Air conditioning system, heating control method thereof and vehicle
By combining the heat pump circuit and auxiliary heating circuit control, the long-term maximum speed operation of the compressor of the automotive air conditioning system is avoided, the reliability and service life of the heat pump circuit is improved, and maintenance costs and energy efficiency are reduced.
Patent Information
- Application Number
- CN202310620451.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-29
- Publication Date
- 2024-11-29
AI Technical Summary
In the heating mode, the compressor operates at the maximum speed for a long time, resulting in low efficiency, increased leakage, shortened service life and high maintenance costs.
By adopting a combined control method of heat pump circuit and auxiliary heating circuit, by obtaining the desired effective output heat of the air conditioning system and the maximum effective output heat of the heat pump circuit, determine whether the auxiliary heating circuit is started, and control the auxiliary heating parameters and main heating parameters. To avoid maximum load operation of heat pump circuit.
It effectively improves the reliability and service life of the heat pump circuit, and reduces the maintenance cost and energy efficiency of the air conditioning system.
Smart Images

Figure CN119037077A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of vehicle heating, and in particular to an air-conditioning system and a heating control method thereof, and a vehicle. Background Art
[0002] Currently, among the heating methods of automobile air-conditioning systems, heat pump heating has higher energy efficiency than traditional single PTC heating and is increasingly valued by the industry.
[0003] Figure 1 It is a structural schematic diagram of an air conditioning system in a car in the prior art, such as Figure 1 As shown, when the heat pump circuit 10' is used to heat the cabin at its maximum capacity and still cannot reach the cabin air supply temperature, the PTC circuit 20' is often added to the indoor side (cabin side) for additional heating after the heat pump circuit heats the high-pressure side air supply to the cabin. It should be noted that in the case of a large air supply load, this heating mode causes the compressor 11' to operate at the maximum speed (or load), which will produce a series of serious consequences, such as:
[0004] (1) The increase in the leakage rate of the compressor refrigerant will lead to an increase in the leakage of the entire heat pump system, which will not only increase the annual refrigerant filling cost and refrigerant maintenance cost in the air-conditioning system, but also the additional cost caused by the decrease in system energy efficiency due to leakage is also included in the leakage rate induction factor.
[0005] (2) The increase in pressure ratio leads to lower compressor efficiency and higher exhaust temperature. In order to better maintain the normal operation of the compressor, the oil return capacity of the entire air-conditioning system needs to be stronger. This is a greater challenge to the oil return capacity of other components of the pipeline, such as the oil return hole inside the gas-liquid separator (involving the design of the oil return hole). Poor oil return can easily cause the compressor to lose its lubrication ability, resulting in severe wear and overheating.
[0006] (3) According to industry experience and information provided by compressor manufacturers, compressors operate at maximum speed (i.e., extreme load) for a long time, which greatly reduces the service life of the compressors. The resulting compressor replacement increases the cost of automotive air conditioning. Summary of the invention
[0007] The present invention provides an air conditioning system and a heating control method thereof, and a vehicle, so as to prevent a compressor from running at a maximum speed for a long time, thereby increasing the service life of the air conditioning system and reducing its maintenance cost.
[0008] According to one aspect of the present invention, a heating control method of an air-conditioning system is provided. The air-conditioning system is applied to a vehicle. The air-conditioning system includes a heat pump circuit and a first auxiliary heating circuit. The heat pump circuit includes a low-pressure side located outside a vehicle compartment and a high-pressure side located inside the vehicle compartment. The low-pressure side is used to exchange heat with external air outside the vehicle compartment, and the high-pressure side is used to heat high-pressure side intake air transported to the vehicle compartment. The heating control method of the air-conditioning system includes:
[0009] After obtaining the heating start signal, obtaining the expected effective heat output of the air conditioning system and the maximum effective heat output of the heat pump circuit;
[0010] Determining whether to start the first auxiliary heating circuit according to the expected effective heat output of the air conditioning system and the maximum effective heat output of the heat pump circuit;
[0011] If yes, then obtain the current auxiliary heating parameters and main heating parameters;
[0012] According to the auxiliary heating parameter, the first auxiliary heating circuit is controlled to heat the external air and then transmit it to the low-pressure side of the heat pump circuit;
[0013] The heat pump circuit is controlled according to the main heating parameter to heat the high-pressure side inlet air temperature to a target supply air temperature.
[0014] According to another aspect of the present invention, there is provided an air conditioning system, applied to a vehicle, comprising: a heat pump circuit, a first auxiliary heating circuit, and a second auxiliary heating circuit;
[0015] The heat pump circuit includes a low-pressure side located outside the vehicle compartment and a high-pressure side located inside the vehicle compartment; the high-pressure side is used to heat the high-pressure side intake air delivered to the vehicle compartment;
[0016] The heat pump circuit includes a compressor, an in-vehicle condenser, a throttling mechanism and an out-vehicle heat exchanger which are connected end to end in sequence through pipelines; the out-vehicle heat exchanger is located on the low-pressure side, and the in-vehicle condenser is located on the high-pressure side;
[0017] The first auxiliary heating circuit includes a PTC heater, a circulation pump, a first three-way valve, a first warm air radiator and a second three-way valve which are sequentially connected end to end through a pipeline; along the flow direction of the external air, the first warm air radiator and the external heat exchanger are arranged in an arranged manner;
[0018] The second auxiliary heating circuit includes a second warm air radiator, and the second auxiliary heating circuit and the first auxiliary heating circuit share the PTC heater, the first three-way valve, the second three-way valve and the circulation pump; the PTC heater, the circulation pump, the first three-way valve, the second warm air radiator and the second three-way valve are sequentially connected end to end through a pipeline; along the flow direction of the high-pressure side inlet air, the second warm air radiator is arranged in an array with the in-vehicle condenser;
[0019] The air conditioning system further includes a controller, and the controller is used to execute the heating control method of the air conditioning system.
[0020] According to another aspect of the present invention, a vehicle is provided, comprising the above-mentioned air conditioning system.
[0021] The heating control method of the air-conditioning system provided in the embodiment of the present invention controls the first auxiliary heating circuit to start when it is determined that the expected effective output heat of the air-conditioning system exceeds the operating load of the heat pump circuit, and obtains the auxiliary heating parameters and the main heating parameters, controls the first auxiliary heating circuit to operate according to the auxiliary heating parameters to heat the external air and transmit it to the low-pressure side of the heat pump circuit, and controls the heat pump circuit to operate according to the main heating parameters so that the heat pump circuit heats the high-pressure side inlet air temperature to the target supply air temperature. This can avoid the heat pump circuit from operating at maximum load, effectively improve the reliability and service life of the heat pump circuit, and thus effectively improve the economic benefits of the air-conditioning system.
[0022] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0024] Figure 1 It is a structural schematic diagram of an air conditioning system in a car in the prior art;
[0025] Figure 2 is a structural schematic diagram of an air conditioning system provided by an embodiment of the present invention;
[0026] Figure 3 is a flow chart of a heating control method of an air conditioning system provided by an embodiment of the present invention;
[0027] Figure 4 is a flow chart of another heating control method of an air conditioning system provided by an embodiment of the present invention;
[0028] Figure 5 is a structural schematic diagram of an air conditioning system provided by an embodiment of the present invention;
[0029] Figure 6 is a structural schematic diagram of an air conditioning system provided by an embodiment of the present invention;
[0030] Figure 7 It is a schematic diagram of the energy efficiency-temperature relationship curve of the heat pump circuit heating;
[0031] Figure 8 is a schematic diagram of an energy efficiency-temperature relationship curve when an air conditioning system uses the air conditioning system provided by an embodiment of the present invention to perform heating;
[0032] Fig. 9 This is a flow chart of another heating control method for an air-conditioning system provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0033] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0034] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0035] An embodiment of the present invention provides a heating control method for an air-conditioning system, which can prevent the compressor from running at the maximum speed for a long time, thereby increasing the service life of the air-conditioning system and reducing its maintenance cost. The heating control method for the air-conditioning system can be executed by a controller in the air-conditioning system provided by the embodiment of the present invention.
[0036] Figure 2 A schematic diagram of the structure of an air conditioning system provided by an embodiment of the present invention is shown in FIG. Figure 2 As shown, the air conditioning system is applied to a vehicle, including a heat pump circuit 10 and a first auxiliary heating circuit 20. The heat pump circuit 10 includes a low-pressure side 10a located outside the vehicle and a high-pressure side 10b located inside the vehicle. The low-pressure side 10a is used to exchange heat with the external air outside the vehicle (that is, the outdoor ambient air), and the high-pressure side 10b is used to heat the high-pressure side intake air transported to the interior of the vehicle. The high-pressure side intake air may include part of the ambient fresh air from the outside of the vehicle and part of the indoor return air inside the vehicle, or all of the ambient fresh air from the outside of the vehicle. In the heating mode, the high-pressure side intake air is at least heated by the high-pressure side 10b of the heat pump circuit 10 before being transported to the interior of the vehicle.
[0037] Figure 3 is a flow chart of a heating control method of an air conditioning system provided by an embodiment of the present invention, combined with reference to Figure 2 and Figure 3 , the heating control method of the air conditioning system includes:
[0038] S110 . After the heating start signal is obtained, the expected effective heat output of the air-conditioning system and the maximum effective heat output of the heat pump circuit are obtained.
[0039] Specifically, the user can send a heating start signal through a button in the car or a touch screen display, so that the target air supply temperature can be determined according to the desired temperature of the cabin set by the user. The target air supply temperature is the outlet air temperature of the air conditioning system (the default is the outlet air temperature to the cabin), which can be positively correlated with the desired cabin temperature set by the user. The expected effective output heat of the air conditioning system can be the heat required to heat the inlet air temperature of the high-pressure side to the target air supply temperature, and can also be understood as the heat required to raise the temperature in the cabin from the current temperature to the desired temperature set by the user.
[0040] S120. Determine whether to start the first auxiliary heating circuit according to the expected effective heat output of the air-conditioning system and the maximum effective heat output of the heat pump circuit; if so, execute step S130; if not, execute step S110.
[0041] Specifically, the expected effective heat output Q of the air conditioning system can be A Subtract the maximum effective heat output Q' of the heat pump circuit 10, if Q A-Q′≥0, it means that the heat pump circuit 10 cannot raise the outlet air temperature of the air conditioning system to the target air supply temperature when heating alone, or the heat pump circuit 10 can only raise the outlet air temperature of the air conditioning system to the target air supply temperature when operating at the maximum load. When the heat pump circuit 10 operates at the maximum load, the aforementioned series of consequences will occur. Therefore, it is determined that the first auxiliary heating circuit 20 needs to be started to reduce the operating load of the heat pump circuit 10. A -Q′<0, it means that the heat pump circuit 10 can heat the air outlet temperature of the air conditioning system to the target air supply temperature by heating alone, that is, it can be determined not to start the auxiliary heating circuit 20, and only the heat pump circuit 10 is started to control the heat pump circuit 10 to heat alone.
[0042] S130: Obtain current auxiliary heating parameters and main heating parameters.
[0043] Specifically, when it is determined that the first auxiliary heating circuit needs to be controlled to start 20, the auxiliary heating parameters for controlling the operation of the first auxiliary heating circuit 20 and the main heating parameters for controlling the operation of the heat pump circuit 10 can be first obtained, so as to control the operation of the first auxiliary heating circuit 20 and the heat pump circuit 10 based on the auxiliary heating parameters. The auxiliary heating parameters and the main heating parameters can be calibrated and stored through experiments, such as the initial temperature T1 of the external air, the high pressure side inlet air temperature T C , Target air supply temperature T A The corresponding relationship between the auxiliary heating parameters and the main heating parameters under the optimal working conditions of the air conditioner is calibrated to improve the temperature increase efficiency of the heating process. However, due to the complexity of the working conditions, the auxiliary heating parameters and the main heating parameters can also be obtained through testing to improve the accuracy of the heating control process.
[0044] Exemplary, reference Figure 2 The first auxiliary heating circuit 20 includes a PTC heater 21, a circulation pump 24, a first three-way valve 22, a first warm air radiator 25 and a second three-way valve 23 which are connected end to end in sequence through pipelines; along the flow direction of the external air, the first warm air radiator 25 is arranged in an array with the external heat exchanger 12.
[0045] At this time, the first auxiliary heating circuit is controlled to start, that is, the first three-way valve 22 and one end of the PTC heater 21 and one end of the first warm air radiator 25 can be controlled to open, and the second three-way valve 23 and one end of the PTC heater 21 and one end of the first warm air radiator 25 can be controlled to open, so that the heat transfer medium can flow in the first auxiliary heating circuit 20 through the circulation pump 24. When only the heat pump circuit 10 is controlled to start, and the first auxiliary heating circuit 20 is controlled not to start, in the process of controlling the heat pump circuit 10 to heat, the ports of the first three-way valve 22 and the second three-way valve 23 can be controlled to be closed, and no power is output to the PTC heater 21.
[0046] At this time, the auxiliary heating parameter may include a preset power of the PTC heater 21 .
[0047] Specifically, as described above, the preset power of the PTC heater 21 and the preset speed of the compressor 11 can be calibrated in advance through experiments. For example, the temperature values (initial temperature T1 of the external air, inlet temperature T2 of the in-vehicle condenser 13, etc.) can be calibrated under the conditions of satisfying the reliability of the compressor 11 and the energy efficiency of the air conditioning system. C , Target air supply temperature T A ) is calibrated by the preset power of the PTC heater 21 and the preset speed of the compressor 11. Thus, after determining the current initial temperature T1 of the external air and the inlet air temperature T C , Target air supply temperature T A Afterwards, the corresponding preset power of the PTC heater 21 and the preset speed of the compressor 11 can be obtained according to the above correspondence.
[0048] S140, controlling the first auxiliary heating circuit according to the auxiliary heating parameters to heat the external air and then transmit it to the low-pressure side of the heat pump circuit.
[0049] Specifically, when supplying heat to the vehicle compartment, the outside air can be heated by the first auxiliary heating circuit 20, so that the temperature of the outside air transmitted to the low-pressure side 10a is increased by a certain amount, so that the outside air with the increased temperature can exchange heat with the low-pressure side 10a of the heat pump circuit 10, thereby reducing the operating load of the heat pump circuit 10, so that the heat pump circuit 10 can operate at a lower load, thereby achieving the effect of improving the reliability and service life of the heat pump circuit 10.
[0050] Exemplarily, when the auxiliary heating parameters include a preset power of the PTC heater, the PTC heater 21 can be controlled to operate at the preset power so that the PTC heater 21 outputs heat, which is transmitted to the first warm air radiator 25 through the heat transfer medium in the pipeline, so that the first warm air radiator 25 can heat the external air.
[0051] S150: Control the heat pump circuit according to the main heating parameters to heat the high-pressure side inlet air temperature to the target supply air temperature.
[0052] Specifically, after the first auxiliary heating circuit 20 heats the external air, the operation of the heat pump circuit 10 can be controlled according to the main heating parameters, so that the high-pressure side 10b of the heat pump circuit 10 can heat its high-pressure side inlet air temperature to the target supply air temperature, and then deliver the high-pressure side inlet air heated to the target temperature to the interior of the vehicle.
[0053] Exemplarily, the heat pump circuit 10, as the main heating circuit of the air-conditioning system, may include a compressor 11, an in-vehicle condenser 13, a throttling mechanism 14, and an out-vehicle heat exchanger 12 connected end to end through pipelines; the out-vehicle heat exchanger 12 is located on the low-pressure side 10a; the in-vehicle condenser 13 is located on the high-pressure side 10b. The out-vehicle heat exchanger 12 is used to exchange heat with the outside air, and the in-vehicle condenser 13 is used to heat the high-pressure side intake air transported to the interior of the vehicle. When the heat pump system 10 is running, the refrigerant of the heat pump system 10 exchanges heat with the outside air in the low-pressure side out-vehicle heat exchanger 12 to absorb heat, and then is pressurized by the compressor 11 to increase the temperature and pressure, and then exchanges heat with the high-pressure side intake air in the high-pressure side in-vehicle condenser 13 to achieve the effect of increasing the high-pressure side intake air temperature.
[0054] Among them, the main heating parameter may include a preset speed of the compressor 11. At this time, since the outside air has been heated by the first auxiliary heating circuit 20 (the first warm air radiator 25), the refrigerant of the heat pump system 10 exchanges heat with the heated outside air in the vehicle-external heat exchanger 12 to absorb heat, and can absorb more heat and increase the temperature. On this basis, when the heat pump circuit is controlled according to the main heating parameter to heat the high-pressure side inlet air temperature to the target air supply temperature, the compressor 11 can be controlled to operate at a preset speed to output heat, so that the refrigerant can reach the desired pressure and temperature when operating at a lower speed, so that the in-vehicle condenser 13 connected to the compressor 11 pipeline can heat its high-pressure side inlet air temperature to the target air supply temperature, and then deliver the high-pressure side inlet air to the interior of the vehicle.
[0055] For example, the compressor 11 can be controlled to run at a preset speed while the PTC heater is controlled to run at a preset power. In this way, the high-pressure side air inlet temperature can be quickly increased from the current temperature to the target air supply temperature in a short time on the basis of reducing the compressor speed, thereby increasing the temperature increase rate on the basis of improving the reliability and service life of the compressor.
[0056] The heating control method of the air-conditioning system provided in the embodiment of the present invention controls the first auxiliary heating circuit to start when it is determined that the expected effective output heat of the air-conditioning system exceeds the operating load of the heat pump circuit, and obtains the auxiliary heating parameters and the main heating parameters, controls the first auxiliary heating circuit to operate according to the auxiliary heating parameters to heat the external air and transmit it to the low-pressure side of the heat pump circuit, and controls the heat pump circuit to operate according to the main heating parameters so that the heat pump circuit heats the high-pressure side inlet air temperature to the target supply air temperature. In this way, the heat pump circuit can be prevented from operating at maximum load, and the reliability and service life of the heat pump circuit can be effectively improved, thereby effectively improving the economic benefits of the air-conditioning system.
[0057] Optional, Figure 4is a flow chart of another heating control method of an air conditioning system provided by an embodiment of the present invention. Figure 4 As shown, the heating control method of the air conditioning system includes:
[0058] S210, after obtaining the heating start signal, obtain the target air supply temperature T in the vehicle A 、Inlet air temperature of the condenser in the vehicle T C 、Air intake volume E of the condenser in the vehicle C 、Inlet air density of the car condenser ρ C , the specific heat capacity of the air entering the condenser in the car C C , the initial temperature of the outside air T1 and the maximum speed of the compressor r max .
[0059] S220: Based on the first formula, according to the target air supply temperature T A 、Inlet air temperature of the condenser in the vehicle T C 、Air intake volume E of the condenser in the vehicle C 、Inlet air density of the car condenser ρ C and the specific heat capacity C of the air entering the condenser in the car C Determine the expected effective heat output Q of the air conditioning system A .
[0060] Among them, the first formula is: Q A =(T A -T C )*E C *ρ C *C C .
[0061] Specifically, the inlet air temperature T of the in-vehicle condenser 13 C , the air intake volume E of the in-vehicle condenser 13 C , the air density of the inlet air of the in-vehicle condenser 13 ρ C , the specific heat capacity C of the inlet air of the condenser 13 in the vehicle C All of these can be obtained through in-vehicle sensors or air property software. Substituting the acquired data into the first formula, the heat required by the air conditioning system to heat the high-pressure side inlet air temperature from the current temperature to the target air supply temperature can be calculated, that is, the expected effective output heat Q of the air conditioning system. A .
[0062] S230, based on the initial temperature T1 of the outside air and the inlet air temperature T C and the maximum speed of the compressor r max Determine the maximum effective heat output of the heat pump system.
[0063] Specifically, the maximum effective heat output of the heat pump circuit 10 can be calculated based on the temperature value of the high-pressure side inlet air temperature increase when the heat pump circuit 10 is running at the maximum load (the compressor is running at the maximum speed). When the target air supply temperature is constant, if the ambient temperature outside the vehicle compartment is lower (i.e., the temperature of the outside air is lower), the load required on the low-pressure side 10a is greater. If the high-pressure side 10b is to heat its inlet air temperature to the target air supply temperature, the speed of the compressor 11 needs to be greater to meet the heat demand of the high-pressure side 10b.
[0064] Therefore, obtaining the maximum effective heat output of the heat pump system may include: obtaining the initial temperature T1 of the external air, the inlet air temperature T C and the maximum speed r of the compressor under the current working condition max ; Based on the initial temperature T1 of the external air and the maximum speed r of the compressor max Determine the maximum effective heat output of the heat pump system.
[0065] When the compressor 11 is running at the maximum speed, multiple sets of initial temperature T1 of the external air and the inlet air temperature T C and the maximum effective heat output of the heat pump system 10 to determine the correspondence between the three under the maximum speed condition, which can be a three-dimensional data set or a functional relationship. In this way, when the compressor 11 is running at the maximum speed, the current initial temperature T1 of the external air and the inlet temperature T1 of the condenser 13 in the vehicle are obtained. C After that, the initial temperature T1 of the outside air and the inlet air temperature T1 of the condenser 13 in the vehicle can be directly found. C The corresponding relationship with the maximum effective heat output of the heat pump system 10 determines the maximum effective heat output of the heat pump system, which can improve the efficiency of obtaining the maximum effective heat output.
[0066] In other feasible embodiments of the present invention, after obtaining the heating start signal, only the heat pump circuit is controlled to start, and the compressor 11 is controlled to run at the maximum speed, and the outlet air temperature T of the condenser 13 in the vehicle is obtained. B , the inlet air temperature T of the in-vehicle condenser 13 C , the air volume E of the in-vehicle condenser 13 C , the air density of the inlet air of the in-vehicle condenser 13 ρ C and the specific heat capacity C of the inlet air of the condenser 13 in the vehicle C , Substitute each data into the formula Q′=(T B -T C )*E C * C *C CIn the embodiment of the present invention, the maximum effective heat output Q′ of the heat pump system 10 under the current working condition is obtained by testing. This embodiment of the present invention does not specifically limit this.
[0067] For example, in order to prevent the compressor from running at the maximum speed, a speed protection threshold of the compressor (slightly less than the maximum speed of the compressor) can be set. When determining the maximum effective heat output of the heat pump system, the effective heat output when the compressor runs at the speed protection threshold can be determined as the maximum effective heat output. In this way, in the process of obtaining the maximum effective heat output of the heat pump system by testing, it can also be ensured that the compressor will not run at a large speed, thereby further ensuring the reliability of the compressor.
[0068] S240, judging whether to start the first auxiliary heating circuit according to the expected effective heat output of the air-conditioning system and the maximum effective heat output of the heat pump circuit; if so, executing step S250.
[0069] S250: Obtain current auxiliary heating parameters and main heating parameters.
[0070] S260: Control the first auxiliary heating circuit according to the auxiliary heating parameters to heat the external air and then transmit it to the low-pressure side of the heat pump circuit.
[0071] S270: Control the heat pump circuit according to the main heating parameters to heat the high-pressure side inlet air temperature to the target supply air temperature.
[0072] Optional, Figure 5 is a schematic diagram of the structure of another air conditioning system provided by an embodiment of the present invention. Figure 5 As shown, the air-conditioning system also includes a second auxiliary heating circuit 30, the second auxiliary heating circuit 30 includes a second warm air radiator 31, and the second auxiliary heating circuit 30 and the first auxiliary heating circuit 20 share the PTC heater 21, the first three-way valve 22, the second three-way valve 23 and the circulation pump 24; the PTC heater 21, the circulation pump 24, the first three-way valve 22, the second warm air radiator 31 and the second three-way valve 23 are connected end to end in sequence through pipelines; along the flow direction of the high-pressure side air intake, the second warm air radiator 31 is arranged with the in-vehicle condenser 13. Figure 6 is a flow chart of another heating control method of an air conditioning system provided by an embodiment of the present invention, with reference to Figure 5 and Figure 6 , the heating control method of the air conditioning system includes:
[0073] S311. After obtaining a heating start signal, obtain an expected effective heat output of the air-conditioning system and a maximum effective heat output of the heat pump circuit.
[0074] S312, judging whether to start the first auxiliary heating circuit according to the expected effective heat output of the air-conditioning system and the maximum effective heat output of the heat pump circuit; if so, executing step S313.
[0075] S313, controlling the second auxiliary heating circuit to be turned on and the first auxiliary heating circuit to be turned off.
[0076] S314: Obtain a first comprehensive performance parameter of the air conditioning system when the air outlet temperature of the second warm air radiator reaches the target air supply temperature.
[0077] The first comprehensive performance parameter includes the first refrigerant leakage rate M1 of the compressor, the first actual life L1 of the compressor and the first system energy efficiency COP of the air conditioning system. SYS 1.
[0078] Specifically, when obtaining the current auxiliary heating parameters and main heating parameters, the second auxiliary heating circuit 30 can be controlled to be opened and the first auxiliary heating circuit 10 can be controlled to be closed, that is, the end of the first three-way valve 22 connected to the PTC heater 21 is controlled to be opened, the end connected to the second warm air radiator 31 is controlled to be opened, and the end connected to the first warm air radiator 25 is controlled to be closed, and the end of the second three-way valve 23 connected to the PTC heater 21 is controlled to be opened, the end connected to the second warm air radiator 31 is controlled to be opened, and the end connected to the first warm air radiator 25 is controlled to be closed, so that the first warm air radiator 25 does not heat the external air, that is, the external air at the initial temperature directly exchanges heat with the external heat exchanger 12, and at the same time, the internal condenser 13 and the second warm air radiator 31 heat the incoming air on the high-pressure side. That is, it is equivalent to the air conditioning system with the prior art ( Figure 1 ) is used for heating in the same manner as in the conventional heating method. At this time, the first comprehensive performance parameter of the air-conditioning system when the heat pump circuit 10 is running at full load (i.e., the compressor 11 is running at the maximum speed) can be obtained as one of the bases for determining the auxiliary heating parameters and the main heating parameters.
[0079] Among them, the refrigerant leakage rate of the compressor 11 affects the refrigerant filling cost and maintenance cost of the entire heat pump circuit 10, that is, the higher the refrigerant leakage rate, the more frequent the refrigerant filling in the heat pump circuit 10, and the higher the maintenance cost of the refrigerant leakage part. The actual life of the compressor 11 is related to its actual operating speed and pressure ratio (the ratio of the exhaust port pressure to the inlet port pressure). Under normal circumstances, the higher the pressure ratio of the compressor and the greater the speed, the shorter the life of the compressor. The correlation between the life and the speed and pressure ratio can be obtained from the measured data or the compressor manufacturer, or multiple sets of data can be collected and obtained by linear fitting of the multiple sets of data. When the compressor 11 is running at full load, its speed is the maximum speed it can reach. The maximum speed can be calibrated and stored in advance, or the actual speed of the compressor 11 can be obtained by a sensor. In addition, the pressure at the exhaust port position of the compressor 11 and the pressure at the inlet position can be obtained by a pressure sensor, so that the pressure ratio can be obtained, and then the first actual life of the air conditioning system under the full load operation state of the main heating circuit 10 (which can also be understood as the full load operation state of the compressor) can be determined. The system energy efficiency of the air conditioning system and the expected effective heat output Q of the air conditioning system A The power consumption of the compressor 11 is related to the power consumption of the PTC heater 21, wherein the power consumption of the compressor 11 is the actual power of the compressor, and the power consumption of the PTC heater is the actual power.
[0080] Exemplarily, obtaining the first comprehensive performance parameter of the air conditioning system when the air outlet temperature of the second warm air radiator reaches the target air supply temperature includes:
[0081] S3141, when the in-vehicle condenser and the second warm air radiator heat the high-pressure side inlet air temperature to the target air supply temperature in turn, obtain the first refrigerant density ρ1 at the compressor exhaust port, the first pressure difference △P1 between the compressor exhaust port and the air intake port, the first actual speed RPM1 and the first pressure ratio PR1 of the compressor, and the first power consumption W of the compressor HP 1 and the first power consumption W of the PTC heater PTC 1.
[0082] Specifically, the first refrigerant density ρ1 at the compressor exhaust port can be obtained by general means, such as directly obtaining it by detecting the pressure and temperature parameters of the exhaust port in combination with the refrigerant physical property software. The pressure at the compressor exhaust port and the air intake port can be obtained by the sensor, and then the two pressures are subtracted to obtain the first pressure difference △P1. The first actual speed RPM1 of the compressor can be obtained by sensor detection, and the first pressure ratio PR1 is the ratio of the pressure at the compressor exhaust port to the air intake port.
[0083] S3142. Based on the second formula, determine the first refrigerant leakage rate M1 according to the first refrigerant density ρ1 and the first pressure difference ΔP1.
[0084] Specifically, the second formula is: M1 = Cd0*A0*(ρ1*△P1) 1 / 2 ; Wherein, Cd0 is the leakage coefficient of the compressor, which is usually an empirical coefficient; A0 is the leakage flow area of the internal cavity of the compressor, which is usually related to the structural characteristics of the cavity of the compressor 11 and can be obtained through compressor product information or through measurement. In other feasible embodiments of the present invention, the leakage coefficient Cd0 and the leakage flow area A0 can be constants to simplify the calculation process without affecting the results.
[0085] S3143. Determine the first actual life L1 based on the third formula according to the first actual speed RPM1 and the first pressure ratio PR1.
[0086] Specifically, the third formula is: L1 = k1 * RPM1 (-a) *PR1 (-b) ; Wherein, k1, a and b are empirical parameters of the compressor, and k1, a and b are all constants greater than 0, which are related to the type and working conditions of the compressor and can be determined according to actual conditions. For example, according to empirical summary, the value range of a can be 2.0 to 3.5, and the value range of b can be 0.5 to 0.8.
[0087] S3144: Based on the fourth formula, according to the expected effective heat output Q of the air conditioning system A , the first power consumption W of the compressor HP 1 and the first power consumption W of the PTC heater PTC 1. Determine the energy efficiency COP of the first system SYS 1. Among them, the fourth formula is COP SYS 1=Q A / (W HP 1+W PTC 1). It can be understood that at this time, the first power consumption W of the compressor is HP 1 is the maximum power consumption, which can be directly obtained from calibration data or obtained through sensor detection. The first power consumption of PTC is W PTC 1Can be obtained through sensor detection.
[0088] S315, controlling the first auxiliary heating circuit to be turned on and the second auxiliary heating circuit to be turned off.
[0089] Specifically, after the first comprehensive parameter is acquired, the second auxiliary heating circuit is closed and the first auxiliary heating circuit is opened. That is, the first three-way valve 22 is controlled to open at one end connected to the PTC heater 21, open at one end connected to the first warm air radiator 25, and close at one end connected to the second warm air radiator 31, and the second three-way valve 23 is controlled to open at one end connected to the PTC heater 21, open at one end connected to the first warm air radiator 25, and close at one end connected to the second warm air radiator 31, so that the first warm air radiator 25 in the first auxiliary heating circuit 20 heats the outside air and transmits the heated outside air to the low-pressure side of the heat pump circuit 10. The outside heat exchanger 12 on the low-pressure side of the heat pump circuit 10 exchanges heat with the heated outside air, so that the refrigerant therein absorbs more heat, and the second warm air radiator 31 in the second auxiliary heating circuit 30 does not heat the outside air. At this time, the high-pressure side intake air is heated by the in-vehicle condenser 13 and sent into the vehicle compartment.
[0090] S316, adjusting the actual power of the PTC heater.
[0091] Specifically, the actual power of the PTC heater can be adjusted within the rated power range to obtain the second comprehensive performance parameter of the air conditioning system when the inlet air temperature on the high-pressure side reaches the target supply air temperature under different actual powers of the PTC heater.
[0092] For example, after the first auxiliary heating circuit is controlled to be turned on and the second auxiliary heating circuit is controlled to be turned off, the actual power of the PTC heater can be adjusted to a minimum value (for example, its actual power is adjusted to zero), and then the power of the PTC heater is adjusted to increase gradually on this basis. When the power of the PTC heater is adjusted to increase gradually, the actual power of the PTC heater can be adjusted to increase with a preset power step, or the actual power of the PTC can be adjusted to control the first outlet air temperature at the outlet of the first warm air radiator to increase with a preset temperature step.
[0093] S317: Obtain a first air outlet temperature of a first warm air radiator.
[0094] Specifically, the first outlet air temperature is the air temperature transmitted to the low-pressure side of the heat pump circuit 10 after the first warm air radiator 25 heats the external air at the initial temperature. A temperature sensor can be set at the air outlet of the first warm air radiator 25 (close to the side of the external heat exchanger) to obtain the first outlet air temperature.
[0095] S318, determining whether the difference between the first air outlet temperature and the initial temperature does not exceed the preset temperature; if so, executing step S319; if not, executing step S320.
[0096] Specifically, the preset temperature can be set in combination with the rated power of the PTC heater 21 and the economic benefits of the air conditioning system, or can be the protection power threshold of the PTC heater. When the difference between the first air outlet temperature and the initial temperature is less than or equal to the preset temperature, it means that the power of the PTC heater is not very large at this time, and the economic benefits of the air conditioning system can be maintained within the normal range. When the difference between the first air outlet temperature and the initial temperature is greater than the preset temperature, it means that the power of the PTC heater is too large at this time, which is easy to cause damage to the PTC heater 21, which will aggravate the failure of the air conditioning system.
[0097] S319, obtaining the second comprehensive performance parameter of the air conditioning system, the actual power of the PTC heater and the actual speed of the compressor when the air outlet temperature of the condenser in the vehicle reaches the target air supply temperature; and returning to execute step S316.
[0098] The second comprehensive performance parameter includes the second refrigerant leakage rate, the second actual life of the compressor 11, and the second system energy efficiency of the air-conditioning system.
[0099] Specifically, after adjusting the actual power of the PTC heater once, if it is determined that the difference between the first outlet air temperature at the outlet of the first warm air radiator 25 and the initial temperature of the external air does not exceed the preset temperature, the compressor speed is adjusted until the inlet air temperature on the high-pressure side reaches the target air supply temperature after being heated by the in-vehicle condenser 13. At this time, the second comprehensive performance parameter of the air-conditioning system is obtained, and the actual power of the current PTC heater 21 and the actual speed of the compressor 11 are recorded. After completing the data acquisition for the current time, the actual power of the PTC heater is returned to continue to be adjusted to obtain data for the next time.
[0100] Exemplarily, based on the same principle as that of obtaining the first comprehensive parameter, the second comprehensive performance parameter of the air conditioning system is obtained when the air outlet temperature of the in-vehicle condenser 13 reaches the target air supply temperature, including:
[0101] S3191, when the high-pressure side inlet air temperature is heated to the target air supply temperature by the in-vehicle condenser, the second refrigerant density ρ2 at the compressor exhaust port, the second pressure difference △P2 between the compressor exhaust port and the air intake port, the second actual speed RPM2 of the compressor and the second pressure ratio PR2, and the second power consumption W of the heat compressor are obtained. HP 2 and the second power consumption W of the PTC heater PTC 2.
[0102] S3192. Based on the fifth formula, determine the second refrigerant leakage rate M2 according to the second refrigerant density ρ2 and the second pressure difference ΔP2.
[0103] Specifically, the fifth formula is: M2 = Cd0*A0*(ρ2*△P2) 1 / 2; Among them, Cd0 is the leakage coefficient of the compressor, and A0 is the leakage flow area of the internal cavity of the compressor.
[0104] S3193. Based on the sixth formula, determine the second actual life L2 according to the second actual speed RPM2 and the second pressure ratio PR2.
[0105] Specifically, the sixth formula is: L2 = k1 * RPM2 (-a) *PR2 (-b) ; Wherein, k1, a and b are constants greater than 0.
[0106] S3194, based on the seventh formula, according to the expected effective heat output Q of the air conditioning system A , the second power consumption W of the compressor HP 2 and the second power consumption W of PTC PTC 2 Determine the energy efficiency COP of the second system SYS 2.
[0107] Among them, the seventh formula is COP SYS 2=Q A / (W HP 2+W PTC 2) It can be understood that the current second power consumption W of the compressor 11 is HP 2 can be obtained by sensor detection. The current second power consumption W of the PTC heater 21 PTC 2 can be obtained through sensor detection.
[0108] In addition, the energy efficiency COP of the heat pump circuit HP Defined as: COP HP =Q / W HP The ratio of the heat output of the second auxiliary heating circuit to the total heat output of the air conditioning system is X PTC It can be defined as: X PTC =W PTC *η0 / Q, where η0 is the energy efficiency of the PTC heater, which can be directly obtained from product information. Therefore, the seventh formula can also be expressed as, COP SYS 2=1 / (1 / COP HP 2+X PTC 2 / η0), this relationship can better reflect the relationship between the energy efficiency of the air-conditioning system and the energy efficiency of the heat pump circuit and the second auxiliary heating circuit during the regulation process.
[0109] S320, determining a preset power of the PTC heater and a preset speed of the compressor according to the first comprehensive performance parameter, the second comprehensive performance parameter obtained after adjusting the actual power of the PTC heater each time, the actual power of the PTC heater and the actual speed of the compressor.
[0110] Specifically, after adjusting the actual power of the PTC heater 21 once, when the difference between the first outlet temperature of the first warm air radiator 25 and the initial temperature of the external air is greater than the preset temperature, the current second comprehensive performance parameter is not obtained, and the current actual power of the PTC heater 21 and the actual speed of the compressor 11 are not recorded, and the actual power of the PTC heater 21 is adjusted again. In addition, the preset power of the PTC heater 21 and the preset speed of the compressor 11 can be determined by combining the first comprehensive performance parameter obtained, the second comprehensive performance parameter obtained after each adjustment of the actual power of the PTC heater 21, the actual power of the PTC heater 21, and the actual speed of the compressor 11.
[0111] Exemplarily, when the second comprehensive performance parameter is obtained after adjusting the actual power of the PTC heater 21 each time according to the first comprehensive performance parameter, the comprehensive performance index of the air conditioning system after each adjustment of the actual power of the PTC heater 21 can be determined based on the eighth formula according to the first comprehensive performance parameter and the second comprehensive performance parameter obtained after each adjustment of the actual power of the PTC heater 21. Then determine the comprehensive performance index with the largest value among a series of comprehensive performance indexes. is the optimal comprehensive performance index; finally, the actual power of the PTC heater 21 corresponding to the optimal comprehensive performance index is determined to be the preset power of the PTC heater 21, and the actual speed 11 of the compressor 11 corresponding to the optimal comprehensive performance index is determined to be the preset speed of the compressor 11.
[0112] Among them, the eighth formula is: Among them, A, B, and C are all greater than 0, and A+B+C=1. It can be understood that A, B, and C are the proportions of the refrigerant leakage rate, the compressor life, and the system energy efficiency that affect the comprehensive performance index of the air-conditioning system throughout the life cycle, and can be set according to the design requirements. For example, the value range of A can be 8% to 18%. Within this range, the specific value of A can be set according to the type of refrigerant. For example, if the refrigerant is R134a, then due to its low price, the value of A can be set to be smaller. If the refrigerant is R1234yf, then due to its high price (more than 6 times that of R134a), the value of A can be set to be relatively large. If the refrigerant is CO2, although its price is low, because it is a high-pressure working fluid, the system maintenance cost of CO2 as a refrigerant is high, so the value of A can also be set to be relatively large. Since the compressor 11 is the core component of the heat pump circuit 10 and its price is high, the value range of B can be 25% to 45%. Since the system energy efficiency affects the operating cost of the air-conditioning system, its proportion can be set larger, and the value range of C can be 30% to 65%.
[0113] Specifically, by substituting the first comprehensive performance parameter and the second comprehensive performance parameter obtained each time into the seventh formula, multiple comprehensive performance indexes can be obtained. The larger the value of the comprehensive performance index, the better the comprehensive performance of the air-conditioning system. Therefore, the comprehensive performance index with the largest value is selected as the optimal comprehensive performance index, and the actual power of the PTC heater corresponding to the optimal comprehensive performance index is determined as the preset power of the PTC heater, and the actual speed of the compressor corresponding to the optimal comprehensive performance index is determined as the preset speed of the compressor, so that the operation of the PTC heater can be controlled according to the preset power, and the compressor can be controlled to operate at a preset speed, so that on the basis of reducing the operating load of the heat pump system 10, that is, on the basis of reducing the operating speed of the compressor 11, the high-pressure side inlet air temperature is heated to the target supply air temperature, so as to ensure the reliability and service life of the compressor on the basis of meeting the heating demand, and reduce the refrigerant filling cost and refrigerant maintenance cost, thereby improving the service life and economic benefits of the entire heat pump system.
[0114] S321, controlling the PTC heater to operate at a preset power so that the first warm air radiator heats the external air and transmits it to the low-pressure side of the heat pump circuit.
[0115] S322: Control the compressor to run at a preset speed so that the in-vehicle condenser heats the inlet air temperature on the high-pressure side to the target supply air temperature.
[0116] Figure 7 It is a schematic diagram of the energy efficiency-temperature relationship curve of the heat pump circuit heating, such as Figure 7 As shown in the figure, when only the heat pump circuit is used to heat the external air, the higher the temperature T on the air inlet side of the heat pump circuit, the lower the speed of the compressor, and the energy efficiency COP of the air conditioning system HP The higher the heat pump circuit 10, the higher the energy efficiency COP. HP It generally shows an increasing trend until the temperature T on the air inlet side of the heat pump circuit 10 reaches a maximum value tmax. Figure 8 is a schematic diagram of the energy efficiency-temperature relationship curve for heating using the air conditioning system provided by an embodiment of the present invention, such as Figure 8 As shown, under certain heating conditions, in the initial stage of heating of the air conditioning system (i.e., when the air inlet temperature T of the low-pressure side of the heat pump circuit 10 is t1), the heat pump circuit 10 and the second auxiliary heating circuit 30 are turned on to obtain the first comprehensive performance parameter. At this time, the speed of the compressor 11 is relatively high, and the system energy efficiency COP is sys After that, the second auxiliary heating circuit 30 is closed and the first auxiliary heating circuit 20 is opened. The second comprehensive performance parameter is obtained in the process of adjusting the actual power of the PTC heater 21. The air inlet temperature T on the low-pressure side of the heat pump circuit 10 rises from t1 to t2. At this time, the compressor speed gradually decreases, and the system energy efficiency COPsys Gradually increases until the air inlet temperature T of the heat pump circuit rises to t3, the system energy efficiency COP sys The increase of low-pressure side inlet air temperature T indicates that the power of PTC heating startup increases, thus leading to the system energy efficiency COP sys After reaching the peak value, it shows a downward trend. In the process of decline, that is, when the inlet air temperature T on the low-pressure side of the heat pump circuit 10 rises from temperature t3 to the maximum temperature tmax, there is a system energy efficiency COP corresponding to a certain temperature point t4. sys System energy efficiency COP corresponding to temperature t1 sys It can be understood that the system energy efficiency COP corresponding to temperature t1 is sys Equivalent to Figure 1 The system energy efficiency of the air-conditioning system when heating is shown. That is, when the heating method of the air-conditioning system of the present proposal is adopted, as the inlet air temperature T on the low-pressure side of the heat pump circuit 10 increases, there is a possibility that the system energy efficiency is lower than the system energy efficiency in the prior art, but the rotation speed of the compressor 11 will always show a downward trend as the temperature T increases, so that the compressor refrigerant leakage rate decreases, which is beneficial to reducing the refrigerant filling cost and refrigerant maintenance cost in the air-conditioning system, and can reduce the pressure ratio of the compressor, which is beneficial to improving the efficiency of the compressor and the exhaust temperature. The operation of the compressor at a low speed is beneficial to extending its service life, which is of great significance for improving the comprehensive index of the air-conditioning system. Therefore, from the perspective of the overall life cycle of the air-conditioning system, the embodiment of the present invention not only takes into account the system energy efficiency, but also takes into account the refrigerant leakage rate and service life of the compressor, and takes into account the durability and economy of the reliable operation of the air-conditioning system from multiple angles, which can maximize the comprehensive performance of the air-conditioning system. Furthermore, when the above-mentioned air conditioning system is used for heating, compared with the air conditioning system of the prior art, only a warm air radiator 25, two three-way valves (the first three-way valve 22 and the second three-way valve 23) and a short pipeline need to be added on the low-pressure side of the heat pump circuit 10, which is low in cost. During operation, only the state of each port of the first three-way valve 22 and the second three-way valve 23 needs to be controlled to realize the switching between the first auxiliary heating circuit 20 and the second auxiliary heating circuit 30, which is simple to operate and suitable for wide use. In other feasible embodiments, since multi-way valves (including valves with more than three ports) are used more frequently in the system for managing waste heat in vehicles, other multi-way valves can be coupled to replace the first three-way valve 22 and / or the second three-way valve 23 in the embodiment of the present invention to further reduce costs.
[0117] Optional, Fig. 9 is a flow chart of another heating control method of an air conditioning system provided by an embodiment of the present invention. Fig. 9 As shown, the heating control method of the air conditioning system includes:
[0118] S411 . After obtaining a heating start signal, the expected effective heat output of the air-conditioning system and the maximum effective heat output of the heat pump circuit.
[0119] S412. Determine whether to start the first auxiliary heating circuit according to the expected effective heat output of the air-conditioning system and the maximum effective heat output of the heat pump circuit; if so, execute step S413.
[0120] S413, controlling the second auxiliary heating circuit to be turned on and the first auxiliary heating circuit to be turned off.
[0121] S414: Obtain a first comprehensive performance parameter of the air conditioning system when the air outlet temperature of the second warm air radiator reaches the target air supply temperature.
[0122] S415, controlling the first auxiliary heating circuit to be turned on and the second auxiliary heating circuit to be turned off.
[0123] S416: Adjust the actual power of the PTC heater.
[0124] S417: Obtain a first air outlet temperature of a first warm air radiator.
[0125] S418, determining whether the difference between the first air outlet temperature and the initial temperature does not exceed a preset temperature; if so, executing step S419; if not, executing step S424.
[0126] S419: Obtain the exhaust temperature of the compressor.
[0127] S420, determine whether the exhaust temperature of the compressor is greater than the protection temperature; if so, return to step S416; if not, execute step S421.
[0128] Specifically, if the compressor provides relatively large heat, its exhaust temperature will be too high. If the exhaust temperature of the compressor is greater than its protection temperature, the compressor stops running due to overheating protection. At this time, the current second comprehensive performance parameter can be ignored. The actual power of the current PTC heater and the actual speed of the compressor can be recorded for subsequent adjustments, and the next adjustment of the actual power of the PTC heater 21 can be returned to increase the actual power of the PTC heater again. At this time, the compressor speed can be reduced to lower its exhaust temperature. The actual power of the PTC heater 21 is repeatedly adjusted to obtain the suction superheat of the compressor when the exhaust temperature of the compressor does not exceed the protection temperature, under the condition that the difference between the first outlet air temperature and the initial temperature does not exceed the preset temperature.
[0129] S421. Obtain the suction superheat of the compressor.
[0130] S422, determine whether the suction superheat of the compressor is greater than 0; if so, execute step S423; if not, execute step S424.
[0131] Specifically, the suction superheat can be defined as the difference between the suction temperature of the compressor 11 and the refrigerant (refrigerant) in the evaporator ( Figure 2 (not shown in the figure), during the operation of the compressor 11, it is usually necessary to ensure that the suction superheat of the compressor 11 is greater than 0 to prevent liquid refrigerant from entering the compressor, thereby preventing the compressor from being damaged due to liquid hammer. Therefore, when the speed of the compressor 11 is too low, the suction superheat of the compressor 11 is obtained to determine whether the compressor has liquid hammer according to the suction superheat. If the suction superheat is greater than 0, it is determined that the compressor 11 has no liquid hammer, and the second comprehensive performance parameter of the air-conditioning system, which is more reliable at this time, can be obtained, and the actual power of the PTC heater and the actual speed of the compressor can be recorded. If the suction superheat is not greater than 0, it is determined that liquid hammer has occurred, then the actual power of the PTC heater 21 is stopped from being adjusted, and the optimal comprehensive performance index is determined based on the first comprehensive performance parameter obtained previously and the second comprehensive performance parameter of each time, so as to determine the preset power of the PTC heater and the preset speed of the compressor. Exemplarily, the suction temperature of the compressor and the evaporation temperature of the refrigerant can be obtained by a temperature sensor to further achieve the acquisition of the suction superheat.
[0132] S423, obtaining the second comprehensive performance parameter of the air conditioning system, the actual power of the PTC heater, and the actual speed of the compressor when the air outlet temperature of the condenser in the vehicle reaches the target air supply temperature; and returning to step S416.
[0133] S424, determining a preset power of the PTC heater and a preset speed of the compressor according to the first comprehensive performance parameter, the second comprehensive performance parameter obtained after adjusting the actual power of the PTC heater each time, the actual power of the PTC heater and the actual speed of the compressor.
[0134] S425: Control the PTC heater to operate at a preset power so that the first warm air radiator heats the external air and transmits it to the low-pressure side of the heat pump circuit.
[0135] S426: Control the compressor to run at a preset speed so that the in-vehicle condenser heats the high-pressure side inlet air temperature to the target supply air temperature.
[0136] For example, the heat pump circuit 10 with CO2 as the refrigerant is compared with the conventional heating method. Figure 5 The heating methods provided by the corresponding embodiments are compared. Assuming that the current outdoor temperature, i.e., the initial temperature T1 of the external air, is -10°C, the air volume E of the in-vehicle condenser 13 in the heat pump circuit 10 is C350m 3 / h, inlet air temperature T C is 0℃, the air density of inlet air is ρ C 1.291kg / m 3 And the specific heat capacity of the inlet air C C is 1.005 (kJ / kg·K), the wind speed on the air inlet side of the first warm air radiator 25 is 2.4 m / s, and the target air supply temperature T A is 55°C, the energy efficiency of the PTC heater is η0=0.95, and the maximum speed of the compressor 11 is 6800 rpm. A =55℃、T C =0℃、E C =350m 3 / h、ρ C =1.291kg / m 3 and C C =1.005 (kJ / kg·K) Substituting into the first formula, the expected effective heat output Q of the air conditioning system can be determined A is about 6.9kW, and at T1 = -10°C and T C =0℃, the heat Q′ provided by the compressor 11 at the maximum speed is about 6.1kW, which is less than the expected effective output heat Q of the air conditioning system. A That is, when the heat pump circuit 10 is heating alone at maximum load, the outlet air temperature on the high-pressure side of the heat pump circuit 10 cannot reach the target supply air temperature, so the auxiliary heating circuit needs to be turned on for auxiliary heating.
[0137] If the heating method of the prior art is adopted, that is, the heat pump circuit 10 and the second auxiliary heating circuit 30 are used to heat the high-pressure side inlet air temperature in turn, until the outlet air temperature of the second warm air radiator 31 reaches the target air supply temperature, the first power consumption W of the compressor is obtained. HP 1 and the first power consumption W of the PTC heater PTC 1, and the first power consumption W HP 1. The first power consumption W PTC 1 and the expected effective heat output Q of the air conditioning system A Substituting into the fourth formula, the first system energy efficiency COP of the air conditioning system can be determined after testing: SYS 1 = 1.53, where the first power consumption of the compressor W HP 1 and the first power consumption W of the PTC heater PTC 1 can be obtained through sensor measurement. The current first refrigerant density ρ1 obtained through the sensor is 119kg / m 3, the first pressure difference △P1 between the compressor exhaust port and the suction port is 6.6MPa, the first pressure ratio PR1 is 4.66, then it can be determined that the first refrigerant leakage rate M1=28.025*Cd0*A0, the first actual life L1=k1*6800 (-a) *6.6 (-b) Alternatively, the first-year leakage rate R of the compressor under maximum load can be obtained directly from the compressor manufacturer. leak 1 is 10% (R leak 1=k2*M1, k2 is a constant greater than 0), the first actual life span L1 is 4 years.
[0138] The second auxiliary heating circuit 30 is turned off and the first auxiliary heating circuit 20 is turned on. Assume that the maximum difference between the outlet temperature and the inlet temperature of the first warm air radiator 25 is 10°C, that is, the current preset temperature is 10°C. Adjust the actual power of the PTC heater 21 to gradually increase the heating output. Assume that the outlet temperature of the first warm air radiator 25 is adjusted in increments of 2°C. After each adjustment of the actual power of the PTC heater 21, if the outlet temperature of the first warm air radiator 25 does not exceed 0°C, determine whether the exhaust temperature of the compressor 11 is greater than the protection temperature. If it is greater than the protection temperature, return to continue to adjust the actual power of the PTC heater 21. If it is not greater than the protection temperature, continue to determine whether the suction superheat of the compressor 11 is greater than 0. If it is greater than 0, adjust the speed of the compressor 11 until the high-pressure side inlet temperature of the air sent to the compartment reaches the target air supply temperature, and obtain the key parameters of the current air conditioning system (the second refrigerant density ρ2, the second pressure difference △P2, the second actual speed RPM2 of the compressor and the second pressure ratio PR2, the second power consumption W of the compressor). HP 2 and the second power consumption W of the PTC heater PTC 2) in order to obtain the second comprehensive performance parameter, and record the actual power of the PTC heater 21 and the actual speed of the compressor 11, and repeat this cycle until the outlet air temperature of the first warm air radiator 25 is greater than 0°C, or the suction air superheat is not greater than 0, then stop adjusting the actual power of the PTC heater 21.
[0139] The second comprehensive performance parameter obtained after adjusting the actual power of the PTC heater 21 for each time, as well as the actual power of the PTC heater 21 and the actual speed of the compressor 11 recorded, are sorted out, and the comprehensive performance index of each time is calculated based on the eighth formula. Select the maximum value of each comprehensive performance index φ as the optimal comprehensive performance index After testing, when the outlet temperature of the first warm air radiator 25 is -6°C, the corresponding comprehensive performance index is the largest, which is 1.194 (the value is A=10%, B=35%, C=55%). At this time, the second system energy efficiency COP determined according to the seventh formulaSYS 2=1.587, calculate the leakage rate R in the second year leak 2, the second leakage rate M2 can be calculated based on the fifth formula, and then based on the formula R leak 2=k2*M2 to calculate the leakage rate R in the second year leak 2; Alternatively, the leakage rate R in the first year can be known. leak 1=10%, combining the second formula with the fifth formula, we can get: R leak 2=R leak 1*Cd0*A0*(ρ2*△P2) 1 / 2 / [Cd0*A0*(ρ1*△P1) 1 / 2 ]=R leak 1*(ρ2*△P2) 1 / 2 / [(ρ1*△P1) 1 / 2 ] = 9.6%. The second actual life L2 = k1 * RPM2 is determined based on the sixth formula (-a) *PR2 (-b) =k1*5850 (-a) *3.86 (-b) , where a=2.0 and b=0.5 can be set. Based on the known first actual life L1=4 years, the third formula and the sixth formula are combined to obtain: L2=L1*k1*RPM2 (-a) *PR2 (-b) / (k1*RPM1 (-a) *PR1 (-b) )=L1*RPM2 (-a) *PR2 (-b) / (RP M1 (-a) *PR1 (-b) )=5.94, that is, the second actual life span L2 is 5.94 years. Comparing the heating method of the air-conditioning system provided by the embodiment of the present invention with the heating method of the air-conditioning system in the prior art, the energy efficiency COP of the second system SYS 2Compared to the first system energy efficiency COP SYS 1 increased by 3.6%, and the leakage rate in the second year R leak 2Compared to the first year leakage rate R leak 1 decreased by about 4%, and the second actual life L2 was extended by about 48% compared with the first service life L1. The actual power of the corresponding PTC heater 21 is 1200W, and the actual speed of the compressor 11 is 5850rpm, so the preset power of the PTC heater 21 can be determined to be 1200W, and the preset speed of the compressor 11 can be determined to be 5850rpm. In the subsequent heating process, the compressor 11 is controlled to run at a speed of 5850rpm, and the PTC heater 21 is controlled to run at a power of 1200W. In this way, due to the decrease in the refrigerant leakage rate, the refrigerant filling cost and refrigerant maintenance cost in the air-conditioning system can be effectively reduced, and the pressure ratio of the compressor 11 is reduced (from the first pressure ratio PR1=4.66 to the second pressure ratio RP2=3.86), which can reduce the demand for the oil return capacity of the air-conditioning system, and due to the decrease in the speed of the compressor 11, the reliability of the compressor 11 can be effectively improved and the service life of the compressor can be extended, thereby improving the reliability of the air-conditioning system as a whole, and extending the service life of the air-conditioning system as a whole.
[0140] The embodiment of the present invention also provides a vehicle air conditioning system, referring to Figure 5The air conditioning system includes a heat pump circuit 10, a first auxiliary heating circuit 20 and a second auxiliary heating circuit 30; the heat pump circuit 10 includes a low-pressure side 10a located outside the vehicle compartment and a high-pressure side 10b located inside the vehicle compartment; the low-pressure side 10a is used to exchange heat with the external air outside the vehicle compartment, and the high-pressure side 10b is used to heat the high-pressure side intake air transported to the interior of the vehicle compartment; and the heat pump circuit 10 includes a compressor 11, an in-vehicle condenser 13, a throttling mechanism 14 and an out-vehicle heat exchanger 12 connected end to end through pipelines in sequence; the out-vehicle heat exchanger 12 is located on the low-pressure side 10a, and the in-vehicle condenser 13 is located on the high-pressure side 10b; the first auxiliary heating circuit 20 includes a PTC heater connected end to end through pipelines in sequence 21, a circulation pump 24, a first three-way valve 22, a first warm air radiator 25 and a second three-way valve 23; along the flow direction of the external air, the first warm air radiator 25 is arranged in parallel with the external heat exchanger 12; the second auxiliary heating circuit 30 includes a second warm air radiator 31, and the second auxiliary heating circuit 30 and the first auxiliary heating circuit 20 share the PTC heater 21, the first three-way valve 22, the second three-way valve 23 and the circulation pump 24; the PTC heater 21, the circulation pump 24, the first three-way valve 22, the second warm air radiator 31 and the second three-way valve 23 are connected end to end in sequence through pipelines; along the flow direction of the high-pressure side air intake, the second warm air radiator 31 is arranged in parallel with the in-vehicle condenser 13. The air-conditioning system also includes a controller (not shown in the figure), which is used to execute the heating control method of the air-conditioning system provided by any embodiment of the present invention. Therefore, the air-conditioning system provided by the embodiment of the present invention includes the technical features of the heating control method of the air-conditioning system provided by any embodiment of the present invention, and can achieve the beneficial effects of the heating control method of the air-conditioning system provided by any embodiment of the present invention. The similarities can be referred to the above description of the heating control method of the air-conditioning system provided by the embodiment of the present invention, and will not be repeated here.
[0141] Specifically, the throttling mechanism 14 may include an electronic expansion valve for converting the high-pressure refrigerant on the high-pressure side into a low-pressure refrigerant and transmitting it to the off-board heat exchanger 12. One end of the PTC heater 21 is connected to the first port of the first three-way valve 22 through a pipeline, and the other end of the PTC heater 21 is connected to the circulation pump 24 and the first port of the second three-way valve 23 through a pipeline in sequence; one end of the first warm air radiator 25 is connected to the second port pipeline of the first three-way valve 21, and the other end of the first warm air radiator 25 is connected to the second port pipeline of the second three-way valve 23; one end of the second warm air radiator 31 is connected to the third port pipeline of the first three-way valve 22, and the other end of the second warm air radiator 31 is connected to the third port pipeline of the second three-way valve 23. When the first auxiliary heating circuit 20 is controlled to be opened, the first port and the second port of the first three-way valve 22 can be controlled to be opened and the third port can be closed, and the first port and the second port of the second three-way valve 23 can be controlled to be opened and the third port can be closed. When the second auxiliary heating circuit 30 is controlled to be opened, the first port and the third port of the first three-way valve 22 can be controlled to be opened and the second port can be closed, and the first port and the third port of the second three-way valve 23 can be controlled to be opened and the second port can be closed. The controller can be electrically connected or communicatively connected with the first three-way valve 22, the second three-way valve 23, the circulation pump 24, etc., and is used to output control signals to the first three-way valve 22, the second three-way valve 23, and the circulation pump 24.
[0142] Exemplarily, the heat pump circuit may also include a fan 01 and a fan 02. Among them, the fan 01 may be arranged on the air inlet side of the outdoor heat exchanger 12, and the fan 02 may be arranged on the air inlet side of the indoor condenser 13 to control the air flow direction. The air conditioning system may also include a plurality of temperature sensors 03, and the figure only shows an exemplary temperature sensor 03a located at the air inlet position of the first warm air radiator 25, a temperature sensor 03b located at the air outlet position of the first warm air radiator 25, and a temperature sensor 03c located at the air outlet position of the outdoor heat exchanger 12, which are respectively used to detect the initial temperature of the external air, the air outlet temperature of the first warm air radiator 25, and the air outlet temperature of the outdoor heat exchanger 12. It can be understood that multiple sensors can be set according to design requirements to achieve temperature measurement requirements. In addition, multiple pressure sensors (not shown in the figure) can also be included to detect the pressure at the air inlet position of the compressor 11, the pressure at the air outlet position, etc. And each temperature sensor and pressure sensor are electrically connected to the controller for communication. Among them, the controller can be a vehicle controller.
[0143] Based on the same inventive concept, an embodiment of the present invention further provides a vehicle, which is used to execute the air-conditioning system provided by any embodiment of the present invention. Therefore, the vehicle provided by the embodiment of the present invention includes the technical features of the air-conditioning system provided by any embodiment of the present invention, and can achieve the beneficial effects of heating provided by any embodiment of the present invention. The similarities can be referred to the above description of the air-conditioning system provided by the embodiment of the present invention, and will not be repeated here.
[0144] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0145] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A heating control method for an air conditioning system, the air conditioning system being applied to a vehicle, the air conditioning system comprising a heat pump circuit and a first auxiliary heating circuit, the heat pump circuit comprising a low-pressure side located outside a vehicle compartment and a high-pressure side located inside the vehicle compartment, the low-pressure side being used for heat exchange with external air outside the vehicle compartment, the high-pressure side being used for heating high-pressure side intake air transported to the vehicle compartment, characterized in that: The heating control method of the air conditioning system comprises: After obtaining the heating start signal, obtaining the expected effective heat output of the air conditioning system and the maximum effective heat output of the heat pump circuit; Determining whether to start the first auxiliary heating circuit according to the expected effective heat output of the air conditioning system and the maximum effective heat output of the heat pump circuit; If yes, then obtain the current auxiliary heating parameters and main heating parameters; According to the auxiliary heating parameter, the first auxiliary heating circuit is controlled to heat the external air and then transmit it to the low-pressure side of the heat pump circuit; The heat pump circuit is controlled according to the main heating parameter to heat the high-pressure side inlet air temperature to a target supply air temperature.
2. The heating control method of the air conditioning system according to claim 1, characterized in that: The heat pump circuit includes a compressor, an in-vehicle condenser, a throttling mechanism and an out-vehicle heat exchanger which are connected end to end in sequence through pipelines; the out-vehicle heat exchanger is located on the low-pressure side, and the in-vehicle condenser is located on the high-pressure side; Obtaining the expected effective heat output of the air conditioning system and the maximum effective heat output of the heat pump system, including: Get the target air supply temperature T in the car A , the inlet air temperature T of the in-vehicle condenser C , the air intake volume E of the in-vehicle condenser C , the inlet air density ρ of the in-vehicle condenser C , the specific heat capacity C of the inlet air of the in-vehicle condenser C , the initial temperature T1 of the external air and the maximum speed r of the compressor max ; Based on the first formula, according to the target air supply temperature T A , the inlet air temperature T of the in-vehicle condenser C , the air intake volume E of the in-vehicle condenser C , the inlet air density ρ of the in-vehicle condenser C and the specific heat capacity C of the inlet air of the in-vehicle condenser C Determine the expected effective heat output Q of the air conditioning system A ; The first formula is: Q A =(T A -T C )*E C * C *C C ; According to the initial temperature T1 of the outside air and the inlet air temperature T C and the maximum speed r of the compressor max The maximum effective heat output of the heat pump system is determined.
3. The heating control method of the air conditioning system according to claim 2, characterized in that: The first auxiliary heating circuit includes a PTC heater, a circulation pump, a first three-way valve, a first warm air radiator and a second three-way valve which are sequentially connected end to end through a pipeline; along the flow direction of the external air, the first warm air radiator and the external heat exchanger are arranged in an arranged manner; The auxiliary heating parameter includes a preset power of the PTC heater, and the main heating parameter includes a preset speed of the compressor; Controlling the first auxiliary heating circuit to preheat the external air from the initial temperature to the first temperature according to the auxiliary heating parameter includes: Controlling the PTC heater to operate at the preset power so that the first warm air radiator transmits the heated air to the low-pressure side of the heat pump circuit; Controlling the heat pump circuit according to the main heating parameter to heat the high-pressure side inlet air temperature to a target supply air temperature includes: The compressor is controlled to operate at a preset speed so that the in-vehicle condenser heats the high-pressure side inlet air temperature to a target supply air temperature.
4. The heating control method of the air conditioning system according to claim 3, characterized in that: The air conditioning system further includes a second auxiliary heating circuit, the second auxiliary heating circuit includes a second warm air radiator, and the second auxiliary heating circuit and the first auxiliary heating circuit share the PTC heater, the first three-way valve, the second three-way valve and the circulation pump; the PTC heater, the circulation pump, the first three-way valve, the second warm air radiator and the second three-way valve are sequentially connected end to end through a pipeline; along the flow direction of the high-pressure side inlet air, the second warm air radiator is arranged in an array with the in-vehicle condenser; The auxiliary heating parameters and the main heating parameters are determined according to the expected effective heat output of the air conditioning system and the maximum effective heat output of the heat pump system, including: Controlling the second auxiliary heating circuit to be turned on and the first auxiliary heating circuit to be turned off; Obtaining a first comprehensive performance parameter of the air conditioning system when the outlet air temperature of the second warm air radiator reaches the target air supply temperature; the first comprehensive performance parameter includes a first refrigerant leakage rate M1 of the compressor, a first actual life L1 of the compressor, and a first system energy efficiency COP of the air conditioning system SYS 1; Controlling the first auxiliary heating circuit to be turned on and the second auxiliary heating circuit to be turned off; Adjusting the actual power of the PTC heater; After adjusting the actual power of the PTC, obtaining a first air outlet temperature of the first warm air radiator; Determining whether the difference between the first air outlet temperature and the initial temperature does not exceed a preset temperature; If so, then obtain the second comprehensive performance parameter of the air conditioning system, the actual power of the PTC heater and the actual speed of the compressor when the air outlet temperature of the in-vehicle condenser reaches the target air supply temperature; the second comprehensive performance parameter includes the current second refrigerant leakage rate M2 of the compressor, the second actual life L2, and the second system energy efficiency COP of the air conditioning system SYS 2; Until the difference between the first air outlet temperature and the initial temperature is greater than the preset temperature, the preset power of the PTC heater and the preset speed of the compressor are determined according to the first comprehensive performance parameter, the second comprehensive performance parameter obtained after each adjustment of the actual power of the PTC heater, the actual power of the PTC heater and the actual speed of the compressor.
5. The heating control method of the air conditioning system according to claim 4, characterized in that: The first comprehensive performance parameter of the air conditioning system is obtained when the air outlet temperature of the second warm air radiator reaches the target air supply temperature, including: When the in-vehicle condenser and the second warm air radiator heat the high-pressure side inlet air temperature to the target air supply temperature in turn, the first refrigerant density ρ1 at the compressor exhaust port, the first pressure difference ΔP1 between the compressor exhaust port and the air intake port, the first actual speed RPM and the first pressure ratio PR1 of the compressor, and the first power consumption W of the compressor are obtained. HP 1 and the first power consumption W of the PTC heater PTC 1; Based on a second formula, determining the first refrigerant leakage rate M1 according to the first refrigerant density ρ1 and the first pressure difference ΔP1; The second formula is: M1 = Cd0*A0*(ρ1*△P1) 1 / 2 ; Wherein, Cd0 is the leakage coefficient of the compressor, and A0 is the leakage flow area of the internal cavity of the compressor; Based on a third formula, the first actual life L1 is determined according to the first actual speed RPM1 and the first pressure ratio PR1; The third formula is: L1 = k1 * RPM1 (-a) *PR1 (-b) ; Wherein, k1, a and b are constants greater than 0; Based on the fourth formula, according to the expected effective heat output Q of the air conditioning system A , the first power consumption W of the compressor HP 1 and the first power consumption W of the PTC heater PTC 1 Determine the energy efficiency COP of the first system SYS 1; The fourth formula is: COP SYS 1=Q A / (W HP 1+W PTC 1).
6. The heating control method of the air conditioning system according to claim 4, characterized in that: Before adjusting the actual power of the PTC heater, the method further includes: Adjusting the actual power of the PTC heater to the minimum power; Adjusting the actual power of the PTC heater includes: The actual power of the PTC heater is adjusted to increase with a preset power step size, or the actual power of the PTC is adjusted to control the first air outlet temperature at the air outlet of the first warm air radiator to increase with a preset temperature step size.
7. The heating control method of the air conditioning system according to claim 4, characterized in that: Before obtaining the second comprehensive performance parameter when the air outlet temperature of the in-vehicle condenser reaches the target air supply temperature, the actual power of the PTC heater and the actual speed of the compressor, the method further includes: Acquiring the exhaust temperature of the compressor; Determining whether the exhaust temperature of the compressor is greater than the protection temperature; If yes, return to the step of adjusting the actual power of the PTC heater; If not, obtaining the suction superheat of the compressor; Determining whether the suction superheat of the compressor is greater than 0; If yes, the step of obtaining a second comprehensive performance parameter when the air outlet temperature of the in-vehicle condenser reaches the target air supply temperature, the actual power of the PTC heater, and the actual speed of the compressor is performed; If not, execute the step of determining the preset power of the PTC heater and the preset speed of the compressor based on the first comprehensive performance parameter, the second comprehensive performance parameter obtained after adjusting the actual power of the PTC heater each time, the actual power of the PTC heater and the actual speed of the compressor.
8. The heating control method of the air conditioning system according to claim 4, characterized in that: The second comprehensive performance parameter of the air conditioning system is obtained when the air outlet temperature of the in-vehicle condenser reaches the target air supply temperature, including: When the high-pressure side inlet air temperature is heated to the target air supply temperature by the in-vehicle condenser, the second refrigerant density ρ2 at the compressor exhaust port, the second pressure difference ΔP2 between the compressor exhaust port and the air intake port, the second actual speed RPM2 of the compressor and the second pressure ratio PR2, and the second power consumption W of the compressor are obtained. HP 2 and the second power consumption W of the PTC heater PTC 2; Based on the fifth formula, the second refrigerant leakage rate M2 is determined according to the second refrigerant density ρ2 and the second pressure difference ΔP2; The fifth formula is: M2 = Cd0*A0*(ρ2*△P2) 1 / 2 ; Wherein, Cd0 is the leakage coefficient of the compressor, and A0 is the leakage flow area of the internal cavity of the compressor; Based on a sixth formula, the second actual life L2 is determined according to the second actual speed RPM2 and the second pressure ratio PR2; The sixth formula is: L2 = k1 * RPM2 (-a) *PR2 (-b) ; Where a and b are constants greater than 0; Based on the seventh formula, according to the expected effective heat output Q of the air conditioning system A , the second power consumption W of the compressor HP 2 and the second power consumption W of the PTC heater PTC 2 Determine the energy efficiency COP of the second system SYS 2; The seventh formula is: COP SYS 2=Q A / (W HP 2+W PTC 2).
9. The heating control method of the air conditioning system according to claim 4, characterized in that: Determining a preset power of the PTC heater and a preset speed of the compressor according to the first comprehensive performance parameter, the second comprehensive performance parameter obtained after adjusting the actual power of the PTC heater each time, the actual power of the PTC heater, and the actual speed of the compressor, including: Based on the eighth formula, according to the first comprehensive performance parameter and the second comprehensive performance parameter obtained after adjusting the actual power of the PTC heater each time, determining the comprehensive performance index φ of the air conditioning system after adjusting the actual power of the PTC heater each time; The eighth formula is: φ=A*M1 / M2+B*L2 / L1+C*COP SYS 2 / COP SYS 1; A, B, and C are all greater than 0, and A+B+C=1; Determine the comprehensive performance index with the largest value as the optimal comprehensive performance index; The actual power of the PTC heater corresponding to the optimal comprehensive performance index is determined as the preset power of the PTC heater, and the actual speed of the compressor corresponding to the optimal comprehensive performance index is determined as the actual speed of the compressor.
10. An air conditioning system, applied to a vehicle, characterized in that: include: a heat pump circuit, a first auxiliary heating circuit, and a second auxiliary heating circuit; The heat pump circuit includes a low-pressure side located outside the vehicle compartment and a high-pressure side located inside the vehicle compartment; the low-pressure side is used to exchange heat with the external air outside the vehicle compartment, and the high-pressure side is used to heat the high-pressure side intake air transported to the interior of the vehicle compartment; The heat pump circuit includes a compressor, an in-vehicle condenser, a throttling mechanism and an out-vehicle heat exchanger which are connected end to end in sequence through pipelines; the out-vehicle heat exchanger is located on the low-pressure side, and the in-vehicle condenser is located on the high-pressure side; The first auxiliary heating circuit includes a PTC heater, a circulation pump, a first three-way valve, a first warm air radiator and a second three-way valve which are sequentially connected end to end through a pipeline; along the flow direction of the external air, the first warm air radiator and the external heat exchanger are arranged in an arranged manner; The second auxiliary heating circuit includes a second warm air radiator, and the second auxiliary heating circuit and the first auxiliary heating circuit share the PTC heater, the first three-way valve, the second three-way valve and the circulation pump; the PTC heater, the circulation pump, the first three-way valve, the second warm air radiator and the second three-way valve are sequentially connected end to end through a pipeline; along the flow direction of the high-pressure side inlet air, the second warm air radiator is arranged in an array with the in-vehicle condenser; The air conditioning system further comprises a controller, and the controller is used to execute the heating control method of the air conditioning system according to any one of claims 1 to 9.
11. A vehicle, characterized in that: An air conditioning system comprising the air conditioning system of claim 10.