Drawing checking center internal control method and system, electronic equipment and storage medium
By calculating the load value and efficiency of the map reviewers and dynamically allocating task allocation, the problems of waste of resources and inefficiency caused by fixed task allocation in the existing technology are solved, and the work efficiency of the map review center is improved.
Patent Information
- Application Number
- CN202411120890.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-12-03
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing internal control method of the map review center relies on a fixed number of task allocation, making it difficult to accurately consider the workload of the map review personnel, resulting in waste of resources and inefficiency.
By obtaining the current number and type of the map reviewers, calculating their map review load value, filtering out target personnel with too high or too low load, combining their efficiency and the baseline number of map review centers, dynamically allocate the task allocation volume to achieve load Equalization and efficiency improvement.
It realizes accurate calculation and dynamic allocation of task volume of map reviewers, improves the efficiency of internal control of map review centers, and avoids resource waste and work overload.
Smart Images

Figure CN119067376A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of data processing technology, and in particular to an internal control method, system, electronic equipment and storage medium of a drawing review center. Background Art
[0002] With the rapid growth of information technology and data management needs, all walks of life are facing the challenge of processing and reviewing large amounts of data. Especially in areas such as architectural planning review, the role of the review center has become particularly important. The review center is responsible for ensuring that the submitted documents meet specific standards and regulations. This process is crucial to ensure the accuracy of the information. Nowadays, faced with a large amount of review work, the staff within the review center are facing challenges. How to coordinate the work within the review center has become a problem that needs to be overcome urgently.
[0003] At present, the existing internal control methods of the review center rely on assigning a fixed number of tasks to the reviewers in the review center. However, in actual applications, due to the different complexity of review tasks, it is often difficult to accurately consider the workload of reviewers only by assigning a fixed number of tasks, which may cause some reviewers to be overloaded due to being assigned too complex or too many tasks, while others may waste resources due to insufficient tasks, resulting in low efficiency of internal control of the review center. Summary of the invention
[0004] The present application provides a method, system, electronic device and storage medium for internal control of a drawing review center, which have the effect of improving the efficiency of internal control of the drawing review center.
[0005] In a first aspect, the present application provides an internal control method of a drawing review center, comprising: Acquire the current number of tasks and task types of multiple reviewers in the review center, and determine the review load value of each reviewer based on the number of tasks and the task type; Screening out target personnel whose drawing review load values exceed the standard drawing review load value range from among the drawing review personnel; Obtaining the number of drawings reviewed by each target person within a preset period, and determining the drawing review efficiency of each target person based on the number of drawings reviewed; Determine the task allocation of each target person based on the review efficiency and review load value of each target person and the benchmark review quantity of the review center; Based on the assigned amount of each task, the current number of tasks for each target person is adjusted.
[0006] In a second aspect of the present application, a drawing review center internal control system is provided, the system comprising: The task information acquisition module is used to obtain the current task quantity and task type of multiple reviewers in the review center, and determine the review load value of each reviewer based on the task quantity and task type; A target personnel determination module is used to screen out target personnel whose drawing review load value exceeds the standard drawing review load value range from among the drawing review personnel; The task allocation amount determination module is used to obtain the number of drawings reviewed by each target person within a preset period, and determine the drawing review efficiency of each target person based on the number of drawings reviewed; and determine the task allocation amount of each target person in combination with the drawing review efficiency and drawing review load value of each target person and the benchmark drawing review number of the drawing review center; The task allocation module is used to allocate the current task quantity of each target person based on the task allocation quantity.
[0007] In a third aspect of the present application, an electronic device is provided, comprising a memory, a processor, and a program stored in the memory and executable on the processor, wherein the program can implement an internal control method of a drawing review center when loaded and executed by the processor.
[0008] In a fourth aspect of the present application, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the processor implements a method for internal control of a drawing review center.
[0009] In summary, one or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages: By adopting the above technical solution, the current number and type of tasks of the target personnel are obtained, and their review load values are calculated, so that the personnel with too high loads can be accurately judged. Then the system obtains the number of reviews of the target personnel within the preset period to determine their review efficiency. After clarifying the efficiency and load conditions of the target personnel, the system can reasonably determine the task allocation for each person in combination with the center's benchmark review volume. Finally, the system dynamically allocates the current number of tasks of the target personnel based on the calculated task allocation, and realizes the accurate calculation and dynamic allocation of the target personnel's task volume under different loads and efficiencies. It comprehensively considers the working conditions of the target personnel and the overall requirements of the center, realizes the reasonable control of the task volume, and can dynamically allocate tasks for reviewers with heavy task loads and fewer tasks, thereby improving the efficiency of internal control of the review center. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] Figure 1 It is a flowchart of an internal control method of a drawing review center provided in an embodiment of the present application; Figure 2It is a structural diagram of an internal control system of a drawing review center provided in an embodiment of the present application; Figure 3 It is a structural schematic diagram of an electronic device provided in an embodiment of the present application.
[0011] Description of reference numerals: 300, electronic device; 301, processor; 302, communication bus; 303, user interface; 304, network interface; 305, memory. DETAILED DESCRIPTION
[0012] In order to enable technicians in this field to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this application, not all of the embodiments.
[0013] In the description of the embodiments of the present application, words such as "for example" or "for example" are used to indicate examples, illustrations or explanations. Any embodiment or design described as "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "for example" or "for example" is intended to present related concepts in a specific way.
[0014] In the description of the embodiments of the present application, the meaning of the term "multiple" refers to two or more. For example, multiple systems refer to two or more systems, and multiple screen terminals refer to two or more screen terminals. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the indicated technical features. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. The terms "include", "comprise", "have" and their variations all mean "including but not limited to", unless otherwise specifically emphasized.
[0015] This application embodiment provides an internal control method for a drawing review center. In one embodiment, please refer to Figure 1 , Figure 1 This is a flow chart of the internal control method of the drawing review center provided in the embodiment of the present application. The method can be implemented by a computer program, which can be integrated into an application or run as an independent tool application. The method can also be implemented by a single-chip microcomputer or run in an internal control system of the drawing review center based on the von Neumann system. Specifically, the method can include the following steps: Step 101: obtaining the current task quantity and task type of multiple reviewers in the review center, and determining the review load value of each reviewer based on the task quantity and task type.
[0016] The number of tasks refers to the number of pending review tasks currently assigned to each reviewer. In the embodiment of the present application, the number of tasks can be understood as the total number of various drawings, documents and other materials that each reviewer needs to process and review within a given time period.
[0017] Task types refer to different categories of drawing review tasks, reflecting the work attributes and complexity of each task. In the embodiment of the present application, task types can be understood as the classification of drawing review tasks, such as the complexity level of the drawings, the number of file pages, etc. Different types represent different attributes of the tasks, corresponding to different workloads required to complete the tasks.
[0018] The review load value refers to the quantitative value of the workload of each reviewer within a given time. In the embodiment of the present application, the review load value can be understood as a comprehensive index obtained by calculating the number of tasks and task types of each reviewer, which is used to evaluate and reflect the actual workload of each reviewer and is the basis for determining whether it is necessary to adjust the task allocation to achieve load balancing.
[0019] Specifically, the current number of tasks for each reviewer is obtained by statistics, that is, the number of drawing files that each reviewer needs to process and review. At the same time, the type of each task is obtained, where the task type is a classification of the complexity of the drawing, such as simple drawings, medium-complex drawings, and highly complex drawings. Then, according to the preset task type weight table, the weight coefficients corresponding to different task types are specified, such as the weight coefficient of simple drawing tasks is 1, the weight coefficient of medium-complex drawing tasks is 1.5, and the weight coefficient of highly complex drawing tasks is 2. The system calculates the weight of each task based on this, and then multiplies it by the number of tasks corresponding to the reviewer, and finally accumulates all the task weights of each person to obtain the review load value of this reviewer. In this way, not only the number of tasks is taken into account, but also the actual work complexity of different types of tasks, so that the calculated review load value can more accurately reflect the actual workload of each reviewer, and provide an accurate basis for determining task allocation based on the load value in the future, thereby improving the effect of internal control of the review center.
[0020] Based on the above embodiment, as an optional embodiment, in step 101: determining the review load value of each reviewer based on the number of tasks and the type of tasks, this step may also include the following steps: Step 201: Obtain a preset task type weight table, which includes weight coefficients corresponding to different task types; based on the task type weight table, determine the weight coefficients corresponding to each type of review task currently assigned to each reviewer.
[0021] The preset task type weight table refers to a mapping table pre-stored by the system for determining the weight coefficients corresponding to different types of drawing review tasks. In the embodiment of the present application, the preset task type weight table can be understood as a database table or a configuration file, which clarifies the correspondence between various drawing review task categories such as simple drawings, complex drawings, etc. and the weight coefficients of the tasks of this type.
[0022] Specifically, in order to accurately calculate the load value of each reviewer, it is necessary to obtain the correspondence between the task type and the weight. The purpose of this step is to obtain the preset task type weight table, and determine the weight coefficient of each task accordingly, as an intermediate parameter for calculating the load value. A task type weight table is pre-stored, which clarifies the mapping relationship between different types of review tasks and corresponding weight coefficients, such as a simple drawing task weight of 1, a medium-complex drawing task weight of 1.5, etc. After obtaining each person's task type, the system determines the weight coefficient of each task according to this preset table. This can avoid human subjective judgment and evaluate the load size of different task types through a standardized weight table. The larger the weight coefficient, the greater the workload required to complete the task. After determining the weight coefficient, multiply it by the number of tasks to realize the load value calculation considering the complexity of the task. Through this process, the standard correspondence between the task type and the weight is obtained and applied to each specific task to calculate the standardized weight coefficient, which provides an accurate basis for the subsequent summary of the load value, so that the load value can objectively reflect the workload.
[0023] Step 202: For each reviewer, multiply the weight coefficient corresponding to each type of review task by the number of corresponding types of review tasks in the task quantity to obtain the review load value of the reviewer.
[0024] Specifically, the number of tasks of each reviewer is counted. For example, a person has 5 simple drawing tasks and 3 complex drawing tasks. Then the task type weight table is consulted to obtain the corresponding weight coefficient. The weight coefficient of simple drawing tasks is 1, and the weight coefficient of complex drawing tasks is 2. According to this weight coefficient, the system calculates the weight of each task separately, that is, the weight of 5 simple drawing tasks is 5, and the weight of 3 complex drawing tasks is 6. The weights of all tasks of the reviewer are added together, that is, 5+6=11, as the review load value of the reviewer. In this way, by calculating the product of the number of tasks and the weight, and summarizing the weights of all tasks of each person, the impact of the task type can be fully considered, so that the review load value can truly reflect the workload of each reviewer.
[0025] Step 102: Filter out target personnel whose review load values exceed the standard review load value range from among the reviewers.
[0026] Specifically, a standard review load value range is preset, for example, the load value should not exceed 100. The system then traverses the load value calculated by each reviewer and compares it with the standard range. If a person's load value is greater than 100, the person is identified as a target person with an overload. By comparing and screening with the standard range, the reviewers who are truly overloaded can be automatically and efficiently found. These target personnel will exceed the reasonable workload to complete the current task, so task allocation and load reduction are required. This process realizes the automatic screening of target personnel with the risk of overload by setting the standard load value range.
[0027] Step 103: Obtain the number of drawings reviewed by each target person within a preset period, and determine the drawing review efficiency of each target person based on the number of drawings reviewed.
[0028] Among them, the number of drawing reviews refers to the total number of drawing reviews completed by the target personnel within a given statistical period. In the embodiment of the present application, the number of drawing reviews can be understood as the total number of drawings actually reviewed and completed by the target personnel within the statistical period.
[0029] The efficiency of drawing review refers to the effectiveness of the target personnel in completing the drawing review work within a given time. In the embodiment of the present application, the efficiency of drawing review can be understood as the average number of drawings reviewed by the target personnel per day during the statistical period, which is equal to the actual number of drawings reviewed during the statistical period divided by the working time, and is used to evaluate and compare the work efficiency of the target personnel. The higher the efficiency of drawing review, the more drawings are reviewed in the same time, and the higher the work efficiency.
[0030] Specifically, after identifying the target personnel with excessive workload, it is necessary to evaluate the work efficiency of these personnel in order to formulate targeted control measures. The purpose of this step is to obtain the number of drawings reviewed by the target personnel in a statistical period and calculate their review efficiency. A statistical period is preset, such as the last month. Then the number of drawings reviewed by each target personnel in this period is counted, that is, the total number of drawings reviewed. The system also obtains the number of drawings that are unqualified and need to be reworked in these drawings, and calculates the actual effective number of drawings reviewed by each person. Then the system obtains the working time of each target personnel in the statistical period, that is, the total working time of the period. Finally, according to the drawing review efficiency = actual number of drawings reviewed / working time, the drawing review efficiency of each target personnel is calculated. In this way, by obtaining the drawing review quantity and working time parameters of the target personnel in the statistical period, a standardized drawing review efficiency can be calculated to evaluate the work efficiency of different target personnel, which serves as the basis for determining how to reasonably control and allocate resources in the future.
[0031] Based on the above embodiment, as an optional embodiment, in step 103: determining the review efficiency of each target person based on the number of drawings reviewed, this step may also include the following steps: Step 301: Determine the number of unqualified work in each review quantity; based on each review quantity and the number of unqualified work in each review quantity, determine the actual review quantity of each target personnel.
[0032] The actual number of drawings reviewed refers to the total number of valid drawings reviewed by the target personnel after excluding unqualified drawings reviewed. In the embodiment of the present application, the actual number of drawings reviewed can be understood as the total number of drawings reviewed by the target personnel within the statistical period minus the remaining number of unqualified drawings that need to be reworked.
[0033] Specifically, in order to accurately calculate the review efficiency of the target personnel, it is necessary to eliminate the number of unqualified reviewers and obtain the actual effective review quantity. Count the total number of reviewers for each target personnel in the statistical period. Then, check these reviews one by one and filter out the number of reviews that are of unqualified quality and need to be reworked. Then, according to the actual number of reviews = total number of reviews - number of unqualified reviews, the actual effective number of reviews for each target personnel in the statistical period is obtained. For example, if the total number of reviews of a reviewer is 100 and the number of unqualified reviews is 10, then the actual number of reviews is 100-10=90. This can eliminate the unqualified parts, so that the subsequent calculated review efficiency more accurately reflects the actual work efficiency level of each target personnel. That is, the actual number of reviews divided by the working time is used to evaluate work efficiency.
[0034] Step 302: Obtain the actual working hours of each target person within a preset period; for each target person, divide the actual number of drawings reviewed by the corresponding actual working hours to obtain the drawing review efficiency of the target person.
[0035] Among them, the actual working hours refer to the actual working hours of the target personnel in the statistical period after excluding non-working time. In the embodiment of the present application, the actual working hours can be understood as the pure working time after deducting the non-working time such as leave and rest from the total working time of the target personnel in the statistical period.
[0036] Specifically, in order to accurately calculate the drawing review efficiency, after obtaining the actual number of drawings reviewed, it is also necessary to obtain the actual working time as a calculation parameter. The purpose of this process is to obtain the actual working time and calculate the drawing review efficiency of each target person. The total working time of each target person in the statistical period is counted, and then the non-working time such as leave and rest is eliminated to obtain the actual working time of the statistical period. Then, according to the drawing review efficiency = actual number of drawings reviewed / actual working time, the actual number of drawings reviewed by each target person is obtained, and divided by the corresponding actual working time, the average drawing review efficiency of the target person in the statistical period can be calculated.
[0037] Step 104: Determine the task allocation of each target person based on the review efficiency and review load value of each target person and the benchmark review quantity of the review center.
[0038] The benchmark review quantity refers to the standard review quantity that each reviewer needs to complete within a given time as specified by the review center. In the embodiment of the present application, the benchmark review quantity can be understood as the review quantity indicator that each person needs to complete every day or week, which is preset by the review center.
[0039] The task allocation refers to the specific number of review tasks assigned to each target person. In the embodiment of the present application, the task allocation can be understood as determining the number of review tasks that the target person needs to complete within a certain period of time in the future according to his / her work situation.
[0040] Specifically, in order to dynamically control the target personnel's review task volume, it is necessary to comprehensively consider multiple factors to determine the new task allocation. The current review efficiency and load value of each target personnel are counted. Then the system queries the preset benchmark review quantity of the review center, that is, the standard workload of each person. Then, the system will evaluate the actual work status of each target personnel based on the above three factors. For those with low efficiency and heavy load, reduce their new task volume; for those with high efficiency but heavy load, maintain or slightly increase the task volume. In this way, a new task allocation that takes into account both efficiency and load can be formulated for each target personnel, realizing dynamic optimization control of workload.
[0041] Based on the above embodiment, as an optional embodiment, in step 104: combining the review efficiency and review load value of each target person and the benchmark review quantity of the review center to determine the task allocation amount of each target person, this step may also include the following steps: Step 401: summing up the drawing review efficiencies of each target person to obtain a total drawing review efficiency value; dividing the drawing review efficiency of each target person by the total drawing review efficiency value to obtain an efficiency weight of each target person.
[0042] The efficiency weight refers to the proportion of the target personnel's review efficiency to the total efficiency of all target personnel. In the embodiment of the present application, the efficiency weight can be understood as the result of dividing the review efficiency of each target personnel by the sum of the review efficiencies of all target personnel.
[0043] Specifically, in order to reasonably determine the amount of new tasks assigned to each target person, their work efficiency needs to be considered. The purpose of this step is to calculate the efficiency weight as an important reference for allocating task volumes. Collect the drawing review efficiency data of all target personnel during the statistical period and calculate the total efficiency value. Then divide each person's drawing review efficiency by the above total efficiency value in turn to get the efficiency weight of the target person. For example, the system monitors a total of 5 people, with efficiencies of 0.5, 0.8, 1, 0.7, and 0.6, respectively, and the total efficiency value is 3.6. Then the efficiency weight of the first person is 0.5 / 3.6=0.139. By calculating the efficiency weight of each target person, the efficiency and contribution to the total amount can be evaluated, which provides an important reference for the subsequent formulation of task allocation plans and arranges the workload reasonably according to the efficiency.
[0044] Step 402: Multiply the efficiency weight of each target person by the benchmark drawing review quantity to obtain the initial task allocation of each target person.
[0045] The initial task allocation refers to the task allocation of the target personnel preliminarily calculated based on the efficiency weight and the benchmark number. In the embodiment of the present application, the initial task allocation can be understood as the number of tasks obtained by multiplying the efficiency weight of each target person by the benchmark drawing review number.
[0046] Specifically, after obtaining the efficiency weight of the target personnel, it is necessary to preliminarily calculate the task allocation amount based on the benchmark quantity. The purpose of this step is to obtain the initial task allocation plan. The efficiency weight of each target personnel is counted. Then the system queries the preset benchmark drawing review quantity. Next, the system multiplies the efficiency weight of each person by the benchmark quantity, that is, to allocate the benchmark workload according to the efficiency ratio. If the benchmark quantity is 100 and someone's efficiency weight is 0.2, then his initial task volume is 100*0.2=20. In this way, a task allocation plan that takes into account efficiency factors and meets the benchmark quantity can be preliminarily obtained, so that high-efficiency personnel can take on more work and low-efficiency personnel have less tasks. By calculating the initial task allocation, the system can reasonably determine the initial workload of each person based on the efficiency difference, providing a basis for further optimization.
[0047] Step 403: For each target person, the initial task allocation is adjusted based on the drawing review load value to obtain the task allocation of the target person.
[0048] Specifically, after calculating the initial task allocation, it is necessary to consider the load conditions of the target personnel and make adjustments to obtain the final task volume. The purpose of this step is to optimize and adjust the initial task allocation plan based on the load value, and calculate the initial task allocation for each target person according to the efficiency weight. The system then obtains the current drawing review load value of each target person. For people with too high a load, the system will appropriately reduce their initial task volume; otherwise, the task volume can be increased. If the initial volume is 100 and the load factor is 0.9, the final task volume can be adjusted to 90. In this way, the efficiency and current load conditions can be comprehensively considered to optimize the initial task allocation, so that the final task allocation can improve efficiency while taking into account the load, and achieve reasonable resource planning.
[0049] Based on the above embodiment, as an optional embodiment, in step 403: adjusting the initial task allocation based on the drawing review load value to obtain the task allocation of the target personnel, this step may also include the following steps: Step 413: Based on the drawing review load value, determine the corresponding task compensation amount in the database.
[0050] Specifically, in order to alleviate the workload of the target personnel, it is necessary to determine the corresponding task compensation amount based on the load value. The purpose of this step is to query the corresponding compensation amount in the database based on the load value. The current load coefficient of each target person has been recorded. The system will consult the correspondence table between the load value and the compensation amount preset in the database. For example, the table stipulates that a load coefficient of 0.9 corresponds to a compensation of 5 tasks, and 0.95 corresponds to a compensation of 10 tasks. For a person with a load coefficient of 0.93, the system queries and determines that his compensation task amount is 10. In this way, by querying the mapping relationship in the database, the compensation amount that matches the current load condition can be quickly determined to adjust the work of the overloaded target personnel to prevent them from being overworked.
[0051] Step 423: Determine whether the initial task allocation amount is greater than or equal to the preset standard task allocation amount; if the initial task allocation amount is greater than or equal to the preset standard task allocation amount, subtract the task compensation amount from the initial task allocation amount to obtain the task allocation amount of the target person.
[0052] The preset standard task allocation refers to the minimum amount of task allocation preset by the system. In the embodiment of the present application, the preset standard task allocation can be understood as the minimum number of task allocations for each target person within a given time.
[0053] Specifically, in order to prevent the task volume from being too small, it is necessary to determine whether the initial volume is higher than the standard volume and then adjust it. The purpose of this step is to determine the final task allocation volume through judgment and calculation. The system has obtained the initial task allocation volume and the corresponding compensation volume of each target person. The system also presets the lower limit of the standard task allocation, and then the system determines whether the initial task volume of each person is greater than or equal to the standard volume. If so, the compensation volume is subtracted from the initial volume to obtain the final adjusted task allocation volume. For example, if someone's initial volume is 100, the compensation volume is 10, and the standard volume is 80, then the final task volume is calculated as 100-10=90. In this way, the system can optimize the control of task allocation in combination with the compensation volume while ensuring that the task volume is not too small.
[0054] Step 433: If the initial task allocation amount is less than the preset standard task allocation amount, the initial task allocation amount is added to the task compensation amount to obtain the task allocation amount of the target person.
[0055] Specifically, if the initial task allocation is lower than the standard amount, an additive adjustment is required. The purpose of this step is to prevent too little task allocation. The initial task allocation and compensation amount of each target person have been calculated. The system also presets a standard task allocation lower limit. Next, the system determines whether the initial task amount of each person is lower than the standard amount. If so, the initial amount of the target person is added to his compensation amount to obtain the adjusted final task allocation amount. For example, someone's initial amount is 80, the compensation amount is 10, and the standard amount is 100. Then the final task amount is calculated to be 80+10=90. In this way, when the initial task amount is small, the system can increase the task amount through addition calculation to ensure that the task allocation is not lower than the standard lower limit, taking into account the load impact and ensuring work efficiency.
[0056] Step 105: Based on the allocation amount of each task, the current task quantity of each target person is allocated.
[0057] Specifically, after determining the final task allocation of each target person, it is necessary to carry out actual task allocation based on this amount. The purpose of this step is to achieve dynamic allocation of the number of tasks. The system has calculated the task allocation of each target person in the current cycle. The system also has data on the number of tasks that each person currently has not completed. The system will increase or decrease the allocation of tasks so that the final actual number of tasks for each person meets the calculated task allocation. For example, if someone currently has 50 tasks and the calculated task allocation is 80, the system will assign 30 additional tasks to the employee. In this way, the system can dynamically and real-timely allocate the number of tasks for the target person based on the calculation results, thereby achieving the purpose of reasonably controlling the workload and improving work efficiency.
[0058] Based on the above embodiment, as an optional embodiment, in step 105: based on the allocation amount of each task, the current number of tasks for each target person is allocated. This step may also include the following steps: Step 501: Calculate the task difference between the current task quantity of each target person and the corresponding task allocation quantity.
[0059] Specifically, the task allocation of each target person has been obtained, that is, the optimal number of tasks calculated based on factors such as their review efficiency and review load value. Then this allocation is subtracted from the actual number of tasks currently held by the target person to obtain a task difference. For target persons with a positive task difference, it means that they currently have too many tasks and need to reduce the amount of tasks appropriately; for target persons with a negative task difference, it means that they currently have too few tasks and need to increase the amount of tasks appropriately. By calculating the difference, we can clearly understand the deviation of the current task allocation of each person. Next, according to these task differences, the target persons are divided into two groups: persons to be added with tasks and persons to be reduced with tasks. The former have too few tasks, while the latter have too many tasks. Then, according to the preset task allocation rules, the excess tasks on hand of the persons to be reduced are allocated to the persons to be added with tasks, so that the actual number of tasks for each person is as close to the optimal allocation as possible. The effect of this is that the workload within the review center is reasonably redistributed and balanced, avoiding the situation where tasks are over-concentrated or idle.
[0060] Step 502: Based on the differences of each task, determine a plurality of personnel to be added and a plurality of personnel to be removed from the target personnel.
[0061] Specifically, the task differences of all target personnel are traversed. For those with positive differences, they are divided into the group of personnel to be reduced; for those with negative differences, they are divided into the group of personnel to be added. In this way, the group to be reduced has too many tasks to be allocated, and the group to be added has insufficient tasks to be supplemented. Through this grouping, the object and direction of task allocation are determined. The excess tasks in the hands of the personnel to be reduced will be reallocated to the personnel to be added until the actual number of tasks for all people is as close to the optimal allocation as possible. The effect of this is to reasonably rebalance the workload within the review center, avoid the extreme imbalance of task distribution among personnel, improve the review efficiency as a whole, and also help control the review quality and prevent individual personnel from overloading and causing negligence or errors.
[0062] Step 503: According to the preset task allocation rules, the redundant tasks of the personnel whose tasks are to be reduced are allocated to the personnel whose tasks are to be increased.
[0063] The preset task allocation rule refers to the norms and principles of task allocation preset in the system. In the embodiment of the present application, the preset task allocation rule can be understood as a specific algorithm or mapping relationship for determining the number of tasks to be increased or decreased according to the task difference.
[0064] The personnel to be reduced refer to the target personnel whose task amount needs to be reduced. In the embodiment of the present application, the personnel to be reduced can be understood as the target personnel whose current task amount is greater than the calculated task allocation, that is, the target personnel whose task difference is less than zero.
[0065] The personnel to be added refer to the target personnel whose task amount needs to be increased and adjusted. In the embodiment of the present application, the personnel to be added can be understood as the target personnel whose current task amount is less than the calculated task allocation amount, that is, the target personnel whose task difference is greater than zero.
[0066] Specifically, for each person whose tasks are to be reduced, we first need to determine the number of excess tasks that need to be allocated to him based on his task difference. Then we traverse the task differences of all the people whose tasks are to be added, and match the person whose task is to be added with the smallest absolute difference into a deployment group. After forming multiple deployment groups, in each group, the excess tasks of the people whose tasks are to be reduced are deployed to the corresponding people whose tasks are to be increased according to certain rules. The rules can be to allocate all tasks directly, or to allocate them according to a certain ratio or other algorithms, depending on the preset deployment rules. Through this step, the number of work tasks of the internal personnel of the drawing review center has been redistributed, and the imbalance of too many or too few tasks has been corrected, so that the actual number of tasks for each person is as close as possible to the calculated ideal allocation.
[0067] Based on the above embodiment, as an optional embodiment, in step 503: according to the preset task allocation rule, the redundant tasks of each task personnel to be reduced are allocated to each task personnel to be added. This step may also include the following steps: Step 513: Determine the redundant tasks of each person whose tasks are to be reduced based on the task difference of each person whose tasks are to be reduced.
[0068] Specifically, we traverse all personnel whose tasks are to be reduced, and for each person, we directly use the value of their task difference as the number of excess tasks that need to be allocated. For example, if the task difference of a certain personnel A who needs to reduce tasks is +20, then we determine that the number of excess tasks that need to be allocated in A's hands is 20. In this way, the number of excess tasks for all personnel whose tasks are to be reduced can be determined. Through this step, we not only know which personnel have excess tasks that need to be allocated, but also obtain an accurate allocation target value, that is, the specific number of tasks that each person needs to allocate. This points out the direction and scope for subsequent allocation work. After determining the number of excess tasks, we can start to reasonably allocate these tasks to those personnel who have insufficient tasks to be increased, so that the actual number of tasks for each person can eventually be close to the optimal allocation amount calculated previously, thereby balancing the workload within the drawing review center.
[0069] Step 523: traverse the task differences of each person to be added and each person to be reduced, and take the person to be added and the person to be reduced with the smallest deviation between the task differences as a task allocation group, to obtain multiple task allocation groups.
[0070] The task allocation group refers to a set of target personnel for task allocation. In the embodiment of the present application, the task allocation group can be understood as dividing the target personnel into two groups, one to be added and one to be reduced, according to the task volume difference, as the objects of task allocation.
[0071] Specifically, in order to achieve balanced allocation of task quantities, it is necessary to pair the personnel to be added or reduced with the smallest task difference deviation into allocation groups. The purpose of this step is to obtain multiple allocation groups required for task allocation. The system has counted the difference in task quantities for each person to be added and reduced, and traversed the difference between each person to be added and reduced one by one, looking for the person to be added or reduced with the smallest absolute value of the difference deviation to pair up and form an allocation group. In this way, multiple allocation groups are formed by traversing and forming an allocation group through matching with the minimum deviation, which can make the allocation of task quantities tend to be balanced and reasonable, and avoid the situation where the adjustment amount of one party is too large.
[0072] Step 533: In each task allocation group, the redundant tasks of the personnel to be reduced are allocated to the personnel to be added.
[0073] Specifically, after forming the task allocation group, it is necessary to redistribute tasks within each group. The purpose of this step is to achieve a balanced allocation of tasks within the group. The system has matched and generated multiple task allocation groups, each of which contains one person whose tasks are to be reduced and one person whose tasks are to be increased. In each allocation group, the system will directly allocate the excess tasks of the person to be reduced to the person to be increased in the group. In this way, by directly allocating excess tasks within the group, a balanced allocation of tasks within the group can be achieved, avoiding excessive changes in the task volume of the target personnel, and realizing the allocation of the drawing review tasks.
[0074] Reference Figure 2 , is an internal control system of a drawing review center provided in an embodiment of the present application, the system comprises: a task information acquisition module, a target personnel determination module, a task allocation quantity determination module, and a task allocation module, wherein: The task information acquisition module is used to obtain the current task quantity and task type of multiple reviewers in the review center, and determine the review load value of each reviewer based on the task quantity and task type; The target personnel determination module is used to screen out the target personnel whose review load value exceeds the standard review load value range among various review personnel; The task allocation quantity determination module is used to obtain the number of drawings reviewed by each target person in a preset period, and determine the drawing review efficiency of each target person based on the number of drawings reviewed; and determine the task allocation quantity of each target person in combination with the drawing review efficiency and drawing review load value of each target person and the benchmark drawing review quantity of the drawing review center; The task allocation module is used to allocate the current number of tasks for each target person based on the allocation amount of each task.
[0075] On the basis of the above embodiment, the task information acquisition module is also used to obtain a preset task type weight table, which includes weight coefficients corresponding to different task types; based on the task type weight table, the weight coefficients corresponding to each type of review task currently assigned to each reviewer are determined; for each reviewer, the weight coefficient corresponding to each type of review task is multiplied by the number of corresponding type of review tasks in the task quantity to obtain the review load value of the reviewer.
[0076] On the basis of the above embodiment, the task allocation quantity determination module is also used to determine the number of work that failed the review in each review quantity; determine the actual review quantity of each target personnel based on each review quantity and the number of work that failed the review in each review quantity; obtain the actual working time of each target personnel within a preset period; for each target personnel, divide the actual review quantity by the corresponding actual working time to obtain the review efficiency of the target personnel.
[0077] On the basis of the above embodiment, the task allocation amount determination module is further used to sum the drawing review efficiency of each target personnel to obtain the total drawing review efficiency; divide the drawing review efficiency of each target personnel by the total drawing review efficiency to obtain the efficiency weight of each target personnel; multiply the efficiency weight of each target personnel by the benchmark drawing review quantity to obtain the initial task allocation amount of each target personnel; for each target personnel, adjust the initial task allocation amount based on the drawing review load value to obtain the task allocation amount of the target personnel.
[0078] On the basis of the above embodiment, the task allocation quantity determination module is also used to determine the corresponding task compensation quantity in the database based on the drawing review load value; judge whether the initial task allocation quantity is greater than or equal to the preset standard task allocation quantity; if the initial task allocation quantity is greater than or equal to the preset standard task allocation quantity, then subtract the task compensation quantity from the initial task allocation quantity to obtain the task allocation quantity of the target personnel; if the initial task allocation quantity is less than the preset standard task allocation quantity, then add the initial task allocation quantity to the task compensation quantity to obtain the task allocation quantity of the target personnel.
[0079] Based on the above embodiment, the task allocation module is also used to calculate the task difference between the current number of tasks of each target personnel and the corresponding task allocation amount; based on each task difference, determine a plurality of task personnel to be added and a plurality of task personnel to be reduced among the target personnel; according to the preset task allocation rules, allocate the excess tasks of each task personnel to be reduced to each task personnel to be added.
[0080] On the basis of the above embodiment, the task allocation module is also used to determine the redundant tasks of each task personnel to be reduced based on the task difference of each task personnel to be reduced; traverse the task differences of each task personnel to be added and each task personnel to be reduced, and take the task personnel to be added and the task personnel to be reduced with the smallest deviation between the task differences as a task allocation group to obtain multiple task allocation groups; in each task allocation group, the redundant tasks of the task personnel to be reduced are allocated to the task personnel to be added.
[0081] It should be noted that: when the device provided in the above embodiment realizes its function, only the division of the above functional modules is used as an example. In actual application, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. In addition, the device and method embodiments provided in the above embodiment belong to the same concept, and the specific implementation process is detailed in the method embodiment, which will not be repeated here.
[0082] The present application also discloses an electronic device. Figure 3 , Figure 3 The electronic device 300 may include: at least one processor 301 , at least one network interface 304 , a user interface 303 , a memory 305 , and at least one communication bus 302 .
[0083] The communication bus 302 is used to realize the connection and communication between these components.
[0084] The user interface 303 may include a display interface and a camera interface. Optionally, the user interface 303 may also include a standard wired interface and a wireless interface.
[0085] The network interface 304 may optionally include a standard wired interface or a wireless interface (such as a WI-FI interface).
[0086] Among them, the processor 301 may include one or more processing cores. The processor 301 uses various interfaces and lines to connect various parts in the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory 305, and calling data stored in the memory 305. Optionally, the processor 301 can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field-Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor 301 can integrate one or a combination of a central processing unit (Central Processing Unit, CPU), a graphics processing unit (Graphics Processing Unit, GPU) and a modem. Among them, the CPU mainly processes the operating system, user interface diagrams and applications, etc.; the GPU is responsible for rendering and drawing the content to be displayed on the display screen; the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor 301, and it can be implemented separately through a chip.
[0087] Among them, the memory 305 may include a random access memory (Random Access Memory, RAM) and may also include a read-only memory (Read-Only Memory). Optionally, the memory 305 includes a non-transitory computer-readable storage medium. The memory 305 can be used to store instructions, programs, codes, code sets or instruction sets. The memory 305 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. The memory 305 may optionally also be at least one storage device located away from the aforementioned processor 301. Refer to Figure 3 The memory 305 as a computer storage medium may include an operating system, a network communication module, a user interface module, and an application program for an internal control method of a drawing review center.
[0088] exist Figure 3 In the electronic device 300 shown, the user interface 303 is mainly used to provide an input interface for the user and obtain the data input by the user; and the processor 301 can be used to call the application program storing a method for internal control of the drawing review center in the memory 305. When executed by one or more processors 301, the electronic device 300 executes one or more methods in the above-mentioned embodiments. It should be noted that for the aforementioned method embodiments, for the sake of simple description, they are all expressed as a series of action combinations, but those skilled in the art should know that the present application is not limited to the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required for the present application.
[0089] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0090] In the several embodiments provided in this application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are only schematic, such as the division of units, which is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some service interfaces, and the indirect coupling or communication connection of devices or units can be electrical or other forms.
[0091] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0092] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0093] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to execute all or part of the steps of the various embodiments of the present application. The aforementioned memory includes: various media that can store program codes, such as USB flash drives, mobile hard drives, magnetic disks or optical disks.
[0094] The above are only exemplary embodiments of the present disclosure and cannot be used to limit the scope of the present disclosure. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the disclosure of the specification and the truth of practice, those skilled in the art will easily think of other embodiments of the present disclosure.
[0095] This application is intended to cover any variation, use or adaptation of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the art not recorded in the present disclosure. The description and examples are to be regarded as exemplary only.
Claims
1. A method for internal control of a drawing review center, characterized in that: include: Acquire the current number of tasks and task types of multiple reviewers in the review center, and determine the review load value of each reviewer based on the number of tasks and the task type; Screening out target personnel whose drawing review load values exceed the standard drawing review load value range from among the drawing review personnel; Obtaining the number of drawings reviewed by each target person within a preset period, and determining the drawing review efficiency of each target person based on the number of drawings reviewed; Determine the task allocation of each target person based on the review efficiency and review load value of each target person and the benchmark review quantity of the review center; Based on the assigned amount of each task, the current number of tasks for each target person is adjusted.
2. The internal control method of the drawing review center according to claim 1 is characterized in that: The determining of the review load value of each reviewer based on the task quantity and the task type includes: Obtaining a preset task type weight table, wherein the task type weight table includes weight coefficients corresponding to different task types; Based on the task type weight table, determine the weight coefficient corresponding to each type of drawing review task currently assigned to each of the drawing reviewers; For each of the reviewers, the weight coefficient corresponding to each type of review task is multiplied by the number of the corresponding type of review tasks in the number of tasks to obtain the review load value of the reviewer.
3. The internal control method of the drawing review center according to claim 1 is characterized in that: Determining the drawing review efficiency of each target person based on the number of drawings reviewed includes: Determine the number of works that failed the review among the number of reviews mentioned above; Determine the actual number of drawings reviewed by each target person based on the number of drawings reviewed and the number of work that failed the drawings reviewed; Obtaining the actual working hours of each target person in the preset period; For each of the target personnel, the actual number of drawing reviews is divided by the corresponding actual working hours to obtain the drawing review efficiency of the target personnel.
4. The internal control method of the drawing review center according to claim 1 is characterized in that: The step of determining the task allocation amount for each target person in combination with the review efficiency and review load value of each target person and the benchmark review quantity of the review center includes: The drawing review efficiency of each target person is summed up to obtain the total drawing review efficiency; Divide the drawing review efficiency of each target person by the total drawing review efficiency to obtain the efficiency weight of each target person; Multiplying the efficiency weight of each target person by the benchmark drawing review quantity to obtain the initial task allocation of each target person; For each of the target personnel, the initial task allocation amount is adjusted based on the drawing review load value to obtain the task allocation amount of the target personnel.
5. The internal control method of the drawing review center according to claim 4 is characterized in that: The adjusting the initial task allocation based on the drawing review load value to obtain the task allocation of the target personnel includes: Based on the drawing review load value, determining a corresponding task compensation amount in a database; Determining whether the initial task allocation amount is greater than or equal to a preset standard task allocation amount; If the initial task allocation is greater than or equal to the preset standard task allocation, the task compensation amount is subtracted from the initial task allocation to obtain the task allocation of the target person; If the initial task allocation amount is less than the preset standard task allocation amount, the initial task allocation amount is added to the task compensation amount to obtain the task allocation amount of the target person.
6. The internal control method of the drawing review center according to claim 1, characterized in that: The step of allocating the current number of tasks for each target person based on the assigned amount of each task includes: Calculate the task difference between the current number of tasks of each target person and the corresponding task allocation; Based on each of the task differences, determining a plurality of personnel to be added and a plurality of personnel to be reduced from the target personnel; According to the preset task allocation rules, the redundant tasks of each of the task personnel to be reduced are allocated to each of the task personnel to be added.
7. The internal control method of the drawing review center according to claim 6, characterized in that: The step of allocating the redundant tasks of the personnel to be reduced to the personnel to be increased according to the preset task allocation rules includes: Determining redundant tasks of each of the personnel whose tasks are to be reduced based on the task differences of each of the personnel whose tasks are to be reduced; Traversing the task differences of the personnel to be added and the personnel to be reduced, taking the personnel to be added and the personnel to be reduced with the smallest deviation between the task differences as a task allocation group, and obtaining a plurality of task allocation groups; In each of the task allocation groups, the redundant tasks of the personnel to be reduced are allocated to the personnel to be added.
8. An internal control system of a drawing review center, characterized in that: The system comprises: The task information acquisition module is used to obtain the current task quantity and task type of multiple reviewers in the review center, and determine the review load value of each reviewer based on the task quantity and task type; A target personnel determination module is used to screen out target personnel whose drawing review load value exceeds the standard drawing review load value range from among the drawing review personnel; The task allocation amount determination module is used to obtain the number of drawings reviewed by each target person within a preset period, and determine the drawing review efficiency of each target person based on the number of drawings reviewed; and determine the task allocation amount of each target person in combination with the drawing review efficiency and drawing review load value of each target person and the benchmark drawing review number of the drawing review center; The task allocation module is used to allocate the current task quantity of each target person based on the task allocation quantity.
9. An electronic device, characterized in that: The device comprises a processor, a memory, a user interface and a network interface, wherein the memory is used to store instructions, the user interface and the network interface are used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes the internal control method of the drawing review center as described in any one of claims 1 to 7.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores instructions, and when the instructions are executed, the internal control method of the drawing review center according to any one of claims 1 to 7 is executed.