Project progress management system and method based on milestone prediction model
Through the project progress management system based on the milestone prediction model, the PCA-BP neural network is used to predict the project progress and automatically calculate the settlement amount, the problem of inefficient construction progress management in the existing technology is solved, and intelligent management and efficient engineering progress are achieved Adjustment.
Patent Information
- Application Number
- CN202410928473.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2024-11-15
AI Technical Summary
In engineering construction, the existing technology analysis methods are long and inefficient, which makes it difficult to manage the construction progress, affecting the completion of the project progress as planned, and there are many quotations for the construction contract, which requires a large amount of manual calculation of the settlement amount.
Using the project progress management system and method based on the milestone prediction model, a project progress prediction model is established through the PCA-BP neural network, the project volume and investment progress are automatically calculated, progress charts and comparison charts are generated, and intelligent management is realized.
It realizes intelligent management of project progress, and managers can grasp the progress in real time, discover problems in a timely manner and adjust plans, improving the efficiency and accuracy of construction progress management.
Smart Images

Figure CN118967007A_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the technical field of engineering management, and in particular to an engineering progress management system and method based on a milestone prediction model. Background Art
[0002] In the construction of engineering buildings, the scale and speed of construction are directly related to the quality of the building and the safety of construction. In engineering construction, due to the lack of technology and management, there are many quality problems. In the management of construction, due to the difficulty of management of construction sites, in construction projects, affected by various factors such as funds, personnel, materials, weather, geological conditions and management, the construction progress often cannot be completed as planned. For the many factors that lead to the failure of the construction progress to be completed as planned, most of them are manually investigated and analyzed, and the progress is adjusted.
[0003] The analysis methods in the existing technology have a long cycle and low efficiency, and affect the progress of the project.
[0004] At the same time, there are many quotation items in the construction contract, and each quotation item must be settled proportionally according to the progress of the project equipment installation completion. Each time the user settles, he needs to manually calculate the settlement amount of each quotation item in the electromechanical contract progress. Summary of the invention
[0005] In view of the above problems, the present disclosure provides a project progress management system and method based on a milestone prediction model.
[0006] In a first aspect, a project progress management system based on a milestone prediction model comprises:
[0007] Plan and progress management unit, project image progress control unit, contract engineering quantity plan and completion status comparison and analysis unit, and contract investment plan and completion status comparison and analysis unit;
[0008] The planning and progress management unit is used to break down the entire project into projects, determine the goals of each project, the scope of work of each project, and plan project milestones;
[0009] The project progress control unit is used to record the progress of the project every day and accumulate the actual project completion amount;
[0010] The contract engineering quantity plan and completion status comparison and analysis unit is used to compare the planned engineering completion quantity of the contract engineering quantity plan with the actual engineering completion quantity data and generate a project completion progress chart;
[0011] The contract investment plan and completion status comparison analysis unit is used to compare the project investment plan with the actual project completion amount and generate a comparison chart of the project investment amount and the project completion progress.
[0012] Furthermore, the objectives of each project include:
[0013] The estimated daily completion volume of the project and the planned completion date of the project.
[0014] Furthermore, the actual project completion volume is accumulated, including:
[0015] The cumulative amount of the project completed so far and the percentage of the cumulative amount of completion to the planned amount of completion;
[0016] The cumulative amount of work completed so far for the entire project and the percentage of the cumulative amount of work completed to the entire project.
[0017] Further, project milestones include: milestone groups and milestone items;
[0018] Milestone items are symbols that represent the progress of each sub-project;
[0019] A milestone group is a collection of milestone items, and there is a one-to-many relationship between milestone groups and milestone items.
[0020] In the second aspect, a project progress management method based on a milestone prediction model includes:
[0021] Based on the above, a project progress management system based on a milestone prediction model;
[0022] Decompose the entire project into a predetermined number of projects according to the contract and determine the project schedule milestones;
[0023] Use PCA-BP neural network to establish a project progress prediction model to predict the project progress and formulate a contract investment plan and its corresponding contract engineering quantity plan;
[0024] Enter the daily project progress data and accumulate it to generate the actual project completion amount;
[0025] Comparing the planned project completion amount of the contract project quantity plan with the actual project completion amount data, generating a project completion progress chart and displaying the project completion progress chart on a display device;
[0026] Compare the contract investment plan with the actual project completion data, generate a comparison chart of the project investment amount and the project completion progress, and display the comparison chart of the project investment amount and the project completion progress on a display device.
[0027] Furthermore, a PCA-BP neural network is used to establish a project progress prediction model to predict the project progress and formulate a contract investment plan and its corresponding contract engineering quantity plan, including:
[0028] Determine the initial parameters of the PCA-BP neural network model based on the materials, facilities, physical quantities, personnel and environment required for the engineering sub-item process;
[0029] According to the primary parameters, the principal components of the input samples for the PCA-BP neural network model are obtained through PCA data dimensionality reduction. The principal components include: the physical quantity Q of the engineering sub-item, the number of personnel in this process P, the geological and hydrological environment C, the strength E of the machinery in this process, and the strength M of the materials in this process;
[0030] The output value of the PCA-BP neural network model is the normalized duration of the sub-project of the water conservancy project. A three-layer PCA-BP neural network model is established based on the input samples and output values.
[0031] Matlab is used to perform network training operations on actual engineering data samples, and the training set and test set are divided into training set and test set according to a 5:1 ratio. The training set and test set are not repeated, and the PCA-BP neural network model is trained.
[0032] Furthermore, it also includes:
[0033] According to the progress requirements of each sub-project contract settlement and the contract quotation items, the contract settlement amount is calculated separately according to the proportion of the project milestone progress, and summarized as the total settlement amount for settlement.
[0034] Furthermore, enter the daily project progress data, including: project progress and budget consumption progress.
[0035] Furthermore, the planned project completion volume of the contract project quantity plan is compared with the actual project completion volume data, including:
[0036] Calculate the lead or delay of the project based on the accumulated actual project completion volume;
[0037] Generate an estimated project completion date that is different from the planned project completion date based on the project's advance or delay, and calculate the updated project schedule and budget changes based on the estimated project completion date.
[0038] Furthermore, the contract investment plan is compared with the actual project completion data, including:
[0039] Compare the project investment plan with the actual project completion volume to determine whether corrective measures should be taken;
[0040] When corrective measures are taken, a comparison chart of the project investment amount and the project completion progress is generated based on the project changes caused by the corrective measures.
[0041] Further, corrective action project changes include: the expected completion date of the project, project schedule changes, and project budget changes.
[0042] In a third aspect, an electronic device includes a processor, a communication interface, a memory, and a communication bus, wherein the processor, the communication interface, and the memory communicate with each other via the communication bus;
[0043] a memory storing a computer program;
[0044] The processor is used to implement the above-mentioned project progress management method based on the milestone prediction model when executing the computer program stored in the memory.
[0045] In a fourth aspect, a computer-readable storage medium stores a computer program, which, when executed by a processor, implements the above-mentioned project progress management method based on a milestone prediction model.
[0046] The present disclosure has at least the following beneficial effects:
[0047] The present invention decomposes a complete project into multiple projects according to a prescribed format, each project has a predetermined amount of work, and the amount of work corresponds to the step-by-step investment cost, inputs the progress regularly, automatically outputs the progress index, and performs fund management according to the progress. The present invention provides a progress measurement system based on the construction index of the construction amount, which is used to implement intelligent management of construction projects, so that management personnel can grasp the progress of the project in real time, discover and solve problems in time, and adjust the plan in time.
[0048] Other features and advantages of the present disclosure will be described in the following description, and partly become apparent from the description, or be understood by implementing the present disclosure. The purpose and other advantages of the present disclosure can be realized and obtained by the structures indicated in the description and the drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0049] In order to more clearly illustrate the embodiments of the present disclosure or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0050] Figure 1 This is a schematic diagram of the management system structure of an embodiment of the present disclosure;
[0051] Figure 2 This is a flowchart of the management method of the embodiment of the present disclosure;
[0052] Figure 3 This is a schematic diagram of the electronic device structure of the disclosed management system. DETAILED DESCRIPTION
[0053] In order to make the purpose, technical solution and advantages of the embodiments of the present disclosure clearer, the technical solution in the embodiments of the present disclosure will be clearly and completely described below in conjunction with the drawings in the embodiments of the present disclosure. Obviously, the described embodiments are part of the embodiments of the present disclosure, not all of the embodiments. Based on the embodiments in the present disclosure, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present disclosure.
[0054] The construction project schedule is a comprehensive arrangement and planning of the various construction tasks or construction sequence, start time, end time, and the mutual connection between various tasks in the construction project. It is a guiding document that guides the construction sequence and ensures the realization of the project construction goals.
[0055] Schedule management refers to the management of the entire process of preparation, optimization, organization and implementation, planning control and coordination of the project construction schedule.
[0056] like Figure 1 As shown, a project progress management system based on a milestone prediction model includes:
[0057] Plan and progress management unit 101, project image progress control unit 102, contract engineering quantity plan and completion status comparison and analysis unit 103 and contract investment plan and completion status comparison and analysis unit 104;
[0058] The planning and progress management unit 101 is used to decompose the entire project into projects, determine the objectives of each project, the scope of work of each project, and plan project milestones;
[0059] The project image progress control unit 102 is used to record the progress of the project every day and accumulate and generate the actual project completion amount;
[0060] The contract engineering quantity plan and completion status comparison and analysis unit 103 is used to compare the planned engineering completion quantity of the contract engineering quantity plan with the actual engineering completion quantity data and generate an engineering completion progress chart;
[0061] The contract investment plan and completion status comparison and analysis unit 104 is used to compare the project investment plan with the actual project completion amount and generate a comparison chart of the project investment amount and the project completion progress.
[0062] Example:
[0063] The project progress management system based on the milestone prediction model includes: a plan and progress management unit, a project image progress control unit, a contract engineering quantity plan and completion status comparison and analysis unit, and a contract investment plan and completion status comparison and analysis unit;
[0064] The planning and progress management unit breaks down the entire project into projects, determines the objectives of each project, the scope of work of each project, and plans project milestones;
[0065] The project progress control unit is used to record the progress of the project every day and accumulate the actual project completion amount;
[0066] The contract engineering quantity plan and completion status comparison and analysis unit compares the planned engineering completion quantity with the actual engineering completion quantity data and generates an engineering completion progress chart;
[0067] Contract investment plan and completion status comparison analysis unit; compares the project investment plan with the actual project completion amount, and generates a comparison chart of the project investment amount and the project completion progress.
[0068] The objectives of each project include: the estimated daily completion volume of the project and the planned completion date of the project.
[0069] The actual project completion volume generated by cumulative addition includes: the cumulative completion volume of the project to date and the percentage of the cumulative completion volume to the planned completion volume; the cumulative project completion volume of the entire project to date and the percentage of the cumulative project completion volume to the entire project.
[0070] like Figure 2 As shown, a project progress management method based on a milestone prediction model includes:
[0071] Based on the above, a project progress management system based on a milestone prediction model;
[0072] S201, decompose the entire project into a predetermined number of projects according to the contract and determine the project schedule milestones;
[0073] S202, using PCA-BP neural network to establish a project progress prediction model to predict the project progress and formulate a contract investment plan and its corresponding contract engineering quantity plan;
[0074] S203, inputting the daily project progress data, and accumulating and generating the actual project completion amount;
[0075] S204, comparing the planned engineering completion quantity of the contract engineering quantity plan with the actual engineering completion quantity data, generating an engineering completion progress chart and displaying the engineering completion progress chart on a display device;
[0076] S205, comparing the contract investment plan with the actual project completion data, generating a comparison chart of the project investment amount and the project completion progress, and displaying the comparison chart of the project investment amount and the project completion progress on a display device.
[0077] The specific implementation is as follows:
[0078] Decomposing the entire project into a predetermined number of projects in accordance with the contract, defining the schedule milestones of the said projects;
[0079] Among them, the contract milestone settlement function can cover both POI items and HRC items. The newly added contract milestone settlement function expands the breadth of the original business processing and can achieve the transition from milestone settlement to the original settlement business processing through the processing procedure;
[0080] The main functions of contract milestone settlement are:
[0081] (1) Contract milestone definition: including milestone group, milestone item, milestone group classification code, and milestone group and contract association definition;
[0082] (2) Contract milestone settlement: including the application, approval, review and conversion of contract milestone settlement data into contract cost data;
[0083] The construction milestone settlement function is developed based on the characteristics of settlement. It is aimed at construction contracts with many quotation items. Each quotation item must be settled proportionally according to the progress of project equipment installation completion. Each time the user settles, a lot of manual calculations are required to calculate the settlement amount of each quotation item in the electromechanical contract progress.
[0084] The milestone settlement function of the electromechanical contract is to associate each sub-project of the electromechanical contract with the contract quotation item, package them according to the progress requirements of the contract settlement, and perform batch settlement of contract data based on the principle of progress ratio;
[0085] The construction milestone settlement function is developed based on the characteristics of settlement. It is mainly aimed at construction contracts with many quotation items, and each quotation item must be settled proportionally according to the progress of the project equipment installation completion. Each time the user settles, he needs to manually calculate the settlement amount of each quotation item in the electromechanical contract progress.
[0086] The PCA-BP neural network is used to establish a project progress prediction model to predict the project progress and formulate a contract investment plan and its corresponding contract engineering quantity plan, including:
[0087] (1) Determine the model parameters. By combining the factors affecting the progress of actual engineering projects, the model for predicting the construction period of engineering sub-items and processes also considers the following five aspects: materials, facilities, physical quantities, personnel, and environment required for the engineering sub-items and processes;
[0088] (2) Model establishment: Through PCA data dimensionality reduction, the input samples of the BP neural network prediction model are the five principal components obtained by dimensionality reduction using the software SPSS, the physical quantity Q of the engineering sub-item, the number of personnel in this process P, the geological and hydrological environment C, the strength E of the machinery in this process, the strength M of the material in this process, and the neurons as the input layer. The output value of the BP neural network is the normalized duration of the process of the water conservancy project sub-item. In this way, a three-layer BP neural network prediction model is established.
[0089] (3) The network training operation is performed on the actual engineering data samples through the software Matlab 2022a. The division of the training set and the test set is based on the principle of 5:1, and they are not repeated. Because Matlab has the structure of normalization function, the training set and test set matrices are first transposed, the appropriate function is selected, the reasonable operating parameters are set, the output error is calculated, and reasonable adjustments are made while checking the calculation results.
[0090] Enter the daily project progress data, and the project image progress control unit accumulates and generates the actual project completion amount;
[0091] Comparing the planned project completion amount with the actual project completion amount data, generating a project completion progress chart and displaying the project completion progress chart on a display device;
[0092] The contract investment plan is compared with the actual project completion amount, a comparison chart of the project investment amount and the project completion progress is generated, and the comparison chart of the project investment amount and the project completion progress is displayed on a display device.
[0093] like Figure 3 As shown, the present disclosure provides an electronic device, including a processor 301, a communication interface 302, a memory 303 and a communication bus 304, wherein the processor 301, the communication interface 302 and the memory 303 communicate with each other through the communication bus 304;
[0094] Memory 303, storing computer programs;
[0095] The processor 301 is configured to implement the above method when executing the computer program stored in the memory 303 .
[0096] The present disclosure provides a computer-readable storage medium storing a computer program, and the computer program implements the above method when executed by a processor.
[0097] The computer-readable storage medium may be included in the device / apparatus described in the above embodiment; or it may exist independently without being assembled into the device / apparatus. The above computer-readable storage medium carries one or more programs, and when the above one or more programs are executed, the method according to the embodiment of the present disclosure is implemented.
[0098] According to an embodiment of the present disclosure, a computer-readable storage medium may be a non-volatile computer-readable storage medium, for example, may include but is not limited to: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination thereof. In the present disclosure, a computer-readable storage medium may be any tangible medium containing or storing a program that may be used by or in conjunction with an instruction execution system, apparatus, or device.
[0099] Although the present disclosure has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present disclosure.
Claims
1. A project progress management system based on a milestone prediction model, characterized in that: include: Plan and progress management unit, project image progress control unit, contract engineering quantity plan and completion status comparison and analysis unit, and contract investment plan and completion status comparison and analysis unit; The planning and progress management unit is used to break down the entire project into projects, determine the goals of each project, the scope of work of each project, and plan project milestones; The project progress control unit is used to record the progress of the project every day and accumulate the actual project completion amount; The contract engineering quantity plan and completion status comparison and analysis unit is used to compare the planned engineering completion quantity of the contract engineering quantity plan with the actual engineering completion quantity data and generate a project completion progress chart; The contract investment plan and completion status comparison analysis unit is used to compare the project investment plan with the actual project completion amount and generate a comparison chart of the project investment amount and the project completion progress.
2. The project progress management system based on the milestone prediction model according to claim 1 is characterized in that: The objectives of each project include: The estimated daily completion volume of the project and the planned completion date of the project.
3. The project progress management system based on the milestone prediction model according to claim 1, characterized in that: The actual project completion volume is accumulated, including: The cumulative amount of the project completed so far and the percentage of the cumulative amount of completion to the planned amount of completion; The cumulative amount of work completed so far for the entire project and the percentage of the cumulative amount of work completed to the entire project.
4. The project progress management system based on the milestone prediction model according to claim 1, characterized in that: Project milestones, including milestone groups and milestone items; Milestone items are symbols that represent the progress of each sub-project; A milestone group is a collection of milestone items.
5. A project progress management method based on a milestone prediction model, characterized in that: include: A project progress management system based on a milestone prediction model according to any one of claims 1 to 4; Decompose the entire project into a predetermined number of projects according to the contract and determine the project schedule milestones; Use PCA-BP neural network to establish a project progress prediction model to predict the project progress and formulate a contract investment plan and its corresponding contract engineering quantity plan; Enter the daily project progress data and accumulate it to generate the actual project completion amount; Comparing the planned project completion amount of the contract project quantity plan with the actual project completion amount data, generating a project completion progress chart and displaying the project completion progress chart on a display device; Compare the contract investment plan with the actual project completion data, generate a comparison chart of the project investment amount and the project completion progress, and display the comparison chart of the project investment amount and the project completion progress on a display device.
6. A project progress management method based on a milestone prediction model according to claim 5, characterized in that: The PCA-BP neural network is used to establish a project progress prediction model to predict the project progress and formulate a contract investment plan and its corresponding contract engineering quantity plan, including: Determine the initial parameters of the PCA-BP neural network model based on the materials, facilities, physical quantities, personnel and environment required for the engineering sub-item process; According to the primary parameters, the principal components of the input samples for the PCA-BP neural network model are obtained through PCA data dimensionality reduction. The principal components include: the physical quantity Q of the engineering sub-item, the number of personnel in this process P, the geological and hydrological environment C, the strength E of the machinery in this process, and the strength M of the materials in this process; The output value of the PCA-BP neural network model is the normalized duration of the sub-project of the water conservancy project. A three-layer PCA-BP neural network model is established based on the input samples and output values. The Matlab software is used to perform network training operations on actual engineering data samples. The training set and test set are divided into 5:
1. The training set and test set are not repeated, and the PCA-BP neural network model is trained.
7. The project progress management method based on the milestone prediction model according to claim 5 is characterized in that: Compare the planned project completion quantity of the contract project quantity plan with the actual project completion quantity data, generate a project completion progress chart, and then include: According to the progress requirements of each sub-project contract settlement and the contract quotation items, the contract settlement amount is calculated separately according to the proportion of the project milestone progress, and summarized as the total settlement amount for settlement.
8. The project progress management method based on the milestone prediction model according to claim 5 is characterized in that: Enter daily project progress data, including: Project progress and budget consumption progress.
9. The project progress management method based on the milestone prediction model according to claim 5 is characterized in that: Compare the planned works completion data of the contract works quantity plan with the actual works completion data, including: Calculate the lead or delay of the project based on the accumulated actual project completion volume; Generate an estimated project completion date that is different from the planned project completion date based on the project's advance or delay, and calculate the updated project schedule and budget changes based on the estimated project completion date.
10. The project progress management method based on the milestone prediction model according to claim 5, characterized in that: Compare the contract investment plan with the actual project completion data, including: Compare the project investment plan with the actual project completion volume to determine whether corrective measures should be taken; When corrective measures are taken, a comparison chart of the project investment amount and the project completion progress is generated based on the project changes caused by the corrective measures.
11. A project progress management method based on a milestone prediction model according to claim 10, characterized in that: Corrective action project changes include: project expected completion date, project schedule changes, and project budget changes.
12. An electronic device, characterized in that: It includes a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other through the communication bus; a memory storing a computer program; The processor is used to implement a project progress management method based on a milestone prediction model as described in any one of claims 5 to 11 when executing a computer program stored in the memory.
13. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the method for project progress management based on a milestone prediction model described in any one of claims 5 to 11 is implemented.
Citation Information
Patent Citations
Engineering project construction process evaluation method
CN106991534A
Method for monitoring progress of power grid project
CN107977785A
Supervision method and risk assessment method of construction process of engineering project
CN109064077A
Power transmission and transformation project visual management method and system based on GIS + BIM technology