Method for determining reserves of deep and thick riverbed covering layer as artificial aggregate and related product

Through drilling layered sampling and computer-aided analysis, the problem of material composition and reserve evaluation of deep riverbed cover layer was solved, and the accurate assessment of qualified material reserves of riverbed cover layer was achieved, which improved resource utilization and engineering efficiency and reduced the environment Influence.

CN118965525AActive Publication Date: 2024-11-15CHINA HYDROELECTRIC ENGINEERING CONSULTING GROUP CHENGDU RESEARCH HYDROELECTRIC INVESTIGATION DESIGN AND INSTITUTE

Patent Information

Application Number
CN202411050593.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-11-15
Estimated Expiration
2044-08-01

AI Technical Summary

Technical Problem

The prior art is difficult to accurately evaluate the material composition, reserves and distribution of deep riverbed covers, resulting in insufficient resource utilization, high engineering costs and great environmental impact.

Method used

By determining the riverbed range line to be excavated, drilling holes to cover bedrock under the cover layer, layered sampling and aggregate tests, drawing an isoth thickness map of the unqualified material, and using parallel section method and isoth thickness map to calculate the difference of each layer The qualified material reserves are obtained, and a comprehensive layered zoning reserve chart is formed.

Benefits of technology

The accurate assessment of the qualified material reserves of deep riverbed covers has been achieved, the aggregate utilization rate has been improved, the engineering costs and environmental impact have been reduced, and the construction period and mining costs have been saved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118965525A_ABST
    Figure CN118965525A_ABST
Patent Text Reader

Abstract

The invention relates to the field of water-power engineering, in particular to a method for determining the reserve volume of a deep and thick riverbed covering layer as artificial aggregate and a related product, and the method comprises the following steps: determining the position of an exploratory hole; drilling holes; layering a riverbed covering layer; disqualified materials of each layer are found out; drawing an equal-thickness graph of the unqualified material; calculating the total reserves; calculating the reserves of unqualified materials; determining qualified material reserves of each covering layer; on the basis of layering of the deep and thick covering layer, an equal-thickness map of unqualified materials is drawn on a plane of each layer according to exploration test results, the reserves of the unqualified materials in each layer are calculated through the equal-thickness map and the average thickness, and the qualified rate reserves of each layer are obtained by subtracting the reserves of the unqualified materials from the total reserves of the covering layer in each layer. And a comprehensive layered and partitioned reserve map is formed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of hydropower engineering, and in particular to a method for determining the reserve of a thick riverbed cover layer used as artificial aggregate and related products. Background Art

[0002] In hydropower projects, concrete is an important material for constructing hydraulic structures, and its quality directly affects the structural stability and operational safety of the project. As an important component of concrete, the selection of concrete aggregate is crucial to the quality of concrete. Usually, the concrete aggregate of hydropower projects comes from natural sand and gravel in the riverbed cover or artificially processed aggregate.

[0003] The riverbed overburden is a sediment formed by long-term scouring, transportation and accumulation of rivers, mainly including sand, pebbles and gravel. These materials can be directly used as concrete aggregates after screening and processing. However, in actual projects, the thickness and quality of the overburden are often uneven, which affects the utilization efficiency of aggregates. In addition, the deep riverbed overburden has certain technical difficulties in the process of mining and exploration, such as the difficulty in accurately assessing the reserves and distribution of materials in each layer.

[0004] Traditional exploration methods mainly rely on surface surveys and drilling sampling, lack a systematic reserve calculation method, and it is difficult to fully grasp the material composition and distribution of the riverbed cover. In this case, the commonly used reserve calculation method has large errors and low efficiency, resulting in insufficient resource utilization, increased project costs and environmental burdens.

[0005] Therefore, it is necessary to develop a new technical method to evaluate the aggregate reserves of the deep riverbed cover in detail through scientific exploration and reserve calculation methods, and provide reliable data support for project planning and construction. This can not only improve the utilization rate of aggregates and reduce project costs, but also reduce the impact on the environment and achieve sustainable development of the project. Summary of the invention

[0006] The technical problem to be solved by the present invention is that it is difficult to accurately evaluate the material composition, reserves and distribution of the deep riverbed cover layer in the prior art. The purpose is to provide a method and related products for determining the reserves of the deep riverbed cover layer used as artificial aggregate, thereby realizing the evaluation of the reserves of qualified materials for the deep riverbed cover layer.

[0007] The present invention is achieved through the following technical solutions:

[0008] A method for determining the amount of deep riverbed cover for use as artificial aggregate reserves comprises:

[0009] Determine the scope line of the riverbed to be excavated and determine the location of the exploration hole within the scope line of the riverbed;

[0010] Drilling is performed at the location of the exploration hole, and the exploration hole is made to penetrate into the bedrock under the overburden layer;

[0011] The core material composition is revealed through the exploration holes, and the riverbed cover layer is divided into the first layer, the second layer and the third layer. The first layer is a floating pebble gravel layer or a floating pebble crushed gravel layer, the second layer is a sandy pebble gravel layer and a gravel-containing sand layer, and the third layer is a floating sand pebble gravel layer or a floating sand pebble crushed gravel layer.

[0012] Core sampling is carried out for each layer, and aggregate tests are performed to identify unqualified materials in each layer;

[0013] Draw the equal thickness map of the unqualified materials to determine the distribution and thickness of the unqualified materials in different layers;

[0014] The total reserves of each overburden layer are calculated using the parallel section method;

[0015] Use the equal thickness map to calculate the unqualified material reserves for each layer and each partition;

[0016] The qualified material reserves of each overburden layer are determined as the difference between the total reserves and the unqualified material reserves.

[0017] Optionally, the total reserves, the unqualified material reserves and the qualified material reserves are marked on the equal thickness map corresponding to each layer of the covering layer.

[0018] Specifically, the method for determining the location of the exploration hole includes:

[0019] The longitudinal exploration lines are determined along the direction parallel to the river flow direction, and the distance between adjacent longitudinal exploration lines is a;

[0020] Determine the transverse exploration line in the direction perpendicular to the river flow direction, and the distance between adjacent transverse exploration lines is b;

[0021] The intersection point between the longitudinal exploration line and the transverse exploration line is determined and taken as the location of the exploration hole.

[0022] Optionally, a=b.

[0023] Specifically, the indicators of unqualified materials are: mud content greater than 1% and oversized stone content greater than 10%.

[0024] Optionally, the method for drawing the equal thickness map includes:

[0025] Determine the exploration layout according to the stratification situation;

[0026] Determine the distribution of unqualified materials on the exploration layout of each layer;

[0027] Determine the range boundary of unqualified materials and the corresponding position of maximum thickness;

[0028] Project the range boundary onto the plane map to obtain the 0 edge line of the equal thickness map; the 0 edge line is a closed smooth curve centered at the corresponding position of the maximum thickness;

[0029] Set the spacing c between equal thickness lines, set n fixed points from the 0 edge line to the center, the distance between radially adjacent fixed points is c, use smooth curves to connect the fixed points with the same distance from the 0 edge line in sequence, and obtain n equal thickness lines;

[0030] Obtain the corresponding equal thickness map for each layer.

[0031] Optionally, the calculation method of the unqualified material reserve includes:

[0032] Calculate the distribution area S of unqualified materials according to the 0 equal thickness line, and determine the maximum thickness H;

[0033] The unqualified material reserve V=0.5*S*H of each layer is obtained respectively.

[0034] Optionally, if each covering layer contains multiple 0-isothickness lines, the unqualified material reserves of multiple partitions are calculated respectively according to the 0-isothickness lines, and the sum of the unqualified material reserves of the multiple partitions is taken as the unqualified material reserves of the layer.

[0035] A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the method for determining the amount of a thick riverbed cover layer used as artificial aggregate reserves as described above.

[0036] A computer program product comprises a computer program / instruction, which when executed by a processor implements a method for determining the amount of a thick riverbed cover layer used as artificial aggregate reserves as described above.

[0037] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0038] The present invention is based on the stratification of deep overburden and draws an equal thickness map of unqualified materials for each layer on the plane according to the exploration test results. The equal thickness map is used to calculate the reserves of unqualified materials in each layer by equally dividing the thickness. The total reserves in the overburden in each layer are deducted from the reserves of each unqualified material to obtain the qualified rate reserves of each layer, thus forming a comprehensive stratified and zoned reserves map.

[0039] Based on the distribution of indicators, the reserves of qualified materials are calculated in layers and zones using equal thickness maps. This method can not only reflect the distribution of qualified materials in each layer and each adjacent layer from the plane, but also reflect the distribution of qualified materials in each layer from the elevation. It can provide a basis for formulating reasonable mining routes and mining plans in the next step, and can effectively save construction time, reduce excavation and transportation costs, and reduce waste slag and materials. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] The accompanying drawings illustrate exemplary embodiments of the present invention and, together with the description thereof, are used to explain the principles of the present invention. These drawings are included to provide a further understanding of the present invention, and the accompanying drawings are included in and constitute a part of this specification and do not constitute a limitation of the embodiments of the present invention.

[0041] Figure 1 It is a schematic flow chart of the method for determining the reserve of deep riverbed cover layer used as artificial aggregate and related products according to the present invention.

[0042] Figure 2 It is a schematic diagram of the arrangement of the exploration holes according to the present invention.

[0043] Figure 3 is a hierarchical schematic diagram according to the present invention.

[0044] Figure 4 is an isothimetry diagram of the first layer according to the present invention.

[0045] Figure 5 is an isopach diagram of the second layer according to the present invention.

[0046] Figure 6 is an isopach diagram of the third layer according to the present invention. DETAILED DESCRIPTION

[0047] To make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and implementation methods. It is understood that the specific implementation methods described herein are only used to explain the relevant content, rather than to limit the present invention.

[0048] It should also be noted that, for the convenience of description, only the parts related to the present invention are shown in the drawings.

[0049] In the absence of conflict, the embodiments and features of the embodiments of the present invention may be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0050] Embodiment 1

[0051] like Figure 1 A method for determining the amount of artificial aggregate reserves of a deep riverbed cover is provided, comprising:

[0052] The first step is to determine the scope line of the riverbed to be excavated and determine the location of the exploration holes within the riverbed scope line; determine the boundary of the riverbed area to be excavated according to the engineering design drawings, and plan and mark the locations of multiple exploration holes in the area.

[0053] The second step is to drill at the exploration hole location and make the exploration hole deep into the bedrock under the overburden layer; use mechanical equipment to drill vertically downward on the ground to obtain underground rock and soil layer samples. At the same time, the drilling depth must reach and pass through the overburden layer to the bedrock in order to obtain comprehensive geological profile information.

[0054] The third step is to reveal the core material composition through the exploration holes, and divide the riverbed cover into the first, second and third layers. The first layer is a drifted pebble gravel layer or a drifted pebble crushed gravel layer, the second layer is a sand pebble gravel layer and a gravel-containing sand layer, and the third layer is a drifted sand pebble gravel layer or a drifted sand pebble crushed gravel layer. By analyzing the core samples taken from the exploration holes, the material composition at different depths is revealed, and the riverbed cover is divided into three main layers according to its characteristics.

[0055] The fourth step is to take core samples from each layer and conduct aggregate tests to find out the unqualified materials in each layer; the aggregate test is to test whether the core samples meet the requirements of concrete aggregate, usually including indicators such as particle size distribution, strength, and mud content.

[0056] The fifth step is to draw an isothickness map of the unqualified material to determine the distribution and thickness of the unqualified material in different layers; an isothickness map is a map that uses isovalue lines to represent the thickness distribution of a specific material (such as unqualified material) in different areas. Isovalue lines are lines connecting points of the same thickness, similar to contour lines.

[0057] The sixth step is to calculate the total reserves of each layer of the covering layer using the parallel section method; by dividing the layer into multiple parallel sections, the covering layer area of ​​each section is calculated, and then the total reserves of the entire covering layer are calculated through the area and spacing of these sections.

[0058] The seventh step is to calculate the reserves of unqualified materials for each partition of each layer using the equal thickness map; divide the unqualified materials in each layer into multiple partitions through the equal thickness map, and then calculate the reserves of unqualified materials in each partition separately, and finally obtain the total reserves of unqualified materials in each layer.

[0059] The eighth step is to determine the qualified material reserves of each overburden layer as the difference between the total reserves and the unqualified material reserves. By subtracting the unqualified material reserves from the total reserves, the qualified material reserves that meet the standards in each layer are calculated, thereby accurately evaluating the amount of resources that can be used as artificial aggregate.

[0060] The ninth step is to mark the total reserves, unqualified material reserves and qualified material reserves on the isopach map corresponding to each layer of the overburden.

[0061] According to the equal thickness map of each layer of unqualified material, the distribution range, thickness, reserves, etc. of each layer of qualified material can be seen from the plane, and the range line and thickness of qualified material in adjacent layers are also reflected. The reserve calculation results of the layers and zones are marked next to the plane map (the reserve calculation can be used as the basis for mining planning. When mining from top to bottom to the layer boundary, the lower layer mining line and mining plan are formulated according to the layer and zone reserves, so as to better plan mining, save construction time, and reduce abandoned materials).

[0062] Embodiment 2

[0063] In the first step provided in this embodiment, the method for determining the location of the exploration hole includes:

[0064] The longitudinal exploration line is determined along the direction parallel to the river flow, and the distance between adjacent longitudinal exploration lines is a; the transverse exploration line is determined along the direction perpendicular to the river flow, and the distance between adjacent transverse exploration lines is b.

[0065] Determine the intersection between the longitudinal exploration line and the transverse exploration line, and use the intersection as the location of the exploration hole. By arranging exploration holes at the intersection of the longitudinal exploration line and the transverse exploration line, a grid-like exploration layout can be formed throughout the riverbed. The location of each intersection is the location of an exploration hole, so that the entire area to be explored can be systematically covered to ensure that comprehensive and uniform geological information is obtained.

[0066] As a preferred embodiment, a=b can be set, that is, equal longitudinal and lateral spacings are selected so that the exploration holes are evenly distributed in the entire grid, simplifying the exploration layout design while ensuring the uniformity and integrity of the exploration coverage.

[0067] Embodiment 3

[0068] For the fourth step, the indicators of unqualified materials are: mud content greater than 1% (too high mud content will affect the quality of concrete), and oversized stone content greater than 10%.

[0069] The oversized stone content refers to the stone content in the concrete aggregate that exceeds the specified particle size. Oversized stone will affect the particle size gradation of the aggregate, thereby affecting the performance of the concrete. The specific value of the oversized stone content needs to be determined according to the project requirements.

[0070] For the fifth step, the method of drawing the equal thickness map includes:

[0071] Determine the exploration layout diagram (a plan showing the location of each exploration hole and the layout of the exploration line) according to the stratification situation;

[0072] Determine the distribution of rejects on the exploration layout map for each layer.

[0073] Determine the range boundary of unqualified materials (the distribution boundary of unqualified materials on the plane) and the corresponding position of the maximum thickness (the maximum thickness of unqualified materials in the vertical direction and its corresponding plane position);

[0074] Project the range boundary onto the plane map to obtain the 0 edge line of the equal thickness map; the 0 edge line is a closed smooth curve centered at the corresponding position of the maximum thickness;

[0075] Set the spacing c between equal thickness lines, set n fixed points from the 0 edge line toward the center in sequence, the distance between radially adjacent fixed points is c, and use smooth curves to connect the fixed points that are equal to the distance from the 0 edge line in sequence to obtain n equal thickness lines; that is, starting from the 0 edge line, set fixed points inward in sequence according to the set spacing c to form a series of points that are equal to the distance from the 0 edge line, and then use smooth curves to connect these fixed points to form multiple equal thickness lines, indicating the distribution of different thicknesses.

[0076] Obtain the corresponding equal thickness map of each layer, draw the equal thickness map of each layer of unqualified materials, and intuitively display the thickness distribution of each layer of unqualified materials on the plane.

[0077] Embodiment 4

[0078] In the sixth step, the total reserves are determined using the parallel section method, which is a common method for calculating the reserves or volume of geological bodies (such as ore deposits, soil layers, overburden, etc.). This method divides the geological body into multiple parallel sections, calculates the area of ​​each section, and then estimates the volume or reserves of the entire geological body based on the areas of these sections and the distances between them.

[0079] Steps of the Parallel Section Method

[0080] Divide sections: Divide multiple sections in parallel directions (usually perpendicular to the main direction, such as the direction of a river) in a geological body. The spacing between each section should be consistent, and the common spacing is determined by the size and shape of the geological body.

[0081] Calculate the cross-sectional area: Draw a cross-sectional diagram on each cross-section based on the actual shape and data of the geological body (such as drilling data, exploration data, etc.). To calculate the area of ​​each cross-section, you can use geometric segmentation methods (such as triangles, rectangles, etc.) or integration methods.

[0082] Calculate the volume between adjacent sections: Take the average of the areas of two adjacent sections and multiply it by the distance between the two sections to get the volume of this section. Volume = (area of ​​section 1 + area of ​​section 2) / 2 * distance between sections

[0083] Cumulative calculation of total reserves or volume: add up the volumes between all adjacent sections to obtain the total reserves or volume of the entire geological body.

[0084] In the seventh step, the calculation method of the unqualified material reserves includes:

[0085] The distribution area S of unqualified materials is calculated according to the 0 isopach line, and the maximum thickness H is determined; according to the drawn isopach map, the unqualified material area surrounded by the 0 isopach line is identified, and the total area S of the area is calculated. At the same time, by analyzing the data of each exploration hole, the maximum thickness H of the unqualified material in the area is determined.

[0086] The unqualified material reserve V=0.5*S*H of each layer is obtained respectively.

[0087] In one overlay layer, there may be multiple areas of defective material distribution, each area is defined by its own 0 isopach line.

[0088] If each layer of the covering layer contains multiple 0-isothickness lines, the unqualified material reserves of multiple partitions are calculated respectively according to the 0-isothickness lines, and the sum of the unqualified material reserves of multiple partitions is taken as the unqualified material reserves of the layer.

[0089] Embodiment 5

[0090] A specific example is provided below to illustrate this.

[0091] The first step is to arrange the exploration lines according to the scope of the riverbed to be excavated in the engineering design drawing at a spacing of about 40m. The vertical arrangement is horizontal 1, horizontal 2, horizontal 3, horizontal 4, and horizontal 5; the arrangement along the river direction is vertical 1, vertical 2, and vertical 3; the exploration hole depth is 10m into the bedrock under the overburden. Figure 2 shown.

[0092] The second step is to drill a hole at the location of the exploration hole and make the exploration hole penetrate into the bedrock under the overburden layer.

[0093] The third step is to stratify the riverbed cover layer from old to new and from bottom to top according to the core material composition revealed by the drilling, and to divide it into ① floating pebble (crushed) gravel layer, ② sand pebble gravel layer and gravel-containing sand layer, and ③ floating sand pebble (crushed) gravel layer;

[0094] In the fourth step, according to the stratification, core samples are taken from each layer for aggregate testing to find out the unqualified sections with mud content greater than 1% and too many oversized stones, and mark them on the profile in time. Finally, three layers of range lines are formed on the plane map. The distribution of overburden stratification and unqualified materials is shown in the figure. Figure 3 shown.

[0095] The fifth step is to draw a thickness map of unqualified materials. The thickness lines are drawn with dotted lines, and the thickness difference between two adjacent lines is 1 meter. First, find out the distribution of unqualified materials in each layer on the exploration layout map according to the layers;

[0096] Then, based on the borehole revelations and cross-sections, find the boundary of the unqualified material and the thickest position; project the position of the unqualified material boundary onto the plan view, and the boundary line is the 0 boundary line of the isopach map. The drawing of the 0 boundary line should be centered on the thickest part to form a closed curve (on the cross-section, connect the range of the unqualified material according to the outcropping situation in the boreholes with a smooth curve to form the distribution and shape of the unqualified material on the cross-section).

[0097] Then, according to the cross-section, determine the fixed points of the 1m isopach line from the boundary line (0m isopach line) to the thicker part on each nearby cross-section, and then connect them with a smooth curve to form a closed curve with an isopach of 1m.依次相邻两条线按照1米的厚度差分别绘制1米、2米……n米等厚度线。最后形成每层的不合格料的等厚度图,如 Figure 4 、 Figure 5 、 Figure 6 所示。

[0098] Step 6: According to the exploration revelations and test results, use the parallel cross-section method to calculate the reserves of the overburden layer for each layer (calculate the area of the overburden layer for each layer on each cross-section, then calculate the average value of the overburden layer areas on two adjacent cross-sections, and the average value multiplied by the distance between the two cross-sections is the qualified material reserve between the two cross-sections). The calculation results are respectively marked as V①, V②, V③ beside the plan view.

[0099] Step 7: Use the isopach map to calculate the reserves of the unqualified rate for each partition of each layer. As shown in layer ① in the figure, there are 2 partitions of unqualified material in this layer. According to the exploration revelations, the unqualified material with a high mud content generally appears in a lenticular shape, and oversize stones generally develop locally. To calculate the reserves of the unqualified material in each layer more accurately, calculate in the isopach map of the unqualified material for each layer: First, calculate the distribution area S of the unqualified material according to the range of the 0 isopach line; then find the maximum value H of the thickness in the isopach map; finally, evenly divide the thickness between the maximum isopach line and the 0 isopach line; that is, the reserve of each partition of the unqualified material in each layer is 0.5×S×H, which are respectively recorded as V①-1, V①-2, ….

[0100] Step 8: The reserve of the qualified material for each layer is: the reserve of the overburden layer for each layer minus the reserve of the unqualified material included in each layer. The total reserve of the overburden layer is the sum of the qualified material reserves of each sub-layer. The calculation results are marked beside the plan view. V qualified ① = V① - V①-1 - V①-2; V qualified ② = V② - V②-1 - V②-2; V qualified ③ = V③ - V③-1. V qualified = V qualified ① + V qualified ② + V qualified ③. As Figure 5 、 Figure 6 所示。

[0101] The ninth step, according to the equal thickness map of unqualified materials in layers ①, ② and ③, the distribution range, thickness, reserves, etc. of qualified materials in each layer can be seen from the plane, and the range line and thickness of qualified materials in adjacent layers are also reflected. The reserve calculation results of the layers and zones are marked next to the plane map (the reserve calculation can be used as the basis for mining planning. When mining from top to bottom to the layer boundary, the lower layer mining line and mining plan are formulated according to the layer and zone reserves, so as to better plan mining, save construction time and reduce abandoned materials).

[0102] According to the excavation plan, exploration and test work are arranged within the excavation range to find out the material composition, genesis, structure, etc. of the deep riverbed cover layer, and to stratify the deep cover layer; on each layer, according to the distribution of unqualified materials on the section, draw an equal thickness map of the unqualified materials on the plan view of the layer, and use the equal thickness map to calculate the reserves of unqualified materials in each layer by equally dividing the thickness. The total reserves of the cover layer in each layer are deducted from the reserves of each unqualified material to obtain the qualified reserves of each layer.

[0103] Based on the distribution of overburden indicators, the use of equal thickness maps to calculate the reserves of qualified materials in layers and zones can not only reflect the distribution of qualified materials in each layer and each adjacent layer from the plane, but also reflect the distribution of qualified materials in each layer from the elevation. It can provide a basis for the formulation of reasonable mining routes and mining plans in the next step, effectively save construction time, reduce excavation and transportation costs, and reduce waste slag and materials.

[0104] Embodiment 6

[0105] A computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method for determining the reserve of a deep riverbed cover layer used as artificial aggregate is implemented.

[0106] Without loss of generality, computer readable media may include computer storage media and communication media. Computer storage media include volatile and non-volatile, removable and non-removable media implemented in any method or technology for storing information such as computer readable instruction data structures, program modules or other data. Computer storage media include RAM, ROM, EPROM, EEPROM, flash memory or other solid-state storage technology, CD-ROM, DVD or other optical storage, cassettes, magnetic tapes, disk storage or other magnetic storage devices. Of course, those skilled in the art will appreciate that computer storage media are not limited to the above. The above-mentioned system memory and mass storage devices can be collectively referred to as memory.

[0107] A computer program product comprises a computer program / instruction, which, when executed by a processor, implements the above-mentioned method for determining the reserve of a deep riverbed cover layer for use as artificial aggregate.

[0108] A computer program product includes a computer program or set of instructions for performing specific tasks or implementing specific functions. These programs or instructions are designed to be executed by a processor to implement a series of predefined steps or operations. The program product may be stored in various forms of computer storage media, such as memory, hard disk, solid-state drive, optical disk or other forms of digital storage devices. It may exist in the form of compiled binary code or in the form of scripts or bytecodes that can be executed by an interpreter. The program product uses carefully designed algorithms and logical instructions to enable the processor to process data in a specific order and manner to complete various functions such as data analysis, user interaction, device control, etc.

[0109] In the description of this specification, the description with reference to the terms "one embodiment / method", "some embodiments / methods", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment / method or example are included in at least one embodiment / method or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment / method or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments / methods or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments / methods or examples described in this specification and the features of the different embodiments / methods or examples, unless they are contradictory.

[0110] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0111] It should be understood by those skilled in the art that the above embodiments are only for the purpose of clearly illustrating the present invention, and are not intended to limit the scope of the present invention. For those skilled in the art, other changes or modifications may be made based on the above invention, and these changes or modifications are still within the scope of the present invention.

Claims

1. A method for determining the amount of deep riverbed cover used as artificial aggregate reserves, characterized in that: include: Determine the scope line of the riverbed to be excavated and determine the location of the exploration hole within the scope line of the riverbed; Drilling is performed at the location of the exploration hole, and the exploration hole is made to penetrate into the bedrock under the overburden layer; The core material composition is revealed through the exploration holes, and the riverbed cover layer is divided into the first layer, the second layer and the third layer. The first layer is a floating pebble gravel layer or a floating pebble crushed gravel layer, the second layer is a sandy pebble gravel layer and a gravel-containing sand layer, and the third layer is a floating sand pebble gravel layer or a floating sand pebble crushed gravel layer. Core sampling is carried out for each layer, and aggregate tests are performed to identify unqualified materials in each layer; Draw the equal thickness map of the unqualified materials to determine the distribution and thickness of the unqualified materials in different layers; The total reserves of each overburden layer are calculated using the parallel section method; Use the equal thickness map to calculate the reserve of unqualified materials in each layer and each partition; The qualified material reserves of each overburden layer are determined as the difference between the total reserves and the unqualified material reserves.

2. A method for determining the reserve of a deep riverbed cover layer for use as artificial aggregate according to claim 1, characterized in that: Mark the total reserves, unqualified material reserves and qualified material reserves on the isopach map corresponding to each layer of the overburden.

3. A method for determining the reserve of a deep riverbed cover layer for use as artificial aggregate according to claim 1, characterized in that: Methods for determining the location of exploration holes include: The longitudinal exploration lines are determined along the direction parallel to the river flow direction, and the distance between adjacent longitudinal exploration lines is a; Determine the transverse exploration line in the direction perpendicular to the river flow direction, and the distance between adjacent transverse exploration lines is b; The intersection point between the longitudinal exploration line and the transverse exploration line is determined and taken as the location of the exploration hole.

4. A method for determining the reserve of a deep riverbed cover layer for use as artificial aggregate according to claim 3, characterized in that: a=b.

5. A method for determining the reserve of a deep riverbed cover layer for use as artificial aggregate according to claim 1, characterized in that: The indicators of unqualified materials are: mud content greater than 1% and oversized stone content greater than 10%.

6. A method for determining the reserve of a deep riverbed cover layer for use as artificial aggregate according to claim 1, characterized in that: The methods for drawing equal thickness maps include: Determine the exploration layout according to the stratification situation; Determine the distribution of unqualified materials on the exploration layout of each layer; Determine the range boundary of unqualified materials and the corresponding position of maximum thickness; Project the range boundary onto the plane map to obtain the 0 edge line of the equal thickness map; the 0 edge line is a closed smooth curve centered at the corresponding position of the maximum thickness; Set the spacing c between equal thickness lines, set n fixed points from the 0 edge line to the center, the distance between radially adjacent fixed points is c, use smooth curves to connect the fixed points with the same distance from the 0 edge line in sequence, and obtain n equal thickness lines; Obtain the corresponding equal thickness map for each layer.

7. A method for determining the reserve of a deep riverbed cover layer for use as artificial aggregate according to claim 1, characterized in that: The calculation method of the unqualified material reserve includes: Calculate the distribution area S of unqualified materials according to the 0 equal thickness line, and determine the maximum thickness H; The unqualified material reserve V=0.5*S*H of each layer is obtained respectively.

8. A method for determining the reserve of a deep riverbed cover layer for use as artificial aggregate according to claim 7, characterized in that: If each layer of the covering layer contains multiple 0-isothickness lines, the unqualified material reserves of multiple partitions are calculated respectively according to the 0-isothickness lines, and the sum of the unqualified material reserves of multiple partitions is taken as the unqualified material reserves of the layer.

9. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 8 is implemented.

10. A computer program product comprising a computer program / instructions, characterized in that When the computer program / instructions are executed by a processor, the method according to any one of claims 1 to 8 is implemented.

Citation Information

Patent Citations

  • Three-dimensional visual geological exploration reserve estimation method

    CN103824329A

  • Concrete artificial aggregate surveying method

    CN105929463A

  • Method and system for estimating carbon emission and carbon reserve of mineral resource base

    CN114969665A

  • Method, system and equipment for obtaining earth material reserves in earth material field and storage medium

    CN118012969A

  • Method and system for measuring stock ground reserves in pumped storage power station warehouse

    CN118246198A

Cited By

  • A method for quality evaluation and reserve determination of river terrace gravel material

    CN122731815A