Development cost determination method and device for various adjustable load resources in park

By acquiring and processing the current requirements of adjustable load resources in the park and generating and optimizing cost modes, the problem of unsatisfactory allocation efficiency of the adjustable load resource cost mode is solved, and the resource allocation efficiency is improved.

CN119027153APending Publication Date: 2024-11-26STATE GRID ENERGY RES INST CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411025029.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The cost mode allocation efficiency of adjustable load resources in the prior art is not ideal, making it difficult for the park to build an adjustable load resource library and promote demand-side response.

Method used

By obtaining the current load requirements of multiple adjustable load resources in the target park, using the target model to process it, generating candidate cost modes of different modes, and determining the target mode according to decision-making needs, optimizing resource allocation.

Benefits of technology

The cost mode of adjustable load resource is realized, the efficiency of the target mode is improved, and the problem of unsatisfactory configuration efficiency of the cost mode is solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119027153A_ABST
    Figure CN119027153A_ABST
Patent Text Reader

Abstract

The invention discloses a method and a device for determining development cost of various adjustable load resources in a park. The method comprises the following steps: acquiring current load requirements respectively corresponding to various adjustable load resources existing in a target park; based on the current load demands corresponding to the multiple adjustable load resources, processing is carried out by adopting a target model, and cost demands corresponding to multiple preset candidate cost modes are obtained, and the multiple candidate cost modes are different modes obtained based on the multiple adjustable load resources; the target model is generated based on historical load demands corresponding to various adjustable load resources in the target park; and in response to the decision demand, determining a target mode of the application in the target park based on the cost demands corresponding to the plurality of candidate cost modes. According to the invention, the technical problem that the cost mode configuration efficiency of adjustable load resources is not ideal in the prior art is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of power system planning, and in particular to a method and device for determining development costs of multiple adjustable load resources in a park. Background Art

[0002] The potential of adjustable load resources is huge. The adjustable resources in the demand response resource library are diverse and have considerable capacity. Fully developing and tapping the response potential of adjustable resources on the user side, giving full play to the value of adjustable load resources, and mobilizing adjustable load resources on the user side are crucial to ensuring the balance of supply and demand in the power system and improving the flexible adjustment and resilience of the power grid. Adjustable loads include distributed generation, temperature control loads, electric vehicles and other resources. Different types of resources have great differences in sensitivity to electricity prices and adjustment performance.

[0003] In the process of promoting the implementation of different types of adjustable load projects in relevant technologies, there is a lack of feasibility analysis and cost model evaluation and comparison of the investment and operation of adjustable load resource projects. The quantitative evaluation of the cost model of adjustable load resources is not objective enough, resulting in unsatisfactory model configuration efficiency, making it difficult to build an adjustable load resource library for the park and provide technical support for the promotion of demand-side response.

[0004] To address the above-mentioned problems, no effective solution has been proposed yet. Summary of the invention

[0005] The embodiment of the present invention provides a method and device for determining the development cost of multiple adjustable load resources in a park, so as to at least solve the technical problem of unsatisfactory configuration efficiency of the cost model of adjustable load resources in the related art.

[0006] According to one aspect of an embodiment of the present invention, a method for determining development costs of multiple adjustable load resources in a park is provided, including: obtaining current load demands corresponding to multiple adjustable load resources in a target park; based on the current load demands corresponding to the multiple adjustable load resources, processing using a target model to obtain cost demands corresponding to multiple predetermined candidate cost patterns, wherein the multiple candidate cost patterns are different patterns obtained based on the multiple adjustable load resources, and the target model is generated based on historical load demands corresponding to the multiple adjustable load resources in the target park; in response to decision-making requirements, determining the target pattern applied in the target park based on the cost demands corresponding to the multiple candidate cost patterns.

[0007] Optionally, obtaining the current load demands corresponding to the various adjustable load resources existing in the target park includes: determining the temperature control load demand and the power load demand of the target park based on the park scale of the target park, the park application type, and current meteorological information; determining the current load demand according to the temperature control load demand and the power load demand, using the Internet of Things method, and / or data analysis method.

[0008] Optionally, the method also includes: determining a first objective function based on the construction unit costs and rated capacities corresponding to the various adjustable load resources; determining a second objective function based on the operating unit costs, output and resource usage corresponding to the various adjustable load resources, wherein the first objective function and the second objective function are respectively used to obtain the minimization values ​​of different types of costs; and generating the target model based on the first objective function and the second objective function.

[0009] Optionally, the method also includes: determining an operating constraint based on the fact that the processing volume corresponding to each of the multiple adjustable load resources is less than the rated capacity; determining a supply and demand constraint based on the current total adjustable load and the current non-adjustable electrical load; obtaining a first constraint condition based on the operating constraint and the supply and demand constraint; the current load demand corresponding to each of the multiple adjustable load resources is processed using a target model to obtain cost demands corresponding to each of the predetermined multiple candidate cost modes, including: based on the current load demand corresponding to each of the multiple adjustable load resources, the first objective function included in the target model is processed to obtain the minimized value of the first objective function that satisfies the first constraint condition as the first cost minimization value; based on the first cost minimization value, the cost demands corresponding to each of the multiple candidate cost modes are obtained.

[0010] Optionally, the multiple adjustable load resources include: air-conditioning equipment and electric vehicles, and the current load demands corresponding to the multiple adjustable load resources are processed using a target model to obtain cost demands corresponding to the predetermined multiple candidate cost models, including: determining the temperature control adjustable resources based on the current load demand corresponding to the air-conditioning equipment; determining the electric vehicle adjustable resources based on the current load demand corresponding to the electric vehicle; and obtaining the current total adjustable load based on the temperature control adjustable resources and the electric vehicle adjustable resources.

[0011] Optionally, the method also includes: determining the gas power generation constraint based on the power generation efficiency and resource usage of the gas power generation equipment included in the multiple adjustable load resources; determining the energy storage constraint based on the power inventory and charging and discharging efficiency of the energy storage equipment included in the multiple adjustable load resources; obtaining a second constraint condition according to the gas power generation constraint and the energy storage constraint; the current load demands corresponding to the multiple adjustable load resources are processed using the target model to obtain the cost demands corresponding to the predetermined multiple candidate cost modes, including: based on the current load demands corresponding to the multiple adjustable load resources, the second objective function included in the target model is processed to obtain the minimized value of the second objective function that satisfies the second constraint condition as the second cost minimization value; based on the second cost minimization value, the cost demands corresponding to the multiple candidate cost modes are obtained.

[0012] Optionally, the decision requirement includes a decision target and a decision criterion, and the response to the decision requirement is to determine the target cost model in the target park based on the cost requirements respectively corresponding to the multiple candidate cost models, including: using a hierarchical analysis method to determine evaluation indicators of the multiple candidate cost models based on the decision target, the decision criterion, and the multiple candidate cost models; determining the target cost model in the target park based on the evaluation indicators of the multiple candidate cost models and the cost requirements respectively corresponding to the multiple candidate cost models.

[0013] According to another aspect of an embodiment of the present invention, a device for determining development costs of multiple adjustable load resources in a park is provided, including: a load demand acquisition module, which acquires current load demands corresponding to multiple adjustable load resources in a target park; a cost demand calculation module, which uses a target model to process the current load demands corresponding to the multiple adjustable load resources to obtain cost demands corresponding to multiple predetermined candidate cost patterns, wherein the multiple candidate cost patterns are different patterns obtained based on the multiple adjustable load resources, and the target model is generated based on historical load demands corresponding to the multiple adjustable load resources in the target park; a target pattern confirmation module, which determines the target pattern applied in the target park based on the cost demands corresponding to the multiple candidate cost patterns in response to decision requirements.

[0014] According to another aspect of an embodiment of the present invention, a non-volatile storage medium is provided, wherein the non-volatile storage medium stores a plurality of instructions, wherein the instructions are suitable for being loaded by a processor and executing any one of the methods for determining the development cost of multiple adjustable load resources in a park.

[0015] According to another aspect of an embodiment of the present invention, there is provided an electronic device, comprising: one or more processors and a memory, the memory being used to store one or more programs, wherein when the one or more programs are executed by the one or more processors, the one or more processors implement any one of the methods for determining the development cost of multiple adjustable load resources in a park.

[0016] In an embodiment of the present invention, a development cost determination method for multiple adjustable load resources in a park is adopted, by obtaining the current load demands corresponding to the multiple adjustable load resources in the target park; based on the current load demands corresponding to the multiple adjustable load resources, a target model is used for processing to obtain the cost demands corresponding to the predetermined multiple candidate cost modes, wherein the multiple candidate cost modes are different modes obtained based on the multiple adjustable load resources, and the target model is generated based on the historical load demands corresponding to the multiple adjustable load resources in the target park; in response to decision-making requirements, the target mode applied in the target park is determined based on the cost demands corresponding to the multiple candidate cost modes. The purpose of reasonably configuring the cost mode of the adjustable load resources is achieved, and the technical effect of improving the efficiency of the target mode is realized, thereby solving the technical problem of unsatisfactory configuration efficiency of the cost mode of the adjustable load resources in the related technology. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0018] Figure 1 It is a flowchart of an optional method for determining development costs of multiple adjustable load resources in a park provided according to an embodiment of the present invention;

[0019] Figure 2 is a first schematic diagram of an optional method for determining development costs of multiple adjustable load resources in a park provided according to an embodiment of the present invention;

[0020] Figure 3 is a second schematic diagram of an optional method for determining development costs of multiple adjustable load resources in a park provided according to an embodiment of the present invention;

[0021] Figure 4 is a third schematic diagram of an optional method for determining development costs of multiple adjustable load resources in a park provided according to an embodiment of the present invention;

[0022] Figure 5is a schematic flow chart of an optional method for determining development costs of multiple adjustable load resources in a park provided according to an embodiment of the present invention;

[0023] Figure 6 It is a visual schematic diagram of an optional method for determining development costs of multiple adjustable load resources in a park provided according to an embodiment of the present invention;

[0024] Figure 7 It is a schematic diagram of an optional device for determining development costs of multiple adjustable load resources in a park provided according to an embodiment of the present invention. DETAILED DESCRIPTION

[0025] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0026] For the convenience of description, some nouns or terms involved in the embodiments of the present application are explained below:

[0027] Internet of Things (IoT): It is a network that connects physical devices, vehicles, household appliances and other items through the Internet, which can collect and exchange data and realize intelligent identification, positioning, tracking, monitoring and management. The core of IoT is to enable objects to autonomously exchange information and communicate through built-in sensors, software and other technologies, so as to achieve the purpose of remote control, automated operation and data analysis. This solution collects the operating data of various adjustable load resources in the park in real time by deploying sensors and equipment.

[0028] CHP (Combined Heat and Power) is a highly efficient way of utilizing energy. It produces electricity and heat at the same time, and uses waste heat for heating or cooling, thus improving the efficiency of energy utilization. In a combined heat and power production system, heat and electricity are produced at the same time, making the maximum use of waste heat, thereby reducing energy consumption and greenhouse gas emissions.

[0029] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0030] In response to the above problems, an embodiment of the present invention provides a method embodiment of a method for determining the development cost of multiple adjustable load resources in a park. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although the logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0031] Figure 1 is a flow chart of an optional method for determining development costs of multiple adjustable load resources in a park according to an embodiment of the present invention, such as Figure 1 As shown, the method comprises the following steps:

[0032] Step S102: obtaining current load demands corresponding to various adjustable load resources in the target park.

[0033] Step S104, based on the current load demands corresponding to the various adjustable load resources, the target model is used for processing to obtain the cost demands corresponding to the predetermined multiple candidate cost modes, wherein the multiple candidate cost modes are different modes obtained based on the various adjustable load resources, and the target model is generated based on the historical load demands corresponding to the various adjustable load resources in the target park.

[0034] Step S106 , in response to the decision-making requirements, based on the cost requirements corresponding to the multiple candidate cost models, determine the target model to be applied in the target park.

[0035] It can be understood that the current load demands corresponding to the various adjustable load resources in the target park are obtained, a target model is generated based on the historical load demands, the target model is used to process the current load demand, and the cost demands corresponding to the predetermined multiple candidate cost modes are obtained. In response to the decision-making requirements, the target mode applied in the target park is determined based on the cost demands corresponding to the multiple candidate cost modes. Through the above steps S102 to S106, the purpose of reasonably configuring the cost mode of the adjustable load resources is achieved, and the technical effect of improving the efficiency of the target mode is achieved, thereby solving the technical problem of unsatisfactory configuration efficiency of the cost mode of the adjustable load resources in the related technology.

[0036] In an optional embodiment, the current load demands corresponding to the various adjustable load resources existing in the target park are obtained, including: determining the temperature control load demand and the power load demand of the target park based on the park scale, the park application type, and the current meteorological information of the target park; and determining the current load demand based on the temperature control load demand and the power load demand by using the Internet of Things and / or data analysis method.

[0037] It can be understood that based on the scale, purpose and meteorological conditions of the park, the temperature control load demand and power load demand of the target park are determined by using the Internet of Things and / or data analysis. Through the Internet of Things and / or data analysis, real-time collection and transmission of energy consumption data can be achieved, ensuring the accuracy and timeliness of the data.

[0038] Optionally, the temperature control load demand and power load demand at least include: according to the meteorological conditions, scale and purpose of the park and the use of equipment at different times, Figure 2 is a first schematic diagram of an optional method for determining development costs of multiple adjustable load resources in a park according to an embodiment of the present invention, such as Figure 2 As shown, the cold, hot and electric load demand results of typical users at different times are recorded. The above-mentioned times T1 to T24 respectively represent the collection times, and the above-mentioned heat load and cold load are respectively the temperature loads related to the temperature control load demand. The specific data in Table 1 are for illustration only and are not specifically limited.

[0039] Table 1 Park load demand settings

[0040]

[0041] In an optional embodiment, the method also includes determining a first objective function based on the construction unit costs and rated capacities corresponding to the various adjustable load resources; determining a second objective function based on the operating unit costs, outputs and resource usage corresponding to the various adjustable load resources, wherein the first objective function and the second objective function are respectively used to obtain the minimization values ​​of different types of costs; and generating a target model based on the first objective function and the second objective function.

[0042] It can be understood that based on a variety of adjustable load resources, the construction unit cost, i.e., the investment unit price, the operation unit cost, i.e., the operation unit price, and the resource usage, i.e., the sum of the purchase volume and the purchase unit price of natural gas, are determined, and a double-layer objective function is established. The upper layer takes the minimization of investment cost as the objective function, i.e., the first objective function, and the lower layer takes the minimization of operation cost as the objective function, i.e., the second objective function. Through the double-layer objective function, the resource usage and cost can be accurately calculated, and the resource procurement and use strategy can be optimized to improve the efficiency of resource utilization.

[0043] Optionally, the target model construction method at least includes: establishing a two-layer objective function, the upper layer takes investment cost minimization as the objective function (i.e., the first objective function), and the lower layer takes operation cost minimization as the objective function (i.e., the second objective function), and the formula is as follows:

[0044]

[0045] Among them, f min,1 is the objective function of the upper model, representing the minimization of investment cost, in yuan (i.e. the first objective function); f min,2 is the objective function of the lower model, representing the minimization of operating costs, in yuan (i.e., the second objective function); i is the equipment type, i=1 is the gas power generation system, i=2 is the energy storage equipment; i=3 is the temperature control variable frequency air conditioning group; i=4 is the electric vehicle; C C,i is the unit price of investment and construction of the i-th equipment, in yuan / kW (kilowatt); P C,i is the construction rated capacity of the i-th type of equipment, in kW; C E,i is the unit price of the operating cost of the i-th equipment, in yuan / kW; P E,i (t) is the output of the ith device at time t, in kW; C g is the purchase price of natural gas, in yuan / m 3 (square meters); V g (t) is the purchase amount of natural gas at time t, in m 3 .

[0046] In an optional embodiment, the method also includes: determining an operating constraint based on that the processing volume corresponding to each of the multiple adjustable load resources is less than the rated capacity; determining a supply and demand constraint based on the current total adjustable load and the current non-adjustable electrical load; obtaining a first constraint condition based on the operating constraint and the supply and demand constraint; based on the current load demand corresponding to each of the multiple adjustable load resources, processing using a target model to obtain cost demands corresponding to each of the predetermined multiple candidate cost modes, including: based on the current load demand corresponding to each of the multiple adjustable load resources, processing using a first objective function included in the target model to obtain a minimized value of the first objective function that satisfies the first constraint condition as a first cost minimization value; based on the first cost minimization value, obtaining cost demands corresponding to each of the multiple candidate cost modes.

[0047] It can be understood that the actual processing capacity of each adjustable load resource during operation will not exceed its designed rated capacity and the current total adjustable load and the current non-adjustable electrical load. The operating constraints and supply and demand constraints of the model are determined, combined with the current load demand, and processed using the target model to obtain the cost requirements corresponding to different cost models. Under the premise of ensuring the safe operation of the equipment, the adjustable load resources are reasonably allocated and adjusted to meet the energy needs of the entire system.

[0048] Optionally, the first minimum cost is the minimum investment cost, and the above operation constraint and supply and demand constraint calculations include at least the following formula:

[0049] 0≤P E,1 (t)≤P C,1

[0050] 0≤P E,2 (t)≤P C,2

[0051] 0≤P E,3 (t)≤P C,3

[0052] 0≤P E,4 (t)≤P C,4

[0053] 0≤P E,5 (t)≤P C,5

[0054] Among them, the constraint condition of the upper model, namely the first constraint condition, represents that the output of gas power generation equipment, energy storage equipment, variable frequency air conditioner and electric vehicle at time t is less than their rated capacity.

[0055]

[0056] Among them, P E,2ch (t) is the charging capacity of the energy storage device at time t, in kW; P E,2 dis (t) is the discharge capacity of the energy storage device at time t, in kW; β is a 0-1 parameter, β(t) = 1 means that the energy storage device is in a charging state at time t, otherwise it is in a discharging state, H E (t) is the non-adjustable electric load at time t, in kW, and b is the variable frequency air conditioning energy supply simulation parameter. α is a 0-1 parameter, α(t) = 1 means that the electric vehicle is in a charging state at time t, otherwise it is in a discharging state.

[0057] In an optional embodiment, the multiple adjustable load resources include: air-conditioning equipment and electric vehicles. Based on the current load demands corresponding to the multiple adjustable load resources, the target model is used for processing to obtain the cost demands corresponding to the predetermined multiple candidate cost models, including: determining the temperature control adjustable resources based on the current load demand corresponding to the air-conditioning equipment; determining the electric vehicle adjustable resources based on the current load demand corresponding to the electric vehicle; and obtaining the current total adjustable load based on the temperature control adjustable resources and the electric vehicle adjustable resources.

[0058] It can be understood that based on the current load demand corresponding to the air-conditioning equipment and the current load demand corresponding to the electric vehicle, the temperature control adjustable resources and the electric vehicle adjustable resources are determined, and the two resources are combined to obtain the current total adjustable load. By integrating different types of adjustable load resources, the existing energy infrastructure can be used more effectively and the overall energy utilization rate can be improved.

[0059] Optionally, the above temperature control adjustable resources can be obtained through a temperature control load adjustable potential calculation model, which is mathematically expressed as follows:

[0060]

[0061] Among them, T in (t) is the indoor temperature of the air conditioner at time t, in °C; τ is the simulation setting time step; η is the energy supply efficiency of the variable frequency air conditioner; a, b, c, d are the energy supply simulation parameters of the variable frequency air conditioner; T out (t) is the outdoor temperature at time t, in °C; T set (t) is the set temperature of the air conditioner at time t, in °C; H is the thermal conductivity between the room where the air conditioner is located and the outdoors; E is the equivalent thermal mass of the room where the air conditioner is located.

[0062] Optionally, the above electric vehicle adjustable resources can be obtained through an electric vehicle adjustable potential calculation model, which is mathematically expressed as follows:

[0063]

[0064] Where s(t) is the electric energy of the electric vehicle at time t, in kW; η ch is the charging efficiency of electric vehicles, P E,4 ch (t) is the charging power of the electric vehicle at time t, in kW; η dis is the discharge efficiency of the electric vehicle, PE,4dis(t) is the discharge power of the electric vehicle at time t, in kW; α is a 0-1 parameter, α(t) = 1 means that the electric vehicle is in a charging state at time t, otherwise it is in a discharging state.

[0065] Figure 3 is a second schematic diagram of an optional method for determining development costs of multiple adjustable load resources in a park according to an embodiment of the present invention, such as Figure 3 The figure shows a line graph showing the trend of the charging power and discharging power of electric vehicles as an adjustable load resource over time.

[0066] In an optional embodiment, the method further includes: determining a gas-fired power generation constraint based on the power generation efficiency and resource usage of the gas-fired power generation equipment included in the multiple adjustable load resources; determining an energy storage constraint based on the power inventory and charge-discharge efficiency of the energy storage equipment included in the multiple adjustable load resources; obtaining a second constraint condition according to the gas-fired power generation constraint and the energy storage constraint; based on the current load demands corresponding to the multiple adjustable load resources, respectively, processing using a target model to obtain cost demands corresponding to the predetermined multiple candidate cost modes, respectively, including: based on the current load demands corresponding to the multiple adjustable load resources, processing using a second objective function included in the target model to obtain a minimized value of the second objective function that satisfies the second constraint condition, as a second cost minimization value; based on the second cost minimization value, obtaining cost demands corresponding to the multiple candidate cost modes, respectively.

[0067] It can be understood that based on the power generation efficiency and resource usage of gas-fired power generation equipment and the power holdings and charging and discharging efficiency of energy storage equipment, the gas-fired power generation constraints and energy storage constraints are determined, and the two are combined to obtain the second constraint condition. The target model is used to process the current load demand. Based on the second constraint condition, the second cost minimization value, that is, the operating cost minimization value, is obtained, and the cost requirements corresponding to different cost models are calculated. By comprehensively considering the efficiency and constraints of gas-fired power generation and energy storage equipment, energy use can be planned more effectively to ensure that energy consumption and operating costs are minimized while meeting load demand.

[0068] Optionally, the above operation constraint and supply and demand constraint calculation includes at least the following formula:

[0069] V g (t)η g (t) = PE,1 (t)

[0070]

[0071] Among them, the constraint condition of the lower model, that is, the second constraint condition, η g (t) is the power generation efficiency of the gas-fired power generation equipment at time t; g(t) is the power reserve of the energy storage equipment at time t, in kW; The charging efficiency of the energy storage device; is the discharge efficiency of the energy storage device.

[0072] Optionally, a two-layer operation constraint is established, and the specific formula is as follows:

[0073]

[0074] λ j ≥0

[0075] Among them, L j (x,λ j ) is the double-layer operation constraint condition, h j (x) is the constraint expression, j = 1, 2, 3, 4. When j = 1, h1 is the expression of the temperature control load adjustable potential calculation model:

[0076]

[0077] When j = 1, h2 is the expression of the electric vehicle adjustable potential calculation model:

[0078]

[0079] When j=3, h3 is the expression:

[0080] V g (t)η g (t) = P E,1 (t)

[0081] When j=4, h4 is the expression:

[0082]

[0083] Among them, λ j The above calculation processes are coupled to establish a two-level optimization model for the configuration and operation of the integrated energy system taking into account the adjustable load, and then solve it to obtain the investment cost and operation cost of the integrated energy system covering adjustable projects such as variable frequency air conditioners and electric vehicles.

[0084] In an optional embodiment, the decision requirements include decision goals and decision criteria. In response to the decision requirements, a target cost model in the target park is determined based on the cost requirements corresponding to the multiple candidate cost models, including: using a hierarchical analysis method to determine evaluation indicators of the multiple candidate cost models based on the decision goals, decision criteria, and the multiple candidate cost models; determining the target cost model in the target park based on the evaluation indicators of the multiple candidate cost models and the cost requirements corresponding to the multiple candidate cost models.

[0085] It can be understood that based on the decision-making objectives, decision-making criteria and candidate cost models, the evaluation indicators are determined, the cost requirements corresponding to the candidate cost models are evaluated using the evaluation indicators, and the target cost model in the target park is determined. By evaluating different cost models, it is possible to identify which cost model can meet energy requirements while minimizing costs, thereby optimizing the cost structure of the park.

[0086] Optionally, using the analytic hierarchy process to establish an indicator system includes at least: quantitative evaluation of factors at different levels to obtain more scientific and reasonable decision support. By establishing a hierarchical model, clarifying the decision-making goals, considerations (decision-making criteria) and different cost model types, dividing them into the highest level, middle level and lowest level according to their mutual relationships, and drawing a hierarchical diagram. Construct a judgment (paired comparison) matrix (see Table 2), compare all factors pairwise, and use the nine-scale method (see Table 3) to minimize the difficulty of comparing factors of different natures to improve accuracy.

[0087] Table 2 Judgment Matrix

[0088]

[0089] Table 3 Nine-scale method

[0090]

[0091] Among them, i and j can take values ​​from 1 to n, and the scale is a ij For C nn Hint.

[0092] Perform hierarchical single sorting and consistency test. Calculate the relative weight of the evaluation criteria and determine the weight of each indicator. Through the consistency test, ensure the rationality and scientificity of the evaluation results. The RI value can be obtained through Table 4. Ensure that the consistency ratio (CR) value of the judgment matrix is ​​less than 0.1. If it is not satisfied, the judgment matrix needs to be adjusted for consistency until the calculation results meet the following conditions.

[0093] CR=CI / RI

[0094] CI=(λ max-n)(n-1)n=1,2,3,…,9

[0095] Where: CI is the consistency index; CR is the consistency ratio; RI is the average consistency index.

[0096] Table 4 RI value determination

[0097]

[0098] Based on the above analysis, different cost models are evaluated and optimized, providing detailed judgment basis and methods for optimizing decision-making, fully considering the decision makers' understanding of the problem and the accuracy of their evaluation, and determining the cost model that best meets the park's energy needs, regulation potential and continuous optimization.

[0099] Optionally, database creation includes at least: database establishment, based on MySQL relational database system, designing data tables and views such as parameters, demand, weather, equipment information, etc., designing field types and storage space, ensuring effective storage and efficient retrieval of data, and establishing a cost model database that can adjust the flexibility of load resource configuration. The main data tables designed are as follows:

[0100] Table 5 Parameters

[0101]

[0102] Table 6 Energy demand table

[0103]

[0104] Table 7 Weather Table

[0105]

[0106] Table 8 Equipment information table

[0107]

[0108] Table 9 Cost model table

[0109]

[0110] Table 10 Economic cost table

[0111]

[0112] Figure 4 is a third schematic diagram of an optional method for determining development costs of multiple adjustable load resources in a park according to an embodiment of the present invention, such as Figure 4 As shown, a software interface formed based on the above model library encapsulation is illustrated, which illustrates some parameters in the above Tables 5-10.

[0113] Based on Python language (a programming language), the cost model optimization method for the flexible configuration of adjustable load resources is programmed, and the PyInstaller tool (a Python program packaging tool) is used to encapsulate the model to create reusable computer components for easy deployment in third-party systems. To install PyInstaller, open the command prompt (CMD) window on the computer and execute the command "pip install pyinstaller" to install it. In the command prompt (CMD) window, switch the command execution path to the folder where the Python file is located. Execute the command "pyinstaller-FPython file name" to encapsulate the program source code. After the encapsulation is completed, the generated exe file is stored in the predetermined folder generated under the directory where the Python file is located, recorded as the dist folder, and the packaging of the source code program is completed.

[0114] Formulate the overall architecture and modular structure of the system, complete the front-end interface design and system back-end design. Use C# programming language and development tools to write and implement each module and function of the system. Perform unit testing, integration testing and system testing to verify the functions and performance of the system. Finally, deploy the system to the target environment, including installing, configuring and initializing the system to ensure that the system can operate normally and meet user needs.

[0115] Based on the above embodiments and optional embodiments, the present invention proposes an optional implementation mode: Figure 5 is a schematic flow chart of an optional method for determining development costs of multiple adjustable load resources in a park according to an embodiment of the present invention, such as Figure 5 As shown, by using data analysis and simulation technology, a cost model of adjustable load resources is designed, the potential of flexible configuration of adjustable load resources is calculated, the effect of flexible configuration of adjustable load resources under different cost models is simulated and evaluated, the investment parameters and investment returns of different cost models are quantified and measured, and technical support is provided for the development space of various cost models of adjustable load resources.

[0116] Step A: Use technologies such as the Internet of Things and big data analysis to monitor the energy consumption of the park in real time and obtain the load demands for electricity, heat, cooling, etc. at different times;

[0117] Among them, in step A, according to the meteorological conditions, scale and purpose of the park and the use of equipment at different times, the cold, hot and electric load demand results of the typical user side at different times are obtained.

[0118] Step B, establish a temperature control load and electric vehicle adjustable potential calculation model to calculate the adjustable load resource potential of the park.

[0119] Wherein, step B includes: step B1, establishing a temperature control load adjustable potential calculation model, which can be used to determine the temperature control adjustable resources, and the specific form is as follows:

[0120]

[0121] Among them, T in (t) is the indoor temperature of the air conditioner at time t, ℃; τ is the simulation setting time step; η is the energy supply efficiency of the variable frequency air conditioner; a, b, c, d are the energy supply simulation parameters of the variable frequency air conditioner; T out (t) is the outdoor temperature at time t, °C; T set (t) is the set temperature of the air conditioner at time t, ℃; H is the thermal conductivity between the room where the air conditioner is located and the outdoors; E is the equivalent thermal mass of the room where the air conditioner is located.

[0122] Step B2, establish an electric vehicle adjustable potential calculation model, which can be used to calculate the adjustable resources of electric vehicles. The specific form is as follows:

[0123]

[0124] Where s(t) is the electric energy of the electric vehicle at time t, kW; η ch is the charging efficiency of electric vehicles, P E,4 ch (t) is the charging power of the electric vehicle at time t, kW; η dis is the discharge efficiency of the electric vehicle, P E,4 dis (t) is the discharge power of the electric vehicle at time t, kW; α is a 0-1 parameter, α(t) = 1 represents that the electric vehicle is in a charging state at time t, otherwise it is in a discharging state.

[0125] Step C, with the goal of minimizing the overall cost, taking into account the system investment cost and operating cost, establish a two-layer optimization model for the configuration and operation of the comprehensive energy system taking into account the adjustable load, and optimize the cost model for configuring the adjustable resources in the park;

[0126] The above step C includes: step C1, establishing a double-layer objective function. The upper layer takes minimizing investment cost as the objective function (i.e., the first objective function), and the lower layer takes minimizing operation cost as the objective function (i.e., the second objective function).

[0127]

[0128] Among them, f min,1 is the objective function of the upper model, representing the minimization of the system investment cost, element (i.e., the first objective function); f min,2is the objective function of the lower model, representing the minimization of the system's operating cost, i (i.e., the second objective function); i is the type of equipment in the system, i=1 is a gas power generation system, i=2 is an energy storage device; i=3 is a temperature-controlled variable-frequency air conditioning group; i=4 is an electric vehicle; C C,i is the unit price of investment and construction of the i-th equipment, yuan / kW; P C,i is the construction rated capacity of the i-th equipment, kW; C E,i is the unit price of the operating cost of the i-th equipment, yuan / kW; P E,i (t) is the output of the ith device at time t, kW; C g is the purchase price of natural gas, yuan / m 3 ; V g (t) is the purchase amount of natural gas at time t, m 3 .

[0129] Step C2, setting the equipment operation constraints and supply and demand balance constraints of the upper model and the lower model, the specific form is as follows:

[0130] 0≤P E,1 (t)≤P C,1

[0131] 0≤P E,2 (t)≤P C,2

[0132] 0≤P E,3 (t)≤P C,3

[0133] 0≤P E,4 (t)≤P C,4

[0134] 0≤P E,5 (t)≤P C,5

[0135] Among them, the constraint condition of the upper model, namely the first constraint condition, represents that the output of gas power generation equipment, energy storage equipment, variable frequency air conditioner and electric vehicle at time t is less than their rated capacity.

[0136]

[0137] Among them, P E,2 ch (t) is the charging capacity of the energy storage device at time t, in kW; P E,2 dis (t) is the discharge capacity of the energy storage device at time t, in kW; β is a 0-1 parameter, β(t) = 1 means that the energy storage device is in a charging state at time t, otherwise it is in a discharging state, H E(t) is the non-adjustable electric load at time t, in kW, and b is the variable frequency air conditioning energy supply simulation parameter. α is a 0-1 parameter, α(t) = 1 means that the electric vehicle is in a charging state at time t, otherwise it is in a discharging state.

[0138] V g (t)η g (t) = P E,1 (t)

[0139]

[0140] Among them, the constraint condition of the lower model, that is, the second constraint condition, η g (t) is the power generation efficiency of the gas-fired power generation equipment at time t; g(t) is the power reserve of the energy storage equipment at time t, in kW; The charging efficiency of the energy storage device; is the discharge efficiency of the energy storage device.

[0141] Step C3, coupling step B1, step B2, and step C2 to establish a double-layer operation constraint.

[0142]

[0143] λ j ≥0

[0144] Among them, L j (x,λ j ) is the double-layer operation constraint condition, h j (x) is the constraint expression, j = 1, 2, 3, 4. When j = 1, h1 is the expression of the temperature control load adjustable potential calculation model:

[0145]

[0146] When j = 1, h2 is the expression of the electric vehicle adjustable potential calculation model:

[0147]

[0148] When j=3, h3 is the expression:

[0149] V g (t)η g (t) = P E,1 (t)

[0150] When j=4, h4 is the expression:

[0151]

[0152] Among them, λ j is the Lagrangian operator.

[0153] Step C4, coupling step C1, step C2, and step C3, establishing a two-layer optimization model for the configuration and operation of the comprehensive energy system taking into account the adjustable load, and solving it to obtain the investment cost and operation cost of the comprehensive energy system covering adjustable projects such as variable frequency air conditioners and electric vehicles.

[0154] Step D, comprehensively and quantitatively evaluate the calculation results obtained by the above-mentioned adjustable potential calculation and optimization analysis method, and finally determine the optimal result of the park cost model;

[0155] Among them, step D includes: step D1, by establishing a hierarchical model, clarifying the decision-making goals, considerations (decision-making criteria) and different cost model types, dividing them into the highest level, middle level and lowest level according to their mutual relationships, and drawing a hierarchical diagram.

[0156] Step D2, construct a judgment (paired comparison) matrix, compare all factors pairwise, use the nine-scale method for comparison, and minimize the difficulty of comparing factors of different natures to improve accuracy.

[0157] Step D3, perform hierarchical single sorting and consistency test. Calculate the relative weight of the evaluation criteria and determine the weight of each indicator. Through consistency test, ensure the rationality and scientificity of the evaluation results. Ensure that the consistency ratio (CR) value of the judgment matrix is ​​less than 0.1. If it is not satisfied, the judgment matrix needs to be adjusted for consistency until the calculation results meet the following conditions.

[0158] CR=CI / RI

[0159] CI=(λ max -n)(n-1)n=1,2,3,…,9

[0160] Among them, CI is the consistency index; CR is the consistency ratio; RI is the average consistency index.

[0161] Step D4, based on the above analysis, evaluate and optimize different cost models. This method provides a detailed set of judgment basis and optimization decision-making methods in this process, fully considers the decision maker's understanding of the problem and the accuracy of the evaluation, and determines the cost model that best meets the energy demand, regulation potential and continuous optimization of the park.

[0162] Step E: construct four modules: demand setting, potential calculation, optimization analysis, and cost model evaluation, and deploy a cost model optimization system for the flexible configuration of adjustable load resources in the park.

[0163] Among them, step E includes: Step E1: Database establishment. Based on the MySQL relational database system, design data tables and views such as parameters, requirements, weather, and equipment information, design field types and storage space, ensure effective storage and efficient retrieval of data, and establish a cost model database that can adjust the flexibility of load resource configuration.

[0164] Step E2, model library packaging, based on Python language, the cost model optimization method of adjustable load resource flexibility configuration is programmed, and the model is packaged using the PyInstaller tool to make reusable computer components for easy deployment in third-party systems.

[0165] Step E3, system development and implementation, formulate the overall architecture and modular structure of the system, complete the front-end interface design and system back-end design. Use C# programming language and development tools to write and implement each module and function of the system. Perform unit testing, integration testing and system testing to verify the functions and performance of the system. Finally, deploy the system to the target environment, including installation, configuration and initialization of the system to ensure that the system can operate normally and meet user needs.

[0166] Figure 6 is a visual schematic diagram of an optional method for determining the development cost of multiple adjustable load resources in a park provided according to an embodiment of the present invention, such as Figure 6 As shown, different cost models can be used according to needs, and a variety of optional visualization methods can be used for intuitive comparison. The cost models include CHP model, CHP and energy storage battery combination model, CHP, electric boiler and heat storage tank combination model, CHP, electric boiler, heat storage tank and energy storage battery combination model.

[0167] The above optional implementation method can at least achieve the following effects: using the Internet of Things, big data analysis and other technical means to monitor energy consumption in real time and obtain the load demand of electricity, heat, cold and other loads at different times in the park; secondly, establish a temperature control load and electric vehicle adjustable potential calculation model to realize the calculation of the adjustable load resource potential of the park; next, with the lowest comprehensive cost as the goal, considering the system investment cost and operation cost, establish a comprehensive energy system configuration operation double-layer optimization model taking into account the adjustable load, and optimize the cost model of the adjustable resources in the park; then, establish an evaluation index system based on the AHP (Analytic Hierarchy Process) method to evaluate and optimize different cost models; finally, construct four modules of demand setting, potential calculation, optimization analysis and cost model evaluation, and deploy a cost model optimization system for the flexible configuration of adjustable load resources in the park. This method can quantitatively evaluate the supporting role of the adjustable potential of the park's load resources for the optimization of the cost model, and provide technical support for the construction of an adjustable load resource library in the park and the promotion of demand-side response.

[0168] It should be noted that the steps shown in the flowcharts of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and that, although a logical order is shown in the flowcharts, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0169] In this embodiment, a device for determining the development cost of multiple adjustable load resources in a park is also provided, and the device is used to implement the above-mentioned embodiments and preferred implementation modes, and the descriptions that have been made will not be repeated. As used below, the terms "module" and "device" can implement a combination of software and / or hardware for a predetermined function. Although the devices described in the following embodiments are preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.

[0170] According to an embodiment of the present invention, there is also provided an apparatus embodiment for implementing a method for determining development costs of multiple adjustable load resources in a park. Figure 7 is a schematic diagram of a device for determining development costs of multiple adjustable load resources in a park according to an embodiment of the present invention, such as Figure 7 As shown, the development cost determination device for the above-mentioned multiple adjustable load resources in the park includes: a load demand acquisition module 702, a cost demand calculation module 704, and a target mode confirmation module 706. The device is described below.

[0171] The load demand acquisition module 702 is used to acquire the current load demands corresponding to the various adjustable load resources in the target park;

[0172] The cost demand calculation module 704 is connected to the load demand acquisition module 702, and is used to process the current load demands corresponding to the multiple adjustable load resources using the target model to obtain the cost demands corresponding to the multiple predetermined candidate cost modes, wherein the multiple candidate cost modes are different modes obtained based on the multiple adjustable load resources, and the target model is generated based on the historical load demands corresponding to the multiple adjustable load resources in the target park;

[0173] The target mode confirmation module 706 is connected to the cost requirement calculation module 704, and is used to determine the target mode applied in the target park in response to the decision-making requirements based on the cost requirements corresponding to the multiple candidate cost modes.

[0174] In a development cost determination device for multiple adjustable load resources in a park provided by an embodiment of the present invention, a load demand acquisition module 702 is used to obtain the current load demand corresponding to the multiple adjustable load resources in the target park; a cost demand calculation module 704 is connected to the load demand acquisition module 702, and is used to process the current load demand corresponding to the multiple adjustable load resources using a target model to obtain the cost demand corresponding to the predetermined multiple candidate cost modes, wherein the multiple candidate cost modes are different modes obtained based on the multiple adjustable load resources, and the target model is generated based on the historical load demand corresponding to the multiple adjustable load resources in the target park; a target mode confirmation module 706 is connected to the cost demand calculation module 704, and is used to respond to the decision-making requirements and determine the target mode applied in the target park based on the cost demand corresponding to the multiple candidate cost modes. The purpose of reasonably configuring the cost mode of the adjustable load resources is achieved, and the technical effect of improving the efficiency of the target mode is achieved, thereby solving the technical problem of unsatisfactory cost mode configuration efficiency of the adjustable load resources in the related technology.

[0175] It should be noted that the above modules can be implemented by software or hardware. For example, for the latter, it can be implemented in the following ways: the above modules can be located in the same processor; or the above modules can be located in different processors in any combination.

[0176] It should be noted that the load demand acquisition module 702, the cost demand calculation module 704, and the target mode confirmation module 706 correspond to steps S102 to S106 in the embodiment, and the examples and application scenarios implemented by the modules and the corresponding steps are the same, but are not limited to the contents disclosed in the above embodiment. It should be noted that the modules as part of the device can be run in a computer terminal.

[0177] It should be noted that the optional or preferred implementation of this embodiment can refer to the relevant description in the embodiment, which will not be repeated here.

[0178] The above-mentioned development cost determination device for multiple adjustable load resources in the park may also include a processor and a memory. The load demand acquisition module 702, the cost demand calculation module 704, the target mode confirmation module 706, etc. are all stored in the memory as program units, and the processor executes the above-mentioned program units stored in the memory to realize the corresponding functions.

[0179] The processor includes a kernel, which retrieves the corresponding program unit from the memory. There can be one or more kernels. The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM, and the memory includes at least one storage chip.

[0180] An embodiment of the present invention provides a non-volatile storage medium on which a program is stored. When the program is executed by a processor, a cost model method for adjustable load resources is implemented.

[0181] An embodiment of the present invention provides an electronic device, which includes a processor, a memory, and a program stored in the memory and executable on the processor. When the processor executes the program, the following steps are implemented: obtaining current load demands corresponding to a plurality of adjustable load resources in a target park; based on the current load demands corresponding to a plurality of adjustable load resources, processing using a target model to obtain cost demands corresponding to a plurality of predetermined candidate cost modes, wherein the plurality of candidate cost modes are different modes obtained based on a plurality of adjustable load resources, and the target model is generated based on historical load demands corresponding to a plurality of adjustable load resources in the target park; in response to decision requirements, determining a target mode applied in the target park based on the cost demands corresponding to a plurality of candidate cost modes. The device in this article may be a server, a PC, etc.

[0182] The present invention also provides a computer program product, which, when executed on a data processing device, is suitable for executing a program that initializes the following method steps: obtaining current load demands corresponding to a variety of adjustable load resources in a target park; based on the current load demands corresponding to a variety of adjustable load resources, processing using a target model to obtain cost demands corresponding to a predetermined variety of candidate cost models, wherein the variety of candidate cost models are different models obtained based on a variety of adjustable load resources, and the target model is generated based on historical load demands corresponding to a variety of adjustable load resources in the target park; in response to decision-making needs, determining the target model to be applied in the target park based on the cost demands corresponding to a variety of candidate cost models.

[0183] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0184] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0185] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0186] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process in the computer or other programmable device. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0187] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0188] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.

[0189] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.

[0190] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0191] It will be appreciated by those skilled in the art that embodiments of the present invention may be provided as methods, systems or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.

[0192] The above are only embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent substitution, improvement, etc. made within the spirit and principle of the present invention should be included in the scope of the claims of the present invention.

Claims

1. A method for determining the development cost of multiple adjustable load resources in a park, characterized in that: include: Obtain the current load demands corresponding to various adjustable load resources in the target park; Based on the current load demands respectively corresponding to the multiple adjustable load resources, a target model is used for processing to obtain cost demands respectively corresponding to the predetermined multiple candidate cost modes, wherein the multiple candidate cost modes are different modes obtained based on the multiple adjustable load resources, and the target model is generated based on the historical load demands respectively corresponding to the multiple adjustable load resources in the target park; In response to the decision-making requirements, a target model applied in the target park is determined based on the cost requirements respectively corresponding to the multiple candidate cost models.

2. The method according to claim 1, characterized in that: The obtaining of current load demands corresponding to the various adjustable load resources in the target park includes: Determine the temperature control load demand and power load demand of the target park based on the park scale, park application type, and current meteorological information of the target park; According to the temperature control load demand and the power load demand, the current load demand is determined by adopting the Internet of Things method and / or data analysis method.

3. The method according to claim 1, characterized in that The method further comprises: Determining a first objective function based on the construction unit costs and rated capacities respectively corresponding to the plurality of adjustable load resources; Determine a second objective function based on the operating unit costs, outputs and resource usages respectively corresponding to the multiple adjustable load resources, wherein the first objective function and the second objective function are respectively used to obtain minimization values ​​of different types of costs; The target model is generated based on the first target function and the second target function.

4. The method according to claim 3, characterized in that The method further includes: determining an operation constraint based on that the processing amounts respectively corresponding to the plurality of adjustable load resources are less than the rated capacity; Determine supply and demand constraints based on the current total adjustable load and the current non-adjustable electric load; Based on the operation constraint and the supply and demand constraint, a first constraint condition is obtained; The current load demands corresponding to the multiple adjustable load resources are processed by using a target model to obtain cost demands corresponding to the multiple predetermined candidate cost modes, including: Based on the current load demands respectively corresponding to the multiple adjustable load resources, the first objective function included in the target model is used for processing to obtain a minimized value of the first objective function that satisfies the first constraint condition as a first cost minimization value; Based on the first cost minimization value, cost requirements respectively corresponding to the multiple candidate cost modes are obtained.

5. The method according to claim 4, characterized in that The multiple adjustable load resources include: air conditioning equipment and electric vehicles. The current load demands corresponding to the multiple adjustable load resources are processed using a target model to obtain cost demands corresponding to the multiple predetermined candidate cost modes, including: Determining temperature control adjustable resources based on the current load demand corresponding to the air conditioning equipment; Determining adjustable resources for the electric vehicle based on a current load demand corresponding to the electric vehicle; Based on the temperature control adjustable resources and the electric vehicle adjustable resources, the current total adjustable load is obtained.

6. The method according to claim 3, characterized in that The method further includes: determining a gas power generation constraint based on power generation efficiency and resource usage of gas power generation equipment included in the plurality of adjustable load resources; Determining energy storage constraints based on the power reserves and charging and discharging efficiencies of energy storage devices included in the plurality of adjustable load resources; According to the gas power generation constraint and the energy storage constraint, a second constraint condition is obtained; The current load demands corresponding to the multiple adjustable load resources are processed by using a target model to obtain cost demands corresponding to the multiple predetermined candidate cost modes, including: Based on the current load demands respectively corresponding to the multiple adjustable load resources, a second objective function included in the target model is used for processing to obtain a minimized value of the second objective function that satisfies the second constraint condition as a second cost minimization value; Based on the second cost minimization value, cost requirements respectively corresponding to the multiple candidate cost modes are obtained.

7. The method according to claim 1, characterized in that The decision requirement includes a decision target and a decision criterion. The response to the decision requirement, based on the cost requirements respectively corresponding to the multiple candidate cost models, determines the target cost model in the target park, including: Using the analytic hierarchy process, based on the decision goal, the decision criterion, and the multiple candidate cost models, determining evaluation indicators of the multiple candidate cost models; Based on the evaluation indicators of the multiple candidate cost models and the cost requirements respectively corresponding to the multiple candidate cost models, a target cost model in the target park is determined.

8. A method and device for determining the development cost of multiple adjustable load resources in a park, characterized in that: include: A load demand acquisition module obtains the current load demands corresponding to various adjustable load resources in the target park; A cost demand calculation module, based on the current load demands respectively corresponding to the multiple adjustable load resources, uses a target model for processing to obtain cost demands respectively corresponding to the multiple predetermined candidate cost modes, wherein the multiple candidate cost modes are different modes obtained based on the multiple adjustable load resources, and the target model is generated based on the historical load demands respectively corresponding to the multiple adjustable load resources in the target park; The target mode confirmation module determines the target mode applied in the target park in response to the decision-making requirements and based on the cost requirements respectively corresponding to the multiple candidate cost modes.

9. A non-volatile storage medium, characterized in that: The non-volatile storage medium stores a plurality of instructions, and the instructions are suitable for being loaded by a processor and executing the method for determining the development cost of multiple adjustable load resources in a park as described in any one of claims 1 to 7.

10. An electronic device, characterized in that: include: One or more processors and a memory, wherein the memory is used to store one or more programs, wherein when the one or more programs are executed by the one or more processors, the one or more processors implement the method for determining the development cost of multiple adjustable load resources in a park as described in any one of claims 1 to 7.