Equipment maintenance method, system and equipment based on Bayesian network and knowledge graph
Through Bayesian network and knowledge graph technology, a maintenance operation map database is established, the condition probability is calculated, and the optimization of maintenance processes is recommended, which solves the problems of low efficiency and quality in equipment maintenance, and realizes the recommendation and efficiency improvement of intelligent maintenance processes.
Patent Information
- Application Number
- CN202310629112.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-30
- Publication Date
- 2024-12-03
AI Technical Summary
During the equipment maintenance process, traditional methods rely on manual experience and intuition, resulting in inefficiency and low quality, and ignore the value of standard documents for maintenance operations, resulting in a large number of repetitive operations during the maintenance process, reducing the quality of maintenance and labor efficiency.
Using Bayesian network and knowledge graph methods, extract information through historical maintenance operation standards, establish a maintenance operation graph database, calculate the conditional probability of the graph nodes, form a Bayesian network model, recommend an optimized maintenance operation process, and reduce repetition operate.
It improves the efficiency and quality of maintenance operations, shortens maintenance time, avoids economic losses caused by failures, and realizes intelligent optimization and recommendation of the maintenance process.
Smart Images

Figure CN119067628A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of equipment maintenance, and in particular to an equipment maintenance method, system and equipment based on Bayesian network and knowledge graph. Background Art
[0002] In industrial production, equipment failures require corresponding repair and maintenance. Traditionally, maintenance solutions are determined based on human experience and intuition, but this approach is not only inefficient but also prone to errors. With the continuous development of computer technology and information processing technology, people have begun to try to use automation and intelligent technology to improve maintenance efficiency and quality.
[0003] At present, there have been many research results in the field of intelligent maintenance. For example, fault diagnosis and fault prediction technologies have been widely used in the fields of machine learning, pattern recognition, and data mining. However, these methods lack structured descriptions and detailed grasp of maintenance operations, and also ignore the value of standard maintenance operation documents in the early stage.
[0004] Maintenance work is an important part of the whole process management of equipment maintenance, and is also the main content of production technology management. It plays a vital role in improving the level of equipment maintenance management. The maintenance work refers to the maintenance work standards, including standard basic dictionary management, standard process management, operation management, etc., and also refines and quantifies the operation process in the form of data or diagrams.
[0005] Due to ignoring the value of the previous maintenance work standard documents, each maintenance project or no matter when and who performs the work, needs to be maintained according to the maintenance work process, which includes a large number of repetitive operations, resulting in low maintenance quality and manual labor efficiency.
[0006] Therefore, the present invention aims to provide a maintenance operation process recommendation method and system to solve the above-mentioned problems. Summary of the invention
[0007] The purpose of this application is to provide an equipment maintenance method, system and equipment based on Bayesian network and knowledge graph, which is used to solve the problem in the prior art that the maintenance operation process contains a large number of repetitive operations during maintenance, resulting in low maintenance quality and manual labor efficiency.
[0008] In the first aspect, the present application provides an equipment maintenance method based on a Bayesian network and a knowledge graph, the method comprising: extracting information using historical maintenance operation standards, establishing a maintenance operation graph database with equipment as the knowledge graph entity; performing data statistics on each of the maintenance operation graphs to obtain graph nodes with probabilities; calculating the conditional probabilities of the graph nodes, and linking them to form a Bayesian network model; collecting associated equipment corresponding to fault information, and querying the associated equipment corresponding to the fault information based on the Bayesian network model to obtain maintenance operation process recommendations.
[0009] In an implementation of the first aspect, the data statistics of the maintenance operation map are performed to obtain graph nodes with probability, including: based on the maintenance operation map database and historical maintenance history data, designing and establishing a data structure of each map node and directed edge; using the data structure to perform data statistics on the maintenance operation map in the maintenance operation map database to obtain graph nodes with probability.
[0010] Furthermore, the data structure includes: actual maintenance time, unified component number, used tools, material number and personnel code.
[0011] In an implementation of the first aspect, the conditional probability of each of the graph nodes is calculated and linked to form a Bayesian network model, including: setting the order of conditional probabilities according to the work hours and processes of the maintenance work standards and the cause-and-effect relationship; calculating the conditional probability of each of the graph nodes; and linking the conditional probabilities of each of the graph nodes to form a Bayesian network model.
[0012] In an implementation of the first aspect, after the Bayesian network model is formed, the method further includes: adjusting and correcting the link relationship and conditional probability distribution in the Bayesian network model based on experience values.
[0013] In an implementation of the first aspect, the historical maintenance work standards include: required tools, material numbers, personnel codes, and work hours and processes.
[0014] In an implementation manner of the first aspect, the associated device corresponding to the fault information includes: an associated device name, model, and parameters.
[0015] In an implementation of the first aspect, the method further includes: if the fault information is not found, adopting a general maintenance operation process and storing the fault information.
[0016] In the second aspect, the present application provides an equipment maintenance system based on a Bayesian network and a knowledge graph, the system comprising: a database module, a data processing module, a model building module and a query module; the database module is used to extract information using historical maintenance operation standards, and establish a maintenance operation graph database with equipment as the knowledge graph entity; the data processing module is used to perform data statistics on the maintenance operation graph to obtain graph nodes with probabilities; the model building module is used to calculate the conditional probability of the graph nodes, and link them to form a Bayesian network model with conditional probabilities; the query module is used to collect associated equipment corresponding to the fault information, and query the associated equipment corresponding to the fault information based on the Bayesian network model to obtain maintenance operation process recommendations.
[0017] In a third aspect, the present application provides an electronic device, comprising a processor and a memory; the memory is used to store a computer program; the processor is used to execute the computer program stored in the memory, so that the electronic device performs the equipment maintenance method based on the Bayesian network and knowledge graph as described in any one of the first aspects of the present application.
[0018] As described above, the equipment maintenance method, system and equipment based on Bayesian network and knowledge graph described in this application have the following beneficial effects:
[0019] First, in this application, the combination of Bayesian network and knowledge graph can realize process optimization and intelligent recommendation of maintenance operations, and improve the timeliness of maintenance operations based on diagnosis of historical maintenance data sets;
[0020] Second, in the actual maintenance production process, it can use the historical equipment maintenance history and maintenance operation standards to form a graphical mapping relationship, and at the same time recommend related operation methods based on the probability relationship formed in the knowledge base during the maintenance operation;
[0021] Third, it can improve maintenance efficiency, shorten maintenance time, and avoid economic losses caused by serious failures. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 Shown is a schematic diagram of a scene of an electronic device in an embodiment of the present application.
[0023] Figure 2 Shown is a schematic diagram of the equipment maintenance method based on Bayesian network and knowledge graph described in an embodiment of the present application.
[0024] Figure 3 Shown is a schematic diagram of the equipment maintenance method based on Bayesian network and knowledge graph described in an embodiment of the present application.
[0025] Figure 4Shown is a schematic diagram of the equipment maintenance method based on Bayesian network and knowledge graph described in an embodiment of the present application.
[0026] Figure 5 Shown is a structural schematic diagram of the equipment maintenance system based on Bayesian network and knowledge graph described in an embodiment of the present application.
[0027] Figure 6 Shown is a schematic diagram of the structure of an electronic device described in an embodiment of the present application.
[0028] Component number description
[0029] 11. Cell Phone
[0030] 12 Tablet
[0031] 13 Laptop
[0032] 100 Equipment maintenance system based on Bayesian network and knowledge graph
[0033] 101 Database Module
[0034] 102 Data processing module
[0035] 103 Model Building Module
[0036] 104 Query Module
[0037] 105 Storage Module
[0038] 61 processing units
[0039] 62 Memory
[0040] 621 Random Access Memory
[0041] 622 Cache memory
[0042] 623 Storage System
[0043] 624 Programs / Utilities
[0044] 6241 Program Module
[0045] 63 Bus
[0046] 64 Input / Output Interfaces
[0047] 651 Network Adapter
[0048] Steps S1 to S4
[0049] Steps S21 to S22
[0050] Steps S31 to S33 DETAILED DESCRIPTION
[0051] The following describes the embodiments of the present application through specific examples, and those skilled in the art can easily understand other advantages and effects of the present application from the contents disclosed in this specification. The present application can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present application. It should be noted that the following embodiments and features in the embodiments can be combined with each other without conflict.
[0052] It should be noted that the illustrations provided in the following embodiments are only schematic illustrations of the basic concept of the present application, and thus the drawings only show components related to the present application rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed at will, and the component layout may also be more complicated.
[0053] The following embodiments of the present application provide an equipment maintenance method based on Bayesian network and knowledge graph, which can be applied to Figure 1 The electronic device described in this application may include a mobile phone 11 with wireless charging function, a tablet computer 12, a laptop computer 13, a wearable device, a vehicle-mounted device, an augmented reality (AR) / virtual reality (VR) device, an ultra-mobile personal computer (UMPC), a netbook, a personal digital assistant (PDA), etc. The embodiments of this application do not impose any restrictions on the specific types of electronic devices.
[0054] For example, the electronic device may be a station (STAION, ST) in a WLAN with a wireless charging function, a cellular phone, a cordless phone, a Session Initiation Protocol (SIP) phone, a Wireless Local Loop (WLL) station, a Personal Digital Assistant (PDA) device, a handheld device with a wireless charging function, a computing device or other processing device, a computer, a laptop computer, a handheld communication device, a handheld computing device, and / or other devices for communicating on a wireless system and a next generation communication system, such as a mobile terminal in a 5G network, a mobile terminal in a future evolved Public Land Mobile Network (PLMN), or a mobile terminal in a future evolved Non-terrestrial Network (NTN).
[0055] For example, the electronic device can communicate with the network and other devices through wireless communication. The above wireless communication can use any communication standard or protocol, including but not limited to Global System of Mobile communication (GSM), General Packet Radio Service (GPRS), Code Division Multiple Access (CDMA), Wideband Code Division Multiple Access (WCDMA), Long Term Evolution (LTE), email, Short Messaging Service (SMS), BT, GNSS, WLAN, NFC, FM, and / or IR technology. GNSS can include Global Positioning System (GPS), Global Navigation Satellite System (GLONASS), BeiDou navigation Satellite System (BDS), Quasi-Zenith Satellite System (QZSS) and / or Satellite Based Augmentation Systems (SBAS).
[0056] Below, the embodiments of the present application are described in conjunction with the drawings in the embodiments of the present application, so that those skilled in the art can understand the equipment maintenance method, system and equipment based on the Bayesian network and knowledge graph of the present embodiment without creative work.
[0057] In one embodiment, the present application provides an equipment maintenance method based on Bayesian network and knowledge graph, such as Figure 2 As shown, the equipment maintenance method based on Bayesian network and knowledge graph of the present application includes:
[0058] S1. Use historical maintenance operation standards to extract information and establish a maintenance operation graph database with equipment as the knowledge graph entity.
[0059] Specifically, historical maintenance work standards include: required tools, material numbers, personnel codes and work hours and processes.
[0060] Specifically, collect historical maintenance operation standard data, integrate the data into a standard format, and remove erroneous information to ensure that the information in the database is accurate and reliable; define equipment as the ontology of the knowledge graph, convert the collected maintenance operation standard data into entities and attributes in the knowledge graph ontology, and define the relationship between maintenance operation standard data and equipment to form a complete knowledge graph infrastructure; for equipment maintenance operations, it is necessary to extract the name, model and parameter information of the equipment and map it to the corresponding knowledge graph ontology entity; according to the different categories of equipment, store the extracted information on the corresponding nodes, and use links to combine them into a maintenance operation graph database.
[0061] It should be noted that the maintenance operation graph database can perform maintenance operation process reasoning and relationship query based on unified semantics.
[0062] It should be noted that with the passage of time and changes in actual operations, maintenance work standards and implementation methods may change, and the information in the database needs to be updated and optimized regularly.
[0063] S2. Perform data statistics on the maintenance operation graph to obtain graph nodes with probabilities.
[0064] In one embodiment, performing data statistics on the maintenance operation graph to obtain graph nodes with probabilities includes:
[0065] S21. Based on the maintenance operation graph database and the historical maintenance record data, the data structure of each graph node and directed edge is designed and established.
[0066] Specifically, the data structure of the directed edge includes: actual maintenance time, unified part number, used tool, material number and personnel code.
[0067] Specifically, based on the entities and attributes extracted from the maintenance operation graph database, determine the nodes that need to be represented in the graph. For example, each maintenance operation process can be represented as a node, and the name, description, time consumption and other attributes of the node can be marked; in the maintenance operation graph database, each maintenance operation process will involve multiple operation steps and material usage information. Therefore, it is necessary to determine the dependencies between different nodes and represent them as directed edges. For example, if a maintenance process requires the use of a certain equipment or tool, the maintenance process node can point to the corresponding equipment or tool node.
[0068] It should be noted that two data structures are usually used to implement this: an adjacency list or an adjacency matrix. An adjacency list connects the edges adjacent to each node to form a linked list, and uses an array to store the entire graph; an adjacency matrix uses a two-dimensional array to store the relationship between all nodes in the entire graph.
[0069] S22. Perform data statistics on the maintenance operation graph in the maintenance operation graph database using the data structure to obtain graph nodes with probabilities.
[0070] Specifically, statistics are collected on the historical maintenance history data in the maintenance operation atlas database, and probability values are assigned to the statistical results according to the data structure to obtain atlas nodes with probabilities.
[0071] S3. Calculate the conditional probability of each graph node and link them to form a Bayesian network model.
[0072] In one embodiment, calculating the conditional probability of each graph node and linking the conditional probabilities to form a Bayesian network model includes:
[0073] S31. According to the standard working hours of maintenance work, the order of conditional probabilities is set based on cause and effect relationships.
[0074] S32. Calculate the conditional probability of each graph node.
[0075] Specifically, different fault types and maintenance operations are represented by graph nodes, and the causal relationship between them is represented. For example, for a piece of equipment, operations such as part replacement, cleaning, and calibration can be used as nodes, and edges are established between them to represent the dependency relationship between them; for each node, the conditional probability of each graph node is calculated by counting the number of times the given node and the target node appear at the same time in the historical data.
[0076] S33. Link the conditional probabilities of each graph node to form a Bayesian network model.
[0077] Specifically, a link based on conditional probability is established between each graph node, and a link based on conditional probability is established between each node as the starting point and the end point, and the obtained links are combined into a Bayesian network model. The Bayesian network model can be used to deduce and predict based on prior knowledge and new data; when new equipment maintenance history data arrives, the model can be used to predict the next possible fault and take necessary measures to avoid the fault.
[0078] In one embodiment, after the Bayesian network model is formed, the method further includes: adjusting and correcting the link relationship and conditional probability distribution in the Bayesian network model based on the experience value.
[0079] Specifically, after the Bayesian network model is formed, the probability distribution of the link relationship in the Bayesian network is adjusted and corrected through expert experience, including network relationship supplementation and subjective probability distribution setting.
[0080] S4. Collect the associated equipment corresponding to the fault information, and query the associated equipment corresponding to the fault information based on the Bayesian network model to obtain a maintenance operation process recommendation.
[0081] Specifically, when the maintenance task begins, fault information is collected, and the associated equipment corresponding to the fault information is obtained. The operating time, personnel, materials, tools and other restrictive conditions of the associated equipment are matched to the graph for relationship query. The maintenance graph database queries and outputs the path that maximizes the probability of meeting the query conditions based on the probability of each node in the previous production, and obtains maintenance operation process recommendations.
[0082] Specifically, the fault information is pushed to the system front desk, and the results of the fault diagnosis are saved in the historical data after the staff reviews it. The newly added historical data can be used for the next training of the Bayesian network model.
[0083] In one embodiment, if no fault information is found, a general maintenance operation process is used and the fault information is stored.
[0084] Specifically, according to the query corresponding to the maintenance method based on graph reasoning, if there is no maintenance method record for the fault temporarily, a general maintenance method can be used.
[0085] The equipment maintenance method based on Bayesian network and knowledge graph described in the present application is not limited to the execution order of the steps listed in the above embodiments. All solutions implemented by adding, reducing or replacing steps in the prior art based on the principles of the present invention are included in the protection scope of the present invention.
[0086] In one embodiment, the present application provides an equipment maintenance system based on a Bayesian network and a knowledge graph, such as Figure 4As shown, the equipment maintenance system 100 based on the Bayesian network and the knowledge graph includes: a database module 101, a data processing module 102, a model building module 103 and a query module 104.
[0087] The database module 101 is used to extract information using historical maintenance operation standards and establish a maintenance operation graph database with equipment as the knowledge graph entity.
[0088] The data processing module 102 is used to perform data statistics on the maintenance operation graph to obtain graph nodes with probabilities.
[0089] The model building module 103 is used to calculate the conditional probabilities of the graph nodes and link them to form a Bayesian network model.
[0090] The query module 104 is used to collect the associated devices corresponding to the fault information, and query the associated devices corresponding to the fault information based on the Bayesian network model to obtain maintenance operation process recommendations.
[0091] In one embodiment, the equipment maintenance system 100 based on the Bayesian network and the knowledge graph further includes a storage module 105 .
[0092] The storage module 105 is used to store the fault information in the maintenance operation map database.
[0093] Specifically, the storage module 105 is used to push the fault information to the system front desk, and save the result of the fault diagnosis to the historical data after the staff reviews it. The newly added historical data can be used for the next training of the Bayesian network model.
[0094] It should be noted that regardless of whether the fault information is found in the maintenance map database, the fault information needs to be pushed to the system front desk and stored.
[0095] It should be noted that it should be understood that the division of the above modules is only a division of logical functions. In actual implementation, they can be fully or partially integrated into one physical entity, or they can be physically separated. And these modules can all be implemented in the form of software called by processing elements; they can also be all implemented in the form of hardware; some modules can also be implemented in the form of software called by processing elements, and some modules can be implemented in the form of hardware. For example, the x module can be a separately established processing element, or it can be integrated in a chip of the above-mentioned device for implementation. In addition, it can also be stored in the memory of the above-mentioned device in the form of program code, and called and executed by a processing element of the above-mentioned device. The implementation of other modules is similar. In addition, these modules can be fully or partially integrated together, or they can be implemented independently. The processing element described here can be an integrated circuit with signal processing capabilities. In the implementation process, each step of the above method or each module above can be completed by an integrated logic circuit of hardware in the processor element or instructions in the form of software.
[0096] For example, the above modules may be one or more integrated circuits configured to implement the above methods, such as one or more application specific integrated circuits (ASIC), or one or more microprocessors (DSP), or one or more field programmable gate arrays (FPGA). For another example, when a module is implemented in the form of a processing element scheduling program code, the processing element may be a general-purpose processor, such as a central processing unit (CPU) or other processor that can call program code. For another example, these modules may be integrated together and implemented in the form of a system-on-a-chip (SOC).
[0097] In one embodiment, the embodiment of the present application also provides a computer-readable storage medium. A person of ordinary skill in the art can understand that all or part of the steps in the method for implementing the above embodiment can be completed by instructing the processor through a program, and the program can be stored in a computer-readable storage medium, and the storage medium is a non-transitory medium, such as a random access memory, a read-only memory, a flash memory, a hard disk, a solid-state hard disk, a magnetic tape, a floppy disk, an optical disc, and any combination thereof. The above storage medium can be any available medium that can be accessed by a computer or a data storage device such as a server or a data center that includes one or more available media integrated. The available medium can be a magnetic medium (e.g., a floppy disk, a hard disk, a tape), an optical medium (e.g., a digital video disc (DVD)), or a semiconductor medium (e.g., a solid-state disk (SSD)), etc.
[0098] In one embodiment, the present application also provides an electronic device, including: a processor and a memory.
[0099] Specifically, the memory is used to store computer programs; the memory includes: ROM, RAM, disk, USB flash drive, memory card or CD and other media that can store program codes.
[0100] The processor is used to execute the computer program stored in the memory so that the electronic device executes the above-mentioned equipment maintenance method based on the Bayesian network and knowledge graph.
[0101] Preferably, the processor can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components.
[0102] like Figure 6As shown, the electronic device of the present application is in the form of a general computing device. The components of the electronic device may include but are not limited to: one or more processors or processing units 61, a memory 62, and a bus 63 connecting different system components (including the memory 62 and the processing unit 61).
[0103] Bus 63 represents one or more of several types of bus structures, including a memory bus or memory controller, a peripheral bus, an accelerated graphics port, a processor or a local bus using any of a variety of bus architectures. These architectures include, by way of example, but are not limited to, an Industry Standard Architecture (ISA) bus, a Micro Channel Architecture (MAC) bus, an Enhanced ISA bus, a Video Electronics Standards Association (VESA) local bus, and a Peripheral Component Interconnect (PCI) bus.
[0104] Electronic devices typically include a variety of computer system readable media. These media can be any available media that can be accessed by the electronic device, including volatile and non-volatile media, removable and non-removable media.
[0105] The memory 62 may include computer system readable media in the form of volatile memory, such as random access memory (RAM) 621 and / or cache memory 622. The electronic device may further include other removable / non-removable, volatile / non-volatile computer system storage media. By way of example only, the storage system 623 may be used to read and write non-removable, non-volatile magnetic media ( Figure 6 not shown, usually called a "hard drive"). Although Figure 6 Not shown, a disk drive for reading and writing to a removable non-volatile disk (e.g., a "floppy disk"), and an optical disk drive for reading and writing to a removable non-volatile optical disk (e.g., a CD-ROM, a DVD-ROM, or other optical media) may be provided. In these cases, each drive may be connected to the bus 63 via one or more data medium interfaces. The memory 62 may include at least one program product having a set (e.g., at least one) of program modules that are configured to perform the functions of the various embodiments of the present invention.
[0106] A program / utility 624 having a set (at least one) of program modules 6241 may be stored, for example, in the memory 62, such program modules 6241 including but not limited to an operating system, one or more application programs, other program modules, and program data, each of which or some combination may include an implementation of a network environment. The program modules 6241 generally perform the functions and / or methods of the embodiments described herein.
[0107] The electronic device may also communicate with one or more external devices (e.g., keyboards, pointing devices, displays, etc.), one or more devices that enable a user to interact with the electronic device, and / or any device that enables the electronic device to communicate with one or more other computing devices (e.g., network cards, modems, etc.). Such communication may be performed via input / output (I / O) interface 64. Furthermore, the electronic device may also communicate with one or more networks (e.g., local area networks (LANs), wide area networks (WANs), and / or public networks, such as the Internet) via network adapter 65. Figure 6 As shown, the network adapter 65 communicates with other modules of the electronic device via the bus 63. It should be understood that, although not shown in the figure, other hardware and / or software modules can be used in conjunction with the electronic device, including but not limited to: microcode, device drivers, redundant processing units, external disk drive arrays, RAID systems, tape drives, and data backup storage systems.
[0108] The descriptions of the processes or structures corresponding to the above-mentioned figures have different emphases. For parts that are not described in detail in a certain process or structure, please refer to the relevant descriptions of other processes or structures.
[0109] In summary, first, in this application, the combination of Bayesian network and knowledge graph can realize the process optimization and intelligent recommendation of maintenance operations, and improve the timeliness of maintenance operations based on the diagnosis of historical maintenance data sets; second, in the face of actual maintenance production processes, it can use historical equipment maintenance records and maintenance operation standards to form a graphical mapping relationship, and at the same time, during the maintenance operation process, it can recommend related operation methods based on the probability relationship formed by the knowledge base; third, it can improve the efficiency of maintenance work, shorten the maintenance time, and avoid economic losses caused by serious failures. Therefore, this application effectively overcomes the various shortcomings of the prior art and has a high industrial utilization value.
[0110] The above embodiments are merely illustrative of the principles and effects of the present application and are not intended to limit the present application. Anyone familiar with the technology may modify or change the above embodiments without violating the spirit and scope of the present application. Therefore, all equivalent modifications or changes made by a person of ordinary skill in the art without departing from the spirit and technical ideas disclosed in the present application shall still be covered by the claims of the present application.
Claims
1. An equipment maintenance method based on Bayesian network and knowledge graph, It is characterized in that The method comprises: Use historical maintenance operation standards to extract information and establish a maintenance operation graph database with equipment as the knowledge graph ontology; Performing data statistics on the maintenance operation graph to obtain graph nodes with probabilities; Calculating the conditional probability of each of the graph nodes, and linking them to form a Bayesian network model; The associated devices corresponding to the fault information are collected, and the associated devices corresponding to the fault information are queried based on the Bayesian network model to obtain a maintenance operation process recommendation.
2. The equipment maintenance method based on Bayesian network and knowledge graph according to claim 1, It is characterized in that The performing of data statistics on the maintenance operation graph to obtain graph nodes with probabilities includes: Based on the maintenance operation graph database and historical maintenance history data, design and establish the data structure of each graph node and directed edge; The data structure is used to perform data statistics on the maintenance operation graph in the maintenance operation graph database to obtain graph nodes with probabilities.
3. The equipment maintenance method based on Bayesian network and knowledge graph according to claim 2, It is characterized in that The data structure includes: actual maintenance time, unified component number, used tools, material number and personnel code.
4. The equipment maintenance method based on Bayesian network and knowledge graph according to claim 1, It is characterized in that The calculating of the conditional probability of each of the graph nodes and linking the conditional probabilities to form a Bayesian network model includes: According to the standard working hours of maintenance work, the order of conditional probability is set based on cause and effect relationship; Calculating the conditional probability of each of the graph nodes; The conditional probabilities of the graph nodes are linked to form a Bayesian network model.
5. The equipment maintenance method based on Bayesian network and knowledge graph according to claim 1, It is characterized in that After the Bayesian network model is formed, the method further includes: adjusting and correcting the link relationship and conditional probability distribution in the Bayesian network model based on the experience value.
6. The equipment maintenance method based on Bayesian network and knowledge graph according to claim 1, It is characterized in that The historical maintenance work standards include: required tools, material numbers, personnel codes and working hours and processes.
7. The equipment maintenance method based on Bayesian network and knowledge graph according to claim 1, It is characterized in that The associated devices corresponding to the fault information include: associated device name, model and parameters.
8. The equipment maintenance method based on Bayesian network and knowledge graph according to claim 1, It is characterized in that The method further includes: if the fault information is not found, adopting a general maintenance operation process and storing the fault information.
9. An equipment maintenance system based on Bayesian network and knowledge graph, It is characterized in that The system includes: a database module, a data processing module, a model building module and a query module; The database module is used to extract information using historical maintenance operation standards and establish a maintenance operation graph database with equipment as the knowledge graph entity; The data processing module is used to perform data statistics on each of the maintenance operation graphs to obtain graph nodes with probabilities; The model building module is used to calculate the conditional probabilities of the graph nodes and link them to form a Bayesian network model; The query module is used to collect associated equipment corresponding to the fault information, and query the associated equipment corresponding to the fault information based on the Bayesian network model to obtain a maintenance operation process recommendation.
10. An electronic device, It is characterized in that include: Processor and memory; The memory is used to store computer programs; The processor is used to execute the computer program stored in the memory so that the electronic device executes the equipment maintenance method based on the Bayesian network and knowledge graph as described in any one of claims 1 to 8.
Citation Information
Cited By
Building equipment fault rapid attribution and self-optimization method
CN121093778A
A method for rapid fault attribution and self-optimization of construction equipment
CN121093778B