Road engineering progress management method and system

Through the BIM building management model and weighing components + NFC tag identification system, the problem of difficult to measure the weight of vehicle materials in traditional cameras is solved, accurate monitoring of project progress and cutting corners is achieved, and management efficiency and construction quality are improved.

CN118982319AInactive Publication Date: 2024-11-19CHANGSHA UNIVERSITY OF SCIENCE AND TECHNOLOGY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411011156.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-11-19
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional camera detection is difficult to measure the weight of the vehicle's transport materials, which affects the quality of the project and is difficult to effectively manage the project progress.

Method used

The BIM building management model is used to combine weighing components and NFC tag identification system to weigh and identify transport materials, calculate project progress, and feed back to managers in real time to detect and prevent cutting corners.

Benefits of technology

Accurate and timely monitoring of project progress, improve management efficiency, ensure project quality and safety, reduce design change risks, and improve construction quality and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118982319A_ABST
    Figure CN118982319A_ABST
Patent Text Reader

Abstract

The invention discloses a highway engineering progress management method and system in the technical field of highway engineering management. The system comprises a BIM building management model which is used for managing construction progress, personnel, materials and equipment; the project progress management module comprises a progress calculation unit, and the progress calculation unit is used for calculating project progress data; the positioning management module is used for identifying and positioning constructors, construction equipment and construction materials; the feedback module is used for sending the abnormal information to equipment of a manager according to a first priority; the weighing assembly is used for identifying and weighing the building materials conveyed by the transportation equipment entering the highway construction site; the progress calculation unit is used for calculating the progress of a project by using the data of the building materials; the building materials are weighed through the weighing assembly, then weight information is sent to the progress calculation unit and converted into progress data, and the project progress can be managed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of highway engineering management, and in particular is a method and system for highway engineering progress management. Background Art

[0002] Highway project progress management is a complex and critical process that involves all stages of the project, from preliminary preparation to construction process to completion acceptance.

[0003] In addition, with the development of technology, trends such as digital transformation, artificial intelligence (AI) and automation, and remote work are changing the way projects are managed. These new technologies and tools can help project managers achieve more efficient resource allocation, task tracking, and progress management, and improve project efficiency.

[0004] At present, the BIM model, short for Building Information Modeling, is a digital representation used to describe the physical and functional characteristics of a building or facility. It integrates various information data required for a construction project and provides a basis for collaborative work for all participants at different stages of the project. The BIM model has the following significant features:

[0005] Information integration: BIM models integrate all information about the building project, including geometry, space, physics, and function, including various professional contents such as architecture, structure, electromechanical, and pipelines. These information are interrelated in the model, realizing unified management and query of information.

[0006] Visualization: BIM models have powerful 3D visualization capabilities, which can intuitively display the appearance, internal structure and spatial layout of building projects. This enables designers, engineers and owners to understand design intentions and plans more clearly and improve communication efficiency.

[0007] Collaboration: BIM models support collaborative work among multiple disciplines and parties. Each professional team can design, analyze and modify in the same model, and achieve real-time sharing and updating of information. This helps reduce conflicts and errors, and improves project quality and efficiency.

[0008] Simulation: BIM models can simulate the construction process and operation status of building projects, helping project teams predict potential problems and risks and develop targeted solutions. In addition, BIM models can also perform performance analysis such as energy saving, sunlight, and evacuation, providing a basis for design optimization.

[0009] Optimization: Through in-depth analysis and mining of data in the BIM model, unreasonable aspects of the design can be discovered and optimized, which helps reduce project costs, improve building performance and meet owner needs.

[0010] In practical applications, BIM models have been widely used in various engineering projects such as buildings, bridges, roads, tunnels, etc. It can not only improve design quality and efficiency, but also optimize the construction process and reduce project costs. With the continuous development and improvement of technology, BIM models will play a more important role in the future and promote the construction industry to develop in the direction of digitalization and intelligence.

[0011] The traditional engineering management model can no longer meet the current situation of rapid development of construction technology, especially when all hardware equipment for construction is close to or reaches the advanced level of foreign countries. It is urgent to use modern real-time detection technology, unlimited transmission network technology and intelligent technology to solve the quality control problem in the process of highway engineering. If data acquisition and computer data analysis technology can be used to control and dynamically manage the quality of road materials, the quality of road and bridge construction can be monitored in real time and effectively, unqualified road materials can be prevented from being used on the road, and unqualified structures can be prevented from affecting the quality of bridges. It is of great significance to save costs and ensure the safety and quality of highway construction. Traditional camera detection is difficult to measure whether the materials transported by vehicles and personnel are of sufficient weight, which affects the quality of the project. At the same time, it is difficult for cameras to manage the progress of the project. Therefore, it is necessary to propose a method and system for highway project progress management. Summary of the invention

[0012] In order to solve the above-mentioned problem that it is difficult to measure whether the materials transported by vehicles and personnel are of sufficient weight and whether there is any cutting of corners through camera detection, the purpose of the present invention is to provide a method and system for highway engineering progress management. Since highway construction grows linearly, the progress of highway construction can be managed by weighing the materials transported to the construction site, and comparing the weight of each truckload of materials with the percentage of the total weight of the planned materials. The percentages are accumulated to obtain the progress of the project, thereby achieving highway engineering progress management.

[0013] In order to achieve the above-mentioned object, the technical solution of the present invention is as follows: a system for highway engineering progress management, comprising a BIM building management model, an engineering progress management module, a positioning management module, a feedback module and a weighing component;

[0014] The BIM building management model is used to provide information such as construction procedures, material requirements and schedules. Through the information such as procedures, material requirements and schedules, a visual 3D model diagram of the overall project information can be provided in advance. Through the 3D model, the appearance of the highway, the internal space of the land and the road structure information can be intuitively viewed. At the same time, it is used for the visualization of the project progress calculation. The BIM building management model is also used for the remote visualization management of construction personnel, construction materials and construction equipment;

[0015] The project progress management module includes a progress calculation unit, which is used to calculate the project progress data and send the information to the BIM building management model;

[0016] The positioning management module includes a number of NFC tags and an NFC tag identification system. The NFC tags are used to store information about construction personnel, construction equipment, and construction materials for identification by the NFC tag identification system, and the identification information is sent to the BIM building management model.

[0017] The feedback module is used to remotely feed back the project progress, construction personnel and equipment information and status of the BIM building management model to the management client through the Internet, and send various abnormal information to the management client with the first priority;

[0018] The weighing component is used to identify and weigh the construction materials transported by the transportation equipment entering the highway construction site. The identification and weighing operations of the construction materials correspond to the material requirement list in the BIM building management model, and are used by the progress calculation unit to calculate the progress of the project.

[0019] The principle of the basic solution is: weigh each truckload of cargo materials through the weighing component, and send the weighing information to the project progress management module. The project progress management module is used to calculate the weight information of each truckload of materials and compare it with the total material weight information to calculate the progress information. The progress calculation result is sent to the BIM building management model for progress management and graphical display. The BIM building management model sends the summary information to the management personnel client to facilitate management. At the same time, the weighing component detects the existence of cutting corners and sends it to the feedback module with the first priority. The feedback module sends the cutting corners information to the management personnel client.

[0020] The beneficial effects of the basic program are:

[0021] 1. Traditionally, it is difficult to detect whether the materials transported by vehicles are of sufficient weight through camera detection, which affects the quality of the project. At the same time, it is difficult for cameras to manage the progress of the project. Weighing the vehicle can be more directly converted into the weight of the material. In combination with the BIM building management model, it can manage the progress of the project and detect whether the weight is sufficient to avoid cutting corners.

[0022] 2. Through the control and positioning of logistics personnel and logistics materials, managers can manage materials while managing personnel, thereby improving management efficiency;

[0023] 3. The BIM building management model can simulate and analyze the performance of buildings in the design phase to optimize the design plan. During the construction process, the BIM building management model can be updated in real time, track the simulation in stages and steps, assist in guiding construction, and provide feedback on construction progress, material usage, cost estimates, etc. The use of the BIM building management model helps reduce the risk of design changes and improve construction quality and efficiency.

[0024] Furthermore, the weighing component includes an identification component, an identification rod, an NFC tag identifier, a floor scale and a controller. The identification rods are symmetrical and fixedly connected to both sides of the floor scale. The identification components are fixedly connected to the identification rods. The NFC tag identifier is fixedly connected to the identification rods. The floor scale is set at the entrance and exit of transportation equipment at the highway engineering construction site. The identification component, NFC tag identifier and floor scale are all connected to the controller signal.

[0025] The beneficial effects of the basic program are:

[0026] 1. NFC tags are used to store information, and the information can be erased and written, and can record personnel information, vehicle information and material information;

[0027] 2. The NFC tag reader is used to cooperate with the NFC tag to read the information stored in the NFC and send it to the BIM building management model, so that the management personnel can know the vehicle location information and material weight information at this time, which is convenient for the management personnel's reference and tracing.

[0028] Furthermore, while the weighing scale performs in and out weighing operations on all vehicles entering and leaving the construction site, it can also weigh empty vehicles leaving the site. If there is an empty vehicle and materials have not been loaded and unloaded, the controller on the weighing scale will send this information to the management client through the BIM building management model for the management to review whether there is any cutting of corners.

[0029] The beneficial effect of the basic solution is that by comparing the weight of the empty vehicle and the loaded vehicle, it can be known whether the vehicle has been unloaded. At the same time, this information is sent to the management personnel so that the management personnel can check whether there is any cutting corners, thereby ensuring the quality and safety of the project.

[0030] Furthermore, NFC tags are respectively set on construction vehicles and construction workers, and the information of construction workers, vehicles and loading materials is set on the NFC tags on the construction workers and construction vehicles, and one person, one vehicle, and one tag management is implemented. When the construction vehicle enters the material collection point and passes the weighing scale at the construction site, the NFC tag identifier identifies the vehicle information set on the NFC tag on the passing vehicle, and compares the personnel information to determine whether it corresponds. At the same time, the identification information, identification location and person-vehicle correspondence information are sent to the BIM building management model. The BIM building management model sends the identification information at this time to the manager client to realize a positioning function for the vehicle.

[0031] The beneficial effect of the basic solution is that the personnel and vehicle information can be recorded and managed in detail, so that the management personnel can know the location and stay time of the personnel and vehicles, which is convenient for the assessment and management of the construction personnel.

[0032] Furthermore, the identification component includes a photoelectric sensor, which is symmetrical and fixedly connected to the identification rod. The photoelectric sensor and the controller are connected by signal. When the vehicle passes through the weighing scale, the photoelectric sensor is set on the identification rod, and the installation height is consistent with the height limit of the vehicle. When the vehicle passes through the weighing scale and the cargo carried is too high, the photoelectric sensor collects the height information of the over-high cargo and sends a signal to the controller. The controller sends the over-height information and the corresponding construction vehicle information and construction personnel to the BIM building management model. The BIM building management model sends this information to the management personnel to manage the height limit.

[0033] The beneficial effect of the basic solution is that by imposing over-height restrictions on trucks, the safety of vehicles can be further guaranteed, the occurrence of safety accidents can be reduced, and safety management can be facilitated.

[0034] Furthermore, the BIM construction management model is also used to calculate the time taken for construction vehicles to travel back and forth from various material delivery points, and to record the road condition information of the corresponding material collection and delivery sections by marking red for congestion and green for smooth traffic, and send this road condition information to management personnel for their deployment of vehicles.

[0035] The beneficial effect of the basic plan is that the display of road conditions for transporting materials can enable managers to more conveniently allocate vehicles and personnel, formulate transportation routes and transportation plans, and further increase construction efficiency.

[0036] Furthermore, when there are several different materials needed, the NFC tag sets multiple material information to identify the materials, and sends the information to the BIM building management model for identification and management.

[0037] The beneficial effect of the basic solution is that by recording material information, the BIM building management model can identify weight information and material information at the same time, and further enable the BIM weighing management system to calculate and manage the project progress by classifying materials.

[0038] Furthermore, a camera is provided on the identification rod, and the camera is connected to the controller by signal.

[0039] The beneficial effect of the basic solution is that adding cameras can facilitate managers' remote supervision of the construction site and on-site safety supervision.

[0040] Furthermore, by using the BIM building management model to calculate the progress, managers can rationally arrange the construction personnel, formulate the highway construction schedule and manage the materials.

[0041] The beneficial effects of the basic solution are: calculation of construction progress and graphical display can make progress management more convenient and intuitive, and lower the threshold for use.

[0042] Furthermore, a method for highway engineering progress management is characterized by comprising the following steps:

[0043] Step 1: Control the highway construction site and set up a scale to weigh the vehicles. The weight of each vehicle is compared with the percentage of the total weight of the planned materials. This percentage is accumulated to monitor the progress of the project.

[0044] Step 2: When weighing the vehicle, use the photoelectric sensor installed on the identification rod of the scale to limit the height of the vehicle. If the vehicle is overheight, the controller will send the overheight information and the corresponding construction vehicle information and construction personnel information to the BIM building management model. The BIM building management model will send this information to the management personnel to manage the height limit.

[0045] Step 3: Weigh the empty vehicles leaving the site. If there are still materials that have not been loaded and unloaded, the system will send this information to the management client through the BIM building management model for the management to review whether there is any cutting corners;

[0046] Step 4: When the vehicle is weighed, the NFC tag reader identifies the vehicle information and personnel information set on the NFC tag on the passing vehicle and compares them to see if they correspond. At the same time, the identification information, identification location and personnel-vehicle correspondence information are sent to the BIM building management model;

[0047] Step 5: When a vehicle picks up materials, the NFC tag reader identifies the vehicle information and personnel information set on the NFC tag on the passing vehicle, compares them to see if they correspond, and sends the identification information, identification location, and personnel-vehicle correspondence information to the BIM building management model;

[0048] Step 6. After the vehicle is weighed, the BIM building management model will calculate the percentage of the material weight of each vehicle and the total weight of the pre-designed material requirement table, calculate the percentage of the total weight, calculate and manage the project progress, and BIM will display the project progress at this time in a graphical form on the manager's client.

[0049] The beneficial effects of the basic program are:

[0050] 1. Real-time monitoring of the project progress is achieved by weighing the weight of each truckload of materials in real time, comparing it with the planned total weight of materials, and then adding up these percentages. This method can ensure the accuracy and timeliness of project progress data and provide managers with a reliable basis for decision-making.

[0051] 2. The identity information of vehicles and personnel is identified and compared through the NFC tag reader, realizing the refined management of construction personnel and construction vehicles. This method not only improves the efficiency of construction management, but also enhances the orderliness and standardization of the construction site.

[0052] 3. The BIM building management model displays the project progress in a graphical way on the manager's client, allowing the manager to intuitively understand the actual situation and changing trends of the project progress. This graphical display method not only improves the efficiency and accuracy of information transmission, but also enhances the manager's intuitive feeling of project progress management: BRIEF DESCRIPTION OF THE DRAWINGS

[0053] Figure 1 The present invention is a structural diagram of a highway engineering progress management system according to an embodiment of the present invention.

[0054] Figure 2 It is an axonometric view of the weighing assembly in an embodiment of the present invention.

[0055] Figure 3 for Figure 2 Axonometric drawing of an NFC tag in Figure 2.

[0056] The reference numerals in the drawings of the specification include: weighing component 1, identification component 2, identification rod 3, NFC tag identifier 4, NFC tag 5, controller 6, photoelectric sensor 7, floor scale 8, camera 9. DETAILED DESCRIPTION

[0057] The following is further described in detail through specific implementation methods:

[0058] Embodiment 1:

[0059] Basically as attached Figure 1As shown: A highway engineering progress management system, including a BIM building management model, an engineering progress management module, a positioning management module, a feedback module and a weighing component;

[0060] The BIM building management model is used to provide information such as construction procedures, material requirements and schedules. Through the information such as procedures, material requirements and schedules, a visual 3D model diagram of the overall project information can be provided in advance. Through the 3D model, the appearance of the highway, the internal space of the land and the road structure information can be intuitively viewed. At the same time, it is used for the visualization of the project progress calculation. The BIM building management model is also used for the remote visualization management of construction personnel, construction materials and construction equipment;

[0061] The project progress management module includes a progress calculation unit, which is used to calculate the project progress data and send the information to the BIM building management model;

[0062] The positioning management module includes a number of NFC tags 5 and an NFC tag 5 identification system. The NFC tag 5 is used to store information about construction personnel, construction equipment, and construction materials for identification by the NFC tag 5 identification system, and to send the identification information to the BIM building management model.

[0063] The feedback module is used to remotely feed back the project progress, construction personnel and equipment information and status of the BIM building management model to the management client through the Internet, and send various abnormal information to the management client with the first priority;

[0064] The weighing component is used to identify and weigh the construction materials transported by the transportation equipment entering the highway construction site. The identification and weighing of the construction materials correspond to the material demand list in the BIM building management model, and are used by the progress calculation unit to calculate the progress of the project.

[0065] Each truckload of cargo materials is weighed by the weighing component, and the weighing information is sent to the project progress management module. The project progress management module is used to calculate the weight information of each truckload of materials and compare it with the total material weight information to calculate the progress information. The progress calculation result is sent to the BIM building management model for progress management and graphical display. The BIM building management model sends the summary information to the management personnel client to facilitate management. At the same time, the weighing component detects the existence of shoddy work and sends it to the feedback module with the first priority. The feedback module sends the shoddy work information to the management personnel client.

[0066] Example 2

[0067] The difference from the above embodiment is that the Figure 2 -Attached Figure 3As shown, a method for highway project progress management, the steps are:

[0068] Step 1: Control the highway construction site, set up a weighbridge 8 for weighing vehicles, compare the weight of each vehicle with the percentage of the total weight of the planned materials, and accumulate the percentages to monitor the progress of the project;

[0069] Among them, the weighing component 1 includes an identification component 2, an identification rod 3, an NFC tag identifier 4, a weighing scale 8 and a controller 6. The identification rod 3 is symmetrical and bolted to both sides of the weighing scale 8. The identification component 2 is bolted to the identification rod 3. The NFC tag identifier 4 is bolted to the identification rod 3. The weighing scale 8 is set at the entrance and exit of the transportation equipment at the construction site of the highway project. The identification component 2, the NFC tag identifier 4 and the weighing scale 8 are all connected to the controller 6 signal. The identification component 2 includes a photoelectric sensor 7. The photoelectric sensor 7 is symmetrical and bolted to the identification rod 3. The photoelectric sensor 7 is connected to the controller 6 signal. When the vehicle passes When passing the weighbridge 8, the photoelectric sensor 7 is set on the identification rod 3, and the installation height is consistent with the height limit of the vehicle. When the vehicle passes and the loaded cargo is super high, the super high cargo will be detected by the photoelectric sensor 7. At this time, the photoelectric sensor 7 will send an overheight signal to the controller 6. The controller sends the superheight information and the corresponding construction vehicle information and construction personnel to the BIM building management model. The BIM building management model sends this information to the management personnel for height limit management. A camera 9 is provided on the identification rod, and the camera 9 is connected to the controller 6 by signal. The management personnel can use the camera 9 to monitor the entire engineering system in real time;

[0070] Step 2: When weighing the vehicle, the photoelectric sensor 7 set on the identification rod of the scale is used to limit the height of the vehicle. If the vehicle is overheight, the controller sends the overheight information and the corresponding construction vehicle information and construction personnel information to the BIM building management model, and the BIM building management model sends this information to the management personnel for height limit management;

[0071] Among them, the weighbridge can weigh all vehicles entering and leaving the construction site, and can also weigh empty vehicles leaving the site. If there is an empty vehicle with materials that have not been loaded and unloaded, the controller on the weighbridge will send this information to the feedback module. At the same time, the feedback module will also send this information to the management client through the BIM building management model for the management to review whether there is any cutting corners;

[0072] Step 3: Weigh the empty vehicles leaving the site. If there are still materials that have not been loaded and unloaded, the system will send this information to the management client through the BIM building management model for the management to review whether there is any cutting corners;

[0073] Among them, NFC tags 5 are respectively set on the construction vehicles and construction personnel, and the information of the construction personnel, vehicles and loading materials are set into the NFC tags 5 on the construction personnel and the construction vehicles, so as to implement one person, one vehicle, and one NFC tag 5 management;

[0074] Step four, when the construction vehicle enters the material collection point and passes the weighing scale 8 at the construction site, the NFC tag identifier 4 identifies the vehicle information set by the NFC tag 5 on the passing vehicle, and compares the personnel information to determine whether it corresponds. At the same time, the identification information, identification location and person-vehicle correspondence information are sent to the BIM building management model. The BIM building management model sends the identification information at this time to the manager client to realize a positioning function for the vehicle.

[0075] Step 5: When a vehicle picks up materials, the NFC tag reader identifies the vehicle information set on the NFC tag on the passing vehicle, compares the personnel information to see if they correspond, and sends the identification information, identification location, and personnel-vehicle correspondence information to the BIM building management model;

[0076] Among them, the BIM construction management model calculates the round-trip time of construction vehicles from each material delivery point, and the road condition information of the corresponding material collection and delivery sections is marked with red for congestion and green for smooth traffic, and this road condition information is sent to the management client for the management personnel to allocate vehicles.

[0077] Step 6. After the vehicle is weighed, the BIM building management model will calculate the percentage of the material weight of each vehicle and the total weight of the pre-designed material requirement table, calculate the percentage of the total weight, calculate and manage the project progress, and BIM will display the project progress at this time in a graphical form on the manager's client.

[0078] Among them, through progress calculation, managers can reasonably arrange construction personnel, formulate highway construction progress plans and manage materials.

[0079] The above is only an embodiment of the present invention. The common sense such as the known specific structure and characteristics in the scheme is not described in detail here. The ordinary technicians in the relevant field know all the common technical knowledge in the technical field of the invention before the application date or priority date, can obtain all the existing technologies in the field, and have the ability to apply the conventional experimental means before that date. The ordinary technicians in the relevant field can improve and implement this scheme in combination with their own abilities under the enlightenment given by this application. Some typical known structures or known methods should not become obstacles for ordinary technicians in the relevant field to implement this application. It should be pointed out that for those skilled in the art, without departing from the structure of the present invention, several deformations and improvements can be made, which should also be regarded as the protection scope of the present invention, which will not affect the effect of the implementation of the present invention and the practicality of the patent. The protection scope required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. A highway engineering progress management system, characterized by: Including BIM building management model, project progress management module, positioning management module, feedback module and weighing component; The BIM building management model is used to provide construction process, material requirements and schedule information. Through the process, material requirements and schedule information, a visual 3D model diagram of the overall project information is provided in advance. Through the 3D model, the appearance of the highway, the internal space of the land and the road structure information can be intuitively viewed. At the same time, it is used for the visualization of the project progress calculation. The BIM building management model is also used for remote visualization management of construction personnel, construction materials and construction equipment; The project progress management module includes a progress calculation unit, which is used to calculate the project progress data and send the information to the BIM building management model; The positioning management module includes a number of NFC tags and an NFC tag identification system. The NFC tags are used to store information about construction personnel, construction equipment, and construction materials for identification by the NFC tag identification system, and the identification information is sent to the BIM building management model. The feedback module is used to remotely feed back the project progress, construction personnel and equipment information and status of the BIM building management model to the management client through the Internet, and send various abnormal information to the management client with the first priority; The weighing component is used to identify and weigh the construction materials transported by the transportation equipment entering the highway construction site. The identification and weighing operations of the construction materials correspond to the material requirement list in the BIM building management model, and are used by the progress calculation unit to calculate the progress of the project.

2. The method and system for highway engineering progress management according to claim 1, characterized in that: The weighing component includes an identification component, an identification rod, an NFC tag identifier, a floor scale and a controller. The identification rods are symmetrical and fixedly connected to both sides of the floor scale. The identification components are fixedly connected to the identification rods. The NFC tag identifier is fixedly connected to the identification rods. The floor scale is set at the entrance and exit of transportation equipment at the highway construction site. The identification component, NFC tag identifier and floor scale are all connected to the controller signal.

3. The method and system for highway engineering progress management according to claim 2, characterized in that: The scale can weigh all vehicles entering and leaving the construction site, and can also weigh empty vehicles leaving the site. When there is an empty truck and materials have not been loaded and unloaded, the controller on the scale will send this information to the feedback module, and the feedback module will send this information to the management client through the BIM building management model for the management to review whether there is any cutting corners.

4. The method and system for highway engineering progress management according to claim 3, characterized in that: Set NFC tags on construction vehicles and construction personnel respectively, and set the information of construction personnel, vehicles and loading materials into the NFC tags on construction personnel and construction vehicles, so as to implement one person, one vehicle and one tag management; When a construction vehicle enters the material collection point and passes the weighing scale at the construction site, the NFC tag reader identifies the vehicle information and personnel information set on the NFC tag on the passing vehicle, compares them to determine whether they correspond, and sends the identification information, identification location and person-vehicle correspondence information to the BIM building management model. The BIM building management model sends this identification information to the manager client to locate the vehicle.

5. The method and system for highway engineering progress management according to claim 4, characterized in that: The identification component includes a photoelectric sensor, which is symmetrically and fixedly connected to the identification rod, and the installation height is consistent with the height limit of the vehicle. The photoelectric sensor is connected to the controller signal; When a vehicle passes through a weighing scale and the cargo it carries is too high, the photoelectric sensor collects the height information of the excessively high cargo and sends a signal to the controller. The controller sends the excessive height information and the corresponding construction vehicle information and construction personnel information to the BIM building management model. The BIM building management model sends this information to the management personnel for height limit management.

6. The method and system for highway engineering progress management according to claim 5, characterized in that: The BIM construction management model is also used to calculate the time it takes for construction vehicles to travel back and forth from various material delivery points, and to send the traffic information of the corresponding material collection and delivery sections by marking red for congestion and green for smooth traffic, and to the management client for the management to allocate vehicles.

7. The method and system for highway engineering progress management according to claim 6, characterized in that: When several different materials are needed, the NFC tag sets multiple material information to identify the materials and sends the information to the BIM building management model for identification and management.

8. The method and system for highway engineering progress management according to claim 7, characterized in that: A camera is arranged on the identification rod, and the camera is connected with the controller signal.

9. The method and system for highway engineering progress management according to claim 8, characterized in that: By calculating the progress through the project progress management module, managers can reasonably arrange the construction personnel, formulate the highway construction progress plan and manage the materials.

10. A method for highway engineering progress management, characterized in that: The following steps are involved: Step 1: Control the highway construction site and set up a scale to weigh the vehicles. The weight of each vehicle is compared with the percentage of the total weight of the planned materials. This percentage is accumulated to monitor the progress of the project. Step 2: When weighing the vehicle, use the photoelectric sensor installed on the identification rod of the scale to limit the height of the vehicle. If the vehicle is overheight, the controller will send the overheight information and the corresponding construction vehicle information and construction personnel information to the BIM building management model. The BIM building management model will send this information to the management personnel to manage the height limit. Step 3: Weigh the empty vehicles leaving the site. If there are still materials that have not been loaded and unloaded, the system will send this information to the management client through the BIM building management model for the management to review whether there is any cutting corners; Step 4: When the vehicle is weighed, the NFC tag reader identifies the vehicle information and personnel information set on the NFC tag on the passing vehicle and compares them to see if they correspond. At the same time, the identification information, identification location and personnel-vehicle correspondence information are sent to the BIM building management model; Step 5: When a vehicle picks up materials, the NFC tag reader identifies the vehicle information and personnel information set on the NFC tag on the passing vehicle, compares them to see if they correspond, and sends the identification information, identification location, and personnel-vehicle correspondence information to the BIM building management model; Step 6. After the vehicle is weighed, the BIM building management model will calculate the percentage of the material weight of each vehicle and the total weight of the pre-designed material requirement table, calculate the percentage of the total weight, calculate and manage the project progress, and the BIM building management model will display the project progress at this time in a graphical form on the manager's client.