Double-wall steel hanging box guiding and limiting device and construction method thereof
By using circumferential hinge and concrete connection in the guide limiting device of double-wall steel hanging box in the sea, combined with the adjustment mechanism of the guide groove and steel wedge, the load on the guide limiting device of the steel hanging box is solved by in-sea water flow and waves on the guide limiting device of the steel hanging box in the sea The problem ensures structural safety and precise positioning and improves construction quality.
Patent Information
- Application Number
- CN202411225585.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-11-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the deposition process of the sea-based double-arm steel hanging box, due to the fast water flow rate, high waves and anti-table conditions, the conventional guided limiting device cannot meet the design requirements, resulting in a structural safety threat and the risk of damage is caused to the steel casing.
A double-wall steel hanging box guide limiting device is designed. By filling sand and pouring concrete into the steel casing, four-layer circumferential clamping hoops are set up to connect to the steel casing. The top limiting device includes steel pipes and stigmas. The bottom-level limiting device includes connecting the truss and annular hoop, the guide device includes a first cross rod and a guide groove, and the steel wedges are temporarily fixed and adjusted by pins and wire ropes to ensure accurate positioning and post-filling concrete connection.
The strength of the guide limiting device and steel casing is enhanced to ensure that it is not damaged under unfavorable working conditions in the sea, and the precise positioning and structural safety of the steel crane box are achieved, and the construction quality is ensured.
Smart Images

Figure CN119041425A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of bridge engineering construction, and more specifically, to a double-walled steel hanging box guide and limit device and a construction method thereof. Background Art
[0002] After entering the 21st century, my country's bridge development has entered the fast lane, and a large number of bridges across mountainous areas, canyons, rivers, lakes and seas are under construction or planning.
[0003] Double-arm steel hoisting boxes are widely used in the construction of high pile caps in the sea. During the lowering process of the double-arm steel hoisting box, in order to ensure the accurate positioning of the steel hoisting box, limit and guide devices must be set. Due to the fast flow velocity and high wave height in the sea, and the typhoon resistance conditions must also be considered, the guide and limit devices of the double-arm steel hoisting box are subject to heavy loads. The conventional guide and limit device structure cannot meet the design requirements, and the guide and limit transfer a large load to the steel casing, posing a great threat to the structural safety of the steel casing. Summary of the invention
[0004] The purpose of the present invention is to provide a double-walled steel hanging box guiding and limiting device and a construction method thereof. During the lowering and positioning process of the double-walled steel hanging box in the sea, in order to avoid the destructive effects of the double-walled steel hanging box guiding and limiting device and the steel casing due to adverse working conditions such as fast sea water flow velocity, high wave height, and typhoon resistance, sand is poured and concrete is poured within a certain range of the steel casing to enhance the strength of the steel casing; the bottom limiting device is provided with four layers of annular hoops, which are respectively connected with the wall ring plate and the steel casing, and C30 concrete is poured between the annular hoops and the steel casing, so that the force transmission path is clear and the strength of the limiting structure is greatly enhanced. A guiding device is set on the top of the limiting device. Before the steel hanging box is lowered, the steel wedge block needs to be temporarily fixed on the guiding device with a pin. After the steel hanging box is lowered into place, the steel wedge block is lifted up by a steel wire rope and the pin is pulled out. The steel wedge block adjusts its position under the action of its own weight, and the entire steel hanging box is positioned to ensure the accurate positioning of the steel hanging box. After fine-tuning into place, C30 concrete is poured between the limiting device clamp and the steel casing to firmly connect the limiting device and the steel casing.
[0005] The technical solution adopted by the present invention to solve this technical problem is: a double-walled steel hanging box guide and limit device, including: a top limit flat joint, a bottom limit device and a guide device;
[0006] The top limit flat joint includes a steel pipe and a column head. The column head is fixed to one end of the steel pipe and welded to the wall of the steel hanging box through the column head. The other end of the steel pipe is welded and fixed to the steel casing of the bored pile after the steel hanging box is accurately positioned.
[0007] The bottom limiting device includes a connecting truss and an annular hoop, one end of the connecting truss is connected to the wall of the steel hanging box, and the other end is connected to the annular hoop, and the bottom limiting device is fixed to the steel casing through a concrete layer;
[0008] The guide device includes a first cross bar, a guide groove, and a steel wedge block; after the steel hanging box is lowered into place, the wedge surface of the guide groove is opposite to the steel casing, the steel wedge block is arranged between the guide groove and the steel casing, and the guide device is located above the bottom limiting device.
[0009] As a further solution of the present invention, the annular hoop comprises a steel pipe and a hoop ring plate; the connecting truss comprises a crossbar group;
[0010] The steel pipe is sleeved on the outside of the steel casing, and a hoop ring plate is installed on the outside of the steel pipe. When there are multiple hoop ring plates, they are arranged outside the steel pipe at intervals from top to bottom, and stiffening plates are arranged between adjacent ring plates. The number of the hoop ring plates corresponds to the number of the cross bar groups one by one, and each cross bar group includes two second cross bars symmetrically arranged in an eight-shaped shape, one end of the second cross bar is connected to the hoop ring plate, and the other end of the second cross bar is connected to the wall of the steel hanging box; when there are multiple cross bar groups, the second cross bars between adjacent cross bar groups are connected by vertical braces, the outer sides of multiple cross bar groups are fixed by diagonal braces, and the inner sides of the two second cross bars in the cross bar group are fixed by braces.
[0011] As a further solution of the present invention, after the steel hanging box is lowered and finely adjusted into place, concrete is poured between the steel pipe and the steel casing, and the bottom limit device is connected to the steel casing through the concrete layer.
[0012] As a further solution of the present invention, the steel wedge block is temporarily fixed on the guide groove by a latch before the steel hanging box is lowered, and a steel wire rope is installed on the steel wedge block.
[0013] As a further solution of the present invention, before the steel hanging box is lowered, sand is poured into the steel casing provided with the guide limit device to the top elevation of the bottom limit device, and then C30 concrete is poured within the elevation range of the guide device.
[0014] The present invention also provides a construction method using the double-walled steel hanging box guide and limit device, comprising the following steps:
[0015] S1 steel hoisting box guide limit device processing, the steel wedge block of the guide device is temporarily fixed on the guide groove with a pin before the steel hoisting box is lowered; before the double-walled steel hoisting box is lowered as a whole, sand is poured into the steel casing where the guide limit device is set to the top elevation of the limit device, and then C30 concrete is poured within the elevation range of the guide device;
[0016] S2 steel hoisting box is lowered as a whole: after the steel hoisting box is processed, it is hoisted as a whole by floating crane. After preliminary positioning, the annular clamp of the bottom limit device is inserted into the steel casing, and the steel hoisting box is lowered as a whole to the designed elevation position;
[0017] S3 Adjustment of the guide limit device of the steel hanging box: After the steel hanging box is lowered into place, the steel wedge block of the guide device is lifted up by the steel wire rope, and the pin is pulled out. The steel wedge block adjusts its position under the action of its own weight to position the entire steel hanging box;
[0018] S3 steel hoisting box guide limit device fixation: After the steel hoisting box is finely adjusted into place, C30 concrete is poured between the limit device clamp and the steel casing, and the bottom limit device, limit flat joint and steel casing are firmly connected respectively.
[0019] As a further solution of the present invention, S1 specifically includes: before the double-walled steel hanging box is lowered as a whole, the top limit flat joint, the bottom limit device and the guide device are processed, and they are firmly welded to the wall of the steel hanging box respectively, and the wall of the connection part between the top limit flat joint, the bottom limit device, the guide device and the steel hanging box shall be locally strengthened.
[0020] The present invention includes at least the following beneficial effects: the present invention is suitable for the construction of double-walled steel hanging boxes under various unfavorable working conditions such as fast sea current velocity, high wave height, and the need to consider typhoon resistance. The guide and limit device has high strength and a clear force transmission path, ensuring that the guide and limit device and the steel casing structure are not damaged under various unfavorable working conditions in the sea, thereby ensuring structural safety. The guide device adjusts the position of the steel hanging box to ensure accurate positioning of the steel hanging box and ensure the construction quality of the steel hanging box.
[0021] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 This is the elevation view of the double-walled steel hanging box guide limit device;
[0023] Figure 2 It is the top limit parallel joint plan layout;
[0024] Figure 3 yes Figure 2 1-1 sectional view;
[0025] Figure 4 It is the plan layout of the bottom limit device;
[0026] Figure 5 It is the elevation layout of the bottom-floor limit device;
[0027] Figure 6 It is the plan layout of the guide device;
[0028] Figure 7 It is the elevation layout of the guide device;
[0029] Figure 8 This is a schematic diagram of the state before the guide device is adjusted;
[0030] Fig. 9 It is a schematic diagram of the limit state of the guide device adjustment.
[0031] In the figure: 1-steel pipe, 2-column, 3-second cross bar, 4-support rod, 5-vertical support, 6-diagonal support, 7-steel pipe, 8-hoop ring plate, 9-stiffening plate, 10-first cross bar, 11-guide groove, 12-steel wedge block, 13-top limit flat joint, 14-bottom limit device, 15-guide device, 16-steel hanging box ring plate, 17-steel hanging box wall, 18-steel casing. DETAILED DESCRIPTION
[0032] The present invention is described in detail and completely below in conjunction with the accompanying drawings. A person of ordinary skill in the art will be able to implement the present invention based on these descriptions. Before describing the present invention in conjunction with the accompanying drawings, it should be particularly noted that the technical solutions and technical features provided in each part of the present invention, including the following description, can be combined with each other without conflict.
[0033] In addition, the embodiments of the present invention involved in the following description are generally only a part of the embodiments of the present invention, rather than all the embodiments. Therefore, based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0034] The present invention is further described in detail below in conjunction with the accompanying drawings and implementations, and its specific implementation process is as follows:
[0035] like Figures 1 to 9 As shown, the present invention provides a double-walled steel hanging box guiding and limiting device, comprising: a top limiting flat joint 13, a bottom limiting device 14 and a guiding device 15;
[0036] The top limit flat joint 13 includes a steel pipe 71 and a column head 2. The column head 2 is fixed to one end of the steel pipe 71 and is welded to the steel hanging box wall 17 through the column head 2. The other end of the steel pipe 71 is welded and fixed to the steel casing 18 of the bored pile after the steel hanging box is accurately positioned.
[0037] The bottom limiting device 14 includes a connecting truss and an annular hoop, one end of the connecting truss is connected to the steel hanging box wall 17, and the other end is connected to the annular hoop, and the bottom limiting device 14 is fixed to the steel casing 18 through a concrete layer;
[0038] The guide device 15 includes a first cross bar 10, a guide groove 11, and a steel wedge block 12; after the steel hanging box is lowered into place, the wedge surface of the guide groove 11 is opposite to the steel casing 18, and the steel wedge block 12 is arranged between the guide groove 11 and the steel casing 18. The steel wedge block 12 adjusts its own position under the action of its own weight to position the entire steel hanging box. The guide device 15 is located above the bottom limiting device 14.
[0039] The technical solution may also include the following technical details to better achieve the technical effect: the annular hoop includes a steel pipe 71 and a hoop ring plate 8; the connecting truss includes a crossbar group;
[0040] The steel pipe 71 is sleeved on the outside of the steel casing 18, and a hoop ring plate 8 is installed on the outside of the steel pipe 71. When there are multiple hoop ring plates 8, they are arranged outside the steel pipe 71 at intervals from top to bottom, and stiffening plates 9 are arranged between adjacent ring plates. The number of the hoop ring plates 8 corresponds to the number of the cross bar groups. Each cross bar group includes two second cross bars 3 symmetrically arranged in an eight-shaped shape, one end of the second cross bar 3 is connected to the hoop ring plate 8, and the other end of the second cross bar 3 is connected to the steel hanging box wall 17; when there are multiple cross bar groups, the second cross bars 3 between adjacent cross bar groups are connected by vertical struts 5, the outer sides of multiple cross bar groups are fixed by diagonal struts 6, and the inner sides of the two second cross bars 3 in the cross bar group are fixed by struts 4.
[0041] In this embodiment, there are four layers of hoop plates 8 and second cross bars 3 corresponding to each other from top to bottom. The number of hoop plates and second cross bars 3 is determined according to the effects of external water pressure, water flow force and wave force on the hanging box when the hanging box is lowered, and then the force generated on the guide limit device of the present application is determined. The number of hoop plates 8 and second cross bars 3 is determined by finally calculating the force generated by the guide limit device.
[0042] The present technical solution may also include the following technical details to better achieve the technical effect: after the steel hanging box is lowered and fine-tuned into place, C30 concrete is poured between the steel pipe 71 and the steel casing 18, and the bottom limiting device 14 and the steel casing 18 are firmly connected through the concrete layer.
[0043] The present technical scheme may also include the following technical details to better achieve the technical effect: the steel wedge block 12 is temporarily fixed to the guide groove 11 by a pin before the steel hanging box is lowered, and a steel wire rope is installed on the steel wedge block 12. After the steel hanging box is lowered into place, the steel wedge block 12 is lifted up by the steel wire rope, and the pin is pulled out. The steel wedge block 12 adjusts its own position under the action of its own weight to position the entire steel hanging box.
[0044] This technical solution can also include the following technical details to better achieve the technical effect: before the steel hanging box is lowered, sand is filled into the steel casing 18 where the guide limit device is set to the top elevation of the bottom limit device 14, and then C30 concrete is poured within the elevation range of the guide device 15.
[0045] The double-walled steel hoisting box guiding and limiting device greatly enhances the strength of the guiding and limiting device and the steel casing 18 by filling sand in the steel casing 18, pouring concrete, and filling C30 concrete between the annular hoop steel pipe 71 and the steel casing 18. The steel hoisting box ring plate 16 is connected to the annular hoop ring plate 8 by a connecting truss, and the force transmission path is clear, ensuring that the guiding and limiting device and the steel casing 18 structure are not damaged under various adverse working conditions in the sea. The guiding device 15 can adjust the position of the steel hoisting box to ensure the precise positioning of the steel hoisting box.
[0046] The present invention also provides a construction method using the double-walled steel hanging box guide and limit device, comprising the following steps:
[0047] S1 steel hoisting box guide limit device processing, the steel wedge block 12 of the guide device 15 is temporarily fixed on the guide groove 11 by a pin before the steel hoisting box is lowered; before the double-walled steel hoisting box is lowered as a whole, sand is poured into the steel casing 18 where the guide limit device is set to the top elevation of the limit device, and then C30 concrete is poured within the elevation range of the guide device 15;
[0048] S2 The steel box is lowered as a whole: After the steel box is processed, it is hoisted as a whole by floating crane. After preliminary positioning, the annular clamp of the bottom limit device 14 is inserted into the steel casing 18, and the steel box is lowered as a whole to the designed elevation position;
[0049] S3 Adjustment of the guide limit device of the steel hanging box: After the steel hanging box is lowered into place, the steel wedge block 12 of the guide device 15 is lifted up by the steel wire rope, and the pin is pulled out. The steel wedge block 12 adjusts its position under the action of its own weight to position the entire steel hanging box;
[0050] S3 Steel hoisting box guide limit device fixation: After the steel hoisting box is finely adjusted into place, C30 concrete is poured between the limit device clamp and the steel casing 18, and the bottom limit device 14, the limit flat joint and the steel casing 18 are firmly connected respectively.
[0051] The present technical scheme may also include the following technical details to better achieve the technical effect: S1 specifically includes: before the double-walled steel hanging box is lowered as a whole, the top limit flat joint 13, the bottom limit device 14 and the guide device 15 are processed, and they are firmly welded to the steel hanging box wall 17 respectively, and the wall of the connection part between the top limit flat joint 13, the bottom limit device 14, the guide device 15 and the steel hanging box shall be locally strengthened.
[0052] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes. They can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the embodiments shown and described herein.
Claims
1. A double-walled steel hanging box guide and limit device, characterized in that: include: Top limit parallel joint, bottom limit device and guide device; The top limit flat joint includes a steel pipe and a column head. The column head is fixed to one end of the steel pipe and welded to the wall of the steel hanging box through the column head. The other end of the steel pipe is welded and fixed to the steel casing of the bored pile after the steel hanging box is accurately positioned. The bottom limiting device includes a connecting truss and an annular hoop, one end of the connecting truss is connected to the wall of the steel hanging box, and the other end is connected to the annular hoop, and the bottom limiting device is fixed to the steel casing through a concrete layer; The guide device includes a first cross bar, a guide groove, and a steel wedge block; after the steel hanging box is lowered into place, the wedge surface of the guide groove is opposite to the steel casing, the steel wedge block is arranged between the guide groove and the steel casing, and the guide device is located above the bottom limiting device.
2. The double-walled steel hanging box guide and limit device according to claim 1, characterized in that: The annular hoop comprises a steel pipe and a hoop ring plate; the connecting truss comprises a crossbar group; The steel pipe is sleeved on the outside of the steel casing, and a hoop ring plate is installed on the outside of the steel pipe. When there are multiple hoop ring plates, they are arranged outside the steel pipe at intervals from top to bottom, and stiffening plates are arranged between adjacent ring plates. The number of the hoop ring plates corresponds to the number of the cross bar groups one by one, and each cross bar group includes two second cross bars symmetrically arranged in an eight-shaped shape, one end of the second cross bar is connected to the hoop ring plate, and the other end of the second cross bar is connected to the wall of the steel hanging box; when there are multiple cross bar groups, the second cross bars between adjacent cross bar groups are connected by vertical braces, the outer sides of multiple cross bar groups are fixed by diagonal braces, and the inner sides of the two second cross bars in the cross bar group are fixed by braces.
3. The double-walled steel hanging box guide and limit device according to claim 2, characterized in that: When the steel hanging box is lowered and fine-tuned into place, concrete is poured between the steel pipe and the steel casing, and the bottom limit device is connected to the steel casing through the concrete layer.
4. The double-walled steel hanging box guide and limit device according to claim 1, characterized in that: The steel wedge block is temporarily fixed on the guide groove by a latch before the steel hanging box is lowered, and a steel wire rope is installed on the steel wedge block.
5. The double-walled steel hanging box guide and limit device according to claim 1, characterized in that: Before the steel hanging box is lowered, sand is filled into the steel casing where the guide limit device is set to the top elevation of the bottom limit device, and then C30 concrete is poured within the elevation range of the guide device.
6. A construction method using the double-walled steel hanging box guide and limit device as claimed in any one of claims 1 to 5, characterized in that: The following steps are involved: S1 steel hoisting box guide limit device processing, the steel wedge block of the guide device is temporarily fixed on the guide groove with a pin before the steel hoisting box is lowered; before the double-walled steel hoisting box is lowered as a whole, sand is poured into the steel casing where the guide limit device is set to the top elevation of the limit device, and then C30 concrete is poured within the elevation range of the guide device; S2 steel hoisting box is lowered as a whole: after the steel hoisting box is processed, it is hoisted as a whole by floating crane. After preliminary positioning, the annular clamp of the bottom limit device is inserted into the steel casing, and the steel hoisting box is lowered as a whole to the designed elevation position; S3 Adjustment of the guide limit device of the steel hanging box: After the steel hanging box is lowered into place, the steel wedge block of the guide device is lifted up by the steel wire rope, and the pin is pulled out. The steel wedge block adjusts its position under the action of its own weight to position the entire steel hanging box; S3 steel hoisting box guide limit device fixation: After the steel hoisting box is finely adjusted into place, C30 concrete is poured between the limit device clamp and the steel casing, and the bottom limit device, limit flat joint and steel casing are firmly connected respectively.
7. The construction method according to claim 6, characterized in that: The S1 specifically includes: before the double-walled steel hanging box is lowered as a whole, the top limit flat joint, the bottom limit device and the guide device are processed, and they are firmly welded to the wall of the steel hanging box respectively. The wall of the connection part between the top limit flat joint, the bottom limit device, the guide device and the steel hanging box must be locally strengthened.
Citation Information
Patent Citations
Rapid positioning device for installation of steel hanging box
CN213741149U
Adjusting device for adjusting horizontal position of steel hanging box by means of steel casing
CN214832810U
Double-wall steel cofferdam sinking positioning adjustable guide device
CN218757552U
Cited By
Rapid limiting and anti-swing device for super-large water head steel hanging box under severe sea condition
CN122190262A