Large pipeline concrete buttress mounting method
By dividing the large concrete piers into upper and lower parts and being cast and welded in stages, the problems of deflection and handling difficulties in the installation of the piers are solved, ensuring the firm installation of the rubber pads, and improving construction safety and quality.
Patent Information
- Application Number
- CN202411145258.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-11-19
AI Technical Summary
In the installation of large concrete pipelines, there are common quality problems such as skew and height deviation in the installation of support piers. Traditional methods have difficulties in handling and on-site adjustments. The rubber pads are not installed firmly, which affects the installation quality and safety.
The entire support pier is divided into two parts, the lower support pier is poured in one go, the upper reinforcement bar is reserved, the upper support pier is poured in second place, and a rubber pad is installed on the steel cage of the upper support pier, and fixed by welding to ensure the thickness of the steel protective layer. and the rubber pad position.
The problem of large concrete back-transportation volume was solved, the on-site dimension adjustment of the support piers and the aesthetic and firm installation of rubber pads were achieved, ensuring stable pipeline support and improving construction safety.
Smart Images

Figure CN118979995A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of large-scale concrete pipeline installation, and in particular to a method for installing a large-scale pipeline concrete pier. Background Art
[0002] The installation of large pipelines in the integrated pipe gallery is difficult to carry and adjust during construction due to the heavy weight of the pipelines themselves. The requirements for the accuracy of the pouring of the gallery floor and the installation of the pipeline piers are high, and it is not easy to adjust after the installation is completed. The installation of the piers often has quality problems such as deflection, different axes, and height deviation, which makes the pipeline and the pier not fit tightly and the support unstable.
[0003] Rubber pads need to be installed before the pipeline is installed. The rubber pads are fixed to the pipeline by binding or placed on piers before the pipeline is installed. Rubber pads often have problems such as skewed placement, wrinkles, and damaged corners.
[0004] Traditional pier installation methods include:
[0005] 1) The piers are prefabricated in the factory and transported to the site for installation. They are often bumped during transportation and on-site handling, resulting in chipping of edges and corners of the pipeline piers, affecting the appearance quality. After the piers prefabricated according to the drawings are installed at the turns and elevation changes of the corridor, they often have common quality problems such as tilted arc-shaped support surfaces, inconsistency between the support surfaces and the pipeline axis, and height deviation. Even in the standard section of the corridor, there is a common problem of height deviation.
[0006] 2) The pier is cast on site as a whole. First, the temporary support of the pipeline is installed in place, and then the pier is cast with formwork. The arc-shaped support surface uses the pipeline itself as a template, and a rubber pad is placed in the middle. This can better solve the common problems of pipeline installation surface deflection and elevation deviation. However, this method requires a large workload for concrete transportation. When the height of the corridor structure is greater than 3m, concrete segregation is prone to occur during the unloading process. The installation of the rubber pad, due to the lack of fixed points, causes common quality problems such as deflection and wrinkles of the installed rubber pad. The rubber pad is directly installed on the steel bars of the pier, which is prone to problems such as exposed steel bars and insufficient thickness of the protective layer. Summary of the invention
[0007] In view of this, the present invention proposes a method for installing a large-scale pipeline concrete pier, comprising:
[0008] Construction preparation: divide the whole pier into two parts, upper and lower, and construct them separately. Design the steel cage and rubber pad according to the size of the pier;
[0009] The lower pier is cast in one time, the lower pier is prefabricated in the factory, and the upper steel bars are reserved above the lower pier;
[0010] The upper pier is poured for the second time. Pipes are installed on the basis of the reinforcement cage of the upper pier, and the whole is transported to the lower pier, and then the upper pier is poured for the second time.
[0011] Furthermore, the lower pier is a rectangular pier body, and the upper pier is a pier with an arc-shaped surface, one end of the upper plane is arranged close to the lower pier, and one end of the upper arc-shaped surface is used to support the pipeline to be installed.
[0012] Furthermore, the curvature of the steel cage of the upper pier is consistent with the curvature of the pipe body of the pipeline.
[0013] Furthermore, a rubber pad is provided on the steel cage of the upper pier, and the rubber pad is arranged along a side of the steel cage of the upper pier that supports the pipeline.
[0014] Furthermore, the steel cage of the upper pier and the rubber pad are both fixed to the pipeline.
[0015] Furthermore, a concrete pad is arranged between the rubber pad and the steel bars of the upper pier, so as to ensure the thickness of the steel bar protective layer.
[0016] Furthermore, before the secondary pouring of the upper pier, the steel cage of the upper pier is adjusted and then fixed to the reserved upper steel bars on the lower pier.
[0017] Furthermore, before the secondary pouring of the upper pier, the steel cage of the upper pier is subjected to rust removal treatment.
[0018] Furthermore, the upper steel bars reserved above the lower pier are connected to the steel cage of the upper pier by welding.
[0019] Furthermore, the rubber pad is arranged on the steel cage of the upper pier by binding.
[0020] The invention provides a method for installing a large-scale pipeline concrete pier, which has the following advantages: the method divides the overall pier into two parts, the lower pier is a rectangular pier, which is cast and formed at one time with the main structure of the pipeline corridor, and fixed steel bars are reserved on the joint surface; the upper pier is a part with a circular arc support surface, and a steel cage and a rubber pad are fixed on the pipeline in advance. After the pipeline is installed, the position of the steel cage and the rubber pad is adjusted, and the steel cage is welded and fixed to the steel bars reserved in the lower pier, and the upper half of the pier is cast for the second time; it not only solves the problem of large amount of concrete transported for cast-in-place piers, but also solves the problem that the prefabricated piers cannot be adjusted in size according to the actual situation on site and are difficult to transport on site, the rubber pad installation is also more beautiful and firm, and after the pipeline has a fixed pier, it will not roll during transport, and the construction is safer. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:
[0022] Figure 1 A step diagram of an installation method provided by an embodiment of the present invention;
[0023] Figure 2 A schematic diagram of the structure of the lower pier provided by an embodiment of the present invention;
[0024] Figure 3 A schematic diagram of the structure of an upper buttress provided in an embodiment of the present invention;
[0025] Figure 4 A schematic structural diagram of an upper pier reinforcement cage with a rubber pad provided in an embodiment of the present invention;
[0026] Figure 5 A schematic diagram of the structure of the upper pier reinforcement cage, rubber pad and pipeline assembly provided in an embodiment of the present invention;
[0027] Figure 6 A schematic diagram of a structure in which an upper pier reinforcement cage and reserved reinforcements of a lower pier are welded and fixed to each other according to an embodiment of the present invention;
[0028] Figure 7 A schematic diagram of the structure after the secondary casting of the upper pier provided in an embodiment of the present invention is completed. DETAILED DESCRIPTION
[0029] Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present disclosure and to be able to fully convey the scope of the present disclosure to those skilled in the art. It should be noted that, in the absence of conflict, the embodiments of the present invention and the features described in the embodiments can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0030] See also Figure 1 , which is a large-scale pipeline concrete pier installation method provided by an embodiment of the present invention, comprising the following operations:
[0031] Step 1: Construction preparation: Divide the overall pier into two parts, upper and lower, and construct them separately. Design the steel cage and rubber pad according to the size of the pier;
[0032] Step 2: The lower pier is cast at one time. The lower pier is prefabricated in the factory, and upper steel bars are reserved above the lower pier;
[0033] Step 3: Secondary pouring of the upper pier: Install the pipe on the basis of the reinforcement cage of the upper pier, install the whole on the lower pier, and then carry out secondary pouring of the upper pier.
[0034] Furthermore, the lower pier is a rectangular pier body, and the upper pier is a pier with an arc-shaped surface, one end of the upper plane is arranged close to the lower pier, and one end of the upper arc-shaped surface is used to support the pipeline to be installed.
[0035] Furthermore, the curvature of the steel cage of the upper pier is consistent with the curvature of the pipe body of the pipeline.
[0036] Furthermore, a rubber pad is provided on the steel cage of the upper pier, and the rubber pad is arranged along a side of the steel cage of the upper pier that supports the pipeline.
[0037] Furthermore, the steel cage of the upper pier and the rubber pad are both fixed to the pipeline.
[0038] Furthermore, a concrete pad is arranged between the rubber pad and the steel bars of the upper pier, so as to ensure the thickness of the steel bar protective layer.
[0039] Furthermore, before the secondary pouring of the upper pier, the steel cage of the upper pier is adjusted and then fixed to the reserved upper steel bars on the lower pier.
[0040] Furthermore, before the secondary pouring of the upper pier, the steel cage of the upper pier is subjected to rust removal treatment.
[0041] Furthermore, the upper steel bars reserved above the lower pier are connected to the steel cage of the upper pier by welding.
[0042] Furthermore, the rubber pad is arranged on the steel cage of the upper pier by binding.
[0043] The embodiment of the present invention discloses a specific method for installing a large-scale pipeline concrete pier, as follows:
[0044] 1. Construction preparation
[0045] Cut the steel bars in the factory, ensure that the arc-shaped steel bars of the upper pier are consistent with the curvature of the pipe body, weld the corresponding steel cage of the pier according to the pier size and the thickness of the steel bar protective layer; cut the rubber pad according to the size of the design drawing and put it aside;
[0046] Combine the upper pier reinforcement cage with the rubber pad and fix it on the pipeline;
[0047] 2. Installation steps
[0048] The lower pier is cast once → the upper steel, steel cage and rubber pad of the lower pier are made and assembled in the factory → the assembled steel cage and rubber pad are fixed on the pipeline on site → pipeline installation → adjustment and fixation of steel cage → secondary casting of the upper pier
[0049] 3. Construction application
[0050] Cast the lower pier at one time and reserve steel bars for fixing the upper pier (such as Figure 2 ), after the pier steel bars and rubber pads are cut, make the upper pier steel cage (such as Figure 3 ), and tie and fix the rubber pad to the upper pier steel cage. Concrete pads should be set between the rubber pad and the steel bars of the upper pier to ensure the thickness of the steel bar protection layer (such as Figure 4 ); Fix the upper pier steel cage and rubber pad combination on the pipe body (such as Figure 5 ).
[0051] Install the pipeline, correct the reserved steel bars on the lower pier, adjust and fix the upper pier steel cage, and complete the steel bar rust removal; weld the upper steel cage to the upper reserved steel bars of the lower pier to ensure a firm connection (such as Figure 6 ); Protective measures should be taken for the rubber pad during welding to avoid damage to the rubber pad; Secondary pouring of upper pier concrete (such as Figure 7 ).
[0052] A method for installing a large-scale pipeline concrete pier disclosed in an embodiment of the present invention has the following beneficial technical effects: the method divides the overall pier into an upper and lower part, the lower pier is a rectangular pier, which is cast and formed at one time with the main structure of the pipeline corridor, and fixed steel bars are reserved on the joint surface; the upper pier is a part with a circular arc support surface, and the upper pier steel cage and rubber pad are fixed to the pipeline in advance. After the pipeline is installed, the position of the upper pier steel cage and rubber pad is adjusted, and the upper pier steel cage is welded and fixed to the reserved steel bars of the lower pier, and the upper pier is cast for a second time; it not only solves the problem of large amount of cast-in-place pier concrete transported, but also solves the problem that the prefabricated pier cannot be adjusted in size according to the actual situation on site and is difficult to transport on site, the rubber pad is installed more beautifully and firmly, and after the pipeline has a fixed pier, it will not roll during transport, and the construction is safer.
[0053] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.
[0054] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0055] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A method for installing large-scale pipeline concrete piers. It is characterized in that include: Construction preparation: divide the whole pier into two parts, upper and lower, and construct them separately. Design the steel cage and rubber pad according to the size of the pier; The lower pier is cast in one time, the lower pier is prefabricated in the factory, and the upper steel bars are reserved above the lower pier; The upper pier is poured for the second time. Pipes are installed on the basis of the reinforcement cage of the upper pier, and the whole is transported to the lower pier, and then the upper pier is poured for the second time.
2. The large-scale pipeline concrete pier installation method according to claim 1, It is characterized in that The lower pier is a rectangular pier body, and the upper pier is a pier with an arc-shaped surface. One end of the upper plane is arranged close to the lower pier, and one end of the upper arc-shaped surface is used to support the pipeline to be installed.
3. The large-scale pipeline concrete pier installation method according to claim 1, It is characterized in that The curvature of the steel cage of the upper pier is consistent with the curvature of the pipe body of the pipeline.
4. The large-scale pipeline concrete pier installation method according to claim 1, It is characterized in that The steel cage of the upper pier is also provided with a rubber pad, and the rubber pad is arranged along a side of the steel cage of the upper pier that carries the pipeline.
5. The large-scale pipeline concrete pier installation method according to claim 4, It is characterized in that The steel cage of the upper pier and the rubber pad are both fixed to the pipeline.
6. The large-scale pipeline concrete pier installation method according to claim 4, It is characterized in that A concrete pad is arranged between the rubber pad and the steel bars of the upper pier, so as to ensure the thickness of the steel bar protective layer.
7. The large-scale pipeline concrete pier installation method according to claim 1, It is characterized in that Before the secondary pouring of the upper pier, the steel cage of the upper pier is adjusted and then fixed to the reserved upper steel bars on the lower pier.
8. The large-scale pipeline concrete pier installation method according to claim 1, It is characterized in that Before the secondary pouring of the upper pier, the steel cage of the upper pier is subjected to rust removal treatment.
9. The large-scale pipeline concrete pier installation method according to claim 1, It is characterized in that The upper steel bars reserved above the lower pier are connected to the steel cage of the upper pier by welding.
10. The large-scale pipeline concrete pier installation method according to claim 4, It is characterized in that The rubber pad is arranged on the steel cage of the upper pier by binding.