water head difference between the board and the soil, thereby significantly accelerating the seepage consolidation of the soft soil.
[0025] 5. In the present invention, when the foundation treatment depth is 20m, the hydrostatic pressure of the water in the board core at the bottom of the board can reach 200kPa. After the water in the board core is emptied by air lift, the hydrostatic pressure of the board core at the bottom of the board becomes 0kPa, while the hydrostatic pressure in the surrounding soil at the depth of the bottom of the board is still 200kPa. Obviously, a pressure difference of 200kPa is formed between the board and the soil, which can effectively accelerate the seepage and aggregation of pore water to the drainage board. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 This is a schematic diagram of the overall structure of the improved drainage board of the present invention.
[0027] Figure 2 It is an overall schematic diagram of the construction site of the present invention.
[0028] Figure 2 Notes: 1. Ventilation pipe, 2. Plate core, 3. Joint, 4. Air compressor, 5. Air lift pipeline, 6. Drain board, 7. Sand cushion layer, 8. Non-woven fabric (two layers), 9. Slag.
[0029] Figure 3 It is the water pressure in the core of the drainage board during the preloading process of the present invention and the pressure change in the board after using the air lift method. DETAILED DESCRIPTION
[0030] The present invention is described in detail below in conjunction with the accompanying drawings.
[0031] refer to Figures 1 to 3 The invention discloses an efficient treatment method for soft soil foundation by combining gas lift with preloading, which is suitable for preloading and drainage treatment of soft soil foundation. The treatment method comprises the following steps:
[0032] S1: Modify the drainage board;
[0033] A joint 3 is installed at the bottom of the drain plate 6 to connect the vent pipe 1;
[0034] S2: The ventilation pipe 1 is connected to the joint 3 at the bottom and is driven into the soft soil foundation together with the drainage board 6 by a board driving machine;
[0035] S3: After all the drainage boards 6 are driven into the soft soil foundation, a sand cushion layer 7 is laid;
[0036] S4: Lay the air lift pipeline 5 on the sand cushion layer 7, connect it to the air compressor 4, and extend it from the air compressor 4 to each drain board 6;
[0037] S5: Connect the gas lift pipeline 5 to the vent pipe 1, and lay two layers of non-woven fabric 8 on the gas lift pipeline 5;
[0038] S6: The machinery enters the site and starts loading step by step, while air lifting is performed by intermittently opening the air compressor 4.
[0039] Specifically, since the gas lift pipeline is easily crushed and damaged during the loading process, it is necessary to lay a sand cushion layer after the drainage board is driven into the foundation, and then lay it on top of the gas lift pipeline after the gas lift pipeline is connected.
[0040] Specifically, the bottom joint 3 of the drainage board 6 is installed before being inserted into the soil, ensuring that the gas lift pipeline 5 is unobstructed in the soil and the piled slag 9; and the compressed gas pipeline is covered with non-woven fabric to achieve a protective effect.
[0041] In one embodiment, in step S6, the specific process of gas lift is as follows:
[0042] The compressed gas generated by the air compressor is passed into the bottom of the drain board along the air lift pipeline, and the water stored in the core of the drain board is carried to the top in the form of air-water two-phase flow, thereby emptying the water stored in the core of the drain board, clearing the static water pressure of the core of the drain board, and increasing the seepage pressure difference between the board and the soil, thereby significantly increasing the consolidation pressure of the soil.
[0043] In one embodiment, in step S6, during the preloading process, air lift ventilation can be intermittently adopted according to the load classification during loading, soil consolidation rate, pore water pressure of soil around the drain board, and water level rise rate in the drain board. The air lift operation interval is 6h / time to 24h / time.
[0044] like Figure 1 The figure shows that when the drainage board is working, the stored water gathers in the board core. At this time, the pressure inside the board is the hydrostatic pressure, and the pressure of the soil around the board is the combination of the slag pile pressure and the hydrostatic pressure. That is, the driving force that drives the soil pore water to flow to the drainage board is only the additional stress caused by the slag pile (such as Figure 3 As shown in the figure, the driving force is a rectangular distribution); after the gas lift method is improved, the water in the plate is discharged and the hydrostatic pressure inside the plate core is cleared. At this time, the driving force becomes a combination of the additional stress of the pile load and the hydrostatic pressure (as shown in the figure). Figure 2 As shown in the figure, the driving force is a trapezoidal distribution). Obviously, the driving force of soil seepage consolidation is significantly improved after gas lift, and the degree of improvement increases with the increase of depth (trapezoidal distribution), which will significantly improve the seepage consolidation rate of foundation soil.
[0045] like Figure 3 As shown, (1) is the hydrostatic pressure distribution diagram inside the drainage board, (2) and (3) are the pressure distribution diagrams inside the soil, which are composed of hydrostatic pressure and slag load. According to the conventional construction method of preloading, the pressure inside the soil will be partially offset by the hydrostatic pressure in the board, that is, the load acting on the seepage part is only the slag load; while the air lift combined with preloading described in the present invention can use air lift to discharge the water inside the board, so that the hydrostatic pressure inside the board gradually decreases until it reaches zero; in this way, the pressure acting on the seepage is composed of the slag load and the hydrostatic pressure outside the board, which greatly increases the seepage pressure difference between the board and the soil, and significantly increases the consolidation pressure of the soil, especially the deep soil of the drainage board; at the same time, air lift can form splitting cracks in the soil around the board, shorten the radial drainage distance of the soil and increase the permeability coefficient of the soil, thereby improving the seepage consolidation efficiency of the soil during preloading.
[0046] In addition, the positive pressure gas moving along the core of the plate will partially penetrate the drainage board filter membrane and escape into the surrounding soft soil, forming splitting cracks in the soil, thereby further increasing the soft soil drainage channel, shortening the drainage path, and further accelerating the drainage and consolidation of the soft soil foundation. In fact, the above-mentioned gas lift process can be carried out periodically, thereby accelerating the seepage consolidation of the soft soil foundation during the entire foundation preloading treatment period.
[0047] In general, the present invention proposes a method of draining the water in the drain board by means of gas lift at the bottom of the drain board, clearing the hydrostatic pressure of the drain board core in a short time, significantly increasing the seepage pressure difference between the board and the soil, and thus increasing the consolidation pressure of the soil; at the same time, splitting cracks can be formed in the soil around the board, shortening the radial drainage distance of the soil and increasing the permeability coefficient of the soil, so that the seepage consolidation efficiency of the soil is improved. Since the deeper the depth, the greater the hydrostatic pressure in the board, the greater the pressure difference between the board and the soil after the water in the board core is drained, so the inventive method is particularly effective in improving the consolidation pressure of deep soil. In addition, the construction method for the reasonable placement of gas pipelines is also explored.
[0048] The contents described in the embodiments of this specification are merely an enumeration of the implementation forms of the inventive concept. The protection scope of the present invention should not be regarded as limited to the specific forms described in the embodiments. The protection scope of the present invention also extends to the equivalent technical means that can be conceived by those skilled in the art based on the inventive concept.
Claims
1. An efficient treatment method for soft soil foundation by air lift combined with preloading, which is suitable for preloading and drainage treatment of soft soil foundation, and is characterized by: The processing method comprises the following steps: S1: Modify the drainage board; Install a joint at the bottom of the drain board to connect the vent pipe; S2: The ventilation pipe is connected to the joint at the bottom and is driven into the soft soil foundation together with the drainage board through a board driving machine; S3: After all the drainage boards are driven into the soft soil foundation, lay the sand cushion layer; S4: Lay the air lift pipeline on the sand cushion layer and connect it to the air compressor, and extend it from the air compressor to each drain board; S5: Connect the gas lift pipeline to the vent pipe and lay two layers of non-woven fabric on the gas lift pipeline; S6: The machinery enters the site and starts loading step by step, while air lifting is performed by intermittently turning on the air compressor.
2. The method for efficiently treating soft soil foundation by combining air lift and preloading as claimed in claim 1, characterized in that: In step S6, the specific process of gas lift is as follows: The compressed gas generated by the air compressor is passed into the bottom of the drain board along the air lift pipeline, and the water stored in the core of the drain board is carried to the top in the form of air-water two-phase flow, thereby emptying the water stored in the core of the drain board, clearing the static water pressure of the core of the drain board, and increasing the seepage pressure difference between the board and the soil, thereby significantly increasing the consolidation pressure of the soil.
3. The method for efficiently treating soft soil foundation by combining air lift and preloading as claimed in claim 1, characterized in that: In step S6, during the preloading process, air lift ventilation can be intermittently adopted according to the load classification during the loading period, the soil consolidation rate, the pore water pressure of the soil around the drain board, and the water level rising speed in the drain board. The air lift operation interval is 6h / time to 24h / time.