Supporting and reinforcing construction method for reducing vehicle load safety influence on sludge stratum

By setting up isolation and reinforcement areas on the outside of the foundation pit, the cured slurry and steel pipe caps are used to reduce the impact of vehicle load on the silt formation, and a stable foundation pit support structure is formed, which solves the problem of vehicle load on the stability of foundation pits in the silt formation. , improves the stability of foundation pit and construction economy.

CN118979420APending Publication Date: 2024-11-19SHENZHEN HONGYEJI GEOTECHNICAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411058992.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

In the prior art, vehicle load has a great impact on the stability of the foundation pit in the silt formation, resulting in excessive deformation of the support structure and unstable deep foundation pit, and excessively large and uneconomical design reserves, and unstable dynamic load transmission.

Method used

Set up isolation areas and reinforcement areas on the outside of the foundation pit, and form a cured layer and concrete surface layer through isolation piles and reinforced piles. Use the cured slurry and steel pipe caps to reduce the impact of load on the sludge layer, and evenly distribute the load through the isolation wall to reduce the amount of load. The impact of the support structure.

Benefits of technology

It effectively reduces the impact of vehicle load on the silt formation, reduces the lateral deformation of the foundation pit, improves the stability of the foundation pit, and improves the construction economy through the reusable material.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979420A_ABST
    Figure CN118979420A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of foundation pit supporting, and discloses a supporting and reinforcing construction method for reducing vehicle load safety influence on a sludge stratum, which comprises the following steps of: 1) determining a road construction area which comprises an isolation area and a reinforcing area along a direction far away from a foundation pit; (2) a plurality of isolation piles are formed in the isolation area through construction, and every two adjacent isolation piles are engaged with each other to form a linear isolation wall; 3) solidifying the original soil to form a solidified layer; (4) a plurality of reinforcing piles are constructed and formed on the curing layer, in the process that the steel pipe is inserted into the reinforcing construction position, a steel pipe cap is fixedly connected to the top of the steel pipe, and when the top of the steel pipe cap is flush with the top of the curing layer, downward insertion of the steel pipe is stopped, and the reinforcing piles are formed; (5) geogrids are laid on the reinforcing layer, then graded broken stones are laid on the geogrids, and a broken stone hardcore is formed; and (6) concrete is poured and cured, a concrete surface layer is formed, and the broken stone hardcore is covered with the concrete surface layer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention patent relates to the technical field of foundation pit support, specifically, to a support and reinforcement construction method for reducing the safety impact of vehicle loads in silt formations. Background Art

[0002] During the construction process, in order to speed up the progress of the project, temporary roads are often needed to be built around the foundation pit for heavy construction vehicles to use, which poses a challenge to the stability of the foundation pit.

[0003] The silt soil has low shear strength, high sensitivity, poor permeability, high compressibility and porosity, and is very prone to problems such as excessive deformation of the support structure, uplift of the pit bottom, and excessive subsidence of the surrounding surface. In addition, the vehicle load has the characteristics of instantaneous change, reciprocating, and uneven size, which further amplifies the impact on the deformation of the foundation pit retaining structure. Figure 1 .

[0004] In the prior art, the vehicle load is simply equivalent to a uniformly distributed static load, and the support design reserve is blindly increased in order to reduce the impact of the vehicle dynamic load. The foundation pit design based on this has an excessively large design reserve, which is not economical. On the other hand, the dynamic load is still unstable and will be transmitted to the support structure, which will still affect the soft soil on the side wall, thereby affecting the stability of the deep foundation pit and causing problems such as excessive deformation of the silt stratum. Summary of the invention

[0005] The purpose of the present invention is to provide a support and reinforcement construction method for reducing the safety impact of vehicle loads in silt strata, aiming to solve the problem in the prior art that vehicle loads have a great impact on the stability of foundation pits in silt strata.

[0006] The present invention is achieved by a support and reinforcement construction method for reducing the safety impact of vehicle load in silt strata, comprising the following construction steps:

[0007] 1) Determine a road construction area outside the foundation pit, a support structure is provided on the periphery of the foundation pit, the road construction area is located outside the support structure, and in a direction away from the foundation pit, the road construction area includes an isolation area and a reinforcement area, and the isolation area is located between the support structure and the reinforcement area;

[0008] 2) constructing a plurality of isolation piles in the isolation area, wherein adjacent isolation piles engage with each other to form a straight-line isolation wall, and the bottom of the isolation piles passes through the silt layer;

[0009] 3) Providing an excavator, wherein the excavator is connected to a mixing head, wherein the mixing head is connected to a grouting pipe, and the soil on the road construction area is stirred by the mixing head, and a solidifying slurry is sprayed into the soil through the grouting pipe, wherein the solidifying slurry is stirred and mixed with the soil to form a solidified layer;

[0010] 4) Determine a plurality of reinforcement construction positions on the solidified layer of the reinforcement area, insert steel pipes into the reinforcement construction positions using a driving and pulling machine to form reinforcement piles, wherein the bottom of the reinforcement pile passes through the silt layer, and the upper part of the reinforcement pile is located in the solidified layer;

[0011] During the process of inserting the steel pipe at the reinforcement construction site, a steel pipe cap is fixedly connected to the top of the steel pipe, and when the top of the steel pipe cap is flush with the top of the solidified layer, the steel pipe is stopped from being inserted to form the reinforcement pile;

[0012] 7) laying a geogrid on the reinforcement layer, and then spreading graded crushed stone on the geogrid to form a crushed stone cushion layer, wherein the geogrid is fixed at the bottom of the crushed stone cushion layer;

[0013] 8) A formwork is set up on the road construction area, the formwork surrounds a pouring area, concrete is poured in the pouring area, and cured to form a concrete surface layer, and the concrete surface layer covers a crushed stone cushion layer.

[0014] Optionally, in the construction step 2), isolation piles are constructed in the isolation area using a pile mixing machine; the pile mixing machine is connected to the grouting pipe, and the pile mixing machine has a mixing drill bit. During the process of mixing and drilling in the soil of the isolation area using the mixing drill bit, solidifying slurry is sprayed into the soil through the grouting pipe, and the solidifying slurry is mixed with the soil in the isolation area to form the isolation piles.

[0015] Optionally, the solidification slurry includes cement, slag powder, gypsum, complex salt and water.

[0016] Optionally, in the construction step 2), a plurality of steel bars are inserted into the top of the isolation pile, the lower portion of the steel bars is inserted into the isolation pile, and the upper portion of the steel bars is exposed above the isolation pile to form a connecting section, and the outer end of the connecting section is bent downward in a bent shape.

[0017] Optionally, in the construction step 6), the connection section is located in the pouring area, and after the concrete surface layer is formed by curing, the connection section is inserted into the concrete surface layer.

[0018] Optionally, in step 5), the graded crushed stone spread on the geogrid is compacted using compaction equipment.

[0019] Optionally, in step 6), a plurality of anti-slip grooves are constructed on the surface of the concrete surface layer.

[0020] Optionally, the steel pipe cap includes a pressure plate, the top of the pressure plate has a flat top surface, the bottom of the pressure plate has a mounting ring formed by a downward protrusion, the mounting ring is located in the middle of the pressure plate, and the mounting ring encloses a mounting area;

[0021] In step 4), the top of the steel pipe is embedded into the installation area, and then the steel pipe and the steel pipe cap are fixedly connected by welding; in the process of embedding the steel pipe into the reinforcement construction position, when the top surface is flush with the solidified layer, the downward pressure on the steel pipe is stopped.

[0022] Optionally, a central screw hole is provided in the middle of the pressure plate, the central screw hole passes through the pressure plate from top to bottom, and the bottom of the central screw hole is connected to the installation area;

[0023] In the step 5), after the civil engineering grid is laid, a center bar is screwed into the center screw hole, and an elastic layer is provided at the bottom of the center bar, and the elastic layer is pressed against the top of the steel pipe, and the elastic layer is in a compressed state;

[0024] The upper part of the center bar passes through the geogrid to form an upper extension section, and the middle part of the upper extension section radially expands outward to form a positioning ring; in the step 5), when the gravel cushion layer is formed, the bottom of the positioning ring is pressed against the top of the gravel cushion layer;

[0025] A top cover is provided on the top of the upper extension section, and a concave groove is formed on the top of the top cover. In the step 6), during the process of pouring concrete in the pouring area, the concrete fills the concave groove.

[0026] Optionally, the outer periphery of the pressure plate has an annular edge region, the edge region is provided with a plurality of edge holes, and the plurality of edge holes are arranged at intervals around the circumference of the pressure plate;

[0027] In step 5), after laying the geogrid, the side strips are screwed into the edge holes, the bottom of the side strips are embedded in the edge holes, the upper part of the side strips passes through the geogrid, and the top of the side strips is provided with a fan-shaped plate; the bottom of the fan-shaped plate is connected to the side strip, and the top of the fan-shaped plate is arranged to extend upward at an angle, and the width of the fan-shaped plate gradually increases from bottom to top; when the side strips are fixedly connected to the pressure plate, the fan-shaped plate is arranged to be inclined toward the isolation wall from bottom to top.

[0028] Compared with the prior art, the support reinforcement construction method for reducing the safety impact of vehicle load in silt strata provided by the present invention, the reinforcement piles pass through the silt layer, and the upper load can be transferred to the solid soil layer below the silt layer, reducing the impact of the load on the silt soil layer, and reducing the lateral deformation of the foundation pit caused by the weak soil layer, thereby ensuring the stability of the foundation pit. In addition, by connecting a steel pipe cap to the top of the steel pipe, the load-bearing area of ​​the upper part of the steel pipe is increased, and the dynamic load of the vehicle is transferred downward to act on the steel pipe cap, and then transferred downward along the reinforcement pile to the solid soil layer. The load on the soft soil layer is weakened and the deformation is reduced. At the same time, the isolation piles form a uniform "isolation wall", which can further redistribute the load that has been evenly transmitted downward on the isolation pile wall, reducing the load that finally falls on the support structure and making it more uniform, and the impact on the support structure is also smaller.

[0029] Then, the construction materials can be reused to increase their use value. The concrete surface layer is removed with a blasting machine, the gravel cushion layer is removed with an excavator, and the steel caps and steel pipes can be collected and reused. In this way, the temporary road can better bear the dynamic load of vehicles, and can reduce and balance the dynamic load, reduce the range of variation, and transfer the load downward more evenly, ultimately reducing the impact on the deep foundation pit. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a schematic diagram of load transfer of a construction vehicle provided by the present invention;

[0031] Figure 2 It is a schematic flow chart of a support and reinforcement construction method for reducing the safety impact of vehicle load in a silt formation provided by the present invention;

[0032] Figure 3 It is a structural schematic diagram of the support structure, isolation piles, reinforcement piles, solidification layer, geogrid, crushed stone cushion layer and concrete surface layer provided by the present invention;

[0033] Figure 4 It is a schematic diagram of the structure of the reinforcement pile, steel pipe cap, solidification layer, geogrid, crushed stone cushion layer and concrete surface layer provided by the present invention;

[0034] Figure 5 It is a plan schematic diagram of the concrete surface layer provided by the present invention;

[0035] Figure 6 It is a schematic diagram of the arrangement of the steel pipe cap, the isolation wall and the reinforcement structure provided by the present invention;

[0036] Figure 7 It is a schematic diagram of the arrangement of the reinforcement piles, isolation walls and reinforcement structures provided by the present invention;

[0037] Figure 8 It is a three-dimensional schematic diagram of the steel pipe cap provided by the present invention;

[0038] Fig. 9 It is a structural schematic diagram of the isolation pile provided by the present invention;

[0039] Fig.10 It is a cross-sectional schematic diagram of the reinforcement pile, steel pipe cap, center strip, side strip, solidification layer, geogrid, crushed stone cushion layer and concrete surface layer provided by the present invention; DETAILED DESCRIPTION

[0040] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0041] The implementation of the present invention is described in detail below in conjunction with specific embodiments.

[0042] The same or similar numbers in the drawings of this embodiment correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0043] Reference Figure 1-10 The figure shows a preferred embodiment of the present invention.

[0044] The support and reinforcement construction method for reducing the safety impact of vehicle load in silt strata provided by the present invention comprises the following construction steps:

[0045] 1) A road construction area is determined outside the foundation pit. A support structure 100 is provided on the periphery of the foundation pit. The road construction area is located outside the support structure 100. In the direction away from the foundation pit, the road construction area includes an isolation area and a reinforcement area. The isolation area is located between the support structure 100 and the reinforcement area.

[0046] 2) A plurality of isolation piles 200 are constructed in the isolation area, and adjacent isolation piles 200 are interlocked with each other to form a straight-line isolation wall, and the bottom of the isolation piles 200 passes through the silt layer;

[0047] 3) Providing an excavator, the excavator is connected to a mixing head, the mixing head is connected to a grouting pipe, the mixing head is used to mix the soil on the road construction area, and a solidifying slurry is sprayed into the soil through the grouting pipe, and the solidifying slurry is mixed with the soil to form a solidified layer 400;

[0048] 4) Determine multiple reinforcement construction positions on the solidified layer 400 of the reinforcement area, insert steel pipes into the reinforcement construction positions using a driving and pulling machine to form reinforcement piles 300, the bottom of the reinforcement pile 300 passes through the silt layer, and the upper part of the reinforcement pile 300 is located in the solidified layer 400;

[0049] During the process of inserting the steel pipe at the reinforcement construction site, a steel pipe cap 310 is fixedly connected to the top of the steel pipe. When the top of the steel pipe cap 310 is flush with the top of the solidified layer 400, the steel pipe is stopped from being inserted to form a reinforcement pile 300.

[0050] 7) Laying a geogrid 500 on the reinforcement layer, and then spreading graded gravel on the geogrid 500 to form a gravel cushion layer 600, and the geogrid 500 is fixed to the bottom of the gravel cushion layer 600;

[0051] 8) A formwork is set up on the road construction area, the formwork surrounds a pouring area, concrete is poured in the pouring area, and cured to form a concrete surface layer 700 , which covers the gravel cushion layer 600 .

[0052] The support reinforcement construction method for reducing the safety impact of vehicle load in the silt stratum provided above, the reinforcement pile 300 passes through the silt layer, and the upper load can be transferred to the solid soil layer below the silt layer, reducing the impact of the load on the silt soil layer, reducing the lateral deformation of the foundation pit caused by the weak soil layer, thereby ensuring the stability of the foundation pit. In addition, by connecting the steel pipe cap 310 at the top of the steel pipe, the load-bearing area of ​​the upper part of the steel pipe is increased, and the dynamic load of the vehicle is transmitted downward to act on the steel pipe cap 310, and is transmitted downward along the reinforcement pile 300 to the solid soil layer. The load on the soft soil layer is weakened and the deformation is reduced. At the same time, the isolation pile 200 forms a uniform "isolation wall", which can further redistribute the load that has been evenly transmitted downward on the isolation pile 200 wall, reducing the load that finally falls on the support structure 100 and making it more uniform, and the impact on the support structure 100 is also smaller.

[0053] Then, the construction materials can be reused to increase their use value. The concrete surface layer 700 is removed by a blasting machine, and the gravel cushion layer 600 is removed by an excavator. The steel caps and steel pipes can be collected and reused. In this way, the temporary road can better bear the dynamic load of vehicles, and can reduce and balance the dynamic load, reduce the range of variation, and transfer the load downward more evenly, ultimately reducing the impact on the deep foundation pit.

[0054] Specifically, in construction step 2), a pile mixer is used to construct the isolation pile 200 in the isolation area; the pile mixer is connected to the grouting pipe, and the pile mixer has a mixing drill. During the process of mixing and drilling in the soil of the isolation area using the mixing drill, the solidifying slurry is sprayed into the soil through the grouting pipe, and the solidifying slurry is mixed with the soil in the isolation area to form the isolation pile 200. In this way, the molding quality of the isolation pile 200 is ensured by drilling downwards to the set pile bottom twice, lifting the rod out of the hole, and rotating and spraying the solidifying slurry during the drilling and lifting process.

[0055] Specifically, the steel pipe needs to be inserted into the ground before the soil and the solidifying slurry are initially solidified in construction step 2) to prevent the reinforcement piles 300 from being unable to be inserted into the site after solidification.

[0056] The solidifying slurry includes cement, slag powder, gypsum, double salt and water.

[0057] In construction step 2), a plurality of steel bars 210 are inserted into the top of the isolation pile 200, the lower part of the steel bars 210 is inserted into the isolation pile 200, and the upper part of the steel bars 210 is exposed above the isolation pile 200, forming a connecting section 211, and the outer end of the connecting section 211 is bent downward in a bent shape. In this way, the design of the connecting section 211 can be connected with the subsequent road surface layer, the connection is strengthened, the upper and lower ends of the isolation wall are fixed, and the impact caused by silt extrusion is reduced.

[0058] Specifically, in construction step 6), the connection section 211 is located in the pouring area, and after the concrete surface layer 700 is formed by curing, the connection section 211 is inserted into the concrete surface layer 700 .

[0059] Specifically, in step 5), the graded crushed stone spread on the geogrid 500 is compacted using a compaction device to ensure the density.

[0060] In step 6), a plurality of anti-skid grooves 701 are formed on the surface of the concrete surface layer 700. In this way, during the curing process of the concrete surface layer 700, the anti-skid grooves 701 are pressed on the surface to increase driving safety.

[0061] The steel pipe cap 310 includes a pressure plate 311, the top of the pressure plate 311 has a flat top surface, the bottom of the pressure plate 311 has a mounting ring 312 protruding downward, the mounting ring 312 is located in the middle of the pressure plate 311, and the mounting ring 312 encloses a mounting area 3120;

[0062] In step 4), the top of the steel pipe is embedded into the installation area 3120, and then the steel pipe and the steel pipe cap 310 are fixedly connected by welding; in the process of embedding the steel pipe into the reinforcement construction position, when the top surface is flush with the solidified layer 400, the steel pipe is stopped from being pressed down. In this way, the steel pipe cap 310 is positioned and installed through the function of the installation ring 312. After embedding, it only needs to be welded at three or four positions, which is convenient for breaking the connection between the steel pipe cap 310 and the steel pipe later and reused.

[0063] In this embodiment, a central screw hole is provided in the middle of the pressure plate 311, and the central screw hole passes through the pressure plate 311 from top to bottom, and the bottom of the central screw hole is connected to the installation area 3120;

[0064] In step 5), after the geogrid 500 is laid, the center bar 320 is screwed into the center screw hole. The bottom of the center bar 320 is provided with an elastic layer, which is pressed against the top of the steel pipe and is in a compressed state.

[0065] The upper part of the center bar 320 passes through the geogrid 500 to form an upper extension section, and the middle part of the upper extension section radially expands outward to form a positioning ring 321; in step 5), when the crushed stone cushion layer 600 is formed, the bottom of the positioning ring 321 presses against the top of the crushed stone cushion layer 600;

[0066] A top cover 322 is provided at the top of the upper extension section, and a concave groove 323 is formed at the top of the top cover 322. In step 6), during the pouring of concrete in the pouring area, the concrete fills the concave groove 323. In this way, by designing the central screw hole, the central bar 320 can be installed after the geogrid 500 is laid, thereby avoiding increasing the difficulty of laying the geogrid 500. In addition, by designing the positioning ring 321, the thickness of the crushed stone cushion layer 600 can be clearly controlled. Then, by designing the top cover 322, the connection between the reinforced pile 300 and the concrete surface layer 700 and the crushed stone cushion layer 600 can be realized.

[0067] The outer periphery of the pressure plate 311 has an annular edge region, and a plurality of edge holes are arranged on the edge region. The plurality of edge holes are arranged at intervals around the circumference of the pressure plate 311;

[0068] In step 5), after laying the geogrid 500, the side strip 330 is screwed into the edge hole, the bottom of the side strip 330 is embedded in the edge hole, the upper part of the side strip 330 passes through the geogrid 500, and the top of the side strip 330 is provided with a fan-shaped plate 331; the bottom of the fan-shaped plate 331 is connected to the side strip 330, and the top of the fan-shaped plate 331 is arranged to extend upward at an angle, and the width of the fan-shaped plate 331 gradually increases from bottom to top; when the side strip 330 is fixedly connected to the pressure plate 311, the fan-shaped plate 331 is arranged to be inclined toward the isolation wall from bottom to top. In this way, by installing the side strips 330 after laying the geogrid 500, the geogrid can be laid quickly, and the inclination direction of the fan-shaped plate 331 on the side strip 330 can be controlled by screwing it in, so that the fan-shaped plate 331 can withstand the squeezing of the laterally moving silt and concrete, thereby reducing the load that finally falls on the support structure 100 and having less impact on the support structure 100.

[0069] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A support and reinforcement construction method for reducing the safety impact of vehicle load in silt formations, characterized in that: The construction steps include: 1) Determine a road construction area outside the foundation pit, a support structure is provided on the periphery of the foundation pit, the road construction area is located outside the support structure, and in a direction away from the foundation pit, the road construction area includes an isolation area and a reinforcement area, and the isolation area is located between the support structure and the reinforcement area; 2) constructing a plurality of isolation piles in the isolation area, wherein adjacent isolation piles engage with each other to form a straight-line isolation wall, and the bottom of the isolation piles passes through the silt layer; 3) Providing an excavator, wherein the excavator is connected to a mixing head, wherein the mixing head is connected to a grouting pipe, and the soil on the road construction area is stirred by the mixing head, and a solidifying slurry is sprayed into the soil through the grouting pipe, wherein the solidifying slurry is stirred and mixed with the soil to form a solidified layer; 4) Determine a plurality of reinforcement construction positions on the solidified layer of the reinforcement area, insert steel pipes into the reinforcement construction positions using a driving and pulling machine to form reinforcement piles, wherein the bottom of the reinforcement pile passes through the silt layer, and the upper part of the reinforcement pile is located in the solidified layer; During the process of inserting the steel pipe at the reinforcement construction site, a steel pipe cap is fixedly connected to the top of the steel pipe, and when the top of the steel pipe cap is flush with the top of the solidified layer, the steel pipe is stopped from being inserted to form the reinforcement pile; 7) laying a geogrid on the reinforcement layer, and then spreading graded crushed stone on the geogrid to form a crushed stone cushion layer, wherein the geogrid is fixed at the bottom of the crushed stone cushion layer; 8) A formwork is set up on the road construction area, the formwork surrounds a pouring area, concrete is poured in the pouring area, and cured to form a concrete surface layer, and the concrete surface layer covers a crushed stone cushion layer.

2. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt formation according to claim 1 is characterized in that: In the construction step 2), isolation piles are constructed in the isolation area using a pile mixing machine; the pile mixing machine is connected to the grouting pipe, and the pile mixing machine has a mixing drill bit. During the process of mixing and drilling in the soil of the isolation area using the mixing drill bit, solidifying slurry is sprayed into the soil through the grouting pipe, and the solidifying slurry is mixed with the soil in the isolation area to form the isolation piles.

3. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt formation according to claim 1 is characterized in that: The solidified slurry comprises cement, slag powder, gypsum, double salt and water.

4. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt formation according to claim 1 is characterized in that: In the construction step 2), a plurality of steel bars are inserted into the top of the isolation pile, the lower portion of the steel bars is inserted into the isolation pile, and the upper portion of the steel bars is exposed above the isolation pile to form a connecting section, and the outer end of the connecting section is bent downward in a bent shape.

5. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt formation according to claim 4 is characterized in that: In the construction step 6), the connection section is located in the pouring area, and after the concrete surface layer is formed by curing, the connection section is inserted into the concrete surface layer.

6. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt formation according to claim 1 is characterized in that: In step 5), the graded crushed stone spread on the geogrid is compacted using compaction equipment.

7. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt formation according to claim 1 is characterized in that: In the step 6), a plurality of anti-slip grooves are constructed on the surface of the concrete surface layer.

8. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt strata according to any one of claims 1 to 7, characterized in that: The steel pipe cap comprises a pressure plate, the top of the pressure plate has a flat top surface, the bottom of the pressure plate has a mounting ring formed by a downward protrusion, the mounting ring is located in the middle of the pressure plate, and the mounting ring encloses a mounting area; In step 4), the top of the steel pipe is embedded into the installation area, and then the steel pipe and the steel pipe cap are fixedly connected by welding; in the process of embedding the steel pipe into the reinforcement construction position, when the top surface is flush with the solidified layer, the downward pressure on the steel pipe is stopped.

9. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt formation according to claim 8, characterized in that: A central screw hole is provided in the middle of the pressure bearing plate, the central screw hole passes through the pressure bearing plate from top to bottom, and the bottom of the central screw hole is connected to the installation area; In the step 5), after laying, a center strip is screwed into the center screw hole, and an elastic layer is provided at the bottom of the center strip, and the elastic layer is pressed against the top of the steel pipe, and the elastic layer is in a compressed state; The upper part of the center bar passes through the geogrid to form an upper extension section, and the middle part of the upper extension section radially expands outward to form a positioning ring; in the step 5), when the gravel cushion layer is formed, the bottom of the positioning ring is pressed against the top of the gravel cushion layer; A top cover is provided on the top of the upper extension section, and a concave groove is formed on the top of the top cover. In the step 6), during the process of pouring concrete in the pouring area, the concrete fills the concave groove.

10. The support and reinforcement construction method for reducing the safety impact of vehicle load in silt formation according to claim 8, characterized in that: The outer periphery of the pressure plate has an annular edge region, and the edge region is provided with a plurality of edge holes, and the plurality of edge holes are arranged at intervals around the circumference of the pressure plate; In step 5), after laying the geogrid, the side strips are screwed into the edge holes, the bottom of the side strips are embedded in the edge holes, the upper part of the side strips passes through the geogrid, and the top of the side strips is provided with a fan-shaped plate; the bottom of the fan-shaped plate is connected to the side strip, and the top of the fan-shaped plate is arranged to extend upward at an angle, and the width of the fan-shaped plate gradually increases from bottom to top; when the side strips are fixedly connected to the pressure plate, the fan-shaped plate is arranged to be inclined toward the isolation wall from bottom to top.