Filling loading process observation data fused settlement prediction confidence analysis method

Through the Weibull model correction settlement difference method and the merged subgrade settlement prediction confidence analysis method, a roadbed settlement prediction confidence analysis model was constructed with the observation data of the filling loading process, which solved the calculation deviation and the utilization of observation data in railway subgrade settlement prediction. The full problem has improved the prediction accuracy and confidence and met the settlement control requirements of high-speed railways.

CN119025818AActive Publication Date: 2024-11-26RAILWAY CONSTR RES INST OF CHINA ACAD OF RAILWAY SCI CO LTD +2

Patent Information

Application Number
CN202411216942.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-26
Estimated Expiration
2044-09-02

AI Technical Summary

Technical Problem

The existing technology has problems of calculation deviation and insufficient utilization of observation data in railway subgrade settlement prediction, especially in the construction of high-speed railways, and it is difficult to meet the strict settlement control requirements, and there is a lack of confidence in the settlement prediction of observation data in the fusion filling loading process. degree analysis technology.

Method used

The Weibull model is used to correct the traditional settlement difference method, and the roadbed settlement prediction confidence analysis model is constructed that integrates the observation data of the filling loading process. Through the merger and correction settlement difference method and the roadbed settlement prediction confidence analysis method, the statistical average of settlement is analyzed for the filling loading method. and the influence law of standard deviation.

Benefits of technology

It improves the accuracy and confidence of settlement prediction, reduces the error of prediction mean and standard deviation, meets the strict requirements of high-speed railways for roadbed settlement control, and is better than traditional and improved hyperbolic method.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119025818A_ABST
    Figure CN119025818A_ABST
Patent Text Reader

Abstract

The invention discloses a filling and loading process observation data fused settlement prediction confidence analysis method, which comprises the following steps of: S1, correcting and deducing a traditional settlement difference method by adopting a Weibull model so as to obtain a settlement prediction model of the corrected settlement difference method; s2, merging the corrected settlement difference method settlement prediction model and a roadbed settlement prediction confidence analysis method to construct a roadbed settlement prediction confidence analysis model capable of fusing the observation data of the filling and loading process; and S3, based on the roadbed settlement prediction confidence coefficient analysis model capable of fusing the observation data of the filling and loading process, comparing confidence coefficients of the various settlement prediction models capable of fusing the observation data of the filling and loading process, analyzing an influence rule of a filling and loading mode on a predicted settlement statistical mean value and a standard deviation, and obtaining a correlation corresponding to the influence rule. The invention further discloses a corresponding analysis system, electronic equipment and a computer readable storage medium.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of railway and roadbed settlement prediction and analysis, and in particular to a settlement prediction confidence analysis method and system integrating observation data of filling and loading process. Background Art

[0002] Railway transportation occupies a backbone position in my country's overall transportation network. In recent years, based on the rapid development of my country's high-speed railways, railway construction and operation and maintenance have become an important driving force for my country's domestic economic growth and a beautiful business card for displaying its international image. my country has made plans for the medium- and long-term development of railways. However, since my country is a country with widespread soft soil, railway lines are bound to pass through a large number of soft soil areas. An important problem faced by the construction of high-speed railways in soft soil areas is the control of foundation settlement and post-construction settlement. Different settlement control standards are proposed for railways of different grades. The high smoothness requirements of high-speed railway ballastless tracks put forward more stringent requirements for post-construction settlement of the roadbed. Generally, the post-construction settlement is required to be no more than 15mm, which requires the final settlement of the roadbed to be accurately controlled during the construction process.

[0003] However, the prior art still has the following technical defects:

[0004] First, in current engineering design and construction, settlement calculation is mainly performed in the design stage and roadbed settlement observation, prediction and evaluation are performed in the construction stage to control post-construction settlement. However, due to the nonlinearity of soil stress-strain relationship, variability and anisotropy of geotechnical parameters, etc., the theoretical calculation method, especially the theoretical calculation method based on the layered summation method in the design stage, has large calculation deviations for the settlement development process and final settlement of the foundation. The roadbed settlement observation, prediction and evaluation in the construction stage is to extrapolate the settlement development process and final settlement based on the observation data. Since the settlement observation process is affected by many factors such as foundation treatment form, geological conditions, observation conditions, etc., and the influence of the above factors on the settlement prediction results is unclear, it is not easy to control the settlement of high-speed railway roadbed using settlement observation prediction.

[0005] Second, there is no mature technical solution in the prior art for integrating the confidence of settlement prediction with observation data of the filling and loading process, especially by establishing a settlement prediction model that integrates observation data of the filling and loading process, comprehensively utilizing filling period data and constant load period data to predict settlement of natural foundations and sand well foundations, and studying the influence of roadbed filling time, roadbed filling level and observation conditions on the mean and standard deviation of settlement prediction.

[0006] Third, the method commonly used in engineering projects to predict post-construction settlement using the data from the constant load period after the completion of roadbed filling is difficult to meet the actual needs of increasingly shortened construction periods. Summary of the invention

[0007] The purpose of the present invention is to provide a settlement prediction confidence analysis method and system that integrates observation data of the filling and loading process. By improving the traditional settlement difference method, a modified settlement difference method is derived, and the model is merged with the roadbed settlement prediction confidence analysis method used in the previous article to construct (unified: a roadbed settlement prediction confidence analysis model that can integrate observation data of the filling and loading process). Compare the confidences of various settlement prediction models that integrate observation data of the filling and loading process, analyze the influence of the filling and loading method on the statistical mean and standard deviation of the predicted settlement, and obtain their correlation.

[0008] The first aspect of the present invention is to provide a settlement prediction confidence analysis method integrating observation data of filling and loading process, comprising:

[0009] S1, the traditional settlement difference method is modified and derived using the Weibull model, thereby obtaining the settlement prediction model of the modified settlement difference method;

[0010] S2, combining the modified settlement difference method settlement prediction model with the roadbed settlement prediction confidence analysis method to construct a roadbed settlement prediction confidence analysis model that can integrate observation data of the filling and loading process;

[0011] S3, based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, compare the confidence of multiple settlement prediction models that integrate the observation data of the filling and loading process, analyze the influence of the filling and loading method on the predicted settlement statistical mean and standard deviation, and obtain the correlation corresponding to the influence law.

[0012] Preferably, the S1 comprises:

[0013] S11, determine the average consolidation degree of the foundation under multi-level loading conditions of soft soil roadbed settlement, modify it according to the Weibull model, and determine the basic assumptions of the settlement prediction model of the modified settlement difference method;

[0014] S12, based on the basic assumptions of the settlement prediction model of the Weibull model, the traditional settlement difference method is corrected and derived using the Weibull model, thereby obtaining a settlement prediction model of the corrected settlement difference method.

[0015] Preferably, the basic assumptions include:

[0016] (1) The consolidation process caused by each load increment occurs independently and has nothing to do with the consolidation degree caused by the previous load increment;

[0017] (2) The total degree of consolidation is equal to the sum of the degrees of consolidation under each level of load increment;

[0018] (3) Loading period is 0~ti The load increment of the uniform loading is related to the load increment at t i / 2 The degree of consolidation caused by applying the load increment instantaneously once is equivalent;

[0019] (4) Average degree of consolidation U t It is defined according to the settlement deformation, that is, Among them, s t Indicates the current settlement deformation, s ∞ Indicates the maximum settlement deformation;

[0020] (5) The degree of consolidation under each level of load is corrected according to the load ratio and superimposed to obtain the average degree of consolidation under the total load, as shown in formula (1):

[0021]

[0022] Where: U ti is the degree of consolidation under the i-th level load;

[0023] p i is the i-th load increment;

[0024] p is the total load;

[0025] n is the total number of stages of graded loading;

[0026] Based on the basic assumptions (4) and (5), it can be deduced that the consolidation settlement s caused by a certain level of load is cpi Total consolidation settlement s caused by total load cp The ratio is equal to the load increment p of this level. i The ratio of the load to the total load p is shown in formula (2):

[0027]

[0028] Preferably, the S12 includes:

[0029] According to the Weibull model, at t 0pi Under the action of the i-th level load increment applied instantaneously at time t, the foundation consolidation degree equivalent to the i-th level load increment is between t1 and t2 (t2>t1>t opi ) are:

[0030]

[0031] Then the roadbed settlement caused by the i-th level load increment at time t1 and t2 are:

[0032]

[0033] Substituting formula (2) into formula (5) and formula (6) yields:

[0034]

[0035] If the load is constant during the period from t1 to t2, the settlement difference during the period from t1 to t2 caused by the incremental loads applied during the loading period is:

[0036]

[0037] Where: t op1 - the moment of application of the first load increment, corrected according to basic assumption (3);

[0038] t1, t2——any time in the constant load period after the load filling is completed, and t2>t1;

[0039] ——are the accumulated settlement at time t1 and time t2 respectively;

[0040] m——the number of graded loads applied during the loading period;

[0041] p i —— load of level i;

[0042] p——total load of roadbed filling;

[0043] S cp , α, b, r——model fitting parameters, optimized and solved using the least squares method.

[0044] Preferably, the S2 of merging the settlement prediction model of the modified settlement difference method with the roadbed settlement prediction confidence analysis method includes merging the settlement prediction model that can integrate the observation data of the filling and loading process with the roadbed settlement prediction confidence analysis method, and obtaining the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process after selecting the optimal model based on the confidence; wherein the settlement prediction model that can integrate the observation data of the filling and loading process includes the improved hyperbolic method, the traditional settlement difference method and the modified settlement difference method.

[0045] Preferably, the roadbed settlement prediction confidence analysis method of S2 includes:

[0046] generating simulated settlement observation data, wherein the simulated settlement observation data is generated based on discrete observation data with observation errors;

[0047] Performing a confidence analysis on roadbed settlement prediction based on the simulated settlement observation data;

[0048] Wherein, generating simulated settlement observation data comprises:

[0049] Aiming at the settlement problem of soft soil roadbed under different foundation treatment forms and different soil conditions, the corresponding theoretical continuous data under different conditions are calculated based on the homogeneous natural foundation calculation model and the sand well foundation calculation model;

[0050] The theoretical continuous data is divided into observation period data and late settlement data according to different first settlement observation conditions, and the observation period data is discretized according to the second settlement observation condition to obtain discrete data;

[0051] superimposing observation errors on discrete observation period data according to different third settlement observation conditions to generate discrete observation data with the observation errors, and generating the simulated settlement observation data based on the discrete observation data with the observation errors;

[0052] Among them, the first settlement observation condition is the observation duration; the second settlement observation condition is the observation frequency; the third settlement observation condition is the observation accuracy;

[0053] The confidence analysis of roadbed settlement prediction based on the simulated settlement observation data includes:

[0054] Based on the discrete observation data with the observation error, a curve fitting method is used to predict and obtain the prediction value corresponding to each group of observation data; the above process is repeated to obtain multiple prediction values ​​to form a prediction result;

[0055] Performing statistical analysis on the prediction results to obtain a statistical mean value and a standard deviation of the predicted settlement;

[0056] Preferably, the S3, based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, compares the confidence of multiple settlement prediction models that integrate the observation data of the filling and loading process, analyzes the influence of the filling and loading method on the statistical mean and standard deviation of the predicted settlement, and obtains the correlation corresponding to the influence law, including:

[0057] The statistical mean calculation formulas for predicted settlement of homogeneous natural foundation and homogeneous sand well foundation obtained by integrating the observation data of filling and loading process by the modified settlement difference method are shown in equations (16) and (17):

[0058] Natural foundation:

[0059]

[0060] Sand well foundation:

[0061]

[0062] The curve of the change of the predicted settlement standard deviation with the observation time is described by formula (18):

[0063] σ=A1exp(-x1 / t1)+A2exp(-x1 / t2) (18);

[0064] Where: σ——predicted settlement standard deviation (mm);

[0065] x1——observation duration (days);

[0066] A1, t1, A2, t2——model fitting parameters;

[0067] The relationship between the model fitting parameters A1, t1, A2, and t2 of the fitting curve obtained by formula (18) for natural foundation and sand well foundation and the length of roadbed filling. The fitting curve can be determined by formula (19) and formula (20):

[0068] A1=a1·x4+b1 (19);

[0069] A2=a2·x4+b2 (20);

[0070] Where: x4——roadbed filling time (days);

[0071] The calculation formulas for the predicted settlement standard deviation of homogeneous natural foundation and homogeneous sand well foundation obtained by integrating the observation data of the filling and loading process with the modified settlement difference method are shown in equations (21) and (22):

[0072] Natural foundation:

[0073]

[0074] Sand well foundation:

[0075]

[0076] And, determine the influence of roadbed filling levels on the statistical mean and standard deviation of predicted settlement.

[0077] The second aspect of the present invention further provides a settlement prediction confidence analysis system integrating observation data of filling and loading process, which is used to implement the method of the first aspect, comprising:

[0078] The first model building module (101) is used to modify and derive the traditional differential settlement method using the Weibull model, thereby obtaining a modified differential settlement method settlement prediction model;

[0079] The second model building module (102) is used to combine the modified settlement difference method settlement prediction model with the roadbed settlement prediction confidence analysis method to construct a roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process;

[0080] The confidence analysis module (103) is used to compare the confidences of multiple settlement prediction models integrating the observation data of the filling and loading process based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, analyze the influence of the filling and loading method on the statistical mean and standard deviation of the predicted settlement, and obtain the correlation corresponding to the influence law.

[0081] A third aspect of the present invention provides an electronic device, comprising a processor and a memory, wherein the memory stores a plurality of instructions, and the processor is configured to read the instructions and execute the method described in the first aspect.

[0082] A fourth aspect of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium stores a plurality of instructions, and the plurality of instructions can be read by a processor and execute the method described in the first aspect.

[0083] Beneficial effects of the method and system of the present invention:

[0084] (1) Based on the Weibull model and the traditional settlement difference method, a settlement difference prediction model based on the Weibull model is derived. The roadbed settlement prediction confidence analysis method is merged with the settlement prediction model to obtain a roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process.

[0085] (2) The settlement difference method based on the Weibull model derived in this paper is compared with the original improved hyperbola method and the traditional settlement difference method: for the same observation time, the relationship between the statistical mean and standard deviation of the predicted settlement of the three prediction models is: modified settlement difference method < traditional settlement difference method < improved hyperbola method, which shows the superiority of the settlement difference method based on the Weibull model.

[0086] (3) The change rules of the predicted settlement statistical mean with the roadbed filling time and observation time were analyzed, and the empirical formula for the predicted statistical mean affected by the observation time and roadbed filling time was obtained. The settlement difference based on the Weibull model and the predicted settlement statistical mean using the conventional curve fitting method were compared when the roadbed filling time was 30 days, 40 days, 50 days, and 60 days. Compared with the use of only the constant load data, the relative error of the predicted statistical mean using the filling period data was reduced by 9.83%, 9.87%, 10.06%, and 10.3%, respectively.

[0087] (4) The predicted settlement standard deviation was analyzed to determine the variation of the roadbed filling time and observation time, and the empirical formula for the influence of observation time and roadbed filling time on the predicted settlement standard deviation was obtained. The settlement difference based on the Weibull model and the predicted settlement standard deviation using the conventional curve fitting method were compared with the predicted settlement standard deviation using the conventional curve fitting method when the roadbed filling time was 30 days, 40 days, 50 days, and 60 days. Compared with the use of only the constant load data, the predicted standard deviation using the integrated filling period data was reduced by 9.96 mm, 9.94 mm, 9.90 mm, and 9.87 mm, respectively.

[0088] (5) The distribution of roadbed filling levels should be mainly controlled by the stability of the foundation during the soft soil roadbed filling process. The distribution of roadbed filling levels has little effect on the statistical mean and standard deviation of the predicted settlement. BRIEF DESCRIPTION OF THE DRAWINGS

[0089] In order to more clearly illustrate the specific embodiments of the present invention or the technical solutions in the related technologies, the drawings required for use in the specific embodiments or the related technical descriptions will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0090] Figure 1 (a) is a flow chart of a settlement prediction confidence analysis method for integrating observation data of a filling and loading process provided in accordance with an embodiment of the present invention;

[0091] Figure 1 (b) is a schematic diagram of a settlement prediction confidence analysis method for integrating observation data of a filling and loading process according to an embodiment of the present invention;

[0092] Figure 2 A histogram of the statistical mean values ​​of settlement predicted by different settlement prediction models provided according to an embodiment of the present invention;

[0093] Figure 3 A histogram of standard deviations of settlement predicted by different settlement prediction models provided according to an embodiment of the present invention;

[0094] Figure 4 It is a prediction distribution diagram of different settlement prediction models with an observation time of 50 days provided according to an embodiment of the present invention;

[0095] Figure 5 A prediction distribution diagram of different settlement prediction models with an observation time of 60 days provided according to an embodiment of the present invention;

[0096] Figure 6 It is a prediction distribution diagram of different settlement prediction models with an observation time of 70 days provided according to an embodiment of the present invention;

[0097] Figure 7A prediction distribution diagram of different settlement prediction models with an observation time of 90 days provided according to an embodiment of the present invention;

[0098] Figure 8 A histogram of the statistical mean of predicted settlement under different roadbed filling time conditions for natural foundations provided by an embodiment of the present invention;

[0099] Fig. 9 A histogram of the statistical mean of predicted settlement under different roadbed filling time conditions of a sand well foundation provided according to an embodiment of the present invention;

[0100] Fig.10 A time history diagram of the statistical mean of predicted settlement of a natural foundation with different observation durations provided according to an embodiment of the present invention;

[0101] Fig.11 A time history diagram of the statistical mean of predicted settlement of a sand well foundation at different observation times provided according to an embodiment of the present invention;

[0102] Fig.12 A time history diagram of predicted settlement standard deviation under different roadbed filling time conditions for natural foundations provided by an embodiment of the present invention;

[0103] Fig.13 A time history diagram of predicted settlement standard deviation under different roadbed filling time conditions of a sand well foundation provided by an embodiment of the present invention;

[0104] Fig.14 A distribution diagram of prediction results under different roadbed filling durations of natural foundations when the observation duration is 30 days according to an embodiment of the present invention;

[0105] Fig.15 A distribution diagram of prediction results under different roadbed filling duration conditions of sand well foundation when the observation duration is 30 days according to an embodiment of the present invention;

[0106] Fig.16 A distribution diagram of prediction results under different roadbed filling duration conditions of natural foundation when the observation duration is 60 days according to an embodiment of the present invention;

[0107] Fig.17 A distribution diagram of prediction results under different roadbed filling duration conditions of sand well foundation when the observation duration is 60 days according to an embodiment of the present invention;

[0108] Fig.18 A time history diagram of standard deviation of predicted settlement of a natural foundation with different observation durations provided according to an embodiment of the present invention;

[0109] Fig.19 This is a time history diagram of the standard deviation of predicted settlement of a sand well foundation with different observation durations provided according to an embodiment of the present invention

[0110] Fig. 20A histogram of the statistical mean of predicted settlement under different roadbed filling levels of natural foundation provided by an embodiment of the present invention;

[0111] Fig.21 A histogram of the statistical mean of predicted settlement under different roadbed filling levels of a sand well foundation provided according to an embodiment of the present invention;

[0112] Fig. 22 A time history diagram of predicted settlement standard deviation under different roadbed filling levels of natural foundation provided by an embodiment of the present invention;

[0113] Fig.23 A time history diagram of predicted settlement standard deviation under different roadbed filling levels of a sand well foundation provided according to an embodiment of the present invention;

[0114] Fig.24 A distribution diagram of prediction results under different roadbed filling levels of natural foundation when the observation time is 30 days according to an embodiment of the present invention;

[0115] Fig.25 A distribution diagram of prediction results under different roadbed filling levels of sand well foundation when the observation time is 30 days according to an embodiment of the present invention;

[0116] Fig.26 A distribution diagram of prediction results under different roadbed filling levels of natural foundation when the observation time is 60 days according to an embodiment of the present invention;

[0117] Fig. 27 A distribution diagram of prediction results under different roadbed filling levels of sand well foundation when the observation time is 60 days according to an embodiment of the present invention;

[0118] Fig.28 A structural diagram of an electronic device provided according to an embodiment of the present invention. DETAILED DESCRIPTION

[0119] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0120] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0121] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0122] Embodiment 1

[0123] like Figure 1 (a) and Figure 1 As shown in (b), this embodiment provides a settlement prediction confidence analysis method integrating observation data of filling and loading process, comprising:

[0124] S1, the traditional settlement difference method is modified and derived using the Weibull model, thereby obtaining the settlement prediction model of the modified settlement difference method;

[0125] S2, combining the modified settlement difference method settlement prediction model with the roadbed settlement prediction confidence analysis method to construct a roadbed settlement prediction confidence analysis model that can integrate observation data of the filling and loading process;

[0126] S3, based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, compare the confidence of multiple settlement prediction models that integrate the observation data of the filling and loading process, analyze the influence of the filling and loading method on the predicted settlement statistical mean and standard deviation, and obtain the correlation corresponding to the influence law.

[0127] As a preferred embodiment, the S1 includes:

[0128] S11, determine the average consolidation degree of the foundation under multi-level loading conditions of soft soil roadbed settlement, modify it according to the Weibull model, and determine the basic assumptions of the settlement prediction model of the modified settlement difference method;

[0129] In this embodiment, under the multi-stage loading condition of soft soil roadbed settlement, the average consolidation degree of the foundation is corrected according to the Weibull model, and the following basic assumptions are determined:

[0130] (1) The consolidation process caused by each load increment occurs independently and has nothing to do with the consolidation degree caused by the previous load increment;

[0131] (2) The total degree of consolidation is equal to the sum of the degrees of consolidation under each level of load increment;

[0132] (3) Loading period is 0~t i The load increment of the uniform loading is related to the load increment at t i / 2 The degree of consolidation caused by applying the load increment instantaneously once is equivalent;

[0133] (4) Average degree of consolidation U t It is defined according to the settlement deformation, that is,

[0134] (5) The degree of consolidation under each level of load is corrected according to the load ratio and superimposed to obtain the average degree of consolidation under the total load, as shown in formula (1):

[0135]

[0136] Where: U ti is the degree of consolidation under the i-th level load;

[0137] p i is the i-th load increment;

[0138] p is the total load;

[0139] n is the total number of stages of graded loading;

[0140] Based on the basic assumptions (4) and (5), it can be deduced that the consolidation settlement s caused by a certain level of load is cpi Total consolidation settlement s caused by total load cp The ratio is equal to the load increment p of this level. i The ratio of the load to the total load p is shown in formula (2):

[0141]

[0142] S12, using the Weibull model to correct and derive the traditional differential settlement method, thereby obtaining a modified differential settlement method settlement prediction model, wherein the modified differential settlement method settlement prediction model corresponds to the differential settlement method based on the Weibull model;

[0143] In this embodiment, the S12 includes:

[0144] According to the Weibull model, at t 0pi Under the action of the i-th level load increment applied instantaneously at time t, the foundation consolidation degree equivalent to the i-th level load increment is between t1 and t2 (t2>t1>t opi ) are:

[0145]

[0146] Then the roadbed settlement caused by the i-th level load increment at time t1 and t2 are:

[0147]

[0148] Substituting formula (2) into formula (5) and formula (6) yields:

[0149]

[0150] If the load is constant during the period from t1 to t2, the settlement difference during the period from t1 to t2 caused by the incremental loads applied during the loading period is:

[0151]

[0152] Where: t op1 - the moment of application of the first load increment, corrected according to basic assumption (3);

[0153] t1, t2——any time in the constant load period after the load filling is completed, and t2>t1;

[0154] ——are the accumulated settlement at time t1 and time t2 respectively;

[0155] m——the number of graded loads applied during the loading period;

[0156] p i —— load of level i;

[0157] p——total load of roadbed filling;

[0158] S cp , α, b, r——model fitting parameters, optimized and solved using artificial intelligence algorithm.

[0159] In this embodiment, in order to further verify the effectiveness of the settlement prediction model based on the Weibull model, the influence of different prediction models on the prediction confidence is calculated and determined.

[0160] Figure 2The following is a bar chart of the statistical mean values ​​of predicted settlement obtained by using the improved hyperbola method, the traditional settlement difference method, and the settlement difference method based on the Weibull model after observation and prediction at different observation times. As can be seen from the figure, at the same observation time, the statistical mean values ​​of predicted settlement obtained by the three prediction models, that is, the systematic errors, are significantly different. The statistical mean value of predicted settlement by the improved hyperbola method is larger than that by the traditional settlement difference method and the settlement difference method based on the Weibull model, indicating that the improved hyperbola method is not suitable for settlement prediction of the fusion filling and loading process observation data, and the traditional settlement difference method is slightly inferior to the settlement difference method based on the Weibull model, indicating that the settlement difference method based on the Weibull model is most suitable for settlement prediction of the fusion filling and loading process observation data. Figure 3 The bar graph shows the standard deviation of predicted settlement obtained by using the improved hyperbolic method, the traditional settlement difference method, and the settlement difference method based on the Weibull model at different observation times. Figure 3 It can be seen that when the observation time is the same, the predicted settlement standard deviations, that is, the accidental errors, obtained by the three prediction models have obvious differences. The predicted settlement standard deviation of the improved hyperbola method is larger than that of the traditional settlement difference method and the settlement difference method based on the Weibull model, indicating that the improved hyperbola method is not suitable for settlement prediction based on the observation data of the filling and loading process. The traditional settlement difference method is slightly inferior to the settlement difference method based on the Weibull model, indicating that the settlement difference method based on the Weibull model is most suitable for settlement prediction based on the observation data of the filling and loading process.

[0161] Figure 4-Figure 7 The probability distribution of the prediction results of the three prediction models integrating the observation data of the filling and loading process with the same number of observations were plotted respectively. Comparing the above four probability distribution diagrams, whether it is the improved hyperbola method, the traditional settlement difference method or the settlement difference method based on the Weibull model, as the observation time increases, the settlement prediction probability density at the predicted mean value increases, indicating that as the observation time increases, the prediction results converge in the observation prediction process. The prediction results of the three prediction models integrating the filling and loading process gradually approach zero, and the prediction results are more stable. Under different observation time conditions, the probability distribution of the settlement difference method based on the Weibull prediction model is more concentrated, and the traditional settlement difference method is similar to it, but the results are more discrete. The prediction results of the improved hyperbola are the worst, and its results are also more discrete. This shows that by comparing the three prediction models that integrate the observation data of the filling and loading process, it can be seen that the prediction results of the settlement difference method based on the Weibull prediction model are more stable, and the prediction results are more concentrated during the prediction process. The prediction results of the improved hyperbola method for railways with different post-construction settlement requirements are relatively unstable, and the prediction results are more discrete during the prediction process. The prediction stability of the traditional settlement difference method is slightly worse than that of the settlement difference method based on the Weibull prediction model, but better than the improved hyperbola method.

[0162] As a preferred implementation, the roadbed settlement prediction confidence analysis method of S2 includes:

[0163] Generate simulated settlement observation data, wherein the simulated settlement observation data is generated based on discrete observation data with observation errors. The method of this embodiment is particularly suitable for using data from a roadbed heap loading period and a dead load period of 3 months for prediction, thereby achieving the purpose of early prediction;

[0164] A confidence analysis of roadbed settlement prediction is performed based on the simulated settlement observation data.

[0165] As a preferred implementation, the generating of simulated settlement observation data comprises:

[0166] Aiming at the settlement problem of soft soil roadbed under different foundation treatment forms and different soil conditions, the corresponding theoretical continuous data under different conditions are calculated based on the homogeneous natural foundation calculation model and the sand well foundation calculation model;

[0167] The theoretical continuous data is divided into observation period data and late settlement data according to different first settlement observation conditions, and the observation period data is discretized according to the second settlement observation condition to obtain discrete data;

[0168] superimposing observation errors on discrete observation period data according to different third settlement observation conditions to generate discrete observation data with the observation errors, and generating the simulated settlement observation data based on the discrete observation data with the observation errors;

[0169] Among them, the first settlement observation condition is the observation duration; the second settlement observation condition is the observation frequency; and the third settlement observation condition is the observation accuracy.

[0170] In this embodiment, the observation accuracy refers to the influence of the observation accuracy conditions of Class I level, Class II level, Class III level, Class IV level and those with greater observation errors than Class IV level in engineering level measurement on the confidence of settlement prediction, and the error in the elevation of the deformation point is used as the control indicator to distinguish the accuracy of each level of level measurement.

[0171] The observation frequency refers to the number or frequency of observations made using the leveling observation method within the observation period. When analyzing the impact of observation frequency on settlement prediction confidence, the different constant load periods after the completion of roadbed filling are divided into three observation periods: 0 to 3 months after completion of filling, 4 to 6 months after completion of filling, and 6 months after completion of filling. The impact of increasing or decreasing the observation frequency in the corresponding observation period compared with the current relevant regulations on the prediction confidence is determined.

[0172] As a preferred implementation, the roadbed settlement prediction confidence analysis based on the simulated settlement observation data includes:

[0173] Based on the discrete observation data with the observation error, a curve fitting method is used to predict and obtain the prediction value corresponding to each group of observation data; the above process is repeated to obtain multiple prediction values ​​to form a prediction result;

[0174] Performing statistical analysis on the prediction results to obtain a statistical mean value and a standard deviation of the predicted settlement;

[0175] The corresponding influence rules are derived based on the predicted settlement statistical mean and the predicted settlement standard deviation respectively; the influence rules include the influence rule of observation time on the predicted settlement statistical mean, the influence rule of observation accuracy on the predicted settlement statistical mean, the influence rule of observation frequency on the predicted settlement statistical mean, the influence rule of soil conditions on the predicted settlement statistical mean, the influence rule of observation time on the predicted settlement standard deviation, the influence rule of observation accuracy on the predicted settlement standard deviation, the influence rule of observation frequency on the predicted settlement standard deviation and the influence rule of soil conditions on the predicted settlement standard deviation.

[0176] As a preferred embodiment, the calculation formulas for the predicted settlement statistical mean and standard deviation are shown in the following formulas (11) and (12):

[0177]

[0178] Where, μ is the settlement prediction mean; σ is the settlement prediction standard deviation; N s S is the number of samples to be calculated; k The kth predicted value of settlement.

[0179] The S2 of merging the settlement prediction model of the modified settlement difference method with the roadbed settlement prediction confidence analysis method includes merging the settlement prediction model that can integrate the observation data of the filling and loading process with the roadbed settlement prediction confidence analysis method, and obtaining the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process after selecting the optimal model based on the confidence; wherein the settlement prediction model that can integrate the observation data of the filling and loading process includes the improved hyperbolic method, the traditional settlement difference method and the modified settlement difference method.

[0180] As a preferred implementation, S3, based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, compares the confidence of multiple settlement prediction models that integrate the observation data of the filling and loading process, analyzes the influence of the filling and loading method on the statistical mean and standard deviation of the predicted settlement, and obtains the correlation corresponding to the influence law, including:

[0181] 1. The influence of roadbed filling time on the statistical mean and standard deviation of predicted settlement

[0182] Figure 8The figure is a bar chart of the statistical mean of predicted settlement under different roadbed filling time of natural foundation. The change of the statistical mean of predicted settlement with observation time under different roadbed filling time conditions is consistent with the above description. As the observation time gradually increases, the statistical mean of predicted settlement gradually decreases. The shortening of roadbed filling time plays an important role in effectively controlling the statistical mean of predicted settlement. Fig. 9 The figure is a bar chart of the predicted settlement statistical mean under different roadbed filling time of the sand well foundation. The change of the predicted settlement statistical mean with the observation time under different roadbed filling time conditions is consistent with the above description. As the observation time gradually increases, the predicted settlement statistical mean gradually decreases. The shortening of roadbed filling time plays an important role in effectively controlling the predicted settlement statistical mean.

[0183] Fig.10 The time course curve of the statistical mean of predicted settlement of natural foundation at different observation times. Fig.11 The time course curve of the statistical mean of predicted settlement at different observation times of the sand well foundation. The statistical mean of predicted settlement gradually approaches zero as the observation time gradually increases, indicating that as the observation time increases, the difference between the mean of the predicted value obtained by the curve fitting method through observation prediction and the theoretical value obtained by the roadbed settlement calculation method gradually decreases, and the settlement prediction result gradually approaches the true value. At the same time, as the observation time increases, the rate of change of the statistical mean of predicted settlement gradually decreases. When the observation time is short, the difference between the statistical mean of predicted settlement between two adjacent days is large. As the observation time increases, the difference between the statistical mean of predicted settlement between two adjacent days decreases significantly, indicating that as the observation time increases, the statistical mean of predicted settlement also gradually stabilizes.

[0184] Fig.10 and Fig.11 The curve of the change of the statistical mean of the predicted settlement with the observation time can be described by formula (13):

[0185] δ=A1exp(-x1 / t1)+A2exp(-x1 / t2) (13)

[0186] Where: δ——predicted settlement statistical mean;

[0187] x1——Observation duration (days).

[0188] A1, t1, A2, t2——model fitting parameters.

[0189] The relationship between the model fitting parameters A1, t1, A2, and t2 of the fitting curve obtained by formula (13) for natural foundation and sand well foundation and the length of roadbed filling. The fitting curve can be determined by formula (14) and formula (15).

[0190] A1=a1·x4+b1 (14)

[0191] A2=a2·x4+b2 (15)

[0192] In the formula: x4——roadbed filling time (days).

[0193] From the above analysis, it can be obtained that the statistical mean calculation formula for the predicted settlement of natural foundation sand well foundation obtained by integrating the observation data of the filling and loading process with the settlement difference method based on the Weibull model is shown in Equation (16) and Equation (17).

[0194] Natural foundation:

[0195]

[0196] Sand well foundation:

[0197]

[0198] Fig.12 and Fig.13The following are the time course diagrams of the predicted settlement standard deviation under different roadbed filling times for natural foundation and sand well foundation, respectively. It can be seen from the two figures that under different roadbed filling times, the predicted settlement standard deviation gradually decreases with the increase of the number of observations, indicating that with the increase of the number of observations, the discreteness of the settlement prediction results gradually decreases, and the prediction results gradually concentrate near the statistical mean of the predicted settlement. In logarithmic coordinates, the curves of the predicted settlement standard deviation under different roadbed filling times and the number of observations are approximately parallel, that is, the ratio of the predicted settlement standard deviation under different roadbed filling times does not increase with the extension of the observation time. When the observation time is 30 days, the predicted settlement standard deviation of the roadbed filling time of 50 days is 0.845 of that of the roadbed filling time of 66 days, the predicted settlement standard deviation of the roadbed filling time of 40 days is 0.498 of that of the roadbed filling time of 66 days, and the predicted settlement standard deviation of the roadbed filling time of 33 days is 0.66. The standard deviation is 0.318 for 66 days of embankment filling. When the observation time is 60 days, the standard deviation of predicted settlement for 50 days of embankment filling is 0.845 for 66 days of embankment filling, 40 days of embankment filling is 0.498 for 66 days of embankment filling, and 33 days of embankment filling is 0.318 for 66 days of embankment filling. This shows that the influence of embankment filling time on the discreteness of settlement prediction results is consistent at different observation times. The predicted settlement standard deviations obtained by different foundation treatment forms under the same number of observations and embankment filling time are different, and the influence of different embankment filling time on the discreteness of settlement prediction results is also different. For natural foundation, when the observation time is 30 days, the standard deviations of predicted settlement when the roadbed filling time is 66 days, 50 days, 40 days and 33 days are 7.57, 6.40, 3.77 and 2.41 respectively, and the ratios of the standard deviations of predicted settlement when the roadbed filling time is 50 days, 40 days, 33 days to that when the roadbed filling time is 66 days are as mentioned above. When the observation time is 60 days, the standard deviations of predicted settlement when the roadbed filling time is 66 days, 50 days, 40 days and 33 days are 0.32, 0.27, 0.16 and 0.10 respectively, and the ratios of the standard deviations of predicted settlement when the roadbed filling time is 50 days, 40 days, 33 days to that when the roadbed filling time is 66 days are as mentioned above. For the sand well foundation, when the observation time was 30 days, the standard deviations of the predicted settlement when the roadbed filling time was 66 days, 50 days, 40 days and 33 days were 38.05, 34.09, 25.88 and 21.14 respectively, and the ratios of the standard deviations of the predicted settlement when the roadbed filling time was 50 days, 40 days, 33 days to that when the roadbed filling time was 66 days were 0.896, 0.680 and 0.556 respectively. When the observation time was 60 days, the standard deviations of the predicted settlement when the roadbed filling time was 66 days, 50 days, 40 days and 33 days were 1.61, 1.45, 1.10 and 0.90 respectively, and the ratios of the standard deviations of the predicted settlement when the roadbed filling time was 50 days, 40 days, 33 days to that when the roadbed filling time was 66 days were 0.896, 0.680 and 0.556 respectively.

[0199] Fig.14 , Fig.16 These are the distribution maps of natural foundation prediction results when the observation duration is 30 days and 60 days respectively. Fig.15 , Fig.17 The following are the distribution diagrams of sand well foundation prediction results when the observation time is 30 days and 60 days respectively. Fig.14 , Fig.15 and Fig.16 , Fig.17 It can be seen that the faster the roadbed filling time, the smaller the discreteness of the settlement prediction results, and the settlement prediction results are more concentrated near the statistical mean of the predicted settlement. The slower the roadbed filling time, the greater the discreteness of the settlement prediction results, and the settlement prediction results are distributed in a wider distribution range on both sides of the settlement prediction result mean. In addition, the distribution range of the settlement prediction results obtained from the natural foundation is narrower than that of the settlement prediction results obtained from the sand well foundation. Fig.14 , Fig.16 and Fig.15 , Fig.17 It can be seen that as the number of observations increases, the statistical mean of the predicted settlement gradually approaches zero, indicating that as the number of observations increases, the difference between the theoretical value and the predicted value becomes smaller. For the same roadbed filling time, as the number of observations increases, the discreteness of the settlement prediction results becomes smaller, and the settlement prediction results are more concentrated near the statistical mean of the predicted settlement, indicating that as the number of observations increases, the settlement prediction results become more accurate.

[0200] Fig.18 Time history curve of the predicted settlement standard deviation for natural foundations with different observation times. Fig.19 The time course curve of the predicted settlement standard deviation for different observation times of the sand well foundation. The predicted settlement standard deviation gradually approaches zero as the observation time gradually increases, indicating that as the observation time increases, the discreteness of the predicted value obtained by the curve fitting method through observation prediction gradually decreases, and the settlement prediction results gradually approach the predicted settlement statistical mean, and the prediction results gradually stabilize. At the same time, as the observation time increases, the rate of change of the predicted settlement standard deviation gradually decreases. When the observation time is short, the difference in the predicted settlement standard deviation between two adjacent days is large. As the observation time increases, the difference in the predicted settlement standard deviation between two adjacent days decreases significantly, indicating that as the observation time increases, the predicted settlement standard deviation also gradually stabilizes.

[0201] Fig.18 and Fig.19 The curve of the change of the predicted settlement standard deviation with the observation time can be described by formula (18):

[0202] σ=A1exp(-x1 / t1)+A2exp(-x1 / t2) (18)

[0203] Where: σ——predicted settlement standard deviation (mm);

[0204] x1——Observation duration (days).

[0205] A1, t1, A2, t2——model fitting parameters.

[0206] The relationship between the model fitting parameters A1, t1, A2, and t2 of the fitting curve obtained by formula (18) for natural foundation and sand well foundation and the length of roadbed filling can be determined by formula (19) and formula (20).

[0207] A1=a1·x4+b1 (19)

[0208] A2=a2·x4+b2 (20)

[0209] In the formula: x4——roadbed filling time (days).

[0210] From the above analysis, it can be obtained that the calculation formula for the standard deviation of predicted settlement of natural foundation sand well foundation obtained by integrating the observation data of filling and loading process with the settlement difference method based on Weibull model is shown in Equation (21) and Equation (22).

[0211] Natural foundation:

[0212]

[0213] Sand well foundation:

[0214]

[0215] The influence of roadbed filling levels on the statistical mean and standard deviation of predicted settlement

[0216] Fig. 20 The figure is a bar chart of the statistical mean of predicted settlement under different roadbed filling levels of natural foundation. The change of the statistical mean of predicted settlement with observation time under different roadbed filling levels is consistent with the above description. As the observation time gradually increases, the statistical mean of predicted settlement gradually decreases. Changing the roadbed filling level has basically no effect on effectively controlling the statistical mean of predicted settlement. Fig.21 The figure is a bar chart of the predicted settlement statistical mean under different roadbed filling levels of the sand well foundation. The change of the predicted settlement statistical mean with the observation time under different roadbed filling levels is consistent with the above description. As the observation time gradually increases, the predicted settlement statistical mean gradually decreases. The change of roadbed filling level has basically no effect on the effective control of the predicted settlement statistical mean.

[0217] Fig. 22 and Fig.23The following are the time history diagrams of the predicted settlement standard deviation under different roadbed filling levels for natural foundation and sand well foundation, respectively. It can be seen from the two figures that under different roadbed filling levels, the predicted settlement standard deviation gradually decreases with the increase of the number of observations, indicating that with the increase of the number of observations, the discreteness of the settlement prediction results gradually decreases, and the prediction results gradually concentrate near the statistical mean of the predicted settlement. In logarithmic coordinates, the curves of the predicted settlement standard deviation with the number of observations under different roadbed filling levels are basically coincident, which shows that the roadbed filling level has the same effect on the discreteness of the settlement prediction results at different observation times. The predicted settlement standard deviations obtained under the same number of observations and roadbed filling levels obtained by different foundation treatment forms are different. For natural foundation, when the number of observations is 30, the standard deviations of predicted settlement are 2.41, 2.40, 2.39, and 2.37 when the roadbed filling level is 2, 4, 6, and 8, respectively. When the number of observations is 60, the standard deviations of predicted settlement are 0.10, 0.10, 0.10, and 0.10 when the roadbed filling level is 2, 4, 6, and 8, respectively. For sand well foundation, when the number of observations is 30, the standard deviations of predicted settlement are 21.22, 21.14, 21.03, and 20.82 when the roadbed filling level is 2, 4, 6, and 8, respectively. When the number of observations is 60, the standard deviations of predicted settlement are 0.90, 0.90, 0.89, and 0.88 when the roadbed filling level is 2, 4, 6, and 8, respectively.

[0218] Fig.24 , Fig.26 The distribution diagrams of natural foundation prediction results when the number of observations is 30 and 60 respectively. Fig.25 , Fig. 27 The distribution diagrams of sand well foundation prediction results when the number of observations is 30 and 60 respectively. Fig.24 , Fig.25 and Fig.26 , Fig. 27 It can be seen that the discreteness of the roadbed filling level and the settlement prediction results are not closely related. Increasing the roadbed filling level has little effect on effectively reducing the distribution range of the roadbed settlement prediction results. The distribution range of the settlement prediction results obtained from the natural foundation is narrower than that of the settlement prediction results obtained from the sand well foundation. Fig.24 , Fig.26 and Fig.25 , Fig. 27 It can be seen that as the number of observations increases, the statistical mean of the predicted settlement gradually approaches zero, indicating that as the number of observations increases, the difference between the theoretical value and the predicted value becomes smaller. For the same roadbed filling level, as the number of observations increases, the discreteness of the settlement prediction results becomes smaller, and the settlement prediction results are more concentrated near the statistical mean of the predicted settlement, indicating that as the number of observations increases, the settlement prediction results become more accurate.

[0219] Embodiment 2

[0220] This embodiment also provides a settlement prediction confidence analysis system integrating observation data of filling and loading process, including:

[0221] The first model building module 101 is used to modify and derive the traditional differential settlement method using the Weibull model, thereby obtaining a modified differential settlement method settlement prediction model;

[0222] The second model building module 102 is used to combine the modified settlement difference method settlement prediction model with the roadbed settlement prediction confidence analysis method to construct a roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process;

[0223] The confidence analysis module 103 is used to compare the confidence of multiple settlement prediction models that integrate the observation data of the filling and loading process based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, analyze the influence of the filling and loading method on the predicted settlement statistical mean and standard deviation, and obtain the correlation corresponding to the influence law.

[0224] The present invention also provides a memory storing a plurality of instructions, wherein the instructions are used to implement the method as in the first embodiment.

[0225] like Fig.28 As shown, the present invention also provides an electronic device, including a processor 301 and a memory 302 connected to the processor 301, the memory 302 stores a plurality of instructions, and the instructions can be loaded and executed by the processor so that the processor can execute the method as in the first embodiment.

[0226] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A settlement prediction confidence analysis method integrating observation data of filling and loading process, characterized in that: include: S1, the traditional settlement difference method is modified and derived using the Weibull model, thereby obtaining the settlement prediction model of the modified settlement difference method; S2, combining the modified settlement difference method settlement prediction model with the roadbed settlement prediction confidence analysis method to construct a roadbed settlement prediction confidence analysis model that can integrate observation data of the filling and loading process; S3, based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, compare the confidence of multiple settlement prediction models that integrate the observation data of the filling and loading process, analyze the influence of the filling and loading method on the predicted settlement statistical mean and standard deviation, and obtain the correlation corresponding to the influence law.

2. A settlement prediction confidence analysis method integrating observation data of filling and loading process according to claim 1, characterized in that: The S1 includes: S11, determine the average consolidation degree of the foundation under multi-level loading conditions of soft soil roadbed settlement, modify it according to the Weibull model, and determine the basic assumptions of the settlement prediction model of the modified settlement difference method; S12, the Weibul l model is used to correct and derive the traditional settlement difference method, so as to obtain the settlement prediction model of the modified settlement difference method.

3. A settlement prediction confidence analysis method integrating observation data of filling and loading process according to claim 2, characterized in that: The basic assumptions include: (1) The consolidation process caused by each load increment occurs independently and has nothing to do with the consolidation degree caused by the previous load increment; (2) The total degree of consolidation is equal to the sum of the degrees of consolidation under each level of load increment; (3) Loading period is 0~t i The load increment of the uniform loading is related to the load at t i / 2 The degree of consolidation caused by applying the load increment instantaneously once is equivalent; (4) Average degree of consolidation U t It is defined according to the settlement deformation, that is, Among them, s t Indicates the current settlement deformation, s ∞ Indicates the maximum settlement deformation; (5) The degree of consolidation under each level of load is corrected according to the load ratio and superimposed to obtain the average degree of consolidation under the total load, as shown in formula (1): Where: U ti is the degree of consolidation under the i-th level load; p i is the i-th load increment; p is the total load; n is the total number of stages of graded loading; Based on the basic assumptions (4) and (5), it can be deduced that the consolidation settlement s caused by a certain level of load is cpi Total consolidation settlement s caused by total load cp The ratio is equal to the load increment p of this level. i The ratio of the load to the total load p is shown in formula (2):

4. A settlement prediction confidence analysis method integrating observation data of filling and loading process according to claim 3, characterized in that: The S12 includes: According to the Weibull model, at t 0pi Under the action of the i-th level load increment applied instantaneously at time t, the foundation consolidation degree equivalent to the i-th level load increment is between t1 and t2 (t2>t1>t opi ) are: Then the roadbed settlement caused by the i-th level load increment at time t1 and t2 are: Substituting formula (2) into formula (5) and formula (6) yields: If the load is constant during the period from t1 to t2, the settlement difference during the period from t1 to t2 caused by the incremental loads applied during the loading period is: Where: t op1 - the moment of application of the first load increment, corrected according to basic assumption (3); t1, t2——any time in the constant load period after the load filling is completed, and t2>t1; ——are the accumulated settlement at time t1 and time t2 respectively; m——the number of graded loads applied during the loading period; p i —— load of level i; p——total load of roadbed filling; S cp , α, b, r——model fitting parameters, optimized and solved based on intelligent algorithms.

5. The method for analyzing the confidence of settlement prediction by integrating observation data of filling and loading process according to claim 4 is characterized in that: The S2 of merging the settlement prediction model of the modified settlement difference method with the roadbed settlement prediction confidence analysis method includes merging the settlement prediction model that can integrate the observation data of the filling and loading process with the roadbed settlement prediction confidence analysis method, and obtaining the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process after selecting the optimal model based on the confidence; wherein the settlement prediction model that can integrate the observation data of the filling and loading process includes the improved hyperbolic method, the traditional settlement difference method and the modified settlement difference method.

6. A settlement prediction confidence analysis method integrating observation data of filling and loading process according to claim 5, characterized in that: The roadbed settlement prediction confidence analysis method of S2 includes: generating simulated settlement observation data, wherein the simulated settlement observation data is generated based on discrete observation data with observation errors; Performing a confidence analysis on roadbed settlement prediction based on the simulated settlement observation data; Wherein, generating simulated settlement observation data comprises: Aiming at the settlement problem of soft soil roadbed under different foundation treatment forms and different soil conditions, the corresponding theoretical continuous data under different conditions are calculated based on the homogeneous natural foundation calculation model and the sand well foundation calculation model; The theoretical continuous data is divided into observation period data and late settlement data according to different first settlement observation conditions, and the observation period data is discretized according to the second settlement observation condition to obtain discrete data; superimposing observation errors on discrete observation period data according to different third settlement observation conditions to generate discrete observation data with the observation errors, and generating the simulated settlement observation data based on the discrete observation data with the observation errors; Among them, the first settlement observation condition is the observation duration; the second settlement observation condition is the observation frequency; the third settlement observation condition is the observation accuracy; The confidence analysis of roadbed settlement prediction based on the simulated settlement observation data includes: Based on the discrete observation data with the observation error, a curve fitting method is used to predict and obtain the prediction value corresponding to each group of observation data; the above process is repeated to obtain multiple prediction values ​​to form a prediction result; The prediction results are statistically analyzed to obtain the predicted settlement statistical mean and predicted settlement standard deviation.

7. A settlement prediction confidence analysis method integrating observation data of filling and loading process according to any one of claims 1 to 6, characterized in that: The S3, based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, compares the confidence of multiple settlement prediction models that integrate the observation data of the filling and loading process, analyzes the influence of the filling and loading method on the statistical mean and standard deviation of the predicted settlement, and obtains the correlation corresponding to the influence law, including: The statistical mean calculation formulas for predicted settlement of homogeneous natural foundation and homogeneous sand well foundation obtained by integrating the observation data of filling and loading process by the modified settlement difference method are shown in equations (16) and (17): Natural foundation: Sand well foundation: The curve of the change of the predicted settlement standard deviation with the observation time is described by formula (18): σ=A1exp(-x1 / t1)+A2exp(-x1 / t2) (18); Where: σ——predicted settlement standard deviation (mm); x1——observation duration (days); A1, t1, A2, t2——model fitting parameters; The relationship between the model fitting parameters A1, t1, A2, and t2 of the fitting curve obtained by formula (18) for natural foundation and sand well foundation and the length of roadbed filling. The fitting curve can be determined by formula (19) and formula (20): A1=a1·x4+b1 (19); A2=a2·x4+b2 (20); Where: x4——roadbed filling time (days); The calculation formulas for the predicted settlement standard deviation of homogeneous natural foundation and homogeneous sand well foundation obtained by integrating the observation data of the filling and loading process with the modified settlement difference method are shown in equations (21) and (22): Natural foundation: Sand well foundation: And, determine the influence of roadbed filling levels on the statistical mean and standard deviation of predicted settlement.

8. A settlement prediction confidence analysis system integrating observation data of filling and loading process, used to implement the method of any one of claims 1 to 7, characterized in that: include: The first model building module (101) is used to modify and derive the traditional differential settlement method using the Weibul model, thereby obtaining a modified differential settlement method settlement prediction model; The second model building module (102) is used to combine the modified settlement difference method settlement prediction model with the roadbed settlement prediction confidence analysis method to construct a roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process; The confidence analysis module (103) is used to compare the confidences of multiple settlement prediction models integrating the observation data of the filling and loading process based on the roadbed settlement prediction confidence analysis model that can integrate the observation data of the filling and loading process, analyze the influence of the filling and loading method on the statistical mean and standard deviation of the predicted settlement, and obtain the correlation corresponding to the influence law.

9. An electronic device, characterized in that: The method comprises a processor and a memory, wherein the memory stores a plurality of instructions, and the processor is used to read the instructions and execute the method according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a plurality of instructions, and the plurality of instructions can be read by a processor to execute the method according to any one of claims 1 to 7.

Citation Information

Patent Citations

  • Ground subsidence prediction system and method based on support vector machine

    CN107153843A

  • Vacuum combined surcharge preloading drain board foundation lateral deformation prediction method

    CN116341137A

  • Pile foundation settlement monitoring and data processing method for pile plate type soilless roadbed

    CN118152723A

  • Method of restoration of foundations

    RU2199628C1

  • Fallout Management Engine (FAME)

    US20230289690A1

Cited By

  • High-speed rail stratified foundation settlement early prediction confidence analysis method and high-speed rail stratified foundation settlement early prediction confidence analysis system

    CN119918348A