Bridge pier protection method capable of resisting multistage impact of debris flow

Through scientific calculation and rational arrangement of RC columns, waste tires and protective nets, the problem of existing pier protection technology lacks buffer design in mudslide impacts is solved, effective pier protection and resource conservation are achieved, and maintenance costs are reduced.

CN119021089APending Publication Date: 2024-11-26NORTHWEST RES INST CO LTD OF C R E C +3
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411280190.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing bridge pier protection technology lacks buffer design when facing the impact of mudslides, which is prone to damage. Maintenance and repair require dismantling of the overall structure, which increases maintenance difficulty and cost.

Method used

Through scientific calculations, the pier protection device that meets the characteristics of local mudslides was determined. The RC column and waste tires were used as buffers, and the screws and wooden boards were connected, and a protective net was set up on the outside to optimize and adjust the spacing between RC columns and bridge piers and wooden boards to improve the length of the side of the board to improve the Load capacity and protective effect.

Benefits of technology

Effectively protect the bridge piers from being damaged by mudslide impact, reduce project costs, use waste tires and wooden boards to facilitate disassembly and replace, extend service life and reduce maintenance costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021089A_ABST
    Figure CN119021089A_ABST
Patent Text Reader

Abstract

The invention discloses a bridge pier protection method capable of resisting multistage impact of debris flow, which comprises the following steps of: 1, determining the structural type of a bridge pier according to actual engineering design, and judging the basic characteristics of the debris flow at the position of the bridge pier through field investigation and data combination and experiments; 2, the size and number of RC columns arranged around the pier and the distance between the RC columns and the pier are calculated; 3, waste tires and wood boards which are convenient to disassemble and have a buffering effect are arranged on the outer sides of the RC columns, and relevant parameters are calculated; 4, a protective net is arranged on the inner side of the RC column; through calculation and arrangement of the bridge pier protection device according with debris flow characteristics, on the basis of effectively protecting the bridge pier from being impacted and damaged by debris flow, resources are saved, the engineering cost is effectively reduced, the waste tires are used as the buffering parts of the RC columns, rigid impact between stones in the debris flow and the RC columns can be effectively avoided, and the service life of the RC columns is prolonged. The service life is long, disassembly and replacement are convenient, and maintenance cost is low.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge construction, and in particular relates to a bridge pier protection method for resisting multi-level impact of debris flow. Background Art

[0002] In bridge engineering, the safety of bridge piers, as the key supporting part of the bridge structure, is of vital importance. When bridge piers are attacked by natural disasters such as mudslides, serious structural damage and safety hazards will be caused. Existing bridge pier protection technologies usually use reinforcement materials such as reinforced concrete and protective walls to resist the impact of mudslides, which mainly rely on the fixation and sealing design of high-strength materials. However, these protection measures lack buffer design and are easily damaged when facing the impact of large rocks carried by mudslides, erosion of gravel and uneven overall impact. The overall structure needs to be dismantled for maintenance and repair, which increases the difficulty and cost of maintenance. Summary of the invention

[0003] The purpose of the present invention is to provide a bridge pier protection method for resisting multi-stage impact of debris flow, so as to solve the problems raised by the above-mentioned background technology.

[0004] To achieve the above object, the present invention provides the following technical solution: a method for protecting bridge piers against multi-stage impact of debris flow, characterized in that it comprises the following steps: S1: The structural type of the bridge pier is determined according to the actual engineering design, and then the basic characteristics of the debris flow at the location of the bridge pier are determined through on-site investigation and combined with data and experiments to obtain the debris flow velocity. V c , the speed of large rocks V , the overall impact force of debris flow F δ , impact force of large rocks F , Maximum impact height of debris flow H , Gravel particle size d min ; S2: Calculate the technical parameters of the RC columns arranged around the piers and take the height of the RC columns h=H , iterative calculation of the bearing capacity of RC columns P c , determine the overall impact force of debris flow F δ and the impact of large rocks F Is it less than the bearing capacity of a rectangular RC column? P c , the iterative calculation is done by the formula, , , where P c is the bearing capacity of the RC column; is the compressive strength of concrete; is the transverse cross-sectional area of ​​the RC column, a is the length of the RC column, b is the width of the RC column. During the iterative calculation process, it is set according to the relevant specifications and the common sizes of waste tires to be fixed on the RC column. a and b The value is substituted into the iterative calculation formula for verification until the set a and b The value of P c > F δ and P c > F ; S3: Calculate the distance between the RC columns arranged around the piers and the piers S , through the formula S = 0.5D , where D is the diameter of the bridge pier; S4: Calculate the number of RC columns , through the formula ; S5: Number of waste tires fixed on the outside of the RC column Calculated according to the following formula: , where is the outer diameter of the waste tire, n for The integer multiple relationship of ; represents the floor function, the number of square wooden boards fixed on the outside of the waste tire N T and side length Calculated according to the following formula: , ; S6: Optimize the spacing between RC columns and bridge piers S and the length of the outer board , calculated according to the following formula: , where The optimized spacing between the bridge piers and RC columns is achieved by taking the nearest value for the side length of the wooden board. ; S7: According to the number of RC columns and optimized spacing , evenly distribute the RC columns around the bridge piers, fix the waste tires and wooden boards on the outside of the RC columns by screws and nuts, and the wooden boards are set on the outside of the waste tires, and a protective net is fixed on the inside of the RC columns. The width of the protective net is w and length l Calculated according to the following formula: , The diameter of the mesh of the protective net is smaller than the particle size of the gravel. d min .

[0005] Preferably, the basic characteristics of the debris flow in step S1 also include: Gamma , Solid matter bulk density Gamma H , Roughness coefficient n , sediment correction factor , average mud depth H c , hydraulic slope I c 、Angle of force surface , Maximum stone particle size d max .

[0006] Preferably, in step S1, the debris flow velocity Calculated according to the following formula: , the speed of the large rock movement V Calculated according to the following formula: , where c is a constant, with a value of 4. The overall impact force of the debris flow F δ Calculated according to the following formula: , where g is the acceleration due to gravity, λ is the building shape coefficient, the rectangular value is 1.33, in step S2, the impact force of the large stone F Calculate according to the following formula , where E is the elastic modulus of the component, J is the moment of inertia, J The calculation can be done by get; g is the acceleration due to gravity, W The weight of the large stone.

[0007] Preferably, in step S1, the maximum impact height of the debris flow is H Calculated according to the following formula: , where g is the acceleration due to gravity.

[0008] Preferably, in step S7, the diameter of the screw d Calculated according to the following formula: , where is the yield strength of the screw material.

[0009] Preferably, the nuts are arranged in pairs at both ends of the screw rod for fixing the waste tire and the wooden board, and a spring is sleeved between each group of paired nuts.

[0010] A spring is arranged between the nuts and the nuts are pre-compressed by the spring to prevent the nuts from loosening.

[0011] Preferably, the spring stiffness coefficient of the spring is selected , where The preset compression for the spring.

[0012] Compared with the prior art, the present invention has the following beneficial effects: The present invention arranges a pier protection device that meets the local debris flow characteristics through reasonable and scientific calculations. On the basis of effectively protecting the pier from damage by the debris flow impact, it saves resources and effectively reduces the project cost. The present invention reasonably utilizes waste tires as a buffer part of the RC column, which can effectively avoid the rigid collision of stones in the debris flow with the RC column, and has a long service life. The waste tires and the wooden board are connected by screws, which is convenient for disassembly and replacement, and has a low maintenance cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Picture 1 It is a top view of a pier protection structure for resisting multi-stage impact of debris flow provided by an embodiment of the present invention; Picture 2 It is a schematic diagram of a forward cross-sectional structure of a bridge pier protection device for resisting multi-stage impact of debris flow provided by an embodiment of the present invention; Picture 3 It is a flow chart of the design of bridge pier protection against multi-stage impact of debris flow provided by an embodiment of the present invention; In the figure, 1-bridge pier, 2-RC column, 3-waste tire, 4-wooden board, 5-screw, 6-spring, 7-protective net. DETAILED DESCRIPTION

[0014] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0015] See also Picture 1-Picture 3 The present invention takes the protection of the piers of the Daleigou Bridge on the Mianjiu Expressway as an example. The piers of the Daleigou Bridge on the Mianjiu Expressway are circular piers with a diameter of 1. D= 1.6 m .

[0016] Based on the field investigation and combined with data and experiments, the basic characteristics of the debris flow at the location of Pier 1 are determined. The basic characteristics of the debris flow in Daleigou are shown in the following table: Table 1 Basic characteristics of Daleigou debris flow

[0018] (1) Calculation of debris flow velocity , the speed of large rocks V , the overall impact force of debris flow , Maximum impact height of debris flow H : ; ( c is a constant, with a value of 4); ( λ is the building shape coefficient, the value of rectangle is 1.33); ; The results are shown in the table below: Table 2 Calculation of debris flow characteristics

[0019] (2) In order to form an effective protection, the height of the RC column 2 set outside the pier 1 should not be less than the maximum impact height of the debris flow. Therefore, the height of the RC column 2 is set h=H= 3.43 m According to the requirements of the "Concrete Structure Design Code" (GB50010-2010), the cross-sectional size of the rectangular RC column 2 should not be less than 0.3m, the aspect ratio of the RC column 2 should be less than or equal to 4, and the strength grade of the important structural concrete should not be lower than C30; at the same time, considering the common outer diameter specifications of the waste tire 3 that needs to be set outside the RC column for buffering 0.65 m , 0.75 m , 0.8 m , a and b The following conditions must be met, namely , , ; n For waste tires 3 outer diameter The integer multiple relationship; take the length of the rectangular RC column 2 a= 1.3 m ,Width b= 0.325 m , n =2, select C30 concrete, substitute into the formula , , where is the bearing capacity of RC column 2; is the compressive strength of concrete; is the transverse cross-sectional area of ​​RC column 2, calculated as , = 8872.5 kPa ; F δ < , then the length of RC column 2 is preliminarily determined a ,Width b and the strength grade of concrete, substituting the impact force of the large stone into F Perform verification, , where E is the elastic modulus of the component, the elastic modulus of C30 concrete is 30000000 kPa , J is the moment of inertia, , calculated J= 0.00372m 4 ; g is the acceleration due to gravity, W The weight of the large rocks is mainly biotite granite (density 28 kg / m 3 ), the volume of the approximate sphere is 1.15 m³ , W= 1.15*28 = 32.2 kg= 0.322 KN ; Calculated F =50.813 kPa , F < , then the final length of RC column 2 is determined a =1.3 m ,Width b =0.325 m and the strength grade of concrete is C30, RC column 2 height h = H =3.43 m .

[0020] (3) Calculate the diameter of the screw 5 used to fix the waste tire 3 d : ;Pick = 250000 kPa , then the diameter of screw 5 d =16.1 mm , considering the calculation error and leaving appropriate margin, select M20 screw.

[0021] (4) Nuts need to be set at both ends of the screw 5 to lock it. In order to prevent the screw 5 from loosening, a pair of nuts are set at both ends of the screw 5. A pre-compressed spring 6 is set between the nuts to prevent the nuts from loosening. Calculate the spring stiffness coefficient of spring 6. k : ;Pick =0.1 m , then the stiffness coefficient of spring 6 is =508.13 kN / m .

[0022] (5) Determine the distance between pier 1 and rectangular RC column 2 S : S =0.5 D ; Take the spacing S =0.8 m .

[0023] (6) Calculate the number of rectangular RC columns 2 arranged around pier 1 : ; Round the result to get the number of RC column 2 =7.

[0024] (7) Calculate the number and size of the waste tires 3 and the square wooden boards 4 used for blocking on the outside: , , ;Pick =0.65 m , =70, =70, =0.7 m .

[0025] (8) Optimize and adjust the spacing according to actual working conditions S and the length of the 4 sides of the outer plank x : , ;get =0.65 m , which can be divided by h And with the original x The closest value x The value is 0.68, then x =0.68 m .

[0026] (9) Determine the size parameters and mesh parameters of the flexible protective net 7: , , mesh size of protective net< d min ;Pick w =3.43 m , l =9.1m , the mesh size of the protective net 7 is 0.05 m .

[0027] The final technical parameters of the bridge pier protection structure to be constructed are shown in the following table: Table 3 Technical parameters of pier protection structure

[0028] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for protecting bridge piers against multi-level impact of debris flow, characterized in that: The following steps are involved: S1: The structural type of the bridge pier is determined according to the actual engineering design, and then the basic characteristics of the debris flow at the location of the bridge pier are determined through on-site investigation and combined with data and experiments to obtain the debris flow velocity. V c , the speed of large rocks V 、The overall impact force of debris flow F δ , impact force of large rocks F , Maximum impact height of debris flow H , Gravel particle size d min ; S2: Calculate the technical parameters of the RC columns arranged around the piers and take the height of the RC columns h = H , iterative calculation of the bearing capacity of RC columns P c , determine the overall impact force of debris flow F δ and the impact of large rocks F Is it less than the bearing capacity of a rectangular RC column? P c , the iterative calculation is performed by the formula , , where P c is the bearing capacity of the RC column; is the compressive strength of concrete; is the transverse cross-sectional area of ​​the RC column, is the length of the RC column, is the width of the RC column. During the iterative calculation process, it is set according to the relevant specifications and the common sizes of waste tires to be fixed on the RC column. and The value is substituted into the iterative calculation formula for verification until the set and The value of > F δ and > F ; S3: Calculate the distance between the RC columns arranged around the piers and the piers S , through the formula S =0.5 D , where D is the diameter of the bridge pier; S4: Calculate the number of RC columns , through the formula ; S5: Number of waste tires fixed on the outside of the RC column Calculated according to the following formula: , where is the outer diameter of the waste tire, n for The integer multiple relationship of ; represents the floor function, the number of square wooden boards fixed on the outside of the waste tire N T and side length Calculated according to the following formula: , ; S6: Optimize the spacing between RC columns and bridge piers S and the length of the outer board , calculated according to the following formula: , where Optimized spacing between piers and RC columns, side length of wooden boards The nearest value ; S7: According to the number of RC columns and optimized spacing , evenly distribute the RC columns around the bridge piers, fix the waste tires and wooden boards on the outside of the RC columns by screws and nuts, and the wooden boards are set on the outside of the waste tires, and a protective net is fixed on the inside of the RC columns. The width of the protective net is and length Calculated according to the following formula: , The diameter of the mesh of the protective net is smaller than the particle size of the gravel. d min .

2. The bridge pier protection method for resisting multi-stage impact of debris flow according to claim 1 is characterized in that: The basic characteristics of the debris flow in step S1 also include: γ , Solid matter bulk density γ H , Roughness coefficient n , sediment correction factor , average mud depth H c , hydraulic slope I c 、Angle of force surface , Maximum stone particle size d max .

3. The bridge pier protection method for resisting multi-stage impact of debris flow according to claim 2 is characterized in that: In step S1, the debris flow velocity Calculated according to the following formula: , the speed V of the large stone is calculated according to the following formula: , where is a constant, with a value of 4. The overall impact force of the debris flow F δ Calculated according to the following formula: , where g is the acceleration due to gravity, λ is the building shape coefficient, and the rectangular value is 1.

33. In step S2, the large rock impact force F is calculated according to the following formula: , where E is the elastic modulus of the component, J is the moment of inertia, J The calculation can be done by get; g is the acceleration due to gravity, W The weight of the large stone.

4. The bridge pier protection method for resisting multi-stage impact of debris flow according to claim 1 is characterized in that: In step S1, the maximum impact height of the debris flow H Calculated according to the following formula: , where g is the acceleration due to gravity.

5. The bridge pier protection method for resisting multi-stage impact of debris flow according to claim 3 is characterized in that: In step S7, the diameter of the screw d Calculated according to the following formula: , where is the yield strength of the screw material.

6. The bridge pier protection method for resisting multi-stage impact of debris flow according to claim 5 is characterized in that: The nuts are arranged in pairs at both ends of the screw rod for fixing the waste tire and the wooden board, and a spring is sleeved between each group of paired nuts.

7. The bridge pier protection method for resisting multi-stage impact of debris flow according to claim 6 is characterized in that: The spring stiffness coefficient of the spring is selected , where The preset compression value for the spring.

Citation Information

Cited By

  • High-energy-absorption and strong-water-permeability energy dissipation pile system capable of reducing disaster through high-energy debris flow toughness

    CN121381668A