Machine tool system regular preventive maintenance optimization method based on non-dominated genetic algorithm
Regular preventive maintenance optimization of the machine tool system through non-dominant genetic algorithms, solving the problem of difficult to balance availability and maintenance costs in maintenance cycle modeling in the prior art, and achieving the effect of reducing maintenance costs and improving maintenance efficiency.
Patent Information
- Application Number
- CN202411124374.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-29
AI Technical Summary
In the modeling of machine tool maintenance cycles, it is difficult to minimize maintenance costs while increasing availability, and ignore the randomness and uncertainty of faults.
The machine tool system is regularly preventive maintenance optimization based on non-dominant genetic algorithms. By dividing the system, establishing reliability and cost models, and multi-objective optimization, Pareto optimal solution set is generated and the optimal maintenance plan is selected.
While reducing the maintenance costs of machine tool systems, it improves maintenance efficiency, ensures reliability and availability, adapts to different specific needs, and provides a non-unique optimal maintenance plan.
Smart Images

Figure CN119045451A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of industrial equipment preventive maintenance optimization, and in particular to a periodic preventive maintenance optimization method for a machine tool system based on a non-dominated genetic algorithm. Background Art
[0002] As the "mother machine of industry", CNC machine tools dominate the technological transformation of the manufacturing industry and promote the process of national industrialization and intelligence. As early as 2010, my country became the world's largest machine tool producer. However, domestic CNC machine tools have always been in a state of "big but not strong", specifically manifested in the fact that low- and medium-end CNC machine tools do not have international competitive advantages, resulting in overcapacity, while high-end CNC machine tools rely more on imports. The bottom line is that domestic CNC machine tools are not reliable. In response to this severe situation, my country has formulated "Made in China 2025", elevating high-end CNC machine tools to strategic equipment, and striving to achieve the goal of a manufacturing power.
[0003] The inherent reliability of CNC machine tools is determined before they leave the factory, but this is not the final reliability of the entire machine tool. It also includes the operational reliability during the service phase. Therefore, adopting a reasonable maintenance strategy can effectively maintain the inherent reliability of the machine tool and improve operational reliability. The maintenance strategy refers to the maintenance policy and maintenance decision made in the service phase for the deterioration of the equipment, which can restore the faulty equipment to normal and avoid the occurrence of some potential failures, thereby reducing maintenance costs and maximizing equipment utilization. CNC machine tools usually adopt a combination of preventive maintenance and post-maintenance maintenance measures.
[0004] Post-maintenance refers to maintenance activities carried out after a system fails or is damaged, and can only be used for passive maintenance. Therefore, it does not require planned or preventive arrangements in advance, and can reduce the cost of equipment maintenance and upkeep. However, for equipment with frequent failures, it is likely to lead to long maintenance time, high maintenance costs, and easy safety accidents.
[0005] Preventive maintenance is a series of maintenance and inspection activities implemented before a failure may occur, in order to prevent problems before they occur. It is a typical proactive maintenance. Although preventive maintenance increases downtime and downtime, the maintenance costs required are generally less than passive maintenance. Maintaining, servicing or replacing equipment in advance according to a scheduled time or plan to keep the equipment in the specified normal working condition can slow down the performance degradation of the product, improve equipment availability, and thus reduce the frequency of failures and maintenance costs.
[0006] Li et al. implemented economic design by combining CUSUM chart and incomplete preventive maintenance strategy based on service life, and then established an optimization model for minimizing expected cost rate; Zhang Qingshan et al. established an incomplete maintenance decision model with the goal of minimizing maintenance cost based on a mixed failure rate model under the premise of ensuring equipment effectiveness and reliability, and obtained the optimal maintenance plan; Lee et al. used conditional reliability threshold instead of system reliability threshold, and used a mixed failure rate model to describe the impact of incomplete preventive maintenance activities, and determined the optimal conditional reliability threshold and the optimal number of preventive maintenance activities by minimizing the expected total maintenance cost per unit time; Li et al. evaluated the importance of machine tools on automated production lines, divided them into three groups: key machine tools, secondary machine tools and general machine tools, and developed a group maintenance method based on delay time theory; Wang Jinhe et al. applied the queuing theory model to a parallel system composed of multiple devices to maximize the savings in maintenance costs and established an optimal group maintenance model.
[0007] Although the above-mentioned machine tool maintenance strategy formulation has achieved certain results, the current modeling of the maintenance cycle generally aims at maximizing availability or minimizing maintenance costs. However, in actual engineering, users often hope to achieve high availability while minimizing maintenance costs. The relationship between maximizing availability and minimizing maintenance costs is contradictory. Furthermore, the current modeling of the maintenance cycle often ignores the randomness and uncertainty of failures.
[0008] Therefore, how to provide a periodic preventive maintenance optimization method for a machine tool system based on a non-dominated genetic algorithm is an urgent problem to be solved by those skilled in the art. Summary of the invention
[0009] One purpose of the present invention is to propose a method for optimizing the periodic preventive maintenance of a machine tool system based on a non-dominated genetic algorithm. The present invention uses a non-dominated genetic algorithm to optimize the periodic preventive maintenance of a machine tool system. The subsystems are divided according to the structure and functional characteristics of the CNC machine tool, and appropriate maintenance methods are selected according to the failure rate trends of different subsystems, including corrective maintenance and periodic preventive maintenance. At the same time, the present invention considers two key factors, maintenance cost and maintenance time, and models and optimizes them respectively. Through this method, the present invention improves the maintenance efficiency while reducing the maintenance cost of the machine tool system, ensures the reliability and availability of the machine tool system, and adapts to different specific needs.
[0010] The method for optimizing the periodic preventive maintenance of a machine tool system based on a non-dominated genetic algorithm according to an embodiment of the present invention comprises the following steps:
[0011] S1. Collect machine tool system fault data, and classify the faults into different subsystems according to components to obtain a fault data set for each subsystem;
[0012] S2. Reliability modeling is performed on the fault data set of each subsystem. Weibull distribution is selected as the fitting function of the machine tool subsystem fault interval time data. The shape parameters and scale parameters of the model are estimated using the maximum likelihood estimation method to establish reliability modeling of the machine tool fault interval time data.
[0013] S3. Establish a total cost model for preventive maintenance. According to the maintenance requirements of different subsystems, three maintenance methods, replacement, repair and maintenance, are adopted. The total cost of preventive maintenance is calculated comprehensively by considering the cost of preventive maintenance, the unused value of parts caused by replacement, and the cost of minor repairs for random failures.
[0014] S4. Establish a total operation time model for preventive maintenance, combine the time required for each preventive maintenance with the expected time for minor repairs to handle sudden failures, and calculate the total operation time for preventive maintenance;
[0015] S5. Construct a multi-objective optimization function of maintenance time and maintenance cost, and solve the multi-objective optimization of maintenance time and maintenance cost;
[0016] S6. Use the multi-objective optimization method of non-dominated genetic algorithm to generate the Pareto optimal solution set and select the optimal maintenance plan from it;
[0017] S7. Determine the final machine tool system maintenance plan based on the optimal maintenance plan in the Pareto optimal solution set and combined with specific needs.
[0018] Optionally, the S2 specifically includes:
[0019] S21, for each subsystem fault data set X i ={x 1i ,x 2i ,…,x ni}, where i represents the number of the subsystem, n represents the total number of subsystems, ni represents the number of fault data collected by the ith subsystem, and Weibull distribution is selected as the fitting function of the subsystem fault interval data;
[0020] S22. Set the probability density function of Weibull distribution to:
[0021]
[0022] Where f(t) represents the probability density function at time t, t represents time, η represents the scale parameter of Weibull distribution, and β represents the shape parameter of Weibull distribution;
[0023] S23. Use the maximum likelihood estimation method to estimate the parameters of the Weibull distribution model, and calculate the log-likelihood function based on the fault data set:
[0024]
[0025] Among them, lnL(η,β|X) represents the log-likelihood function, t i represents the i-th fault data, N represents the number of data in the fault data set, and X represents the fault data set of all subsystems;
[0026] S24. By solving the partial derivative equations of the log-likelihood function, the estimated values of the parameters η and β, i.e., the maximum likelihood estimates, are obtained:
[0027]
[0028] in, represents the partial derivative of the log-likelihood function lnL(η,β|X) with respect to the parameter η, represents the partial derivative of the log-likelihood function lnL(η,β|X) with respect to the parameter β;
[0029] S25. Substitute the obtained parameters η and β into the Weibull distribution function to construct the reliability function of the subsystem:
[0030]
[0031] Where R(t) represents the reliability function value at time t;
[0032] S26. Finally, the reliability model of all subsystems is obtained.
[0033] Optionally, the S3 specifically includes:
[0034] S31. Define the maintenance method of each subsystem ij , where i represents the subsystem number, j represents the operation during the jth preventive maintenance, and the maintenance methods include maintenance m ij =0, maintenance m ij = 1 and replace m ij =2;
[0035] S32. Calculate the single preventive maintenance cost c for each subsystem ij :
[0036] c ij =c s +c aij ;
[0037] Among them, c s represents the fixed maintenance cost of the subsystem, c aij represents uncertain costs;
[0038] S33, uncertain cost c aij Calculated based on subsystem failure rate:
[0039]
[0040] Among them, c xi Indicates the single maintenance cost of the subsystem:
[0041]
[0042] Among them, c xmaxi Indicates that the subsystem reaches the maximum unreliability F maxi The maintenance cost at time F ij represents the immediate unreliability of the subsystem at the jth maintenance, F maxi represents the maximum unreliability of the subsystem, c ci represents the replacement cost of the subsystem;
[0043] S34. Calculate the unused value of the subsystem when it is replaced c wij :
[0044]
[0045] Among them, v i It represents the total utilization value of the subsystem from the initial state to the minimum reliability, R ij- Represents the reliability of the subsystem before replacement, R mini Indicates the minimum reliability allowed for the subsystem;
[0046] S35. Calculate the expected cost of minor repairs to handle sudden failures during the preventive maintenance cycle c mj :
[0047]
[0048] Among them, c ri represents the minor repair cost of subsystem i, R i (t) represents the reliability of subsystem i at time t, and T represents the preventive maintenance cycle;
[0049] S36, finally the single preventive maintenance cost of each subsystem c ij 、Unutilized value c wij and the expected cost of minor repairs c mj Add up and get the total cost of preventive maintenance M c :
[0050]
[0051] Where m represents the number of preventive maintenance in the study period.
[0052] Optionally, the S4 specifically includes:
[0053] S41. Define the maintenance time t required for each preventive maintenance of the machine tool ij , where i represents the subsystem number, j represents the jth preventive maintenance, and the maintenance time is calculated according to different maintenance methods;
[0054] S42, maintenance time t ij According to the maintenance mode of subsystem ij Perform segmented calculations:
[0055]
[0056] Among them, t 0i represents the time required for maintenance of subsystem i, t xi represents the time required for maintenance of subsystem i, t ci It represents the time required for subsystem i to be replaced;
[0057] S43. Calculate the total operation time T for each preventive maintenance j :
[0058] T j =max(t 1j ,t 2j ,…,t nj );
[0059] Among them, t 1j ,t 2j ,…,t nj represents the maintenance time of each subsystem at the jth preventive maintenance, and n represents the total number of subsystems;
[0060] S44. Consider the expected time for minor repairs required to handle unexpected failures during the preventive maintenance cycle:
[0061]
[0062] Among them, t rj represents the expected time of minor repairs in the jth preventive maintenance cycle of subsystem i, R i (t) represents the reliability of subsystem i at time t, and T represents the preventive maintenance cycle;
[0063] S45. Calculate the total operation time M of preventive maintenance t , the operation time of each preventive maintenance and the expected time of minor repairs are accumulated:
[0064]
[0065] Where m represents the number of preventive maintenance in the study period.
[0066] Optionally, the S5 specifically includes:
[0067] S51. Define the maintenance time optimization objective function f 1 (M t ), where M t represents the total operation time of preventive maintenance, and the goal is to minimize the total operation time:
[0068] f 1 (M t )=min(M t );
[0069] S52. Define the maintenance cost optimization objective function f 2 (M c ), where M c represents the total cost of preventive maintenance, and the goal is to minimize the total cost:
[0070] f 2 (M c )=min(M c );
[0071] S53, f 1 (M t ) and f 2 (M c ) as independent optimization objectives to construct a multi-objective optimization problem:
[0072] min{f 1 (M t ),f 2 (M c )};
[0073] S54, introduce constraints and define the reliability R of subsystem i i (t) At time t, the minimum reliability R must be met mini Constraints:
[0074]
[0075] Where T represents the preventive maintenance cycle, R mini It represents the minimum reliability allowed for the operation of subsystem i;
[0076] S55. Limit the maximum time T of the maintenance plan max , to ensure that the maintenance time within the study interval does not exceed the specified upper limit;
[0077] S56. Combine the multi-objective optimization function and constraints to build the final multi-objective optimization problem model:
[0078] min{f 1 (M t ),f 2 (M c )}, subject to R i (t)≥R mini ,T≤T max ;
[0079] S57. Optimize the multi-objective optimization problem model and determine the Pareto optimal solution set that satisfies all constraints.
[0080] Optionally, the multi-objective problem of the multi-objective optimization method of the non-dominated genetic algorithm satisfies any two solutions z 1 and z 2 There are two kinds of relationships between them: ① one solution dominates another solution; ② no solution dominates another solution;
[0081] If 1 Domination 2 , then two conditions must be met at the same time: ① For all targets z 1 Non-inferior to z 2 ;② At least one target z 1 Better than z 2, All non-dominated solutions of the multi-objective optimization problem constitute the Pareto optimal set;
[0082] The kth individual z in the g+1th generation population k There are u individuals in the population that dominate it, and its rank in the population (z k )for:
[0083] rank(z k )=1+u.
[0084] The rank of all non-inferior solutions in the Pareto optimal set is 1. When the number of cycles required by the algorithm is reached, the solution with rank 1 is selected to generate the Pareto optimal set.
[0085] The beneficial effects of the present invention are:
[0086] First, the present invention divides the machine tool subsystems according to the structural parts and functional characteristics of the CNC machine tool, and finds out the subsystems with higher fault occurrence frequency. For the subsystems with low fault occurrence frequency, corrective maintenance is adopted, and for the subsystems with obvious increasing fault rate, regular preventive maintenance is selected.
[0087] Secondly, the present invention adopts three maintenance methods, namely replacement, repair and maintenance, and considers the preventive maintenance cost of each subsystem, the unutilized value of parts caused by replacement, and the minor repair cost of random failures to establish the total cost of preventive maintenance, and divides the cost of each subsystem into fixed cost and variable cost to achieve modeling of economic correlation.
[0088] In addition, the present invention also considers the maintenance time required for preventive maintenance and the expected time for minor repairs to handle sudden failures within a preventive maintenance cycle to establish a total time model for preventive maintenance.
[0089] Finally, the present invention optimizes maintenance time and maintenance cost simultaneously, which belongs to a multi-objective optimization problem. It adopts a non-dominated genetic algorithm to optimize and solve, and obtains an optimized maintenance plan for the machine tool. The situation where multiple objectives are optimal at the same time does not exist, so the final maintenance plan is not unique and can be selected according to specific needs. BRIEF DESCRIPTION OF THE DRAWINGS
[0090] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0091] Figure 1 A flowchart of a method for optimizing periodic preventive maintenance of a machine tool system based on a non-dominated genetic algorithm proposed by the present invention;
[0092] Figure 2 A schematic diagram of the division of CNC machine tool subsystems of the periodic preventive maintenance optimization method for machine tool systems based on a non-dominated genetic algorithm proposed by the present invention;
[0093] Figure 3 A graph showing the failure data of the spindle system of the machine tool system based on the non-dominated genetic algorithm proposed by the present invention;
[0094] Figure 4 A curve diagram of feed system failure data of the periodic preventive maintenance optimization method for a machine tool system based on a non-dominated genetic algorithm proposed by the present invention;
[0095] Figure 5 A curve diagram of fault data of a control electrical system of a machine tool system periodic preventive maintenance optimization method based on a non-dominated genetic algorithm proposed by the present invention;
[0096] Figure 6 A curve diagram of tool magazine system failure data of the periodic preventive maintenance optimization method for machine tool system based on non-dominated genetic algorithm proposed by the present invention;
[0097] Figure 7A schematic diagram of the Pareto rank of individuals in a population of a periodic preventive maintenance optimization method for a machine tool system based on a non-dominated genetic algorithm proposed by the present invention;
[0098] Figure 8 This is a scatter diagram of target values of solutions under different population algebras for the periodic preventive maintenance optimization method for machine tool systems based on a non-dominated genetic algorithm proposed in the present invention. DETAILED DESCRIPTION
[0099] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the components related to the present invention.
[0100] refer to Figure 1-8 , a periodic preventive maintenance optimization method for machine tool systems based on non-dominated genetic algorithm includes the following steps:
[0101] S1. Collect machine tool system fault data, and classify the faults into different subsystems according to components to obtain a fault data set for each subsystem;
[0102] S2. Reliability modeling is performed on the fault data set of each subsystem. Weibull distribution is selected as the fitting function of the machine tool subsystem fault interval time data. The shape parameters and scale parameters of the model are estimated using the maximum likelihood estimation method to establish reliability modeling of the machine tool fault interval time data.
[0103] S3. Establish a total cost model for preventive maintenance. According to the maintenance requirements of different subsystems, three maintenance methods, replacement, repair and maintenance, are adopted. The total cost of preventive maintenance is calculated comprehensively by considering the cost of preventive maintenance, the unused value of parts caused by replacement, and the cost of minor repairs for random failures.
[0104] S4. Establish a total operation time model for preventive maintenance, combine the time required for each preventive maintenance with the expected time for minor repairs to handle sudden failures, and calculate the total operation time for preventive maintenance;
[0105] S5. Construct a multi-objective optimization function of maintenance time and maintenance cost, and solve the multi-objective optimization of maintenance time and maintenance cost;
[0106] S6. Use the multi-objective optimization method of non-dominated genetic algorithm to generate the Pareto optimal solution set and select the optimal maintenance plan from it;
[0107] S7. Determine the final machine tool system maintenance plan based on the optimal maintenance plan in the Pareto optimal solution set and combined with specific needs.
[0108] In this implementation, S2 specifically includes:
[0109] S21, for each subsystem fault data set X i ={x 1i ,x 2i ,…,x ni}, where i represents the number of the subsystem, n represents the total number of subsystems, ni represents the number of fault data collected by the ith subsystem, and Weibull distribution is selected as the fitting function of the subsystem fault interval data;
[0110] S22. Set the probability density function of Weibull distribution to:
[0111]
[0112] Where f(t) represents the probability density function at time t, t represents time, η represents the scale parameter of Weibull distribution, and β represents the shape parameter of Weibull distribution;
[0113] S23. Use the maximum likelihood estimation method to estimate the parameters of the Weibull distribution model, and calculate the log-likelihood function based on the fault data set:
[0114]
[0115] Among them, lnL(η,β|X) represents the log-likelihood function, t i represents the i-th fault data, N represents the number of data in the fault data set, and X represents the fault data set of all subsystems;
[0116] S24. By solving the partial derivative equations of the log-likelihood function, the estimated values of the parameters η and β, i.e., the maximum likelihood estimates, are obtained:
[0117]
[0118] in, represents the partial derivative of the log-likelihood function lnL(η,β|X) with respect to the parameter η, represents the partial derivative of the log-likelihood function lnL(η,β|X) with respect to the parameter β;
[0119] S25. Substitute the obtained parameters η and β into the Weibull distribution function to construct the reliability function of the subsystem:
[0120]
[0121] Where R(t) represents the reliability function value at time t;
[0122] S26. Finally, the reliability model of all subsystems is obtained.
[0123] In this implementation, S3 specifically includes:
[0124] S31. Define the maintenance method of each subsystem ij , where i represents the subsystem number, j represents the operation during the jth preventive maintenance, and the maintenance methods include maintenance m ij =0, maintenance m ij = 1 and replace m ij =2;
[0125] S32. Calculate the single preventive maintenance cost c for each subsystem ij :
[0126] c ij =c s +c aij ;
[0127] Among them, c s represents the fixed maintenance cost of the subsystem, c aij represents uncertain costs;
[0128] S33, uncertain cost c aij Calculated based on subsystem failure rate:
[0129]
[0130] Among them, c xi Indicates the single maintenance cost of the subsystem:
[0131]
[0132] Among them, c xmaxi Indicates that the subsystem reaches the maximum unreliability F maxi The maintenance cost at time F ij represents the immediate unreliability of the subsystem at the jth maintenance, F maxi represents the maximum unreliability of the subsystem, c ci represents the replacement cost of the subsystem;
[0133] S34. Calculate the unused value of the subsystem when it is replaced c wij :
[0134]
[0135] Among them, v i It represents the total utilization value of the subsystem from the initial state to the minimum reliability, R ij- Represents the reliability of the subsystem before replacement, R mini Indicates the minimum reliability allowed for the subsystem;
[0136] S35. Calculate the expected cost of minor repairs to handle sudden failures during the preventive maintenance cycle cmj :
[0137]
[0138] Among them, c ri represents the minor repair cost of subsystem i, R i (t) represents the reliability of subsystem i at time t, and T represents the preventive maintenance cycle;
[0139] S36, finally the single preventive maintenance cost of each subsystem c ij 、Unutilized value c wij and the expected cost of minor repairs c mj Add up and get the total cost of preventive maintenance M c :
[0140]
[0141] Where m represents the number of preventive maintenance in the study period.
[0142] In this implementation, S4 specifically includes:
[0143] S41. Define the maintenance time t required for each preventive maintenance of the machine tool ij , where i represents the subsystem number, j represents the jth preventive maintenance, and the maintenance time is calculated according to different maintenance methods;
[0144] S42, maintenance time t ij According to the maintenance mode of subsystem ij Perform segmented calculations:
[0145]
[0146] Among them, t 0i represents the time required for maintenance of subsystem i, t xi represents the time required for maintenance of subsystem i, t ci It represents the time required for subsystem i to be replaced;
[0147] S43. Calculate the total operation time T for each preventive maintenance j :
[0148] T j =max(t 1j ,t 2j ,…,t nj );
[0149] Among them, t 1j ,t 2j ,…,t njrepresents the maintenance time of each subsystem at the jth preventive maintenance, and n represents the total number of subsystems;
[0150] S44. Consider the expected time for minor repairs required to handle unexpected failures during the preventive maintenance cycle:
[0151]
[0152] Among them, t rj represents the expected time of minor repairs in the jth preventive maintenance cycle of subsystem i, R i (t) represents the reliability of subsystem i at time t, and T represents the preventive maintenance cycle;
[0153] S45. Calculate the total operation time M of preventive maintenance t , the operation time of each preventive maintenance and the expected time of minor repairs are accumulated:
[0154]
[0155] Where m represents the number of preventive maintenance in the study period.
[0156] In this implementation manner, S5 specifically includes:
[0157] S51. Define the maintenance time optimization objective function f 1 (M t ), where M t represents the total operation time of preventive maintenance, and the goal is to minimize the total operation time:
[0158] f 1 (M t )=min(M t );
[0159] S52. Define the maintenance cost optimization objective function f 2 (M c ), where M c represents the total cost of preventive maintenance, and the goal is to minimize the total cost:
[0160] f 2 (M c )=min(M c );
[0161] S53, f 1 (M t ) and f 2 (M c ) as independent optimization objectives to construct a multi-objective optimization problem:
[0162] min{f 1 (M t),f 2 (M c )};
[0163] S54, introduce constraints and define the reliability R of subsystem i i (t) At time t, the minimum reliability R must be met mini Constraints:
[0164]
[0165] Where T represents the preventive maintenance cycle, R mini It represents the minimum reliability allowed for the operation of subsystem i;
[0166] S55. Limit the maximum time T of the maintenance plan max , to ensure that the maintenance time within the study interval does not exceed the specified upper limit;
[0167] S56. Combine the multi-objective optimization function and constraints to build the final multi-objective optimization problem model:
[0168] min{f 1 (M t ),f 2 (M c )}, subject to R i (t)≥R mini ,T≤T max ;
[0169] S57. Optimize the multi-objective optimization problem model and determine the Pareto optimal solution set that satisfies all constraints.
[0170] In this embodiment, the multi-objective problem of the multi-objective optimization method of the non-dominated genetic algorithm satisfies any two solutions z 1 and z 2 There are two kinds of relationships between them: ① one solution dominates another solution; ② no solution dominates another solution;
[0171] If 1 Domination 2 , then two conditions must be met at the same time: ① For all targets z 1 Non-inferior to z 2 ;② At least one target z 1 Better than z 2, All non-dominated solutions of the multi-objective optimization problem constitute the Pareto optimal set;
[0172] The kth individual z in the g+1th generation population k There are u individuals in the population that dominate it, and its rank in the population (z k )for:
[0173] rank(z k )=1+u.
[0174] The rank of all non-inferior solutions in the Pareto optimal set is 1. When the number of cycles required by the algorithm is reached, the solution with rank 1 is selected to generate the Pareto optimal set.
[0175] The optimization result of machine tool maintenance plan is obtained. The maintenance plan of machine tool can be obtained through multi-objective genetic algorithm, such as Figure 8 As shown in the figure. It can be seen from the figure that when the population generation reaches 150 times, the optimization result has remained stable. In the multi-objective optimization problem, there is no situation where multiple objectives are optimal at the same time, so the final maintenance plan is not unique and can be selected according to specific needs. Example 1 As shown in Table 1, the total number of maintenance times in the first 2500 hours is 5 times. According to the maintenance plan, the expected maintenance time is 36.25h and the expected maintenance cost is 100,390 yuan.
[0176] Table 1 Optimization results of machine tool maintenance plan
[0177]
[0178]
[0179] Table 1 lists in detail the types of maintenance performed on the various subsystems of the machine tool system at different time points. Specifically, at time point 520 hours, the spindle system was replaced (maintenance type 2), while the feed system and control electrical system were repaired (maintenance type 1), and the tool magazine system did not undergo any maintenance (maintenance type 0). At 994 hours, the spindle system was replaced again, while the feed system and control electrical system continued to receive maintenance, and the tool magazine system was replaced.
[0180] As time went by, at 1430 hours, the spindle system was replaced, the feed system was not maintained, the control electrical system was replaced, and the tool magazine system was repaired. At 1833 hours, the spindle system was only repaired, the feed system was still not maintained, and the control electrical system and tool magazine system continued to receive maintenance. Finally, at 2209 hours, the spindle system was replaced again, the feed system and control electrical system were also repaired, and the tool magazine system was not maintained.
[0181] From the overall analysis, the spindle system is frequently replaced and repaired due to its criticality and high failure rate; the control electrical system also needs to be maintained and replaced more frequently to ensure the stability and reliability of the system; while the maintenance frequency of the feed system and tool magazine system is relatively low, which may be related to their low failure rate or less maintenance requirements. Through such a maintenance plan, the service life of the machine tool system can be effectively extended, the risk of sudden failures can be reduced, and the normal operation of the equipment can be ensured.
[0182] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A periodic preventive maintenance optimization method for machine tool systems based on a non-dominated genetic algorithm, characterized in that: The steps include: S1. Collect machine tool system fault data, and classify the faults into different subsystems according to components to obtain a fault data set for each subsystem; S2. Reliability modeling is performed on the fault data set of each subsystem. Weibull distribution is selected as the fitting function of the machine tool subsystem fault interval time data. The shape parameters and scale parameters of the model are estimated using the maximum likelihood estimation method to establish reliability modeling of the machine tool fault interval time data. S3. Establish a total cost model for preventive maintenance. According to the maintenance requirements of different subsystems, three maintenance methods, replacement, repair and maintenance, are adopted. The total cost of preventive maintenance is calculated comprehensively by considering the cost of preventive maintenance, the unused value of parts caused by replacement, and the cost of minor repairs for random failures. S4. Establish a total operation time model for preventive maintenance, combine the time required for each preventive maintenance with the expected time for minor repairs to handle sudden failures, and calculate the total operation time for preventive maintenance; S5. Construct a multi-objective optimization function of maintenance time and maintenance cost, and solve the multi-objective optimization of maintenance time and maintenance cost; S6. Use the multi-objective optimization method of non-dominated genetic algorithm to generate the Pareto optimal solution set and select the optimal maintenance plan from it; S7. Determine the final machine tool system maintenance plan based on the optimal maintenance plan in the Pareto optimal solution set and combined with specific needs.
2. The method for optimizing the periodic preventive maintenance of a machine tool system based on a non-dominated genetic algorithm according to claim 1, characterized in that: The S2 specifically includes: S21. For each subsystem fault data set X i ={x 1i ,x 2i ,…,x ni }, where i represents the subsystem number, n represents the total number of subsystems, ni represents the number of fault data collected by the ith subsystem, and Weibull distribution is selected as the fitting function of the subsystem fault interval data; S22. Set the probability density function of Weibull distribution to: Where f(t) represents the probability density function at time t, t represents time, η represents the scale parameter of Weibull distribution, and β represents the shape parameter of Weibull distribution; S23. Use the maximum likelihood estimation method to estimate the parameters of the Weibull distribution model, and calculate the log-likelihood function based on the fault data set: Among them, lnL(η,β|X) represents the log-likelihood function, t i represents the i-th fault data, N represents the number of data in the fault data set, and X represents the fault data set of all subsystems; S24. By solving the partial derivative equations of the log-likelihood function, the estimated values of the parameters η and β, i.e., the maximum likelihood estimates, are obtained: in, represents the partial derivative of the log-likelihood function lnL(η,β|X) with respect to the parameter η, represents the partial derivative of the log-likelihood function lnL(η,β|X) with respect to the parameter β; S25. Substitute the obtained parameters η and β into the Weibull distribution function to construct the reliability function of the subsystem: Where R(t) represents the reliability function value at time t; S26. Finally, the reliability model of all subsystems is obtained.
3. The method for optimizing periodic preventive maintenance of a machine tool system based on a non-dominated genetic algorithm according to claim 1, characterized in that: The S3 specifically includes: S31. Define the maintenance method of each subsystem ij , where i represents the subsystem number, j represents the operation during the jth preventive maintenance, and the maintenance methods include maintenance m ij =0, maintenance m ij = 1 and replace m ij =2; S32. Calculate the single preventive maintenance cost c for each subsystem ij : c ij =c s +c aij ; Among them, c s represents the fixed maintenance cost of the subsystem, c aij represents uncertain costs; S33, uncertain cost c aij Calculated based on subsystem failure rate: Among them, c xi Indicates the single maintenance cost of the subsystem: Among them, c xmaxi Indicates that the subsystem reaches the maximum unreliability F maxi The maintenance cost at time F ij represents the immediate unreliability of the subsystem at the jth maintenance, F maxi represents the maximum unreliability of the subsystem, c ci represents the replacement cost of the subsystem; S34. Calculate the unused value of the subsystem when it is replaced c wij : Among them, v i It represents the total utilization value of the subsystem from the initial state to the minimum reliability, R ij- Represents the reliability of the subsystem before replacement, R mini Indicates the minimum reliability allowed for the subsystem; S35. Calculate the expected cost of minor repairs to handle sudden failures during the preventive maintenance cycle c mj : Among them, c ri represents the minor repair cost of subsystem i, R i (t) represents the reliability of subsystem i at time t, and T represents the preventive maintenance cycle; S36, finally the single preventive maintenance cost of each subsystem c ij 、Unutilized value c wij and the expected cost of minor repairs c mj Add up and get the total cost of preventive maintenance M c : Where m represents the number of preventive maintenance in the study period.
4. The method for optimizing periodic preventive maintenance of a machine tool system based on a non-dominated genetic algorithm according to claim 1, characterized in that: The S4 specifically includes: S41. Define the maintenance time t required for each preventive maintenance of the machine tool ij , where i represents the subsystem number, j represents the jth preventive maintenance, and the maintenance time is calculated according to different maintenance methods; S42, maintenance time t ij According to the maintenance mode of subsystem ij Perform segmented calculations: Among them, t 0i represents the time required for maintenance of subsystem i, t xi represents the time required for maintenance of subsystem i, t ci It represents the time required for subsystem i to be replaced; S43. Calculate the total operation time T for each preventive maintenance j : T j =max(t 1j ,t 2j ,…,t nj ); Among them, t 1j ,t 2j ,…,t nj represents the maintenance time of each subsystem at the jth preventive maintenance, and n represents the total number of subsystems; S44. Consider the expected time for minor repairs required to handle unexpected failures during the preventive maintenance cycle: Among them, t rj represents the expected time of minor repairs in the jth preventive maintenance cycle of subsystem i, R i (t) represents the reliability of subsystem i at time t, and T represents the preventive maintenance cycle; S45. Calculate the total operation time M of preventive maintenance t , the operation time of each preventive maintenance and the expected time of minor repairs are accumulated: Where m represents the number of preventive maintenance in the study period.
5. The method for optimizing periodic preventive maintenance of a machine tool system based on a non-dominated genetic algorithm according to claim 1, characterized in that: The S5 specifically includes: S51, define the maintenance time optimization objective function f1(M t ), where M t represents the total operation time of preventive maintenance, and the goal is to minimize the total operation time: f1(M t )=min(M t ); S52, define the maintenance cost optimization objective function f2(M c ), where M c represents the total cost of preventive maintenance, and the goal is to minimize the total cost: f2(M c )=min(M c ); S53, f1(M t ) and f2(M c ) as independent optimization objectives to construct a multi-objective optimization problem: min{f1(M t ),f2(M c )}; S54, introduce constraints and define the reliability R of subsystem i i (t) At time t, the minimum reliability R must be met mini Constraints: Where T represents the preventive maintenance cycle, R mini It represents the minimum reliability allowed for the operation of subsystem i; S55. Limit the maximum time of the maintenance plan; S56. Combine the multi-objective optimization function and constraints to build the final multi-objective optimization problem model: min{f1(M t ),f2(M c )},subjectto R i (t)≥R mini ,T≤T max ; S57. Optimize the multi-objective optimization problem model and determine the Pareto optimal solution set that satisfies all constraints.
6. The method for optimizing periodic preventive maintenance of a machine tool system based on a non-dominated genetic algorithm according to claim 1, characterized in that: The multi-objective problem of the multi-objective optimization method of the non-dominated genetic algorithm satisfies two relationships between any two solutions z1 and z2: ① one solution dominates the other solution; ② no solution dominates the other solution; If z1 dominates z2, two conditions must be met at the same time: ① z1 is not inferior to z2 for all targets; ② at least one target z1 is superior to z2 2, All non-dominated solutions of the multi-objective optimization problem constitute the Pareto optimal set; The kth individual z in the g+1th generation population k There are u individuals in the population that dominate it, and its rank in the population (z k )for: rank(z k )=1+u。