Power grid planning method and device
By obtaining grid structure information and power data and dynamically adjusting the power supply substation, the problem of low planning quality in traditional grid planning methods is solved, and the operation stability and power supply reliability of the power grid are improved.
Patent Information
- Application Number
- CN202411222014.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-09-02
AI Technical Summary
The traditional power grid planning method has the problem of low planning quality, which leads to the impact of new or expanded sites, lines or power plants on the operating mode of the power grid, making it difficult to effectively adjust and optimize.
By obtaining grid structure information and power data, determine the load status and line status of primary and secondary substations, dynamically adjust the power supply substations to ensure the power supply safety and reliability of power lines and optimize the grid operation mode.
It improves the quality of power grid planning, reduces the operating risks of power grids, maintains the stability of voltage, frequency and power angles, and adapts to different load needs.
Smart Images

Figure CN119010042A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of electric power technology, and in particular to a power grid planning method and device. Background Art
[0002] With the continuous growth of electricity demand and the increasing complexity of the power grid structure, higher requirements are placed on the operating efficiency and stability of the power grid; due to the development of the regional economy, electricity consumption continues to grow, and new or expanded sites, lines or power plants are needed to support economic development and the growth of electricity consumption. The construction or expansion of new sites, lines or power plants will have an impact on the original operation mode of the power grid, and power grid planning is needed to reduce the impact on the power grid.
[0003] However, traditional power grid planning methods suffer from the problem of low planning quality. Summary of the invention
[0004] Based on this, it is necessary to provide a power grid planning method and device that can improve planning quality in response to the above technical problems.
[0005] In a first aspect, the present application provides a power grid planning method, the method comprising:
[0006] Obtaining the grid structure information in the planning area, the grid structure information includes the number of primary substations connected to the power line and the line information between the primary substation and the secondary substation; wherein the operating current corresponding to the primary substation is greater than the operating current corresponding to the secondary substation;
[0007] When it is detected that the power equipment is connected to the power line, if it is determined according to the grid structure information that the power line is connected to a first substation and a second substation, the first substation is selected to supply power to the power line; wherein the first substation and the second substation are both first-level substations;
[0008] Determine a first line state of the first substation based on the line information, and confirm a load state of the first substation based on power data corresponding to the first substation;
[0009] When the first line state meets the preset line condition and the load state of the first substation is not fully loaded, it is confirmed that the power line is powered by the first substation, otherwise the second substation is reselected to power the power line; wherein the preset line condition includes that each main transformer in the secondary substation under the primary substation is connected to the primary substation through different lines;
[0010] Determining a second line state of the second substation based on the line information, and confirming a load state of the second substation based on power data corresponding to the second substation;
[0011] According to the first line state, the second line state, the load state of the first substation and the load state of the second substation, it is determined whether the first substation or the second substation supplies power to the power line.
[0012] In one embodiment, determining a first line state of a first substation based on line information includes:
[0013] Acquire the connection status of each main transformer in the secondary substation below the first substation and the first substation according to the line information;
[0014] Determining a second line state of a second substation based on the line information includes:
[0015] The connection status of each main transformer in the secondary substation below the second substation and the second substation is obtained according to the line information.
[0016] In one embodiment, the power data includes an annual total power supply and a maximum load; and confirming the load state of the first substation according to the power data corresponding to the first substation includes:
[0017] Calculating the load rate of the first substation based on the total annual power supply corresponding to the first substation and the maximum load corresponding to the first substation, and determining the load state of the first substation according to the numerical range of the load rate of the first substation;
[0018] Confirming the load state of the second substation according to the power data corresponding to the second substation includes:
[0019] The load rate of the second substation is calculated based on the total annual power supply corresponding to the second substation and the maximum load corresponding to the second substation, and the load state of the second substation is determined according to the numerical range of the load rate of the second substation.
[0020] In one embodiment, determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation, and the load state of the second substation includes:
[0021] If the first line state does not meet the preset line condition, the second line state meets the preset line condition, and the load state of the second substation is not fully loaded, it is determined that the second substation supplies power to the power line;
[0022] If the first line status does not meet the preset line conditions, the second line status meets the preset line conditions, and the load status of the second substation is fully loaded, it is determined that the second substation will supply power to the power line and output an early warning message. The early warning message is used to instruct the user to expand the second substation or add a new first-level substation.
[0023] In one embodiment, determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation, and the load state of the second substation includes:
[0024] If the first line state does not meet the preset line condition, and the second line state does not meet the preset line condition, a prompt message is output, and the prompt message is used to instruct the user to determine whether the power line is powered by the first substation or the second substation.
[0025] In one embodiment, determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation, and the load state of the second substation includes:
[0026] If the first line status meets the preset line conditions, the load status of the first substation is fully loaded, and the second line status does not meet the preset line conditions, it is determined that the first substation will supply power to the power line and output an early warning message, which is used to instruct the user to expand the first substation or add a new first-level substation.
[0027] In one embodiment, determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation, and the load state of the second substation includes:
[0028] If the first line state meets the preset line condition, the load state of the first substation is in a full load state, the second line state meets the preset line condition, and the load state of the second substation is not in a full load state, it is determined that the second substation supplies power to the power line;
[0029] If the first line status meets the preset line conditions, the load status of the first substation is fully loaded, the second line status meets the preset line conditions, and the load status of the second substation is fully loaded, then based on the load status of the first substation and the load status of the second substation, it is determined that the first substation or the second substation will supply power to the power line, and an early warning message is output. The early warning message is used to instruct the user to expand the first substation or the second substation, or to instruct the user to add a new first-level substation.
[0030] In a second aspect, the present application further provides a power grid planning device, the device comprising:
[0031] An acquisition module is used to acquire the grid structure information in the planning area, the grid structure information includes the number of primary substations connected to the power line, and the line information between the primary substation and the secondary substation; wherein the operating current corresponding to the primary substation is greater than the operating current corresponding to the secondary substation;
[0032] A selection module, for, when it is detected that the power equipment is connected to the power line, if the power line is connected to a first substation and a second substation, selecting the first substation to supply power to the power line; wherein the first substation and the second substation are both first-level substations;
[0033] A determination module, configured to determine a first line state of the first substation based on the line information, and to confirm a load state of the first substation according to power data corresponding to the first substation;
[0034] A judgment module is used to confirm that the power line is powered by the first substation when the first line state meets the preset line condition and the load state of the first substation is not fully loaded, otherwise reselect the second substation to power the power line; wherein the preset line condition includes that each main transformer in the secondary substation under the primary substation is connected to the primary substation through different lines;
[0035] The determination module is further used to determine the second line state of the second substation based on the line information, and to confirm the load state of the second substation according to the power data corresponding to the second substation;
[0036] The judgment module is also used to determine whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation and the load state of the second substation.
[0037] In a third aspect, the present application further provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and the processor implements the steps of the above method when executing the computer program.
[0038] In a fourth aspect, the present application also provides a computer-readable storage medium having a computer program stored thereon, which implements the steps of the above method when the computer program is executed by a processor.
[0039] The above-mentioned power grid planning method and device obtain the power grid structure information in the planning area. When it is detected that the power equipment is connected to the power line, if it is determined according to the power grid structure information that the first substation and the second substation are connected to the power line, the first substation is selected to supply power to the power line, and the load state and the first line state of the first substation are determined based on the line information and the corresponding power data. When the first line state meets the preset line conditions and the load state of the first substation is not fully loaded, it is confirmed that the power line is supplied by the first substation, otherwise the second substation is re-selected to supply power to the power line, and the load state and the second line state of the second substation are determined based on the line information and the corresponding power data. According to the first line state, the second line state, the load state of the first substation, and the load state of the second substation, it is determined that the first substation or the second substation supplies power to the power line; this application realizes adjustment and optimization of the power grid operation mode by comprehensively considering the structural information and load operation conditions of the power grid, thereby improving the planning quality of the power grid. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] In order to more clearly illustrate the technical solutions in the embodiments of the present application or related technologies, the drawings required for use in the embodiments of the present application or related technical descriptions will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0041] FIG1 is a schematic diagram of a flow chart of a power grid planning method in one embodiment;
[0042] FIG2 is a schematic diagram of a flow chart of a power grid planning method in another embodiment;
[0043] FIG3 is a structural block diagram of a power grid planning device in one embodiment;
[0044] FIG. 4 is a diagram showing the internal structure of a computer device in one embodiment. DETAILED DESCRIPTION
[0045] In order to facilitate understanding of the present application, the present application will be described more fully below with reference to the relevant drawings. Embodiments of the present application are provided in the drawings. However, the present application can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present application more thorough and comprehensive.
[0046] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those generally understood by those skilled in the art of the technical field of the present application. The terms used herein in the specification of the present application are only for the purpose of describing specific embodiments and are not intended to limit the present application. It is understood that the terms "first", "second", etc. used in the present application can be used to describe various elements in this article, but these elements are not limited by these terms. These terms are only used to distinguish a first element from another element.
[0047] When used herein, the singular forms "a", "an", and "said / the" may also include plural forms, unless the context clearly indicates otherwise. It should also be understood that the terms "include / comprise" or "have" and the like specify the presence of stated features, wholes, steps, operations, components, parts, or combinations thereof, but do not exclude the possibility of the presence or addition of one or more other features, wholes, steps, operations, components, parts, or combinations thereof. At the same time, the term "and / or" used in this specification includes any and all combinations of the relevant listed items.
[0048] At present, after the construction of a new site (substation), line or power supply, the original operation mode of the power grid will be impacted. That is, after the new site, line and power supply are connected, it is necessary to adjust the most reasonable operation mode of the power grid, that is, to carry out power grid planning to reduce the impact on the power grid after the new power equipment is connected. However, the traditional power grid planning method has the problem of low planning quality; among them, the power equipment can be a device for converting and transmitting power. In the embodiment of the present application, the power equipment is mainly a transformer as an example for explanation.
[0049] The power grid planning method provided in the embodiment of the present application adjusts the primary substation that supplies power to the power line according to the power grid structure information and corresponding power data in the planning area when detecting that the power equipment is connected to the power line, so as to ensure the safety and reliability of power supply. That is, by comprehensively considering the structural information of the power grid and the load operation conditions, the adjustment and optimization of the power grid operation mode is achieved, thereby improving the planning quality of the power grid.
[0050] In an exemplary embodiment, as shown in FIG1 , a power grid planning method is provided, and the method is described by taking the application of the method to a computer device as an example. The method includes:
[0051] S102, obtaining the grid structure information in the planning area, the grid structure information including the number of primary substations connected to the power line and the line information between the primary substation and the secondary substation; wherein the operating current corresponding to the primary substation is greater than the operating current corresponding to the secondary substation.
[0052] Among them, the planning area can be set according to actual conditions and is not limited in the embodiments of the present application.
[0053] Specifically, the computer equipment can obtain the power grid data within the planning area. The power grid data includes power grid structure information and power data (load operation data) corresponding to substations of different voltage levels. The substations of different voltage levels include primary substations and secondary substations as an example. The line information may include the connection status of lines and busbars between substations of different voltage levels, which is not limited in the embodiments of the present application.
[0054] It should be noted that, in the embodiment of the present application, the primary substation is a 220kV substation, the secondary substation is a 110kV substation, and the power line is a 110kV line as an example for explanation, wherein the 220kV substation is connected to the 110kV substation through a 110kV line.
[0055] For example, computer equipment can collect various types of data of the power grid (grid data) in real time, including structural data of the current grid (grid structure information), load operation data, etc.; and clean, verify and standardize the collected data to ensure the accuracy and reliability of the data.
[0056] S104, when it is detected that the power equipment is connected to the power line, if it is determined according to the grid structure information that the power line is connected to a first substation and a second substation, the first substation is selected to supply power to the power line; wherein the first substation and the second substation are both first-level substations.
[0057] Specifically, when the computer equipment detects that a new main transformer (power equipment) is connected to the power line, the upper-level 220kV substation of the power line is determined through the connected line information. If the power line is connected to two 220kV substations (the first substation and the second substation), the historical operation mode is followed and the first substation is selected to supply power to the power line. That is, when the power equipment is not connected to the power line, the power line is powered by the first substation.
[0058] For example, if the power line is only connected to one 220 kV substation, the operation mode of the newly connected power equipment is on the power line, that is, the 220 kV substation supplies power to the power line.
[0059] S106, determining a first line state of the first substation based on the line information, and confirming a load state of the first substation according to power data corresponding to the first substation.
[0060] Among them, power data may include annual total power supply and maximum load.
[0061] Specifically, the computer device can determine the first line status of the first substation based on the line information, and obtain the load rate of the first substation based on the total power supply and maximum load corresponding to the first substation. The computer device can determine the load status of the first substation based on the load rate.
[0062] S108, when the first line state meets the preset line conditions and the load state of the first substation is not fully loaded, confirm that the power line is powered by the first substation, otherwise reselect the second substation to power the power line; wherein the preset line conditions include that each main transformer in the secondary substation under the primary substation is connected to the primary substation through different lines.
[0063] Specifically, when the computer equipment determines that the main transformers in the secondary substation below the first substation are connected to the first substation through different lines (the first line state meets the preset line conditions), and the load state of the first substation is not fully loaded (satisfying the N-1 condition), it is confirmed that the power line is powered by the first substation, otherwise the operation mode of the power line is adjusted to the second substation, that is, the second substation is reselected to power the power line to ensure the reliability and safety of power supply and improve the planning quality.
[0064] It should be noted that when the load rate is greater than 100%, it indicates that it is in an overload state and is set to not satisfy the N-1 condition; if it does not exceed 100%, it is set to satisfy the N-1 condition.
[0065] S110, determining a second line state of the second substation based on the line information, and confirming a load state of the second substation according to power data corresponding to the second substation.
[0066] Specifically, the computer device can determine the second line status of the second substation based on the line information, and obtain the load rate of the second substation based on the total power supply and maximum load corresponding to the second substation, and then confirm the load status of the second substation. The method of obtaining the load rate of the second substation is the same as the above-mentioned method of obtaining the load rate of the first substation, and is not limited in the embodiment of the present application.
[0067] S112, determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation and the load state of the second substation.
[0068] Specifically, the computer equipment can comprehensively consider the first line status, the second line status, the load status of the first substation and the load status of the second substation, that is, comprehensively consider the line status (first line status, second line status) and load status of the first substation and the second substation respectively, so as to ensure the power supply reliability of substations and users of various voltage levels and meet the needs of different loads.
[0069] In the above-mentioned power grid planning method, by acquiring the power grid structure information in the planning area, when it is detected that the power equipment is connected to the power line, if it is determined according to the power grid structure information that the first substation and the second substation are connected to the power line, the first substation is selected to supply power to the power line, and the load state and the first line state of the first substation are determined based on the line information and the corresponding power data. When the first line state meets the preset line conditions and the load state of the first substation is not fully loaded, it is confirmed that the power line is supplied by the first substation, otherwise the second substation is re-selected to supply power to the power line, and the load state and the second line state of the second substation are determined based on the line information and the corresponding power data. According to the first line state, the second line state, the load state of the first substation, and the load state of the second substation, it is determined that the first substation or the second substation supplies power to the power line. By comprehensively considering the structure information and load operation of the power grid, the operation mode of the power line is reasonably adjusted to reduce the probability of power grid risk problems, which is helpful to maintain the stability of voltage, frequency and power angle, improve the overall stability of the power grid system, and improve the planning quality of the power grid.
[0070] In one embodiment, determining a first line state of a first substation based on line information includes:
[0071] Acquire the connection status of each main transformer in the secondary substation below the first substation and the first substation according to the line information;
[0072] Determining a second line state of a second substation based on the line information includes:
[0073] The connection status of each main transformer in the secondary substation below the second substation and the second substation is obtained according to the line information.
[0074] Specifically, the line information includes the connection status of the lines and busbars between the primary substation and the secondary substation. The computer equipment can obtain whether the connection of the power equipment causes the main transformers in the secondary substation below the primary substation to operate on the same busbar based on the line information, that is, obtain the connection status of each main transformer in the secondary substation below the first substation (primary substation) with the first substation, and the connection status of each main transformer in the secondary substation below the second substation (primary substation) with the second substation.
[0075] In an embodiment of the present application, by obtaining the connection status of each main transformer in the secondary substation below the first substation and the first substation based on the line information, and obtaining the connection status of each main transformer in the secondary substation below the second substation and the second substation, it is convenient to adjust the operation mode of the power line later and improve the planning quality.
[0076] In one embodiment, the power data includes an annual total power supply and a maximum load; and confirming the load state of the first substation according to the power data corresponding to the first substation includes:
[0077] Calculating the load rate of the first substation based on the total annual power supply corresponding to the first substation and the maximum load corresponding to the first substation, and determining the load state of the first substation according to the numerical range of the load rate of the first substation;
[0078] Confirming the load state of the second substation according to the power data corresponding to the second substation includes:
[0079] The load rate of the second substation is calculated based on the total annual power supply corresponding to the second substation and the maximum load corresponding to the second substation, and the load state of the second substation is determined according to the numerical range of the load rate of the second substation.
[0080] Specifically, the computer device can obtain the load rate P of the first substation according to the total power supply W and the maximum load H corresponding to the first substation, as shown in the following equations (1) and (2):
[0081] A = W / 8760; (1)
[0082] P = (A / H) * 100%; (2)
[0083] Among them, A represents the average load.
[0084] It should be noted that when the load rate is less than 100%, it indicates a non-full load state, and when the load rate is greater than or equal to 100%, it indicates a full load state; the method of obtaining the load state of the second substation is the same as the above-mentioned method of obtaining the load state of the first substation, and will not be repeated in the embodiment of the present application.
[0085] In the embodiment of the present application, the load rate of the primary substation is calculated based on the annual total power supply corresponding to the primary substation (the first substation, the second substation) and the maximum load corresponding to the primary substation, and the load state of the primary substation is determined according to the numerical range of the load rate of the primary substation, so as to quickly identify the primary substation in the risky operation range (the primary substation in the full load state), thereby ensuring the operation of the power grid and the safety of users' electricity use, and improving the planning quality of the power grid.
[0086] In one embodiment, as shown in FIG2 , determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation, and the load state of the second substation includes:
[0087] If the first line state does not meet the preset line condition, the second line state meets the preset line condition, and the load state of the second substation is not fully loaded, it is determined that the second substation supplies power to the power line;
[0088] If the first line status does not meet the preset line conditions, the second line status meets the preset line conditions, and the load status of the second substation is fully loaded, it is determined that the second substation will supply power to the power line and output an early warning message. The early warning message is used to instruct the user to expand the second substation or add a new first-level substation.
[0089] Specifically, as shown in Figure 2, when the power line is powered by the first substation, the connected power equipment will cause the main transformers in the secondary substation below the first substation to be connected to the first substation through the same busbar (the first line state does not meet the preset line conditions), and when the power line is powered by the second substation, the connected power equipment will not cause the main transformers in the secondary substation below the second substation to be connected to the second substation through the same busbar (the second line state meets the preset line conditions), and at this time the load state of the second substation is not fully loaded (satisfying the N-1 condition), then it is determined that the second substation is responsible for powering the power line.
[0090] As shown in Figure 2, when the first substation supplies power to the power line, the connected power equipment will cause the main transformers in the secondary substation below the first substation to be connected to the first substation through the same busbar (the first line state does not meet the preset line conditions), and when the second substation supplies power to the power line, the connected power equipment will not cause the main transformers in the secondary substation below the second substation to be connected to the second substation through the same busbar (the second line state meets the preset line conditions), and at this time the load state of the second substation is full load (does not meet the N-1 condition), then it is determined that the second substation supplies power to the power line, and outputs an early warning message, which is used to prompt the user that the second substation is in a critical state and needs to expand the second substation or add a new primary substation.
[0091] It should be noted that substation A in FIG. 2 is the first substation, and substation B is the second substation.
[0092] In the embodiment of the present application, by determining whether the first substation or the second substation supplies power to the power line based on the first line status, the second line status, the load status of the first substation, and the load status of the second substation, that is, comprehensively considering the structural information of the power grid and the load operation status, reasonably adjusting the operation mode of the power line to reduce the probability of grid risk problems, help maintain the stability of voltage, frequency and power angle, improve the overall stability of the power grid system, and improve the planning quality of the power grid.
[0093] In one embodiment, as shown in FIG2 , determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation, and the load state of the second substation includes:
[0094] If the first line state does not meet the preset line condition, and the second line state does not meet the preset line condition, a prompt message is output, and the prompt message is used to instruct the user to determine whether the power line is powered by the first substation or the second substation.
[0095] Specifically, as shown in Figure 2, when the power line is powered by the first substation, the connected power equipment will cause the main transformers in the secondary substation below the first substation to be connected to the first substation through the same busbar (the first line state does not meet the preset line conditions), and when the power line is powered by the second substation, the connected power equipment will cause the main transformers in the secondary substation below the second substation to be connected to the second substation through the same busbar (the second line state does not meet the preset line conditions), then a prompt message is output, the prompt message is used to instruct the user to determine that the power line is powered by the first substation or the second substation, that is, to manually arrange the operation mode of the power line.
[0096] In one embodiment, as shown in FIG2 , determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation, and the load state of the second substation includes:
[0097] If the first line status meets the preset line conditions, the load status of the first substation is fully loaded, and the second line status does not meet the preset line conditions, it is determined that the first substation will supply power to the power line and output an early warning message, which is used to instruct the user to expand the first substation or add a new first-level substation.
[0098] Specifically, as shown in Figure 2, when the power line is powered by the first substation, the connected power equipment will not cause the main transformers in the secondary substation below the first substation to be connected to the first substation through the same busbar (the first line state meets the preset line conditions), and the load state of the first substation is full load (does not meet the N-1 condition). When the power line is powered by the second substation, the connected power equipment will cause the main transformers in the secondary substation below the second substation to be connected to the second substation through the same busbar (the second line state does not meet the preset line conditions), then it is determined that the first substation will power the power line, and an early warning message is output. The early warning message is used to prompt the user that the second substation is in a critical state and that the second substation needs to be expanded or a new primary substation needs to be added.
[0099] In one embodiment, as shown in FIG2 , determining whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation, and the load state of the second substation includes:
[0100] If the first line state meets the preset line condition, the load state of the first substation is in a full load state, the second line state meets the preset line condition, and the load state of the second substation is not in a full load state, it is determined that the second substation supplies power to the power line;
[0101] If the first line status meets the preset line conditions, the load status of the first substation is fully loaded, the second line status meets the preset line conditions, and the load status of the second substation is fully loaded, then based on the load status of the first substation and the load status of the second substation, it is determined that the first substation or the second substation will supply power to the power line, and an early warning message is output. The early warning message is used to instruct the user to expand the first substation or the second substation, or to instruct the user to add a new first-level substation.
[0102] Specifically, as shown in Figure 2, when the power line is powered by the first substation, the connected power equipment will not cause the main transformers in the secondary substation below the first substation to be connected to the first substation through the same busbar (the first line state meets the preset line conditions), and the load state of the first substation is full load (does not meet the N-1 condition). When the power line is powered by the second substation, the connected power equipment will not cause the main transformers in the secondary substation below the second substation to be connected to the second substation through the same busbar (the second line state meets the preset line conditions), and at this time the load state of the second substation is not full load (meets the N-1 condition), then it is determined that the second substation supplies power to the power line.
[0103] As shown in FIG2 , when the first substation supplies power to the power line, the connected power equipment will not cause the main transformers in the secondary substation below the first substation to be connected to the first substation through the same busbar (the first line state meets the preset line condition), and the load state of the first substation is in a full load state (not meeting the N-1 condition). When the second substation supplies power to the power line, the connected power equipment will not cause the main transformers in the secondary substation below the second substation to be connected to the second substation through the same busbar (the second line state meets the preset line condition), and at this time the load state of the second substation is in a full load state (not meeting the N-1 condition). Then, the load rate of the first substation and the load rate of the second substation are compared, and the power line is operated in a substation with a relatively small load rate, that is, the power line is supplied by a substation with a relatively small load rate, and an early warning message is output, and the early warning message is used to instruct the user to expand the first substation or the second substation, or to instruct the user to add a new primary substation.
[0104] It should be understood that, although the various steps in the flowcharts involved in the above-mentioned embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps does not have a strict order restriction, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above-mentioned embodiments can include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily to be carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.
[0105] Based on the same inventive concept, the embodiment of the present application also provides a power grid planning device for implementing the power grid planning method involved above. The implementation scheme for solving the problem provided by the device is similar to the implementation scheme recorded in the above method, so the specific limitations in one or more power grid planning device embodiments provided below can refer to the limitations of the power grid planning method above, and will not be repeated here.
[0106] In an exemplary embodiment, as shown in FIG3 , a power grid planning device 300 is provided, and the device 300 includes:
[0107] The acquisition module 301 is used to acquire the grid structure information in the planning area, where the grid structure information includes the number of primary substations connected to the power line and the line information between the primary substation and the secondary substation; wherein the operating current corresponding to the primary substation is greater than the operating current corresponding to the secondary substation;
[0108] A selection module 302 is used for, when it is detected that the power equipment is connected to the power line, if the power line is connected to a first substation and a second substation, selecting the first substation to supply power to the power line; wherein the first substation and the second substation are both first-level substations;
[0109] A determination module 303, configured to determine a first line state of the first substation based on the line information, and to confirm a load state of the first substation according to power data corresponding to the first substation;
[0110] The judgment module 304 is used to confirm that the power line is powered by the first substation when the first line state meets the preset line condition and the load state of the first substation is not fully loaded, otherwise reselect the second substation to power the power line; wherein the preset line condition includes that each main transformer in the secondary substation under the primary substation is connected to the primary substation through different lines;
[0111] The determination module 303 is further used to determine the second line state of the second substation based on the line information, and to confirm the load state of the second substation according to the power data corresponding to the second substation;
[0112] The judgment module 304 is further used to determine whether the first substation or the second substation supplies power to the power line according to the first line state, the second line state, the load state of the first substation and the load state of the second substation.
[0113] In one embodiment, the determination module 303 is further used to obtain the connection status of each main transformer in the secondary substation under the first substation and the first substation according to the line information;
[0114] The determination module 303 is further used to obtain the connection status between each main transformer in the secondary substation located below the second substation and the second substation according to the line information.
[0115] In one embodiment, the power data includes an annual total power supply and a maximum load; the determination module 303 is further used to calculate the load rate of the first substation based on the annual total power supply corresponding to the first substation and the maximum load corresponding to the first substation, and determine the load state of the first substation according to the numerical range of the load rate of the first substation;
[0116] The determination module 303 is also used to calculate the load rate of the second substation based on the annual total power supply corresponding to the second substation and the maximum load corresponding to the second substation, and determine the load state of the second substation according to the numerical range of the load rate of the second substation.
[0117] In one embodiment, the judgment module 304 is further used to determine that the second substation supplies power to the power line if the first line state does not meet the preset line condition, the second line state meets the preset line condition, and the load state of the second substation is not fully loaded;
[0118] If the first line status does not meet the preset line conditions, the second line status meets the preset line conditions, and the load status of the second substation is fully loaded, it is determined that the second substation will supply power to the power line and output an early warning message. The early warning message is used to instruct the user to expand the second substation or add a new first-level substation.
[0119] In one embodiment, the judgment module 304 is also used to output a prompt message if the first line state does not meet the preset line conditions and the second line state does not meet the preset line conditions. The prompt message is used to instruct the user to determine whether the power line is powered by the first substation or the second substation.
[0120] In one embodiment, the judgment module 304 is also used to determine that the first substation supplies power to the power line if the first line state meets the preset line conditions, the load state of the first substation is fully loaded, and the second line state does not meet the preset line conditions, and output warning information, the warning information is used to instruct the user to expand the first substation or add a new first-level substation.
[0121] In one embodiment, the judgment module 304 is further used to determine that the second substation supplies power to the power line if the first line state meets the preset line condition, the load state of the first substation is in a full load state, the second line state meets the preset line condition, and the load state of the second substation is in a non-full load state;
[0122] If the first line status meets the preset line conditions, the load status of the first substation is fully loaded, the second line status meets the preset line conditions, and the load status of the second substation is fully loaded, then based on the load status of the first substation and the load status of the second substation, it is determined that the first substation or the second substation will supply power to the power line, and an early warning message is output. The early warning message is used to instruct the user to expand the first substation or the second substation, or to instruct the user to add a new first-level substation.
[0123] Each module in the above-mentioned power grid planning device can be implemented in whole or in part by software, hardware and a combination thereof. Each of the above-mentioned modules can be embedded in or independent of a processor in a computer device in the form of hardware, or can be stored in a memory in a computer device in the form of software, so that the processor can call and execute the operations corresponding to each of the above modules.
[0124] In an exemplary embodiment, a computer device is provided, which may be a terminal, and its internal structure diagram may be shown in FIG4. The computer device includes a processor, a memory, an input / output interface, a communication interface, a display unit, and an input device. The processor, the memory, and the input / output interface are connected via a system bus, and the communication interface, the display unit, and the input device are connected to the system bus via the input / output interface. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The input / output interface of the computer device is used to exchange information between the processor and an external device. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner may be implemented through WIFI, a mobile cellular network, near field communication (NFC) or other technologies. When the computer program is executed by the processor, a power grid planning method is implemented. The display unit of the computer device is used to form a visually visible picture, which may be a display screen, a projection device, or a virtual reality imaging device. The display screen can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device can be a touch layer covering the display screen, or a button, trackball or touchpad set on the computer device shell, or an external keyboard, touchpad or mouse.
[0125] Those skilled in the art will understand that the structure shown in FIG. 4 is merely a block diagram of a partial structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than shown in the figure, or combine certain components, or have a different arrangement of components.
[0126] In an exemplary embodiment, a computer device is provided, including a memory and a processor, wherein a computer program is stored in the memory, and the processor implements the above-mentioned power grid planning method when executing the computer program.
[0127] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the above-mentioned power grid planning method is implemented.
[0128] In one embodiment, a computer program product is provided, comprising a computer program, which implements the above-mentioned power grid planning method when executed by a processor.
[0129] It should be noted that the data involved in this application (including but not limited to data used for analysis, stored data, displayed data, etc.) are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of relevant data must comply with relevant regulations.
[0130] A person of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment method can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided in the present application can include at least one of non-volatile memory and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided in this application may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided in this application may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, an artificial intelligence (AI) processor, etc., but are not limited to this.
[0131] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this application.
[0132] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.
Claims
1. A power grid planning method, characterized in that: The method comprises: Obtaining grid structure information within the planning area, the grid structure information including the number of primary substations connected to the power line and line information between the primary substation and the secondary substation; wherein the operating current corresponding to the primary substation is greater than the operating current corresponding to the secondary substation; When it is detected that the power equipment is connected to the power line, if it is determined according to the grid structure information that the power line is connected to a first substation and a second substation, the first substation is selected to supply power to the power line; wherein the first substation and the second substation are both the first-level substations; determining a first line state of the first substation based on the line information, and confirming a load state of the first substation according to power data corresponding to the first substation; When the first line state meets the preset line condition and the load state of the first substation is not fully loaded, confirm that the power line is powered by the first substation, otherwise reselect the second substation to power the power line; wherein the preset line condition includes that each main transformer in the secondary substation under the primary substation is connected to the primary substation through different lines; determining a second line state of the second substation based on the line information, and confirming a load state of the second substation according to power data corresponding to the second substation; According to the first line state, the second line state, the load state of the first substation and the load state of the second substation, it is determined that the first substation or the second substation supplies power to the power line.
2. The method according to claim 1, characterized in that The determining a first line state of the first substation based on the line information includes: Acquire the connection status of each main transformer in the secondary substation located below the first substation and the first substation according to the line information; The determining the second line state of the second substation based on the line information includes: The connection status between each main transformer in the secondary substation below the second substation and the second substation is obtained according to the line information.
3. The method according to claim 1, characterized in that The power data includes an annual total power supply and a maximum load; and confirming the load state of the first substation based on the power data corresponding to the first substation includes: Calculating the load rate of the first substation based on the total annual power supply corresponding to the first substation and the maximum load corresponding to the first substation, and determining the load state of the first substation according to the numerical range of the load rate of the first substation; The confirming the load state of the second substation according to the power data corresponding to the second substation includes: Based on the annual total power supply corresponding to the second substation and the maximum load corresponding to the second substation, the load rate of the second substation is calculated, and the load state of the second substation is determined according to the numerical range of the load rate of the second substation.
4. The method according to claim 1, characterized in that: The determining, according to the first line state, the second line state, the load state of the first substation and the load state of the second substation, that the first substation or the second substation supplies power to the power line comprises: If the first line state does not meet the preset line condition, the second line state meets the preset line condition, and the load state of the second substation is not fully loaded, then determining that the second substation supplies power to the power line; If the first line status does not meet the preset line conditions, the second line status meets the preset line conditions, and the load status of the second substation is fully loaded, it is determined that the second substation supplies power to the power line, and outputs early warning information, wherein the early warning information is used to instruct the user to expand the second substation or add the first-level substation.
5. The method according to claim 1, characterized in that The determining, according to the first line state, the second line state, the load state of the first substation and the load state of the second substation, that the first substation or the second substation supplies power to the power line comprises: If the first line state does not meet the preset line condition and the second line state does not meet the preset line condition, a prompt message is output, wherein the prompt message is used to instruct the user to determine that the power line is powered by the first substation or the second substation.
6. The method according to claim 1, characterized in that The determining, according to the first line state, the second line state, the load state of the first substation and the load state of the second substation, that the first substation or the second substation supplies power to the power line comprises: If the first line status meets the preset line condition, the load status of the first substation is fully loaded, and the second line status does not meet the preset line condition, it is determined that the first substation supplies power to the power line, and outputs early warning information, wherein the early warning information is used to instruct the user to expand the first substation or add the first-level substation.
7. The method according to claim 1, characterized in that The determining, according to the first line state, the second line state, the load state of the first substation and the load state of the second substation, that the first substation or the second substation supplies power to the power line comprises: If the first line state meets the preset line condition, the load state of the first substation is in a full load state, the second line state meets the preset line condition, and the load state of the second substation is not in a full load state, it is determined that the second substation supplies power to the power line; If the first line status meets the preset line conditions, the load status of the first substation is fully loaded, the second line status meets the preset line conditions, and the load status of the second substation is fully loaded, then according to the load status of the first substation and the load status of the second substation, it is determined that the first substation or the second substation supplies power to the power line, and an early warning message is output, wherein the early warning message is used to instruct the user to expand the first substation or the second substation, or to instruct the user to add the first-level substation.
8. A power grid planning device, characterized in that: The device comprises: An acquisition module is used to acquire the grid structure information in the planning area, wherein the grid structure information includes the number of primary substations connected to the power line and the line information between the primary substation and the secondary substation; wherein the operating current corresponding to the primary substation is greater than the operating current corresponding to the secondary substation; A selection module, for, when it is detected that the power equipment is connected to the power line, if the power line is connected to a first substation and a second substation, selecting the first substation to supply power to the power line; wherein the first substation and the second substation are both the first-level substations; a determination module, configured to determine a first line state of the first substation based on the line information, and to confirm a load state of the first substation according to power data corresponding to the first substation; A judgment module, configured to confirm that the power line is powered by the first substation when the first line state meets the preset line condition and the load state of the first substation is not fully loaded, otherwise reselect the second substation to power the power line; wherein the preset line condition includes that each main transformer in the secondary substation below the primary substation is connected to the primary substation through different lines; The determination module is further configured to determine a second line state of the second substation based on the line information, and to confirm a load state of the second substation based on power data corresponding to the second substation; The judgment module is further used to determine whether the first substation or the second substation supplies power to the power line according to the first line status, the second line status, the load status of the first substation and the load status of the second substation.
9. A computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 7 are implemented.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 7 are implemented.
Citation Information
Patent Citations
Power distribution network planning method based on maximum power supply capacity
CN102622711A
A distributed power grid connection case base design method with good distribution network