Intelligent cement mixing pile construction control process based on Internet of Things technology
The intelligent construction system based on Internet of Things technology enables real-time quality control throughout the entire cement mixing pile construction process, solves the problem of delayed construction quality evaluation, improves the level of intelligence and standardization, and ensures a high rate of excellent construction quality.
Patent Information
- Application Number
- CN202411174725.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-15
AI Technical Summary
The current quality evaluation of cement mixing pile construction is lagging behind, relies on manual operation, and has a low level of intelligence and standardization, leading to quality accidents and economic losses.
The intelligent construction system based on Internet of Things (IoT) technology enables real-time online allocation, monitoring, and quality evaluation of multiple data points throughout the entire process and at all times through intelligent allocation of construction resources, IoT networking of the entire construction process, monitoring and collection of construction data, and command control.
It enables real-time and accurate assessment of the construction quality of cement mixing piles, improves the level of intelligence and standardization, ensures a 100% excellent pile quality rate, and avoids quality accidents and economic losses.
Smart Images

Figure CN118958280A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of soft foundation treatment construction of highway engineering, and in particular relates to an intelligent construction control process of cement mixing piles based on Internet of Things technology. Background Art
[0002] In the soft foundation treatment construction of highway engineering, cement mixing pile construction technology is extremely widely used, and its construction process is highly concealed. In recent years, some improved information technologies have emerged, but the implementation process is still highly dependent on human operation, and is relatively backward in terms of quality control, quality assessment, intelligent information management and control, and the quality evaluation of cement mixing pile construction has a lag. After reaching the strength cycle, it is difficult to remedy the problems found. In severe cases, it will lead to quality accidents and cause certain economic losses. Therefore, how to improve the intelligent level of cement mixing pile construction and strengthen the quality control before and during the event has become the key to ensuring the excellent quality rate of piles. In this regard, the present invention designs a new intelligent construction control process of cement mixing piles based on Internet of Things technology. Summary of the invention
[0003] In view of the deficiencies in the prior art, the present invention provides an intelligent construction control process for cement mixing piles based on the Internet of Things technology. Through the four stages of intelligent allocation of construction resources, Internet of Things networking for the entire construction process, construction data monitoring and collection, and command control operation of the intelligent construction system for cement mixing piles based on the Internet of Things technology, the mixing pile construction can be allocated, monitored, analyzed and controlled in real time online for the entire process, all time periods, and multiple data. The construction effect of the mixing piles can be intuitively obtained, and the quality can be evaluated in time. The single pile and the overall processing section can be effectively evaluated to ensure that the quality rate of cement mixing pile construction reaches 100%.
[0004] The present invention achieves the above technical objectives through the following technical means.
[0005] An intelligent construction control process for cement mixing piles based on Internet of Things technology includes the following processes: Step 1: Level the site; Step 2: Intelligent zoning and segmentation, and intelligent configuration of construction resources; Step 3: Site drainage; Step 4: Machinery and supporting equipment enter the site; Step 5: Mechanical placement; Step 6: Sensor installation; Step 7: Debug; Step 8: Align and level the pile, and put the pile driver in place; Step 9: Mixing cement slurry; Step 10: Shotcrete drilling, remixing and lifting to form mixing piles; Step 11: Confirmation of pile formation.
[0006] Furthermore, the step 2 comprises: The construction sections are divided according to the site geological and hydrological conditions and the overall progress plan. The design element data information including the horizontal curve of the plan, elevation information, designed length of cement mixing piles, pile diameter and pile spacing are input into the system platform. The system platform automatically arranges the pile positions according to the plum blossom pile principle, and obtains the elevation and plane coordinates of each pile to guide the positioning of the foreground pile driver for construction. According to the division of construction sections and the pile position design information, the system platform calculates the total number of meters of section mixing piles, and intelligently configures the construction resources including foreground and background machinery, raw materials and labor in combination with the construction progress priority and machinery layout requirements.
[0007] Furthermore, the sensor types and installation arrangements in step 6 are as follows: Personnel are located and allocated through the positioning chips in their helmets; raw materials are allocated through the positioning chips in cement tankers and dump trucks; Front-end pile driver sensor network: The pile driver is equipped with a positioning sensor to provide the pile driver construction elevation and coordinate positioning information; the pile length sensor is installed on the drill rod rack to detect the real-time construction pile length of the mixing pile; the flow sensor is set on the cement slurry delivery pipe to detect the real-time flow rate of the cement slurry and the accumulated mud flow; the density sensor is set on the cement slurry delivery pipe to detect the density of the cement slurry; the current sensor is set on the motor to detect the instantaneous current of the motor and the average current of the entire construction process; the inclination sensor is set on the drill rod to detect the inclination of the pile; the speed sensor is set on the drill bit to detect the pile driver's drilling speed and drilling speed; Background pulping sensor network: weight sensors are installed on the pulping machine and cement tank to measure and detect the weight of raw materials; speed sensors are installed on the mixing blades of the pulping machine to measure the mixing speed of the pulping machine.
[0008] Furthermore, in step 7, debugging refers to debugging the front-end and back-end machinery and various sensors, checking the IoT networking effect, interconnecting the sensors on personnel, materials, and mechanical equipment to form an IoT for the entire construction process, and starting to put the pile driver into place after all the facilities are normal.
[0009] Furthermore, in step 10, the process of shotcrete drilling is: After filtering the prepared cement slurry through a sieve, pour it into the slurry storage barrel, turn on the mortar pump, and send the slurry to the mixing head; start the mixer to cut the soil downward along the guide frame, and at the same time turn on the slurry pump to spray cement slurry into the soil. The two sets of blades rotate forward and reverse at the same time to cut and mix the soil. The mixer continues to sink, and the sinking speed is controlled at 0.7 m / min, the inner drill rod speed is 50r / min, the outer drill rod speed is 70r / min, and the grouting pressure during sinking is 0.30MPa; when drilling and spraying and mixing to the designed pile length, spray and mix on the spot for 10 seconds.
[0010] Furthermore, in step 10, the process of re-stirring and lifting is: The drill rod is lifted at a speed of 0.8 m / min, the inner drill rod rotates at 50 r / min, the outer drill rod rotates at 70 r / min, the mixer is lifted, and the two sets of blades rotate forward and reverse at the same time to mix the cement soil until it reaches the surface.
[0011] Furthermore, in the step 10, during the construction of the mixing piles, the construction data is monitored and collected through various sensors: according to the pile layout diagram automatically generated by the system platform, the construction is carried out according to the pile positioning, and the BIM model information is constructed according to the design element data information of the current drawing, the current construction progress and the unfinished progress are automatically obtained, and the progress is monitored in combination with the estimated rate, and early warning information is issued in advance; at the same time, the data information of the construction resources that can be allocated during the current construction process is obtained, and the material supply rate information within a unit time is calculated; the construction resources are allocated according to the estimated construction rate and the material supply rate information within a unit time, and the construction resources are monitored; finally, according to the various sensors installed on the front and back end machinery, the parameters including the mileage section number, pile driver number, pile number, pile depth, drilling speed, drilling speed, current, water-cement ratio, slurry volume, pile verticality, start time, and end time are monitored in real time; through the quality monitor set on the pile driver, the IoT data of the entire construction process monitored is transmitted to the Internet system platform in real time; Based on the construction data collected by the Internet of Things, the system platform conducts real-time comparative analysis of the pile driver construction positioning information, construction process quality parameters, and construction raw material usage to verify whether they exceed the pre-set allowable values. The construction site quality monitoring instrument, PC platform, and mini-program simultaneously display real-time data to conduct multi-dimensional comparison, analysis, and evaluation of the construction quality. It also implements early warning and disposal during the construction process based on the early warning standards entered in advance, and sends corresponding control instructions to relevant personnel via text messages at different levels, closes the real-time early warning, and realizes real-time quality control.
[0012] Furthermore, the step 11 comprises: Confirm the construction quality of the completed mixing piles, check whether there is any warning information on the system platform, and carry out graded processing if there is, otherwise proceed to the next pile construction; the system platform takes the establishment of a large database as the guiding principle, and organizes and analyzes the database formed by the monitoring data of the project to guide the design and construction of cement mixing piles under various complex conditions, and at the same time, the construction quality is formally written in the form of weekly or monthly reports.
[0013] The present invention has the following beneficial effects: The present invention describes the intelligent construction system and control process of cement mixing piles based on the Internet of Things technology through four stages, namely, intelligent allocation of construction resources, Internet of Things networking of the entire construction process, monitoring and collection of construction data, and command control operation, aiming to solve the problems of lag in quality evaluation of cement mixing piles and low levels of intelligence and standardization; while the mixing piles are being constructed, the quality of the piles can be accurately determined in real time through the intelligent construction system and control process of cement mixing piles based on the Internet of Things technology, which has good foresight and improves the level of intelligence and standardization. The present invention adopts the Internet of Things technology, advocates intelligent and standardized construction, and through the intelligent allocation of construction resources, the innovation of Internet of Things networking of the entire construction process, the optimization of monitoring and collection of construction data, and the upgrade of command control operation, the projects that originally needed to wait for 28d coring strength detection can evaluate the construction quality in real time, ensuring 100% of the pile quality rate, and having promotion value, so that more projects can adopt such intelligent and standardized construction systems and control processes when treating soft foundations. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 A schematic diagram of the four-stage operation of the system platform of the present invention; Figure 2 This is a schematic diagram of IoT networking for the entire construction process; Figure 3 This is a process flow chart of intelligent construction control of cement mixing piles based on Internet of Things technology according to the present invention. DETAILED DESCRIPTION
[0015] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but the protection scope of the present invention is not limited thereto.
[0016] Reference Figure 1 , 3 The intelligent construction control process of cement mixing piles based on Internet of Things technology of the present invention specifically includes the following processes: Step 1: Level the site; Before construction, the site for pile mixing construction must be leveled, and all obstacles below the ground (including stones, tree roots and garbage, etc.) must be removed and compacted with a roller. Low-lying areas or ponds on the site should be drained and silted before backfilling with plain soil (miscellaneous fill soil must not be backfilled) to the leveling elevation, and appropriately compacted, with a required compaction degree of 87%.
[0017] Step 2: Intelligent zoning and segmentation: Use the cement mixing pile intelligent construction quality monitoring system platform (hereinafter referred to as the system platform) to divide and segment the construction site, determine the section boundary line and all pile positions; The construction sections are divided according to the site geology, hydrological conditions, and overall schedule. After the horizontal curve of the widening section, elevation information, cement mixing pile design pile length, pile diameter, pile spacing and other design element data information are input into the system platform, the comprehensive platform automatically arranges the pile positions according to the plum blossom pile principle, and obtains the elevation and plane coordinates of each pile at the same time, which is convenient for guiding the front-end pile driver to locate the construction. According to the construction section division and pile position design information, the system platform calculates the total number of meters of section mixing piles, and intelligently configures the front-end and back-end machinery, raw materials, labor and other construction resources in combination with the construction progress priority and machinery layout requirements.
[0018] Step 3: Site drainage; Drainage ditches and collection wells with a depth of not less than 60cm are dug on the outside of the section to collect wastewater and waste slurry, and avoid environmental pollution caused by cement dust, slurry overflow, mechanical oil dripping and mechanical noise.
[0019] Step 4: Machinery and supporting equipment enter the site; Each pile driver is equipped with two bulk cement tanks with "A, B" labels affixed, with a capacity of no less than 50 tons, a solid foundation, and wind cables for stabilization, and its anti-overturning capacity meets the requirements for outdoor operations.
[0020] Step 5: Mechanical placement; After the pile driver and ancillary equipment are transported to the construction site, they are uniformly labeled, and the operating procedures are hung and the construction and management responsibilities are posted.
[0021] Step 6: Reference Figure 2 , sensor installation; Personnel are located and allocated through the positioning chips in their helmets; raw materials are allocated through the positioning chips in cement tankers and dump trucks; Front-end pile driver sensor network: The pile driver is equipped with a Trimble GNSS positioning sensor to provide the pile driver with construction elevation and coordinate positioning information; the pile length sensor is installed on the drill rod rack to detect the real-time construction length of the mixing pile; the flow sensor is set on the cement slurry delivery pipe to detect the real-time flow rate of the cement slurry and the accumulated mud flow; the density sensor is set on the cement slurry delivery pipe to detect the density of the cement slurry; the current sensor is set on the motor to detect the instantaneous current of the motor and the average current of the entire construction process; the inclination sensor is set on the drill rod to detect the inclination of the pile; the speed sensor is set on the drill bit to detect the pile driver's drilling speed and drilling speed; Background pulping sensor network: weight sensors are installed on the pulping machine and cement tank to measure and detect the weight of raw materials; speed sensors are installed on the mixing blades of the pulping machine to measure the mixing speed of the pulping machine.
[0022] Step 7: Debug; Reference Figure 2, debug the front-end and back-end machinery and various sensors, and check the effect of the Internet of Things network, that is, interconnect the sensors of personnel, materials, machinery, etc. to form an Internet of Things for the entire construction process. After all the facilities are normal, start putting the pile driver into place.
[0023] Step 8: Alignment and leveling; The construction personnel put the debugged slurry spraying pile machine into place, aligning the drill bit with the center of the pile, and the pile position deviation must not be greater than 5cm; adjust the verticality of the pile driver in the center and in both directions to keep the deviation within 1.0%; and adjust the pile driver's posture by checking the quality monitoring instrument installed on the pile driver.
[0024] Step 9: Mixing cement slurry; The cement slurry shall be prepared strictly according to the established mix ratio. The order of material addition is: water - cement. The slurry shall be prepared by using an automatic slurry mixer equipped with a flow meter and a measuring weighing sensor. The slurry shall be mixed evenly without lumps. When pouring the aggregate, it shall be sieved and filtered to prevent damage to the pump body. Before pumping the slurry, the pipeline shall be kept moist to facilitate slurry delivery and continuous slurry supply. The slurry reserves shall not be less than the amount used for one pile, otherwise the construction of the next pile shall not be carried out.
[0025] Step 10: Shotcrete drilling, remixing and lifting to form mixing piles; Shotcrete drilling: After filtering the prepared cement slurry through a sieve, pour it into the slurry storage barrel, turn on the mortar pump, and send the slurry to the mixing head. Start the mixer and make it cut the soil downward along the guide frame. At the same time, turn on the slurry pump to spray cement slurry to the soil. The two sets of blades rotate forward and reverse at the same time to cut and mix the soil. The mixer continues to sink, and the sinking speed is controlled at 0.7 m / min. The speed of the inner drill rod is 50r / min, and the speed of the outer drill rod is 70r / min. The grouting pressure during sinking is 0.30MPa. When the drilling and grouting are mixed to the designed pile length, the grouting is mixed in situ for 10 seconds.
[0026] Multiple mixing and lifting: lift the drill rod, the lifting speed is 0.8m / min, the inner drill rod speed is 50r / min, the outer drill rod speed is 70r / min, the mixer is lifted, and the two sets of blades rotate forward and reverse at the same time to mix the cement soil until it reaches the surface.
[0027] Reference Figure 2During the construction of the above-mentioned mixing piles, the construction data is monitored and collected through the above-mentioned sensors: according to the pile layout map automatically generated by the system platform, the construction is carried out according to the pile positioning, and the BIM model information is constructed according to the design element data information of the current drawing, and the current construction progress and the unfinished progress are automatically obtained. Combined with the estimated rate, the progress is monitored and early warning information is issued in advance; at the same time, the data information of the construction resources that can be allocated in the current construction process is obtained, and the material supply rate information within a unit time is calculated; the construction resources are allocated according to the estimated construction rate and the material supply rate information within a unit time, and the construction resources are monitored; finally, the mileage section number, pile driver number, pile number, pile depth, drilling speed, drilling speed, current, water-cement ratio, slurry volume, pile verticality, start time, end time and other parameters are monitored in real time according to the sensors installed on the front and back end machinery; through the quality monitor installed on the pile driver, the IoT data of the entire construction process monitored is transmitted to the Internet system platform in real time; Based on the construction data collected by the Internet of Things, the system platform conducts real-time comparative analysis of the pile driver construction positioning information, construction process quality parameters, and construction raw material usage to verify whether they exceed the pre-set allowable values. The construction site quality monitoring instrument, PC platform, and mini-program simultaneously display real-time data to conduct multi-dimensional comparison, analysis, and evaluation of the construction quality. It also implements early warning and disposal during the construction process based on the early warning standards entered in advance, and sends corresponding control instructions to relevant personnel via text messages at different levels, closes the real-time early warning, and realizes real-time quality control.
[0028] Step 11: Confirmation of pile formation; Confirm the construction quality of the completed mixing piles and check whether there is any warning information on the system platform. If there is, carry out graded processing; if not, proceed to the next pile construction.
[0029] The system platform takes the establishment of a large database as its guiding principle. The database formed by collating and analyzing the monitoring data of the project provides guidance for the design and construction of cement mixing piles under various sites, strata and other complex conditions. At the same time, the construction quality is formally documented in the form of weekly or monthly reports, which effectively monitors and controls the construction process and ensures the quality of the piles.
[0030] The embodiments are preferred implementations of the present invention, but the present invention is not limited to the above-mentioned implementations. Any obvious improvements, substitutions or modifications that can be made by those skilled in the art without departing from the essential content of the present invention belong to the protection scope of the present invention.
Claims
1. An intelligent construction control process for cement mixing piles based on Internet of Things technology, characterized in that: The process includes the following: Step 1: Level the site; Step 2: Intelligent zoning and segmentation, and intelligent configuration of construction resources; Step 3: Site drainage; Step 4: Machinery and supporting equipment enter the site; Step 5: Mechanical placement; Step 6: Sensor installation; Step 7: Debug; Step 8: Align and level the pile, and put the pile driver in place; Step 9: Mixing cement slurry; Step 10: Shotcrete drilling, remixing and lifting to form mixing piles; Step 11: Confirmation of pile formation.
2. According to the intelligent construction control process of cement mixing piles based on Internet of Things technology in claim 1, it is characterized in that: The step 2 comprises: The construction sections are divided according to the site geological and hydrological conditions and the overall progress plan. The design element data information including the horizontal curve of the plan, elevation information, designed length of cement mixing piles, pile diameter and pile spacing are input into the system platform. The system platform automatically arranges the pile positions according to the plum blossom pile principle, and obtains the elevation and plane coordinates of each pile to guide the positioning of the foreground pile driver for construction. According to the division of construction sections and the pile position design information, the system platform calculates the total number of meters of section mixing piles, and intelligently configures the construction resources including foreground and background machinery, raw materials and labor in combination with the construction progress priority and machinery layout requirements.
3. According to claim 1, the intelligent construction control process of cement mixing piles based on Internet of Things technology is characterized in that: The sensor types and installation arrangements in step 6 are as follows: Personnel are located and allocated through the positioning chips in their helmets; raw materials are allocated through the positioning chips in cement tankers and dump trucks; Front-end pile driver sensor network: The pile driver is equipped with a positioning sensor to provide the pile driver construction elevation and coordinate positioning information; the pile length sensor is installed on the drill rod rack to detect the real-time construction pile length of the mixing pile; the flow sensor is set on the cement slurry delivery pipe to detect the real-time flow rate of the cement slurry and the accumulated mud flow; the density sensor is set on the cement slurry delivery pipe to detect the density of the cement slurry; the current sensor is set on the motor to detect the instantaneous current of the motor and the average current of the entire construction process; the inclination sensor is set on the drill rod to detect the inclination of the pile; the speed sensor is set on the drill bit to detect the pile driver's drilling speed and drilling speed; Background pulping sensor network: weight sensors are installed on the pulping machine and cement tank to measure and detect the weight of raw materials; speed sensors are installed on the mixing blades of the pulping machine to measure the mixing speed of the pulping machine.
4. The intelligent construction control process for cement mixing piles based on Internet of Things technology according to claim 1 is characterized in that: In step 7, debugging refers to debugging the front-end and back-end machinery and various sensors, checking the IoT networking effect, interconnecting the sensors on personnel, materials, and mechanical equipment to form an IoT for the entire construction process, and starting to put the pile driver into place after all the facilities are normal.
5. According to the intelligent construction control process of cement mixing piles based on Internet of Things technology as claimed in claim 1, it is characterized in that: In step 10, the process of shotcrete drilling is as follows: after filtering the prepared cement slurry through a sieve, pour it into a slurry storage bucket, turn on the mortar pump, and deliver the slurry to the mixing head; start the mixer, so that the mixer cuts the soil downward along the guide frame, and at the same time, turn on the slurry pump to spray cement slurry to the soil, and the two sets of blades rotate forward and reversely at the same time to cut and mix the soil, the mixer continues to sink, and the sinking speed is controlled at 0.7 m / min, the inner drill rod speed is 50 r / min, the outer drill rod speed is 70 r / min, and the shotcrete pressure during sinking is 0.30 MPa; when drilling and spraying and mixing to the designed pile length, the in-situ spraying and mixing is performed for 10 seconds; The process of remixing and lifting is as follows: lifting the drill rod, the lifting speed is 0.8m / min, the inner drill rod speed is 50r / min, the outer drill rod speed is 70r / min, the mixer is lifted, and the two sets of blades rotate forward and reverse at the same time to mix the cement soil until it reaches the surface.
6. The intelligent construction control process for cement mixing piles based on Internet of Things technology according to claim 1 is characterized in that: During the construction of the mixing piles in step 10, the construction data is monitored and collected through various sensors: according to the pile layout diagram automatically generated by the system platform, the construction is carried out according to the pile positioning, and the BIM model information is constructed according to the design element data information of the current drawing, the current construction progress and the unfinished progress are automatically obtained, and the progress is monitored in combination with the estimated rate, and early warning information is issued in advance; at the same time, the data information of the construction resources that can be allocated during the current construction process is obtained, and the material supply rate information within a unit time is calculated; the construction resources are allocated according to the estimated construction rate and the material supply rate information within a unit time, and the construction resources are monitored; finally, the parameters including the mileage section number, pile driver number, pile number, pile depth, drilling speed, drilling speed, current, water-cement ratio, slurry volume, pile verticality, start time, and end time are monitored in real time according to the sensors installed on the front and back end machinery; By installing a quality monitor on the pile driver, the IoT data of the entire construction process can be transmitted to the Internet system platform in real time; Based on the construction data collected by the Internet of Things, the system platform conducts real-time comparative analysis of the pile driver construction positioning information, construction process quality parameters, and construction raw material usage to verify whether they exceed the pre-set allowable values. The construction site quality monitoring instrument, PC platform, and mini-program simultaneously display real-time data to conduct multi-dimensional comparison, analysis, and evaluation of the construction quality. It also implements early warning and disposal during the construction process based on the early warning standards entered in advance, and sends corresponding control instructions to relevant personnel via text messages at different levels, closes the real-time early warning, and realizes real-time quality control.
7. The intelligent construction control process for cement mixing piles based on Internet of Things technology according to claim 1 is characterized in that: The step 11 comprises: Confirm the construction quality of the completed mixing piles, check whether there is any warning information on the system platform, and carry out graded processing if there is, otherwise proceed to the next pile construction; the system platform takes the establishment of a large database as the guiding principle, and organizes and analyzes the database formed by the monitoring data of the project to guide the design and construction of cement mixing piles under various complex conditions, and at the same time, the construction quality is formally written in the form of weekly or monthly reports.
Citation Information
Cited By
Construction real-time monitoring system for extension rod type cement mixing pile and control method
CN119287996A
Stirring method and system for TRD
CN119784308A
Intelligent control method and system for pile machine monitoring and grout making and feeding linkage
CN120980107A
Intelligent processing system for construction data of mixing pile extension rod type drill rod
CN121345511A
Ultrafine particle soil flow state curing agent and intelligent pile forming process
CN122127115A