Method for operating railway track system, field device and central device
By introducing the driving notification function in the railway track facility and using the existing data transmission infrastructure for two-way transmission, the problems of functional redundancy and high cost in the existing technology are solved, and the situation of minimizing hardware and costs is achieved , allowing the dual functions of driving notifications and setting commands, improving the efficiency and economicality of data transmission.
Patent Information
- Application Number
- CN202410689877.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2023-05-31
- Filing Date
- 2024-05-30
- Publication Date
- 2024-12-03
AI Technical Summary
The existing railway track facility methods fail to effectively utilize the existing data transmission infrastructure, resulting in problems of functional redundancy and high cost when transmitting setup commands and detecting signals.
By introducing a function that allows driving notifications in the adjustment and/or detection device and using existing data transmission infrastructure for two-way transmission, including transmission from the central device to the adjustment and/or detection device, and from the adjustment and/or detection device, as well as from the adjustment and/or detection device The transmission of the device to the rail vehicle uses a radio channel independent of the line-side transmission channel, reducing hardware and costs.
The dual functions of allowing driving notifications and setting commands are realized while minimizing hardware and costs, improving the efficiency and economicality of data transmission and reducing the demand for specialized equipment.
Smart Images

Figure CN119058782A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for operating a railway track facility, in which method setting commands are transmitted from a central device (German: Zentraleinrichtung) to at least one field device in the form of a field or facility-side adjustment and / or detection device, the setting commands leading to the adjustment of setting components of the adjustment and / or detection device, and / or detection signals relating to events or states of the railway track facility are transmitted from the adjustment and / or detection device to the central device, which is a signal station (German: Stellwerk) or a line center (German: Streckenzentrale). Background Art
[0002] An adjusting and detecting device in the sense of the invention may be, for example, a switch, which implements a setting command for adjusting the switch position and feeds back the respectively detected final switch position as a detection signal. A detecting device in the sense of the invention may be, for example, an axle counter device (or a track idle indicator device), which reports the occupation state of the corresponding track section, i.e. idle or occupied, as a detection signal. An adjusting device in the sense of the invention may be, for example, a switching device, which is associated with a signal and adjusts its signal position as a response to a setting command. Summary of the invention
[0003] The technical problem to be solved by the present invention is to improve this method.
[0004] This object is achieved according to the invention by a method having the features according to claim 1. Advantageous embodiments of the method according to the invention are specified in the dependent claims.
[0005] According to the present invention, the adjustment and / or detection device is also designed to receive and forward the permission to start notification, and within the scope of the method, the central device transmits the permission to start notification to the adjustment and / or detection device, and the adjustment and / or detection device forwards the received permission to start notification to the passing rail vehicle.
[0006] A significant advantage of the method according to the invention is that, in addition to the normal, known operating functions, namely control and / or detection, the control and / or detection device is also equipped with the transmission of a permission to start notification as an additional function. Thus, a control and / or detection device operated according to the invention makes it possible, for example, to dispense with a transponder which is designed specifically or only for the transmission of a permission to start notification and to design the railway track installation in a particularly economical manner.
[0007] In terms of minimizing hardware expenditure and minimizing costs, it is advantageous to allow the transmission of start-up notifications and setting commands from the central device to the adjustment and / or detection device via the same data transmission infrastructure. In this case, the existing data transmission infrastructure can also advantageously play a dual role.
[0008] It is also advantageous to allow the transmission of the start-up notification from the central device to the control and / or detection device and the transmission of the detection signal from the control and / or detection device to the central device via the same data transmission infrastructure.
[0009] The transmission of the permission to start notification from the adjustment and / or detection device to the passing rail vehicle is preferably carried out in a separate vehicle-related transmission channel, which is independent of the line-side transmission channel, which is used to transmit setting commands and / or detection signals and to transmit the permission to start notification from the central device to the adjustment and / or detection device.
[0010] In the control and / or detection device, the same interface device is preferably used for receiving the start-up authorization notification and the setting command and / or for receiving the start-up authorization notification and for sending the detection signal.
[0011] The individual vehicle-related transmission channel is preferably a radio channel. The control and / or detection device therefore preferably has a radio device for sending a permission to start notification to a passing rail vehicle. The radio device can be a WLAN radio device, a Bluetooth radio device or any other radio device that can transmit a radio signal containing a permission to start notification to a passing rail vehicle.
[0012] The adjustment and / or detection device is preferably respectively equipped with a control device, which can constitute a so-called field element controller or a component of a so-called field element controller. The control device is preferably connected to the interface device in order to obtain the start permission notification via the interface device; it is also connected to the radio device in order to control the radio device to forward the start permission notification. The interface device and the radio device are preferably also components of the field element controller.
[0013] Advantageously, the adjusting and / or detection device or one of the adjusting and / or detection devices is a switch and a switching command is transmitted from the central device to the switch as a setting command for adjusting the switch position.
[0014] Position signals are preferably transmitted from the switches as detection signals to a central device, which indicate the respective switch position of the switch.
[0015] Advantageously, provision can also be made for the adjusting and / or detecting device or one of the adjusting and / or detecting devices to be an axle counter device, from which a status message is transmitted as a detection signal, which indicates that the track section associated with the axle counter device is free or that the track section is occupied.
[0016] As the data transmission infrastructure, a data transmission network is preferably used or at least used together, for example at least also a network based on Ethernet. The data transmission infrastructure is preferably line-based or at least also line-based.
[0017] The present invention also relates to an adjustment and / or detection device, which is suitable for receiving and executing a setting command from a central device, the setting command leading to the adjustment of a setting component of the adjustment and / or detection device and thereby the adjustment of the railway track facility, and / or the adjustment and / or detection device sending a detection signal related to an event or state of the railway track facility to the central device. According to the present invention, it is provided in the adjustment and / or detection device that it is also designed to receive a start-up permission notification from the central device and forward the start-up permission notification to a passing rail vehicle.
[0018] With regard to the advantages of the adjusting and / or detecting device according to the invention and with regard to advantageous embodiments of the adjusting and / or detecting device according to the invention, reference is made to the above description in connection with the method according to the invention and its advantageous embodiments.
[0019] Advantageously, the regulating and / or detecting device is a switch or an axle counter device.
[0020] The adjustment and / or detection device preferably includes a control device, an interface device connected to the control device for connecting to a data transmission network on the line side and receiving a start-up permission notification from a central device, and also includes a radio device connected to the control device for sending the received start-up permission notification to a passing rail vehicle.
[0021] The control device preferably includes a computing device and a memory. The memory preferably stores a computer program product, which includes program commands, which, when executed by the computing device, forward the start-up permission notification from the central device to the rail vehicle according to the above method.
[0022] The invention also relates to a computer program product for a control and / or detection device. According to the invention, the computer program product comprises program commands which, when executed by a computing device, enable it to forward a start-up authorization notification from a central device to a rail vehicle according to the above method.
[0023] With regard to advantages of the computer program product according to the invention and with regard to advantageous embodiments of the computer program product according to the invention, reference is made to the above description in connection with the method according to the invention and its advantageous embodiments.
[0024] The invention also relates to a central device which is designed to send setting commands to the adjustment and / or detection device, the setting commands leading to the adjustment of setting components of the adjustment and / or detection device, and / or is designed to receive and process detection signals from the adjustment and / or detection device, the detection signals relating to events or states of the railway track facility. According to the invention, it is provided in such a central device that it is also designed to send a start permission notification to the adjustment and / or detection device, the start permission notification being intended for forwarding to a passing rail vehicle.
[0025] The central device preferably comprises a computing device and a memory. The memory preferably stores a computer program product, which comprises program commands, which when executed by the computing device, cause the computing device to send a start permission notification to the control and / or detection device for forwarding to the rail vehicle.
[0026] The invention also relates to a computer program product for a central device. According to the invention, the computer program product comprises program commands which, when executed by a computing device, cause it to send a start-up permission notification to a control and / or detection device for forwarding to a rail vehicle.
[0027] The invention also relates to a railway track facility. According to the invention, it is provided that the railway track facility is equipped with the above-mentioned central device and at least one above-mentioned regulating and / or detecting device. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The present invention is further described below based on the embodiments, wherein:
[0029] Figure 1 A sectional view of a section of an exemplary embodiment of a railway track installation according to the invention is shown, thereby explaining by way of example an exemplary embodiment of a method according to the invention and of an exemplary embodiment of a regulating and / or detecting device according to the invention, wherein the regulating and / or detecting device according to the invention Figure 1 It's a turnout.
[0030] Figure 2 Shown in accordance with Figure 1 Another part of a railway track facility, wherein a further method according to the invention and a further embodiment of the adjustment and / or detection device according to the invention are explained by way of example based on the further part, wherein the further adjustment and / or detection device according to the invention is explained by way of example Figure 2 It is an axle counter device.
[0031] Figure 3 A preferred structure for the adjustment and / or detection device according to the invention is shown in further detail.
[0032] Figure 4 Shown in accordance with Figure 3 The preferred structure, in the case where the turnout is designed as an adjustment and / or detection device,
[0033] Figure 5 Shown in accordance with Figure 3 A preferred configuration is provided in the case where the axle counter device is designed as an adjustment and / or detection device.
[0034] For the sake of clarity, the same reference numbers are always used in the figures for the same or similar components. DETAILED DESCRIPTION
[0035] Figure 1 A section 11 of a railway track system 10 is shown, on which a rail vehicle 20 travels. Figure 1 The section 11 of the railway track system 10 shown is equipped with a regulating and / or detection device in the form of a switch 40 .
[0036] The switch 40 comprises a control device 41 and an interface device 42 connected to the control device 41. The interface device 42 is connected to a central device 60 via a line-side, preferably wired, transmission channel 50. The transmission channel 50 may comprise a data transmission network 51, for example.
[0037] The switch 40 further comprises an arrangement component in the form of a switch drive 43 , which is controlled by a control device 41 and which can adjust the switch tongue of the switch 40 .
[0038] The switch 40 further comprises a position sensor 44 which sends a detection signal DS representing the corresponding position of the switch point rail to the control device 41 .
[0039] The control device 41 ensures normal normal operation of the switch 40 , wherein corresponding detection signals DS of the position sensor 44 are forwarded to the central device 60 and the switch position is adjusted according to the setting command SB sent by the central device 60 .
[0040] according to Figure 1 The switch 40 also includes a radio device 45, which is connected to the control device 41 and provides a separate vehicle-related transmission channel 70. The separate vehicle-related transmission channel 70 is a radio channel, which independently of the line-side transmission channel 50 allows the transmission of a permission to start notification MA (also known as "movement authority" in the professional terminology) to the rail vehicle 20 passing through the switch 40. The term "permission to start notification" or "movement authority" is understood here as a message that informs the rail vehicle whether it is allowed to travel on the track section ahead. In addition to this permission to start notification, other information can also be transmitted, such as maximum speed information or travel restrictions.
[0041] Unlike the conventional control device used in the turnout 40, the control device 41 is designed to forward the start-up permission notification MA to the passing rail vehicle 20. Figure 1 The switch 40 shown can be operated in parallel in forwarding mode, which can be, for example, as follows:
[0042] If the switch 40 forwards the start permission notification MA to the passing rail vehicle 20 , the central device 60 first transmits the start permission notification MA to the interface device 42 of the switch 40 via the track-side transmission channel 50 (including the data transmission network 51 ).
[0043] The interface device 42 transmits the permission to drive notification MA to the control device 41, and the control device 41 controls the radio device 45 so that the radio device 45 transmits the radio signal FS containing the permission to drive notification MA to the passing rail vehicle 20 through the radio channel or a separate vehicle-related transmission channel 50.
[0044] The radio transmission of the start permission notification MA can be started continuously directly after its reception via the trackside transmission channel 50, or can be performed only during the passage of the switch 40. The passage of the switch 40 can be detected, for example, by the radio device 45 by receiving the vehicle-side radio signals continuously emitted by the rail vehicle.
[0045] The control device 41 thus forms a functionally extended switch controller which, compared with conventional switch controllers, provides an extended function of forwarding the permission-to-go notification MA.
[0046] Figure 2 Shown in accordance with Figure 1 Another section 12 of the railway track facility 10. Figure 2 The section 12 of the railway track system 10 shown is equipped with a control and / or detection device in the form of an axle counter device 140 .
[0047] The axle counter device 140 includes a control device 141 and an interface device 142 connected to the control device 141. The interface device 142 is connected to the central device 60 via a line-side transmission channel 150, which can be connected to a transmission channel 150 according to the embodiment of the present invention. Figure 1 on the data transmission network 51.
[0048] The axle counter device 140 further comprises two axle sensors 144, whose sensor signals SS can reach the control device 141. The control device 141 analyzes the sensor signals SS and determines, based on the detected passing events and by counting the axles, whether there is a rail vehicle 20 in the track section 12a monitored by the axle counter device 140. Based on the axle counter result, the control device 141 generates a status message as a detection signal DS, which indicates that the track section 12a is free or the track section 12a is occupied, and transmits the detection signal DS or the status message to the central device 60 via the interface device 142.
[0049] The control device 141 of the axle counter device 140 thus ensures normal, correct operation of a conventional axle counter device.
[0050] according to Figure 2 The axle counter device 140 also includes a radio device 145, which is connected to the control device 141 and provides a separate vehicle-related transmission channel 170. The separate vehicle-related transmission channel 170 is a radio channel that allows the transmission of a start permission notification MA to the rail vehicle 20 passing through the axle counter device 140 independently of the line-side transmission channel 150.
[0051] Unlike conventional control devices used in axle counter devices, the control device 141 is designed to forward the permission to drive notification MA to the passing rail vehicle 20. Figure 2 The axle counter device 140 shown can additionally operate in a forwarding mode, which can be as follows, for example:
[0052] If the axle counter device 140 forwards the start permission notification MA to the passing rail vehicle 20 , the central device 60 first transmits the start permission notification MA to the interface device 142 of the axle counter device 140 via the track-side transmission channel 150 (here including the data transmission network 51 ).
[0053] The interface device 142 forwards the permission to drive notification MA to the control device 141, which in turn controls the radio device 145 so that the radio device 145 transmits the radio signal FS containing the permission to drive notification MA to the passing rail vehicle 20 via a radio channel or a separate vehicle-related transmission channel 170.
[0054] The radio transmission of the permission to drive notification MA can be carried out continuously while the track section 12 a is occupied, or only when a vehicle radio signal continuously emitted by the rail vehicle 20 is detected by the radio device 145 .
[0055] The control device 141 thus forms a functionally expanded axle counter control which, compared with conventional axle counter control, offers an expanded function of forwarding the permission-to-go notification MA.
[0056] Figure 3 An embodiment of an advantageous structure for the adjustment and / or detection device 240 according to the invention is further shown in detail. The adjustment and / or detection device 240 comprises a control device 241, an interface device 242 for connecting the adjustment and / or detection device 240 to a line-side transmission channel 250, a radio device 245, and at least one setting component 243 and / or at least one sensor 244.
[0057] The control device 241 comprises a computing device 241a and a memory 241b. The memory 241 stores a computer program product CPP which determines or at least jointly determines the working mode of the control device 241 when executed by the computing device 241a.
[0058] The computer program product comprises a control and / or detection software module C1 which implements a conventional mode of operation of the control and / or detection device, ie a mode of operation known for control and / or detection devices.
[0059] The computer program product CPP further comprises a forwarding software module C2, which implements the forwarding of the start permission notification MA, which is received from the central device 60 via the interface device 242. If the start permission notification MA is provided to the forwarding software module C2, the forwarding software module C2 controls the radio device 245 to send the start permission notification MA via radio so that the passing rail vehicle can receive the start permission notification MA.
[0060] Figure 4 Show according to Figure 3 The adjusting and / or detecting device shall be designed in accordance with Figure 1 In this case, according to Figure 3 The adjustment and / or detection software module is designed as a switch operation software module C1W, which implements the conventional operating method of the switch, ie the operating method known for switches.
[0061] In the forwarding software module C2, it implements the forwarding operation that allows the start-up notification MA, for which the above combination is applicable Figure 1 and Figure 3 Description.
[0062] Figure 5 Show according to Figure 3 The adjusting and / or detecting device shall be designed in accordance with Figure 2 axle counter device 140. In this case, according to Figure 3 The control and / or detection software module C1 is designed as an axle counter module C1A, which implements a conventional mode of operation of the axle counter device, ie a mode of operation known to axle counter devices.
[0063] In the forwarding software module C2, the implementation allows the forwarding operation of the start notification MA, for which the above combination is applicable Figure 2 and Figure 3 Description.
[0064] Finally, it should be mentioned that the features of all the above-described embodiments can be combined with one another in any manner to form further other embodiments of the present invention.
[0065] Furthermore, all features of the dependent claims may be combined individually with each parallel claim and may be combined arbitrarily either individually or with one or more other dependent claims to obtain further other embodiments.
[0066] List of reference numerals:
[0067] 10 Railway track facilities
[0068] 11 Segment
[0069] 12 Segments
[0070] 12a Track section
[0071] 20 Rail vehicles
[0072] 40 Turnout
[0073] 41 Control device
[0074] 42 Interface device
[0075] 43 Turnout drive device
[0076] 44 Position Sensor
[0077] 45 Radio Device
[0078] 50 Transmission channel on the line side
[0079] 51 Data transmission network
[0080] 60 Central Unit
[0081] 70 Vehicle-related transmission channels
[0082] 140 Axle counter device
[0083] 141 Control Device
[0084] 142 Interface device
[0085] 144 axis sensor
[0086] 145 Radio Device
[0087] 150 Transmission channel on the line side
[0088] 170 Vehicle-related transmission channels
[0089] 240 Adjustment and / or detection device
[0090] 241 Control Device
[0091] 241a Computing Device
[0092] 241b memory
[0093] 242 Interface device
[0094] 243 Setting Components
[0095] 244 Sensors
[0096] 245 Radio Device
[0097] 250 Transmission channel on the line side
[0098] C1 Detection Software Module
[0099] C1A Axis Counter Module
[0100] C1W turnout operation software module
[0101] C2 forwarding software module
[0102] CPP Computer Program Product
[0103] DS detection signal
[0104] FS radio signal
[0105] MA Allowed to Drive Notice
[0106] SB Setting Commands
[0107] SS sensor signal
Claims
1. A method for operating a railway track facility (10), wherein in the method, Transmitting a setting command (SB) from a central device (60) to at least one adjusting and / or detecting device (40, 140, 240), the setting command leading to the adjustment of a setting component (43, 243) of the adjusting and / or detecting device, and / or transmitting a detection signal (DS) relating to an event or a state of the railway track facility (10) from the adjusting and / or detecting device to the central device (60), the central device being a signal station or a line center, It is characterized in that The control and / or detection device is also designed to receive and forward a permission to drive notification (MA), Furthermore, within the scope of the method, the central device (60) transmits a permission to start notification (MA) to the control and / or detection device, and the control and / or detection device forwards the received permission to start notification (MA) to the passing rail vehicle (20).
2. The method according to claim 1, It is characterized in that The transmission of the start-up authorization notification (MA) and the setting command (SB) from the central device (60) to the adjustment and / or detection device is carried out via the same data transmission infrastructure.
3. The method according to claim 1 or 2, It is characterized in that The transmission of the start permission notification (MA) from the central device (60) to the regulating and / or detecting device and the transmission of the detection signal (DS) from the regulating and / or detecting device to the central device (60) are carried out via the same data transmission infrastructure.
4. The method according to any one of the preceding claims, It is characterized in that The transmission of a start permission notification (MA) from the adjustment and / or detection device to a passing rail vehicle (20) takes place in a separate vehicle-related transmission channel (70), which is independent of a line-side transmission channel (50) for transmitting setting commands (SB) and / or detection signals (DS) and for transmitting the start permission notification (MA) from a central device (60) to the adjustment and / or detection device.
5. The method according to any one of the preceding claims, It is characterized in that The same interface device (42, 142, 242) is used in the adjustment and / or detection device for receiving a start permission notification (MA) and a setting command (SB) and / or for receiving a start permission notification (MA) and for sending a detection signal (DS).
6. The method according to any one of claims 4 to 5, It is characterized in that The separate vehicle-related transmission channel (70) is a radio channel and The control and / or detection device has a radio device (45, 145, 245) for sending a start permission notification (MA) to a passing rail vehicle (20).
7. The method according to claim 6, It is characterized in that The regulating and / or detecting device is provided with a control device (41, 141, 241), The control device (41, 141, 241) is connected to the interface device (42, 142, 242) so as to obtain a start permission notification (MA) through the interface device; the control device (41, 141, 241) is also connected to the radio device (45, 145, 245) so as to control the radio device to forward the start permission notification (MA).
8. The method according to any one of the preceding claims, It is characterized in that The one regulating and / or detecting device or one of the plurality of regulating and / or detecting devices is a switch (40), and transmitting a switching command from the central device (60) to the switch (40) as a setting command (SB) for adjusting the switch position, and A position signal is transmitted from the switch (40) as a detection signal (DS) to a central device (60), which indicates the respective switch position of the switch (40).
9. The method according to any one of the preceding claims, It is characterized in that The one adjusting and / or detecting device or one of the multiple adjusting and / or detecting devices is an axle counter device (140), and A status message is transmitted from the axle counter device (140) as a detection signal (DS), the status message indicating that the track segment (12a) corresponding to the axle counter device (140) is free or the track segment (12a) is occupied.
10. An adjustment and / or detection device (40, 140, 240) adapted to receive and execute a setting command (SB) from a central device (60), the setting command resulting in adjustment of a setting component (43, 243) of the adjustment and / or detection device (40, 140, 240), and / or adapted to send a detection signal (DS) related to an event or state of a railway track facility (10) to the central device (60). It is characterized in that The regulating and / or detecting device (40, 140, 240) is also designed to receive a start permission notification (MA) from the central device (60) and forward the start permission notification (MA) to the passing rail vehicle (20).
11. The adjusting and / or detecting device (40, 140, 240) according to claim 10, It is characterized in that The adjusting and / or detecting device (40, 140, 240) comprises a control device (41, 141, 241), an interface device (42, 142, 242) connected to the control device (41, 141, 241) for connecting to a data transmission network on the line side and receiving a start permission notification (MA) from a central device (60), and the adjusting and / or detecting device further comprises a radio device (45, 145, 245) connected to the control device (41, 141, 241) for sending the received start permission notification (MA) to a passing rail vehicle (20).
12. The adjusting and / or detecting device (40, 140, 240) according to claim 11, It is characterized in that The control device (41, 141, 241) includes a computing device (241a) and a memory (241b), and A computer program product (CPP) is stored in the memory (241b), which includes program commands, which when executed by the computing device (241a) forward the start permission notification (MA) of the central device (60) to the rail vehicle (20) according to one of the methods described in one of claims 1 to 9.
13. A computer program product It is characterized in that The computer program product (CPP) comprises program commands which, when executed by a computing device, cause it to forward a start authorization notification (MA) from a central device (60) to a rail vehicle (20) according to the method of one of claims 1 to 9.
14. A central device (60) designed to send setting commands (SB) to a setting and / or detection device (40, 140, 240), the setting commands leading to the setting of a setting component (43, 243) of the setting and / or detection device (40, 140, 240), and / or designed to receive and process detection signals (DS) from the setting and / or detection device (40, 140, 240), the detection signals relating to events or states of a railway track facility (10), It is characterized in that The central device (60) is also designed to send a start permission notification (MA) to the control and / or detection device (40, 140, 240), the start permission notification being intended for forwarding to a passing rail vehicle (20).
15. A railway track system (10) having a central device (60) according to claim 14 and a regulating and / or detection device (40, 140, 240) according to one of claims 10 to 12.