Material distributing machine lifting system and lifting method

By combining the support main frame with limit rails and winch, the fabric machine is stable and quick to adjust the height, solving the problems of high-altitude operation risks and low construction efficiency of the oblique belt machine and the inclined belt machine to match the fabric cantilever, and improving construction safety and adaptation sex.

CN119021225APending Publication Date: 2024-11-26广西平陆运河建设有限公司 +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411454485.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Priority Date
2024-02-04
Filing Date
2024-10-17
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In the prior art, the fabric cantilever of the inclined belt machine and the horizontally installed fabric cantilever needs to be lifted onto a fixed bracket with the help of a tower crane, which has a high risk of high altitude operation and low construction efficiency, so it cannot adapt to the pouring needs of different high warehouse surfaces.

Method used

The fabric machine lifting system that supports the main frame and the limit guide rail and the hoist is adopted. The fabric machine is lifted through the hoist and fixed through the limit guide rail to ensure that the fabric machine only moves in the vertical direction, reduces the load bearing requirements of the lifting system, and improves safety. and stability.

Benefits of technology

The fabric machine is stable and fast to adjust the height, avoiding the risks of high-altitude operations, improving construction efficiency and safety, and meeting the pouring needs of different high-warehouse surfaces.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021225A_ABST
    Figure CN119021225A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of concrete transportation, in particular to a material distributing machine lifting system and method. Height lifting is achieved in the mode that the winch integrally lifts the material distributing machine, meanwhile, the material distributing machine is in sliding fit with the material distributing machine, the movement freedom degree is restrained, the material distributing machine only moves in the vertical direction, the stability of the material distributing machine in the lifting process is guaranteed, and the defect that flexible lifting is unstable is overcome; after the material distributing machine is lifted to a specified height, mechanical connection with the material distributing machine is achieved through the insertion holes in the limiting guide rails, so that the bearing requirement of a lifting system is lowered, and the safety and stability of the system are improved. The device is simple in structure, can stably, quickly and continuously adjust the height of the distributing machine from low to high from the ground, does not need to repeatedly disassemble and assemble the supporting main frame or adjust the height of the supporting main frame, does not need to work aloft by virtue of a tower crane, is convenient to assemble and high in safety, and meets the pouring requirements of different high bin surfaces.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete transportation, and in particular to a concrete placing crane lifting system and a lifting method. Background Art

[0002] A certain ship lock mainly uses low-slump three-grade concrete for pouring construction. It has the characteristics of large length, large width and large volume. During construction, the side wall formwork is first built with an integral steel mold, and then concrete is poured. The implementation of concrete pouring operations requires solving the problem of high-storage surface mold pouring. In the prior art, concrete pump trucks or inclined belt conveyors are often used for high-storage surface mold pouring construction. Concrete pump trucks are machines that use pressure to continuously transport concrete along pipelines. They can only transport concrete with a large slump (an indicator used to characterize the water retention, fluidity and cohesion of concrete), and cannot meet the construction requirements of three-grade concrete pouring. Although the use of inclined belt conveyors to transport concrete materials can adapt to the three-grade concrete pouring, it must be carried out at a certain inclination angle, otherwise it will cause structural interference with nearby structures and even cause concrete materials to fall back. Therefore, in order to expand the pouring range of concrete at the high silo surface, the material distribution operation at the high silo surface is often realized by installing the material distribution boom horizontally on the fixed support in conjunction with the inclined belt conveyor for feeding. The discharge end of the feeding inclined belt conveyor should be matched with the feeding port of the material distribution boom to realize the smooth transmission of concrete. When installing this type of concrete distribution machine, the material distribution boom must be hoisted to the top of the fixed support with sufficient support strength by means of a lifting mechanism such as a tower crane before assembly. The high-altitude operation is risky, and due to the limitation of the feeding inclined belt conveyor, the material distribution boom cannot be increased with the lifting of the casting silo surface, otherwise it is necessary to disassemble or re-adjust the height of the fixed support and the feeding position of the inclined belt conveyor, resulting in low construction efficiency and poor adaptability. Summary of the invention

[0003] The purpose of the present invention is to provide a material placing machine lifting system and lifting method in view of the problem that in the prior art, when an inclined belt conveyor is used for loading materials, a horizontally installed material placing cantilever that cooperates with the inclined belt conveyor needs to be hoisted to a fixed bracket by a tower crane and then assembled, which poses a high risk of high-altitude operations.

[0004] In order to achieve the above object, the technical solution adopted by the present invention is: A material placing boom lifting system comprises a supporting main frame, on which a limit guide rail and a winch are provided, wherein the limit guide rail is arranged in a vertical direction, and a plurality of plug holes are provided on the limit guide rail at vertical intervals, the limit guide rail can slide vertically with the material placing boom and be fixed by a latch, and the winch is used to lift the material placing boom horizontally.

[0005] The above-mentioned concrete placing boom lifting system realizes height lifting by hoisting the concrete placing boom as a whole with a winch, and at the same time constrains the freedom of movement by slidingly cooperating with the concrete placing boom, so that the concrete placing boom moves only in the vertical direction, thereby ensuring the stability of the concrete placing boom during the lifting process and overcoming the defect of unstable flexible lifting; when the concrete placing boom is lifted to the specified height, it is mechanically connected with the concrete placing boom through the socket on the limit guide rail, thereby reducing the load-bearing requirements of the lifting system and improving the safety and stability of the system.

[0006] The above-mentioned material placing and lifting system has a simple structure and can stably and quickly adjust the material placing machine from low to high on the ground. It does not require repeated disassembly and assembly of the supporting main frame or adjustment of the height of the supporting main frame, nor does it require the use of a tower crane for high-altitude operations. It is easy to assemble and has high safety, and can meet the casting needs of different high-storage surfaces.

[0007] As a preferred solution of the present invention, the limit guide rails are respectively arranged on two opposite sides of the supporting main frame and are arranged in the transverse direction, and the insertion hole is arranged in the longitudinal direction of the line.

[0008] This solution preferably arranges the limit guide rails on the opposite sides of the supporting main frame and in the lateral direction. Compared with the arrangement of a single limit guide rail, it is more conducive to improving the structural stability and bearing strength, and is also conducive to simplifying the structure of the limit guide rail. A simple ridge structure or a groove structure can be directly adopted, and the left and right and front and rear side limitations can be achieved through the cooperation of two limit guide rails.

[0009] As other possible implementations, the limit guide rail can also be set on the front side of the supporting main frame. The structure of the limit guide rail can adopt a T-shaped or L-shaped hook fastener, or a long hole-shaped slide groove, directly connected to the material placing machine or through an intermediate connecting piece, and is not limited to the above examples. In addition, a certain space can be reserved at the bottom of the limit guide rail for the material placing machine to be inserted from the end, or it can be installed directly from the front side of the lifting system, which can be selected according to actual needs.

[0010] As a preferred solution of the present invention, the main support frame further includes a pair of pin holders, the pin holders are used to be detachably connected to the material placing machine, the pin holders are provided with claws, the claws on the two pin holders are arranged oppositely, and the claws are used to slide with the limit guide rails on the corresponding sides. Correspondingly, the claws are also provided with jacks. This solution adopts a pin holder that is detachably connected to the material placing machine, which is convenient for replacement and adjustment of position.

[0011] As a preferred solution of the present invention, a walking mechanism is provided at the bottom of the supporting main frame to facilitate movement.

[0012] As a preferred solution of the present invention, the main support frame is a portal truss structure, including two vertically arranged leg columns, a crossbeam is provided between the two leg columns, a load-bearing beam is provided at the bottom of each leg column along the longitudinal direction of the line, the walking mechanism is located at the bottom of the load-bearing beam, an auxiliary support connection is provided between the load-bearing beam and the leg columns, and the auxiliary support is provided on the back of the main support frame. The main support frame adopting the above structure has a stable structure, high bearing strength and good balance.

[0013] As a preferred solution of the present invention, the winch is a symmetrical double-output shaft winch, and the opposite sides of the winch are respectively equipped with a set of wire rope drums; the winch is installed on the load-bearing beam, and the wire rope on the winch is connected to the two ends of the concrete placing boom via a pulley assembly. The double-output shaft winch is used, and the concrete placing boom is hoisted by using the wire rope wound on the two drums on the left and right sides of the winch and guided by the pulley assembly, which can ensure that the concrete placing boom can achieve synchronous hoisting operation during the lifting process. Moreover, the winch is installed on the load-bearing beam, which is convenient for installation, and can be used as a counterweight to support the main frame, which is conducive to reducing the load-bearing requirements of the main frame.

[0014] As a preferred embodiment of the present invention, two sets of fixed pulley groups are symmetrically provided on the top of the supporting main frame, and a set of guide pulley groups is correspondingly provided between the winch and each set of the fixed pulley groups. The winch is connected to both ends of the fabricating machine through two steel ropes passing through the guide pulley groups and fixed pulley groups on the corresponding sides.

[0015] The present invention also provides a method for lifting a material placing boom, comprising the following steps: The above-mentioned concrete placing boom lifting system is used to drive the winch to lift the horizontally arranged concrete placing boom as a whole, so that the concrete placing boom slides vertically along the supporting main frame; After being lifted to a specified height, a pin is inserted to fix the material placing machine.

[0016] The above-mentioned method for lifting the concrete placing boom is simple and effective, can stably lift the pouring height of the concrete placing boom, has low operation risk and high construction efficiency.

[0017] As a preferred solution of the present invention, after the material placing machine is fixed, the winch is turned off, which is beneficial to saving energy and extending the service life.

[0018] As a preferred solution of the present invention, when there are two limit rails, in the process of lifting the fabric crane: first align the sockets on one side of the limit rail and fix them with a pin; then jog the winch in the unloading direction (corresponding to the direction of the fabric crane's fall), align the sockets on the other side of the limit rail, and fix them with a pin; the process of pulling out the pin is similar. If the mechanical pins on the left and right sides cannot be pulled out and inserted at the same time conveniently and quickly, the horizontal posture of the fabric crane can be adjusted at a single point to achieve the convenient and quick pulling out and insertion of the pins on the left and right sides at the same time.

[0019] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are: The material distribution and lifting system provided by the present invention has a simple structure and can stably and quickly continuously adjust the material distribution machine from low to high on the ground. It does not require repeated disassembly and assembly of the supporting main frame or adjustment of the height of the supporting main frame, nor does it require the use of a tower crane for high-altitude operations. It is easy to assemble and has high safety, and can meet the casting needs of different high-storage surfaces. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 is a front view of the use state of the lifting system of the material placing boom in Example 1; Figure 2 It is a side view of the concrete placing boom lifting system in use; Figure 3 It is a top view of the concrete placing boom lifting system in use; Figure 4 yes Figure 3 A magnified view of part A in FIG. Figure 5 It is a structural diagram of the left outrigger column; Figure 6 yes Figure 5 A magnified view of part B in FIG. Figure 7 It is a schematic diagram of the structure of wire rope winding.

[0021] Icons: 1-support main frame; 11-limit guide rail; 12-ladder; 13-support leg column; 14-load-bearing beam; 15-auxiliary support; 16-fixed pulley block; 17-guide pulley block; 2-winch; 3-travel mechanism; 4-pin shaft holder; 41-claw; 42-socket; 5-fabricating machine; 51-movable pulley block. DETAILED DESCRIPTION

[0022] The present invention will be described in detail below in conjunction with the accompanying drawings.

[0023] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0024] Example 1 A concrete placing boom lifting system, such as Figure 1-Figure 6 As shown, it includes a supporting main frame 1, on which a limiting guide rail 11 and a winch 2 are provided. The limiting guide rail 11 is arranged in the vertical direction, and a plurality of plug holes 42 are arranged on the limiting guide rail 11 at vertical intervals. The limiting guide rail 11 can slide vertically with the material placing machine 5 and be fixed by a pin, and the winch 2 is used to lift the material placing machine 5 horizontally.

[0025] The above-mentioned concrete placing boom lifting system realizes height lifting by hoisting the concrete placing boom 5 as a whole with the winch 2, and at the same time constrains the freedom of movement by slidingly cooperating with the concrete placing boom 5, so that the concrete placing boom 5 can only move in the vertical direction, thereby ensuring the stability of the concrete placing boom 5 during the lifting process and overcoming the defect of unstable flexible lifting; when the concrete placing boom 5 is lifted to the specified height, it is mechanically connected with the concrete placing boom 5 through the socket 42 on the limit guide rail 11, thereby reducing the load-bearing requirements of the lifting system and improving the safety and stability of the system.

[0026] Specifically, in this embodiment, the limiting guide rails 11 are respectively arranged on the opposite sides of the supporting main frame 1 and are arranged in the horizontal direction, which is used for guiding the fabric crane 5 during the up and down lifting operation. The limiting guide rail 11 is arranged with a row of sockets 42 from top to bottom, and the height difference of all the sockets 42 is 1m, and the sockets 42 are oriented in the longitudinal direction of the line. Further, the fabric crane lifting system in this embodiment also includes a pair of pin holders 4, which are respectively arranged at both ends of the fabric crane 5. The pin holders 4 are used to be detachably connected with the fabric crane 5, so as to facilitate the adjustment of the installation position according to the limiting guide rails 11. The pin holders 4 in this embodiment are welded by multiple steel plates, and the whole is in the shape of a rectangular ring, which is sleeved on the frame of the fabric crane 5; the pin holders 4 are cantilevered toward one side of the leg column 13 with a claw 41, and the claws 41 on the two pin holders 4 are arranged oppositely, and the claws 41 are used to slide with the limiting guide rail 11. The claws 41 on the two pin holders 4 are arranged outside the corresponding side leg column 13. A groove is correspondingly provided on the side of the claw 41 facing the leg column 13. The shape and size of the groove match the shape and size of the limiting guide rail 11. The size of the groove can be slightly larger than the cross-sectional size of the limiting guide rail 11. A clearance fit is adopted to facilitate sliding. The front and rear sides of the groove are provided with opposite insertion holes 42. The insertion holes 42 are provided with two groups along the height direction with a height difference of 2m for inserting the pins. The slide grooves on the pin holders 4 at both ends of the fabric conveyor 5 are arranged oppositely. During the lifting process of the fabric conveyor 5, the grooves on the claws 41 move along the limiting guide rail 11. The fabric conveyor 5 is limited to the left and right by the cooperation of the limiting guide rails 11 on the left and right sides. The limiting guide rails 11 on each side are limited to the front and rear positions to ensure that the fabric conveyor 5 is lifted smoothly without shaking, and the safety factor is high.

[0027] Furthermore, a walking mechanism 3 is provided at the bottom of the supporting main frame 1 to facilitate movement.

[0028] In this embodiment, the support main frame 1 is a portal truss structure, which is arranged in the transverse direction of the line when in use. The support main frame 1 includes two vertically arranged leg columns 13, and a crossbeam is arranged between the two leg columns 13. A load-bearing beam 14 is arranged at the bottom of each leg column 13 along the longitudinal direction of the line. The load-bearing beam 14 adopts a box beam structure formed by welding steel plates and should have a sufficiently large load strength. The walking mechanism 3 adopts a driving wheel group, and multiple sets are arranged at intervals at the bottom of each load-bearing beam 14. Each set of driving wheel groups is composed of a set of driving wheel boxes, two sets of driving wheel groups and a set of driving reduction motors, which provide driving force for the fabric machine to travel in the longitudinal direction of the line. In this embodiment, each set of driving wheel groups adopts double wheels, and the driving wheel group is installed at the front position of the bottom of the leg column 13. The rear side can be matched with a driven wheel group, which can effectively improve the stability of the whole machine during the walking operation of the fabric machine 5. An auxiliary support 15 is provided between the load-bearing beam 14 and the leg column 13. The auxiliary support 15 is arranged on the back of the supporting main frame 1 to form a stable triangular structure. The minimum clearance height of all auxiliary supports 15 from the ground is not less than 8m to ensure that on-site construction vehicles can pass conveniently and quickly. The leg column 13 in this embodiment is mainly composed of three parts, namely the bottom segment, the middle segment and the top segment. All the leg column 13 segments are transformed from the existing steel pipe truss parts on the project site. The existing steel pipe truss has a rectangular cross-section, the center distance of the main chord is 2.3m×1.2m, and the main chord steel pipe is φ219×10mm steel pipe. The cross-sectional dimensions of the steel pipe and the truss are large enough to meet the load requirements of the fabric belt conveyor hoisting. The supporting main frame 1 adopting the above structure has a stable structure, high bearing strength and good balance.

[0029] Furthermore, in this embodiment, the winch 2 is a symmetrical double-output-shaft winch 2, and a set of wire rope drums are respectively provided on opposite sides of the winch 2; the winch 2 is mounted on the load-bearing beam 14, and the wire ropes on the winch 2 are respectively connected to the two ends of the concrete placing boom 5 via the pulley assembly. The double-output-shaft winch 2 is used to hoist the concrete placing boom 5 by using the wire ropes wound on the two drums on the left and right sides of the winch 2 and guided by the pulley assembly, so that the concrete placing boom 5 can be hoisted synchronously during the lifting process. The wire rope winding diagram is shown in FIG. Figure 7As shown. Moreover, the winch 2 is installed on the load-bearing beam 14, which is convenient for installation and can be used as a counterweight for the supporting main frame 1, which is conducive to reducing the load-bearing requirements of the supporting main frame 1. Specifically, two sets of fixed pulley blocks 16 are installed on the top of the supporting main frame 1, and the two sets of fixed pulley blocks 16 are symmetrically arranged. Some guide pulley blocks 17 are appropriately installed on the inner side of the load-bearing beam 14 or on the support leg column 13. Two steel wire ropes are used to connect the movable pulley block 51, the fixed pulley block 16 and the guide pulley block 17 on the corresponding side in series, so as to realize the vertical synchronous lifting and lowering operation of the concrete placing boom 5. Furthermore, the concrete placing boom 5 in this embodiment can realize bidirectional telescopic movement, that is, it can perform cantilever casting toward both ends.

[0030] When in use, the inclined belt conveyor is tilted, the feeding end can move along the ground, the discharging end is overlapped at the feeding port on the top of the concrete placing machine 5, and the inclined belt conveyor is hingedly connected to the concrete placing machine 5. In the process of lifting the concrete placing machine 5, the discharging end of the inclined belt conveyor can be driven to rise synchronously, thereby adapting to the high-storage surface pouring operation.

[0031] The above-mentioned material distribution and lifting system has a simple structure and can stably and quickly adjust the material distribution machine 5 from low to high on the ground. There is no need to repeatedly disassemble and assemble the support main frame 1 or adjust the height of the support main frame 1, nor is there any need to use a tower crane for high-altitude operations. It is easy to assemble and has high safety, and can meet the casting needs of different high warehouse surfaces.

[0032] Example 2 Based on Example 1, this embodiment provides a method for lifting a material placing boom, comprising the following steps: The above-mentioned material placing machine lifting system is adopted to slide the material placing machine 5 to the front side of the supporting main frame 1, and the inclined belt conveyor is overlapped at the material feeding port of the material placing machine 5; The horizontally arranged material placing machine 5 is hoisted by ropes, and the hoisting machine 2 is driven to realize the overall lifting. During the lifting process, the material placing machine 5 slides vertically along the supporting main frame 1; After the lifting reaches the specified height, a pin shaft is inserted to mechanically connect the material placing machine 5 and the supporting main frame 1, thereby reducing the load-bearing requirements of the lifting system and improving the safety and stability of the whole machine.

[0033] Among them, after the material placing machine 5 is fixed, the winch 2 is turned off, which is beneficial to saving energy and extending the service life.

[0034] In the process of lifting the material distributing machine 5: first align the socket 42 on one side of the limit guide rail 11 and fix it with a pin; then jog the winch 2 in the unloading direction (corresponding to the direction of the material distributing machine 5 falling), align the socket 42 on the other side of the limit guide rail 11, and fix it with a pin; the process of pulling out the pin is similar. If the mechanical pins on the left and right sides cannot be pulled out and inserted at the same time conveniently and quickly, the horizontal posture of the material distributing machine 5 can be adjusted at a single point to achieve the convenient and quick pulling out and insertion of the pins on the left and right sides at the same time.

[0035] The above-mentioned method for lifting the concrete placing boom is simple and effective, can stably lift the pouring height of the concrete placing boom 5, has low operation risk and high construction efficiency.

[0036] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A material placing boom lifting system, comprising a supporting main frame (1), characterized in that: The supporting main frame (1) is provided with a limit guide rail (11) and a winch (2); the limit guide rail (11) is arranged in the vertical direction; a plurality of insertion holes (42) are arranged on the limit guide rail (11) at intervals along the vertical direction; the limit guide rail (11) can be slidably matched with the material placing machine (5) along the vertical direction and can be fixed at the insertion holes (42) by means of a latch; the winch (2) is used to lift the material placing machine (5) horizontally.

2. The material placing boom lifting system according to claim 1, characterized in that: The limiting guide rails (11) are respectively arranged on two opposite sides of the supporting main frame (1) and are arranged in a transverse direction, and the insertion holes (42) are arranged in a longitudinal direction of the line.

3. The material placing boom lifting system according to claim 2, characterized in that: It also comprises a pair of pin shaft clamping seats (4), the pin shaft clamping seats (4) being used for being detachably connected to the material placing machine (5), the pin shaft clamping seats (4) being provided with claws (41), the claws (41) on the two pin shaft clamping seats (4) being arranged opposite to each other, the claws (41) being used for slidingly cooperating with the limiting guide rails (11) on the corresponding sides.

4. The material placing boom lifting system according to claim 1, characterized in that: A walking mechanism (3) is provided at the bottom of the supporting main frame (1).

5. The material placing boom lifting system according to claim 4, characterized in that: The supporting main frame (1) is a portal truss structure, comprising two vertically arranged supporting leg columns (13), a crossbeam connecting the two supporting leg columns (13), a load-bearing beam (14) being provided at the bottom of each supporting leg column (13) along the longitudinal direction of the line, the walking mechanism (3) being located at the bottom of the load-bearing beam (14), an auxiliary support (15) being provided between the load-bearing beam (14) and the supporting leg columns (13), and the auxiliary support (15) being provided on the back side of the supporting main frame (1).

6. The material placing boom lifting system according to claim 5, characterized in that: The hoist (2) is a symmetrical double-output shaft hoist (2), and opposite sides of the hoist (2) are respectively provided with a set of wire rope drums; the hoist (2) is mounted on the load-bearing beam (14), and the wire rope on the hoist (2) is respectively connected to two ends of the material placing machine (5) via a pulley assembly.

7. The material placing boom lifting system according to claim 6, characterized in that: Two sets of fixed pulley blocks (16) are symmetrically arranged on the top of the supporting main frame (1), and a set of guide pulley blocks (17) is correspondingly arranged between the hoist (2) and each set of the fixed pulley blocks (16). The hoist (2) is connected to both ends of the material placing machine (5) through two steel wire ropes passing through the guide pulley blocks (17) and the fixed pulley blocks (16) on the corresponding sides.

8. A method for lifting a material placing boom, characterized in that: The following steps are involved: The concrete placing boom lifting system according to any one of claims 1 to 7 is used to drive the winch (2) to lift the horizontally arranged concrete placing boom (5) as a whole, so that the concrete placing boom (5) slides vertically along the supporting main frame (1); After being lifted to a specified height, a pin is inserted to fix the material placing machine (5).

9. The method for lifting a material placing boom according to claim 8, characterized in that: After the material placing machine (5) is fixed, the winch (2) is turned off.

10. The method for lifting a material placing boom according to claim 8 or 9, characterized in that: When there are two limit guide rails (11), during the process of lifting the material placing machine (5), first align the insertion holes (42) on one side of the limit guide rail (11) and fix them with a latch; then, move the winch (2) in the unloading direction, align the insertion holes (42) on the other side of the limit guide rail (11), and fix them with a latch.