Intelligent site selection method, device and equipment for transformer substation and storage medium

Through the improved multi-peak optimization particle swarm algorithm and the comprehensive processing of multiple factors, the problem of inefficiency of traditional station selection methods is solved, the accuracy and reliability of station selection in power grid engineering is improved, and the most preferred site results are ensured.

CN119067291APending Publication Date: 2024-12-03STATE GRID ECONOMIC TECH RES INST CO LTD +2

Patent Information

Application Number
CN202411072187.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The traditional manual station selection method is inefficient and it is difficult to take into account the terrain, geology, and transportation factors in power grid engineering station selection. The existing optimization algorithms are insufficient in the solution process.

Method used

The improved multi-peak optimization particle swarm algorithm is adopted, combined with multiple influencing factors to optimize the processing, and through data cleaning, integration and unification, the target site selection area is selected, and the pending site is generated in this area, using the objective function and particles The group optimization algorithm finds the optimal site to avoid local convergence.

Benefits of technology

It improves the reliability and accuracy of site selection results, provides clearer site selection guidance, avoids excessive convergence between site sites in different populations, and ensures the most preferred site results.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119067291A_ABST
    Figure CN119067291A_ABST
Patent Text Reader

Abstract

The invention discloses an intelligent site selection method and device for a transformer substation, equipment and a storage medium, and the method comprises the steps: screening regions where the transformer substation can be built according to station selection data, obtaining a target site selection region, and generating N groups of to-be-processed sites in the target site selection region according to a preset site search number; and inputting the to-be-processed station addresses into a search model formed based on an improved multi-peak optimization particle swarm algorithm, screening the optimal station addresses of each group of to-be-processed station addresses, and determining a substation site selection planning result of the target site selection area according to the first N optimal station addresses. According to the method, the site selection areas are screened by adopting a scientific area screening method, so that clearer guidance is provided for site selection; in the process of searching the optimal site, any two sites which are too close to each other are adjusted according to a rejection strategy, so that the distance between multi-peak solutions of the improved multi-peak optimization particle swarm optimization algorithm is ensured, the sites output by different populations are prevented from being excessively converged to local optimum, and the optimal site selection result is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of site selection for power grid projects, and in particular to a method, device, equipment and storage medium for intelligent site selection of a substation. Background Art

[0002] With the acceleration of industrialization and urbanization, the demand for electricity is growing. In order to meet the growing demand for electricity, substations, as an important part of the power system, are particularly important in terms of site selection and construction.

[0003] The site selection for power grid projects is a complex multi-objective optimization problem that requires consideration of multiple factors, including topography, geology, transportation, and environment. Traditional manual site selection methods are inefficient and difficult to balance various factors. In recent years, with the development of geographic information systems and remote sensing technologies, site selection for power grid projects can use multi-source heterogeneous data for intelligent assisted site selection. However, existing optimization algorithms still have problems such as insufficient accuracy in the solution process.

[0004] It can be seen that how to solve the problem of reasonable site selection for substations has become a technical problem that needs to be urgently solved by those skilled in the art. Summary of the invention

[0005] The present invention provides a method for intelligent site selection of a transformer substation, so as to achieve the effect of site selection of the transformer substation according to multiple factors.

[0006] In order to solve the above technical problems, an embodiment of the present invention provides a method for intelligent site selection of a substation, the method comprising:

[0007] The acquired factors affecting the substation planning are optimized to obtain station selection data.

[0008] According to the site selection data, the area where the substation can be built is screened to obtain the target site selection area, and according to the preset site search number N, N groups of sites to be processed are generated in the target site selection area.

[0009] Inputting N groups of the sites to be processed into the site search model, screening the optimal sites of each group of the sites to be processed, and obtaining the top N optimal sites, wherein the site search model executes an improved multi-modal optimization particle swarm algorithm during the processing, and the improved multi-modal optimization particle swarm algorithm includes a relationship between the speed and position of the particles:

[0010]

[0011] x i+1 =x i +v i+1

[0012] Among them, v i is the speed of the particle at step i, x i is the position of the particle at step i, x p-i is the optimal position searched by the i-th particle in the j-th population, x g-j is the optimal position searched by all particles in the jth population, x g-j-other is the distance x g-j The optimal position of the nearest other population, ω is the inertia coefficient, c1 and c2 are learning factors, c3 is a negative number, r1, r2 and r3 are randomly distributed values ​​between [0,1]; the execution strategy of the algorithm includes when the distance between the optimal sites of the two groups of sites to be processed is lower than the preset limit distance, uniformly increasing the number of sites in one group of the sites to be processed and re-determining the optimal site.

[0013] Based on the first N optimal sites, the substation site selection planning result of the target site selection area is determined.

[0014] Furthermore, the optimization processing of the acquired several types of influencing factors affecting substation planning to obtain station selection data includes:

[0015] The elevation data, geological data and road data in the area to be screened are obtained, and then cleaned, integrated and unified to obtain the pre-processed station selection data.

[0016] Furthermore, the area where the substation can be constructed is screened according to the station selection data to obtain the target site selection area, including:

[0017] According to the site selection data, the restricted area in the area to be screened is eliminated to obtain the target site selection area, wherein the restricted area includes the road area, the water system area and the steep area.

[0018] Further, the generating N groups of sites to be processed in the target site selection area according to a preset site search quantity N includes:

[0019] An objective function is constructed based on the earthwork volume, access roads, and control factors of the target site selection area.

[0020] The preset number of site searches N generates N groups of sites to be processed in the target site selection area.

[0021] Furthermore, the objective function is:

[0022] f=S min (volume)+S min (road)+S(control)

[0023] Among them, S min(volume) is the minimum earthwork volume of the substation, S min (road) is the sum of the shortest paths from the substation to the road, and S(control) is the control adjustment factor for the substation.

[0024] Further, the step of inputting N groups of sites to be processed into a site search model, screening the optimal sites of each group of sites to be processed, and obtaining the top N optimal sites includes:

[0025] The positions of the N groups of sites to be processed are iteratively updated according to the objective function and the relationship.

[0026] According to the position iteration update results, the optimal site of each group of sites to be processed is determined, and the top N optimal sites are obtained.

[0027] Furthermore, during the process of the iterative position update, the speed of the iterative position update is limited according to the diversity index, wherein the speed limit is:

[0028]

[0029] |v i-min |=min(W,H)×1%

[0030] Among them, v i-max is the upper limit of particle speed, v0 is the speed at the initial moment, div0 is the particle diversity at the initial moment, div is the particle diversity of the current step, v i-min is the lower limit of particle velocity, W is the number of pixels corresponding to the width direction of the target site selection area, and H is the number of pixels corresponding to the height direction of the target site selection area.

[0031] Another embodiment of the present invention provides a substation intelligent site selection device, including:

[0032] The data acquisition module is used to optimize the acquired factors affecting the substation planning and obtain station selection data.

[0033] The site generation module is used to screen the area where the substation can be built according to the site selection data to obtain the target site selection area, and generate N groups of sites to be processed in the target site selection area according to the preset site search number N.

[0034] The site screening module is used to input N groups of the sites to be processed into the site search model, screen the optimal sites of each group of the sites to be processed, and obtain the top N optimal sites, wherein the site search model executes an improved multi-modal optimization particle swarm algorithm during the processing, and the improved multi-modal optimization particle swarm algorithm includes the relationship between the speed and position of the particles:

[0035]

[0036] x i+1 =x i +v i+1

[0037] Among them, v i is the speed of the particle at step i, x i is the position of the particle at step i, x p-i is the optimal position searched by the i-th particle in the j-th population, x g-j is the optimal position searched by all particles in the jth population, x g-j-other is the distance x g-j The optimal position of the nearest other population, ω is the inertia coefficient, c1 and c2 are learning factors, c3 is a negative number, r1, r2 and r3 are randomly distributed values ​​between [0,1]; the execution strategy of the algorithm includes when the optimal site distance between two groups of sites to be processed is lower than the preset limit distance, uniformly increase the sites to be processed in one of the groups of sites to be processed and re-determine the optimal site.

[0038] The site determination module is used to determine the substation site selection planning result of the target site selection area based on the first N optimal sites.

[0039] Yet another embodiment of the present invention provides a computer device, comprising a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, wherein the processor implements the intelligent site selection method for a substation as described above when executing the computer program.

[0040] Yet another embodiment of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, wherein when the device where the computer-readable storage medium is located executes the computer program, the intelligent site selection method for substations as described above is implemented.

[0041] Compared with the prior art, the embodiments of the present invention have the following advantages:

[0042] (1) Using a variety of factors that affect substation construction, comprehensively considering the various factors that affect substation selection, and improving the reliability of substation selection results;

[0043] (2) Using scientific regional screening methods to screen the site selection areas provides clearer guidance for site selection;

[0044] (3) In the process of searching for the optimal site, any two sites that are too close to each other are adjusted according to the exclusion strategy to avoid excessive convergence of sites output by different populations to the local optimum, so as to ensure the optimal site selection result. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] Figure 1 A flowchart of the steps of the intelligent site selection method for a substation provided by an embodiment of the present invention;

[0046] Figure 2 A schematic diagram of a substation rejection area provided by an embodiment of the present invention;

[0047] Figure 3 A schematic diagram of calculating earthwork volume and access road provided in an embodiment of the present invention;

[0048] Figure 4 A schematic diagram of search results provided by an embodiment of the present invention;

[0049] Figure 5 A structural block diagram of a substation intelligent site selection device provided by an embodiment of the present invention;

[0050] Figure 6 A structural diagram of a computer device provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0051] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. The purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0052] In the description of this application, the terms "first", "second", "third", etc. are used for descriptive purposes only and are not to be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first", "second", "third", etc. may explicitly or implicitly include one or more of the feature. In the description of this application, unless otherwise specified, "plurality" means two or more.

[0053] In the description of the present application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be a connection between the two elements. The terms "vertical", "horizontal", "left", "right", "upper", "lower" and similar expressions used herein are only for illustrative purposes, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0054] In the description of this application, it should be noted that, unless otherwise defined, all technical and scientific terms used in the present invention have the same meaning as those commonly understood by those skilled in the art. The terms used in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood by specific circumstances.

[0055] An embodiment of the present invention provides a method for intelligent site selection of a substation. For details, see Figure 1 , Figure 1 The flowchart of the step of the intelligent site selection method for a substation in one embodiment of the present invention includes steps S11 to S14:

[0056] Step S11, optimizing the acquired types of influencing factors affecting substation planning to obtain station selection data.

[0057] Define the scope of the area where the substation is to be addressed as the area to be screened, and obtain data such as elevation, water system, road, geology and spatial planning within the area to be screened; among them, elevation data, road data and geological data are necessary data. In the actual site selection process, other data can be increased or decreased according to actual conditions. The more data there is, the closer the search results for subsequent site locations will be to reality.

[0058] The data obtained above are cleaned to remove redundant and incomplete data, and then the data of the same type are integrated and stored in the form of images, and all images are uniformly converted to the same size, that is, the number of pixels in the horizontal direction of each image is the same, the number of pixels in the vertical direction of each image is the same, and the same pixel in different images represents the same position coordinates, thereby obtaining the preprocessed station selection data.

[0059] After converting various types of data into pixel data, the pixels at the same position in different images all represent the same actual geographic location coordinates, so that each subsequent particle can quickly correspond to the specific value of each type of data at that position.

[0060] Step S12, based on the site selection data, screen the area where the substation can be built to obtain the target site selection area, and generate N groups of sites to be processed in the target site selection area according to the preset site search number N.

[0061] Based on the site selection data, it is determined whether a substation can be built at each pixel point in the screening area.

[0062] Specifically, based on the road data and water system data, a certain range around the road and water system can be divided into a range where a substation cannot be built.

[0063] Similarly, whether a substation can be built in the area can also be judged based on the elevation data. The specific operation is: establish a 3×3 pixel sliding window, move the center of the window one pixel each time, calculate the slope of the center position of the window and the standard deviation of the entire window; when the elevation in a certain window is greater than α, all areas in the window are excluded from the area where the substation can be built, where α is an artificially set limit value. The larger α is, the higher the area where the station site is allowed to be searched; when the standard deviation of the elevation in the window is greater than β, all areas in the window are excluded from the area where the substation can be built, where β is an artificially set limit value. The larger β is, the steeper the area where the station site is allowed to be searched.

[0064] like Figure 2 As shown, Figure 2 The figure shows a schematic diagram of a substation veto zone, where the veto zone means an area where a substation cannot be built. For ease of display, Figure 2 The value of each pixel in the figure is a schematic diagram magnified 127 times, where the black area represents the veto area where the substation cannot be built. After excluding the area where the substation cannot be built, the target site selection area is obtained.

[0065] By pre-screening the area to be screened, the improved multi-peak optimization particle swarm algorithm will search for the optimal site location in the target site selection area.

[0066] The site search model is constructed, and the objective function is constructed according to the earthwork volume, access road, and control factors of the target site selection area. The expression is as follows:

[0067] f=S min (volume)+S min (road)+S(control)

[0068] Among them, S min(volume) indicates the minimum earthwork volume required to build the substation when the substation outline is determined and the center of the outline is at a certain position. min (road) is the sum of the shortest paths from the substation contour center to the road when the access road is constructed. S(control) is the control adjustment factor for the substation. In the actual substation construction process, other control factors that appear can be set according to actual conditions.

[0069] According to the above objective function, multiple groups of sites to be processed are generated in the target site selection area.

[0070] like Figure 3 As shown, Figure 3 A schematic diagram of the calculation of earthwork volume and access road provided in an embodiment of the present invention is shown. By adopting a scientific regional screening method, a clear guidance is provided for station selection. An objective function is constructed according to the earthwork volume, access road and control adjustment factors in the substation construction process, thereby improving the practical application value of the station selection result.

[0071] Step S13, inputting N groups of the to-be-processed sites into the site search model, screening the optimal sites of each group of the to-be-processed sites, and obtaining the top N optimal sites, wherein the site search model executes an improved multi-modal optimization particle swarm algorithm during the processing, and the improved multi-modal optimization particle swarm algorithm includes a relationship between the speed and position of the particles:

[0072]

[0073] x i+1 =x i +v i+1

[0074] Among them, v i is the speed of the particle at step i, x i is the position of the particle at step i, x p-i is the optimal position searched by the i-th particle in the j-th population, x g-j is the optimal position searched by all particles in the jth population, x g-j-other is the distance x g-j The optimal position of the nearest other population, ω is the inertia coefficient, c1 and c2 are learning factors, c3 is a negative number, r1, r2 and r3 are randomly distributed values ​​between [0,1]; the execution strategy of the algorithm includes when the optimal site distance between two groups of sites to be processed is lower than the preset limit distance, uniformly increase the sites to be processed in one of the groups of sites to be processed and re-determine the optimal site.

[0075] Since it is necessary to obtain multiple sites in the target site selection area, in order to avoid multiple sites converging to the same position during the search optimization process, it is necessary to obtain a multi-peak solution to the site search problem to determine the locations of multiple sites. Therefore, the improved particle optimization algorithm is selected for site search.

[0076] The particle swarm optimization algorithm can maintain the diversity of the population by simulating the group behavior of bird foraging, and to a certain extent avoid falling into the local optimum, thereby ensuring the realization of multi-peak results and having good adaptability to the diverse needs of site selection.

[0077] Each particle population represents a group of sites to be processed. The improved particle optimization algorithm is used to optimize and update each group of sites to be processed, and the optimal site in each group is selected. The specific operations are as follows:

[0078] Determine the number of sites to be found, N, and set N populations. The initial number of particles in each population is the same. The position of each particle represents a potential site. The initial number of particles in each population, pop0, is set to:

[0079]

[0080] Among them, W is the number of pixels corresponding to the width direction of the target site selection area, and H is the number of pixels corresponding to the height direction of the target site selection area.

[0081] The particle position is updated during the evolution process according to the relationship between the particle's velocity and position.

[0082] During the evolution process, each particle will move towards its own optimal position and the optimal position of its own population, while moving away from the optimal positions of other populations.

[0083] In order to monitor the search status of N particle populations in real time, a diversity index is introduced, which is defined as follows:

[0084]

[0085] Among them, x ij represents the position of the i-th particle in the j-th population, Represents the average value of the positions of all particles in the jth population. The physical meaning of the above formula is the normalized distance between all particles and the average position of their respective populations. The smaller the value, the closer the particles are.

[0086] According to the diversity index of particles, the speed of particles is limited, and the range of particle speed amplitude is:

[0087]

[0088] |v i-min|=min(W,H)×1%

[0089] where v i-max is the upper limit of particle speed, v0 is the speed at the initial moment, div0 is the particle diversity at the initial moment, div is the particle diversity of the current step, v i-min is the lower limit of particle velocity.

[0090] According to the above formula, at the initial moment, the particle speed is relatively large and focuses on global exploration. As the particles gather together, the algorithm focuses on local search.

[0091] However, the particle optimization algorithm is prone to fall into the local optimum. In order to avoid the particles of different populations from converging too close, the particle optimization algorithm is improved. The improved algorithm automatically adjusts the number of particles in each step according to the diversity of particles during execution. Its expression is:

[0092]

[0093] Here, Δx represents the distance in the width direction of the optimal positions between different populations, and Δy represents the distance in the height direction between the optimal positions between different populations.

[0094] According to the above formula, the algorithm can avoid falling into the local optimum during the site search process. That is, when the distance between the particles representing the optimal site between the two populations is too close, the number of particles in one of the populations is greatly increased, and the newly added particles are randomly distributed in the entire solution area to redetermine the optimal site. This avoids the problem of different populations searching for an optimal location at the same time and increases the addressing ability of the site search model.

[0095] According to the objective function, various groups are iterated and the particle positions are updated for multiple rounds until the convergence condition is met. The convergence criterion is:

[0096] div≤5%×div0

[0097]

[0098] When the algorithm meets the above conditions, that is, the diversity index of the particles becomes 5% of the initial diversity, and 95% of the particles in each population are gathered in a circle with a radius of 5%×min(W,H), the convergence condition is met. At this time, the position of the optimal site is output from each of the N populations to obtain N optimal sites. The N optimal sites are the first N optimal sites among all the sites to be processed initially generated by the algorithm.

[0099] Step S14, determining the substation site selection planning result of the target site selection area according to the first N optimal sites.

[0100] According to the first N optimal sites outputted in step S13, evaluation and analysis are performed to determine the site selection location of the substation.

[0101] like Figure 4 As shown, Figure 4 A schematic diagram of the search results of this solution is shown in Figure 4 The white area in the figure is used to search for the locations of the three substations. The red dots represent the substation sites, and the blue five-pointed stars represent the nearest road connection points. In actual construction, the substations can be selected based on the site output by the algorithm and the actual situation.

[0102] The intelligent site selection method for substations of the present invention refers to multiple factors, comprehensively considers various factors that affect site selection, and improves the reliability of site selection results; adopts a scientific regional screening method to screen the site selection area, providing clearer guidance for site selection; in the process of finding the optimal site, any two sites that are too close are adjusted according to the exclusion strategy to avoid excessive convergence of sites output by different populations to the local optimum, so as to ensure the optimal site selection result.

[0103] The embodiment of the present invention further provides a substation intelligent site selection device, which is used to execute the substation intelligent site selection method as described above. Figure 5 This is a structural block diagram of a substation intelligent site selection device according to an embodiment of the present invention, and the device includes:

[0104] The data acquisition module 21 is used to optimize the acquired factors affecting the substation planning and obtain station selection data.

[0105] The site generation module 22 is used to screen the area where the substation can be built according to the site selection data to obtain the target site selection area, and generate N groups of sites to be processed in the target site selection area according to the preset site search number N.

[0106] The site screening module 23 is used to input the N groups of sites to be processed into the site search model, screen the optimal sites of each group of sites to be processed, and obtain the top N optimal sites, wherein the site search model executes the improved multi-peak optimization particle swarm algorithm during the processing, and the improved multi-peak optimization particle swarm algorithm includes the relationship between the speed and position of the particles:

[0107]

[0108] x i+1 =x i +v i+1

[0109] Among them, v i is the speed of the particle at step i, x iis the position of the particle at step i, x p-i is the optimal position searched by the i-th particle in the j-th population, x g-j is the optimal position searched by all particles in the jth population, x g-j-other is the distance x g-j The optimal position of the nearest other population, ω is the inertia coefficient, c1 and c2 are learning factors, c3 is a negative number, r1, r2 and r3 are randomly distributed values ​​between [0,1]; the execution strategy of the algorithm includes when the optimal site distance between two groups of sites to be processed is lower than the preset limit distance, uniformly increase the sites to be processed in one of the groups of sites to be processed and re-determine the optimal site.

[0110] The site determination module 24 is used to determine the substation site selection planning result of the target site selection area according to the first N optimal sites.

[0111] The technical features and technical effects of the device proposed in the embodiment of the present invention are the same as those of the method proposed in the embodiment of the present invention, and are not described in detail here. Each module in the above device can be implemented in whole or in part by software, hardware, and a combination thereof. Each of the above modules can be embedded in or independent of a processor in a computer device in the form of hardware, or can be stored in a memory in a computer device in the form of software, so that the processor can call and execute operations corresponding to each of the above modules.

[0112] An embodiment of the present invention further provides a computer-readable storage medium, which includes a stored computer program; wherein, when the computer program is running, it controls the device where the computer-readable storage medium is located to execute the substation intelligent site selection method as described above.

[0113] The embodiment of the present invention further provides a computer device, Figure 6 A structural block diagram of a preferred embodiment of a computer device provided by the present invention, the computer device includes a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, and the processor implements the above-mentioned substation intelligent site selection method when executing the computer program.

[0114] Preferably, the computer program can be divided into one or more modules / units (such as computer program 1, computer program 2, ...), and the one or more modules / units are stored in the memory and executed by the processor to complete the present invention. The one or more modules / units can be a series of computer program instruction segments that can complete specific functions, and the instruction segments are used to describe the execution process of the computer program in the computer device.

[0115] The processor may be a central processing unit (CPU), or other general-purpose processors, a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor, or the processor may be any conventional processor. The processor is the control center of the computer device, and various parts of the computer device are connected using various interfaces and lines.

[0116] The memory mainly includes a program storage area and a data storage area, wherein the program storage area can store an operating system, an application required for at least one function, etc., and the data storage area can store related data, etc. In addition, the memory can be a high-speed random access memory, or a non-volatile memory, such as a plug-in hard disk, a smart memory card (SmartMedia Card, SMC), a secure digital (Secure Digital, SD) card, and a flash card (Flash Card), etc., or the memory can also be other volatile solid-state storage devices.

[0117] It should be noted that the above-mentioned computer device may include, but is not limited to, a processor and a memory. Those skilled in the art will understand that Figure 6 The structural block diagram is merely an example of a computer device and does not constitute a limitation of the computer device, and may include more or less components than shown in the figure, or combine certain components, or different components.

[0118] In summary, the intelligent site selection method, device, equipment and storage medium for substations provided by the embodiments of the present invention have the following beneficial effects compared with the prior art:

[0119] (1) Using a variety of factors that affect substation construction, comprehensively considering the various factors that affect substation selection, and improving the reliability of substation selection results;

[0120] (2) Using scientific regional screening methods to screen the site selection areas provides clearer guidance for site selection;

[0121] (3) In the process of searching for the optimal site, any two sites that are too close to each other are adjusted according to the exclusion strategy to avoid excessive convergence of sites output by different populations to the local optimum, so as to ensure the optimal site selection result.

[0122] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A method for intelligent site selection of substations. It is characterized in that include: Optimize the acquired factors affecting substation planning to obtain station selection data; According to the site selection data, the area where the substation can be built is screened to obtain a target site selection area, and according to a preset site search number N, N groups of sites to be processed are generated in the target site selection area; Inputting N groups of sites to be processed into a search model based on an improved multi-modal optimization particle swarm algorithm, screening the optimal sites of each group of sites to be processed, and obtaining the top N optimal sites, wherein the site search model executes the improved multi-modal optimization particle swarm algorithm during the processing, and the improved multi-modal optimization particle swarm algorithm includes the relationship between the speed and position of the particles: x i+1 =x i +v i+1 Among them, v i is the speed of the particle at step i, x i is the position of the particle at step i, x p-i is the optimal position searched by the i-th particle in the j-th population, x g-j is the optimal position searched by all particles in the jth population, x g-j-other is the distance x g-j The optimal position of the nearest other population, ω is the inertia coefficient, c 1 and c 2 is the learning factor, c 3 is a negative number, r 1 、r 2 and r 3 is a value randomly distributed between [0,1]. The execution strategy of the algorithm includes, when the distance between the optimal sites of the two groups of sites to be processed is lower than a preset limit distance, uniformly increasing the number of sites in one group of sites to be processed and re-determining the optimal site; Based on the first N optimal sites, the substation site selection planning result of the target site selection area is determined.

2. The intelligent site selection method for substation according to claim 1, It is characterized in that The step of optimizing the acquired factors affecting substation planning to obtain station selection data includes: The elevation data, geological data and road data in the area to be screened are obtained, and then cleaned, integrated and unified to obtain the pre-processed station selection data.

3. The intelligent site selection method for substation according to claim 1, It is characterized in that The step of screening the area where the substation can be built according to the station selection data to obtain the target site selection area includes: According to the site selection data, the restricted area in the area to be screened is eliminated to obtain the target site selection area, wherein the restricted area includes the road area, the water system area and the steep area.

4. The intelligent site selection method for substation according to claim 1, It is characterized in that The step of generating N groups of sites to be processed in the target site selection area according to a preset site search quantity N includes: Constructing an objective function based on the earthwork volume, access road, and control factors of the target site selection area; The preset number of site searches N generates N groups of sites to be processed in the target site selection area.

5. The intelligent site selection method for substation according to claim 4, It is characterized in that The objective function is: f=S min (volume)+S min (road)+S(control) Among them, S min (volume) is the minimum earthwork volume of the substation, S min (road) is the sum of the shortest paths from the substation to the road, and S(control) is the control adjustment factor for the substation.

6. The intelligent site selection method for substation according to claim 4, It is characterized in that The step of inputting N groups of the to-be-processed sites into the site search model, screening the optimal site of each group of the to-be-processed sites, and obtaining the top N optimal sites includes: Iteratively update the positions of the N groups of sites to be processed according to the objective function and the relationship; According to the position iteration update results, the optimal site of each group of sites to be processed is determined, and the top N optimal sites are obtained.

7. The intelligent site selection method for substation according to claim 6, It is characterized in that During the process of iterative position updating, the speed of the iterative position updating is limited according to the diversity index, wherein the speed limit is: |v i-min |=min(W,H)×1% Among them, v i-max is the upper limit of particle velocity, v 0 is the initial speed, div0 is the particle diversity at the initial time, div is the particle diversity at the current step, v i-min is the lower limit of particle velocity, W is the number of pixels corresponding to the width direction of the target site selection area, and H is the number of pixels corresponding to the height direction of the target site selection area.

8. A substation intelligent site selection device, It is characterized in that include: The data acquisition module is used to optimize the acquired factors affecting the substation planning to obtain station selection data; A site generation module is used to screen the area where the substation can be built according to the site selection data to obtain a target site selection area, and generate N groups of sites to be processed in the target site selection area according to a preset site search number N; The site screening module is used to input N groups of the sites to be processed into the site search model, screen the optimal sites of each group of the sites to be processed, and obtain the top N optimal sites, wherein the site search model executes an improved multi-modal optimization particle swarm algorithm during the processing, and the improved multi-modal optimization particle swarm algorithm includes the relationship between the speed and position of the particles: x i+1 =x i +v i+1 Among them, v i is the speed of the particle at step i, x i is the position of the particle at step i, x p-i is the optimal position searched by the i-th particle in the j-th population, x g-j is the optimal position searched by all particles in the jth population, x g-j-other is the distance x g-j The optimal position of the nearest other population, ω is the inertia coefficient, c 1 and c 2 is the learning factor, c 3 is a negative number, r 1 、r 2 and r 3 is a value randomly distributed between [0,1]. The execution strategy of the algorithm includes, when the distance between the optimal sites of the two groups of sites to be processed is lower than a preset limit distance, uniformly increasing the number of sites in one group of sites to be processed and re-determining the optimal site; The site determination module is used to determine the substation site selection planning result of the target site selection area based on the first N optimal sites.

9. A computer device, It is characterized in that The method comprises a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, wherein when the processor executes the computer program, the method for intelligent site selection of a substation as claimed in any one of claims 1 to 7 is implemented.

10. A computer-readable storage medium, It is characterized in that The computer-readable storage medium stores a computer program, wherein when the device where the computer-readable storage medium is located executes the computer program, the intelligent site selection method for substations according to any one of claims 1 to 7 is implemented.

Citation Information

Patent Citations

  • Planning system for comprehensive optimization of regional power distribution network

    CN104680427A

  • Improved particle swarm algorithm for solving high-dimensional optimization problem

    CN111310883A

  • Transformer substation optimization site selection method based on gravity center regression and particle swarm hybrid algorithm

    CN112070351A

  • Optimization method for multi-station fusion site selection planning

    CN112949898A

  • Site selection optimization method based on improved multi-modal multi-objective particle swarm optimization algorithm

    CN116702945A

Cited By

  • Substation deployment method and device, electronic equipment and computer readable medium

    CN120875166A

  • Substation deployment method and apparatus, electronic device, and computer readable medium

    CN120875166B