Comprehensive analysis and early warning method for line loss of power system

By determining the resistance value error coefficient and the metering comprehensive error coefficient in the power system, combining the ambient temperature and metering system error, a line power loss model is established, and the problem of the impact of ambient temperature and metering error in line loss management is solved, and more accurate Line loss analysis and early warning improve the operating efficiency and safety of the power system.

CN119001276APending Publication Date: 2024-11-22JIAYUGUAN HONGSHENG ELECTRIC HEATING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411084647.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing technology online loss management fails to effectively consider ambient temperature, measurement error and measurement time error, resulting in inaccurate line loss analysis, affecting the operating efficiency and safety of the power system.

Method used

A comprehensive analysis and early warning method for line loss in power system is proposed. By determining the resistance value error coefficient, the metering comprehensive error coefficient and the load current error threshold, combining the ambient temperature and the metering system error, a mathematical model of line loss is established to perform time-dividing line loss Calculate the rate threshold to realize the warning of line loss abnormality.

Benefits of technology

It improves the accuracy and efficiency of line loss management, accurately detects line loss abnormalities, reduces management difficulty, effectively prevents power loss, and improves work efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure FT_1
    Figure FT_1
  • Figure FT_2
    Figure FT_2
  • Figure SMS_7
    Figure SMS_7
Patent Text Reader

Abstract

The invention relates to the technical field of high-voltage power transmission and distribution, in particular to a comprehensive analysis and early warning method for line loss of a power system, which comprises the following steps of: determining a resistance error coefficient of a distribution line, the resistance error coefficient comprising a positive error coefficient Kmax and a negative error coefficient Kmin; determining a metering comprehensive error coefficient JK; calculating an average load current error threshold value; determining an average load current class system correction coefficient of the distribution line, and calculating and determining a user load current threshold in different time periods; a line loss rate threshold value in the calendar period is determined, the upper limit value of the line loss rate threshold value is Wmax, and the lower limit value of the line loss rate threshold value is Wmin; when the line loss rate of the line exceeds a line loss rate threshold value, line loss abnormity early warning is carried out; according to the method, by comprehensively considering the operating environment temperature change, the watt-hour meter error factor and the mutual inductor error factor, the line active loss mathematical model is established, the positive and negative deviation threshold value of the line active loss is predicted, the hit rate of the abnormal line loss line is effectively increased, the problems of metering loop abnormity, electricity stealing and the like are timely and accurately found, and the management line loss is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of high-voltage power transmission and distribution, and in particular to a comprehensive analysis and early warning method for line losses in a power system. Background Art

[0002] With the continuous expansion of the scale of power systems and the increase in power demand, the problem of line loss has become increasingly prominent. As an important link in power transmission, the safe and efficient operation of the distribution system is of great significance to ensuring power supply. Line loss analysis is an important issue in the operation of power systems, and the line loss rate is one of the important indicators for measuring the operating efficiency of power systems. There are some problems with the existing line loss management technology, such as not considering the impact of temperature, metering error and metering time error on line loss analysis.

[0003] Traditional line loss calculation and analysis methods are mainly based on basic parameters such as current, voltage and power factor, and do not take into account the impact of ambient temperature on line resistance. In actual operation, traditional current calculation methods such as root mean square are quite different from the actual production load. At the same time, changes in ambient temperature will cause changes in line resistance, thus affecting the calculation and analysis of line loss.

[0004] Metering errors and metering time errors also have an adverse effect on line loss analysis. In the power system, energy metering is an important means to accurately measure energy consumption. However, due to factors such as the accuracy, stability and use environment of energy metering equipment, there are certain metering errors. In addition, metering time errors may also lead to inaccurate line loss calculations, especially in demand-side management. Metering time errors may further increase the difficulty of line loss management.

[0005] Failure to consider the characteristics of actual operating load current, line operating environment temperature, metering error and metering time error has an adverse effect on line loss management. In order to more accurately evaluate and manage line losses, future line loss management methods need to consider methods that are more inclined to the actual operating current of the line, consider the impact of temperature on line resistance, and the impact of metering system errors on line losses and other comprehensive factors to improve the accuracy and efficiency of line loss management. Summary of the invention

[0006] The purpose of the present invention is to provide a comprehensive analysis and early warning method for power system line losses, to more accurately evaluate and manage line losses, to consider comprehensive factors such as the actual operating current of the line, the influence of temperature on line resistance, and the influence of metering system errors on line losses, so as to improve the accuracy and efficiency of line loss management.

[0007] To achieve the above technical effects, a method for comprehensive analysis and early warning of power system line losses of the present invention comprises the following steps: Step 1: Determine the resistance error coefficient of the distribution line. The resistance error coefficient includes the positive error coefficient Kmax and negative error coefficient K min ; Step 1.1: Determine the relationship between wire resistance and temperature; Resistance of the conductor at temperature t℃: R t =R 20 [1+a 20 (t-20)]; In the formula: R t is the resistance of the circuit at temperature t℃; R 20 is the resistance when the circuit temperature is 20℃; a 20 is the temperature coefficient of resistance, the temperature coefficient of resistance 1 / ℃; Step 1.2: Determine the positive error coefficient K of the line resistance value during the time period based on the local temperature max And the line resistance negative error coefficient K min ; K max =R 20 [1+a 20 (t-20)] / R 20 =1+a 20 (t max -20), K min =R 20 [1+a 20 (t-20)] / R 20 =1+a 20 (t min -20); In the formula: t max is the highest ambient temperature during the period; t min The lowest ambient temperature during the period; Step 2: Determine the comprehensive measurement error coefficient JK, including the following steps: Step 2.1: According to the accuracy level of the user's electric energy meter, determine the maximum positive and negative deviation value of the electric energy caused by the electric energy meter. Maximum positive error coefficient of power WK max =+S1%, Maximum negative error coefficient of power WK min =-S1%; In the formula, S1 is the accuracy level of the user's electric energy meter; Step 2.2: According to the accuracy level of the user's current transformer and voltage transformer, determine the maximum positive and negative deviation value of the current caused by the current transformer, the maximum positive and negative deviation value of the voltage, and the power error coefficient caused by the current and voltage transformer; Current maximum positive deviation S CTmax =+S2%, Current maximum negative deviation S CTmix =-S2%; In the formula, S2 is the accuracy level of the user's current transformer; Maximum positive voltage deviation S TVmax =+S3%, Maximum negative voltage deviation S TVmix =-S3%; In the formula, S3 is the accuracy level of the user's voltage transformer; The current and voltage transformers cause the electric quantity error coefficient, including the maximum positive error coefficient Kui caused by the current and voltage transformers. max The maximum negative error coefficient Kui caused by the current and voltage transformer min ; Kui max =[U(1+S TVmax )I(1+S CTmax ) / UI]-1=(1+S TVmax )(1+S CTmax )-1, Kui min =[U(1-|S TVmin |)I(1-|S CTmin |) / UI]-1=(1-|S TVmin |)(1-|S CTmin |)-1; Step 2.3: The comprehensive measurement error coefficient JK includes the comprehensive maximum positive measurement error coefficient JK max And the measurement comprehensive maximum negative error coefficient JK min; Measurement comprehensive maximum positive error coefficient JK max =WK max +Kui max , Measurement comprehensive maximum negative error coefficient JK min =WK min +Kui min ; Step 3: Calculate the average load current error threshold according to the comprehensive measurement error coefficient determined in step 2, including the following steps: Step 3.1: Determine the power error threshold based on the user's power consumption and the comprehensive metering error coefficient. The upper limit of the power error threshold is W xmax The lower limit of the power error threshold is W xmin ; W xmax =W×(1+JK max ), W xmin =W×(1-|JK min |); In the formula: W is the electricity consumption in the measured calendar time T; Step 3.2: Determine the average power threshold. The upper limit of the average power threshold is P max The lower limit of the average power threshold is P min ; P max =W xmax / (T×24), P mix =W xmin / (T×24); In the formula, T is the measured calendar time; Step 3.3: The average load current error threshold includes an average load current error threshold upper limit value I max and the average load current error threshold lower limit I mix ; , ; In the formula: U N is the rated voltage of the electrical component; COSθ is the power factor; Step 4: Determine the average load current shift correction coefficient of the distribution line, and calculate the user load current threshold by time period, including the following steps: Step 4.1: Determine the load rate P during the non-production period based on the user's power load and the non-production power load 非生产 %; P 非生产 %=(load during non-production period / installed capacity of electrical equipment)%; Step 4.2: Determine the shift correction factor based on the user's actual production operation shift. The shift correction factor includes the production shift correction factor h 生产 and non-production shift correction factor h 非生产 ; h 生产 =t 1生产 / T, h 非生产 =t 1非生产 / T; In the formula: t 1生产 The actual production shift time of the user; t 1非生产 It is the actual non-production shift time of the user; T is the measurement calendar time; Step 4.3: Calculate the load current and the average load current of the distribution line in different time periods; Non-production load current I 非生产 =I 平均 ×P 非生产 % Production load current I 生产 =I 平均 [1+(1-P非生产 %)×T×h 非生产 / T×h 生产 ] Average load current threshold during non-production period: I max非生产 =I max ×P 非生产 %, I min非生产 =I min ×P 非生产 %; Average load current threshold during production: I max生产 =I max [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ], I min生产 =I min [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ]; Step 5: Determine the line loss rate threshold within the calendar period. The upper limit of the line loss rate threshold is △W max , the lower limit of the line loss rate threshold is △W min ; Step 5.1: Due to the power loss of the distribution line △P=3I 2 R, so the upper limit of power loss of distribution line is △P max And the lower limit of power loss of distribution line △P min The calculation formula is as follows: The upper limit of power loss of distribution line △P max =3×I max 2 ×K max ×R, The lower limit of power loss of distribution line △P min =3×I min 2 ×K min ×R; In the formula: R is the resistance of the circuit; Step 5.2: The calculation formula for active power loss A0 in grid components is: , Therefore, the active power loss threshold of the distribution line is determined by time-division calculation as follows: △W max =3×I max生产 2 ×K max ×R×T×h生产 +3×I max非生产 2 ×K max ×R×T×h 非生产 =3×K max ×R×T×[I max生产 2 ×h 生产 +I max非生产 2 ×h 非生产 ], △W min =3×I min生产 2 ×K min ×R×T×h 生产 +3×I min非生产 2 ×K min ×R×T×h 非生产 =3×K min ×R×T×[I min生产 2 ×h 生产 +I min非生产 2 ×h 非生产 ]; Step 5.3: Determine the upper limit of the line loss rate threshold △W within the calendar period max and lower limit △W min , △W max =(△W max / W)×100%; △W min =(△W min / W)×100%; In the formula: △W max The upper limit of theoretical power loss; △W min is the upper limit of theoretical power loss; W is the power consumption within the measurement calendar time T; Step 6: When the line loss rate of the line is greater than △W determined in step S5 max Or less than △W min When abnormal line loss occurs, an early warning is issued.

[0008] The beneficial effects of the present invention are: 1. The present invention predicts the average load according to the user's actual operating shift and power consumption, which is more in line with the actual production operation status. The predicted line active loss is more inclined to the actual line active loss value, and the predicted line loss is more accurate. It can effectively improve the hit rate of abnormal line loss lines, accurately discover line loss abnormalities, improve work efficiency and reduce management line loss.

[0009] 2. The present invention establishes a mathematical model of active power loss of the line by comprehensively considering the temperature change of the operating environment, the error factors of the electric meter and the mutual inductor, predicts the positive and negative deviation thresholds of the active power loss of the line, and comprehensively considers the error values ​​caused by various factors, which can effectively improve the accuracy of abnormal line loss warning. Through the early warning, the abnormal line metering circuit is checked in a targeted manner, the metering circuit abnormality is discovered in a timely and accurate manner, the power loss is prevented, and the management line loss is effectively reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 This is a schematic diagram of a primary system of a 35kV distribution line in Embodiment 1 of the present invention; Figure 2 Schematic diagram of a mathematical model of power loss in a power distribution line in the first embodiment of the present invention. DETAILED DESCRIPTION

[0011] The present invention provides a method for comprehensive analysis and early warning of power system line losses, comprising the following steps: Step 1: Determine the resistance error coefficient of the distribution line. The resistance error coefficient includes the positive error coefficient K max and negative error coefficient K min ; Step 1.1: Determine the relationship between wire resistance and temperature; Resistance of the conductor at temperature t℃: R t =R 20 [1+a 20 (t-20)]; In the formula: R t is the resistance of the circuit at temperature t℃; R 20 is the resistance when the circuit temperature is 20℃; a 20 is the temperature coefficient of resistance, the temperature coefficient of resistance 1 / ℃; Step 1.2: Determine the positive error coefficient K of the line resistance value during the time period based on the local temperature max And the line resistance negative error coefficient K min ; K max =R 20 [1+a 20 (t-20)] / R 20 =1+a 20 (t max -20), K min =R 20 [1+a 20 (t-20)] / R 20 =1+a 20 (t min -20); In the formula: t maxis the highest ambient temperature during the period; t min The lowest ambient temperature during the period; Since the resistance of the line will also change when the temperature of the line changes, and thus the power loss will also change, the relationship between the resistance of the wire and the temperature must be determined in step 1 of the present invention; for example, the annual maximum ambient temperature of the line is 35°C, the minimum ambient temperature is -25°C, the line material is soft aluminum wire, and the resistance temperature coefficient a 20 is 0.0041. Through step 1, we can get the one-year line Kmax=1+0.0041×(35-20)=1.0615, Kmin=1+0.0041×(-25-20)=0.8155; It can be seen that changes in line ambient temperature will have a significant impact on line resistance; Step 2: Determine the comprehensive measurement error coefficient JK, including the following steps: Step 2.1: According to the accuracy level of the user's electric energy meter, determine the maximum positive and negative deviation value of the electric energy caused by the electric energy meter. Maximum positive error coefficient of power WK max =+S1%, Maximum negative error coefficient of power WK min =-S1%; In the formula, S1 is the accuracy level of the user's electric energy meter; If the user's watt-hour meter accuracy level is 0.5, the maximum positive and negative deviation that may be caused is ±0.5%. The maximum positive error coefficient of electricity caused by the watt-hour meter error is WK max =+0.5%=+0.005, maximum negative error coefficient WK min =-0.5%=-0.005; Step 2.2: According to the accuracy level of the user's current transformer and voltage transformer, determine the maximum positive and negative deviation value of the current caused by the current transformer, the maximum positive and negative deviation value of the voltage, and the power error coefficient caused by the current and voltage transformer; Current maximum positive deviation S CTmax =+S2%, Current maximum negative deviation S CTmix =-S2%; In the formula, S2 is the accuracy level of the user's current transformer; Maximum positive voltage deviation S TVmax =+S3%, Maximum negative voltage deviation S TVmix =-S3%; In the formula, S3 is the accuracy level of the user's voltage transformer; If the accuracy level of the user's current transformer and voltage transformer is 0.5, the maximum positive deviation of the current that may be caused is S CTmax =+0.5%, maximum negative deviation of current S CTmix =-0.5%; maximum positive voltage deviation S TVmax =+0.5%, maximum negative voltage deviation S TVmix =-0.5%; The current and voltage transformers cause the electric quantity error coefficient, including the maximum positive error coefficient Kui caused by the current and voltage transformers. max The maximum negative error coefficient Kui caused by the current and voltage transformer min ; Kui max =[U(1+S TVmax )I(1+S CTmax ) / UI]-1=(1+S TVmax )(1+S CTmax )-1, Kui min =[U(1-|S TVmin |)I(1-|S CTmin |) / UI]-1=(1-|S TVmin |)(1-|S CTmin |)-1; If the accuracy level of the user's current transformer and voltage transformer is 0.5, the maximum positive error coefficient of the current and voltage transformer errors caused by the electric quantity is Kui max =(1+0.005) 2 -1=0.010025, maximum negative error coefficient Kui min = (1-0.005) 2 -1=-0.009975; Step 2.3: The comprehensive measurement error coefficient JK includes the comprehensive maximum positive measurement error coefficient JK max And the measurement comprehensive maximum negative error coefficient JK min; Measurement comprehensive maximum positive error coefficient JK max =WK max +Kui max , Measurement comprehensive maximum negative error coefficient JK min =WK min +Kui min ; If the accuracy level of the user's current transformer and voltage transformer is 0.5, the maximum positive error coefficient of the current and voltage transformer errors caused by the electric quantity is Kui max =0.010025, maximum negative error coefficient Kui min=-0.009975; then: JK max =WK max +Kui max =0.005+0.010025≈+0.015, JK min =WK min +Kui min =-0.005-0.009975≈-0.015; Step 3: Calculate the average load current error threshold according to the comprehensive measurement error coefficient determined in step 2, including the following steps: Step 3.1: Determine the power error threshold based on the user's power consumption and the comprehensive metering error coefficient. The upper limit of the power error threshold is W xmax The lower limit of the power error threshold is W xmin ; W xmax =W×(1+JK max ), W xmin =W×(1-|JK min |); In the formula: W is the electricity consumption in the measured calendar time T; For example, if the comprehensive error coefficient of a user's metering is JK=±0.015, the metering calendar time is T=30 days, and the power consumption within the metering calendar time T is W=3000000kwh, then the power error threshold of this user is: W xmax =W×(1+JKmax)=300000×(1+0.015)=3045000kwh, W xmin =W×(1-|JKmin|)=300000×(1-0.015)=2955000kwh; Step 3.2: Determine the average power threshold. The upper limit of the average power threshold is P max The lower limit of the average power threshold is P min ; P max =W xmax / (T×24), P mix =W xmin / (T×24); In the formula, T is the measured calendar time; For example, if a user's metering calendar time is T = 30 days × 24 hours = 720 hours, and the power consumption during the metering calendar time T is W = 3000000 kwh, then the user's W xmax =3045000kwh,W xmin=2955000kwh, then the average power threshold is: P max =W xmax / (T × 24) = 4229.17kW, P min =W xmin / (T × 24) = 4104.17kW; Step 3.3: The average load current error threshold includes an average load current error threshold upper limit value I max and the average load current error threshold lower limit I mix ; , ; In the formula: U N is the rated voltage of the electrical component; COSθ is the power factor; For example, the average power threshold of a user's measurement calendar time T = 30 days: P max =4229.17kW, P min = 4104.17(kW); COSθ=0.9; U N =35kV; Calculate and determine the average load current threshold: I max =P max / (1.732×U N ×COSθ) = 77.52A, I mix =P min / (1.732×U N ×COSθ)=75.23A; Step 4: Determine the average load current shift correction coefficient of the distribution line, and calculate the user load current threshold by time period, including the following steps: Step 4.1: Determine the load rate P during the non-production period based on the user's power load and the non-production power load 非生产 %; P 非生产 %=(load during non-production period / installed capacity of electrical equipment)%; For example, if the installed capacity of a user's electrical equipment is 5000kW, and the lighting load and living and office power load during the non-production period are 500kW, then P 非生产 %=500kW / 5000kW=10%; Step 4.2: Determine the shift correction factor based on the user's actual production operation shift. The shift correction factor includes the production shift correction factor h 生产 and non-production shift correction factor h 非生产; h 生产 =t 1生产 / T, h 非生产 =t 1非生产 / T; In the formula: t 1生产 The actual production shift time of the user; t 1非生产 It is the actual non-production shift time of the user; T is the measurement calendar time; For example, a factory has a continuous production shift system. The average load current shift correction factor for 720 hours in 30 days is calculated. During the shift handover period, there is a power outage of 2.4 hours per day, and the total power outage time is 72 hours in 30 days. The average load current shift correction factor for the factory during the 720-hour production period is h. 生产 =t 1生产 / T = (720-72) / 720 = 0.9, h 非生产 =t 1非生产 / T=72 / 720=0.1; Step 4.3: Calculate the load current and the average load current of the distribution line in different time periods; Non-production load current I 非生产 =I 平均 ×P 非生产 % Production load current I 生产 =I 平均 [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ] Average load current threshold during non-production period: I max非生产 =I max ×P 非生产 %, I min非生产 =I min ×P 非生产 %; Average load current threshold during production: I max生产 =I max [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ], I min生产 =I min [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ]; For example, a factory has a continuous production shift system, the measurement calendar time T = 720 hours, and the average load current shift correction factor is h 生产 =0.9, h 非生产 =0.1, load factor during non-production period P 非生产 %=10%, I max =77.52A; I min =75.23A then: Average load current threshold during non-production period: I max非生产 =I max ×P 非生产 %=7.75A, I min非生产 =I min ×P 非生产 %=7.52A; Average load current threshold during production: I max生产 =I max [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ]=85.27A, I min生产 =I min [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ]=82.75A; Step 5: Determine the line loss rate threshold within the calendar period. The upper limit of the line loss rate threshold is △W max , the lower limit of the line loss rate threshold is △W min ; Step 5.1: Due to the power loss of the distribution line △P=3I 2 R, so the upper limit of power loss of distribution line is △P max And the lower limit of power loss of distribution line △P min The calculation formula is as follows: The upper limit of power loss of distribution line △P max =3×I max 2 ×K max ×R, The lower limit of power loss of distribution line △P min =3×I min 2 ×K min ×R; In the formula: R is the resistance of the circuit; Step 5.2: The calculation formula for active power loss A0 in grid components is: , Therefore, the active power loss threshold of the distribution line is determined by time-division calculation as follows: △W max =3×I max生产 2 ×K max ×R×T×h 生产 +3×I max非生产 2 ×K max ×R×T×h 非生产 =3×K max ×R×T×[I max生产 2 ×h 生产 +I max非生产 2 ×h 非生产 ], △W min =3×I min生产 2 ×K min ×R×T×h 生产 +3×I min非生产 2 ×K min ×R×T×h 非生产 =3×K min ×R×T×[I min生产 2 ×h 生产 +I min非生产 2 ×h 非生产 ]; Step 5.3: Determine the upper limit of the line loss rate threshold △W within the calendar period max and lower limit △W min , △W max =(△W max / W)×100%; △W min =(△W min / W)×100%; In the formula: △W max The upper limit of theoretical power loss; △W min is the upper limit of theoretical power loss; W is the power consumption within the measurement calendar time T; Step 6: When the line loss rate of the line is greater than △W determined in step 5 max Or less than △W min When abnormal line loss occurs, an early warning is issued.

[0012] In the present invention, the power error threshold W is determined based on the user's power consumption and the comprehensive measurement error coefficient. xmax and W xminThe comprehensive measurement error coefficient is a comprehensive consideration of the positive and negative measurement deviations of the electric energy measurement system caused by the inherent errors of the watt-hour meter, voltage transformer, and current transformer.

[0013] In step 4, the average load current shift correction coefficient of the distribution line is determined, and the user load current threshold I is determined by time period calculation. max and I min The average load current shift correction coefficient is calculated based on the user's production shift system to calculate the average load current of the user during production and non-production periods, and a method for calculating the average load current in different time periods is proposed.

[0014] The present invention proposes a method for calculating the maximum and minimum active power losses of a distribution line by comprehensively considering the influence of ambient temperature on line resistance, the influence of comprehensive error of a metering system on line load current, and the influence of production shifts on line active power losses.

[0015] The present invention proposes a method for improving the prediction of line active power loss by studying the production shift system of users and determining the average load current in different time periods of the non-production period and the production period through the average load current shift correction coefficient, which can accurately reflect the actual line active power loss.

[0016] The present invention proposes to predict the line loss by introducing the distribution line resistance error coefficient by considering the influence of the line operating environment temperature on the line loss, and determining the maximum and minimum active loss thresholds of the line within the metering period according to the highest and lowest operating environment temperatures of the line respectively.

[0017] The present invention proposes to introduce a comprehensive metering error coefficient by comprehensively considering the adverse effects of the positive and negative errors of the voltage, current transformer and watt-hour meter accuracy used for line metering on line loss prediction, and proposes a calculation method for determining the maximum and minimum active loss thresholds of the line according to the maximum positive and negative errors existing in the line metering system.

[0018] The present invention proposes a prediction method for calculating the maximum and minimum active power losses of distribution lines after comprehensively considering the influence of ambient temperature on line resistance, the influence of comprehensive errors of metering systems on line load current, and the influence of production shifts on line active power losses. The present invention also proposes a method for determining the maximum and minimum active power loss thresholds of the line within a metering period based on the above factors, and issuing a line loss warning when the thresholds are exceeded, which can more accurately judge abnormal line losses in distribution lines.

[0019] Embodiment 1: Embodiment 1 is aimed at Figure 1 and Figure 2The distribution line shown in the figure uses the present invention. In this embodiment, the maximum operating environment temperature of the line is 35°C, the minimum environment temperature is 10°C, the accuracy level of the current transformer, voltage transformer and watt-hour meter of the metering system is 0.5, the line material is soft aluminum wire, and the resistance temperature coefficient is a 20 is 0.0041, the measurement calendar time T = 30 days, the power consumption in the measurement calendar time T is W = 3000000 kwh, the installed capacity of the power equipment of this distribution line is 5000 kW, the lighting load and the living and office power load during the non-production period are 500 kW, the user has a power outage of 2.4 hours per day during the shift change, and the total power outage time in 30 days is 72 hours, COSθ = 0.9; U N =35kV; Step 1: Determine the resistance error coefficient of the distribution line. The resistance error coefficient includes the positive error coefficient K max and negative error coefficient K min ; Step 1.1: Determine the relationship between wire resistance and temperature; Resistance of the conductor at temperature t℃: R t =R 20 [1+a 20 (t-20)]; In the formula: R t is the resistance of the circuit at temperature t℃; R 20 is the resistance when the circuit temperature is 20℃; a 20 is the temperature coefficient of resistance, the temperature coefficient of resistance 1 / ℃; Step 1.2: Determine the positive error coefficient K of the line resistance value during the time period based on the local temperature max And the line resistance negative error coefficient K min ; K max =R 20 [1+a 20 (t-20)] / R 20 =1+a 20 (t max -20) = K max =1+0.0041×(35-20)=1.0615, K min =R 20 [1+a 20 (t-20)] / R 20 =1+a 20 (t min -20) 1+0.0041×(-25-20)=0.8155; Table 1 shows the resistance correction calculation results of the distribution line at 10℃ and 35℃. Table 1 Step 2: Determine the comprehensive measurement error coefficient JK, including the following steps: Step 2.1: According to the accuracy level of the user's electric energy meter, determine the maximum positive and negative deviation value of the electric energy caused by the electric energy meter. Maximum positive error coefficient of power WK max =+0.5%=+0.005, Maximum negative error coefficient of power WK min =-0.5%=-0.005; Step 2.2: According to the accuracy level of the user's current transformer and voltage transformer, determine the maximum positive and negative deviation value of the current caused by the current transformer, the maximum positive and negative deviation value of the voltage, and the power error coefficient caused by the current and voltage transformer; Current maximum positive deviation S CTmax =+0.5%, Current maximum negative deviation S CTmix =-0.5%; Maximum positive voltage deviation S TVmax =+0.5%, Maximum negative voltage deviation S TVmix =-0.5%; The current and voltage transformers cause the electric quantity error coefficient, including the maximum positive error coefficient Kui caused by the current and voltage transformers. max The maximum negative error coefficient Kui caused by the current and voltage transformer min ; Kui max =[U(1+S TVmax )I(1+S CTmax ) / UI]-1=(1+S TVmax )(1+S CTmax )-1=(1+0.005) 2 -1=0.010025; Kui min =[U(1-|S TVmin |)I(1-|S CTmin |) / UI]-1=(1-|S TVmin |)(1-|S CTmin |)-1=(1-0.005) 2 -1=-0.009975; Step 2.3: The comprehensive measurement error coefficient JK includes the comprehensive maximum positive measurement error coefficient JK max And the measurement comprehensive maximum negative error coefficient JK min; Measurement comprehensive maximum positive error coefficient JK max =WKmax +Kui max =(0.005+0.010025)≈+0.015, Measurement comprehensive maximum negative error coefficient JK min =WK min +Kui min = (-0.005-0.009975) ≈ -0.015; Step 3: Calculate the average load current error threshold according to the comprehensive measurement error coefficient determined in step 2, including the following steps: Step 3.1: Determine the power error threshold based on the user's power consumption and the comprehensive metering error coefficient. The upper limit of the power error threshold is W xmax The lower limit of the power error threshold is W xmin ; W xmax =W×(1+JK max ) =300000×(1+0.015)=3045000kwh, W xmin =W×(1-|JK min |)=300000×(1-0.015)=2955000kwh; Step 3.2: Determine the average power threshold. The upper limit of the average power threshold is P max The lower limit of the average power threshold is P min ; P max =W xmax / (T×24)=4229.17kW, P mix =W xmin / (T×24)=4104.17kW; Step 3.3: The average load current error threshold includes an average load current error threshold upper limit value I max and the average load current error threshold lower limit I mix ; , ; Step 4: Determine the average load current shift correction coefficient of the distribution line, and calculate the user load current threshold by time period, including the following steps: Step 4.1: Determine the load rate P during the non-production period based on the user's power load and the non-production power load 非生产 %; P 非生产 %=(load during non-production period / installed capacity of electrical equipment)%=500kW / 5000kW=10%; Step 4.2: Determine the shift correction factor based on the user's actual production operation shift. The shift correction factor includes the production shift correction factor h 生产 and non-production shift correction factor h 非生产 ; h 生产 =t 1生产 / T=(720-72) / 720=0.9, h 非生产 =t 1非生产 / T=72 / 720=0.1; Step 4.3: Calculate the load current and the average load current of the distribution line in different time periods; Non-production load current I 非生产 =I 平均 ×P 非生产 % Production load current I 生产 =I 平均 [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ] Average load current threshold during non-production period: I max非生产 =I max ×P 非生产 %=7.75A, I min非生产 =I min ×P 非生产 %=7.52A; Average load current threshold during production: I max生产 =I max [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ]=85.27A, I min生产 =I min [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ]=82.75A; Step 5: Determine the line loss rate threshold within the calendar period. The upper limit of the line loss rate threshold is △W max , the lower limit of the line loss rate threshold is △W min ; Step 5.1: Due to the power loss of the distribution line △P=3I 2 R, so the upper limit of power loss of distribution line is △P max And the lower limit of power loss of distribution line △P minThe calculation formula is as follows: The upper limit of power loss of distribution line △P max =3×I max 2 ×K max ×R, The lower limit of power loss of distribution line △P min =3×I min 2 ×K min ×R; Step 5.2: The calculation formula for active power loss A0 in grid components is: , Therefore, the active power loss threshold of the distribution line is determined by time-division calculation as follows: △W max =3×I max生产 2 ×K max ×R×T×h 生产 +3×I max非生产 2 ×K max ×R×T×h 非生产 =3×K max ×R×T×[I max生产 2 ×h 生产 +I max非生产 2 ×h 非生产 ], △W min =3×I min生产 2 ×K min ×R×T×h 生产 +3×I min非生产 2 ×K min ×R×T×h 非生产 =3×K min ×R×T×[I min生产 2 ×h 生产 +I min非生产 2 ×h 非生产 ]; Step 5.3: Determine the upper limit of the line loss rate threshold △W within the calendar period max and lower limit △W min , △W max =(△W max / W)×100%; △W min =(△W min / W)×100%; Table 2 is a data table of the resistance threshold of the distribution line, the comprehensive difference coefficient of metering, the average load current threshold during production and the average load current threshold during non-production. Table 2, It is calculated from the data in Table 2. △W max =3×I max生产 2 ×K max ×R×T×h 生产 +3×I max非生产 2 ×K max ×R×T×h 非生产 =3×K max ×R×T×[I max生产 2 ×h 生产 +I max非生产 2 ×h 非生产 ] =3×29.0851×720×(85.272×0.9+7.752×0.1) / 1000=411489.08kwh; △W min =3×I min生产 2 ×K min ×R×T×h 生产 +3×I min非生产 2 ×K min ×R×T×h 非生产 =3×K min ×R×T×[I min生产 2 ×h 生产 +I min非生产 2 ×h 非生产 ] =3×26.2766×720×(82.722×0.9+7.522×0.1) / 1000=349852.96kwh; △W max =(△W max / W)×100%=(411489.08 / 3000000)100%=13.72%; △W min =(△W min / W)×100%=(349852.96 / 3000000)100%=11.66%; Step 6: The line loss rate threshold of this user within the metering period is 11.66%-13.72%. When the line loss rate of the line exceeds this range, an abnormal line loss warning is issued.

Claims

1. A comprehensive analysis and early warning method for power system line loss, Features: The steps include: Step 1: Determine the resistance error coefficient of the distribution line. The resistance error coefficient includes the positive error coefficient K max and negative error coefficient K min ; Step 1.1: Determine the relationship between wire resistance and temperature; Resistance of the conductor at temperature t℃: R t =R 20 [1+a 20 (t-20)] In the formula: R t is the resistance of the circuit at temperature t℃; R 20 is the resistance when the circuit temperature is 20℃; a 20 is the temperature coefficient of resistance, the temperature coefficient of resistance 1 / ℃; Step 1.2: Determine the positive error coefficient K of the line resistance value during the time period based on the local temperature max And the line resistance negative error coefficient K min ; K max =R 20 [1+a 20 (t-20)] / R 20 =1+a 20 (t max -20), K min =R 20 [1+a 20 (t-20)] / R 20 =1+a 20 (t min -20); In the formula: t max is the highest ambient temperature during the period; t min The lowest ambient temperature during the period; Step 2: Determine the comprehensive measurement error coefficient JK, including the following steps: Step 2.1: According to the accuracy level of the user's electric energy meter, determine the maximum positive and negative deviation value of the electric energy caused by the electric energy meter. Maximum positive error coefficient of power WK max =+S 1 %, Maximum negative error coefficient of power WK min =-S 1 %; In the formula, S 1 The accuracy level of the user's electric energy meter; Step 2.2: According to the accuracy level of the user's current transformer and voltage transformer, determine the maximum positive and negative deviation value of the current caused by the current transformer, the maximum positive and negative deviation value of the voltage, and the error coefficient of the electric quantity caused by the current and voltage transformer; Current maximum positive deviation S CTmax =+S 2 %, Current maximum negative deviation S CTmix =-S 2 %; In the formula, S 2 The accuracy level of the user's current transformer; Maximum positive voltage deviation S TVmax =+S 3 %, Maximum negative voltage deviation S TVmix =-S 3 %; In the formula, S 3 The accuracy level of the user's voltage transformer; The current and voltage transformers cause the electric quantity error coefficient, including the maximum positive error coefficient Kui caused by the current and voltage transformers. max The maximum negative error coefficient Kui caused by the current and voltage transformer min ; Kui max =[U(1+S TVmax )I(1+S CTmax ) / UI]-1=(1+S TVmax )(1+S CTmax )-1, Kui min =[U(1-|S TVmin |)I(1-|S CTmin |) / UI]-1=(1-|S TVmin |)(1-|S CTmin |)-1; Step 2.3: The comprehensive measurement error coefficient JK includes the comprehensive maximum positive measurement error coefficient JK max And the measurement comprehensive maximum negative error coefficient JK min; Measurement comprehensive maximum positive error coefficient JK max =WK max +Kui max , Measurement comprehensive maximum negative error coefficient JK min =WK min +Kui min ; Step 3: Calculate the average load current error threshold according to the comprehensive measurement error coefficient determined in step 2, including the following steps: Step 3.1: Determine the power error threshold based on the user's power consumption and the comprehensive metering error coefficient. The upper limit of the power error threshold is W xmax The lower limit of the power error threshold is W xmin ; W xmax =W×(1+JK max ), W xmin =W×(1-|JK min |); In the formula: W is the electricity consumption in the measured calendar time T; Step 3.2: Determine the average power threshold. The upper limit of the average power threshold is P max The lower limit of the average power threshold is P min ; P max =W xmax / (T×24), P mix =W xmin / (T×24); In the formula, T is the measured calendar time; Step 3.3: The average load current error threshold includes an average load current error threshold upper limit value I max and the average load current error threshold lower limit I mix ; , ; In the formula: U N is the rated voltage of the electrical component; COSθ is the power factor; Step 4: Determine the average load current shift correction coefficient of the distribution line, and calculate the user load current threshold by time period, including the following steps: Step 4.1: Determine the load rate P during the non-production period based on the user's power load and the non-production power load 非生产 %; P 非生产 %=(load during non-production period / installed capacity of electrical equipment)%; Step 4.2: Determine the shift correction factor based on the user's actual production operation shift. The shift correction factor includes the production shift correction factor h 生产 and non-production shift correction factor h 非生产 ; h 生产 =t 1生产 / T, h 非生产 =t 1非生产 / T; In the formula: t 1生产 The actual production shift time for users; t 1非生产 It is the actual non-production shift time of the user; T is the measurement calendar time; Step 4.3: Calculate the load current and the average load current of the distribution line in different time periods; Non-production load current I 非生产 =I 平均 ×P 非生产 % Production load current I 生产 =I 平均 [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ] Average load current threshold during non-production period: I max非生产 =I max ×P 非生产 %, I min非生产 =I min ×P 非生产 %; Average load current threshold during production: I max生产 =I max [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ], I min生产 =I min [1+(1-P 非生产 %)×T×h 非生产 / T×h 生产 ]; Step 5: Determine the line loss rate threshold within the calendar period. The upper limit of the line loss rate threshold is △W max , the lower limit of the line loss rate threshold is △W min ; Step 5.1: Due to the power loss of the distribution line △P=3I 2 R, so The upper limit of power loss of distribution line △P max =3×I max 2 ×K max ×R, The lower limit of power loss of distribution line △P min =3×I min 2 ×K min ×R; In the formula: R is the resistance of the circuit; Step 5.2: Due to the active power loss A in the grid components 0 The calculation formula is: Therefore, the active power loss threshold of the distribution line is determined by time-division calculation as follows: △W max =3×I max生产 2 ×K max ×R×T×h 生产 +3×I max非生产 2 ×K max ×R×T×h 非生产 =3×K max ×R×T×[I max生产 2 ×h 生产 +I max非生产 2 ×h 非生产 ], △W min =3×I min生产 2 ×K min ×R×T×h 生产 +3×I min非生产 2 ×K min ×R×T×h 非生产 =3×K min ×R×T×[I min生产 2 ×h 生产 +I min非生产 2 ×h 非生产 ]; Step 5.3: Determine the upper limit of the line loss rate threshold △W within the calendar period max and lower limit △W min , △In max =(△W max / W)×100%; △In min =(△W min / W)×100%; In the formula: △W max The upper limit of theoretical power loss; △W min is the upper limit of theoretical power loss; W is the power consumption within the measurement calendar time T]; Step 6: When the line loss rate of the line is greater than △W determined in step S5 max Or less than △W min When abnormal line loss occurs, an early warning is issued.