Lightering system and method for liquid cargo tank LNG in LNG ship gas test process

By combining the immersion and testing pump time in the LNG vessel cargo tank, and using parallel connected cargo pumps and sweeping pumps, the gas test and pumping of the cargo tank are synchronized, and the problem of low efficiency of sweeping pumps is solved. Improve the overall barrier efficiency and shorten the trial flight cycle.

CN118977820AActive Publication Date: 2024-11-19HUDONG ZHONGHUA SHIPBUILDINGGROUP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411260399.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-11-19
Estimated Expiration
2044-09-10

AI Technical Summary

Technical Problem

During the cargo tank barge transportation of LNG ships, the low efficiency of the sweeping pump leads to a long barge transportation time, which increases the overall cost and cycle of trial sailing.

Method used

By changing the transport process, the liquid is transported to the immersion liquid level first and then transferred to the next tank. Combined the immersion pump time and the time of the test pump, and use the parallel connection between the cargo pump and the sweeping pump to realize the cargo tank gas test and Pumping is carried out simultaneously to reduce the transit time.

Benefits of technology

It improves LNG pumping efficiency, shortens the gas test cycle, reduces the trial cost, and improves the quality of the barrier.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118977820A_ABST
    Figure CN118977820A_ABST
Patent Text Reader

Abstract

The invention discloses a lightering system for liquid cargo tank LNG in the LNG ship gas test process, the system comprises a liquid cargo header pipe, liquid cargo branch pipes, a sweeping header pipe and sweeping branch pipes, the liquid cargo header pipe is connected with the liquid cargo branch pipes, the sweeping header pipe is connected with the sweeping branch pipes, the liquid cargo branch pipes and the sweeping branch pipes are respectively arranged in LNG cabins, the liquid cargo branch pipes in the LNG cabins are connected in parallel, and the sweeping branch pipes in the LNG cabins are connected in parallel. The sweeping branch pipes in each LNG cabin are connected in parallel, injection pipes are further arranged in the LNG cabins, the injection pipes are connected with the liquid cargo header pipe and the sweeping header pipe, liquid cargo pumps are arranged at the bottoms of the liquid cargo branch pipes, sweeping pumps are arranged at the bottoms of the sweeping branch pipes, and valves are arranged on the liquid cargo branch pipes, the sweeping branch pipes and the injection pipes; and valves are arranged on the liquid cargo header pipe and the sweeping header pipe. According to the method, the liquid cargo tank gas test and LNG pumping are carried out at the same time, the problem that the efficiency is low when a sweeping pump pumps LNG is solved, the LNG pumping efficiency is improved, meanwhile, the liquid cargo tank gas test is completed, the gas test period is shortened, and the trial flight cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of shipbuilding, and in particular relates to a system and method for transferring LNG in a liquid cargo tank during a gas test of an LNG ship. Background Art

[0002] The gas trial stage is also one of the most difficult stages in the overall construction process. At the same time, the gas trial stage is also a more expensive stage in the entire ship construction stage.

[0003] The main purpose of the cargo tank transfer stage is to test the performance of each pump in the cargo tank of the LNG ship. Generally speaking, there are two cargo pumps and one stripping pump in the cargo tank. The cargo pump is used to quickly transfer the LNG liquid in the cargo tank, so the liquid level height (hereinafter referred to as the start-up liquid level) is relatively high, but the speed of transferring the liquid is faster and the transfer time is shorter. The stripping pump is used to transfer the LNG liquid that other pumps in the tank cannot transfer, so the required start-up liquid level is lower, but the speed of transferring the liquid is slower and the transfer time is longer. Before starting each pump, each pump needs to be completely immersed in LNG liquid for more than one and a half hours. Therefore, the start-up liquid level is also called the liquid level at which the pump is completely immersed (hereinafter referred to as the immersion liquid level). Therefore, the total time of the transfer process between cargo tanks in this article includes the transfer time between each cargo tank and the immersion time before starting the pump.

[0004] The present invention changes the previous transfer process and the idea. The invention does not need to transfer the liquid in one tank to another tank completely. Instead, the remaining liquid is transferred to the next target liquid level after the target tank is transferred to the submerged liquid level, that is, first transfer from tank 1 to tank 4, and when tank 4 reaches the submerged liquid level, the remaining liquid is transferred to tank 2. In this way, the time of the submerged pump and the time of the test pump can be overlapped with the time of transferring the remaining liquid to the next target tank, thereby reducing the transfer time increased by the slow speed of the stripping pump, thereby reducing the time required for the overall transfer process and increasing the quality of transfer. Summary of the invention

[0005] The purpose of the present invention is to overcome the deficiencies in the above-mentioned prior art and to provide a system and method for transferring LNG in a liquid cargo tank during the gas trial of an LNG ship. The present invention performs a gas trial of the liquid cargo tank and LNG pumping simultaneously, thereby avoiding the problem of low efficiency of the stripping pump when pumping LNG. While improving the LNG pumping efficiency, the gas trial of the liquid cargo tank is completed, the gas trial cycle is shortened, and the cost of the sea trial is reduced.

[0006] In order to achieve the above invention purpose, the technical solution provided by the present invention is as follows:

[0007] A system for transferring LNG in a liquid cargo tank during a gas test of an LNG ship, the system comprising a liquid cargo main pipe, a liquid cargo branch pipe, a tank stripping main pipe and a tank stripping branch pipe, the liquid cargo main pipe is connected to the liquid cargo branch pipe, the tank stripping main pipe is connected to the tank stripping branch pipe, liquid cargo branch pipes and tank stripping branch pipes are respectively arranged in the LNG tank, the liquid cargo branch pipes in each LNG tank are connected in parallel, the tank stripping branch pipes in each LNG tank are connected in parallel, injection pipes are also arranged in the LNG tank, the injection pipes are respectively connected to the liquid cargo main pipe and the tank stripping main pipe, a liquid cargo pump is arranged at the bottom of the liquid cargo branch pipe, a tank stripping pump is arranged at the bottom of the tank stripping branch pipe, valves are arranged on the liquid cargo branch pipe, the tank stripping branch pipe and the injection pipe; valves are arranged on the liquid cargo main pipe and the tank stripping main pipe.

[0008] Furthermore, when the injection pipe in the LNG tank is connected to the tank stripping main pipe, the injection pipe and the tank stripping branch pipe are connected in parallel; when the injection pipe in the LNG tank is connected to the liquid cargo main pipe, the injection pipe and the liquid cargo branch pipe are connected in parallel.

[0009] A method for transferring LNG from a liquid cargo tank during a gas test of an LNG ship, the method specifically comprising the following steps:

[0010] S1. Prepare a LNG transfer system for a liquid cargo tank during a gas test of an LNG ship, the system comprising a liquid cargo main pipe, a liquid cargo branch pipe, a tank stripping main pipe and a tank stripping branch pipe, the liquid cargo main pipe is connected to the liquid cargo branch pipe, the tank stripping main pipe is connected to the tank stripping branch pipe, liquid cargo branch pipes and tank stripping branch pipes are respectively arranged in the LNG tank, the liquid cargo branch pipes in each LNG tank are connected in parallel, the tank stripping branch pipes in each LNG tank are connected in parallel, an injection pipe is further arranged in the LNG tank, the injection pipe is respectively connected to the liquid cargo main pipe and the tank stripping main pipe, a liquid cargo pump is arranged at the bottom of the liquid cargo branch pipe, a tank stripping pump is arranged at the bottom of the tank stripping branch pipe, valves are arranged on the liquid cargo branch pipe, the tank stripping branch pipe and the injection pipe; valves are arranged on the liquid cargo main pipe and the tank stripping main pipe;

[0011] S2, pump the LNG used for the test into the first cargo tank. When the LNG pumped into the first cargo tank completely submerges the cargo pump and the stripping pump in the first cargo tank, stop pumping LNG into the first cargo tank and start the gas test of the first cargo tank;

[0012] S3, when the gas test of the first liquid cargo tank is completed, the valve on the liquid cargo branch pipe in the first liquid cargo tank is opened, the valve of the liquid cargo main pipe is started, the liquid cargo pump in the first liquid cargo tank is started, and the liquid cargo pump injects the LNG in the first liquid cargo tank into the fourth liquid cargo tank through the liquid cargo main pipe and the injection pipe in the fourth liquid cargo tank;

[0013] S4, when the LNG in the fourth cargo tank completely submerges the cargo pump and the stripping pump in the fourth cargo tank, close the valve on the injection pipe in the fourth cargo tank, open the valve on the injection pipe in the second cargo tank, and the LNG in the first cargo tank is pumped to the second cargo tank through the cargo pump and the stripping pump; the fourth cargo tank is subjected to gas test;

[0014] S5, when the gas test of the fourth cargo tank is completed, the cargo pump in the fourth cargo tank pumps LNG to the second cargo tank. When the cargo pump and the stripping pump in the second cargo tank are completely submerged by the LNG in the second cargo tank, the valve on the injection pipe in the second cargo tank is closed, and the valve on the injection pipe in the third cargo tank is opened. The LNG in the fourth cargo tank is pumped to the second cargo tank by the cargo pump and the stripping pump; the second cargo tank is subjected to gas test;

[0015] S6. After the gas test of the second liquid cargo tank is completed, the cargo pump and stripping pump in the second liquid cargo tank pump all the LNG in the second liquid cargo tank to the third liquid cargo tank. When the LNG in the third liquid cargo tank completely immerses the cargo pump and stripping pump in the third liquid cargo tank, the third liquid cargo tank is subjected to gas test to complete the gas test of all liquid cargo tanks.

[0016] Furthermore, when the liquid cargo pump is pumping LNG, if the liquid cargo pump cannot pump the LNG in the liquid cargo tank to another liquid cargo tank, the liquid cargo pump is turned off, the stripping pump is started, and the valve on the stripping main pipe is opened, and all the LNG in the liquid cargo tank is pumped into another liquid cargo tank through the stripping pump.

[0017] Furthermore, after the gas test of the liquid cargo tank is completed, all the LNG is transported back to the shore station.

[0018] Based on the above technical solution, the present invention patented a system and method for transferring LNG in a liquid cargo tank during the gas test of an LNG ship, and achieved the following technical advantages through practical application:

[0019] 1. The present invention provides a method for transferring LNG in a liquid cargo tank during a gas test of an LNG ship. The method performs a gas test of the liquid cargo tank and LNG pumping simultaneously, thereby avoiding the problem of low efficiency of a stripping pump when pumping LNG. While improving the LNG pumping efficiency, the gas test of the liquid cargo tank is completed, the gas test period is shortened, and the cost of the sea trial is reduced.

[0020] 2. The present invention provides a method for transferring LNG from a liquid cargo tank during a gas test of an LNG ship, which shortens the gas test by transferring LNG without changing the original transfer pipeline, thereby saving the gas test cycle and cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1The present invention is a structural diagram of a transfer pipeline in a transfer system of LNG in a liquid cargo tank used in a gas test process of an LNG ship. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is described below by the specific examples shown in the accompanying drawings. However, it should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.

[0023] like Figure 1 The present invention belongs to a transshipment system for LNG in a liquid cargo tank during a gas test of an LNG ship, the system comprising a liquid cargo main pipe 31, a liquid cargo branch pipe 32, a tank stripping main pipe 41 and a tank stripping branch pipe 42, the liquid cargo main pipe 31 is connected to the liquid cargo branch pipe 32, the tank stripping main pipe 41 is connected to the tank stripping branch pipe 42, the liquid cargo branch pipe 32 and the tank stripping branch pipe 42 are respectively arranged in the LNG tank, the liquid cargo branch pipe 32 in each LNG tank is connected in parallel, the tank stripping branch pipe 42 in each LNG tank is connected in parallel, an injection pipe 5 is also arranged in the LNG tank, the injection pipe 5 is respectively connected to the liquid cargo main pipe 31 and the tank stripping main pipe 41, a liquid cargo pump 1 is arranged at the bottom of the liquid cargo branch pipe 32, a tank stripping pump 2 is arranged at the bottom of the tank stripping branch pipe 42, valves 6 are arranged on the liquid cargo branch pipe 32, the tank stripping branch pipe 42 and the injection pipe 5; valves 6 are arranged on the liquid cargo main pipe 31 and the tank stripping main pipe 41.

[0024] Furthermore, when the injection pipe 5 in the LNG tank is connected to the tank stripping main pipe 41, the injection pipe 5 and the tank stripping branch pipe 42 are connected in parallel, and when the injection pipe 5 in the LNG tank is connected to the liquid cargo main pipe 31, the injection pipe 5 and the liquid cargo branch pipe 32 are connected in parallel.

[0025] A method for transferring LNG from a liquid cargo tank during a gas test of an LNG ship, the method specifically comprising the following steps:

[0026] S1, prepare a LNG transfer system for a liquid cargo tank during a gas test of an LNG ship, the system comprising a liquid cargo main pipe 31, a liquid cargo branch pipe 32, a tank stripping main pipe 41 and a tank stripping branch pipe 42, the liquid cargo main pipe 31 is connected to the liquid cargo branch pipe 32, the tank stripping main pipe 41 is connected to the tank stripping branch pipe 42, the liquid cargo branch pipe 32 and the tank stripping branch pipe 42 are respectively arranged in the LNG tank, the liquid cargo branch pipe 32 in each LNG tank is connected in parallel, the tank stripping branch pipe 42 in each LNG tank is connected in parallel, an injection pipe 5 is also arranged in the LNG tank, the injection pipe 5 is respectively connected to the liquid cargo main pipe 31 and the tank stripping main pipe 41, a liquid cargo pump 1 is arranged at the bottom of the liquid cargo branch pipe 32, a tank stripping pump 2 is arranged at the bottom of the tank stripping branch pipe 42, the liquid cargo branch pipe 32, the tank stripping branch pipe 42 and the injection pipe 5 are all provided with valves 6; the liquid cargo main pipe 31 and the tank stripping main pipe 41 are provided with valves 6;

[0027] S2, pumping LNG for testing into the first cargo tank pump 71. When the LNG pumped into the first cargo tank completely submerges the cargo pump 1 and the stripping pump 2 in the first cargo tank, stopping the LNG pumping into the first cargo tank pump 71 and starting the gas test of the first cargo tank;

[0028] S3, when the gas test of the first liquid cargo tank is completed, the valve 6 on the liquid cargo branch pipe 32 in the first liquid cargo tank is opened, the valve 6 of the liquid cargo main pipe 31 is started, and the liquid cargo pump 1 in the first liquid cargo tank is started, and the liquid cargo pump 1 injects the LNG in the first liquid cargo tank into the fourth liquid cargo tank 74 through the liquid cargo main pipe 31 and the injection pipe 5 in the fourth liquid cargo tank 74;

[0029] S4, when the LNG in the fourth cargo tank 74 completely submerges the cargo pump 1 and the stripping pump 2 in the fourth cargo tank 74, the valve 6 on the injection pipe 5 in the fourth cargo tank 74 is closed, and the valve 6 on the injection pipe 5 in the second cargo tank 72 is opened, and the LNG in the first cargo tank is pumped to the second cargo tank 72 through the cargo pump 1 and the stripping pump 2; the fourth cargo tank 74 is subjected to a gas test;

[0030] S5, when the gas test of the fourth liquid cargo tank 74 is completed, the liquid cargo pump 1 in the fourth liquid cargo tank 74 pumps the LNG into the second liquid cargo tank 72. When the LNG in the second liquid cargo tank 72 completely immerses the liquid cargo pump 1 and the stripping pump 2 in the second liquid cargo tank 72, the valve 6 on the injection pipe 5 in the second liquid cargo tank 72 is closed, and the valve 6 on the injection pipe 5 in the third liquid cargo tank 73 is opened. The LNG in the fourth liquid cargo tank 74 is pumped into the second liquid cargo tank 72 by the liquid cargo pump 1 and the stripping pump 2; the second liquid cargo tank 72 is subjected to a gas test;

[0031] S6. After the gas test of the second liquid cargo tank 72 is completed, the cargo pump 1 and the stripping pump 2 in the second liquid cargo tank 72 pump all the LNG in the second liquid cargo tank 72 to the third liquid cargo tank 73. When the LNG in the third liquid cargo tank 73 completely immerses the cargo pump 1 and the stripping pump 2 in the third liquid cargo tank 73, the third liquid cargo tank 73 is subjected to a gas test to complete the gas test of all liquid cargo tanks.

[0032] When the liquid cargo pump 1 is pumping LNG, if the liquid cargo pump 1 cannot pump the LNG in the liquid cargo tank to another liquid cargo tank, the liquid cargo pump 1 is closed, the stripping pump 2 is started, and the valve 6 on the stripping main pipe 41 is opened, and all the LNG in the liquid cargo tank is pumped into another liquid cargo tank through the stripping pump 2.

[0033] After the gas test of the liquid cargo tank is completed, all the LNG is transported back to the shore station.

[0034] Example

[0035] Step 1: Taking the common 173,000 cubic large LNG carrier in China as an example, during the process of loading LNG into the cargo tank, since the capacity of tank 1 is small, less liquid can be used to reach the required liquid level of all pumps in the cargo tank. Therefore, LNG is loaded into tank 1 first, and finally 300m3 of LNG is needed. 3 ;

[0036] Step 2: After the test of all pumps in tank 1 is completed, liquid will be transferred to tank 4 through liquid cargo pump 1;

[0037] Step 3: When the LNG liquid is transferred to the 4th tank by the liquid cargo pump 1 and reaches the specified liquid level of 1.94m and the liquid level in the 1st tank is lower than 1m, the stripping pump 2 is started. The liquid transferred by the stripping pump 2 is transferred to the 2nd tank instead of continuing to the 4th tank.

[0038] Step 4: After the pump test of cabin 4 is completed, transfer the liquid from cabin 4 to cabin 2, and transfer the excess liquid to cabin 3.

[0039] Step 5. Finally, transfer all the liquid in tank 2 to tank 3.

[0040] Table 1 Conventional cargo tank lighterage test time

[0041]

[0042]

[0043] Table 2: Tanker test time of the liquid cargo tank in this embodiment

[0044] project Time (h) 1. Tank pump submerged 1.5 1. Tank pump test 0.5 Transfer from cabin 1 to cabin 4 and cabin 2 1 4-compartment pump submersion 1.5 4. Tank Pump Test 0.5 Transfer from cabin 4 to cabin 2 and 3 1 2-compartment pump submerged 1.5 2nd cabin pump test 0.5 The remaining part of cabin 2 is transferred to cabin 3 1 3-tank pump submerged 1.5 3. Tank Pump Test 0.5 3 cabins transferred to gas station 1 total 12

[0045] It can be seen from Table 1 and Table 2 that the time required for the lighterage trial test using this method is reduced by more than four hours compared with the traditional method, which saves the trial cost and improves the efficiency of the trial.

[0046] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.

Claims

1. A transfer system for LNG in a liquid cargo tank during a gas test of an LNG ship, characterized in that: The system comprises a liquid cargo main pipe, a liquid cargo branch pipe, a tank stripping main pipe and a tank stripping branch pipe, wherein the liquid cargo main pipe is connected to the liquid cargo branch pipe, the tank stripping main pipe is connected to the tank stripping branch pipe, liquid cargo branch pipes and tank stripping branch pipes are respectively arranged in the LNG tank, the liquid cargo branch pipes in each LNG tank are connected in parallel, the tank stripping branch pipes in each LNG tank are connected in parallel, injection pipes are also arranged in the LNG tank, the injection pipes are respectively connected to the liquid cargo main pipe and the tank stripping main pipe, a liquid cargo pump is arranged at the bottom of the liquid cargo branch pipe, a tank stripping pump is arranged at the bottom of the tank stripping branch pipe, valves are arranged on the liquid cargo branch pipe, the tank stripping branch pipe and the injection pipe; valves are arranged on the liquid cargo main pipe and the tank stripping main pipe.

2. The system for transferring LNG from a liquid cargo tank during a gas test of an LNG ship according to claim 1, characterized in that: When the injection pipe in the LNG tank is connected to the tank stripping main pipe, the injection pipe and the tank stripping branch pipe are connected in parallel; when the injection pipe in the LNG tank is connected to the liquid cargo main pipe, the injection pipe and the liquid cargo branch pipe are connected in parallel.

3. A method for transferring LNG from a liquid cargo tank during a gas test of an LNG ship, characterized in that: The method specifically comprises the following steps: S1. Prepare a LNG transfer system for a liquid cargo tank during a gas test of an LNG ship, the system comprising a liquid cargo main pipe, a liquid cargo branch pipe, a tank stripping main pipe and a tank stripping branch pipe, the liquid cargo main pipe is connected to the liquid cargo branch pipe, the tank stripping main pipe is connected to the tank stripping branch pipe, liquid cargo branch pipes and tank stripping branch pipes are respectively arranged in the LNG tank, the liquid cargo branch pipes in each LNG tank are connected in parallel, the tank stripping branch pipes in each LNG tank are connected in parallel, an injection pipe is further arranged in the LNG tank, the injection pipe is respectively connected to the liquid cargo main pipe and the tank stripping main pipe, a liquid cargo pump is arranged at the bottom of the liquid cargo branch pipe, a tank stripping pump is arranged at the bottom of the tank stripping branch pipe, valves are arranged on the liquid cargo branch pipe, the tank stripping branch pipe and the injection pipe; valves are arranged on the liquid cargo main pipe and the tank stripping main pipe; S2, pump the LNG used for the test into the first cargo tank. When the LNG pumped into the first cargo tank completely submerges the cargo pump and the stripping pump in the first cargo tank, stop pumping LNG into the first cargo tank and start the gas test of the first cargo tank; S3, when the gas test of the first liquid cargo tank is completed, the valve on the liquid cargo branch pipe in the first liquid cargo tank is opened, the valve of the liquid cargo main pipe is started, the liquid cargo pump in the first liquid cargo tank is started, and the liquid cargo pump injects the LNG in the first liquid cargo tank into the fourth liquid cargo tank through the liquid cargo main pipe and the injection pipe in the fourth liquid cargo tank; S4, when the LNG in the fourth cargo tank completely submerges the cargo pump and the stripping pump in the fourth cargo tank, close the valve on the injection pipe in the fourth cargo tank, open the valve on the injection pipe in the second cargo tank, and the LNG in the first cargo tank is pumped to the second cargo tank through the cargo pump and the stripping pump; the fourth cargo tank is subjected to gas test; S5, when the gas test of the fourth cargo tank is completed, the cargo pump in the fourth cargo tank pumps LNG to the second cargo tank. When the cargo pump and the stripping pump in the second cargo tank are completely submerged by the LNG in the second cargo tank, the valve on the injection pipe in the second cargo tank is closed, and the valve on the injection pipe in the third cargo tank is opened. The LNG in the fourth cargo tank is pumped to the second cargo tank by the cargo pump and the stripping pump; the second cargo tank is subjected to gas test; S6. After the gas test of the second liquid cargo tank is completed, the cargo pump and stripping pump in the second liquid cargo tank pump all the LNG in the second liquid cargo tank to the third liquid cargo tank. When the LNG in the third liquid cargo tank completely immerses the cargo pump and stripping pump in the third liquid cargo tank, the third liquid cargo tank is subjected to gas test to complete the gas test of all liquid cargo tanks.

4. The method for transferring LNG from a liquid cargo tank during a gas test of an LNG ship according to claim 3, characterized in that: When the liquid cargo pump is pumping LNG, if the liquid cargo pump cannot pump the LNG in the liquid cargo tank to another liquid cargo tank, the liquid cargo pump is turned off, the stripping pump is started, and the valve on the stripping main pipe is opened, and all the LNG in the liquid cargo tank is pumped into another liquid cargo tank through the stripping pump.

5. The method for transferring LNG from a liquid cargo tank during a gas test of an LNG ship according to claim 3, characterized in that: After the gas test of the liquid cargo tank is completed, all the LNG is transported back to the shore station.

Citation Information

Patent Citations

  • LNG ship ballast tank strength test method

    CN112098222A

  • Integrated trial flight method for conventional trial flight and gas trial flight of LNG (Liquefied Natural Gas) ship

    CN117382837A

  • Method for installing liquid cargo pipe of LNG (Liquefied Natural Gas) ship and testing air tightness of liquid cargo pipe

    CN117848622A

  • Gas Test Method Of Ship On Near-shore

    KR1020140130996A