Power grid risk-based automatic inspection system, inspection method and power system

Through the automatic inspection system, the intelligent operation and maintenance main station and related main stations allocate inspection tasks, and the intelligent equipment is used to conduct automatic inspection of power grid equipment, solving the problem of low efficiency of power grid risk inspection in the existing technology and achieving high efficiency , reliable power grid operation and maintenance.

CN119031007AActive Publication Date: 2024-11-26GUANGDONG POWER GRID CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411131048.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-26
Estimated Expiration
2044-08-16

AI Technical Summary

Technical Problem

In the prior art, the inspection of power grid risks relies on manual operations, is inefficient and cannot respond quickly, and cannot meet the needs of modern power grids for high efficiency and high reliability operation and maintenance.

Method used

An automatic inspection system based on power grid risks was designed, including intelligent operation and maintenance main station, power grid dispatching and operation management main station, production monitoring main station, Baoxin main station and OCS automation main station, and the power grid is released through the power grid dispatching and operation management main station. Risk, the intelligent operation and maintenance main station generates inspection and dispatch information based on the power grid risks, and dispatches inspection tasks to the production monitoring main station, Baoxin main station and OCS automation main station, and uses intelligent cameras, drones and inspection robots to conduct automatic inspections. , and generate inspection reports.

Benefits of technology

Automatic inspection of power grid equipment is realized, the efficiency from discovering power grid risks to completing inspections is improved, manual intervention is reduced, and the unity and efficiency of operation and maintenance quality is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119031007A_ABST
    Figure CN119031007A_ABST
Patent Text Reader

Abstract

The invention provides an automatic inspection system and method based on power grid risks and a power system, and the system comprises an intelligent operation and maintenance master station which is used for receiving the power grid operation risks, sending target inspection scheduling information, and receiving an inspection report; the power grid dispatching operation management master station is used for generating power grid operation risks according to the power grid operation parameters and sending the power grid operation risks to the intelligent operation and maintenance master station; the production monitoring master station is used for inspecting the primary equipment through the inspection equipment to obtain an inspection report; the intelligent operation and maintenance client is used for controlling the intelligent operation and maintenance master station to send target inspection scheduling information and visually displaying an inspection report; the protection information master station is used for receiving real-time operation information and historical operation information of the protection device of the primary equipment; and the OCS automatic master station is used for receiving the real-time monitoring information and the historical monitoring information of the measurement and control device. The system solves the problem that in the prior art, manual operation and maintenance are carried out, and the efficiency from power grid risk discovery to routing inspection completion is low.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of automatic inspection technology, and in particular to an automatic inspection system based on power grid risk, an inspection method, a computer-readable storage medium, a processor and a power system. Background Art

[0002] In the process of power grid operation and maintenance, monitoring and risk management of safe power grid operation are extremely important. Traditionally, the release of power grid risk information and the inspection and maintenance of equipment often rely on manual operation and management, which is not only inefficient, but also easily affected by human factors, resulting in a lack of standardization and uniformity in operation and maintenance. Especially when the operation mode of the power grid changes and power grid risks arise, the existing manual work order inspection mode cannot quickly respond to and cover all risk-related primary and secondary equipment, and it is difficult to meet the needs of modern power grids for high-efficiency and high-reliability operation and maintenance.

[0003] In the existing technology, after receiving the grid risk notification, the operation and maintenance personnel need to manually sort out the primary and secondary equipment involved, and then the station manager arranges personnel to conduct inspections by dispatching work orders. In this mode, there is a long time delay from the release of risk information to the actual inspection and maintenance, and due to the intervention of human factors, the operation and maintenance quality varies, and it is impossible to ensure that every link can be strictly implemented in accordance with the prescribed standards. Summary of the invention

[0004] The main purpose of this application is to provide an automatic inspection system, inspection method, computer-readable storage medium, processor and power system based on power grid risk, so as to at least solve the problem of low efficiency in the prior art of manual operation and maintenance, from discovering power grid risks to completing inspections.

[0005] In order to achieve the above-mentioned purpose, according to one aspect of the present application, an automatic inspection system based on power grid risk is provided, including: an intelligent operation and maintenance main station, used to receive the power grid operation risk sent by the power grid dispatching and operation management main station and send target inspection scheduling information based on the power grid operation risk, and receive the inspection report and send it to the intelligent operation and maintenance client, the target inspection scheduling information includes one or more of the first inspection scheduling information, the second inspection scheduling information and the third inspection scheduling information, the first inspection scheduling information is used to instruct the production monitoring main station to perform inspection, the second inspection scheduling information is used to instruct the security main station to perform inspection, and the third inspection information is used to instruct the OCS main station to perform inspection; the power grid dispatching and operation management main station is deployed in the office intranet, and is communicated with the intelligent operation and maintenance main station through a firewall and a forward / reverse isolation device. The power grid dispatching and operation management main station is used to generate the power grid operation risk according to the power grid operation parameters and send it to the intelligent operation and maintenance main station; the production monitoring The control master station is communicatively connected with the intelligent operation and maintenance master station through the firewall and the forward / reverse isolation device. The production monitoring master station is used to inspect the primary equipment through the inspection equipment to obtain the inspection report. The inspection equipment at least includes an intelligent camera, a drone and an inspection robot; the intelligent operation and maintenance client is communicatively connected with the intelligent operation and maintenance master station through the firewall and the forward / reverse isolation device. The intelligent operation and maintenance client is used to control the intelligent operation and maintenance master station to send the target inspection scheduling information and to visualize the inspection report; the security master station is communicatively connected with the intelligent operation and maintenance master station. The security master station is used to receive the real-time operation information and historical operation information of the protection device of the primary equipment and generate the inspection report; the OCS automation master station is communicatively connected with the intelligent operation and maintenance master station. The OCS automation master station is used to receive the real-time monitoring information and historical monitoring information of the measurement and control device and generate the inspection report.

[0006] Optionally, the automatic inspection system also includes: an intelligent recorder, which is communicatively connected to the security main station and the protection device, and the intelligent recorder is used to receive the data scheduling information issued by the security main station and forward it to the protection device, and to receive the real-time operation information and the historical operation information uploaded by the protection device and forward them to the security main station.

[0007] Optionally, the automatic inspection system also includes: a motion machine, which is communicatively connected to the OCS automation master station and the measurement and control device, and is used to receive the data scheduling information issued by the OCS automation master station and forward it to the measurement and control device, as well as receive the real-time monitoring information and the historical monitoring information uploaded by the measurement and control device, and forward it to the OCS automation master station.

[0008] Optionally, the motion machine realizes real-time communication transmission with the OCS automation master station through a communication network, and the intelligent recorder realizes real-time communication transmission with the security master station through a communication network.

[0009] According to another aspect of the present application, there is provided an automatic inspection method based on power grid risk, the method being used to control the automatic inspection system, the method comprising: controlling the power grid dispatching and operation management main station to determine the target device according to the power grid operation parameters, generating the power grid operation risk at least according to the target device, and sending it to the intelligent operation and maintenance main station, the target device being the primary device or secondary device with abnormal operation parameters; controlling the intelligent operation and maintenance main station to perform analysis according to the power grid operation and maintenance risk to obtain the target device, generating the target inspection scheduling information at least according to the target device, and sending it to the production monitoring main station or the security main station and the OCS automation main station; when the target inspection scheduling information is sent to the production monitoring main station, controlling the production monitoring main station to generate the target inspection scheduling information according to the target inspection scheduling information The target equipment is inspected by the inspection equipment and an inspection report is generated and sent to the intelligent operation and maintenance main station; when the target inspection scheduling information is sent to the Baoxin main station and the OCS automation main station, the Baoxin main station obtains the real-time operation information and the historical operation information through the intelligent recorder according to the corresponding target inspection scheduling information, generates the inspection report and sends it to the intelligent operation and maintenance main station, and the OCS automation main station obtains the real-time monitoring information and the historical monitoring information through the motion machine according to the corresponding target inspection scheduling information, generates the inspection report and sends it to the intelligent operation and maintenance main station; when the inspection report is received, the intelligent operation and maintenance main station is controlled to generate an early warning report according to the inspection report and send it to the intelligent operation and maintenance client for visual display.

[0010] Optionally, the method also includes: upon receiving the inspection start information sent by the intelligent operation and maintenance client, controlling the intelligent operation and maintenance master station to generate the target inspection scheduling information and send it to the production monitoring master station or the security master station and the OCS automation master station.

[0011] Optionally, generating target inspection scheduling information based on at least the target device and sending it to the production monitoring master station or the security control master station and the OCS automation master station includes: determining a target device tree based on the target device, the target device tree being a hierarchical ledger system according to the affiliation of the target device; determining the corresponding primary device based on the target device tree, and determining the corresponding secondary device based on the primary device; generating a primary equipment inspection list based on the primary equipment, generating the target inspection scheduling information based on the primary equipment inspection list and sending it to the production monitoring master station; generating a secondary equipment inspection list based on the secondary equipment, generating the target inspection scheduling information based on the secondary equipment inspection list and sending it to the security control master station and the OCS automation master station.

[0012] Optionally, controlling the intelligent operation and maintenance main station to generate an early warning report according to the inspection report includes: determining a corresponding target threshold based on historical data in the inspection report, the target threshold being a parameter threshold for normal operation of the corresponding primary equipment or the secondary equipment, and the historical data including historical operation information of the primary equipment and the historical operation information and historical monitoring information corresponding to the secondary equipment; determining abnormal data based on matching the real-time data in the inspection report with the corresponding target threshold, the real-time data being the real-time operation information of the primary equipment and the real-time operation information and real-time monitoring information corresponding to the secondary equipment; determining the equipment defect level corresponding to the corresponding primary equipment or the secondary equipment according to the abnormal data to obtain the early warning report.

[0013] According to another aspect of the present application, a computer-readable storage medium is provided, wherein the computer-readable storage medium includes a stored program, wherein when the program is executed, the device where the computer-readable storage medium is located is controlled to execute any one of the methods described.

[0014] According to another aspect of the present application, there is provided a power system, comprising: one or more processors, a memory, and one or more programs, wherein the one or more programs are stored in the memory and are configured to be executed by the one or more processors, and the one or more programs include methods for executing any one of the described methods.

[0015] Applying the technical solution of the present application, the above-mentioned automatic inspection system based on power grid risk includes: an intelligent operation and maintenance main station, which is used to receive the power grid operation risk sent by the power grid dispatching and operation management main station and send target inspection dispatching information based on the above-mentioned power grid operation risk, and receive the inspection report and send it to the intelligent operation and maintenance client, the above-mentioned target inspection dispatching information includes one or more of the first inspection dispatching information, the second inspection dispatching information and the third inspection dispatching information, the above-mentioned first inspection dispatching information is used to instruct the production monitoring main station to perform inspection, the above-mentioned second inspection dispatching information is used to instruct the security main station to perform inspection, and the above-mentioned third inspection information is used to instruct the OCS main station to perform inspection; the above-mentioned power grid dispatching and operation management main station is deployed in the office intranet, and is communicated with the above-mentioned intelligent operation and maintenance main station through a firewall and a forward / reverse isolation device. The above-mentioned power grid dispatching and operation management main station is used to generate the above-mentioned power grid operation risk according to the power grid operation parameters and send it to the above-mentioned intelligent operation and maintenance main station; the above-mentioned production monitoring main station, through The above-mentioned production monitoring main station is connected to the above-mentioned intelligent operation and maintenance main station through the above-mentioned firewall, the above-mentioned forward / reverse isolation device, and is used to inspect the primary equipment through the inspection equipment to obtain the above-mentioned inspection report. The above-mentioned inspection equipment at least includes an intelligent camera, a drone and an inspection robot; the above-mentioned intelligent operation and maintenance client is connected to the above-mentioned intelligent operation and maintenance main station through the above-mentioned firewall, the above-mentioned forward / reverse isolation device, and is used to control the above-mentioned intelligent operation and maintenance main station to send the above-mentioned target inspection scheduling information and to visualize the above-mentioned inspection report; the above-mentioned security main station is connected to the above-mentioned intelligent operation and maintenance main station, and the above-mentioned security main station is used to receive the real-time operation information and historical operation information of the protection device of the above-mentioned primary equipment, and generate the above-mentioned inspection report; the above-mentioned OCS automation main station is connected to the above-mentioned intelligent operation and maintenance main station, and the above-mentioned OCS automation main station is used to receive the real-time monitoring information and historical monitoring information of the measurement and control device, and generate the above-mentioned inspection report. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 A schematic diagram of a process of an automatic inspection system based on power grid risk provided according to an embodiment of the present application is shown;

[0017] Figure 2 A flow chart of an automatic inspection method based on power grid risk provided according to an embodiment of the present application is shown. DETAILED DESCRIPTION

[0018] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0019] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.

[0020] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0021] As introduced in the background technology, in the prior art, after a grid risk is identified, grid risk information is manually sent, and inspection arrangements are made by dispatching orders step by step, which is inefficient, has high labor costs, and has differentiated operation and maintenance quality. In order to solve the problem of low efficiency in manual operation and maintenance, from discovering grid risks to completing inspections, the embodiments of the present application provide an automatic inspection system, inspection method, computer-readable storage medium, processor, and power system based on grid risks.

[0022] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0023] Figure 1 FIG. 1 is a flow chart of an automatic inspection system based on power grid risk according to an embodiment of the present application. Figure 1 As shown, the system includes:

[0024] The intelligent operation and maintenance master station is used to receive the power grid operation risk sent by the power grid dispatching and operation management master station and send the target inspection and scheduling information based on the above power grid operation risk, and receive the inspection report and send it to the intelligent operation and maintenance client. The above target inspection and scheduling information includes one or more of the first inspection and scheduling information, the second inspection and scheduling information and the third inspection and scheduling information. The first inspection and scheduling information is used to instruct the production monitoring master station to conduct inspections, the second inspection and scheduling information is used to instruct the security master station to conduct inspections, and the third inspection and scheduling information is used to instruct the OCS master station to conduct inspections;

[0025] Specifically, the intelligent operation and maintenance master station refers to a central system that conducts coordinated inspections of various master stations. It can automatically determine the primary and secondary equipment involved in the inspection based on the power grid risks released by the OMS master station, thereby dispatching inspection tasks and processing results. The method is to publish the power grid risks through the OMS master station, transmit them to the intelligent operation and maintenance master station via the network transmission medium, and then the intelligent operation and maintenance master station identifies the primary and secondary equipment specifically involved in the power grid risks, and forms a primary and secondary equipment inspection list. Specifically, the intelligent operation and maintenance master station confirms the corresponding equipment tree according to the name of the power grid equipment such as transmission lines, substations, and user equipment involved in the power grid risks released by the OMS master station, and then confirms the terminal contact equipment of the equipment tree to the lower level, and then generates one or more of the above-mentioned first inspection scheduling information, second inspection scheduling information, and third inspection scheduling information according to the equipment that needs to be inspected.

[0026] The above-mentioned power grid dispatching operation management master station is deployed in the office intranet, and is connected to the above-mentioned intelligent operation and maintenance master station through a firewall and a forward / reverse isolation device. The above-mentioned power grid dispatching operation management master station is used to generate the above-mentioned power grid operation risk according to the power grid operation parameters and send it to the above-mentioned intelligent operation and maintenance master station;

[0027] Specifically, the OMS master station refers to the power grid dispatching and operation management master station, which is deployed in the power grid office intranet. The role of this system is to publish power grid operation risks, connect with the intelligent operation and maintenance master station server through a firewall, and realize the automatic and rapid flow of power grid operation risk information.

[0028] The production monitoring master station is connected to the intelligent operation and maintenance master station through the firewall and the forward / reverse isolation device. The production monitoring master station is used to inspect the primary equipment through inspection equipment to obtain the inspection report. The inspection equipment includes at least an intelligent camera, a drone and an inspection robot.

[0029] Specifically, the production monitoring master station is used to remotely control drones, smart cameras and patrol robots to conduct automatic patrols, receive and process patrol photos and results sent back for archiving, and provide the results of a single equipment patrol involving power grid risks.

[0030] The intelligent operation and maintenance client is connected to the intelligent operation and maintenance main station through the firewall and the forward / reverse isolation device. The intelligent operation and maintenance client is used to control the intelligent operation and maintenance main station to send the target inspection scheduling information and to visualize the inspection report;

[0031] Specifically, the intelligent operation and maintenance user end can issue patrol commands to the intelligent operation and maintenance system through the firewall, forward / reverse isolation device and the intelligent operation and maintenance main station, and at the same time receive automatic patrol results to provide users with visual reading of patrol information.

[0032] The above-mentioned security master station is connected to the above-mentioned intelligent operation and maintenance master station in communication, and the above-mentioned security master station is used to receive the real-time operation information and historical operation information of the protection device of the above-mentioned primary equipment, and generate the above-mentioned inspection report;

[0033] Specifically, the Baoxin master station refers to the receiving system for information sent by the substation-end protection device. The Baoxin master station can autonomously call and record the real-time and historical information of the station-end protection device. The station-end protection device sends information to the Baoxin master station via the intelligent recorder.

[0034] The above-mentioned OCS automation master station is communicatively connected with the above-mentioned intelligent operation and maintenance master station. The above-mentioned OCS automation master station is used to receive real-time monitoring information and historical monitoring information of the measurement and control device, and generate the above-mentioned inspection report.

[0035] Specifically, the OCS automation master station refers to the receiving system for information sent by the measurement and control device at the substation end. The OCS master station can receive and record real-time information and historical information sent by the remote motor. The station-end measurement and control device sends information to the OCS automation master station via the remote motor.

[0036] Applying the technical solution of the present application, in the above-mentioned automatic inspection system based on power grid risk, the intelligent operation and maintenance main station is used to receive the power grid operation risk sent by the power grid dispatching and operation management main station and send the target inspection dispatching information based on the above-mentioned power grid operation risk, as well as receive the inspection report and send it to the intelligent operation and maintenance client, the above-mentioned target inspection dispatching information includes one or more of the first inspection dispatching information, the second inspection dispatching information and the third inspection dispatching information, the above-mentioned first inspection dispatching information is used to instruct the production monitoring main station to perform inspection, the above-mentioned second inspection dispatching information is used to instruct the security main station to perform inspection, and the above-mentioned third inspection information is used to instruct the OCS main station to perform inspection; the above-mentioned power grid dispatching and operation management main station is deployed in the office intranet, and is communicated with the above-mentioned intelligent operation and maintenance main station through a firewall and a forward / reverse isolation device. The above-mentioned power grid dispatching and operation management main station is used to generate the above-mentioned power grid operation risk according to the power grid operation parameters and send it to the above-mentioned intelligent operation and maintenance main station; the above-mentioned production monitoring main station, through The above-mentioned production monitoring main station is connected to the above-mentioned intelligent operation and maintenance main station through the above-mentioned firewall, the above-mentioned forward / reverse isolation device, and is used to inspect the primary equipment through the inspection equipment to obtain the above-mentioned inspection report. The above-mentioned inspection equipment at least includes an intelligent camera, a drone and an inspection robot; the above-mentioned intelligent operation and maintenance client is connected to the above-mentioned intelligent operation and maintenance main station through the above-mentioned firewall, the above-mentioned forward / reverse isolation device, and is used to control the above-mentioned intelligent operation and maintenance main station to send the above-mentioned target inspection scheduling information and to visualize the above-mentioned inspection report; the above-mentioned security main station is connected to the above-mentioned intelligent operation and maintenance main station, and the above-mentioned security main station is used to receive the real-time operation information and historical operation information of the protection device of the above-mentioned primary equipment, and generate the above-mentioned inspection report; the above-mentioned OCS automation main station is connected to the above-mentioned intelligent operation and maintenance main station, and the above-mentioned OCS automation main station is used to receive the real-time monitoring information and historical monitoring information of the measurement and control device, and generate the above-mentioned inspection report. The present application proposes an automatic inspection system, including an intelligent operation and maintenance main station, a power grid dispatching and operation management main station, a production monitoring main station, an intelligent operation and maintenance client, a security main station and an OCS automation main station. The power grid dispatching and operation management main station publishes power grid risks according to the power grid operation status, and the intelligent operation and maintenance main station performs dispatching according to the power grid risks, so that the production monitoring main station or the security main station and the OCS automation main station perform primary equipment or secondary equipment inspections, obtain corresponding inspection results and send them to the client for visual display. This method realizes the automatic inspection of primary and secondary equipment, and solves the problem of low efficiency in the prior art from discovering power grid risks to completing inspections through manual operation and maintenance.

[0037] In an embodiment of the present application, the above-mentioned automatic inspection system further includes:

[0038] An intelligent recorder is communicatively connected to the above-mentioned security main station and the above-mentioned protection device. The above-mentioned intelligent recorder is used to receive the data scheduling information issued by the above-mentioned security main station and forward it to the above-mentioned protection device, and to receive the above-mentioned real-time operation information and the above-mentioned historical operation information uploaded by the above-mentioned protection device and forward them to the above-mentioned security main station.

[0039] In an embodiment of the present application, the above-mentioned automatic inspection system further includes:

[0040] The motion machine is communicatively connected with the above-mentioned OCS automation master station and the above-mentioned measurement and control device. The above-mentioned motion machine is used to receive the data scheduling information issued by the above-mentioned OCS automation master station and forward it to the above-mentioned measurement and control device, as well as receive the above-mentioned real-time monitoring information and the above-mentioned historical monitoring information uploaded by the above-mentioned measurement and control device, and forward them to the above-mentioned OCS automation master station.

[0041] In an embodiment of the present application, the above-mentioned sports machine realizes real-time communication transmission with the above-mentioned OCS automation master station through a communication network, and the above-mentioned intelligent recorder realizes real-time communication transmission with the above-mentioned security master station through a communication network.

[0042] like Figure 2 As shown, an embodiment of the present invention provides an automatic inspection method based on power grid risk, which is used to control the above automatic inspection system. The above method includes:

[0043] Step S301, controlling the grid dispatching operation management master station to determine the target equipment according to the grid operation parameters, generating the grid operation risk at least according to the target equipment, and sending it to the intelligent operation and maintenance master station, wherein the target equipment is the primary equipment or secondary equipment with abnormal operation parameters;

[0044] Specifically, the method is responsible for publishing power grid risks through the OMS master station and transmitting them to the intelligent operation and maintenance master station via network transmission media.

[0045] Step S302, controlling the intelligent operation and maintenance master station to analyze the power grid operation and maintenance risks, obtain the target equipment, and generate target inspection and scheduling information based on at least the target equipment and send it to the production monitoring master station or the security master station and the OCS automation master station;

[0046] Specifically, the intelligent operation and maintenance master station identifies the primary and secondary equipment involved in the grid risk and forms a primary and secondary equipment inspection list. The intelligent operation and maintenance master station confirms the corresponding equipment tree according to the name of the grid equipment, based on the transmission lines, substations, user equipment and other grid equipment involved in the grid risk released by the OMS master station, and then confirms the terminal contact equipment of the equipment tree to the lower level.

[0047] It can be understood that the above-mentioned equipment tree refers to a ledger system in which equipment is hierarchical according to its affiliation, and is composed of transmission equipment, substation equipment, etc. The lower-level terminals correspond to specific transmission line cables, overhead lines, poles and towers, transformers, switches, circuit breakers, busbars and their corresponding secondary protection and measurement and control equipment of substations.

[0048] Step S303, when the target inspection scheduling information is sent to the production monitoring main station, control the production monitoring main station to inspect the target equipment through the inspection equipment according to the target inspection scheduling information and generate an inspection report and send it to the intelligent operation and maintenance main station;

[0049] Specifically, a device inspection list is sent to the production monitoring main station to conduct a device inspection. After receiving the inspection list, the production monitoring main station issues inspection tasks to the smart cameras, drones, and inspection robots to which the site or equipment belongs. An equipment inspection is conducted and an inspection report is sent back. Smart cameras, drones, and inspection robots conduct an equipment inspection autonomously according to the inspection tasks, and then summarize the equipment inspection situation and send it back to the smart operation and maintenance main station.

[0050] In one embodiment, the inspection items include but are not limited to the following items:

[0051] 1. Equipment temperature, real-time temperature, ABC three-phase temperature difference, historical temperature difference, local temperature difference, etc.; 2. Equipment meter conditions, SF6 pressure, oil level, oil pressure, arrester leakage current, etc.; 3. Equipment appearance, dirt, cracks, discharge marks, oil leakage of lines, poles, towers, switches, knife switches, transformers, insulators, cable heads, etc.; 4. GIS equipment partial discharge online monitoring data; 5. Temperature and humidity of the auxiliary box of outdoor equipment.

[0052] Step S304, when the target inspection scheduling information is sent to the Baoxin master station and the OCS automation master station, the Baoxin master station obtains the real-time operation information and the historical operation information through the intelligent recorder according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station, and the OCS automation master station obtains the real-time monitoring information and the historical monitoring information through the motion machine according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station;

[0053] Specifically, the secondary equipment is inspected and the inspection report is sent back. The Baoxin main station and the OCS automation main station issue tasks to independently carry out secondary equipment inspections based on the inspection list, and then summarize the inspection results of the secondary equipment and send them back to the intelligent operation and maintenance main station.

[0054] In one embodiment, the inspection items include but are not limited to the following items:

[0055] 1. Protection device information; 2. Substation automation information;

[0056] The above protection device information includes protection communication status, correctness of set value equipment, correctness of pressure plate insertion and withdrawal, real-time alarm and historical alarm records for one week, analog quantity, input quantity, waveform recording, etc.

[0057] The above substation automation information includes equipment load data, equipment switching quantity, equipment real-time and historical one-week alarm signals, substation equipment communication conditions, etc.

[0058] Step S305, when receiving the inspection report, control the intelligent operation and maintenance main station to generate an early warning report according to the inspection report and send it to the intelligent operation and maintenance client for visual display.

[0059] Specifically, the intelligent operation and maintenance master station summarizes the first and second equipment inspection reports, analyzes and publishes them. The intelligent operation and maintenance master station analyzes the abnormal data in the inspection report, determines the equipment defect level to which the abnormal data belongs and records it in the inspection results. For normal data, the inspection results are recorded as normal, and then archived and published to the intelligent operation and maintenance user terminal and Elink office system to inform the operation and maintenance responsible persons at all levels.

[0060] It can be understood that the Elink office system refers to a power grid-specific office information transmission system, which is used by operation and maintenance personnel to interactively confirm inspection results online. At the same time, the system automatically publishes the inspection results to the operation and maintenance personnel in the form of documents.

[0061] Through this embodiment, first, the power grid dispatching and operation management main station is controlled to determine the target equipment according to the power grid operation parameters, at least generate the power grid operation risk according to the above target equipment, and send it to the intelligent operation and maintenance main station, the above target equipment is the primary equipment or secondary equipment with abnormal operation parameters; then, the above intelligent operation and maintenance main station is controlled to perform analysis according to the above power grid operation and maintenance risk to obtain the above target equipment, at least generate the target inspection scheduling information according to the above target equipment and send it to the production monitoring main station or the security main station and the OCS automation main station; thereafter, when the above target inspection scheduling information is sent to the above production monitoring main station, the above production monitoring main station is controlled to perform inspection on the above target equipment through the inspection equipment according to the above target inspection scheduling information and generate inspection information. The inspection report is sent to the above-mentioned intelligent operation and maintenance main station; thereafter, when the above-mentioned target inspection scheduling information is sent to the above-mentioned Baoxin main station and the above-mentioned OCS automation main station, the above-mentioned Baoxin main station obtains the real-time operation information and the historical operation information through the intelligent recorder according to the corresponding above-mentioned target inspection scheduling information and generates the above-mentioned inspection report and sends it to the above-mentioned intelligent operation and maintenance main station, and the above-mentioned OCS automation main station obtains the real-time monitoring information and the historical monitoring information through the motion machine according to the corresponding above-mentioned target inspection scheduling information and generates the above-mentioned inspection report and sends it to the above-mentioned intelligent operation and maintenance main station; finally, when the above-mentioned inspection report is received, the above-mentioned intelligent operation and maintenance main station is controlled to generate an early warning report according to the above-mentioned inspection report and send it to the intelligent operation and maintenance client for visual display. The present application proposes an automatic inspection system, including an intelligent operation and maintenance main station, a power grid dispatching and operation management main station, a production monitoring main station, an intelligent operation and maintenance client, a security main station and an OCS automation main station. The power grid dispatching and operation management main station publishes power grid risks according to the power grid operation status, and the intelligent operation and maintenance main station performs dispatching according to the power grid risks, so that the production monitoring main station or the security main station and the OCS automation main station perform primary equipment or secondary equipment inspections, obtain corresponding inspection results and send them to the client for visual display. This method realizes the automatic inspection of primary and secondary equipment, and solves the problem of low efficiency in the prior art from discovering power grid risks to completing inspections through manual operation and maintenance.

[0062] In order to generate and send the inspection scheduling information, in an optional implementation, the method further includes:

[0063] Step S401, upon receiving the inspection start information sent by the intelligent operation and maintenance client, control the intelligent operation and maintenance master station to generate the target inspection scheduling information and send it to the production monitoring master station or the security master station and the OCS automation master station.

[0064] In order to generate and send the inspection list, in an optional implementation, the above step S302 includes:

[0065] Step S3021, determining a target device tree according to the target device, wherein the target device tree is a hierarchical ledger system according to the affiliation of the target device;

[0066] Step S3022, determining the corresponding primary device based on the target device tree, and determining the corresponding secondary device according to the primary device;

[0067] Step S3023, generating a primary equipment inspection list according to the primary equipment, generating the target inspection scheduling information based on the primary equipment inspection list and sending it to the production monitoring master station;

[0068] Step S3024, generating a secondary equipment inspection list according to the secondary equipment, generating the target inspection scheduling information based on the secondary equipment inspection list and sending it to the security master station and the OCS automation master station.

[0069] In order to generate an early warning report, in an optional implementation, the above step S305 includes:

[0070] Step S3051, determining a corresponding target threshold based on the historical data in the inspection report, the target threshold being a parameter threshold for normal operation of the corresponding primary device or the secondary device, the historical data including historical operation information of the primary device and the historical operation information and historical monitoring information corresponding to the secondary device;

[0071] Step S3052, determining abnormal data based on matching the real-time data in the inspection report with the corresponding target threshold, where the real-time data is the real-time operation information of the primary equipment and the real-time operation information and real-time monitoring information corresponding to the secondary equipment;

[0072] Step S3053, determining the equipment defect level corresponding to the above-mentioned primary equipment or the above-mentioned secondary equipment according to the above-mentioned abnormal data, and obtaining the above-mentioned early warning report.

[0073] An embodiment of the present invention provides a computer-readable storage medium, which includes a stored program, wherein when the program is executed, the device where the computer-readable storage medium is located is controlled to execute the automatic inspection method based on power grid risk.

[0074] Specifically, the automatic inspection method based on power grid risks includes:

[0075] Step S301, controlling the grid dispatching operation management master station to determine the target equipment according to the grid operation parameters, generating the grid operation risk at least according to the target equipment, and sending it to the intelligent operation and maintenance master station, wherein the target equipment is the primary equipment or secondary equipment with abnormal operation parameters;

[0076] Specifically, the method is responsible for publishing power grid risks through the OMS master station and transmitting them to the intelligent operation and maintenance master station via network transmission media.

[0077] Step S302, controlling the intelligent operation and maintenance master station to analyze the power grid operation and maintenance risks, obtain the target equipment, and generate target inspection and scheduling information based on at least the target equipment and send it to the production monitoring master station or the security master station and the OCS automation master station;

[0078] Specifically, the intelligent operation and maintenance master station identifies the primary and secondary equipment involved in the grid risk and forms a primary and secondary equipment inspection list. The intelligent operation and maintenance master station confirms the corresponding equipment tree according to the name of the grid equipment, based on the transmission lines, substations, user equipment and other grid equipment involved in the grid risk released by the OMS master station, and then confirms the terminal contact equipment of the equipment tree to the lower level.

[0079] It can be understood that the above-mentioned equipment tree refers to a ledger system in which equipment is hierarchical according to its affiliation, and is composed of transmission equipment, substation equipment, etc. The lower-level terminals correspond to specific transmission line cables, overhead lines, poles and towers, transformers, switches, circuit breakers, busbars and their corresponding secondary protection and measurement and control equipment of substations.

[0080] Step S303, when the target inspection scheduling information is sent to the production monitoring main station, control the production monitoring main station to inspect the target equipment through the inspection equipment according to the target inspection scheduling information and generate an inspection report and send it to the intelligent operation and maintenance main station;

[0081] Specifically, a device inspection list is sent to the production monitoring main station to conduct a device inspection. After receiving the inspection list, the production monitoring main station issues inspection tasks to the smart cameras, drones, and inspection robots to which the site or equipment belongs. An equipment inspection is conducted and an inspection report is sent back. Smart cameras, drones, and inspection robots conduct an equipment inspection autonomously according to the inspection tasks, and then summarize the equipment inspection situation and send it back to the smart operation and maintenance main station.

[0082] In one embodiment, the inspection items include but are not limited to the following items:

[0083] 1. Equipment temperature, real-time temperature, ABC three-phase temperature difference, historical temperature difference, local temperature difference, etc.; 2. Equipment meter conditions, SF6 pressure, oil level, oil pressure, arrester leakage current, etc.; 3. Equipment appearance, dirt, cracks, discharge marks, oil leakage of lines, poles, towers, switches, knife switches, transformers, insulators, cable heads, etc.; 4. GIS equipment partial discharge online monitoring data; 5. Temperature and humidity of the auxiliary box of outdoor equipment.

[0084] Step S304, when the target inspection scheduling information is sent to the Baoxin master station and the OCS automation master station, the Baoxin master station obtains the real-time operation information and the historical operation information through the intelligent recorder according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station, and the OCS automation master station obtains the real-time monitoring information and the historical monitoring information through the motion machine according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station;

[0085] Specifically, the secondary equipment is inspected and the inspection report is sent back. The Baoxin main station and the OCS automation main station issue tasks to independently carry out secondary equipment inspections based on the inspection list, and then summarize the inspection results of the secondary equipment and send them back to the intelligent operation and maintenance main station.

[0086] In one embodiment, the inspection items include but are not limited to the following items:

[0087] 1. Protection device information; 2. Substation automation information;

[0088] The above protection device information includes protection communication status, correctness of set value equipment, correctness of pressure plate insertion and withdrawal, real-time alarm and historical alarm records for one week, analog quantity, input quantity, waveform recording, etc.

[0089] The above substation automation information includes equipment load data, equipment switching quantity, equipment real-time and historical one-week alarm signals, substation equipment communication conditions, etc.

[0090] Step S305, when receiving the inspection report, control the intelligent operation and maintenance main station to generate an early warning report according to the inspection report and send it to the intelligent operation and maintenance client for visual display.

[0091] Specifically, the intelligent operation and maintenance master station summarizes the first and second equipment inspection reports, analyzes and publishes them. The intelligent operation and maintenance master station analyzes the abnormal data in the inspection report, determines the equipment defect level to which the abnormal data belongs and records it in the inspection results. For normal data, the inspection results are recorded as normal, and then archived and published to the intelligent operation and maintenance user terminal and Elink office system to inform the operation and maintenance responsible persons at all levels.

[0092] It can be understood that the Elink office system refers to a power grid-specific office information transmission system, which is used by operation and maintenance personnel to interactively confirm inspection results online. At the same time, the system automatically publishes the inspection results to the operation and maintenance personnel in the form of documents.

[0093] An embodiment of the present invention provides a processor, and the processor is used to run a program, wherein the program executes the automatic inspection method based on power grid risk when running.

[0094] Specifically, the automatic inspection method based on power grid risks:

[0095] Step S301, controlling the grid dispatching operation management master station to determine the target equipment according to the grid operation parameters, generating the grid operation risk at least according to the target equipment, and sending it to the intelligent operation and maintenance master station, wherein the target equipment is the primary equipment or secondary equipment with abnormal operation parameters;

[0096] Specifically, the method is responsible for publishing power grid risks through the OMS master station and transmitting them to the intelligent operation and maintenance master station via network transmission media.

[0097] Step S302, controlling the intelligent operation and maintenance master station to analyze the power grid operation and maintenance risks, obtain the target equipment, and generate target inspection and scheduling information based on at least the target equipment and send it to the production monitoring master station or the security master station and the OCS automation master station;

[0098] Specifically, the intelligent operation and maintenance master station identifies the primary and secondary equipment involved in the grid risk and forms a primary and secondary equipment inspection list. The intelligent operation and maintenance master station confirms the corresponding equipment tree according to the name of the grid equipment, based on the transmission lines, substations, user equipment and other grid equipment involved in the grid risk released by the OMS master station, and then confirms the terminal contact equipment of the equipment tree to the lower level.

[0099] It can be understood that the above-mentioned equipment tree refers to a ledger system in which equipment is hierarchical according to its affiliation, and is composed of transmission equipment, substation equipment, etc. The lower-level terminals correspond to specific transmission line cables, overhead lines, poles and towers, transformers, switches, circuit breakers, busbars and their corresponding secondary protection and measurement and control equipment of substations.

[0100] Step S303, when the target inspection scheduling information is sent to the production monitoring main station, control the production monitoring main station to inspect the target equipment through the inspection equipment according to the target inspection scheduling information and generate an inspection report and send it to the intelligent operation and maintenance main station;

[0101] Specifically, a device inspection list is sent to the production monitoring main station to conduct a device inspection. After receiving the inspection list, the production monitoring main station issues inspection tasks to the smart cameras, drones, and inspection robots to which the site or equipment belongs. An equipment inspection is conducted and an inspection report is sent back. Smart cameras, drones, and inspection robots conduct an equipment inspection autonomously according to the inspection tasks, and then summarize the equipment inspection situation and send it back to the smart operation and maintenance main station.

[0102] In one embodiment, the inspection items include but are not limited to the following items:

[0103] 1. Equipment temperature, real-time temperature, ABC three-phase temperature difference, historical temperature difference, local temperature difference, etc.; 2. Equipment meter conditions, SF6 pressure, oil level, oil pressure, arrester leakage current, etc.; 3. Equipment appearance, dirt, cracks, discharge marks, oil leakage of lines, poles, towers, switches, knife switches, transformers, insulators, cable heads, etc.; 4. GIS equipment partial discharge online monitoring data; 5. Temperature and humidity of the auxiliary box of outdoor equipment.

[0104] Step S304, when the target inspection scheduling information is sent to the Baoxin master station and the OCS automation master station, the Baoxin master station obtains the real-time operation information and the historical operation information through the intelligent recorder according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station, and the OCS automation master station obtains the real-time monitoring information and the historical monitoring information through the motion machine according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station;

[0105] Specifically, the secondary equipment is inspected and the inspection report is sent back. The Baoxin main station and the OCS automation main station issue tasks to independently carry out secondary equipment inspections based on the inspection list, and then summarize the inspection results of the secondary equipment and send them back to the intelligent operation and maintenance main station.

[0106] In one embodiment, the inspection items include but are not limited to the following items:

[0107] 1. Protection device information; 2. Substation automation information;

[0108] The above protection device information includes protection communication status, correctness of set value equipment, correctness of pressure plate insertion and withdrawal, real-time alarm and historical alarm records for one week, analog quantity, input quantity, waveform recording, etc.

[0109] The above substation automation information includes equipment load data, equipment switching quantity, equipment real-time and historical one-week alarm signals, substation equipment communication conditions, etc.

[0110] Step S305, when receiving the inspection report, control the intelligent operation and maintenance main station to generate an early warning report according to the inspection report and send it to the intelligent operation and maintenance client for visual display.

[0111] Specifically, the intelligent operation and maintenance master station summarizes the first and second equipment inspection reports, analyzes and publishes them. The intelligent operation and maintenance master station analyzes the abnormal data in the inspection report, determines the equipment defect level to which the abnormal data belongs and records it in the inspection results. For normal data, the inspection results are recorded as normal, and then archived and published to the intelligent operation and maintenance user terminal and Elink office system to inform the operation and maintenance responsible persons at all levels.

[0112] It can be understood that the Elink office system refers to a power grid-specific office information transmission system, which is used by operation and maintenance personnel to interactively confirm inspection results online. At the same time, the system automatically publishes the inspection results to the operation and maintenance personnel in the form of documents.

[0113] An embodiment of the present invention provides a power system, the power system comprising a processor, a memory, and a program stored in the memory and executable on the processor, and when the processor executes the program, at least the following steps are implemented:

[0114] Step S301, controlling the grid dispatching operation management master station to determine the target equipment according to the grid operation parameters, generating the grid operation risk at least according to the target equipment, and sending it to the intelligent operation and maintenance master station, wherein the target equipment is the primary equipment or secondary equipment with abnormal operation parameters;

[0115] Specifically, the method is responsible for publishing power grid risks through the OMS master station and transmitting them to the intelligent operation and maintenance master station via network transmission media.

[0116] Step S302, controlling the intelligent operation and maintenance master station to analyze the power grid operation and maintenance risks, obtain the target equipment, and generate target inspection and scheduling information based on at least the target equipment and send it to the production monitoring master station or the security master station and the OCS automation master station;

[0117] Specifically, the intelligent operation and maintenance master station identifies the primary and secondary equipment involved in the grid risk and forms a primary and secondary equipment inspection list. The intelligent operation and maintenance master station confirms the corresponding equipment tree according to the name of the grid equipment, based on the transmission lines, substations, user equipment and other grid equipment involved in the grid risk released by the OMS master station, and then confirms the terminal contact equipment of the equipment tree to the lower level.

[0118] It can be understood that the above-mentioned equipment tree refers to a ledger system in which equipment is hierarchical according to its affiliation, and is composed of transmission equipment, substation equipment, etc. The lower-level terminals correspond to specific transmission line cables, overhead lines, poles and towers, transformers, switches, circuit breakers, busbars and their corresponding secondary protection and measurement and control equipment of substations.

[0119] Step S303, when the target inspection scheduling information is sent to the production monitoring main station, control the production monitoring main station to inspect the target equipment through the inspection equipment according to the target inspection scheduling information and generate an inspection report and send it to the intelligent operation and maintenance main station;

[0120] Specifically, a device inspection list is sent to the production monitoring main station to conduct a device inspection. After receiving the inspection list, the production monitoring main station issues inspection tasks to the smart cameras, drones, and inspection robots to which the site or equipment belongs. An equipment inspection is conducted and an inspection report is sent back. Smart cameras, drones, and inspection robots conduct an equipment inspection autonomously according to the inspection tasks, and then summarize the equipment inspection situation and send it back to the smart operation and maintenance main station.

[0121] In one embodiment, the inspection items include but are not limited to the following items:

[0122] 1. Equipment temperature, real-time temperature, ABC three-phase temperature difference, historical temperature difference, local temperature difference, etc.; 2. Equipment meter conditions, SF6 pressure, oil level, oil pressure, arrester leakage current, etc.; 3. Equipment appearance, dirt, cracks, discharge marks, oil leakage of lines, poles, towers, switches, knife switches, transformers, insulators, cable heads, etc.; 4. GIS equipment partial discharge online monitoring data; 5. Temperature and humidity of the auxiliary box of outdoor equipment.

[0123] Step S304, when the target inspection scheduling information is sent to the Baoxin master station and the OCS automation master station, the Baoxin master station obtains the real-time operation information and the historical operation information through the intelligent recorder according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station, and the OCS automation master station obtains the real-time monitoring information and the historical monitoring information through the motion machine according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station;

[0124] Specifically, the secondary equipment is inspected and the inspection report is sent back. The Baoxin main station and the OCS automation main station issue tasks to independently carry out secondary equipment inspections based on the inspection list, and then summarize the inspection results of the secondary equipment and send them back to the intelligent operation and maintenance main station.

[0125] In one embodiment, the inspection items include but are not limited to the following items:

[0126] 1. Protection device information; 2. Substation automation information;

[0127] The above protection device information includes protection communication status, correctness of set value equipment, correctness of pressure plate insertion and withdrawal, real-time alarm and historical alarm records for one week, analog quantity, input quantity, waveform recording, etc.

[0128] The above substation automation information includes equipment load data, equipment switching quantity, equipment real-time and historical one-week alarm signals, substation equipment communication conditions, etc.

[0129] Step S305, when receiving the inspection report, control the intelligent operation and maintenance main station to generate an early warning report according to the inspection report and send it to the intelligent operation and maintenance client for visual display.

[0130] Specifically, the intelligent operation and maintenance master station summarizes the first and second equipment inspection reports, analyzes and publishes them. The intelligent operation and maintenance master station analyzes the abnormal data in the inspection report, determines the equipment defect level to which the abnormal data belongs and records it in the inspection results. For normal data, the inspection results are recorded as normal, and then archived and published to the intelligent operation and maintenance user terminal and Elink office system to inform the operation and maintenance responsible persons at all levels.

[0131] It can be understood that the Elink office system refers to a power grid-specific office information transmission system, which is used by operation and maintenance personnel to interactively confirm inspection results online. At the same time, the system automatically publishes the inspection results to the operation and maintenance personnel in the form of documents.

[0132] The present application also provides a computer program product, which, when executed on a data processing device, is suitable for executing a program for initializing at least the following method steps:

[0133] Step S301, controlling the grid dispatching operation management master station to determine the target equipment according to the grid operation parameters, generating the grid operation risk at least according to the target equipment, and sending it to the intelligent operation and maintenance master station, wherein the target equipment is the primary equipment or secondary equipment with abnormal operation parameters;

[0134] Specifically, the method is responsible for publishing power grid risks through the OMS master station and transmitting them to the intelligent operation and maintenance master station via network transmission media.

[0135] Step S302, controlling the intelligent operation and maintenance master station to analyze the power grid operation and maintenance risks, obtain the target equipment, and generate target inspection and scheduling information based on at least the target equipment and send it to the production monitoring master station or the security master station and the OCS automation master station;

[0136] Specifically, the intelligent operation and maintenance master station identifies the primary and secondary equipment involved in the grid risk and forms a primary and secondary equipment inspection list. The intelligent operation and maintenance master station confirms the corresponding equipment tree according to the name of the grid equipment, based on the transmission lines, substations, user equipment and other grid equipment involved in the grid risk released by the OMS master station, and then confirms the terminal contact equipment of the equipment tree to the lower level.

[0137] It can be understood that the above-mentioned equipment tree refers to a ledger system in which equipment is hierarchical according to its affiliation, and is composed of transmission equipment, substation equipment, etc. The lower-level terminals correspond to specific transmission line cables, overhead lines, poles and towers, transformers, switches, circuit breakers, busbars and their corresponding secondary protection and measurement and control equipment of substations.

[0138] Step S303, when the target inspection scheduling information is sent to the production monitoring main station, control the production monitoring main station to inspect the target equipment through the inspection equipment according to the target inspection scheduling information and generate an inspection report and send it to the intelligent operation and maintenance main station;

[0139] Specifically, a device inspection list is sent to the production monitoring main station to conduct a device inspection. After receiving the inspection list, the production monitoring main station issues inspection tasks to the smart cameras, drones, and inspection robots to which the site or equipment belongs. An equipment inspection is conducted and an inspection report is sent back. Smart cameras, drones, and inspection robots conduct an equipment inspection autonomously according to the inspection tasks, and then summarize the equipment inspection situation and send it back to the smart operation and maintenance main station.

[0140] In one embodiment, the inspection items include but are not limited to the following items:

[0141] 1. Equipment temperature, real-time temperature, ABC three-phase temperature difference, historical temperature difference, local temperature difference, etc.; 2. Equipment meter conditions, SF6 pressure, oil level, oil pressure, arrester leakage current, etc.; 3. Equipment appearance, dirt, cracks, discharge marks, oil leakage of lines, poles, towers, switches, knife switches, transformers, insulators, cable heads, etc.; 4. GIS equipment partial discharge online monitoring data; 5. Temperature and humidity of the auxiliary box of outdoor equipment.

[0142] Step S304, when the target inspection scheduling information is sent to the Baoxin master station and the OCS automation master station, the Baoxin master station obtains the real-time operation information and the historical operation information through the intelligent recorder according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station, and the OCS automation master station obtains the real-time monitoring information and the historical monitoring information through the motion machine according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station;

[0143] Specifically, the secondary equipment is inspected and the inspection report is sent back. The Baoxin main station and the OCS automation main station issue tasks to independently carry out secondary equipment inspections based on the inspection list, and then summarize the inspection results of the secondary equipment and send them back to the intelligent operation and maintenance main station.

[0144] In one embodiment, the inspection items include but are not limited to the following items:

[0145] 1. Protection device information; 2. Substation automation information;

[0146] The above protection device information includes protection communication status, correctness of set value equipment, correctness of pressure plate insertion and withdrawal, real-time alarm and historical alarm records for one week, analog quantity, input quantity, waveform recording, etc.

[0147] The above substation automation information includes equipment load data, equipment switching quantity, equipment real-time and historical one-week alarm signals, substation equipment communication conditions, etc.

[0148] Step S305, when receiving the inspection report, control the intelligent operation and maintenance main station to generate an early warning report according to the inspection report and send it to the intelligent operation and maintenance client for visual display.

[0149] Specifically, the intelligent operation and maintenance master station summarizes the first and second equipment inspection reports, analyzes and publishes them. The intelligent operation and maintenance master station analyzes the abnormal data in the inspection report, determines the equipment defect level to which the abnormal data belongs and records it in the inspection results. For normal data, the inspection results are recorded as normal, and then archived and published to the intelligent operation and maintenance user terminal and Elink office system to inform the operation and maintenance responsible persons at all levels.

[0150] It can be understood that the Elink office system refers to a power grid-specific office information transmission system, which is used by operation and maintenance personnel to interactively confirm inspection results online. At the same time, the system automatically publishes the inspection results to the operation and maintenance personnel in the form of documents.

[0151] Obviously, those skilled in the art should understand that the above modules or steps of the present invention can be implemented by a general computing device, they can be concentrated on a single computing device, or distributed on a network composed of multiple computing devices, they can be implemented by a program code executable by a computing device, so that they can be stored in a storage device and executed by the computing device, and in some cases, the steps shown or described can be executed in a different order than here, or they can be made into individual integrated circuit modules, or multiple modules or steps therein can be made into a single integrated circuit module for implementation. Thus, the present invention is not limited to any specific combination of hardware and software.

[0152] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0153] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0154] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0155] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0156] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0157] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.

[0158] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tapes, disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.

[0159] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0160] From the above description, it can be seen that the above embodiments of the present application achieve the following technical effects:

[0161] In the automatic inspection system based on power grid risk of the present application, the intelligent operation and maintenance main station is used to receive the power grid operation risk sent by the power grid dispatching and operation management main station and send the target inspection dispatching information based on the above power grid operation risk, as well as receive the inspection report and send it to the intelligent operation and maintenance client. The above target inspection dispatching information includes one or more of the first inspection dispatching information, the second inspection dispatching information and the third inspection dispatching information. The first inspection dispatching information is used to instruct the production monitoring main station to perform inspections, the second inspection dispatching information is used to instruct the security main station to perform inspections, and the third inspection information is used to instruct the OCS main station to perform inspections; the above power grid dispatching and operation management main station is deployed in the office intranet and is communicated with the above intelligent operation and maintenance main station through a firewall and a forward / reverse isolation device. The above power grid dispatching and operation management main station is used to generate the above power grid operation risk according to the power grid operation parameters and send it to the above intelligent operation and maintenance main station; the above production monitoring main station is connected to the office intranet through the above firewall , the forward / reverse isolation device is communicatively connected to the intelligent operation and maintenance main station, the production monitoring main station is used to inspect the primary equipment through the inspection equipment to obtain the inspection report, and the inspection equipment at least includes intelligent cameras, drones and inspection robots; the intelligent operation and maintenance client is communicatively connected to the intelligent operation and maintenance main station through the firewall and the forward / reverse isolation device, the intelligent operation and maintenance client is used to control the intelligent operation and maintenance main station to send the target inspection scheduling information and to visualize the inspection report; the security main station is communicatively connected to the intelligent operation and maintenance main station, the security main station is used to receive the real-time operation information and historical operation information of the protection device of the primary equipment, and generate the inspection report; the OCS automation main station is communicatively connected to the intelligent operation and maintenance main station, the OCS automation main station is used to receive the real-time monitoring information and historical monitoring information of the measurement and control device, and generate the inspection report. The present application proposes an automatic inspection system, including an intelligent operation and maintenance main station, a power grid dispatching and operation management main station, a production monitoring main station, an intelligent operation and maintenance client, a security main station and an OCS automation main station. The power grid dispatching and operation management main station publishes power grid risks according to the power grid operation status, and the intelligent operation and maintenance main station performs dispatching according to the power grid risks, so that the production monitoring main station or the security main station and the OCS automation main station perform primary equipment or secondary equipment inspections, obtain corresponding inspection results and send them to the client for visual display. This method realizes the automatic inspection of primary and secondary equipment, and solves the problem of low efficiency in the prior art from discovering power grid risks to completing inspections through manual operation and maintenance.

[0162] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. An automatic inspection system based on power grid risk, characterized in that: include: The intelligent operation and maintenance master station is used to receive the power grid operation risk sent by the power grid dispatching and operation management master station and send the target inspection scheduling information based on the power grid operation risk, and receive the inspection report and send it to the intelligent operation and maintenance client, wherein the target inspection scheduling information includes one or more of the first inspection scheduling information, the second inspection scheduling information and the third inspection scheduling information, wherein the first inspection scheduling information is used to instruct the production monitoring master station to perform inspection, the second inspection scheduling information is used to instruct the security master station to perform inspection, and the third inspection information is used to instruct the OCS master station to perform inspection; The power grid dispatching operation management master station is deployed in the office intranet and is connected to the intelligent operation and maintenance master station through a firewall and a forward / reverse isolation device. The power grid dispatching operation management master station is used to generate the power grid operation risk according to the power grid operation parameters and send it to the intelligent operation and maintenance master station; The production monitoring master station is connected to the intelligent operation and maintenance master station through the firewall and the forward / reverse isolation device. The production monitoring master station is used to inspect the primary equipment through the inspection equipment to obtain the inspection report. The inspection equipment includes at least a smart camera, a drone and an inspection robot. The intelligent operation and maintenance client is connected to the intelligent operation and maintenance main station through the firewall and the forward / reverse isolation device, and the intelligent operation and maintenance client is used to control the intelligent operation and maintenance main station to send the target inspection scheduling information and to visualize the inspection report; The security master station is connected to the intelligent operation and maintenance master station for communication, and is used to receive the real-time operation information and historical operation information of the protection device of the primary equipment and generate the inspection report; The OCS automation master station is communicatively connected with the intelligent operation and maintenance master station. The OCS automation master station is used to receive real-time monitoring information and historical monitoring information of the measurement and control device and generate the inspection report.

2. The system according to claim 1, characterized in that The automatic inspection system also includes: An intelligent recorder is communicatively connected with the security main station and the protection device. The intelligent recorder is used to receive the data scheduling information sent by the security main station and forward it to the protection device, and to receive the real-time operation information and the historical operation information uploaded by the protection device and forward them to the security main station.

3. The system according to claim 2, characterized in that The automatic inspection system also includes: The motion machine is communicatively connected with the OCS automation master station and the measurement and control device. The motion machine is used to receive the data scheduling information issued by the OCS automation master station and forward it to the measurement and control device, and to receive the real-time monitoring information and the historical monitoring information uploaded by the measurement and control device, and forward them to the OCS automation master station.

4. The system according to claim 3, characterized in that The sports machine realizes real-time communication transmission with the OCS automation master station through the communication network, and the intelligent recorder realizes real-time communication transmission with the security master station through the communication network.

5. An automatic inspection method based on power grid risk, characterized in that: The method is used to control the automatic inspection system according to any one of claims 1 to 4, and the method comprises: Control the grid dispatching and operation management master station to determine the target device according to the grid operation parameters, generate the grid operation risk at least according to the target device, and send it to the intelligent operation and maintenance master station, wherein the target device is the primary device or secondary device with abnormal operation parameters; Control the intelligent operation and maintenance master station to analyze the power grid operation and maintenance risk to obtain the target device, and at least generate target inspection scheduling information according to the target device and send it to the production monitoring master station or the security master station and the OCS automation master station; When the target inspection scheduling information is sent to the production monitoring main station, the production monitoring main station is controlled to inspect the target device through the inspection device according to the target inspection scheduling information and generate an inspection report and send it to the intelligent operation and maintenance main station; In the case where the target inspection scheduling information is sent to the Baoxin master station and the OCS automation master station, the Baoxin master station obtains the real-time operation information and the historical operation information through the intelligent recorder according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station, and the OCS automation master station obtains the real-time monitoring information and the historical monitoring information through the motion machine according to the corresponding target inspection scheduling information and generates the inspection report and sends it to the intelligent operation and maintenance master station; When the inspection report is received, the intelligent operation and maintenance main station is controlled to generate an early warning report according to the inspection report and send it to the intelligent operation and maintenance client for visual display.

6. The method according to claim 5, characterized in that The method further comprises: When the inspection start information sent by the intelligent operation and maintenance client is received, the intelligent operation and maintenance master station is controlled to generate the target inspection scheduling information and send it to the production monitoring master station or the security master station and the OCS automation master station.

7. The method according to claim 5, characterized in that At least generating target inspection scheduling information according to the target device and sending it to the production monitoring master station or the security master station and the OCS automation master station includes: Determine a target device tree according to the target device, wherein the target device tree is a hierarchical ledger system according to the affiliation of the target device; Determine the corresponding primary device based on the target device tree, and determine the corresponding secondary device according to the primary device; Generate a primary equipment inspection list according to the primary equipment, generate the target inspection scheduling information based on the primary equipment inspection list and send it to the production monitoring main station; A secondary equipment inspection list is generated according to the secondary equipment, and the target inspection scheduling information is generated based on the secondary equipment inspection list and sent to the security master station and the OCS automation master station.

8. The method according to claim 5, characterized in that Controlling the intelligent operation and maintenance master station to generate an early warning report according to the inspection report, including: Determine a corresponding target threshold based on the historical data in the inspection report, the target threshold being a parameter threshold for normal operation of the corresponding primary device or the secondary device, the historical data including the historical operation information of the primary device and the historical operation information and the historical monitoring information corresponding to the secondary device; Based on matching the real-time data in the inspection report with the corresponding target threshold, abnormal data is determined, wherein the real-time data is the real-time operation information of the primary equipment and the real-time operation information and the real-time monitoring information corresponding to the secondary equipment; The equipment defect level of the corresponding primary equipment or the corresponding secondary equipment is determined according to the abnormal data to obtain the early warning report.

9. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored program, wherein when the program is executed, the device where the computer-readable storage medium is located is controlled to execute the method according to any one of claims 5 to 8.

10. A power system, characterized in that: include: One or more processors, a memory, and one or more programs, wherein the one or more programs are stored in the memory and are configured to be executed by the one or more processors, and the one or more programs include methods for executing any one of claims 5 to 8.

Citation Information

Patent Citations

  • Remote intelligent inspection system and method

    CN105515198A

  • Substation operation and maintenance system with cooperative interaction of main station and substation

    CN114928164A

  • Inspection task scheduling method and device, electronic equipment and nonvolatile storage medium

    CN117744978A

  • Automatic patrol inspection method and apparatus for data center, and device and medium

    WO2023087599A1