Grouting construction method for super-long large pipe shed of shallow-buried loess stratum tunnel
By using real-time monitoring equipment and ionization pulse technology in shallow buried loess formation tunnel construction, the problem of limited grouting depth and length is solved, uniform distribution and efficient support of grouting are achieved, construction risks are reduced, and tunnels are guaranteed Quality and safety of the project.
Patent Information
- Application Number
- CN202411005048.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-11-19
AI Technical Summary
In shallow buried loess formations, existing grouting technology is difficult to achieve effective support for ultra-long distances, the grouting depth and length are limited, and the grouting pressure and flow are difficult to accurately control, resulting in uneven grouting, affecting the support effect and Increase construction risks and costs.
Pressure sensors, flowmeters and density meters are arranged inside the grouting tube to monitor and transmit data to the intelligent control center in real time, combine water-expanded rubber strips to form a confined space and an ionization pulse device is installed outside the end of the grouting tube to ensure grouting The formation of paths and the slurry are evenly distributed.
Through real-time monitoring and precise control, the grouting quality is improved, construction risks are reduced, the slurry is fully filled with the target area, material waste is reduced, the stability of the tunnel structure is enhanced, and construction efficiency and safety are improved.
Smart Images

Figure CN118979760A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel engineering, and in particular to a super-long pipe shed grouting construction method for a shallowly buried loess stratum tunnel. Background Art
[0002] Tunnel construction plays an important role in modern infrastructure construction, especially in transportation, energy and other fields. Loess strata are widely distributed in the central and western regions of my country. They have special engineering properties, such as high water content, high porosity and weak cohesion. When tunnel construction is carried out in shallow loess strata, collapse and deformation are very likely to occur, which brings great difficulties and risks to the construction. Traditional support technology is difficult to complete the construction task efficiently while ensuring construction safety and quality.
[0003] Large pipe shed support technology is a pre-support technology widely used in tunnel construction in soft strata. This technology arranges steel pipe sheds around the tunnel to form a stable support system, thereby controlling stratum deformation and enhancing the stability of the soil around the tunnel. However, when large pipe shed technology is applied in shallow loess strata, grouting construction is difficult. Due to the particularity of loess strata, conventional pipe shed grouting technology is prone to problems such as uneven grouting, local leakage, and slurry blockage, which seriously affect the pipe shed support effect and construction safety.
[0004] Existing grouting devices mainly include single-tube grouting, multi-tube grouting and high-pressure rotary jet grouting. These devices have their own advantages and disadvantages under different geological conditions, but when dealing with shallow loess tunnel construction, they generally have the following limitations: the grouting depth and length are limited, making it difficult to achieve effective support over ultra-long distances; the grouting pressure and flow are difficult to accurately control, resulting in uneven grouting, affecting the support effect; grouting liquid leakage is likely to occur during construction, increasing construction risks and costs. Summary of the invention
[0005] The purpose of the present invention is to provide a super-long pipe shed grouting construction method for shallow loess stratum tunnels, which solves the problems that the grouting depth and length of the prior art are limited, it is difficult to achieve effective support over a super-long distance, the grouting pressure and flow are difficult to accurately control, resulting in uneven grouting and affecting the support effect. Grouting liquid leakage is likely to occur during the construction process, increasing construction risks and costs.
[0006] To achieve the above object, the present invention provides the following technical solution: a method for grouting a super-long pipe shed in a shallow loess stratum tunnel, the method comprising the following specific steps:
[0007] S1: Carry out equipment debugging before grouting to ensure that the data acquisition and transmission systems work normally;
[0008] S2: A circle of water-expandable rubber strips is pasted around the grouting pipe. When the grouting pipe is inserted into the pipe shed, the rubber strips expand when exposed to water, forming a closed space between the grouting pipe and the pipe shed.
[0009] S3: Adjust the slurry ratio to ensure that it meets the project requirements and start grouting operation;
[0010] S4: Collect various data during the grouting process in real time and transmit the data to the intelligent control center for analysis and processing;
[0011] S5: An ionization pulse device is installed outside the grouting pipe end. If the grouting pressure increases greatly in a short time when the grouting starts, and the grouting flow rate changes little, then the ionization pulse device is turned on to generate a new grouting path under the action of pulse ionization.
[0012] Preferably, in step S1, the equipment before grouting includes a pressure sensor, a flow meter, and a density meter arranged inside the grouting pipe.
[0013] Preferably, the pressure sensor monitors the slurry pressure state in the pipe shed in real time.
[0014] Preferably, the flow meter monitors the amount of slurry injected into the pipe roof in real time.
[0015] Preferably, the densitometer monitors the slurry concentration state in real time.
[0016] Preferably, in step S3, under the guidance of the intelligent control system, the grouting pump and the mixer are started to start the grouting operation.
[0017] Preferably, in step S4, the data is transmitted to the intelligent control center in real time through the data acquisition and transmission system for analysis and processing. The sensor network monitors various parameters in real time and transmits the data to the intelligent control system in real time.
[0018] Preferably, the ionization pulse in step S5 may be repeated multiple times until the grouting pressure drops significantly.
[0019] It can be seen from the above technical solution that the present invention has the following beneficial effects:
[0020] The super-long pipe shed grouting construction method for shallow loess tunnel can monitor the pressure state of the slurry in the pipe shed, the amount of slurry injected into the pipe shed, and the concentration state of the slurry in real time through the pressure sensor, flow meter and density meter arranged inside the grouting pipe. Through the real-time data acquisition and transmission system, the data is continuously and accurately transmitted to the intelligent control center for analysis and processing. This real-time monitoring and precise control ensures the controllability of the grouting process, improves the grouting quality, and reduces the construction risk. The water-expandable rubber strips pasted around the grouting pipe expand when exposed to water after the grouting pipe is inserted into the pipe shed, ensuring that a closed space is formed between the grouting pipe and the pipe shed. This design effectively prevents the leakage of slurry, ensures that the grouting material can fully fill the target area, improves the grouting efficiency and quality, and reduces material waste. The ionization pulse device set outside the grouting pipe end can effectively solve the problem of insufficient grouting path by turning on the ionization pulse device and generating a new grouting path using pulse ionization. The ionization pulse can be repeated many times until the grouting pressure drops significantly. This innovative technology not only improves the success rate of grouting, but also ensures that the slurry can be evenly distributed in the target area, enhancing the stability of the tunnel structure. By integrating multiple technical means such as real-time monitoring, closed grouting, intelligent control, and ionization pulses, it significantly improves the efficiency and safety of grouting construction. The design of the overall system reduces the uncertainty in the construction process, ensures the smooth progress of the grouting process, effectively reduces construction risks, and ensures the quality and safety of tunnel projects. It solves the problems of limited grouting depth and length in existing technologies, making it difficult to achieve effective support over long distances, and difficult to accurately control grouting pressure and flow, resulting in uneven grouting and affecting the support effect. Grouting liquid leakage is prone to occur during construction, increasing construction risks and costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 is a flow chart of the method of the present invention;
[0022] Figure 2 It is a schematic diagram of the structure of the grouting device of the present invention;
[0023] Figure 3 for Figure 2 Enlarged view of point A in the middle;
[0024] Figure 4 It is a schematic diagram of the structure of the sealing system of the present invention;
[0025] Figure 5 It is a schematic diagram of the structure of the ionization pulse device of the present invention.
[0026] In the figure: 1. Extra-long steel pipe for tube shed; 2. Sensor system; 3. Ionization pulse device; 4. Grouting hole; 5. Seam rubber strip; 6. Data processing and display system; 7. Grouting pipe; 8. Valve; 9. Grouting pump; 10. Slurry pool; 11. Power cord; 12. Ionizing fluid; 13. Electrode. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0028] like Figure 1-Figure 5 As shown, a method for grouting a super-long pipe shed for a shallowly buried loess tunnel is provided, wherein the method comprises the following specific steps:
[0029] S1: Carry out equipment debugging before grouting to ensure that the data acquisition and transmission systems work normally;
[0030] S2: A circle of water-expandable rubber strips is pasted around the grouting pipe. When the grouting pipe is inserted into the pipe shed, the rubber strips expand when exposed to water, forming a closed space between the grouting pipe and the pipe shed.
[0031] S3: Adjust the slurry ratio to ensure that it meets the project requirements and start grouting operation;
[0032] S4: Collect various data during the grouting process in real time and transmit the data to the intelligent control center for analysis and processing;
[0033] S5: An ionization pulse device is installed outside the grouting pipe end. If the grouting pressure increases greatly in a short time when the grouting starts, and the grouting flow rate changes little, then the ionization pulse device is turned on to generate a new grouting path under the action of pulse ionization.
[0034] like Figure 2-Figure 5 As shown, the grouting equipment includes a slurry pool 10, the slurry pool 10 is connected to a grouting pipe 7, a grouting pump 9 is arranged on the grouting pipe 7, the grouting pump 9 provides power for the transportation of slurry, a valve 8 is arranged on the grouting pipe 7 to prevent the slurry from flowing back, a close-seam rubber strip 5 is arranged on the outer surface of the grouting pipe 7, the close-seam rubber strip 5 is located inside the extra-long pipe shed steel pipe 1, a plurality of grouting holes 4 are opened on the extra-long pipe shed steel pipe 1, a sensor system 2 is arranged at the end of the grouting pipe 7 located at the extra-long pipe shed steel pipe 1, the sensor system 2 is connected to an ionization pulse device 3, the sensor system 2 is also connected to a data processing and display system 6, the ionization pulse device 3 includes a power line 11, an electrode 13 is arranged at the end of the power line 11, and the electrode 13 extends into the ionizing liquid 12.
[0035] The above method specifically comprises the following steps:
[0036] Place pressure sensors, flow meters, and density meters inside the grouting pipe to monitor the slurry pressure status in the pipe shed, the amount of slurry injected into the pipe shed, and the slurry concentration status in real time. Perform equipment debugging before grouting to ensure that the data acquisition and transmission system work properly.
[0037] A circle of water-swellable rubber strip is pasted around the grouting pipe 7. When the grouting pipe 7 is inserted into the pipe shed, the rubber strip expands when exposed to water, and a closed space is formed between the grouting pipe and the pipe shed. During the construction of a long and large pipe shed in the loess stratum, the grouting pressure is reduced because the pipe shed is long and the slurry transportation distance is increased. Therefore, it is necessary to ensure that a closed space is formed at the end of the grouting pipe so that the limited grouting pressure can be used to inject the slurry into the stratum;
[0038] Prepare grouting materials (such as cement slurry, chemical slurry, etc.) and adjust the slurry ratio to ensure that the engineering requirements are met. High-precision grouting equipment is the core part of the present invention and is used to perform specific grouting operations. Its main functions include precise positioning: through advanced positioning technology, ensure that the grouting equipment performs grouting at the predetermined position; fine operation: with fine operation capabilities, it can achieve precise pressure and flow control; durable design: the equipment adopts high-durability materials and design to adapt to long-term use under complex geological conditions. Under the guidance of the intelligent control system, the grouting pump and mixer are started to start the grouting operation. The sensors collect data such as pressure, flow, concentration and temperature in the grouting process in real time to ensure the continuity and accuracy of the data. The data acquisition and transmission system is used to collect and transmit various data in the construction process to ensure the timeliness and accuracy of the information. Its main functions include: Data acquisition: efficient collection of data in the geological, grouting and construction processes; Data storage: real-time transmission of data to the central control system through wireless or wired networks; Data storage: reliable storage of construction data for subsequent analysis and tracing; real-time transmission of data to the intelligent control center for analysis and processing. The sensor network monitors various parameters in real time and transmits data to the intelligent control system in real time; outside the grouting pipe end An ionization pulse device is installed in the part. In view of the fact that the loess stratum has few original cracks, a new grouting path is developed in the loess stratum by using the ionization pulse device to ensure that the slurry can be evenly injected around the pipe roof to ensure the grouting effect. If the grouting pressure increases significantly in a short period of time when the grouting starts, and the grouting flow rate changes little, it indicates that there are fewer grouting paths in the loess stratum. At this time, the ionization pulse device is turned on, and a new grouting path is generated under the action of pulse ionization. The ionization pulse can be repeated many times until the grouting pressure drops significantly. The grouting quality perception system is used to perceive grouting pressure, flow and other data to ensure grouting quality. Sensor network: multi-point sensors are arranged to collect grouting quality data in real time. Data analysis: through advanced data analysis algorithms, the grouting effect and quality are evaluated, and feedback and improvement suggestions are provided.
[0039] The pressure sensor, flow meter and density meter arranged inside the grouting pipe can monitor the pressure state of the slurry in the pipe shed, the amount of slurry injected into the pipe shed and the concentration state of the slurry in real time. Through the real-time data acquisition and transmission system, the data is continuously and accurately transmitted to the intelligent control center for analysis and processing. This real-time monitoring and precise control ensures the controllability of the grouting process, improves the grouting quality and reduces the construction risk.
[0040] The water-expandable rubber strips pasted around the grouting pipe expand when exposed to water after the grouting pipe is inserted into the pipe shed, ensuring that a closed space is formed between the grouting pipe and the pipe shed. This design effectively prevents the leakage of slurry, ensures that the grouting material can fully fill the target area, improves the grouting efficiency and quality, and reduces material waste;
[0041] The ionization pulse device is set on the outside of the grouting pipe end. When the pressure rises rapidly in a short period of time during the grouting process and the flow rate changes little, it indicates that there are fewer grouting paths. At this time, by turning on the ionization pulse device and using the pulse ionization effect to generate a new grouting path, the problem of insufficient grouting paths can be effectively solved. The ionization pulse can be repeated many times until the grouting pressure drops significantly. This innovative technology not only improves the success rate of grouting, but also ensures that the slurry can be evenly distributed in the target area, enhancing the stability of the tunnel structure;
[0042] The efficiency and safety of grouting construction have been significantly improved by integrating multiple technical means such as real-time monitoring, closed grouting, intelligent control, and ionization pulses. The overall system design reduces the uncertainty in the construction process, ensures the smooth progress of the grouting process, effectively reduces construction risks, and ensures the quality and safety of tunnel projects.
[0043] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for grouting a super-long pipe shed for a shallow loess tunnel, characterized in that: The method specifically comprises the following steps: S1: Carry out equipment debugging before grouting to ensure that the data acquisition and transmission systems work normally; S2: A circle of water-expandable rubber strips is pasted around the grouting pipe. When the grouting pipe is inserted into the pipe shed, the rubber strips expand when exposed to water, forming a closed space between the grouting pipe and the pipe shed. S3: Adjust the slurry ratio to ensure that it meets the project requirements and start grouting operation; S4: Collect various data during the grouting process in real time and transmit the data to the intelligent control center for analysis and processing; S5: An ionization pulse device is installed outside the grouting pipe end. If the grouting pressure increases greatly in a short time when the grouting starts, and the grouting flow rate changes little, then the ionization pulse device is turned on to generate a new grouting path under the action of pulse ionization.
2. The method for grouting a super-long pipe shed for a shallow loess tunnel according to claim 1, characterized in that: In the step S1, the equipment before grouting includes a pressure sensor, a flow meter, and a density meter arranged inside the grouting pipe.
3. The method for grouting a super-long pipe shed for a shallow loess tunnel according to claim 2, characterized in that: The pressure sensor monitors the slurry pressure state in the pipe shed in real time.
4. The method for grouting a super-long pipe shed for a shallow loess tunnel according to claim 2, characterized in that: The flow meter monitors the amount of slurry injected into the pipe shed in real time.
5. The method for grouting a super-long pipe shed for a shallow loess tunnel according to claim 2, characterized in that: The density meter monitors the slurry concentration state in real time.
6. The method for grouting a super-long pipe shed for a shallow loess tunnel according to claim 1, characterized in that: In step S3, under the guidance of the intelligent control system, the grouting pump and the mixer are started to start the grouting operation.
7. The method for grouting a super-long pipe shed for a shallow loess tunnel according to claim 1, characterized in that: In step S4, the data is transmitted to the intelligent control center in real time through the data acquisition and transmission system for analysis and processing. The sensor network monitors various parameters in real time and transmits the data to the intelligent control system in real time.
8. The method for grouting a super-long pipe shed for a shallow loess tunnel according to claim 1, characterized in that: The ionization pulse in step S5 may be repeated multiple times until the grouting pressure drops significantly.
Citation Information
Patent Citations
Impulse-type grouting method
CN103161478A
Tunnel supporting grouting equipment and grouting method thereof
CN107489432A
Novel soil improvement guide pipe grouting construction technology
CN108612542A
Intelligent cyclic supercharging and pressure relief type dynamic grouting system and method
CN108952760A
Shield tunnel deformation grouting reinforcement correction method suitable for water-rich sand layer
CN117588233A
Cited By
Tunnel stratum grouting method and device, electronic equipment and storage medium
CN120556944A