Project sequential sequence evaluation method
By clustering and calculating abrupt and abnormal degree values, the project timing sequence is corrected, and the problem of low correlation between project timing sequences in the prior art is solved, and more accurate project progress and abnormal analysis is achieved.
Patent Information
- Application Number
- CN202411038860.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-19
AI Technical Summary
In the prior art, the project timing sequence is not fully utilized, resulting in inaccurate decision-making and inability to respond to project changes quickly, and the correlation of multi-dimensional data is small, resulting in inability to intuitively and accurately analyze during project monitoring.
By obtaining multiple project timing sequences, clustering elements, calculating abrupt degree values and abnormal degree values, correcting project timing sequences, improving their correlation, and achieving more intuitive evaluation.
By correcting the abrupt degree value and the overall difference value, the correlation between project timing sequences is improved, making the evaluation results more accurate and reflecting the project progress and abnormal situations.
Smart Images

Figure CN118982253A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an evaluation method for a project time series, and belongs to the technical field of data analysis. Background Art
[0002] Big data has become one of the key resources to promote industrial and social progress. In the field of project management, the whole process from project initiation to completion involves a large amount of data information, which can be presented in the form of project time series. These data include but are not limited to the various stages of project planning, design, implementation, monitoring and termination. The effective collection, processing and analysis of data throughout the project process is crucial to the successful execution of the project. It can provide in-depth insights and decision support, increase the transparency and efficiency of project management, and reduce cost and time overruns.
[0003] In the existing technology, traditional project management often relies on experience and intuition to make decisions, lacking data-driven analysis. The project time series generated throughout the project process are not fully utilized, resulting in inaccurate decisions and an inability to quickly respond to project changes. When collecting project data, because the dimensions of project data are diverse, there is a certain correlation between some dimensions, resulting in a small correlation between some project time series. Therefore, when analyzing them, the correlation of the data becomes smaller because the data is in different dimensions. As a result, when monitoring the project, it is not possible to intuitively and accurately analyze the project based on the project time series collected throughout the project process. Summary of the invention
[0004] The purpose of the present application is to overcome the deficiencies in the prior art and to provide an evaluation method for project time series that improves the correlation between project time series and more intuitively evaluates the project time series.
[0005] In order to achieve the above objectives, this application is implemented by adopting the following technical solutions:
[0006] In a first aspect, the present application provides a method for evaluating a project time series, comprising:
[0007] Get multiple project time series;
[0008] Cluster all elements in each project time series to obtain one or more clusters;
[0009] Obtaining the difference value between each element and the reference element at the same time in the time series of other items; obtaining the overall amplitude of the cluster to which each element belongs; and obtaining the abruptness value of each element according to the difference value and the overall amplitude;
[0010] Get the discrete value between the obtrusiveness value of each element and the obtrusiveness value of its reference element;
[0011] Get the overall difference between the cluster of each element and the cluster of the reference element;
[0012] Obtaining an abnormality value of each element according to the abruptness value, the discrete value and the overall difference value;
[0013] According to the abnormality level value of each element, the project time series sequence is corrected, and the corrected project time series sequence is evaluated to obtain an evaluation result.
[0014] In some embodiments of the first aspect, clustering all elements in each project time series to obtain one or more clusters includes:
[0015] Obtaining the maximum element in the project time series, and obtaining the ratio between each element in the project time series and the maximum element;
[0016] Obtaining the sum of the squares of the differences between each element in the project time series and its adjacent elements;
[0017] The product of the ratio and the sum of the squares of the differences is used as the change characteristic value of the corresponding element in the project time series; wherein the change characteristic value is obtained as follows:
[0018] ,
[0019] In the formula, is the changing characteristic value of the element, is the value of the element in the project time sequence, is the value of the largest element in the project time series, is the ratio, is the number of adjacent elements, is the counting sequence of adjacent elements, For the The values of adjacent elements, is the sum of the squares of the differences;
[0020] All elements are clustered according to the change characteristic value of each element in the project time series to obtain one or more clusters.
[0021] In some embodiments of the first aspect, obtaining the overall amplitude of the cluster in which each element is located includes taking the mean of all elements in the cluster in which each element is located as the corresponding overall amplitude;
[0022] The obtaining of the difference value between each element and a reference element at the same time in a timing sequence of other items includes obtaining a change characteristic value of each element and a change characteristic value of its reference element, and obtaining the difference value according to the difference in the change characteristic value between the element and its reference element.
[0023] In some embodiments of the first aspect, the obtaining of the abruptness value of each element according to the difference value and the overall amplitude includes: an obtaining formula for the abruptness value of the element is as follows:
[0024] ,
[0025] In the formula, is the obtrusiveness value of the element, is the overall amplitude of the element, is the number of reference elements, is the counting number of the reference element, For the The change characteristic value of the reference element, is the difference value.
[0026] In some embodiments of the first aspect, obtaining the overall difference value between the cluster class where each element is located and the cluster class where the reference element is located includes:
[0027] The means of all elements in the cluster where the element is located and the means of all elements in the cluster where the reference element is located are respectively obtained, and multiple absolute values of differences between the two means are obtained, and the absolute values of the differences are used as the overall difference values.
[0028] In some embodiments of the first aspect, the modifying the project time series according to the abnormality level value of each element includes modifying each element in the project time series as follows:
[0029] ,
[0030] In the formula, is the corrected value of the element, is the value of the element in the project time sequence, is a linear normalization function, is the degree of correction of the element, is the number of reference elements, is the abnormality value of the element, is the counting number of the reference element, For the The abnormality value of the reference element.
[0031] In some embodiments of the first aspect, evaluating the modified project time sequence to obtain an evaluation result includes:
[0032] Perform k-means clustering on all the corrected elements in all the corrected project time series to obtain one or more feature clusters;
[0033] extracting a correction element from the corrected project timing sequence;
[0034] Obtaining the absolute value of the difference between the correction element and the mean of all correction elements in the characteristic cluster class where the correction element is located, and outputting an outlier degree evaluation of the correction element according to the absolute value of the difference;
[0035] Obtain the absolute values of the differences of all corrected elements in all corrected project time series, and obtain the mean normalized results of all the absolute values of the differences;
[0036] Get the preset abnormal threshold;
[0037] According to the comparison between the abnormal threshold and the mean normalization result, the abnormal evaluation of the project is output.
[0038] In a second aspect, the present application also provides a computer device, comprising a processor and a memory connected to the processor, wherein a computer program is stored in the memory, and when the computer program is executed by the processor, the steps of the project timing sequence evaluation method described in any embodiment of the first aspect are performed.
[0039] In a third aspect, the present application further provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the method for evaluating a project timing sequence as described in any one of the embodiments of the first aspect.
[0040] In a fourth aspect, the present application further provides a computer program product, comprising a computer program / instruction, characterized in that when the computer program / instruction is executed by a processor, the steps of the project timing sequence evaluation method described in any embodiment of the first aspect are implemented.
[0041] Compared with the prior art, the present invention has the following beneficial effects:
[0042] The project timing sequence evaluation method provided in the present application takes into account that the elements in different project timing sequences at the same moment have a strong correlation with each other. The correlation between different project timing sequences can be well established according to the abruptness value, discrete value and overall difference value between each element and the reference element at the same moment as the element. Then, the elements in all project timing sequences are corrected by the abruptness value, discrete value and overall difference value, so that the project progress can be well reflected when the corrected project timing sequence is used to evaluate the project; wherein, the abruptness value reflects the difference between certain elements in the project timing sequence and the reference elements of other project timing sequences at the same moment, and is used to control the degree of correction of the element. The discrete value and the overall difference value also represent the degree of abnormality of the element from more dimensions, and are also used to control the degree of correction of the element. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] In order to more clearly illustrate the technical solutions in the present application or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0044] Figure 1 is a flowchart of the steps of the project timing sequence evaluation method provided in this embodiment;
[0045] Figure 2 It is a schematic block diagram of the principles of the computer device provided in this embodiment. DETAILED DESCRIPTION
[0046] The technical solution of the present invention is described in detail below through the accompanying drawings and specific embodiments. It should be understood that the embodiments of the present application and the specific features in the embodiments are detailed descriptions of the technical solution of the present application, rather than limitations on the technical solution of the present application. In the absence of conflict, the embodiments of the present application and the technical features in the embodiments can be combined with each other.
[0047] The term "and / or" in this article is only a description of the association relationship of the associated objects, indicating that there can be three relationships. For example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.
[0048] Embodiment 1:
[0049] Figure 1This is a flow chart of a method for evaluating a project time sequence in the first embodiment of the present invention. This flow chart only shows the logical sequence of the method described in this embodiment. In other possible embodiments of the present invention, different methods may be used without conflict. Figure 1 The steps shown or described are accomplished in the order shown.
[0050] The method for evaluating the project time sequence provided in this embodiment can be applied to a terminal, such as a computer device.
[0051] This embodiment takes the data of the entire process of a construction project as an example. During the construction process of a construction project, due to the large number of construction links and the complexity of the project, in order to accurately supervise the construction progress and construction quality, it is necessary to conduct a comprehensive analysis based on several project time series of the project process. However, because the multi-dimensional monitoring data type is complex, and there is a certain correlation between some data, while the correlation between some data is small, when analyzing it, the correlation of the data will become smaller because the data is in different dimensions, so when monitoring the project, it is not possible to intuitively and accurately reflect the progress of the project, etc., so it is necessary to correct the elements in the project time series, improve the correlation between multi-dimensional data, and improve the accuracy of project progress analysis.
[0052] See also Figure 1 The method of this implementation specifically includes the following steps:
[0053] The project data is obtained and organized into multiple project time series. In this embodiment, the project time series includes five types: progress time series, expenditure cost time series, human resource time series, equipment resource time series, and material resource time series. Each project time series arranges multiple elements in the order of time, and each element records the corresponding project information.
[0054] Get the abnormality value of each element in each item time series;
[0055] According to the abnormality degree value of each element, each element is corrected to realize the correction of the project time series, and the corrected project time series is evaluated to obtain the evaluation result.
[0056] The method for obtaining the abnormality value of each element is as follows:
[0057] Cluster all elements in each project time series to obtain one or more clusters;
[0058] Obtain the difference value between each element and the reference element at the same time in the time series of other items; obtain the overall amplitude of the cluster to which each element belongs; obtain the abruptness value of each element based on the difference value and the overall amplitude;
[0059] Get the discrete value between the obtrusiveness value of each element and the obtrusiveness value of its reference element;
[0060] Get the overall difference between the cluster of each element and the cluster of the reference element;
[0061] Obtain the abnormality value of each element based on the abruptness value, discrete value, and overall difference value.
[0062] Among them, all elements in the time series of each project are clustered, and the obtained clusters have certain correlations between elements in a single cluster, and elements between different clusters have certain distinctions. By classifying elements with similar characteristics into one category, the complexity of the analysis is reduced, the data structure is simplified, and it is helpful to evaluate the degree of abnormality more accurately in the future.
[0063] The difference value reflects the degree of deviation of the element from its reference element, and the overall amplitude provides the fluctuation range of the cluster to which the element belongs. The abruptness value is a comprehensive reflection of the difference between the element and the reference element and the overall fluctuation of the cluster to which it belongs. The discrete value reflects the inconsistency of the abruptness between the element and the reference element, and the overall difference value reflects the difference between different clusters. The evaluation of the discrete value increases the dimension of evaluation, making the evaluation of the degree of abnormality more comprehensive.
[0064] The discrete value reflects the inconsistency between the element and the reference element, and the overall difference value reflects the difference between different clusters. The evaluation of the overall difference value increases the dimension of evaluation, making the evaluation of the degree of abnormality more comprehensive and providing a global understanding of the relationship between the cluster to which the element belongs and the reference cluster.
[0065] After obtaining the abruptness value, discrete value and overall difference value corresponding to each element, the abnormality value obtained by the abruptness value, discrete value and overall difference value is equivalent to a multi-dimensional evaluation of the elements to be corrected based on the same cluster elements and the same moment elements. After correcting the elements using the abnormality value, the corrected elements have a good correlation with the same cluster elements and the same moment elements, which improves the correlation between project time series. When the corrected project time series is used to evaluate the project, the correlation of the corrected elements is improved, which can more intuitively and accurately reflect the project progress.
[0066] The abruptness value, the discrete value and the overall difference value may be implemented in other forms known in the art, which will not be described in detail here.
[0067] Embodiment 2:
[0068] This embodiment provides an evaluation method for a project time series. This embodiment is optimized on the basis of the first embodiment to improve the technical effect and refine the technical solution. For the contents not fully described in this embodiment, please refer to the first embodiment.
[0069] Embodiment 1 mentions clustering all elements in each project time series. Optionally, in a further but non-limiting embodiment of the present application, the clustering method includes:
[0070] Get the maximum element in the project time series, and get the ratio between each element in the project time series and the maximum element;
[0071] Get the sum of the squares of the differences between each element and the adjacent elements in the project time series;
[0072] The product of the ratio and the sum of the squares of the differences is taken as the change characteristic value of the corresponding element in the project time series; the change characteristic value is obtained as follows:
[0073] ,
[0074] In the formula, is the changing characteristic value of the element, is the value of the element in the project time sequence, is the value of the largest element in the project time series, is the ratio, is the number of adjacent elements, is the counting sequence of adjacent elements, For the The values of adjacent elements, is the sum of the squares of the differences;
[0075] All elements are clustered according to the change characteristic value of each element in the project time series to obtain one or more clusters.
[0076] By calculating the change characteristic value, clustering analysis can be performed more reasonably, because the accuracy of clustering depends largely on the selection of features, and good features can improve the quality and interpretability of clustering. In this embodiment, the ratio between each element and the maximum element in the project time series sequence, as well as the sum of the squares of the differences between each element and the adjacent elements in the project time series sequence are used to control the value of the change characteristic value. The change characteristic value combines the degree of abnormality and the degree of fluctuation, providing a comprehensive feature description for element abnormality detection.
[0077] As one embodiment, the method for obtaining adjacent elements includes:
[0078] A window of a specific length is constructed with the element as the center, and all elements in the window are recorded as adjacent elements. The length of the window can be 7. In addition, if the elements in the window are less than the specific length, only the elements in the window are recorded as adjacent elements.
[0079] It should be noted that when analyzing the differences and correlations between project time series, it is necessary to make judgments based on the changing characteristics of the project time series over time, so it is necessary to obtain the change characteristic value of each element in the project time series. The main change types of elements in the project time series include steadily changing elements, rising or falling trend elements, inflection point elements, and mutation elements. The difference in the main change types of these elements is mainly reflected in the amplitude of the element and the amplitude difference with nearby elements, so the change characteristic value of the element is constructed accordingly.
[0080] Embodiment 1 also mentions obtaining the overall amplitude of the cluster to which each element belongs. As one embodiment, the mean of all elements in the cluster to which each element belongs is used as the corresponding overall amplitude. Embodiment 1 mentions obtaining the difference between each element and the reference element at the same time in the timing sequence of other items. As one embodiment, the change characteristic value of each element and the change characteristic value of its reference element are obtained, and the difference value is obtained according to the difference in the change characteristic value between the element and its reference element.
[0081] When modifying the elements in the project time series, the analysis is mainly based on the differences and correlations between the project time series, so the differences between the project time series are first analyzed in combination with the change characteristic values of the elements in the project time series. When the change characteristic values of some elements of a project time series are greatly different from the elements of other project time series at the same time, it means that the degree to which these elements in the project time series need to be modified is greater. Therefore, firstly, multiple clusters are obtained according to the change characteristic values of the elements in the project time series, and the abruptness value of each element is obtained according to the difference in the change characteristic values of the elements and the clusters they belong to.
[0082] Since the main change types of elements in the project time series include stable change elements, rising or falling trend elements, inflection point elements, and mutation elements, elements of different change types represent different element change trends. When analyzing the abruptness of elements, it can reflect the changes in various links during the project process. Since there are differences in the change characteristic values between elements of these change types, the elements in the target project time series are first clustered according to the change characteristic values of the elements.
[0083] As one embodiment, k-means clustering is performed on the elements in the project time series according to the change characteristic values of the elements, and optionally, k = 4. K-means clustering can be implemented in other forms known in the art, such as even more other known forms, which will not be described in detail here.
[0084] This embodiment also provides an acquisition formula for the abruptness value of an element. The acquisition formula for the abruptness value of an element is as follows:
[0085] ,
[0086] In the formula, is the obtrusiveness value of the element, is the overall amplitude corresponding to the element. The larger the overall amplitude is, the larger the overall size of all elements in the cluster where the element is located is, and the greater the degree to which the element needs to be corrected. is the number of reference elements, is the counting number of the reference element, For the The change characteristic value of the reference element, is the difference value. The larger the difference value, the greater the difference between the element and its reference element, and the greater the degree to which the element needs to be corrected. Among them, the overall amplitude corresponding to the element represents the change trend value of the element, and the difference value of the change characteristic value between the element and the reference element represents the prominence of the element.
[0087] Embodiment 1 also mentions that the overall difference value between the cluster class where each element is located and the cluster class where the reference element is located is obtained. As one of the embodiments, the mean of all elements in the cluster class where the element is located and the mean of all elements in the cluster class where the reference element is located are obtained respectively, and multiple absolute values of differences between the two means are obtained, and the absolute values of the differences are used as the overall difference values.
[0088] It should be noted that since the changes of elements in all project timing sequences follow the project progress, there is correlation between the project timing sequences of the engineering project. It is necessary to obtain the abnormality degree value of the element based on the correlation between the project timing sequences to improve the reliability of the correction result.
[0089] In an engineering project, when a certain project time sequence changes, the project time sequence associated with that project time sequence will also change accordingly. For example, in the process of building construction, the slow progress of construction may be caused by untimely supply of raw materials or shortage of human resources.
[0090] Therefore, as one of the embodiments, the abnormality value of each element is obtained according to the abruptness value, the discrete value and the overall difference value mentioned in the first embodiment, wherein the acquisition of the overall difference value can also be expanded as follows:
[0091] According to the overall difference between the cluster where the element is located and the cluster where the reference element is located, several dimensional difference values of the element are obtained, and the product of the mean of all dimensional difference values of the element, the method of the abruptness value of the element and its reference element, and the abruptness value is taken as the abnormality value of the element.
[0092] Among them, the method for obtaining the difference value of a single dimension is:
[0093] As mentioned above, there are multiple time series of projects, so there are also multiple reference elements at the same time. For any reference element of the element, obtain the mean of all elements in the cluster where the element is located, and the mean of all elements in the cluster where the selected reference element is located, and use the difference between the two means as a single dimension difference value. Repeat the operation for each reference element until all dimension difference values corresponding to the element are obtained, and use the mean of all dimension difference values as the overall difference value.
[0094] As one embodiment, the variance between the abruptness value of each element and the abruptness value of the reference element, the discrete value between the abruptness value of each element and the abruptness value of the reference element,
[0095] It should be noted that the larger the corresponding overall difference value of an element, the greater the difference in change between the element and the elements in other dimensions, and the more abnormal the element is; the larger the variance between the abruptness value of each element and the abruptness value of its reference element, the more discrete the abruptness of the element in the time series of each item at the moment when the element is located, and the more abnormal the element is.
[0096] After obtaining the abnormality value of each element, the elements in the project time series can be corrected by comparing the differences in the abnormality of the elements between different project time series. Since the correction is to increase the correlation between the project time series and reduce the degree of outliers of the elements of different project time series, the elements in the project time series are corrected accordingly. First, the correction degree of the element is obtained according to the difference in the abnormality value between the element and the reference element, and the element is corrected according to the correction degree of the element, and the project is analyzed according to the corrected result.
[0097] Optionally, in a further but non-limiting embodiment of the present application, the abnormality value is linearly normalized, and the abnormality value after linear normalization is used as the correction degree of the element, and the difference between 1 and the correction degree is calculated, and the product of the element to be corrected and the difference is recorded as the correction value of the element. The correction formula of the element is as follows:
[0098] ,
[0099] In the formula, is the corrected value of the element, is the value of the element in the project time sequence, is a linear normalization function, is the degree of correction of the element, The larger the value, the greater the overall difference between the abnormal degree values of the element and its reference element, and the greater the degree to which the target element needs to be corrected. is the number of reference elements, is the abnormality value of the element, is the counting number of the reference element, For the The abnormality value of the reference element, is the absolute value function.
[0100] According to the method mentioned above, the correction value of each element in each project time series is obtained, and all elements in all project time series are replaced with the correction value corresponding to each element to obtain several corrected project time series. According to the elements in the corrected project time series, all elements are clustered by k-means, and the k value is determined according to the elbow method to obtain several feature clusters.
[0101] Extract the correction element from the corrected project time series; obtain the absolute value of the difference between the correction element and the mean of all correction elements in the feature cluster where the correction element is located, and output the outlier degree evaluation of the correction element according to the absolute value of the difference; the outlier degree evaluation can be recorded as the special degree of the element. The greater the special degree of the element, the greater the degree of outlier of the element.
[0102] The evaluation potential of the corrected project time series can also be further explored. The absolute values of the differences of all the corrected elements in all the corrected project time series are obtained, and the mean normalization results of all the absolute values of the differences are obtained; the mean normalization results can be recorded as the project abnormality index. The more corrected elements with greater specialness in all the corrected project time series, the greater the project abnormality index.
[0103] Furthermore, a preset abnormality threshold is obtained; and according to the comparison between the abnormality threshold and the mean normalization result, an abnormality evaluation of the project is output. For example, if the abnormality index is greater than or equal to the preset abnormality threshold, it is judged that the project is abnormal; if the abnormality index is less than the preset abnormality threshold, it is judged that the project is normal. Optionally, the abnormality threshold is 0.4.
[0104] In summary, this embodiment provides an evaluation method for your project timing sequence, improves the technical effect, and refines the technical solution.
[0105] Embodiment three:
[0106] This embodiment provides a computer device, including a processor and a memory connected to the processor, wherein a computer program is stored in the memory, and when the computer program is executed by the processor, the steps of the project timing sequence evaluation method provided in Embodiment 1 or 2 are performed.
[0107] The computer device may be a server or an electronic terminal. As one embodiment, refer to Figure 2 , the computer device includes a processor, a memory, an input / output interface (Input / Output, referred to as I / O) and a communication interface. The processor, the memory and the input / output interface are connected through a system bus, and the communication interface is connected to the system bus through the input / output interface. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store data obtained and generated in the evaluation method of the project timing sequence. The input / output interface of the computer device is used to exchange information between the processor and an external device. The communication interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, the evaluation method of the project timing sequence provided in embodiment one or two is implemented.
[0108] Those skilled in the art will understand that Figure 2 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.
[0109] The computer device provided in this embodiment has the same technical effects as those in Embodiment 1 or 2, which will not be described in detail here.
[0110] Embodiment 4:
[0111] This embodiment provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps of the project timing sequence evaluation method provided in the first or second embodiment are implemented.
[0112] The computer-readable storage medium provided in this embodiment has the same technical effects as those in Embodiment 1 or 2, and will not be described in detail here.
[0113] Embodiment five:
[0114] This embodiment provides a computer program product, on which a computer program is stored, and when the program is executed by a processor, the steps of the project timing sequence evaluation method provided in Embodiment 1 or Embodiment 2 are implemented. The computer program product provided in this embodiment can be transmitted, distributed and downloaded in the form of a signal via the Internet.
[0115] The computer program product provided in this embodiment has the same technical effects as those in Embodiment 1 or 2, and will not be described in detail here.
[0116] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present application may adopt the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.
[0117] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0118] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0119] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0120] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for evaluating a project time series, characterized in that: include, Get multiple project time series; Cluster all elements in each project time series to obtain one or more clusters; Obtaining the difference value between each element and the reference element at the same time in the time series of other items; obtaining the overall amplitude of the cluster to which each element belongs; and obtaining the abruptness value of each element according to the difference value and the overall amplitude; Get the discrete value between the obtrusiveness value of each element and the obtrusiveness value of its reference element; Get the overall difference between the cluster of each element and the cluster of the reference element; Obtaining an abnormality value of each element according to the abruptness value, the discrete value and the overall difference value; According to the abnormality level value of each element, the project time series sequence is corrected, and the corrected project time series sequence is evaluated to obtain an evaluation result.
2. The method for evaluating a project time series according to claim 1, characterized in that: The clustering of all elements in each project time series to obtain one or more clusters includes: Obtaining the maximum element in the project time series, and obtaining the ratio between each element in the project time series and the maximum element; Obtaining the sum of the squares of the differences between each element in the project time series and its adjacent elements; The product of the ratio and the sum of the squares of the differences is used as the change characteristic value of the corresponding element in the project time series; wherein the change characteristic value is obtained as follows: , In the formula, is the changing characteristic value of the element, is the value of the element in the project time sequence, is the value of the largest element in the project time series, is the ratio, is the number of adjacent elements, is the counting sequence of adjacent elements, For the The values of adjacent elements, is the sum of the squares of the differences; All elements are clustered according to the change characteristic value of each element in the project time series to obtain one or more clusters.
3. The method for evaluating a project time series according to claim 2, characterized in that: The obtaining of the overall amplitude of the cluster in which each element belongs includes taking the mean of all elements in the cluster in which each element belongs as the corresponding overall amplitude; The obtaining of the difference value between each element and a reference element at the same time in a timing sequence of other items includes obtaining a change characteristic value of each element and a change characteristic value of its reference element, and obtaining the difference value according to the difference in the change characteristic value between the element and its reference element.
4. The method for evaluating a project time series according to claim 3, characterized in that: The obtaining of the abruptness value of each element according to the difference value and the overall amplitude includes the following formula for obtaining the abruptness value of the element: , In the formula, is the obtrusiveness value of the element, is the overall amplitude of the element, is the number of reference elements, is the counting number of the reference element, For the The change characteristic value of the reference element, is the difference value.
5. The method for evaluating a project time series according to claim 1, characterized in that: The step of obtaining the overall difference between the cluster class where each element is located and the cluster class where the reference element is located includes: The means of all elements in the cluster where the element is located and the means of all elements in the cluster where the reference element is located are respectively obtained, and multiple absolute values of differences between the two means are obtained, and the absolute values of the differences are used as the overall difference values.
6. The method for evaluating a project time series according to claim 1, characterized in that: The step of correcting the project time series according to the abnormality level value of each element includes the following correction formula for each element in the project time series: , In the formula, is the corrected value of the element, is the value of the element in the project time sequence, is a linear normalization function, is the degree of correction of the element, is the number of reference elements, is the abnormality value of the element, is the counting number of the reference element, For the The abnormality value of the reference element.
7. The method for evaluating a project time series according to claim 1, characterized in that: The step of evaluating the modified project time series to obtain an evaluation result includes: Perform k-means clustering on all the corrected elements in all the corrected project time series to obtain one or more feature clusters; extracting a correction element from the corrected project timing sequence; Obtaining the absolute value of the difference between the correction element and the mean of all correction elements in the characteristic cluster class where the correction element is located, and outputting an outlier degree evaluation of the correction element according to the absolute value of the difference; Obtain the absolute values of the differences of all corrected elements in all corrected project time series, and obtain the mean normalized results of all the absolute values of the differences; Get the preset abnormal threshold; According to the comparison between the abnormal threshold and the mean normalization result, the abnormal evaluation of the project is output.
8. A computer device, characterized in that: It comprises a processor and a memory connected to the processor, wherein a computer program is stored in the memory, and when the computer program is executed by the processor, the steps of the project timing sequence evaluation method as claimed in any one of claims 1 to 7 are executed.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps of the method for evaluating the project timing sequence described in any one of claims 1 to 7 are implemented.
10. A computer program product comprising a computer program / instructions, characterized in that When the computer program / instructions are executed by a processor, the steps of the method for evaluating the project timing sequence as described in any one of claims 1 to 7 are implemented.