Integrated erection construction method for auxiliary three walls of bridge floor

Simultaneous prefabrication of three auxiliary walls with the box beam in a factory addresses inefficiencies and safety risks, enhancing quality and reducing construction time by utilizing beam strength windows.

CN119083330APending Publication Date: 2024-12-06CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411500965.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-25
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The traditional construction sequence of three auxiliary walls on a high-speed railway prefabricated box girder deck is inefficient, with quality difficult to ensure, high safety risks, and prolonged construction periods, and it interferes with other projects.

Method used

The three auxiliary walls are prefabricated simultaneously with the box beam in a factory, with vertical wall A constructed in the beam-making area, the protective wall after prestressed steel strands tensioning is complete, and vertical wall B in the beam storage area, using standardized factory operations to ensure quality and efficiency.

Benefits of technology

This method significantly shortens construction time, enhances quality control, and avoids cross-project interference by utilizing the box beam's strength window, ensuring synchronized construction and improved safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083330A_ABST
    Figure CN119083330A_ABST
Patent Text Reader

Abstract

The invention discloses an integrated erection construction method for three auxiliary walls of a bridge floor, which comprises the following steps of: firstly, after concrete of a box girder body on a girder manufacturing pedestal in a girder manufacturing area is finally set, constructing a vertical wall A on the concrete box girder body which is finally set in the girder manufacturing area; then, in the beam storage area, after the prestressed steel beams of the box beams are finally tensioned, and the prestressed pipeline slurry of the box beams reaches the design strength, a protection wall is constructed on the box beams; and finally, in the beam storage area, after construction of the protection wall is completed, a vertical wall B is constructed on the box beam. According to the method, the auxiliary three walls of the bridge floor and the box girders are prefabricated synchronously in a girder factory, the window time of equal strength and girder storage of the box girders in the girder factory is fully utilized, the bridge construction period is effectively shortened, and factory prefabrication ensures the construction quality of the three walls.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of high-speed railway prefabricated box girder construction, in particular to an integrated erection construction method for three auxiliary walls of a bridge deck. Background Art

[0002] The three walls attached to the prefabricated box girder deck of high-speed railways include the protective wall, vertical wall A and vertical wall B. Vertical wall A is set close to the inner sides of the two longitudinal edges of the box girder deck, and vertical wall B is set between the protective wall and vertical wall A. The three walls are parallel to each other. The traditional construction sequence of the three walls is generally completed after the box girder is erected. The main defects are that the quality of the cast-in-place construction of the box girder deck is difficult to ensure, the safety risk of construction operations near the edge is high, the construction period is long, and there is cross-construction interference with the four-power and track plate projects. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide an integrated erection construction method for three auxiliary walls of a bridge deck. The three auxiliary walls of the bridge deck are prefabricated in a beam factory simultaneously with the box beam, making full use of the window time of the box beam in the beam factory when the strength is equal and the beam is stored, effectively saving the construction period of the bridge. In addition, factory prefabrication ensures the construction quality of the three walls.

[0004] The technical solution of the present invention is:

[0005] A method for erecting three walls attached to a bridge deck in an integrated manner, specifically comprising the following steps:

[0006] (1) After the box girder body concrete on the beam-making pedestal in the beam-making area is finally set, vertical wall A is constructed on the finally set concrete box girder body in the beam-making area;

[0007] (2) In the beam storage area, after the final tensioning of the prestressed steel strands of the box beam is completed and the prestressed pipe slurry of the box beam reaches the design strength, a protective wall is constructed on the box beam;

[0008] (3) In the beam storage area, after the construction of the protective wall is completed, the vertical wall B is constructed on the box beam.

[0009] The construction methods of the protective wall, vertical wall A and vertical wall B sequentially include measurement and layout, roughening of concrete at the bottom of the wall, reinforcement binding, formwork installation, concrete pouring, curing and inspection and acceptance.

[0010] When installing the formwork of the vertical wall A, first fix the bottom end of the outer formwork of the vertical wall A with the top end of the side formwork of the box beam flange plate by bolts. After the concrete of the box beam body is finally set, the embedded parts of the vertical wall A, the inner formwork of the vertical wall A, the vertical wall A tie rod between the inner and outer forms of the vertical wall A, the fracture steel plate and the end membrane of the vertical wall A are installed on the box beam surface in sequence. Finally, after fine-tuning the line type of the vertical wall A formwork, the concrete pouring construction of the vertical wall A is carried out. After the pouring is completed, it is cured until the age period ends, so that the vertical wall A is constructed synchronously with the box beam body in the beam making area.

[0011] The horizontal height of the top of the inner formwork of the vertical wall A is consistent with the horizontal height of the top of the vertical wall A. The top of the inner formwork of the vertical wall A is also connected to an inner heightening formwork. The bottom end of the inner heightening formwork is connected to the top of the inner formwork of the vertical wall A by bolts. The horizontal height of the top of the inner heightening formwork is consistent with the horizontal height of the top of the outer formwork of the vertical wall A. A row of vertical wall A size limiting beams evenly distributed along the extension direction of the vertical wall A are connected to the top of the outer formwork of the vertical wall A and the inner heightening formwork.

[0012] A row of embedded parts positioning boxes are arranged between the upper parts of the outer and inner forms of the vertical wall A, and a connecting positioning beam is welded to the top of the embedded parts positioning box. When the formwork of the vertical wall A is installed, the two ends of the connecting positioning beam extend to the top of the outer and inner forms of the vertical wall A respectively and are fixedly connected to the top of the outer and inner forms of the vertical wall A respectively by bolts, thereby correcting the distance between the inner and outer forms of the vertical wall A, thereby achieving the purpose of adjusting the linear shape of the vertical wall A formwork and reinforcing the formwork.

[0013] The steel cages of the protective wall, vertical wall A and vertical wall B are prefabricated in sections in a factory and then transported to the construction site for installation in sections.

[0014] When installing the template of the protective wall, first install the inner template of the protective wall on the beam surface of the box beam, connect a row of diagonal braces to the outer wall of the inner template of the protective wall, the top end of each diagonal brace is connected to the outer wall of the inner template, and the bottom end of each diagonal brace is connected to the beam surface of the box beam, then install the outer template of the protective wall, and then connect the lower part of the inner template of the protective wall and the outer template through a protective wall pull rod, and finally connect a row of protective wall size limiting beams evenly distributed along the extension direction of the protective wall to the top of the inner template and the outer template of the protective wall.

[0015] When installing the formwork of the vertical wall B, first install the inner formwork of the vertical wall B on the beam surface of the box beam, and at the same time connect the inner transverse horizontal brace between the outer wall of the inner formwork of the vertical wall B and the outer wall of the protective wall, and then install the outer formwork of the vertical wall B, and then connect the vertical wall B pull rod between the inner formwork of the vertical wall B and the middle part of the outer formwork, and connect the outer transverse horizontal brace between the outer wall of the outer formwork of the vertical wall B and the inner wall of the vertical wall A.

[0016] Pre-embedded water hole trapezoidal boxes are arranged between the lower parts of the inner and outer molds of the protective wall and between the lower parts of the inner and outer molds of the vertical wall B. When the templates of the protective wall and the vertical wall B are installed, the inner walls of the inner and outer molds of the protective wall and the inner walls of the inner and outer molds of the vertical wall B are close to the corresponding pre-embedded water hole trapezoidal boxes, so that the distance between the lower parts of the inner and outer molds of the protective wall and the vertical wall B is consistent with the length of the pre-embedded water hole trapezoidal boxes, thereby controlling the lower dimensions of the protective wall and the vertical wall B.

[0017] Advantages of the present invention:

[0018] (1) The present invention prefabricates the three walls attached to the bridge deck in the beam factory synchronously with the box beam, constructs the vertical wall A in the beam manufacturing area, and constructs the protective wall and the vertical wall B in the beam storage area. The construction of the three walls is carried out synchronously in the beam manufacturing area and the beam storage area. When the vertical wall A on a section of the box beam is constructed in the beam manufacturing area, the protective wall and the vertical wall B can be synchronously constructed on another section of the box beam where the vertical wall A has been installed in the beam storage area. The vertical wall A on multiple sections of the box beam can be synchronously constructed in the beam manufacturing area, and the protective wall and the vertical wall B on multiple sections of the box beam can be synchronously constructed in the beam storage area. This significantly shortens the prefabrication time in the beam factory compared to the post-casting time of on-site erection, improves the overall work efficiency, makes full use of the strength of the box beam in the beam factory, and avoids the influence of the cross construction with the bridge deck base plate in the later stage.

[0019] (2) The present invention constructs three walls in the beam factory, and the factory operation is carried out, the management is more standardized, the construction quality is easy to control, and the construction operation standard is higher than the construction standard at the bridge location, which greatly improves the construction quality of the three walls.

[0020] (3) In the present invention, after the final tensioning of the prestressed steel strands of the box girder is completed and the prestressed pipe slurry of the box girder reaches the designed strength, a protective wall is constructed on the box girder, and then a vertical wall B is constructed on the box girder, thereby effectively utilizing the window time of the beam storage and making the box girder meet the requirements of equal strength and maintenance. The box girder can be prefabricated synchronously with the box girder and transported to the site for erection of the box girder.

[0021] (4) The bottom end of the outer side formwork of the vertical wall A of the present invention is fixedly connected to the top end of the side formwork of the box beam flange plate by bolts to form a connecting (beam body) formwork, which can effectively control the casting quality of the outer side surface of the vertical wall A and improve construction efficiency.

[0022] (5) There is a height difference between the inner and outer molds of the vertical wall A of the present invention when it is designed, so an inner heightening mold is added to the upper part of the inner mold A of the vertical wall to eliminate the problem of the height difference of the mold.

[0023] (6) The present invention can quickly realize fine adjustment of the line type of the vertical wall A template by setting a pre-buried trapezoidal box; and can realize control of the bottom size of the protective wall and the vertical wall B by setting a pre-buried trapezoidal box for water holes. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1It is a flow chart of the present invention.

[0025] Figure 2 It is a structural diagram of the three walls attached to the bridge deck.

[0026] Figure 3 It is a schematic diagram of the template installation structure of the vertical wall A of the present invention.

[0027] Figure 4 It is a schematic diagram of the planar installation structure of the embedded part positioning box of the present invention.

[0028] Figure 5 It is a schematic diagram of the template installation structure of the protective wall and the vertical wall B of the present invention.

[0029] Figure 6 It is a schematic diagram of the installation structure of the trapezoidal box with pre-buried water holes between the vertical wall B templates of the present invention.

[0030] Figure markings: 01-vertical wall A, 02-protective wall, 03-vertical wall B, 04-box beam, 11-outer formwork of vertical wall A, 12-inner formwork of vertical wall A, 13-inner heightening formwork of vertical wall A, 14-pull rod of vertical wall A, 15-limiting beam of vertical wall A size, 16-embedded positioning box, 17-connecting positioning beam, 21-inner formwork of protective wall, 22-outer formwork of protective wall, 23-diagonal brace, 24-pull rod of protective wall, 25-limiting beam of protective wall size, 31-inner formwork of vertical wall B, 32-outer formwork of vertical wall B, 33-inner transverse horizontal brace, 34-pull rod of vertical wall B, 35-outer transverse horizontal brace, 36-embedded trapezoidal box of water hole, 41-flange plate side formwork of box beam. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0032] See Figure 1 and Figure 2 A method for erecting three walls attached to a bridge deck in an integrated manner, wherein the three walls attached to the bridge deck include a protective wall 02, a vertical wall A 01 and a vertical wall B 03, and specifically includes the following steps:

[0033] (1) After the box girder concrete on the beam-making pedestal in the beam-making area is finally set, vertical wall A 01 is constructed on the concrete box girder 04 beam body that has finally set in the beam-making area;

[0034] (2) In the beam storage area, after the final tensioning of the prestressed steel strands of the box beam 04 is completed and the prestressed pipe slurry of the box beam 04 reaches the design strength, the protective wall 02 is constructed on the box beam 04;

[0035] (3) In the beam storage area, after the construction of the protective wall is completed, the vertical wall B 03 is constructed on the box beam 04.

[0036] See Figure 3 and Figure 4 , the construction of the vertical wall A formwork is to first fix the bottom end of the vertical wall A 01 outer formwork 11 with the top of the box girder 04 flange plate side formwork 41 by bolts (the steel bars of the vertical wall A 01 are tied and formed synchronously with the steel cage of the box girder 04), and after the concrete of the box girder 04 beam body is finally set, the embedded parts of the vertical wall A are installed, and then the inner formwork 12 of the vertical wall A is installed. Since there is a height difference when the inner and outer formworks of the vertical wall A are designed, the inner heightening formwork 13 is connected to the top of the inner formwork 12 of the vertical wall A, and the horizontal height of the top of the inner formwork 12 of the vertical wall A is consistent with the horizontal height of the top of the vertical wall A 01, and the horizontal height of the top of the inner heightening formwork 13 is consistent with the horizontal height of the top of the outer formwork 11 of the vertical wall A. The middle parts of the outer formwork 11 and the inner formwork 12 of the vertical wall A are connected by the vertical wall A pull rod 14, and a plurality of vertical wall A-shaped plates are connected to the tops of the outer formwork 11 and the inner heightening formwork 13. A row of vertical wall A limit beams with a size of 15 are evenly distributed in the extension direction of 01; the vertical wall A 01 is a segment of two meters, so during construction, A 1cm thick fracture steel plate is set at the joint of each section of 01, and is connected to the outer membrane 11 and the inner membrane 12 through the template installation holes on the outer membrane 11 and the inner membrane 12 of the vertical wall A. The beam end of the vertical wall A is fixed with a pin in the form of a side package end. A row of embedded parts positioning boxes 16 are arranged between the upper part of the outer formwork 11 of the vertical wall A and the inner heightening template 13. A connecting positioning beam 17 is welded to the top of the embedded parts positioning box. When the template of the vertical wall A is installed, the two ends of the connecting positioning beam 17 extend to the top of the outer formwork 11 and the inner formwork 12 of the vertical wall A respectively, and are fixedly connected to the top of the outer formwork 11 of the vertical wall A and the top of the inner heightening template 13 by bolts respectively, so as to correct the distance between the inner and outer forms of the vertical wall A, so as to adjust the linear shape of the template of the vertical wall A and strengthen the template. Then, after the actual elevation is measured and qualified, the pouring construction of the vertical wall A 01 is carried out. After the pouring is completed, it is maintained until the end of the age, so as to realize the on-site vertical wall A 01Synchronous cycle construction from the beam body to the beam manufacturing area.

[0037] Among them, the steel cages of the protective wall 02, vertical wall A 01 and vertical wall B 03 are all prefabricated in sections in the factory, and then transported to the construction site for installation in sections.

[0038] The construction of the protective wall 02 is carried out after the final tensioning of the prestressed steel strands of the box girder 04 is completed and the prestressed pipe slurry of the box girder 04 reaches the design strength. The protective wall formwork points are laid out and the inner side formwork edge lines and chiseled edge lines of the protective wall are popped out with an ink fountain. After acceptance, the segmented prefabricated steel cage of the protective wall 02 is tied and formed, and installed with lines according to the segments.

[0039] See Figure 5 When installing the formwork of the protective wall 02, first install the inner formwork 21 of the protective wall on the beam surface of the box beam 04, connect a row of diagonal braces 23 to the outer wall of the inner formwork 21 of the protective wall, the top of each diagonal brace 23 is connected to the outer wall of the inner formwork 21, and the bottom of each diagonal brace 23 is connected to the beam surface of the box beam 04, then install the outer formwork 22 of the protective wall, and then connect the lower parts of the inner formwork 21 and the outer formwork 22 of the protective wall through the protective wall tie rod 24, and finally connect a row of protective wall size limiting beams 25 evenly distributed along the extension direction of the protective wall 02 to the top of the inner formwork 21 and the outer formwork 22 of the protective wall; the protective wall 02 is a segment of four meters, so during construction, a 1cm thick fracture steel plate is set at the joint of each segment of the protective wall 02, and is connected to the outer membrane 22 and the inner membrane 21 through the template installation holes on the outer membrane 22 and the inner membrane 21 of the protective wall. The protective wall 02 is connected with the membrane 21, and the beam end of the protective wall 02 is fixed with a pin in the form of a side package end. A pre-buried water hole trapezoidal box is arranged between the lower part of the inner mold 21 and the outer mold 22 of the protective wall, and the inner walls of the inner mold 21 and the outer mold 22 of the protective wall are close to the pre-buried water hole trapezoidal box, so that the distance between the lower parts of the inner and outer molds of the protective wall 02 is consistent with the length of the pre-buried water hole trapezoidal box, thereby controlling the lower size of the protective wall, and then the protective wall size limiting beam 25 and the fracture steel plate are used at the upper mouth of the inner and outer molds to fine-tune the structural size and line type of the protective wall. When the template of the entire protective wall 02 is connected and formed, the template line type is fine-tuned and the actual elevation is measured to be qualified, and then the concrete pouring construction of the protective wall 02 is carried out. After the pouring is completed, it is maintained until the end of the age period, so as to realize the cyclic continuous construction of the protective wall 02 in the beam storage area.

[0040] After the construction of protective wall 02 is completed and the formwork is removed, the construction of vertical wall B 03 will be carried out. First, the formwork points of vertical wall B 03 will be laid out and the inner formwork edge line and roughened edge line of vertical wall B 03 will be popped out with an ink fountain. After acceptance, the segmented assembled steel cage of vertical wall B 03 will be installed with lines according to the segments.

[0041] See Figure 5When installing the formwork of the vertical wall B 03, first install the inner formwork 31 of the vertical wall B on the beam surface of the box beam 04, and at the same time connect the inner horizontal support rod 33 between the outer wall of the inner formwork 31 of the vertical wall B and the outer wall of the protective wall 02, and then install the outer formwork 32 of the vertical wall B, and then connect the vertical wall B tie rod 34 between the inner formwork 31 and the middle part of the outer formwork 32 of the vertical wall B, and connect the outer horizontal support rod 35 between the outer wall of the outer formwork 32 of the vertical wall B and the inner wall of the vertical wall A 01; the vertical wall B 03 is a segment of two meters, so when constructing the vertical wall B 03, a 1cm thick fracture steel plate is set at the joint of each segment, and connected to the outer membrane 32 and the inner membrane 31 through the template installation holes on the outer membrane 32 and the inner membrane 31 of the vertical wall B. The beam end of 03 is fixed by a pin in the form of a side package end, and a pre-buried water hole trapezoidal box 36 is provided between the lower part of the inner mold 31 and the outer mold 32 of the vertical wall B (see Figure 6 ), the inner walls of the inner form 31 and the outer form 32 of the vertical wall B are close to the corresponding embedded water hole trapezoidal box 36, so that the distance between the lower parts of the inner and outer forms of the vertical wall B is consistent with the length of the embedded water hole trapezoidal box 36, so as to control the lower size of the vertical wall B03. When the formwork of the entire vertical wall B03 is connected and formed, the formwork line type is fine-tuned and the actual elevation is measured to be qualified, and then the concrete pouring construction of the vertical wall B03 is carried out. After the pouring is completed, it is maintained until the age period ends, so as to realize the cyclic continuous construction of the vertical wall B03 in the beam storage area, thereby achieving the purpose of continuous work.

[0042] In order to ensure continuous and orderly operation of the three walls in the beam factory, four sets of complete formwork for the vertical wall A 01 are equipped in the beam manufacturing area, and three sets of complete formwork for the protective wall 02 and three sets of complete formwork for the vertical wall B 03 are equipped in the beam storage area to ensure continuous operation of the three-wall construction.

[0043] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A method for erecting three walls attached to a bridge deck in an integrated manner, characterized in that: The specific steps include: (1) After the box girder body concrete on the beam-making pedestal in the beam-making area is finally set, vertical wall A is constructed on the finally set concrete box girder body in the beam-making area; (2) In the beam storage area, after the final tensioning of the prestressed steel strands of the box beam is completed and the prestressed pipe slurry of the box beam reaches the design strength, a protective wall is constructed on the box beam; (3) In the beam storage area, after the construction of the protective wall is completed, the vertical wall B is constructed on the box beam.

2. The method for erecting three walls attached to a bridge deck in an integrated manner according to claim 1, characterized in that: The construction methods of the protective wall, vertical wall A and vertical wall B sequentially include measurement and layout, roughening of concrete at the bottom of the wall, reinforcement binding, formwork installation, concrete pouring, curing and inspection and acceptance.

3. The method for erecting three walls attached to a bridge deck in an integrated manner according to claim 2, characterized in that: When installing the formwork of the vertical wall A, first fix the bottom end of the outer formwork of the vertical wall A with the top end of the side formwork of the box beam flange plate by bolts. After the concrete of the box beam body is finally set, the embedded parts of the vertical wall A, the inner formwork of the vertical wall A, the vertical wall A tie rod between the inner and outer forms of the vertical wall A, the fracture steel plate and the end membrane of the vertical wall A are installed on the box beam surface in sequence. Finally, after fine-tuning the line type of the vertical wall A formwork, the concrete pouring construction of the vertical wall A is carried out. After the pouring is completed, it is cured until the age period ends, so that the vertical wall A is constructed synchronously with the box beam body in the beam making area.

4. The method for erecting three walls attached to a bridge deck in an integrated manner according to claim 3, characterized in that: The horizontal height of the top of the inner formwork of the vertical wall A is consistent with the horizontal height of the top of the vertical wall A. The top of the inner formwork of the vertical wall A is also connected to an inner heightening formwork. The bottom end of the inner heightening formwork is connected to the top of the inner formwork of the vertical wall A by bolts. The horizontal height of the top of the inner heightening formwork is consistent with the horizontal height of the top of the outer formwork of the vertical wall A. A row of vertical wall A size limiting beams evenly distributed along the extension direction of the vertical wall A are connected to the top of the outer formwork of the vertical wall A and the inner heightening formwork.

5. The method for erecting three walls attached to a bridge deck in an integrated manner according to claim 3, characterized in that: A row of embedded parts positioning boxes are arranged between the upper parts of the outer and inner forms of the vertical wall A, and a connecting positioning beam is welded to the top of the embedded parts positioning box. When the formwork of the vertical wall A is installed, the two ends of the connecting positioning beam extend to the top of the outer and inner forms of the vertical wall A respectively and are fixedly connected to the top of the outer and inner forms of the vertical wall A respectively by bolts, thereby correcting the distance between the inner and outer forms of the vertical wall A, thereby achieving the purpose of adjusting the linear shape of the vertical wall A formwork and reinforcing the formwork.

6. The method for erecting three walls attached to a bridge deck in an integrated manner according to claim 2, characterized in that: The steel cages of the protective wall, vertical wall A and vertical wall B are prefabricated in sections in a factory and then transported to the construction site for installation in sections.

7. The method for erecting three walls attached to a bridge deck in an integrated manner according to claim 2, characterized in that: When installing the template of the protective wall, first install the inner template of the protective wall on the beam surface of the box beam, connect a row of diagonal braces to the outer wall of the inner template of the protective wall, the top end of each diagonal brace is connected to the outer wall of the inner template, and the bottom end of each diagonal brace is connected to the beam surface of the box beam, then install the outer template of the protective wall, and then connect the lower part of the inner template of the protective wall and the outer template through a protective wall pull rod, and finally connect a row of protective wall size limiting beams evenly distributed along the extension direction of the protective wall to the top of the inner template and the outer template of the protective wall.

8. The method for erecting three-wall integrated bridge deck attachments according to claim 2, characterized in that: When installing the formwork of the vertical wall B, first install the inner formwork of the vertical wall B on the beam surface of the box beam, and at the same time connect the inner transverse horizontal brace between the outer wall of the inner formwork of the vertical wall B and the outer wall of the protective wall, and then install the outer formwork of the vertical wall B, and then connect the vertical wall B pull rod between the inner formwork of the vertical wall B and the middle part of the outer formwork, and connect the outer transverse horizontal brace between the outer wall of the outer formwork of the vertical wall B and the inner wall of the vertical wall A.

9. The method for erecting three walls attached to a bridge deck in an integrated manner according to claim 7 or 8, characterized in that: Pre-embedded water hole trapezoidal boxes are arranged between the lower parts of the inner and outer molds of the protective wall and between the lower parts of the inner and outer molds of the vertical wall B. When the templates of the protective wall and the vertical wall B are installed, the inner walls of the inner and outer molds of the protective wall and the inner walls of the inner and outer molds of the vertical wall B are close to the corresponding pre-embedded water hole trapezoidal boxes, so that the distance between the lower parts of the inner and outer molds of the protective wall and the vertical wall B is consistent with the length of the pre-embedded water hole trapezoidal boxes, thereby controlling the lower dimensions of the protective wall and the vertical wall B.