Goaf transformer substation hydrostatic leveling test system and installation method thereof

By introducing a laser locator and a height fine-tuning mechanism into the static leveling observation sensor, high-precision autonomous installation for settlement observation of substations in goaf areas was achieved, solving the problem of sensor height adjustment and improving the system's installation accuracy and flexibility.

CN118980351APending Publication Date: 2024-11-19PINGDINGSHAN ELECTRIC POWER DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410930430.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The existing static leveling sensors cannot adjust their height autonomously in substations in goaf areas, resulting in large installation errors, affecting the accuracy of settlement observation, and requiring multiple manual adjustments and external equipment for auxiliary measurements.

Method used

By employing a laser locator and a height fine-tuning mechanism, combined with a rotary positioning mechanism and threaded connection, the hydrostatic leveling observation sensor can achieve autonomous height calibration and fine-tuning, ensuring that all sensors are installed on the same horizontal plane.

Benefits of technology

It improves the accuracy of hydrostatic leveling observation, reduces initial liquid level error, simplifies the installation process, reduces equipment costs, and enhances the system's flexibility and reusability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118980351A_ABST
    Figure CN118980351A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of goaf settlement monitoring, and particularly discloses a goaf transformer substation hydrostatic leveling test system and an installation method thereof.The goaf transformer substation hydrostatic leveling test system comprises a liquid storage tank and a main pipeline installed on the liquid storage tank, an assembly shell is installed in the middle of a hydrostatic leveling observation sensor, and an installation sleeve is installed at the top end of one side of the assembly shell; the side groove is communicated with the top opening of the mounting sleeve to form a rotating channel, and a laser positioner is mounted in the rotating channel through a rotating positioning mechanism; light beam probes are installed on the top edges of the surface of one side and the surface of the other side of the laser positioner, a sliding frame is installed on the surface of the rear side of the assembly shell, a lifting frame is installed on the surface of the rear end of the sliding frame in a limiting mode, and a height fine adjustment mechanism is installed between the sliding frame and the lifting frame. By arranging a series of structures, installation of the static leveling observation sensor and a to-be-measured point is assisted, fine adjustment of the height of the sensor is achieved, unification of the installation height of the sensors is promoted, and static leveling testing or monitoring effect implementation is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of goaf area settlement monitoring, in particular to a goaf area substation static leveling test system and an installation method thereof. Background Art

[0002] In view of the geological conditions and structural characteristics of the engineering strata in the goaf area of ​​coal mines, and the fact that most substations in the goaf area are currently built on the ground, settlement and deformation are the main threats to the safe operation of substation buildings (structures) and equipment. Generally speaking, the type of settlement observation of substation buildings and structures and power facilities and equipment foundations in the goaf area belongs to surface settlement observation, and in the existing technology, most of the settlement observations of substations use static leveling observation sensors and constitute a static leveling observation system.

[0003] When installing a static leveling observation system, in order to ensure accurate settlement observation of a single building or equipment, it is necessary to install several static leveling observation sensors. The leveling observation sensor itself uses the principle of connecting pipes, and the liquid level requirements are relatively strict, which can avoid the influence of the initial liquid level error of the observation system. However, the existing static leveling observation sensors do not have their own height error adjustment function. In order to achieve this effect, it is necessary to manually measure the static leveling observation sensors of multiple monitoring points repeatedly and with the help of equipment such as a level. Moreover, it is often necessary to ensure a specific installation height. Each static leveling observation sensor is installed separately, and there is no benchmark reference between the static leveling observation sensors of each other. Summary of the invention

[0004] The object of the present invention is to provide a static leveling test system for a goaf substation and an installation method thereof, so as to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a static level test system for a goaf substation, comprising a liquid storage tank and a main pipe installed on the liquid storage tank, the main pipe extending to one side, and a plurality of static level observation sensors installed on the main pipe, an assembly shell installed in the middle of the static level observation sensor, a mounting sleeve installed at the top of one side of the assembly shell, an external thread is provided on the surface of the mounting sleeve, and an opening is provided at the top of the mounting sleeve, a side groove is provided on the rear side surface of the mounting sleeve, the side groove is connected with the top opening of the mounting sleeve to form a rotating channel, and a laser locator is installed inside the rotating channel through a rotating positioning mechanism; Light beam probes are installed on the top edges of one side surface and the other side surface of the laser locator, a scale bar is installed on the surface of the static level observation sensor adjacent to the laser locator, a sliding frame is installed on the rear side surface of the assembly shell, the bottom of the sliding frame extends laterally backward to form an extension portion, and a lifting frame is installed on the rear end surface of the sliding frame in a limited manner, the bottom of the lifting frame extends laterally backward to form an extension portion, and a height fine-tuning mechanism is installed between the extension portion of the sliding frame and the extension portion of the lifting frame, and at least two assembly screws are installed on the rear end surface of the extension portion of the lifting frame.

[0006] Preferably, a liquid inlet is provided on one side surface of the assembly shell, a shunt pipe is installed between the liquid inlet and the main pipeline, and a control valve is installed on the shunt pipe.

[0007] Preferably, an exhaust cap is installed at the top of the assembly shell away from the mounting sleeve.

[0008] Preferably, the rotational positioning mechanism includes a clamping shaft, a rotating rod, a clamping sleeve and a positioning assembly. The clamping shaft is installed inside the mounting sleeve adjacent to the side groove. The surface of the clamping shaft is snap-connected with the clamping sleeve. The rotating rod is installed on the top of the clamping sleeve, and the positioning assembly is installed on the top of the rotating rod.

[0009] Preferably, the positioning assembly includes a threaded barrel and a movable sleeve, the threaded barrel is installed on the top of the rotating rod, the movable sleeve is installed on the surface of the threaded barrel through a threaded sleeve, and the internal thread of the movable sleeve is used in conjunction with the external thread of the mounting sleeve.

[0010] Preferably, the height fine-adjustment mechanism includes a locking nut, a rotating nut and a lifting screw. Screw holes are arranged in the middle of the sliding frame extension when viewed from top to bottom, and a rotating nut is installed on the surface of the sliding frame extension outside the screw hole through a bearing. The lifting screw is installed on the internal thread of the rotating nut. The top of the lifting screw extends upward through the sliding frame screw hole to the bottom end of the lifting frame extension. The surface of the lifting screw between the lifting frame and the sliding frame and the surface of the lifting screw below the rotating nut are both threadedly installed with a locking nut.

[0011] Preferably, a positioning rod is installed between the top end of the threaded barrel and the bottom end of the laser locator, the positioning rod is connected to the top bearing of the threaded barrel, a clamping block is installed on one side surface of the positioning rod, and a socket is installed on the edge of the top surface of the assembly shell on the rear side of the mounting sleeve, and the socket and the clamping block are used together.

[0012] Preferably, a slide groove is provided on the surface of the lifting frame adjacent to the sliding frame, and a slider is installed on the surface of the sliding frame adjacent to the lifting frame, and the slider is used in conjunction with the slide groove.

[0013] A method for installing a static leveling test system for a goaf substation, specifically comprising the following steps: S1 Determine the substation buildings and basic equipment to be monitored. Based on the connecting vessel principle of the static level observation sensor and the characteristics of the substation buildings in the goaf area, determine the location of the settlement monitoring point. The environment between each monitoring point of a single observation target should be as similar as possible; S2 prepares equipment and personnel for types of antifreeze, types of static level observation sensors, installation tools, and liquid storage tanks; S3 When there are several monitoring points in a single building or infrastructure, several static level observation sensors to be installed in a single building or infrastructure are grouped together, and the most edge monitoring point is selected to determine the installation height first. A single static level observation sensor is moved to the monitoring point with the help of a trolley with a lifting function, and the horizontality of the trolley to the static level observation sensor is adjusted, and the height of the assembly screw is flush with the installation height; S4 first punches a hole on the building surface according to the height of the monitoring point, and the rotating rod moves backward across the side groove to make the card block and the card seat snap connected, turn on the laser locator, adjust the visible light generated by the beam probe at the edge to be flush with the center of the first hole, and use the visible light as a reference to punch the second hole; S5: Install expansion screw sleeves in the two holes and install the assembly screws on the holes to fix the static level observation sensor itself. Put the laser locator upright so that the movable sleeve is threadedly connected with the threaded barrel and the installation sleeve at the same time, and the height of the laser locator remains unchanged. S6: Install the next static leveling observation sensor, preliminarily determine the installation height, rotate the laser locator of the previous static leveling observation sensor so that the light beam probe on the side surface of the laser positioning sensor faces the position to be installed of the next static leveling observation sensor, calculate and determine the height to be installed based on the laser light spot, repeat steps S and S to install the second static leveling observation sensor, and ensure that the laser locators of the static leveling observation sensors are arranged on the same side; After S7 installs several static level observation sensors in sequence, it uses the height fine-tuning mechanism to adjust the height of the static level observation sensors of a single group according to the numerical values ​​of the scale bars illuminated by each beam probe of a single group, ensuring that the height difference of each static level observation sensor of a single group is controlled within ±3mm; S8 determines the location of the liquid storage tank, arranges the pipeline trenches for the main pipeline and line cables, and installs the main pipeline and the lines required for fiber optic Bragg grating signal transmission, completes a single set of static level observation system, and installs other static level observation systems for the object to be measured; S9 numbers the monitoring points of each building or infrastructure to be tested, and uniformly numbers the corresponding static level observation sensors; S10 installation and debugging, ensure that the total amount of connected liquid is controlled within ±30ml; After S11 was debugged, it was put into use. The static level observation sensors with different numbers constituted multiple systems. Multiple systems fed back data to the processing terminal through lines to conduct real-time settlement monitoring. Compared with the prior art, the present invention has the following beneficial effects: 1. This goaf substation static level test system and its installation method, when monitoring the settlement of the goaf substation, the entire test system can be divided into groups according to different objects to be tested, and when multiple static level observation sensors are installed in a single group, the auxiliary installation of the installation height is carried out with the help of its own laser locator and an external lifting vehicle. With each static level observation sensor as a reference, it has its own measuring equipment and performs self-position calibration to ensure that the installation heights of each static level observation sensor in a single group are as uniform as possible, which is beneficial to improving the accuracy of static level observation while reducing the use of external height measurement equipment. After each static level observation sensor is installed and fixed, it still has the function of height fine-tuning to reduce the influence of the initial liquid level error of the monitoring system.

[0014] 2. The static level test system and installation method of the goaf substation are equipped with two light beam probes in different orientations through a laser locator, which can generate two light beams, which are used for auxiliary drilling of building installation and height position adjustment between various static level observation sensors respectively. In combination with the numerical values ​​of the light beam probe and the scale bar, the numerical differences of the light points of each light beam probe of each static level observation sensor are used to adjust the height between each static level observation sensor based on each other, so as to ensure that a single group of static level observation sensors are at the same height as much as possible.

[0015] 3. The static level test system and installation method of the goaf area substation can change the installation state of the laser locator by changing the threaded connection state of the threaded barrel, the movable sleeve and the installation sleeve, and cooperating with the use of the side groove, which is beneficial to the use of different beam probes in different situations and has strong flexibility.

[0016] 4. The static level test system and installation method of the goaf substation realize a detachable connection through the clamping installation effect of the clamping shaft and the clamping sleeve. After the installation of a single set of static level observation sensors is completed, the laser locators can be uniformly removed from the installation sleeves and installed on the next set of static level observation sensors, which is conducive to the reuse of a single set of laser locators and saves equipment costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the overall system structure of the present invention; Figure 2 It is a schematic diagram of the front view structure of the static level observation sensor of the present invention; Figure 3 It is a schematic diagram of the side structure of the static level observation sensor of the present invention; Figure 4 For the present invention Figure 3 A partial enlarged view of the middle part; Figure 5 For the present invention Figure 3 A partial enlarged view of point B in the middle; Figure 6 It is a schematic diagram of the top view of the lifting frame of the present invention; Figure 7 It is a schematic diagram of the cross-sectional structure of the marker of the present invention in a vertical state.

[0018] In the figure: 1. Liquid storage tank; 2. Main pipeline; 3. Static level observation sensor; 4. Diverter pipe; 5. Mounting sleeve; 6. Liquid inlet; 7. Exhaust cap; 8. Assembly shell; 9. Assembly screw; 10. Lifting frame; 11. Locking nut; 12. Sliding frame; 13. Rotating nut; 14. Lifting screw; 15. Slide; 16. Holder; 17. Light beam probe; 18. Laser locator; 19. Movable sleeve; 20. Clamp shaft; 21. Side groove; 22. Rotating rod; 23. Block; 24. Positioning rod; 25. Threaded barrel; 26. Clamping sleeve; 27. Scale bar. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0021] like Figures 1 to 7As shown, the static level test system of the goaf substation in this embodiment and the installation method thereof include a liquid storage tank 1 and a main pipeline 2 installed on the liquid storage tank 1. The liquid storage tank 1 stores antifreeze required for static level test or monitoring, and the main pipeline 2 is used as a pipeline for conveying the antifreeze. The main pipeline 2 extends to one side, and a plurality of static level observation sensors 3 are installed on the main pipeline 2. With the help of the communicating vessel principle, the static level observation sensor 3 is a prior art, which can overcome the interference of the electromagnetic field of the substation, and then perform settlement test and monitoring on the goaf substation. A plurality of static level observation sensors 3 form a group, and are required to be installed at the same horizontal height to perform settlement test and monitoring on the same Buildings or foundation components are monitored. An assembly shell 8 is installed in the middle of the static level observation sensor 3. It is an outward convex shell structure with a large surface area. A mounting sleeve 5 is installed on the top of one side of the assembly shell 8. The surface of the mounting sleeve 5 is provided with an external thread, and the top of the mounting sleeve 5 is provided with an opening. The interior is hollow. The rear surface of the mounting sleeve 5 is connected with a side groove 21. The side groove 21 is connected with the top opening of the mounting sleeve 5 to form a rotating channel. The object inside the mounting sleeve 5 can extend backward through the side groove 21. The interior of the rotating channel is installed with a laser locator 18 through a rotating positioning mechanism. The laser locator 18 is actually a conventional component that can generate a visible light beam.A beam probe 17 is installed on one side surface and the top edge of the other side surface of the laser locator 18, and a scale bar 27 is installed on the surface of the static level observation sensor 3 adjacent to the laser locator 18. The scale bar 27 can assist the installation height when the static level observation sensors 3 are installed at the positions between each other later. The two beam probes 17 actually generate different types of beams. The beam probe 17 at the top edge of the laser locator 18 can generate horizontal visible light similar to a line, similar to the reference positioning line, and the beam probe 17 on one side surface can form a point when irradiated forward on the object. A sliding frame 12 is installed on the rear side surface of the assembly shell 8, which is a fixed installation form. The bottom of the sliding frame 12 extends laterally to the rear side to form an extension portion, forming an L-shaped structure, and a lifting frame 10 is installed on the rear end surface of the sliding frame 12, and the bottom of the lifting frame 10 extends laterally to the rear side to form an extension portion. , the extension of the sliding frame 12 and the extension of the lifting frame 10 form a parallel effect, so that the lifting frame 10 and the sliding frame 12 form an up-and-down stacking effect, and a height fine-tuning mechanism is installed between the extension of the sliding frame 12 and the extension of the lifting frame 10, which can realize the relative movement effect between the lifting frame 10 and the sliding frame 12, and change the position between the two. After the lifting frame 10 is fixedly installed, the sliding frame 12 and the static level observation sensor 3 change the up-and-down position, so that the internal liquid level changes relatively. At least two assembly screws 9 are installed on the rear end surface of the extension of the lifting frame 10. The assembly screws 9 are connected to the external connecting parts. For example, when installed on a wall, they can be installed as expansion screws, and two horizontal holes of the same height need to be drilled on the wall to facilitate the plane installation effect of the lifting frame 10. The light beam generated by the beam probe 17 at the top of the laser locator 18 can be used as a basis for drilling holes. ;

[0022] Specifically, a liquid inlet 6 is provided on one side surface of the assembly shell 8, and a shunt tube 4 is installed between the liquid inlet 6 and the main pipeline 2. The interior of the assembly shell 8 is hollow, which actually allows the antifreeze liquid to enter the entire static level observation sensor 3 through the shunt tube 4 and even the liquid inlet 6, serving as the liquid buoyancy source of the buoyancy component required for fiber grating detection, and a control valve is installed on the shunt tube 4 to control the opening and closing of a single shunt tube 4.

[0023] Furthermore, an exhaust cap 7 is installed at the top of the assembly shell 8 away from the installation sleeve 5, and the exhaust cap 7 can be opened. After the entire system is installed and the liquid starts to be filled, if the antifreeze overflows from the exhaust cap 7, it means that the internal liquid level of the static level observation sensor 3 is higher than the height of the assembly shell 8 and even the exhaust cap 7, and the liquid filling is completed and the exhaust cap 7 is closed in time.

[0024] Furthermore, the rotation positioning mechanism includes a card shaft 20, a rotating rod 22, a sleeve 26 and a positioning assembly. The card shaft 20 is installed inside the installation sleeve 5 adjacent to the side groove 21. It is a horizontal installation form and can rotate under force. The surface of the card shaft 20 is connected with a sleeve 26 by a snap-fit. The sleeve 26 is a certain elastic component. A smaller opening is provided at the bottom of the sleeve 26, which can be squeezed and deformed downward, so that the sleeve 26 can be directly sleeved on the surface of the card shaft 20. A rotating rod 22 is installed on the top of the sleeve 26. The rotating rod 22 rotates around the entire card shaft 20, and the positioning assembly is installed on the top of the rotating rod 22. The rotating rod 22 can move backward through the side groove 21 together with the positioning assembly.

[0025] Furthermore, the positioning assembly includes a threaded barrel 25 and a movable sleeve 19. The threaded barrel 25 is installed on the top of the rotating rod 22. The threaded barrel 25 is in the form of an external thread. Its actual outer diameter and even the external thread are the same as those of the mounting sleeve 5. The surface of the threaded barrel 25 is installed with the movable sleeve 19 through a threaded sleeve. The movable sleeve 19 can move along the surface of the threaded barrel 25 under force. The internal thread of the movable sleeve 19 is used in conjunction with the external thread of the mounting sleeve 5. When the movable sleeve 19 is threadedly connected to the mounting sleeve 5 and the threaded barrel 25 at the same time, a rigid connection effect can be formed. The rotating rod 22 no longer rotates and the entire laser locator 18 is in a vertical state.

[0026] Furthermore, the height fine-tuning mechanism includes a locking nut 11, a rotating nut 13 and a lifting screw 14. Screw holes are arranged in the middle of the extended portion of the sliding frame 12 when viewed from top to bottom, and a rotating nut 13 is installed on the surface of the extended portion of the sliding frame 12 outside the screw hole through a bearing. The rotating nut 13 can be subjected to force and can rotate at the bottom end of the extended portion of the sliding frame 12. The internal thread of the rotating nut 13 is installed with a lifting screw 14. The top of the lifting screw 14 extends upward through the screw hole of the sliding frame 12 to the bottom end of the extended portion of the lifting frame 10. The entire lifting screw 14 is relatively long from top to bottom. The surface of the lifting screw 14 between the lifting frame 10 and the sliding frame 12 and the surface of the lifting screw 14 below the rotating nut 13 are both threadedly installed with locking screws The nut 11 is constituted so that there are locking nuts 11 at the upper and lower positions of the lifting screw 14. In actual use, it is necessary to consider that the upper locking nut 11 is away from the extension part of the sliding frame 12 and the lower locking nut 11 is away from the rotating nut 13. At this time, when the rotating nut 13 is screwed and the lifting screw 14 itself is fixed, the rotating nut 13 and even the sliding frame 12 slide up and down under the reaction of the thread, thereby adjusting the height relationship between the sliding frame 12 and the lifting frame 10, and realizing the fine-tuning effect of the height of the static level observation sensor 3. On the contrary, if fine-tuning is not required, the upper locking nut 11 is required to press the extension part of the sliding frame 12 downward and the lower locking nut 11 is required to press the rotating nut 13 upward.

[0027] Furthermore, a positioning rod 24 is installed between the top end of the threaded tube 25 and the bottom end of the laser locator 18. The positioning rod 24 is used as a mounting component of the laser locator 18. The positioning rod 24 is connected to the bearing at the top end of the threaded tube 25, so that the entire positioning rod 24 and even the laser locator 18 can be subjected to force to rotate, thereby changing the angle of the light beam probe 17 on the laser locator 18. A clamping block 23 is installed on the surface of one side of the positioning rod 24, which is a conventional elastic buckle component. The clamping block 23 is arranged on the same side as the light beam probe 17 at the top edge of the laser locator 18. A clamping seat 16 is installed at the edge of the top surface of the assembly shell 8 on the rear side of the mounting sleeve 5. The clamping seat 16 and the clamping block 23 are used in combination. When the entire positioning rod 24 rotates backward, the clamping block 23 is clamped into the clamping seat 16 to form a limiting effect. At the same time, the light beam probe 17 at the edge of the laser locator 18 just irradiates a straight line downward, and the straight line is irradiated on the wall, which is conducive to auxiliary drilling.

[0028] Furthermore, a slide groove 15 is provided on the surface of the lifting frame 10 adjacent to the sliding frame 12, and a slider is installed on the surface of the sliding frame 12 adjacent to the lifting frame 10, and the slider is used in conjunction with the slide groove 15. The slide groove 15 and the slider are limited in cooperation, and when the sliding frame 12 moves relative to the lifting frame 10, the movement can be limited and guided.

[0029] A method for installing a static leveling test system for a goaf substation, specifically comprising the following steps: S1 Determine the substation buildings and basic equipment to be monitored. Based on the connecting vessel principle of the static level observation sensor 3 and the characteristics of the substation buildings in the goaf area, determine the locations of the settlement monitoring points, such as the four corners of the building, the large corners, and every 10m to 20m along the outer wall or every 2 to 3 column foundations, as well as the building cracks, post-casting belts and settlement joints on both sides, where the foundation depth is greatly different, where the artificial foundation and the natural foundation meet, the boundary between different structures, and the boundary between fill and excavation construction, the main transformer, GIS and other heavy equipment foundations, and the four corners of the equipment foundation with high settlement requirements. The environment between each monitoring point of a single observation target should be as similar as possible, such as the temperature and ventilation conditions of each monitoring point, and large temperature differences must be avoided at each monitoring point; S2 prepares equipment and personnel for the types of antifreeze, static level observation sensors 3, installation tools and liquid storage tank 1. It is best to use one antifreeze to avoid the situation where different lines have different static level liquids; S3 When there are several monitoring points in a single building or infrastructure, several static level observation sensors 3 to be installed in a single building or infrastructure are grouped as one, so that there are as many sensor groups as the objects to be measured. The most marginal monitoring point is selected to determine the installation height first, and the installation height is unified to facilitate the construction of the monitoring system using the connecting pipe principle. A single static level observation sensor 3 is moved to the monitoring point with the help of a cart with a lifting function. The cart preferably has a level calibration function. When carrying the static level observation sensor 3, the cart can be adjusted to the horizontality of the static level observation sensor 3, the horizontal position can be adjusted, and the height of the assembly screw 9 is flush with the installation height. The cart can be manually driven to move back and forth when the height is determined; S4 According to the height of the monitoring point, because the objects to be tested may be different, such as the outer wall of the transformer station, it can be installed by drilling holes, and other objects to be tested need to be connected to the assembly screw 9 with the help of other components. First, a hole can be drilled on the surface of the building, and the rotating rod 22 moves backward over the side groove 21, so that the block 23 and the seat 16 are snap-connected. After the laser locator 18 is fixed in position, the laser locator 18 is turned on. After determining that the first hole is close to the height of the assembly screw 9, the front and rear positions of the cart are adjusted, and then the visible light generated by the beam probe 17 at the edge is adjusted to be flush with the center of the first hole. The second hole is drilled based on the visible light; S5 installs expansion screw sleeves in the two holes, and installs the assembly screw 9 on the hole to fix the static level observation sensor 3 itself, erects the laser locator 18, ensures that the clamping shaft 20 and the clamping sleeve 26 are in stable contact, avoids the height error caused by the gap, and makes the movable sleeve 19 threadedly connected with the threaded barrel 25 and the installation sleeve 5 at the same time. The height of the laser locator 18 will not change, because the assembly shell 8 is large in size, so that the laser generated by the laser locator 18 can pass over the main body of the static level observation sensor 3; S6: Install the next static level observation sensor 3 and preliminarily determine the installation height. Because the bearing structure can make the laser locator 18 rotate under force, rotate the laser locator 18 of the previous static level observation sensor 3 so that the light beam probe 17 on the side surface of the laser locator 18 faces the installation position of the next static level observation sensor 3, especially the wall surface, so that the light spot generated by the light beam probe 17 can fall on the wall surface to be installed. The installation height to be installed is calculated and determined based on the laser light spot. Repeat steps S4 and S5 to install the second static level observation sensor 3, and ensure that the laser locators 18 of the static level observation sensor 3 are arranged on the same side. S7 After installing several static level observation sensors 3 in sequence, with the help of the height fine-tuning mechanism, the numerical values ​​of the scale bars 27 irradiated by each single group of light beam probes 17, such as the numerical values ​​of the scale bars 27 irradiated by each single group of light beam probes 17, can be used as a reference to determine the installation height differences of each static level observation sensor 3. It is necessary to ensure that the numerical values ​​of the irradiated scale bars 27 are as similar as possible, and then the height of the single group of static level observation sensors 3 needs to be adjusted. Because there may be errors and other factors in drilling, it is necessary to ensure that the height difference of each static level observation sensor 3 in a single group is controlled within ±3mm; S8 determines the layout position of the liquid storage tank 1, especially the adjustment of the height of the liquid storage tank 1. When a single set of static level observation sensors 3 are installed on the same horizontal plane, it may be constrained by the on-site construction conditions and the installation height is relatively large. In order to stabilize the liquid supply, the liquid storage tank 1 needs to be raised. After the pipeline grooves for the main pipeline 2 and the line cables are arranged and the main pipeline 2 and the lines required for the fiber grating signal transmission are installed, the single set of static level observation system is completed, and other static level observation systems are installed for the object to be measured; S9 numbers the monitoring points of each building or infrastructure to be tested, and uniformly numbers the corresponding static level observation sensors 3; S10 installation and debugging, ensure that the total amount of connected liquid is controlled within ±30ml; After S11 is debugged, it is put into use. The numbered static level observation sensors 3 constitute multiple systems. Multiple systems use lines to uniformly feed back data to the processing terminal. The on-site processing terminal can be a data demodulation instrument. With the help of a local area network, data can be transmitted to the on-site data acquisition and analysis computer. The computer can use a gateway or a wireless transmitter to feed back data to a remote cloud platform or data server, which is then processed by a remote application server for real-time settlement monitoring.

[0030] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein with equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A static level test system for a goaf substation, comprising a liquid storage tank (1) and a main pipeline (2) installed on the liquid storage tank (1), wherein the main pipeline (2) extends to one side and a plurality of static level observation sensors (3) are installed on the main pipeline (2), characterized in that: An assembly shell (8) is installed in the middle of the static level observation sensor (3), a mounting sleeve (5) is installed on the top of one side of the assembly shell (8), the surface of the mounting sleeve (5) is provided with an external thread, and the top of the mounting sleeve (5) is provided with an opening, and the rear surface of the mounting sleeve (5) is provided with a side groove (21), the side groove (21) is connected with the top opening of the mounting sleeve (5) to form a rotation channel, and a laser locator (18) is installed inside the rotation channel through a rotation positioning mechanism; A beam probe (17) is installed at the top edge of one side surface and the other side surface of the laser locator (18), a scale bar (27) is installed on the surface of the static level observation sensor (3) adjacent to the laser locator (18), a sliding frame (12) is installed on the rear side surface of the assembly shell (8), the bottom of the sliding frame (12) extends laterally to the rear side to form an extension portion, and a lifting frame (10) is installed on the rear end surface of the sliding frame (12) in a limited manner, the bottom of the lifting frame (10) extends laterally to the rear side to form an extension portion, and a height fine-tuning mechanism is installed between the extension portion of the sliding frame (12) and the extension portion of the lifting frame (10), and at least two assembly screws (9) are installed on the rear end surface of the extension portion of the lifting frame (10).

2. The static level test system for goaf substation according to claim 1 is characterized by: A liquid inlet (6) is provided on one side surface of the assembly housing (8), a shunt pipe (4) is installed between the liquid inlet (6) and the main pipeline (2), and a control valve is installed on the shunt pipe (4).

3. The static level test system for goaf substation according to claim 1 is characterized by: An exhaust cap (7) is installed at the top end of the assembly shell (8) away from the installation sleeve (5).

4. The static level test system for goaf substation according to claim 1 is characterized in that: The rotary positioning mechanism comprises a clamping shaft (20), a rotating rod (22), a clamping sleeve (26) and a positioning assembly. The clamping shaft (20) is installed inside a mounting sleeve (5) adjacent to a side groove (21). The surface of the clamping shaft (20) is snap-connected with the clamping sleeve (26). The top of the clamping sleeve (26) is installed with a rotating rod (22), and the positioning assembly is installed on the top of the rotating rod (22).

5. The static level test system for goaf substation according to claim 4 is characterized in that: The positioning assembly comprises a threaded barrel (25) and a movable sleeve (19), wherein the threaded barrel (25) is mounted on the top of the rotating rod (22), the movable sleeve (19) is mounted on the surface of the threaded barrel (25) via a threaded sleeve connection, and the internal thread of the movable sleeve (19) cooperates with the external thread of the mounting sleeve (5).

6. The static level test system for goaf substation according to claim 1 is characterized by: The height fine-tuning mechanism comprises a locking nut (11), a rotating nut (13) and a lifting screw (14); a screw hole is arranged in the middle of the extension of the sliding frame (12) when viewed from top to bottom, and a rotating nut (13) is installed on the surface of the extension of the sliding frame (12) outside the screw hole through a bearing; the lifting screw (14) is installed on the internal thread of the rotating nut (13); the top of the lifting screw (14) extends upward through the screw hole of the sliding frame (12) to the bottom of the extension of the lifting frame (10); the surface of the lifting screw (14) between the lifting frame (10) and the sliding frame (12) and the surface of the lifting screw (14) below the rotating nut (13) are both installed with a locking nut (11) through threads.

7. The static level test system for goaf substation according to claim 5 is characterized by: A positioning rod (24) is installed between the top end of the threaded barrel (25) and the bottom end of the laser locator (18), the positioning rod (24) is connected to the top end bearing of the threaded barrel (25), a clamping block (23) is installed on one side surface of the positioning rod (24), and a clamping seat (16) is installed at the edge of the top end surface of the assembly shell (8) on the rear side of the mounting sleeve (5), and the clamping seat (16) and the clamping block (23) are used in conjunction with each other.

8. The static level test system for goaf substation according to claim 1 is characterized by: A sliding groove (15) is provided on the surface of the lifting frame (10) adjacent to the sliding frame (12), and a sliding block is installed on the surface of the sliding frame (12) adjacent to the lifting frame (10), and the sliding block is used in conjunction with the sliding groove (15).

9. A method for installing a static level test system for a goaf substation, characterized in that: The specific steps include: S1 Determine the substation buildings and basic equipment to be monitored, and determine the location of the settlement monitoring point based on the connecting vessel principle of the static level observation sensor (3) and the characteristics of the substation buildings in the goaf area. The environment between each monitoring point of a single observation target should be as similar as possible; S2 prepares equipment and personnel for the types of antifreeze fluid, the types of static level observation sensors (3), installation tools, and a fluid storage tank (1); S3 When a single building or infrastructure has several monitoring points, the several static level observation sensors (3) to be installed on the single building or infrastructure are grouped together, the most edge monitoring point is selected to first determine the installation height, and a single static level observation sensor (3) is moved to the monitoring point with the help of a trolley with a lifting function, and the horizontality of the trolley to the static level observation sensor (3) is adjusted, and the height of the assembly screw (9) is flush with the installation height; S4: First, a hole is drilled on the surface of the building according to the height of the monitoring point, and the rotating rod (22) moves backward over the side groove (21) so that the clamping block (23) and the clamping seat (16) are snap-connected, and the laser locator (18) is turned on. The visible light generated by the beam probe (17) at the edge is adjusted to be flush with the center of the first hole, and the second hole is drilled based on the visible light; S5: installing expansion screw sleeves in the two holes and installing the assembly screw rod (9) on the holes to fix the static level observation sensor (3) itself, erecting the laser locator (18) so that the movable sleeve (19) is threadedly connected to the threaded cylinder (25) and the installation sleeve (5) at the same time, and the height of the laser locator (18) remains unchanged; S6: installing the next static level observation sensor (3), preliminarily determining the installation height, rotating the laser locator (18) of the previous static level observation sensor (3) so that the light beam probe (17) on the side surface of the laser positioning sensor (18) faces the position to be installed of the next static level observation sensor (3), calculating and determining the height to be installed based on the laser light spot, repeating steps S4 and S5 to install the second static level observation sensor (3), and ensuring that the laser locators (18) of the static level observation sensors (3) are arranged on the same side; After S7 sequentially installs a plurality of static level observation sensors (3), the height of the static level observation sensors (3) of the single group is adjusted according to the numerical values ​​of the scale bars (27) illuminated by each beam probe (17) of the single group by means of a height fine-tuning mechanism, so as to ensure that the height difference of each static level observation sensor (3) of the single group is controlled within ±3 mm; S8 determines the layout position of the liquid storage tank (1), arranges the pipeline grooves for the main pipeline (2) and the line cables, and installs the main pipeline (2) and the lines required for the fiber optic Bragg grating signal transmission, completes a single set of static level observation system, and installs other static level observation systems for the object to be measured; S9 numbers the monitoring points of each building or infrastructure to be tested, and uniformly numbers the corresponding static level observation sensors (3); S10 installation and debugging, ensure that the total amount of connected liquid is controlled within ±30ml; After S11 is debugged and put into use, the numbered static level observation sensors (3) form multiple systems. The multiple systems use lines to uniformly feed back data to the processing terminal for real-time settlement monitoring.