Engineering amount management system based on image progress application
By introducing an image progress-based engineering quantity management system in engineering quantity management, combined with engineering quantity calculation software and PM system, the problem of different data sources and poor business linkage in engineering quantity management is solved, and efficient and accurate engineering quantity management is achieved Linked with business processes, improving project work efficiency.
Patent Information
- Application Number
- CN202411017649.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-11-29
AI Technical Summary
Different sources of data during the project volume management process lead to poor data sharing and data permeability of various business departments of project management, long calculation cycle and poor timeliness, and the project volume is converted into upper measurement ledger, material ledger, and lower inspection work station. Link errors and duplicate work are prone to accounts, resulting in low efficiency and accuracy.
Using an engineering quantity management system based on image progress application, combined with engineering quantity calculation software and project management (PM) system, the WBS structure decomposition, standardized calculation of output value and material consumption, and the lower inspection and pricing Control and realize the homologous origin of engineering quantity data and the vertical connection and horizontal linkage of business processes.
It improves the efficiency and accuracy of project quantity management in the calculation stage, solves the problems of data sharing and permeability, realizes the linkage of business processes, reduces duplicate work, and improves project work efficiency and refined management.
Smart Images

Figure CN119047998A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of engineering quantity management, and more specifically to an engineering quantity management system based on visual progress application. Background Art
[0002] Project quantity management is an effective means to reduce enterprise costs and is also a basic work of the technical management system. For construction companies, most of the current project quantity management, from quantity calculation to quantity usage and quantity control, still adopt an offline working method. There is a lack of linkage between various businesses and they face many problems.
[0003] (1) In the calculation stage of engineering quantity management, there is a situation of multi-person and multi-professional collaboration. The current situation of engineering quantity calculation in most projects mainly relies on auxiliary software such as Excel and CAD, and external experience, which leads to long calculation cycle and poor timeliness. At the same time, it causes the project WBS decomposition and quantity calculation standards to be inconsistent, making it difficult to form a structural decomposition that meets the needs of progress control. It also causes the work of multi-person collaborative quantity calculation to be cumbersome and prone to errors when the results are collected upward. In the process of converting engineering quantities into measurement ledgers, material ledgers, and inspection ledgers, tens of thousands of quantity calculation contents need to be linked to hundreds of contract lists and material codes. At present, most of this kind of work uses Excel formula links. How to link depends entirely on personal experience. It is very easy to have link errors and link duplications. In addition, when subsequent applications need to be changed and adjusted, the business basically needs to be redone, wasting manpower.
[0004] (2) During the application phase of engineering quantity management, the engineering quantity cannot be effectively combined with the needs of management activities such as output value progress, subcontracting, and material saving and overrun, resulting in poor linkage between engineering quantity control and execution, that is, the problem of data homology and data penetration between various businesses.
[0005] Chinese patent CN114648246A discloses a data statistics method and system for construction site progress records and construction ledgers, but the patent only provides a statistical method for the visual progress of a project, and does not combine the application of the visual progress in project quantity management. Summary of the invention
[0006] The technical problem to be solved by the present invention is to provide a construction quantity management system based on the visual progress application, to solve the problems of different data sources in the construction quantity management process, data sharing and data penetration of various business departments of project management, and to improve the efficiency and accuracy of construction quantity review and establishment of 0# ledger in the quantity calculation stage of construction quantity management.
[0007] In order to solve the above technical problems, the technical solutions adopted by the present invention are as follows.
[0008] A quantity management system based on visual progress application includes quantity calculation software for decomposing WBS structure and realizing standardized quantity calculation and PM system for managing quantity data; after the quantity calculation software calculates the project quantity in detail, it pushes the quantity to the PM system, sets the project progress supply points and process methods, and creates a visual progress that matches the progress control needs. During the construction process, the visual progress of the day is reported according to the physical projects completed every day, and the PM system automatically calculates the output value, the material consumption, and controls the pricing of the next inspection.
[0009] To further optimize the technical solution, the engineering quantity calculation software adopts Mengcheng quantity calculation software, refers to cloud structure and WBS dictionary, calculates the project engineering quantity in detail and standardizes the quantity calculation content.
[0010] To further optimize the technical solution, the engineering quantity data initialization of the PM system is to apply the PM system to the quantity calculation content and connect the system front-end business to import the upper measurement list, material dictionary code, business unit and lower subcontract list, and connect the contract list and material code to the quantity calculation content in the system, and establish the 0# ledger of the upper measurement ledger, material ledger, and lower work inspection ledger, and the structural decomposition data as the basis for the implementation of engineering quantity management.
[0011] To further optimize the technical solution, the PM system automatically calculates the output value by calculating and summarizing the list of project quantities completed in the month based on the image progress locked in the month, and then automatically calculates the output value completed in the month based on the unit price of the project quantity 0# ledger list established in the initialization phase.
[0012] To further optimize the technical solution, the PM system automatically calculates the material consumption based on the visual progress locked in the month to summarize the actual project volume completed in the month, and automatically matches the corresponding work surface, process and team code, and then automatically calculates the material consumption for the month by team and part based on the material code of the engineering material ledger established in the initialization phase, and compares the actual material consumption to analyze savings and overages.
[0013] To further optimize the technical solution, the PM system controls the price calculation of the work inspection and decomposes the engineering quantity. When inspecting the work, it is mandatory to control the price calculation of the completed engineering quantity in the contract with the business unit, and control the inspection engineering quantity not to exceed the decomposed engineering quantity.
[0014] Due to the adoption of the above technical scheme, the technical progress achieved by the present invention is as follows.
[0015] The present invention provides an engineering quantity management system based on the image progress application, which improves the efficiency and accuracy of engineering quantity review and establishment of 0# ledger in the quantity calculation stage of engineering quantity management; unifies the engineering image progress with the engineering quantity calculation content in the project usage control stage, and solves the problem of low business standardization and informatization in the usage control stage based on the image progress application, resulting in the inability to fully share data, and the lack of connection in the application of business data such as measurement, material saving and overrun, and work inspection at the lower level, thereby realizing the homology of engineering quantity management data and achieving the effect of vertical connection and horizontal linkage of business processes. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural schematic diagram of the present invention;
[0017] Figure 2 Create a schematic diagram of the structure and WBS dictionary decomposition for the present invention;
[0018] Figure 3 It is a schematic diagram of the engineering quantity calculation diagram of the present invention;
[0019] Figure 4 This is a schematic diagram of the data synchronization to PM system of the present invention;
[0020] Figure 5 This is a schematic diagram of the connection between the present invention and the upper metering list;
[0021] Figure 6 This is a schematic diagram of the material coding and hanging of the present invention;
[0022] Figure 7 This is a schematic diagram of the subcontract list being attached by the business units of the present invention;
[0023] Figure 8 This is a schematic diagram of automatic decomposition of the project structure of the present invention;
[0024] Fig. 9 Establishing a visual progress diagram for the present invention;
[0025] Fig.10 It is a schematic diagram of filling in the daily progress of the present invention;
[0026] Fig.11 This is a schematic diagram of locking the monthly image progress of the present invention;
[0027] Fig.12 This is a schematic diagram of automatic calculation of output value of the present invention;
[0028] Fig.13 This is a schematic diagram of the calculation data produced by teams in the present invention;
[0029] Fig.14 This is a schematic diagram of automatic calculation of material consumption of the present invention;
[0030] Fig.15 It is the main material section super analysis table of the present invention;
[0031] Fig.16 This is a schematic diagram of the present invention's control over the price calculation of downstream inspection work. DETAILED DESCRIPTION
[0032] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0033] A construction quantity management system based on visual progress application, combined with Figure 1 As shown in the figure, it includes engineering quantity calculation software and PM system. The engineering quantity calculation software is used to decompose the WBS structure and realize standardized quantity calculation, and the PM system is used to manage engineering quantity data. After the engineering quantity calculation software calculates the project quantity in detail, it pushes the quantity to the PM system, sets the project progress supply points and process methods, and creates an image progress that matches the progress control needs. During the construction process, the image progress of the day is reported according to the physical projects completed every day. The PM system automatically calculates the output value, the material consumption, and controls the price of the next inspection.
[0034] The management of engineering quantities is mainly divided into three stages: A. Engineering quantity measurement stage, B. Establishing visual progress stage and C. Engineering quantity management application stage.
[0035] A. Engineering quantity measurement stage
[0036] A1. Create structure and WBS dictionary decomposition
[0037] The engineering quantity calculation software uses Dream City Cloud to create the structure of the project. The structure of the project is created and the WBS dictionary is decomposed in Dream City Cloud. The schematic diagram of creating the structure and WBS dictionary decomposition is as follows Figure 2 shown.
[0038] A2. Calculation of Engineering Quantity
[0039] Adopt Mengcheng quantity calculation software, quote cloud structure and WBS dictionary, calculate the project quantity in detail, standardize the quantity calculation content, and the depth of engineering quantity calculation should be able to meet the needs of preparation of construction plan, cost plan, pricing, subcontract inspection, material procurement, material overconsumption analysis and other progress management and engineering economic management. The engineering quantity calculation diagram is as follows Figure 3 shown.
[0040] A4. Synchronize data to PM system
[0041] After the engineering calculation is submitted for review, the engineering quantity data is uploaded to the cloud, and the Mengcheng cloud engineering quantity data and structures are synchronized to the PM system as the data basis for establishing the 0# ledger and image progress creation. The schematic diagram of synchronizing data to the PM system is as follows Figure 4shown.
[0042] A5. Hanging contract list and material code
[0043] The PM system is used to connect the system front-end business to the quantity calculation content, import the upper measurement list, material dictionary code, business unit and lower subcontract list, connect the contract list and material code to the quantity calculation content in the system, establish the upper measurement ledger, material ledger, and lower inspection ledger 0# ledger, structure decomposition data, as the basis for the development of engineering quantity management. The upper measurement list connection diagram is as follows Figure 5 As shown, the material coding hanging diagram is as follows Figure 6 As shown in the figure, the schematic diagram of the connection between the business unit and the subcontract list is as follows Figure 7 shown.
[0044] B. Image building progress stage
[0045] B1. Image building progress
[0046] Push the engineering structure from Mengcheng Technology Cloud to the PM system to complete the structure decomposition, configure the process method in the project progress work point setting and structure management, and create a visual progress that matches the progress control requirements. The project structure automatic decomposition diagram is as follows Figure 8 As shown, the image creation progress diagram is as follows Fig. 9 shown.
[0047] C. Engineering Quantity Management Application Phase
[0048] C1. Daily image progress reporting and locking
[0049] The technical management personnel at the construction site fill in the daily progress report based on the physical projects completed every day. At the end of each month, the progress report will be locked. The system will automatically calculate the amount of work completed that month. The schematic diagram of daily progress report is as follows: Fig.10 As shown, the monthly progress lock diagram is as follows Fig.11 shown.
[0050] C2. Automatic calculation of output value
[0051] The image progress and output value calculation are unified. The PM system calculates and summarizes the list of completed projects in the month based on the image progress locked in the month, and then automatically calculates the completed output value of the month in combination with the unit price of the project quantity 0# ledger list established in the initialization phase. The schematic diagram of automatic output value calculation is shown below: Fig.12 shown.
[0052] C3. Automatic calculation of material consumption
[0053] The PM system calculates and summarizes the physical engineering quantity completed in the month based on the image progress locked in the month, and automatically matches the corresponding working surface, process and team code. Then, combined with the material code of the engineering material ledger established in the initialization stage, it automatically calculates the material consumption of the month by team and part, compares the actual material consumption to analyze the savings and overages, and generates a calculation data diagram by team as shown below. Fig.13 As shown, the schematic diagram of automatic calculation of material consumption is as follows Fig.14 As shown in the table below, the main material section analysis table is as follows Fig.15 shown.
[0054] C4. Control over the price of inspection work
[0055] According to the decomposition of the downstream project quantity, during the inspection of the downstream work, the mandatory control can only inspect and price the completed project quantity in the contract of the trading unit, and at the same time control the inspection project quantity not to exceed the decomposed project quantity. The schematic diagram of the inspection and price control of the downstream is as follows Fig.16 shown.
[0056] The present invention adopts quantity calculation software in the engineering quantity calculation stage, selects the built-in WBS dictionary, completes the sub-item division before calculation, uses the software for collaborative quantity calculation by multiple people, improves the efficiency and accuracy of engineering quantity calculation, and uses the PM system to create 0# ledgers for upper measurement ledgers, material ledgers, and lower work inspection ledgers as the data basis for engineering quantity management. When the engineering quantity data changes, the formed ledgers will also be automatically updated, with multiple changes and data linkage.
[0057] Compared with the traditional offline engineering quantity management mode, in the PM system based on the visual progress application, the dimensions and standards of the project management personnel's progress statistics are unique, and all the business of project management comes from the same data source, which effectively reduces the inconsistency of data calibers of various departments during project implementation, the difficulty of coordination among multiple positions, and the cumbersome work of repeated calculations and repeated statistics, which leads to the delay in the summary of key information. Project management business personnel only need to complete their own duties in the system, and the management interface is clear, which enables the "calculation, use, and management" of project engineering quantity management to be linked to each other, improving the project work efficiency and the degree of refined management and control.
Claims
1. A construction quantity management system based on visual progress application, characterized by: It includes engineering quantity calculation software for decomposing WBS structure and realizing standardized quantity calculation, and PM system for managing engineering quantity data. After the engineering quantity calculation software calculates the project quantity in detail, it pushes the quantity to the PM system, sets the project progress supply points and process methods, and creates a visual progress that matches the progress control needs. During the construction process, the visual progress of the day is reported according to the physical projects completed every day. The PM system automatically calculates the output value, the material consumption, and controls the pricing of the next work inspection.
2. According to claim 1, a construction quantity management system based on visual progress application is characterized by: The engineering quantity calculation software adopts Mengcheng quantity calculation software, refers to cloud structure and WBS dictionary, calculates the project quantity in detail and standardizes the quantity calculation content.
3. According to claim 1, the engineering quantity management system based on the visual progress application is characterized by: The engineering quantity data initialization of the PM system is to apply the PM system to the quantity calculation content and connect the system front-end business to import the upper measurement list, material dictionary code, business unit and lower subcontract list, connect the contract list and material code to the quantity calculation content in the system, and establish the 0# ledger of the upper measurement ledger, material ledger, and lower work inspection ledger, as well as the structural decomposition data, as the basis for the implementation of engineering quantity management.
4. The engineering quantity management system based on the visual progress application according to claim 1 is characterized by: The PM system automatically calculates the output value by calculating and summarizing the list of project quantities completed in the month based on the image progress locked in the month, and then automatically calculates the output value completed in the month based on the unit price of the project quantity 0# ledger list established in the initialization phase.
5. The engineering quantity management system based on the visual progress application according to claim 1 is characterized by: The PM system automatically calculates the material consumption based on the visual progress locked in the month to summarize the actual project volume completed in the month, and automatically matches the corresponding work surface, process and team code. Then, it combines the material code of the engineering material ledger established in the initialization phase to automatically calculate the material consumption for the month by team and part, and compares the actual material consumption to analyze savings and overages.
6. The engineering quantity management system based on the visual progress application according to claim 1 is characterized by: The PM system controls the price calculation of the work inspection and decomposes the engineering quantity. When inspecting the work, it enforces the control of price calculation of the completed engineering quantity in the contract of the business unit, and controls the inspection engineering quantity not to exceed the decomposed engineering quantity.
Citation Information
Patent Citations
Data processing method for engineering project progress and output value linkage
CN112258075A
Resource management method and device thereof
CN113177749A
Design method and system of five-quantity dynamic machine account
CN114648244A
Tunnel management platform taking construction organization as core
CN115456814A